2.1. Modeling Framework
The OSeMOSYS is an open-source modeling system for long-term integrated assessment and energy planning [
29]. The initial working code was developed at KTH Stockholm and published in a presentation at the International Energy Workshop in Paris at the IEA in 2008. It was primarily implemented in GNU MathProg [
30]. It is currently available in three languages: GNUMathprog, Python, and GAMS, which can be run for free and openly. The Python version of OSeMOSYS was chosen in the current paper because of its ease of modification and the possibilities it offers in terms of data processing and results representation.
At present, the model consists of seven functional components, the so-called
blocks, which are shown in solid lines in
Figure 1. They are compatible and potentially replaceable with new blocks (with different or improved functions) with careful and consistent set, variable, and parameter definitions.
The blocks include specifications of the objective function (1), costs (2), storage (3), capacity adequacy (4), energy balance (5), constraints (6), and emissions (7) [
30]. The core idea is that the system consists of technologies involved in the use and production of energy carriers. The production of energy carriers must satisfy the intermediate use by the technologies plus the exogenous demand input by the user. To achieve the objective, a number of constraints and specific rules must be followed, which are defined in Blocks 3–7. Each block is described in more detail below.
The model objective function is the minimization of the net present value (NPV) of an energy system to meet a given demand for energy or energy services. Thus, the model needs to account for the costs incurred by each technology (t), in each year (y), and in each modeled region (r). The costs associated with each technology include operating costs, investment costs, and any penalties for emissions production minus a salvage value. Each cost is calculated in constant monetary value and then discounted to determine the NPV.
To model a storage system in OSeMOSYS, a storage (s) is coupled with at least one technology set. Namely, a storage facility can be charged during the operation of one or more technologies in a specified mode of operation and discharged in another mode. Furthermore, more than one technology may be associated with the same storage facility. The model allows either the charge or discharge of energy during a time slice as long as the storage levels remain within prescribed minimum and maximum limits. If these storage limits are not sufficient, the model investigates whether new storage capacity should be added at a given investment cost per unit of storage capacity [
31].
The Capacity Adequacy block calculates the total capacity of each technology for each year based on the existing capacity from before the modeling period (ResidualCapacity), AccumulatedNewCapacity during the modeling period, and NewCapacity installed in each year. It then ensures that this capacity is sufficient to meet the RateOfTotalActivity (i.e., the activity of a technology t in one mode of operation and in a time slice l, if the latter lasted the whole year) in each TimeSlice and Year. In conclusion, an equation ensures that there is sufficient capacity of technologies to meet at least the average annual demand.
The operation of technologies (RateOfActivity, UseByTechnology (i.e., the energy consumption of a technology), ProductionByTechnology (i.e., the energy produced by a technology), and emissions for each mode of operation and technology) is calculated for each chronologically ordered time slice during the year. It is therefore important to ensure that production, use, and demand for fuels/energy services are feasible in each time slice and year.
A summary of the constraints that can be imposed in the base model are presented as follows [
30]:
A maximum or minimum limit on the TotalCapacity (i.e., the total installed capacity) of a particular technology allowed in a particular year and region.
A maximum or minimum NewCapacityInvestment (i.e., the total investment required for installing new capacity) limit placed on a particular technology per year and region.
A maximum or minimum annual limit on the AnnualActivity (i.e., the annual production of energy/energy services) of a technology. The TotalAnnualActivity of a technology for each year is obtained by adding the product of the rate of activity of each technology with the length of each time slice during a year for each region. Thus, it is a limit on the annual production of energy commodities.
A maximum or minimum limit on the ModelPeriodActivity of a technology. The model period activity of each technology is obtained by summing the total annual activity of each technology for each year and for each region.
A minimum ReserveMargin limit. It verifies that there is enough capacity of a specified collection of technologies to provide a reserve margin (for a specified set of fuels) to the system. By flagging the technologies that are allowed to add the reserve margin, the total capacity in the reserve margin (by year and per region) is determined.
A minimum limit of production from RES. By flagging which technologies are renewable and summing their production, the AnnualRenewableProduction of a particular fuel (by region) is obtained. Lower limits on this limit may then be imposed.
Finally, a technology that is active in its various modes of operation can have an impact on the environment. The extent to which pollutants are emitted is determined by multiplying an EmissionsPerUnitActivityRatio entered by the analyst for each ModeOfOperation of a technology. Thus, the annual emissions of a given technology are determined by summing the annual emissions for each of its modes of operation. An EmissionsPenalty can be inserted, and maximum limits on AnnualEmissions and ModelPeriodEmissions can be selected, for each region of the system.
2.3. The LCOE Calculation Tool
In a certain year
y, the real LCOE (
) of a production technology
t can be evaluated by means of OSeMOSYS parameters and variables. It does not consider the decommissioning cost that may be included into the
CapitalCost and does not consider the carbon cost since it could be implemented through the
EmissionPenalty. The obtained formula is
- -
is the annual cost for operation and maintenance of a specific technology. It already takes into account variable and fixed operating costs, excluding cost for fuel supply.
- -
is the annual electricity produced by a technology.
- -
is the annual fuel demand of a technology.
- -
is the average specific cost of the fuel, weighted on the production of the supply technologies.
- -
is the annuity of the investment. It is defined as
- -
is the capital cost of a technology in a certain year.
- -
is the total installed capacity of a technology in a certain year.
- -
is the discount rate.
- -
is the operational life of a technology.
Since the installation cost of storage does not depend on the energy delivered or stored, only the annuity of the investment is considered in this model:
- -
is the capital cost of a storage technology in a certain year.
- -
is the total installed capacity of a technology in a certain year.
- -
is the operational life of a storage technology.
It is then possible to calculate the average real LCOE for all production technologies, which include the storage cost as well. It is known as the system LCOE and indicated as
:
where
is the annual amount of electricity produced by a technology, and
CostOfStorage is the sum of the annuities of all the storage technologies
S:
Another interesting energy indicator is the theoretical LCOE (
). Unlike the
in the denominator, the
indicates the maximum amount of energy a technology can produce operating at its maximum capacity. Thus, the
and the
match if there are no curtailments or partializations of plants. The
is defined as follows:
where
- -
is the maximum amount of energy that a technology can produce. It is the product of
,
(a yearly average capacity factor), and
:
- -
proprtional to the
:
As for the
, it is possible to evaluate an average
for all of the production technologies, which includes the storage cost. It is known as the theoretical system LCOE (
):
Table 1 reports a summary of the shorthand name of the OSeMOSYS variables included in the equations of this section.
The LCOE tool is available in a GitHub repository [
34]. IBM ILOG® CPLEX® Optimization Studio software [
35] was used as a solver of the MILP model.
The methodology described is based on data assumptions about costs, the lifetime of the power plants, and capacity factors that strongly influence the results. Therefore, a careful selection of data must be made before running the tool. In addition, the future scenarios are based on cost projections, which obviously suffer from a certain degree of uncertainty. Another limitation is the application of the methodology only to the power sector, which could instead be extended to other sectors such as the heat one.
2.4. Case Study: San Pietro Island
The island of San Pietro (LAT 39°08
26
N, LONG 8°16
01
E), shown in
Figure 2, is the sixth largest island in Italy with an area of 51.10 km
. It is one of the two main islands of the Sulcis archipelago and lies 10 km off the southwest coast of Sardinia. Administratively, the entire island of San Pietro, including the islands of Ratti and Piana, belongs to the municipality of Carloforte, which is part of the province of Sud Sardegna (SU). The current population is about 6000, but residents increase dramatically in the summer months because of seaside tourism.
Because of the short distance from the shore (10 km), the electricity network of the island of San Pietro is connected to the rest of Sardinia. However, this fact has led to a lack of investment in power plants, and the municipality is characterized by an extremely low degree of energy self-sufficiency.
In
Figure 3, the reference energy system of San Pietro is shown. Boxes with solid lines represent technologies currently active on the island, while the dashed blocks represent technologies included in the scenarios and planned to be installed in the future. The island system is divided into two regions (Carloforte and Nasca), highlighted by the blue lines, which exchange energy with each other.
According to the GSE (Gestore dei Servizi Energetici) [
36], the total electricity generation capacity of the island of San Pietro consists of 1512 kWp of photovoltaic systems. In detail, there is a large PV plant in the locality of Nasca (999 kWp) and 77 private power plants with an overall capacity of 513 kWp.
The total electricity demand is 16.4 GWh per year, distributed monthly as shown in
Figure 4. It follows that, according to the local DSO, local electricity generation is able to cover only 15.6% of the demand. Demand is characterized by a peak in the summer months, especially in August, due to the strong tourist flows on the island. Another interesting aspect is the high degree of electrification of the domestic heating sector, which is reflected in a rather high domestic demand in winter.
As regards the other energy commodities, they are entirely imported to the island as end products and used in transportation and households. The following is a summary of the energy demands for the imported fuels, obtained through a self elaboration of the data from the island’s energy plan developed in 2011 [
37]:
Diesel: 6.1 GWh
Gasoline: 7.6 GWh
LPG: 2.8 GWh
2.5. Scenario Settings
Thanks to an RES potential assessment, it was possible to limit the maximum installable capacity for each technology. In addition, some scenarios take into account the penetration of electric vehicles, whose impact on electricity demand is noticeable. Hereafter, each technology included in the system in terms of cost, activity, and constraints is described. Future costs are deduced through a linear interpolation of the current costs with the cost projection in 2050, and they are reported in
Table 2 and
Table 3.
PV_P represents the centralized large-scale PV power plants. The current capacity is 999 kWp, but it is assumed that the capacity could be doubled by 2050. The capacity factor is 16.7%, and it was calculated through the actual data from the existing power plant. The capital cost, according to IRENA [
38], is equal to 1285 k€/MW in 2020 but decreases following the trend described in the report. Fixed costs amounts to 16 k€/MW [
32].
PV_D represents the decentralized PV power plants, mostly installed on the roofs of buildings. The current capacity, as mentioned, is 513 kWp, but it is feasible to reach a maximum capacity of 8 MW on the entire island. The capacity factor is assumed to be the same as PV_P. The capital cost is assumed to be 1285 k€/ MW in 2020 according to IRENA [
38] but decreases according to the trend described in the same report. Fixed costs are 19 k€/ MW [
32]. The power constraint is obtained by means of the software QGIS, starting from a DSM (Digital Surface Model) with a granularity of 1 x 1 m and running a simulation with the plugin "SEBE" [
39]. This tool generates a raster file containing the global annual irradiation on the island. It should be pointed out that a DSM takes into account the shading effects caused by obstacles on the ground (building and vegetation). The software QGIS then allows one to cut the raster file using the building shapes, available on the website of Sardegna Geoportale [
40], as a mask. Thus, it is easy to obtain the average irradiation on the roof of each building of the island. From this data, the PV rooftop potential was obtained.
WT represents the onshore wind turbines with a rated power of 850 kWp. It is expected that up to 5 turbines will be installed in a site where a dismissed wind farm already exists. The average capacity factor was estimated to be 23% using WAsP [
41] software. Capital costs are estimated at 1584 k€/MW in 2020 according to IRENA [
42], but are decreasing according to the trend described in the report. Fixed costs amount to 28 k€/MW [
32]. The wind data necessary to obtain the generation profile are obtained from [
43].
WEC represents the Wave Energy Converters, modeled with reference to the Pendulum Wave Energy Converter (PeWEC) device [
44], using potential flow theory [
45] and energy maximization control strategies [
46]. The rated power of each device is 115 kWp, and its productivity was estimated from its power matrix and hourly sea state values off the coast of San Pietro, whose parameters were taken from the ERA5 database. The obtained capacity factor is 15.5%. The capital cost was estimated at 4070 EUR/kW [
47] in 2020 but decreases to 1500 EUR/kW in 2050, while the fixed cost is 86 EUR/kW in 2020 and decreases to 50 EUR/kW in 2050. Cost projections are taken from [
48].
ELC_GRID represents the island’s power grid. Since no specific data was available, its efficiency is considered to be 90%, a medium value between the Sardinian grid efficiency [
49] and the efficiency of Pantelleria’s electricity network [
25]. To ensure sufficient stability, VRES penetration must not exceed 80% of the total production. The costs associated with electricity distribution are considered to be zero.
BATTERIES represents the electrochemical storage systems of the Li-ion typology. A round-trip efficiency of 90% was chosen, and to better model the storage system, the power and energy components were decoupled. Capital costs are assumed to be 234 k€/MW and 252,000 k€/GWh in 2020. Fixed costs are 31 k€/ MW. They are expected to decrease to 162 k€/MW, 90,000 k€/GWh, and 14 k€/MW [
50], respectively.
IMP_GSL, IMP_DSL, IMP_LPG, and IMP_ELC represent the import of the various energy commodities consumed within the system. The fossil fuels are characterized by variable costs, evaluated as the average Italian price excluding VAT in 2019: 118.01 k€/GWh for diesel, 157.73 k€/GWh for gasoline, and 76.92 k€/GWh for LPG [
51]. The price of imported electricity is the average PUN (National Unified Price) in 2019 [
52]: 52.35 k€/GWh.
In order to achieve a satisfying time resolution of the model [
11] without incurring too much computational effort, the time representation is structured as follows. Six
Seasons were chosen, each 2 months long, as shown in
Table 4. Two
DayTypes are then considered: Working Days (5 days per week) and Weekends (2 days per week). Subdividing further, each day is split into eight
DailyTimeBrackets, each 3 hours long, as represented in
Table 5. Thus, 96 time slices are finally obtained.
A graphical representation of the average capacity factor, for each technology, is represented in
Figure 5, for every season considered. Data are obtained as described in
Section 2.5.
Four different scenarios for the evolution of San Pietro’s energy system over the 2020–2050 time horizon were examined. Specifically, these are as follows:
- 1.
the Business-As-Usual (BAU) scenario;
- 2.
the Current-Policy-Projection (CPP) scenario;
- 3.
the Sustainable-Growth (SG) scenario;
- 4.
the Self-Sufficient-Renewable (SSR) scenario.
The BAU scenario is a projection of the current situation to 2050 if no energy policies were adopted and there was no interest in environmental issues. It is often used in energy modeling as a reference scenario to compare results.
The CPP scenario is a projection of energy policy actions taken in recent years. Some steps are being taken toward transition, but the measures are far from sufficient to achieve carbon neutrality.
The SG scenario is the result of consistent energy transition policies that would bring the island close to carbon neutrality. However, because this scenario does not include storage systems, VRES penetration is not able to overcome 72% of the generation mix. Grid interconnection to the mainland remains essential.
Finally, the SSR scenario aims to achieve carbon neutrality by 2050. It assumes a fully renewable generation mix combined with a storage system (Li-ion batteries) that can maximize consumption and ensure grid stability.
Table 6 shows which technologies are included in each scenario within the whole time horizon, with the maximum allowable installed capacity, obtained through an RES potential analysis of the island.
Regarding electric mobility, no targets are set in the BAU scenario or the CPP scenario. In the SG scenario, electric vehicle penetration is projected to reach 50% by 2050, while in the SSR scenario, electric mobility is assumed to reach 100% by 2050. Consequently, the demand for electricity will increase, as estimated by Bellocchi et al. [
53].
Storage, as mentioned, is only considered in the SSG scenario, and its size is selected by the optimization model to achieve energy self-sufficiency by 2050.