Next Article in Journal
Real Time Scheduling of a Microgrid Equipped with Ultra-Fast Charging Stations
Previous Article in Journal
Ship-Based Carbon Capture and Storage: A Supply Chain Feasibility Study
Previous Article in Special Issue
Prioritization of Contracting Methods for Water and Wastewater Projects Using the Fuzzy Analytic Hierarchy Process Method
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Delay Causes and Types in Nigerian Power Construction Projects

1
Department of Nuclear Power Plant Engineering, KEPCO International Nuclear Graduate School, Ulsan 45014, Korea
2
Intelligent Construction Automation Center, Kyungpook National University, Daegu 41566, Korea
*
Authors to whom correspondence should be addressed.
Energies 2022, 15(3), 814; https://doi.org/10.3390/en15030814
Submission received: 24 September 2021 / Revised: 13 January 2022 / Accepted: 16 January 2022 / Published: 23 January 2022
(This article belongs to the Special Issue Construction Project Management 2021)

Abstract

:
Numerous events cause delays to entire power projects’ completion timelines, leading to loss. This paper focuses on revealing the critical delay causes in Nigerian power projects and identifying the delay types such as excusable delay, compensable delay, critical delay, and concurrent delay from the different perspectives of owner and contractor. Based on the survey of the 84 industrial experts in power distribution and transmission projects in Nigeria, this study provides the mean score and rank of 39 delay causes. Among the causes, 14 are identified as critical in the Nigerian power project. The top three critical delay causes are corruption and bureaucracy in government, inadequate fund/budget allocation, and price fluctuation/inflation. Owner and contractor do not show the difference in classifying the 14 delay causes into excusable and compensable delays. However, there was a difference between owner and contractor in categorizing whether a cause is critical or not and concurrent or not. A different viewpoint of types of delay cause can lead to a dispute which may lead to other delays and losses, and thus it is meaningful to understand the types of delay perceived from owner and contractor. Even though the delay cause and types are different depending on an individual project, the results of this study serve as a reference and would be beneficial for the practitioners in the construction industry to help identify the delay causes to manage them effectively.

1. Introduction

Delays can be considered analogous to risk, as most construction projects are exposed to delays. Delays in construction projects in various countries lead to losses on the part of owners and contractors [1]. In Nigeria, Ikechukwu and Emoh [2] stated that the trend of delay events in a construction project including power projects could lead to increased overall costs while also inordinately extending the project completion time by a high percentage. Gatugel Usman et al. [3] also claimed that in Nigeria, there is a prevailing circumstance in that the availability of funds is progressively dwindling, and creative and innovative solutions are pertinent to addressing the power supply problems, in which delays may prove an impediment.
Many previous studies have investigated the delay cause to achieve better project management performance [4,5,6]. However, each project has distinctive characteristics such as region, country, product, stakeholder, and thus each project is exposed to different aspects of delay cause and performance. It is important to understand which delay causes exist and how much they affect to performance for the successful implementation of the following Nigerian power project.
In addition, Trauner [7] claimed that in determining the impact of a project schedule delay, analyzing whether the delay type is excusable, compensable, critical, and concurrent is important. These delay types may also have been perceived differently by either the owners or contractors. It is important to exactly understand how the perception of delay type is different between the main players of the project, the owners and contractors. A different viewpoint of the type of delay cause can lead to a dispute which may cause other delays and losses. The responsibility of delay causes can be appropriately discussed and allocated by understanding the delay type perceived. It is worthy to note that most previous research did not investigate what kinds of delay causes are usually excusable, compensable, critical, or concurrent in construction projects.
Therefore, this study is done to close a gap in past research, by investigating the top delay cause in Nigerian power construction projects and investigating the delay types from the owner and contractor perspectives to effectively manage the delay performance of the project. The rest of the paper is divided as follows. Section 2 is a literature review of delay causes and types, which forms the theoretical background of the study. Section 3 shows the methodology employed in carrying out the research. Section 4 shows the results obtained, with a brief discussion. Finally, Section 5 provides the conclusions and limitations.

2. Research Background

2.1. Causes of Delays

Many researchers have investigated delays in construction projects to improve project management performance. Among them, this study selected the studies that are associated with Nigerian power projects. First, several studies have investigated the delay cause of power projects. Banobi and Jung [6] analyzed the delay of power projects from the perspectives of the owners and contractors for a successful project, identifying gaps between owners and contractors in Tanzania. Results showed that the owners and contractors identified similar causes of delay such as vandalism and long waits to obtain permits from authorities, change in scope, owner’s poor supervision, failure in planning, and design error. Pall et al. [8] examined the unique delay cause factors in power transmission projects and revealed critical causes of delay to projects as external/unavoidable factors. Here, the top-ranked factors were the right of way problems for the transmission lines, frequent changes in transmission line routes, and accessibility to the transmission line tower amongst others.
Second, several studies have investigated the delay cause in developing countries. Nundwe and Mulenga [9] also revealed delay causes in Zambia power construction projects such as late advance payments, poor financial management by the contractor, and irregular payments to sub-contractors. Mahamid et al. [10] analyzed the time performance of road construction projects in the West Bank of Palestine and identified the five most severe delay causes as the political situation, segmentation of the West Bank, limited movement between areas, awarding of projects to lowest bidders, payment delays from the owner, and the shortage of equipment. Aziz and Abdel-Hakam [11] investigated the causes of road construction delays in Egypt and found the delay causes to be financial problems, shortages in equipment, construction materials and skilled operators, inexperienced workers, revisions, changes, or errors in design, delays in design submission, and soil and underground problems. Gebrehiwet and Luo [12], in a past study, investigated and discovered the unique causes of delays in Ethiopia’s construction projects which are corruption, unavailability of utilities at the site, inflation/price increases in materials, lack of quality materials, late design and design documents, slow delivery of materials, unreasonably long lead-times in approving and receiving completed project work, poor site management and performance, late release of budget/funds, and ineffective project planning and scheduling. Bajjou and Chafi [13], in another study in Moroccan construction projects, revealed the top ten causes to be the delays in progress payments, lack of training for employees, lack of waste management strategy, unrealistic contract duration imposed by the client, revisions due to construction errors, excessive subcontracting, delays in obtaining permits from governmental agencies, ineffective planning and scheduling, the lack of collective planning, and the unskilled workforce. Rashid [14] also explored the causes of delay in construction projects executed in Pakistan and identified the significant causes as contractor-related factors, client-related factors, consultant-related factors, material-related factors, labor-related factors, and general-related factors. Sagarkumar [15] analyzed the delay causes in construction projects in India and revealed the major contributing factors to construction delay as lack of labor-management, excess workload, corruption, changes in laws, and shortages of equipment. Hossen et al. [16] found the most significant subfactors in a nuclear power plant construction schedule to be policy changes, political instability, regulatory and license issues, robust designs, document review procedures, redesign due to errors, shortage of qualified experienced nuclear equipment manufacturers. Idow and Tajudeen [17], in the Nigerian experience, found some predominant causes of delay to construction project delivery in Nigeria such as changes in drawing.
Based on the literature review of previous studies on delay causes and types in construction projects which cuts across Nigeria and some developing countries, this study identified 39 delay causes which formed the basis for investigating the Nigerian case, because most construction projects around these developing countries may share some similarity in delay cause (Table 1).

2.2. Delay Types

Delays often arise between contractors and owners of projects, leading to many problems, like liquidated damage or disagreements or litigation about contracts. Over the years, many authors have shared their different perspectives on delay types and the challenges faced by parties in contracts with definitions and analysis. One of the categorizations of delay type is that classifying the delay into four types: excusable delay, compensable delay, critical delay, and concurrent delay [7].

2.2.1. Excusable or Non-Excusable Delays

Hamzah et al. [22] classified delays as excusable and non-excusable delays. The non-excusable delays are caused by the contractors or their suppliers, and this is no fault of the owner in a construction project. Therefore, the contractor is often not entitled to relief, either with money or time and must make up for the time lost by accelerating the work or compensating the owner in other ways. Similarly, Theodore also expressed that all delays are either excusable or non-excusable [7]. An excusable delay is a delay that is due to an unforeseeable event beyond the contractor’s or the subcontractor’s control: for example, delays resulting from general labor strikes fires, floods, acts of God, owner-directed changes, errors and omissions in the plans and specifications, differing site conditions or concealed conditions, severe weather, intervention by outside agencies, and a lack of action by government bodies.

2.2.2. Compensable or Non-Compensable Delays

According to Kasimu and Isah [19], non-compensable delays are caused by third parties or incidents beyond the control of both the owner and the contractor. Examples include acts of God, unusual weather, strikes, fires, acts of government in its sovereign capacity. In this case, the contractor is normally entitled to a time extension but no compensation for delayed damages. In contrast, compensable delays are caused by the owner or the owner’s agents, for example, the late release of drawings from the owner’s architect. This leads to a schedule extension and exposes the owner to a financial damage claim by the contractor; whereas Zaki et al. [23] asserted that the client has more control over compensable delays and can take some actions to prevent them.

2.2.3. Critical or Non-Critical Delays

Gajare et al. [24] expressed that critical delay caused schedule delay to the entire project completion or a milestone date by affecting critical activities, whereas non-critical delays are schedule delays that do not affect the project completion or a milestone date. Fakunle and Fashina [21] said that critical delays prevent the contractor from concluding the work on the scheduled timeline agreed upon in the construction contract.

2.2.4. Concurrent or Non-Concurrent Delays

Concurrent delays are delays that occur at the same time or close to the same time [25]. Typically, many factors delay a project in an overlapping manner, which is more complicated. This delay can be caused by both owners and contractors. Livengood [20] also supported the idea that concurrent delays are very complex, and experts find themselves in disputes over the implementation of schedules when concurrency issues are involved in delays, leading to confusion in expert judgments. Munvar et al. [18] claimed that a concurrent delay in a project’s schedule is due to two or more independent delay events happening at the same time. The concurrent delay leads to difficulties in attributing the responsibility for these delays and in deciding the way they are to be dealt with, as they are complex and intertwined.
The previous studies defined the delay types and investigated the delay causes included in four types in general. However, there lacks research that identifies the types of delay cause in power projects and investigates the classification from the perspective of owner and contractor. It is important to understand the perceived delay type of the owner and contractor since their perception gap can be an impediment to effective delay management and lead to a dispute about the responsibility of delay which causes another delay.

3. Methodology

3.1. Questionnaire Design and Data Collection

The questionnaire is designed based on an exhaustive literature review and respondents’ answer possibility. The questionnaire is structured into four sections: (a) general information about the respondents and their organizations; (b) characteristics of the respondents’ experienced project; (c) intensity of delay cause based on the respondent’s project; and (d) classification of delay types of top five delay cause based on the perspective of owner and contractor, as shown in Appendix A.
In order to collect the sample data, an offline survey was conducted using one hundred and fifty questionnaires to solicit and obtain expert opinions on delay causes and types. Thus, the survey was distributed to Nigerian experts who have experienced the power distribution and power transmission projects. Eighty-four experts validly responded to the total questionnaire issued. That is a total of about 49% of experts experienced the power transmission project and 51% of experts experienced power distribution projects. The offline survey process covered six weeks. The major challenge experienced in carrying out the survey was: (1) the slow response to the questionnaires due to the partial operations of stakeholder organizations as a result of the COVID-19 pandemic; (2) it is not of many difficulties for respondents to allocate weight to the 39 delay causes. However, it is of burden for the respondent to allocate weight to the top five delay types.

3.2. Respondent Profile

Table 2 presents the profile of respondents’ affiliation. The profile shows that 42.9% of the respondents are owners, 35.7% are contractors, while the 21.4% remaining are representatives of such organizations as utility companies.
Additionally, Figure 1 reveals the job position of the respondent that about a quarter of the respondents were project managers (25%), with the largest respondents (38%) as project engineers, and others like technicians (8%), site managers (10%), consultants taking up a 12%, while surveyors made up 7.0%, which constituted the smallest percentage of the respondents.

3.3. Data Analysis

This study investigated the intensity of the delay causes. Thirty-nine delay causes were presented in a questionnaire and rated using the 7-Likert scale. This study provided the duration criteria of each scale when rating the importance as shown in Table 3. Since each respondent has a different opinion of the criteria to each scale, the criteria can be effective to reduce the bias of each response.
The mean score ranking technique was used to rank the delay cause of Nigerian power projects. The perceived importance from the respondents acted as scores used to calculate the mean score for each factor and ranked according to the mean score.
One sample t-test is conducted to identify the critical delay cause of the Nigerian power project. The test value is 2 with a 95% confidence level. According to the duration criteria provided, delay causes whose mean score is higher than 2 are regarded as critical.
As for the analysis of delay type, the delay type of each cause is classified according to the percentage of the respondents who perceived that a delay cause is excusable or not, compensable or not, critical or not and concurrent or not.

4. Results and Discussions

4.1. Critical Delay Causes in Nigerian Power Project

In this study, Table 4 below presents the rank, mean and standard deviation of the delay cause factors in the Nigerian power project. The delay causes are sorted by rank in ascending order. The result of one sample t-test (test value = 2, confidence level = 95%) indicated that 14 delay causes are significantly important in the Nigerian power project. Twenty-five delay causes remaining is regarded as of significantly low importance because the mean value of these has not exceeded 2. The critical delay causes are discussed below.
The corruption and bureaucracy in the Nigerian government which is an external factor to the owner and contractor ranks first (1st) amongst the delay cause factor and negatively affects the schedule of the Nigerian power projects with a mean score of 4.77. Similarly, studies for developing countries such as [12] in Ethiopia, [15] in India, also confirm that corruption is a dominant impediment to the timely completion of civil construction projects.
The inadequate funds and budget allocations (mean score: 4.71) is the 2nd ranked delay cause which also negatively affects the construction of the Nigeria power project. Here, the owner is impacted when inadequate funds and the budget are involved. In the same vein, studies by [9] in Zambia, [11] in Egypt, and [17] in Nigeria, also confirm that poor financial management problems and difficulty contributes to the delay in the scheduled completion of power distribution and other civil construction projects.
When price fluctuation and inflation (DC18, mean score: 4.23) are involved, this gives the 3rd ranked delay cause of the scheduled completion of power projects in Nigeria. This may have arisen as a result of the unstable economy in Nigeria. This delay cause is also seen in [12], confirming that inflation and price increase in a material is a contributor to the delay in the completion of construction projects.
With regulatory and license requirement (DC5), the 4th ranked delay cause with a mean score of 4.05, the delay cause is seen to have also contributed to the scheduled delay cause in the timely completion of a power project in Nigeria. This delay may arise from the owner’s inability to meet regulatory and license requirements or permits by the government to start the project work. Similarly, Hossen et al. [16] also confirm that the regulatory criteria and licensing documents conflicting with existing regulations also contribute to the ultimate delay of schedule completion of nuclear power plant projects.
Economic instability (DC35) ranks 5th among the identified causes of delay in Nigerian power projects, and it also contributes an approximate mean score of 3.75 that negatively affects the schedule completion of the Nigerian power project. This delay cause may have arisen from the unstable state of Nigeria’s economy. Likewise, a previous study by Hossen et al. [16] also buttressed the fact that the economic instability of a country due to inflation and other factors can contribute to the ultimate delay of the scheduled completion of nuclear power and civil construction projects, respectively.
Design changes and the delay in approving changes (DC3), which ranks 6th in the overall delay cause in the scheduled completion of the Nigeria power project, has a mean score of 3.70. Here, the owner who is responsible for the design in the power project is impacted by delay either as a result of slow approval of design or changes. More so, government interference (DC33) ranks seventh and has a mean score of 3.48. It can be seen to equally have contributed delays to some projects in the past. For example, studies by Hossen et al. [16] also confirm this fact, that government interference plays a big role in the delay of the scheduled completion of nuclear power plant construction projects. In addition, lack of cost monitoring planning/poor cost control (DC19) ranks 8th with a mean score of 3.23. This delay cause was perceived to have contributed due to poor cost control by the contractors in the power projects. Inappropriate project scope (DC9) ranks as the 9th delay cause to the overall scheduled completion of the power project in Nigeria with a mean score of 3.13. A previous study in [14] confirmed that DC9 also contributes to the ultimate delay in construction projects. The cost of the material comes 10th in the delay cause to the timely completion of the Nigerian power project.
To sum up, corruption and bureaucracy in government (DC36), economic instability (DC35), inadequate fund/budget allocation (DC1) are frequently high ranked in a developing country such as not only Nigeria and but also Ethiopia and India. Therefore, the owner and government must first try to improve the delay causes by putting adequate measures to curb corruption, stabilize the economy, and provide financial supports to power construction companies. In addition, lack of cost and monitoring planning: poor cost control (DC19) and late procurement orders of material/equipment (DC20) also ranked high. Contractors should improve the related capability to reduce project delays.

4.2. Types of Delay Cause in Nigerian Power Project

This study investigated and classified the 14 critical delay causes into four types (excusable, compensable, critical, and concurrent delay) depending on the perspective of the owner and contractor. Delay causes were classified according to the experts’ responses. For example, DC1: each owner was required to select if the DC1 is excusable, non-excusable, or I don’t know (IDK), and since the percentage of excusable is large, DC1 is classified as an excusable delay from the owner’s perspective. Since no responses were collected about DC20 from the contractors, DC20 is excluded in the contractor column of the table. Table 5 shows the classification results of delay cause and each delay cause is expressed as ID (ID of delay cause)–Rank (Mean score rank of delay cause)–Percentage (Percentage of response of delay type).
For excusable delay, 12 delay causes are classified as excusable delay for both owner and contractor. These delays are excusable when it occurs. Only DC14 and DC20 are non-excusable delay. Delays due to poor project planning and scheduling (DC14) and late procurement orders of material/equipment (DC20) are contractors’ negligence that could be managed during project implementation. The owner and contractor showed no difference in perceived delay type that the delay cause is excusable or not in the Nigerian power project. Excusable delays are recognized as a reasonable delay cause to extend the schedule for both owner and contractor. In other words, the contractor is not negligible for delay. Thus, owners should be concentrated on managing those delay causes and appropriately allocate the responsibility of excusable delay.
For compensable delay, both owner and contractor responded that they don’t know whether the 14 delay causes are compensable or not. This result is due to the background of the respondent. The compensation of damage from delay is usually defined through the contract. Since most of the respondents who are manager, engineer, and technician do not have much knowledge of a contract that requires expertise in law, the response that they don’t know was dominant. Even though compensable delays are responsible for the owner, it is problematic that owners did not recognize or perceive the compensable delay.
For critical delay, both the owner and contractor perceived that DC5, DC9, and DC34 are a critical delay cause. The owner and contractor showed the difference in the criticality of some delay causes perceived. In association with difference, six delay causes (DC3, DC18, DC33, DC35, DC36) are differently perceived between owner and contractor. The owner responded that corruption and bureaucracy in government (DC36) is a critical delay cause, whereas the contractor responded that I don’t know about DC36. The contractor perceived that design changes and delay in approving the changes (DC3) and government interference (DC33) are critical, whereas the owner responded that I don’t know. This result indicated that the owner and contractor showed different viewpoints of criticality following their interest. This kind of difference can lead to disputes and delays. When the contractor claims the change order for these delay causes, the amount of time extension and compensation of both sides is contentious due to the difference in criticality perceived. Critical delays with high rank are properly managed for project delay performance. Among them, owners should concentrate on the excusable and compensable delays, and contractors should concentrate on the non-excusable delays.
For concurrent delay, the contractor perceived that all the delay causes are concurrent, while the owner perceived that several delay causes (DC18, DC34, DC35) are non-concurrent. Though these delay causes are excusable for both owner and contractor, the contractor cannot receive the satisfiable change order from the owner, due to the difference of perceived delay type of cause for price fluctuation/inflation (DC18), cost of material (DC34), economic instability (DC35). In this kind of situation, as from the difference of delay impact analysis of owner and contractor, the dispute may occur.

5. Conclusions

Identifying delay causes and impacts, and understanding the delay types perceived by both owners and contractors are crucial to achieving better project management performance. This study identified 39 delay factors through the literature review and collected the empirical opinions from 84 experts who had experience in power transmission and distribution projects. The delay causes are ranked and identified: 14 important delay causes in the Nigerian power project. In addition, this study classified the delay causes into four types (excusable, compensable, critical, and concurrent) depending on the perspective of the owner and contractor.
This study proposed the 14 critical delay cause in Nigerian power construction projects as: Corruption and bureaucracy in government (DC36), Inadequate fund/budget allocation (DC1), Price fluctuation/inflation (DC18), Regulatory/license requirement (DC5), Economic instability (DC35), design changes and delay in approving the changes (DC3), Government interference (DC33), lack of cost and monitoring planning (DC19), Inappropriate project scope (DC9), Cost of material (DC34), Poor project planning and scheduling (DC14), Poor communication (DC2), Late procurement orders of material/equipment(DC20), and Political instability (DC32), ranked in ascending order.
Further, this study discussed the delay type classification from the perspective of the owner and contractor. The owner and contractor do not show the difference in classifying the 14 delay causes into excusable and compensable delays; whereas, for the critical delay, six delay causes (DC3, DC18, DC33, DC35, DC36) are differently perceived between owner and contractor. For concurrent delay, the contractor perceived that all the delay causes are concurrent, while the owner perceived that several delay causes (DC18, DC34, DC35) are non-concurrent.
In conclusion, results of this study provide some insight for a better understanding of the delay causes in the timely completion of Nigerian power projects for future reference. This study will help owners, contractors, and other players in power projects devise a means to assign levels to the delays and their types to allocate responsibilities (entitlement or claim) to the owners and contractors to achieve better performance of the project. However, delay causes and types can be different depending on project and country conditions. Thus, this study cannot be fully generalized to all projects. Readers are recommended to use these results and discussions as a reference.

Author Contributions

Conceptualization, U.I. and W.J.; Data curation, U.I.; Formal analysis, U.I., W.J. and C.Y.P.; Funding acquisition, W.J.; Investigation, U.I.; Methodology, U.I., W.J. and C.Y.P.; Supervision, W.J.; Writing—original draft, U.I.; Writing—review & editing, W.J. and C.Y.P. All authors have read and agreed to the published version of the manuscript.

Funding

This research was supported by the 2021 research fund of the KEPCO International Nuclear graduate School (KINGS), Republic of Korea and supported by the Basic Science Research Program through the National Research Foundation of Korea (NRF) funded by the Ministry of Education (No. NRF-2020R1A2C1012739).

Data Availability Statement

The data presented in this study are available on request from the corresponding author.

Conflicts of Interest

The authors declare no conflict of interest.

Appendix A

QUESTIONNAIRE CAUSES AND ASSOCIATED TYPES OF DELAYS IN NIGERIAN POWER PROJECTS
Dear Sir/Madam,
A research project concerned with causes and associated types of delays in Nigerian power projects is currently being undertaken. As a stakeholder in development of power projects in Nigeria, your views and contribution to this research will be highly appreciated. Please respond to the questions freely and by ticking, numbering or explaining your views on the asked questions.
All information to be provided will be classified as highly confidential and will only be used for academic purposes only. Thank you very much for your anticipated cooperation.
A. GENERAL INFORMATION
  • Name of respondent (Optional)…………………………………
  • Name of organization (Optional)……………………………….
  • How can you group yourself?
    (a)
    Project owner
    (b)
    Project contractor
    (c)
    Others……………………………………………………….
  • What is your position as per your group selection?
    (a)
    Project Manager
    (b)
    Site manager
    (c)
    Surveyor
    (d)
    Engineer
    (e)
    Technician
    (f)
    Scheduler
    (g)
    Consultant
    (h)
    Others
  • For how many years have you practiced in the power industry?
    (a)
    0–5 Years
    (b)
    6–10years
    (c)
    11–15years
    (d)
    Above 15 years: Outline some of them…………………
B. RESPONDENTS’ EXPERIENCED PROJECT
Please select one project that you fully experienced. Then, answer the followings:
4.
Please, select one among the followings.
(a)
Power Generation Project
(b)
Transmission Project
(c)
Distribution Project
(d)
Others (mention)
5.
Please select the original contract duration of your own experienced project
(a)
Less than 1 year
(b)
1–2 Years
(c)
2–3 Year
(d)
3–4 Years
(e)
More than 4 Years
6.
Please select the original contract price of your experienced project
(a)
Less than $10 million
(b)
$10–50 million
(c)
$50–100 million
(d)
$100–500 million
(e)
Above $500 million
7.
Who was in charge of design or engineering?
(a)
Owner-side
(b)
Contractor-side
(c)
Other (Please, specify)
8.
Please select the funding source
(a)
The Central Government of Nigeria or Public institution
(b)
Private company or commercial bank
(c)
Multilateral development bank (Africa Development Bank, World Bank, etc.)
(d)
Mix of a and b
(e)
Mix of a and c
9.
What is the actual project completion time?
(a)
About 0% increase of original contract duration
(b)
About 5% increase of original contract duration
(c)
About 10% increase of original contract duration
(d)
About 20% increase of original contract duration
(e)
About 30% increase of original contract duration
(f)
About 50% increase of original contract duration
(g)
More than 50% increase of original contract duration
10.
What is the actual cost overrun?
(a)
About 0% increase of original contract cost
(b)
About 5% increase of original contract cost
(c)
About 10% increase of original contract cost
(d)
About 20% increase of original contract cost
(e)
About 30% increase of original contract cost
(f)
About 50% increase of original contract cost
(g)
More than 50% increase of original contract cost
C. CAUSES OF DELAY
Please identify which among the following factors are the causes of Project delay based on your project experience. Please tick (√) against numbers showing the intensity of its contribution in the delay: 1 = No impact, 2 = Very Low (less than 1 week), 3 = Low (less than 2 weeks), 4 = Slightly low (less than 1 month), 5 = Slightly High (less than 3 months), 6 = High (less than 6 months), 7 = Very High (more than 6 months).
IDDelay CausesImpact (Likert Scale)
1
(N/A)
2
(1W)
3
(2W)
4
(1M)
5
(3M)
6
(6M)
7
(6M>)
DC1Inadequate fund/budget allocation
DC2Poor communication
DC3Design changes, and delay in approving the changes
DC4Unrealistic contract duration/type
DC5Regulatory /license requirements
DC6Lack of experience of owner
DC7Delay in owner’s procurement
DC8Poor management; coordination/supervision
DC9Inappropriate Project Scope
DC10Poor standard of drawing
DC11Inadequate design document review procedures
DC12Incomplete design and estimate at the time of tender
DC13Inappropriate data collection
DC14Poor project planning and scheduling
DC15Inadequate site supervision
DC16Strikes by site personnel
DC17Poor construction materials
DC18Price fluctuation/inflation
DC19Lack of cost and monitoring planning; poor cost control
DC20Late procurement orders of material/equipment
DC21Lack of experience of contractor
DC22Shortage of material in the market
DC23Equipment and tool shortage on site
DC24Shortage of manpower
DC25High interest rates on mode of financing
DC26Poor site working condition
DC27Workers’ absenteeism
DC28Vandalism
DC29Kidnapping, Terrorism
DC30Theft
DC31Conflicts with neighbor
DC32Political instability
DC33Government interference
DC34Cost of material
DC35Economic instability
DC36Corruption, and bureaucracy in government
DC37Natural disaster
DC38Unexpected geological conditions
DC39Act of God
D. DELAY TYPES OF TOP FIVE DELAY CAUSES:
1. a. Please, select the 1st ranked delay cause in Section C
(S/N …………………………………….)
1. b. What is the delay type of this 1st ranked cause? (It’s possible to answer more than one), Please tick ()
i.
Excusable delay: Occurs due to events which are outside the control of contractor.
ii.
Non-excusable delay: Are such delay that no excuse can be given for them. They arise due to carelessness or actions and inactions of contractors and subcontractors.
iii.
Concurrent delay: Contains two or more excusable delays that results in time extension distributed between owner and contractor.
iv.
Non-concurrent delay: Contains two or more non-excusable delays which does not result in time extension.
v.
Compensable delay: Are those in which contractor is entitled for extra compensation i.e., monetary and time extension as well.
vi.
Non-compensable delay: Are such where both contractor and client are not responsible for delay. Under such circumstances only time extensions are granted and no monetary compensation is provided. Such delays include act of God
vii.
Critical delay: Are those which cause delay to entire project completion date.
viii.
Non-critical: Are delays that do not necessarily affect the project completion date but affects progress.
ix.
I don’t know exactly
2. a. Please, select 2nd ranked delay cause in section C
(S/N ………………………………………………)
2. b. What is the delay type of this 2nd ranked cause? (It’s possible to answer more than one), Please tick ()
i.
Excusable delay
ii.
Non-excusable delay
iii.
Concurrent delay
iv.
Non-concurrent delay
v.
Compensable delay
vi.
Non-compensable delay
vii.
Critical delay
viii.
Non-critical
ix.
I don’t know exactly
3. a. Please, select 3rd ranked delay cause in Section C
(S/N …………………………………………………….)
3. b. What is the delay type of this 3rd ranked cause? (It’s possible to answer more than one). Please tick ()
i.
Excusable delay
ii.
Non-excusable delay
iii.
Concurrent delay
iv.
Non-concurrent delay
v.
Compensable delay
vi.
Non-compensable delay
vii.
Critical delay
viii.
Non-critical
ix.
I don’t know exactly
4. a. Please, select 4th ranked delay cause in Section C
(S/N …………………………………………………)
4. b. What is the delay type of this 4th ranked cause? (It’s possible to answer more than one). Please tick ()
i.
Excusable delay
ii.
Non-excusable delay
iii.
Concurrent delay
iv.
Non-concurrent delay
v.
Compensable delay
vi.
Non-compensable delay
vii.
Critical delay
viii.
Non-critical
ix.
I don’t know exactly
5. a. Please, select 5th ranked delay cause in Section C
(S/N …………………………………………………….)
5. b. What is the delay type of this 5th ranked cause? (It’s possible to answer more than one). Please tick ()
i.
Excusable delay
ii.
Non-excusable delay
iii.
Concurrent delay
iv.
Non-concurrent delay
v.
Compensable delay
vi.
Non-compensable delay
vii.
Critical delay
viii.
Non-critical
ix.
I don’t know exactly

References

  1. Project Management in Nuclear Power Plant Construction: Guidelines and Experience; Nuclear Energy Series; International Atomic Energy Agency: Vienna, Austria, 2012; ISBN 978-92-0-122210-7.
  2. Ikechukwu, A.C.; Emoh, F.I.; Kelvin, O.A. Causes and Effects of Cost Overruns in Public Building Construction Projects Delivery, In Imo State, Nigeria. IOSR J. Bus. Manag. 2017, 19, 13–20. [Google Scholar] [CrossRef]
  3. Gatugel Usman, Z.; Abbasoglu, S.; Tekbiyik Ersoy, N.; Fahrioglu, M. Transforming the Nigerian power sector for sustainable development. Energy Policy 2015, 87, 429–437. [Google Scholar] [CrossRef]
  4. Vyas, S. Causes of Delay in Project Construction in Developing Countries. Indian J. Commer. Manag. Stud. 2013, IV, 24–29. [Google Scholar]
  5. Long, N.D.; Ogunlana, S.; Quang, T.; Lam, K.C. Large construction projects in developing countries: A case study from Vietnam. Int. J. Proj. Manag. 2004, 22, 553–561. [Google Scholar] [CrossRef]
  6. Banobi, E.T.; Jung, W. Causes and mitigation strategies of delay in power construction projects: Gaps between owners and contractors in successful and unsuccessful projects. Sustainability 2019, 11, 5973. [Google Scholar] [CrossRef] [Green Version]
  7. Trauner, T.J. Construction Delays: Understanding Them Clearly, Analyzing Them Correctly; Butterworth-Heinemann: Oxford, UK, 2009; ISBN 0080957145. [Google Scholar]
  8. Pall, G.K.; Bridge, A.J.; Gray, J.; Skitmore, M. Causes of delay in power transmission projects: An empirical study. Energies 2019, 13, 17. [Google Scholar] [CrossRef] [Green Version]
  9. Nundwe, M.; Mulenga, M.N. Delays in Construction of Electrical Power Transmission Lines in Zambia. Am. Sci. Res. J. Eng. Technol. Sci. 2017, 30, 82–96. [Google Scholar]
  10. Mahamid, I.; Bruland, A.; Dmaidi, N. Causes of delay in road construction projects. J. Manag. Eng. 2012, 28, 300–310. [Google Scholar] [CrossRef]
  11. Aziz, R.F.; Abdel-Hakam, A.A. Exploring delay causes of road construction projects in Egypt. Alex. Eng. J. 2016, 55, 1515–1539. [Google Scholar] [CrossRef] [Green Version]
  12. Gebrehiwet, T.; Luo, H. Analysis of Delay Impact on Construction Project Based on RII and Correlation Coefficient: Empirical Study. Procedia Eng. 2017, 196, 366–374. [Google Scholar] [CrossRef]
  13. Bajjou, M.S.; Chafi, A. Empirical study of schedule delay in Moroccan construction projects. Int. J. Constr. Manag. 2020, 20, 783–800. [Google Scholar] [CrossRef]
  14. Rashid, Y. Analysis of delay factors and their effects on construction projects. Manag. Sci. Lett. 2020, 10, 1197–1204. [Google Scholar] [CrossRef]
  15. Sagarkumar, R.P. Analysis for the Causes of Delay in Construction Projects. Int. J. Res. Appl. Sci. Eng. Technol. 2020, 8, 97–99. [Google Scholar] [CrossRef]
  16. Hossen, M.M.; Kang, S.; Kim, J. Construction schedule delay risk assessment by using combined AHP-RII methodology for an international NPP project. Nucl. Eng. Technol. 2015, 47, 362–379. [Google Scholar] [CrossRef] [Green Version]
  17. Idowu, A.; Tajudeen, O.I. Project Delivery Delay: The Nigeria Experience. IOSR J. Mech. Civ. Eng. 2016, 13, 84–87. [Google Scholar] [CrossRef]
  18. Munvar, C.; Mengistu, D.G.; Mahesh, G. Concurrent Delay Analysis: Methods, Case Law, and Expert Perception. J. Leg. Aff. Disput. Resolut. Eng. Constr. 2020, 12, 04519035. [Google Scholar] [CrossRef]
  19. Kasimu, A.M.; Isah, A.D. Causes of delay in Nigeria construction industry. Interdiscip. J. Contemp. Res. Bus. 2012, 4, 785–794. [Google Scholar]
  20. Livengood, J. Knowns and Unknowns of Concurrent Delay. J. Leg. Aff. Disput. Resolut. Eng. Constr. 2017, 9, 06517002. [Google Scholar] [CrossRef]
  21. Fakunle, F.F.; Fashina, A.A. Major delays in construction projects: A global overview. PM World J. 2020, IX, 1–15. [Google Scholar]
  22. Hamzah, N.; Khoiry, M.A.; Arshad, I.; Tawil, N.M.; Che Ani, A.I. Cause of construction delay—Theoretical framework. Procedia Eng. 2011, 20, 490–495. [Google Scholar] [CrossRef] [Green Version]
  23. Zaki, A.; Elalim, A.M.A.; Samadony, A.E.L. Factors Affecting Schedule Delay and Cost Overrun in Egyptian Construction Projects. In Proceedings of the 2nd International Conference Sustainable Construction and Project Management—Sustainable Infrastructure and Transportation for Future Cities, Aswan, Egypt, 16–18 December 2018; pp. 1–11. [Google Scholar]
  24. Gajare, Y.; Attarde, P.; Parbat, D.K. Assessment of significant causes and effects of delays on the projects completion period. Int. J. Mod. Trends Eng. Res. 2015, 2, 88–93. [Google Scholar]
  25. Jongo, J.S.; Tesha, D.N.G.A.K.; Kasonga, R.; Teyanga, J.J.; Lyimo, K.S. Mitigation Measures in Dealing with Delays and Cost Overrun in Public Building Projects in Dar-Es-Salaam, Tanzania. Int. J. Constr. Eng. Manag. 2019, 8, 81–96. [Google Scholar] [CrossRef]
Figure 1. Sector and Job Position of Respondents.
Figure 1. Sector and Job Position of Respondents.
Energies 15 00814 g001
Table 1. Delay causes identified in previous studies.
Table 1. Delay causes identified in previous studies.
IDDelay CausesDescriptionReferences
DC1Inadequate fund/budget allocationDelay due to inadequate funds and poor budgeting which leads to ultimate delay of construction project[10,11,12,17]
DC2Poor communicationDelay cause which is due to inability to communicate issues that goes to the root of the contract between stakeholder[7,13]
DC3Delay in approving the changesDelay in approving the changes in design and other matters for the project implementation[7,11,14]
DC4Unrealistic contract duration/typeDelay results from the unrealistic period of completion of the project to inexperience[13,14]
DC5Regulatory/license requirementDelay from an inability to meet regulatory license requirements for the construction of nuclear power projects[13,15,16]
DC6Lack of experience of ownerDelay from the inexperienced owner has a significant impact on project performance[9,13,16]
DC7Delay in owner’s procurementDelay from late procurement of owner supply construction material and equipment, and delivery[10,14]
DC8Poor coordination/supervisionDelay from poor supervisory functions like; allocation of work, decisions, monitoring for compliance and providing leadership[14]
DC9Inappropriate project scopeDelay due to unclear specification or contract including the responsibilities of the parties, milestone and technicality of the project[14,17,18]
DC10Poor standard of drawingDelay from poor quality drawings which leads to reconstructions or modification resulting from the errors[14,17,19]
DC11Inadequate review proceduresPoor planning and management procedure definitions for construction work to ensure quality[11,12,16,17]
DC12Incomplete design and estimateDelay due to incomplete fundamental to shape and form of construction which can negatively influence project completion[11,12,16,17]
DC13Inappropriate data collectionDelay due to inability to answer questions concerning the project, also inability to validate results of certain changes leading to distorted recommendations and decisions[14,17]
DC14Poor planning and schedulingDelay due to lack of planning leading to disorganized construction work activities[12,13]
DC15Inadequate site supervisionDelay from poor supervision practices, including poor planning management of tools, equipment, material, and labor[12,14]
DC16Strikes by site personnelDelay due to strikes by site worker[7,14,19]
DC17Poor construction materialsDelay from use of poor quality of material and workmanship which affects overall construction quality and performance[12,19]
DC18Price fluctuation/inflationDelay from economic volatility and the eventual increase in the prices of construction material, equipment and labor[12,20]
DC19Poor cost controlDelay from poor project estimate, design errors, administrative mismanagement, and not hiring the right team[9,12]
DC20Late procurement ordersDelay that can result from contractors’ late procurement of construction material and equipment[9]
DC21Lack of experience of contractorDelay from contractors’ poor leadership and management because of lack of skill in the line of work[11]
DC22Shortage of material in the marketDelay due to shortage of material and problems due to increasing in the cost of construction material[12,21]
DC23Shortage of equipment on siteDelay due to inability to provide sufficient construction equipment to site due low finances and improper budget provision[10,11,15]
DC24Shortage of powerDelay due to inadequate electric power supply outage to the site[9,12]
DC25High interest ratesDelay due to increasing in interest rate results in an overall increase in project cost[14]
DC26Poor working conditionDelay due to poor environmental working conditions which affect the morale of employees[13,14]
DC27Workers’ absenteeismDelay due to employees’ absence from work which goes a long way to affecting productivity[14]
DC28VandalismDelay from the destruction of construction arrangements like material or equipment at the site[6]
DC29Kidnapping or terrorismDelay from abnormal behavior of persons towards the employee, owners and contractors[14]
DC30TheftDelay from theft of construction materials or equipment at the site [14]
DC31Conflicts with neighborDelay from disputes with neighbors due to contradiction of interest of each stakeholder through project implementation[14,16]
DC32Political InstabilityDelay from unforeseen political unrest or events by the government or political[8,10,16]
DC33Government interferenceDelay from a political decision or pressure from the high-level governance[7,8]
DC34Cost of materialDelay due to unforeseen increase in the cost of material due to sudden inflation rate in the economy[8,12,17]
DC35Economic instabilityDelay from economic volatility of host country[8]
DC36Corruption and bureaucracyDelay from corrupt or sharp practices with the management of the project[19,20]
DC37Natural disasterDelay from natural source such as hurricane, typhoon and storm[8,14,19]
DC38Unexpected geological conditionsDelay from unforeseen adverse sites or underground conditions through investigation[7,11,14]
DC39Act of GodDelay which is assumed to comprise merely natural unforeseen situations[7,14,19]
Table 2. Profile of respondents’ affiliation.
Table 2. Profile of respondents’ affiliation.
AffiliationNumberPercentage
Owner3642.9
Contractor3035.7
Others1821.4
Total84100
Table 3. Likert scale and duration criteria.
Table 3. Likert scale and duration criteria.
Likert ScaleIntensityDuration Criteria
1No ImpactN/A
2Very LowLess than 1 Week
3LowLess than 2 Week
4Slightly LowLess than 1 Month
5Slightly HighLess than 3 Month
6HighLess than 6 Month
7Very HighMore than 6 Month
Table 4. Rank and mean score of delay causes.
Table 4. Rank and mean score of delay causes.
IDDelay CauseRankMeanStd.p-Value
DC36Corruption and bureaucracy in government14.772.220.000 *
DC1Inadequate fund/budget allocation24.711.680.000 *
DC18Price fluctuation/inflation34.231.810.000 *
DC5Regulatory/license requirement44.051.830.000 *
DC35Economic instability53.752.150.000 *
DC3Design changes and delay in approving the changes63.701.900.000 *
DC33Government interference73.482.090.000 *
DC19Lack of cost and monitoring planning: poor cost control83.231.910.000 *
DC9Inappropriate project scope93.132.150.000 *
DC34Cost of material102.901.780.000 *
DC14Poor Project planning and scheduling112.731.650.000 *
DC2Poor communication122.551.650.006 *
DC20Late procurement orders of material/equipment132.451.680.025 *
DC32Political Instability142.421.670.033 *
DC30Theft152.291.500.096
DC28Vandalism162.251.710.244
DC25High interest rates on the mode of financing172.211.360.215
DC13Inappropriate data collection182.171.480.315
DC12Incomplete design and estimate at the time of tender191.911.080.501
DC6Lack of experience of owner201.831.190.219
DC17Poor construction materials211.781.310.184
DC8Poor management: coordination/supervision221.770.970.055
DC24Shortage of power221.771.080.084
DC39Act of God241.771.390.162
DC7Delay in owner’s procurement251.771.230.113
DC11Inadequate design document review procedures261.760.900.023
DC10Poor standard of drawing271.701.200.037
DC15Inadequate site supervision281.691.170.028
DC29Kidnapping or terrorism291.651.110.015
DC27Worker’s absenteeism301.611.180.007
DC4Unrealistic contract duration/type311.601.200.007
DC21Lack of experience of contractor321.581.250.006
DC38Unexpected geological conditions331.571.150.003
DC23Equipment and tool shortage on site341.561.070.001
DC31Conflicts with neighbor341.561.000.000
DC22Shortage of material in the market361.510.930.000
DC37Natural disaster371.441.210.001
DC16Strikes by site personnel381.400.890.000
DC26Poor site working condition391.380.730.000
*: p-value < 0.05 which refers to statistically significant.
Table 5. Types of delay cause of owner and contractor.
Table 5. Types of delay cause of owner and contractor.
Delay TypesOwnerContractor
Excusable
delay
ExcusableDC1-R2-90, DC2-R12-100, DC3-R6-86, DC5-R4-95, DC9-R9-100, DC18-R3-61, DC19-R8-77, DC32-R14-100, DC33-R7-100, DC34-R10-75, DC35-R5-60, DC36-R1-98DC1-R-852, DC2-R12-67, DC3-R6-100, DC5-R4-100, DC9-R9-100, DC18-R3-63, DC19-R8-75, DC32-R14-80, DC33-R7-100, DC34-R10-100, DC35-R5-100, DC36-R1-83
Non-excusableDC14-R11-93, DC20-R13-100DC14-R11-100
IDK
Compensable
delay
Compensable
Non-compensable
IDKDC1-R2-100, DC2-R12-100, DC3-R6-80, DC5-R4-100, DC9-R9-100, DC14-R11-100, DC18-R3-72, DC19-R8-100, DC20-R13-100, DC32-R14-100, DC33-R7-88, DC35-R5-100, DC36-R1-100DC1-R2-86, DC2-R12-78, DC3-R6-100, DC5-R4-100, DC9-R9-100, DC14-R11-100, DC18-R3-87, DC19-R8-75, DC32-R14-100, DC33-R7-100, DC34-R10-67, DC35-R5-100, DC36-R1-100
Critical
Delay
CriticalDC5-R4-67, DC9-R9-67, DC34-R10-50, DC36-R1-40DC3-R6-50, DC5-R4-57, DC9-R9-50, DC33-R7-80, DC34-R10-67
Non-criticalDC14-R11-86, DC20-R13-50DC14-R11-60, DC18-R3-50, DC35-R5-100
IDKDC1-R2-42, DC2-R12-60, DC3-R6-78, DC18-R3-61, DC19-R8-69, DC32-R14-100, DC33-R7-75, DC35-R5-100DC1-R2-71, DC2-R12-44, DC19-R8-50, DC32-R14-60, DC36-R1-50
Concurrent
Delay
ConcurrentDC1-R2-83, DC2-R12-100, DC3-R6-100, DC5-R4-82, DC9-R9-89, DC14-R11-57, DC19-R8-54, DC20-R13-50, DC32-R14-67, DC33-R7-100, DC34-R10-50, DC36-R1-70DC1-R2-71, DC2-R12-78, DC3-R6-100, DC5-R4-86, DC9-R9-100, DC14-R11-100, DC18-R3-50, DC19-R8-75, DC32-R14-80, DC33-R7-100, DC34-R10-83, DC35-R5-100, DC36-R1-83
Non-concurrentDC18-R3-34, DC34-R10-50, DC35-R5-50
IDK
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Ismaila, U.; Jung, W.; Park, C.Y. Delay Causes and Types in Nigerian Power Construction Projects. Energies 2022, 15, 814. https://doi.org/10.3390/en15030814

AMA Style

Ismaila U, Jung W, Park CY. Delay Causes and Types in Nigerian Power Construction Projects. Energies. 2022; 15(3):814. https://doi.org/10.3390/en15030814

Chicago/Turabian Style

Ismaila, Usman, Wooyong Jung, and Chan Young Park. 2022. "Delay Causes and Types in Nigerian Power Construction Projects" Energies 15, no. 3: 814. https://doi.org/10.3390/en15030814

APA Style

Ismaila, U., Jung, W., & Park, C. Y. (2022). Delay Causes and Types in Nigerian Power Construction Projects. Energies, 15(3), 814. https://doi.org/10.3390/en15030814

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop