Delay Causes and Types in Nigerian Power Construction Projects
Abstract
:1. Introduction
2. Research Background
2.1. Causes of Delays
2.2. Delay Types
2.2.1. Excusable or Non-Excusable Delays
2.2.2. Compensable or Non-Compensable Delays
2.2.3. Critical or Non-Critical Delays
2.2.4. Concurrent or Non-Concurrent Delays
3. Methodology
3.1. Questionnaire Design and Data Collection
3.2. Respondent Profile
3.3. Data Analysis
4. Results and Discussions
4.1. Critical Delay Causes in Nigerian Power Project
4.2. Types of Delay Cause in Nigerian Power Project
5. Conclusions
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
Appendix A
- Name of respondent (Optional)…………………………………
- Name of organization (Optional)……………………………….
- How can you group yourself?
- (a)
- Project owner
- (b)
- Project contractor
- (c)
- Others……………………………………………………….
- What is your position as per your group selection?
- (a)
- Project Manager
- (b)
- Site manager
- (c)
- Surveyor
- (d)
- Engineer
- (e)
- Technician
- (f)
- Scheduler
- (g)
- Consultant
- (h)
- Others
- For how many years have you practiced in the power industry?
- (a)
- 0–5 Years
- (b)
- 6–10years
- (c)
- 11–15years
- (d)
- Above 15 years: Outline some of them…………………
- 4.
- Please, select one among the followings.
- (a)
- Power Generation Project
- (b)
- Transmission Project
- (c)
- Distribution Project
- (d)
- Others (mention)
- 5.
- Please select the original contract duration of your own experienced project
- (a)
- Less than 1 year
- (b)
- 1–2 Years
- (c)
- 2–3 Year
- (d)
- 3–4 Years
- (e)
- More than 4 Years
- 6.
- Please select the original contract price of your experienced project
- (a)
- Less than $10 million
- (b)
- $10–50 million
- (c)
- $50–100 million
- (d)
- $100–500 million
- (e)
- Above $500 million
- 7.
- Who was in charge of design or engineering?
- (a)
- Owner-side
- (b)
- Contractor-side
- (c)
- Other (Please, specify)
- 8.
- Please select the funding source
- (a)
- The Central Government of Nigeria or Public institution
- (b)
- Private company or commercial bank
- (c)
- Multilateral development bank (Africa Development Bank, World Bank, etc.)
- (d)
- Mix of a and b
- (e)
- Mix of a and c
- 9.
- What is the actual project completion time?
- (a)
- About 0% increase of original contract duration
- (b)
- About 5% increase of original contract duration
- (c)
- About 10% increase of original contract duration
- (d)
- About 20% increase of original contract duration
- (e)
- About 30% increase of original contract duration
- (f)
- About 50% increase of original contract duration
- (g)
- More than 50% increase of original contract duration
- 10.
- What is the actual cost overrun?
- (a)
- About 0% increase of original contract cost
- (b)
- About 5% increase of original contract cost
- (c)
- About 10% increase of original contract cost
- (d)
- About 20% increase of original contract cost
- (e)
- About 30% increase of original contract cost
- (f)
- About 50% increase of original contract cost
- (g)
- More than 50% increase of original contract cost
ID | Delay Causes | Impact (Likert Scale) | ||||||
1 (N/A) | 2 (1W) | 3 (2W) | 4 (1M) | 5 (3M) | 6 (6M) | 7 (6M>) | ||
DC1 | Inadequate fund/budget allocation | |||||||
DC2 | Poor communication | |||||||
DC3 | Design changes, and delay in approving the changes | |||||||
DC4 | Unrealistic contract duration/type | |||||||
DC5 | Regulatory /license requirements | |||||||
DC6 | Lack of experience of owner | |||||||
DC7 | Delay in owner’s procurement | |||||||
DC8 | Poor management; coordination/supervision | |||||||
DC9 | Inappropriate Project Scope | |||||||
DC10 | Poor standard of drawing | |||||||
DC11 | Inadequate design document review procedures | |||||||
DC12 | Incomplete design and estimate at the time of tender | |||||||
DC13 | Inappropriate data collection | |||||||
DC14 | Poor project planning and scheduling | |||||||
DC15 | Inadequate site supervision | |||||||
DC16 | Strikes by site personnel | |||||||
DC17 | Poor construction materials | |||||||
DC18 | Price fluctuation/inflation | |||||||
DC19 | Lack of cost and monitoring planning; poor cost control | |||||||
DC20 | Late procurement orders of material/equipment | |||||||
DC21 | Lack of experience of contractor | |||||||
DC22 | Shortage of material in the market | |||||||
DC23 | Equipment and tool shortage on site | |||||||
DC24 | Shortage of manpower | |||||||
DC25 | High interest rates on mode of financing | |||||||
DC26 | Poor site working condition | |||||||
DC27 | Workers’ absenteeism | |||||||
DC28 | Vandalism | |||||||
DC29 | Kidnapping, Terrorism | |||||||
DC30 | Theft | |||||||
DC31 | Conflicts with neighbor | |||||||
DC32 | Political instability | |||||||
DC33 | Government interference | |||||||
DC34 | Cost of material | |||||||
DC35 | Economic instability | |||||||
DC36 | Corruption, and bureaucracy in government | |||||||
DC37 | Natural disaster | |||||||
DC38 | Unexpected geological conditions | |||||||
DC39 | Act of God |
- i.
- Excusable delay: Occurs due to events which are outside the control of contractor.
- ii.
- Non-excusable delay: Are such delay that no excuse can be given for them. They arise due to carelessness or actions and inactions of contractors and subcontractors.
- iii.
- Concurrent delay: Contains two or more excusable delays that results in time extension distributed between owner and contractor.
- iv.
- Non-concurrent delay: Contains two or more non-excusable delays which does not result in time extension.
- v.
- Compensable delay: Are those in which contractor is entitled for extra compensation i.e., monetary and time extension as well.
- vi.
- Non-compensable delay: Are such where both contractor and client are not responsible for delay. Under such circumstances only time extensions are granted and no monetary compensation is provided. Such delays include act of God
- vii.
- Critical delay: Are those which cause delay to entire project completion date.
- viii.
- Non-critical: Are delays that do not necessarily affect the project completion date but affects progress.
- ix.
- I don’t know exactly
- i.
- Excusable delay
- ii.
- Non-excusable delay
- iii.
- Concurrent delay
- iv.
- Non-concurrent delay
- v.
- Compensable delay
- vi.
- Non-compensable delay
- vii.
- Critical delay
- viii.
- Non-critical
- ix.
- I don’t know exactly
- i.
- Excusable delay
- ii.
- Non-excusable delay
- iii.
- Concurrent delay
- iv.
- Non-concurrent delay
- v.
- Compensable delay
- vi.
- Non-compensable delay
- vii.
- Critical delay
- viii.
- Non-critical
- ix.
- I don’t know exactly
- i.
- Excusable delay
- ii.
- Non-excusable delay
- iii.
- Concurrent delay
- iv.
- Non-concurrent delay
- v.
- Compensable delay
- vi.
- Non-compensable delay
- vii.
- Critical delay
- viii.
- Non-critical
- ix.
- I don’t know exactly
- i.
- Excusable delay
- ii.
- Non-excusable delay
- iii.
- Concurrent delay
- iv.
- Non-concurrent delay
- v.
- Compensable delay
- vi.
- Non-compensable delay
- vii.
- Critical delay
- viii.
- Non-critical
- ix.
- I don’t know exactly
References
- Project Management in Nuclear Power Plant Construction: Guidelines and Experience; Nuclear Energy Series; International Atomic Energy Agency: Vienna, Austria, 2012; ISBN 978-92-0-122210-7.
- Ikechukwu, A.C.; Emoh, F.I.; Kelvin, O.A. Causes and Effects of Cost Overruns in Public Building Construction Projects Delivery, In Imo State, Nigeria. IOSR J. Bus. Manag. 2017, 19, 13–20. [Google Scholar] [CrossRef]
- Gatugel Usman, Z.; Abbasoglu, S.; Tekbiyik Ersoy, N.; Fahrioglu, M. Transforming the Nigerian power sector for sustainable development. Energy Policy 2015, 87, 429–437. [Google Scholar] [CrossRef]
- Vyas, S. Causes of Delay in Project Construction in Developing Countries. Indian J. Commer. Manag. Stud. 2013, IV, 24–29. [Google Scholar]
- Long, N.D.; Ogunlana, S.; Quang, T.; Lam, K.C. Large construction projects in developing countries: A case study from Vietnam. Int. J. Proj. Manag. 2004, 22, 553–561. [Google Scholar] [CrossRef]
- Banobi, E.T.; Jung, W. Causes and mitigation strategies of delay in power construction projects: Gaps between owners and contractors in successful and unsuccessful projects. Sustainability 2019, 11, 5973. [Google Scholar] [CrossRef] [Green Version]
- Trauner, T.J. Construction Delays: Understanding Them Clearly, Analyzing Them Correctly; Butterworth-Heinemann: Oxford, UK, 2009; ISBN 0080957145. [Google Scholar]
- Pall, G.K.; Bridge, A.J.; Gray, J.; Skitmore, M. Causes of delay in power transmission projects: An empirical study. Energies 2019, 13, 17. [Google Scholar] [CrossRef] [Green Version]
- Nundwe, M.; Mulenga, M.N. Delays in Construction of Electrical Power Transmission Lines in Zambia. Am. Sci. Res. J. Eng. Technol. Sci. 2017, 30, 82–96. [Google Scholar]
- Mahamid, I.; Bruland, A.; Dmaidi, N. Causes of delay in road construction projects. J. Manag. Eng. 2012, 28, 300–310. [Google Scholar] [CrossRef]
- Aziz, R.F.; Abdel-Hakam, A.A. Exploring delay causes of road construction projects in Egypt. Alex. Eng. J. 2016, 55, 1515–1539. [Google Scholar] [CrossRef] [Green Version]
- Gebrehiwet, T.; Luo, H. Analysis of Delay Impact on Construction Project Based on RII and Correlation Coefficient: Empirical Study. Procedia Eng. 2017, 196, 366–374. [Google Scholar] [CrossRef]
- Bajjou, M.S.; Chafi, A. Empirical study of schedule delay in Moroccan construction projects. Int. J. Constr. Manag. 2020, 20, 783–800. [Google Scholar] [CrossRef]
- Rashid, Y. Analysis of delay factors and their effects on construction projects. Manag. Sci. Lett. 2020, 10, 1197–1204. [Google Scholar] [CrossRef]
- Sagarkumar, R.P. Analysis for the Causes of Delay in Construction Projects. Int. J. Res. Appl. Sci. Eng. Technol. 2020, 8, 97–99. [Google Scholar] [CrossRef]
- Hossen, M.M.; Kang, S.; Kim, J. Construction schedule delay risk assessment by using combined AHP-RII methodology for an international NPP project. Nucl. Eng. Technol. 2015, 47, 362–379. [Google Scholar] [CrossRef] [Green Version]
- Idowu, A.; Tajudeen, O.I. Project Delivery Delay: The Nigeria Experience. IOSR J. Mech. Civ. Eng. 2016, 13, 84–87. [Google Scholar] [CrossRef]
- Munvar, C.; Mengistu, D.G.; Mahesh, G. Concurrent Delay Analysis: Methods, Case Law, and Expert Perception. J. Leg. Aff. Disput. Resolut. Eng. Constr. 2020, 12, 04519035. [Google Scholar] [CrossRef]
- Kasimu, A.M.; Isah, A.D. Causes of delay in Nigeria construction industry. Interdiscip. J. Contemp. Res. Bus. 2012, 4, 785–794. [Google Scholar]
- Livengood, J. Knowns and Unknowns of Concurrent Delay. J. Leg. Aff. Disput. Resolut. Eng. Constr. 2017, 9, 06517002. [Google Scholar] [CrossRef]
- Fakunle, F.F.; Fashina, A.A. Major delays in construction projects: A global overview. PM World J. 2020, IX, 1–15. [Google Scholar]
- Hamzah, N.; Khoiry, M.A.; Arshad, I.; Tawil, N.M.; Che Ani, A.I. Cause of construction delay—Theoretical framework. Procedia Eng. 2011, 20, 490–495. [Google Scholar] [CrossRef] [Green Version]
- Zaki, A.; Elalim, A.M.A.; Samadony, A.E.L. Factors Affecting Schedule Delay and Cost Overrun in Egyptian Construction Projects. In Proceedings of the 2nd International Conference Sustainable Construction and Project Management—Sustainable Infrastructure and Transportation for Future Cities, Aswan, Egypt, 16–18 December 2018; pp. 1–11. [Google Scholar]
- Gajare, Y.; Attarde, P.; Parbat, D.K. Assessment of significant causes and effects of delays on the projects completion period. Int. J. Mod. Trends Eng. Res. 2015, 2, 88–93. [Google Scholar]
- Jongo, J.S.; Tesha, D.N.G.A.K.; Kasonga, R.; Teyanga, J.J.; Lyimo, K.S. Mitigation Measures in Dealing with Delays and Cost Overrun in Public Building Projects in Dar-Es-Salaam, Tanzania. Int. J. Constr. Eng. Manag. 2019, 8, 81–96. [Google Scholar] [CrossRef]
ID | Delay Causes | Description | References |
---|---|---|---|
DC1 | Inadequate fund/budget allocation | Delay due to inadequate funds and poor budgeting which leads to ultimate delay of construction project | [10,11,12,17] |
DC2 | Poor communication | Delay cause which is due to inability to communicate issues that goes to the root of the contract between stakeholder | [7,13] |
DC3 | Delay in approving the changes | Delay in approving the changes in design and other matters for the project implementation | [7,11,14] |
DC4 | Unrealistic contract duration/type | Delay results from the unrealistic period of completion of the project to inexperience | [13,14] |
DC5 | Regulatory/license requirement | Delay from an inability to meet regulatory license requirements for the construction of nuclear power projects | [13,15,16] |
DC6 | Lack of experience of owner | Delay from the inexperienced owner has a significant impact on project performance | [9,13,16] |
DC7 | Delay in owner’s procurement | Delay from late procurement of owner supply construction material and equipment, and delivery | [10,14] |
DC8 | Poor coordination/supervision | Delay from poor supervisory functions like; allocation of work, decisions, monitoring for compliance and providing leadership | [14] |
DC9 | Inappropriate project scope | Delay due to unclear specification or contract including the responsibilities of the parties, milestone and technicality of the project | [14,17,18] |
DC10 | Poor standard of drawing | Delay from poor quality drawings which leads to reconstructions or modification resulting from the errors | [14,17,19] |
DC11 | Inadequate review procedures | Poor planning and management procedure definitions for construction work to ensure quality | [11,12,16,17] |
DC12 | Incomplete design and estimate | Delay due to incomplete fundamental to shape and form of construction which can negatively influence project completion | [11,12,16,17] |
DC13 | Inappropriate data collection | Delay due to inability to answer questions concerning the project, also inability to validate results of certain changes leading to distorted recommendations and decisions | [14,17] |
DC14 | Poor planning and scheduling | Delay due to lack of planning leading to disorganized construction work activities | [12,13] |
DC15 | Inadequate site supervision | Delay from poor supervision practices, including poor planning management of tools, equipment, material, and labor | [12,14] |
DC16 | Strikes by site personnel | Delay due to strikes by site worker | [7,14,19] |
DC17 | Poor construction materials | Delay from use of poor quality of material and workmanship which affects overall construction quality and performance | [12,19] |
DC18 | Price fluctuation/inflation | Delay from economic volatility and the eventual increase in the prices of construction material, equipment and labor | [12,20] |
DC19 | Poor cost control | Delay from poor project estimate, design errors, administrative mismanagement, and not hiring the right team | [9,12] |
DC20 | Late procurement orders | Delay that can result from contractors’ late procurement of construction material and equipment | [9] |
DC21 | Lack of experience of contractor | Delay from contractors’ poor leadership and management because of lack of skill in the line of work | [11] |
DC22 | Shortage of material in the market | Delay due to shortage of material and problems due to increasing in the cost of construction material | [12,21] |
DC23 | Shortage of equipment on site | Delay due to inability to provide sufficient construction equipment to site due low finances and improper budget provision | [10,11,15] |
DC24 | Shortage of power | Delay due to inadequate electric power supply outage to the site | [9,12] |
DC25 | High interest rates | Delay due to increasing in interest rate results in an overall increase in project cost | [14] |
DC26 | Poor working condition | Delay due to poor environmental working conditions which affect the morale of employees | [13,14] |
DC27 | Workers’ absenteeism | Delay due to employees’ absence from work which goes a long way to affecting productivity | [14] |
DC28 | Vandalism | Delay from the destruction of construction arrangements like material or equipment at the site | [6] |
DC29 | Kidnapping or terrorism | Delay from abnormal behavior of persons towards the employee, owners and contractors | [14] |
DC30 | Theft | Delay from theft of construction materials or equipment at the site | [14] |
DC31 | Conflicts with neighbor | Delay from disputes with neighbors due to contradiction of interest of each stakeholder through project implementation | [14,16] |
DC32 | Political Instability | Delay from unforeseen political unrest or events by the government or political | [8,10,16] |
DC33 | Government interference | Delay from a political decision or pressure from the high-level governance | [7,8] |
DC34 | Cost of material | Delay due to unforeseen increase in the cost of material due to sudden inflation rate in the economy | [8,12,17] |
DC35 | Economic instability | Delay from economic volatility of host country | [8] |
DC36 | Corruption and bureaucracy | Delay from corrupt or sharp practices with the management of the project | [19,20] |
DC37 | Natural disaster | Delay from natural source such as hurricane, typhoon and storm | [8,14,19] |
DC38 | Unexpected geological conditions | Delay from unforeseen adverse sites or underground conditions through investigation | [7,11,14] |
DC39 | Act of God | Delay which is assumed to comprise merely natural unforeseen situations | [7,14,19] |
Affiliation | Number | Percentage |
---|---|---|
Owner | 36 | 42.9 |
Contractor | 30 | 35.7 |
Others | 18 | 21.4 |
Total | 84 | 100 |
Likert Scale | Intensity | Duration Criteria |
---|---|---|
1 | No Impact | N/A |
2 | Very Low | Less than 1 Week |
3 | Low | Less than 2 Week |
4 | Slightly Low | Less than 1 Month |
5 | Slightly High | Less than 3 Month |
6 | High | Less than 6 Month |
7 | Very High | More than 6 Month |
ID | Delay Cause | Rank | Mean | Std. | p-Value |
---|---|---|---|---|---|
DC36 | Corruption and bureaucracy in government | 1 | 4.77 | 2.22 | 0.000 * |
DC1 | Inadequate fund/budget allocation | 2 | 4.71 | 1.68 | 0.000 * |
DC18 | Price fluctuation/inflation | 3 | 4.23 | 1.81 | 0.000 * |
DC5 | Regulatory/license requirement | 4 | 4.05 | 1.83 | 0.000 * |
DC35 | Economic instability | 5 | 3.75 | 2.15 | 0.000 * |
DC3 | Design changes and delay in approving the changes | 6 | 3.70 | 1.90 | 0.000 * |
DC33 | Government interference | 7 | 3.48 | 2.09 | 0.000 * |
DC19 | Lack of cost and monitoring planning: poor cost control | 8 | 3.23 | 1.91 | 0.000 * |
DC9 | Inappropriate project scope | 9 | 3.13 | 2.15 | 0.000 * |
DC34 | Cost of material | 10 | 2.90 | 1.78 | 0.000 * |
DC14 | Poor Project planning and scheduling | 11 | 2.73 | 1.65 | 0.000 * |
DC2 | Poor communication | 12 | 2.55 | 1.65 | 0.006 * |
DC20 | Late procurement orders of material/equipment | 13 | 2.45 | 1.68 | 0.025 * |
DC32 | Political Instability | 14 | 2.42 | 1.67 | 0.033 * |
DC30 | Theft | 15 | 2.29 | 1.50 | 0.096 |
DC28 | Vandalism | 16 | 2.25 | 1.71 | 0.244 |
DC25 | High interest rates on the mode of financing | 17 | 2.21 | 1.36 | 0.215 |
DC13 | Inappropriate data collection | 18 | 2.17 | 1.48 | 0.315 |
DC12 | Incomplete design and estimate at the time of tender | 19 | 1.91 | 1.08 | 0.501 |
DC6 | Lack of experience of owner | 20 | 1.83 | 1.19 | 0.219 |
DC17 | Poor construction materials | 21 | 1.78 | 1.31 | 0.184 |
DC8 | Poor management: coordination/supervision | 22 | 1.77 | 0.97 | 0.055 |
DC24 | Shortage of power | 22 | 1.77 | 1.08 | 0.084 |
DC39 | Act of God | 24 | 1.77 | 1.39 | 0.162 |
DC7 | Delay in owner’s procurement | 25 | 1.77 | 1.23 | 0.113 |
DC11 | Inadequate design document review procedures | 26 | 1.76 | 0.90 | 0.023 |
DC10 | Poor standard of drawing | 27 | 1.70 | 1.20 | 0.037 |
DC15 | Inadequate site supervision | 28 | 1.69 | 1.17 | 0.028 |
DC29 | Kidnapping or terrorism | 29 | 1.65 | 1.11 | 0.015 |
DC27 | Worker’s absenteeism | 30 | 1.61 | 1.18 | 0.007 |
DC4 | Unrealistic contract duration/type | 31 | 1.60 | 1.20 | 0.007 |
DC21 | Lack of experience of contractor | 32 | 1.58 | 1.25 | 0.006 |
DC38 | Unexpected geological conditions | 33 | 1.57 | 1.15 | 0.003 |
DC23 | Equipment and tool shortage on site | 34 | 1.56 | 1.07 | 0.001 |
DC31 | Conflicts with neighbor | 34 | 1.56 | 1.00 | 0.000 |
DC22 | Shortage of material in the market | 36 | 1.51 | 0.93 | 0.000 |
DC37 | Natural disaster | 37 | 1.44 | 1.21 | 0.001 |
DC16 | Strikes by site personnel | 38 | 1.40 | 0.89 | 0.000 |
DC26 | Poor site working condition | 39 | 1.38 | 0.73 | 0.000 |
Delay Types | Owner | Contractor | |
---|---|---|---|
Excusable delay | Excusable | DC1-R2-90, DC2-R12-100, DC3-R6-86, DC5-R4-95, DC9-R9-100, DC18-R3-61, DC19-R8-77, DC32-R14-100, DC33-R7-100, DC34-R10-75, DC35-R5-60, DC36-R1-98 | DC1-R-852, DC2-R12-67, DC3-R6-100, DC5-R4-100, DC9-R9-100, DC18-R3-63, DC19-R8-75, DC32-R14-80, DC33-R7-100, DC34-R10-100, DC35-R5-100, DC36-R1-83 |
Non-excusable | DC14-R11-93, DC20-R13-100 | DC14-R11-100 | |
IDK | |||
Compensable delay | Compensable | ||
Non-compensable | |||
IDK | DC1-R2-100, DC2-R12-100, DC3-R6-80, DC5-R4-100, DC9-R9-100, DC14-R11-100, DC18-R3-72, DC19-R8-100, DC20-R13-100, DC32-R14-100, DC33-R7-88, DC35-R5-100, DC36-R1-100 | DC1-R2-86, DC2-R12-78, DC3-R6-100, DC5-R4-100, DC9-R9-100, DC14-R11-100, DC18-R3-87, DC19-R8-75, DC32-R14-100, DC33-R7-100, DC34-R10-67, DC35-R5-100, DC36-R1-100 | |
Critical Delay | Critical | DC5-R4-67, DC9-R9-67, DC34-R10-50, DC36-R1-40 | DC3-R6-50, DC5-R4-57, DC9-R9-50, DC33-R7-80, DC34-R10-67 |
Non-critical | DC14-R11-86, DC20-R13-50 | DC14-R11-60, DC18-R3-50, DC35-R5-100 | |
IDK | DC1-R2-42, DC2-R12-60, DC3-R6-78, DC18-R3-61, DC19-R8-69, DC32-R14-100, DC33-R7-75, DC35-R5-100 | DC1-R2-71, DC2-R12-44, DC19-R8-50, DC32-R14-60, DC36-R1-50 | |
Concurrent Delay | Concurrent | DC1-R2-83, DC2-R12-100, DC3-R6-100, DC5-R4-82, DC9-R9-89, DC14-R11-57, DC19-R8-54, DC20-R13-50, DC32-R14-67, DC33-R7-100, DC34-R10-50, DC36-R1-70 | DC1-R2-71, DC2-R12-78, DC3-R6-100, DC5-R4-86, DC9-R9-100, DC14-R11-100, DC18-R3-50, DC19-R8-75, DC32-R14-80, DC33-R7-100, DC34-R10-83, DC35-R5-100, DC36-R1-83 |
Non-concurrent | DC18-R3-34, DC34-R10-50, DC35-R5-50 | ||
IDK |
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations. |
© 2022 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Ismaila, U.; Jung, W.; Park, C.Y. Delay Causes and Types in Nigerian Power Construction Projects. Energies 2022, 15, 814. https://doi.org/10.3390/en15030814
Ismaila U, Jung W, Park CY. Delay Causes and Types in Nigerian Power Construction Projects. Energies. 2022; 15(3):814. https://doi.org/10.3390/en15030814
Chicago/Turabian StyleIsmaila, Usman, Wooyong Jung, and Chan Young Park. 2022. "Delay Causes and Types in Nigerian Power Construction Projects" Energies 15, no. 3: 814. https://doi.org/10.3390/en15030814
APA StyleIsmaila, U., Jung, W., & Park, C. Y. (2022). Delay Causes and Types in Nigerian Power Construction Projects. Energies, 15(3), 814. https://doi.org/10.3390/en15030814