1. Introduction
The existing electricity networks face numerous challenges, including generation diversification, optimal deployment of expensive assets, demand response, energy conservation, and reduction of the industry’s overall carbon footprint [
1]. These challenges require the development of smart grids [
2,
3]. Smart grids are electricity networks enabling two-way flow of both information and power exchange between suppliers and customers, thanks to the pervasive deployment of intelligent communication, monitoring and management systems [
4]. The realization of the physical infrastructure alone is not sufficient, but a smart grid must be complemented by the emergence of new business models and practices, new regulations, and more intangible elements like customers’ behavioral changes and social acceptance [
3,
4]. In the last few years, initiatives on smart grids have been growing in number, participants and scope with different aims and results. Substantial public and private investments have been made in research and development (R & D), demonstration and deployment activities (in Europe, Brazil and the U.S. 309 Mio. € 77 Mio. € and 4,900 Mio. € have been invested through public funding schemes, respectively [
4]) [
5,
6]. The size of the projects in terms of investment seems to be generally increasing over the last years, indicating that either larger or more complex solutions are studied [
7].
Currently, most smart grid projects are still in the R & D or demonstration phases. These projects mainly propose and test solutions related to distributed and renewable energy resources, demand response, smart metering, distribution automation, energy storage, and wide area monitoring protection and control among others [
8]. A literature review shows that most projects actually focus on three types of smart grid services within their business models: vehicle-to-grid and grid-to-vehicle services, demand response services, and services to integrate renewable energy sources [
9]. The deployment and full roll-out of the solutions tested in R & D and demonstration projects require a suitable degree of scalability and replicability to prevent projects from remaining local experimental exercises unable to transfer their knowledge and solutions to real-life industrial-scale applications. Thus, scalable and replicable solutions are sought [
10]. Both, the U.S. Department of Energy and the European Commission insist on the need for scalable and replicable solutions [
7,
11]. The shift from R & D and demonstration phases to the deployment phase comes along with a significant investment effort [
7].
Scalability can be defined as the ability of a system to change its scale in order to meet growing volumes of demand [
12]. A system is understood as a set of interacting elements with similar boundary conditions. Note that the ability of a system to scale does not necessarily imply that the scaled-up system performs well. A more restrictive formulation defines scalability then as the ability of a system to maintain its performance (
i.e., relative performance) and function, and retain all its desired properties when its scale is increased without having a corresponding increase in the system’s complexity [
12]. By contrast, replicability denotes the property of a system that allows it to be duplicated at another location or time. Scalability and replicability are the preliminary requisite to perform scaling-up and replication successfully; therefore, scalability and replicability allow for or at least reduce barriers for the growth and reuse of the results of R & D and demonstration projects. This is of importance for companies and utilities since scaling-up and replication bring major benefits for example through a cost-effective application to a larger group of costumers or by reusing proven solutions in a cost-effective way.
Whereas replicability has not attracted much attention in the literature, scalability has been studied in a wide range of context: telecommunication systems, sensor networks and mostly distributed computing systems [
13]. In [
14], a method for studying the scaling-up of a distributed computing system has been proposed, which is based on cost-effectiveness. The cost-effectiveness is defined as a function of the system’s throughput (
i.e., the amount of work processed in a given time) and its quality of service (
i.e., mean response time). The evaluation of the cost-effectiveness is carried out by numerical simulations. In [
15], design principles for the scalability of a sensor network are discussed. A sensor network should be ideally scalable without reengineering the existing network. A multi-tier network architecture has been proposed to avoid an enormous amount of data being delivered to the central base-station when increasing the number of sensor nodes. In case of telecommunication systems, the problem of routing IP packets also requires a high degree of scalability since with the continuing growth of Internet, the routing table in each router, containing information on how to reach all the reachable Internet addresses, is also getting bigger and bigger, which can cause memory problems [
16]. For other systems, scaling rules can be established as it was the case for Moore’s empirical rule [
17] or Dennard’s law [
18]. For example and similar to Moore’s empirical rule, it has been found that the router memory tends to double its size every couple of years [
16]. The importance of scalability for control schemes and in particular for a control scheme of a PV-Diesel microgrid has been recognized in [
19] but without analyzing it further. It has been however found in [
20] that a local control structure seems to be more scalable than a centralized control structure. Actually, a bottom-up smart grid design seems to be more appropriate in terms of scalability, privacy and security since information flow from the customer to the operator is reduced, a centralized control is avoided and since diversifying smart meter devices creates technological non-uniformity, improving security [
20]. Further, it is worthwhile to mention that some sensitivity analyses found in the literature can be interpreted as approaches to evaluate scaling-up and replication. For instance, in [
21] the worthwhileness of scaling-up has been analyzed by evaluating the economic impact of increasing the amount of wind power generation or the number of overload line controllers by dint of numerical simulations. Similarly, reference [
22] has simulated the economic impact of an increasing amount of electric vehicles and of different associated charging strategies on several European power systems. Note that these studies on scaling-up and replication inherently assume a scalable and replicable solution. In fact, references [
15] and [
23] allude to the fact that scalability is design-dependent and that it must be tackled from the very beginning. The focus of this paper is then on scalability and replicability understood as the preliminary requisite to perform scaling-up and replication successfully. Finally and although scaling-up and replication might be interlinked (the growth of a project within a geographic region might bring with a change in the boundary conditions such as terrain conditions, regulation,
etc.), scalability and replicability are independent. The former is rather system dependent, whereas the latter depends on the expected change of the boundary conditions.
This paper studies the scalability and replicability of smart grid projects and their demonstrators. Project demonstrators range from physical implementations to software and toolbox applications. A scalable smart grid project is understood as a project that successfully increases its size under the same boundary conditions (e.g., more smart meters in a specific area or a more detailed model of a power system in case of software), whereas a replicable project refers to a project that successfully performs under different boundary conditions (e.g., simulation of market designs of different countries). For this purpose, the paper tackles first the question of what makes a particular project scalable and replicable. In other words, factors are sought and identified that influence and condition a project’s scalability and replicability. These factors involve technical, economic, regulatory and stakeholder acceptance related aspects. Since smart grid projects tackle a wide area of application, the factors need to be sufficiently generic and cannot be too application-specific. In a second step, a case study is performed on on-going European and national smart grid projects in order to evaluate the factors, which allows then quantifying the status quo of the analyzed projects with respect to the scalability and replicability. Further, projects provide a feedback on to what extent they take into account these factors and on whether their results and solutions are actually able to be scaled-up and replicated. Results of that case study are provided. Whereas scalability and replicability factors already describe requirements for scalability and replicability, the case study on on-going projects will show the achievements and barriers with respect to projects’ scalability and replicability.
The paper is organized as follows:
Section 2 describes the scalability and replicability factors;
Section 3 outlines the methodology for the assessment of the identified scalability and replicability factors. This methodology is applied to a case study on on-going European projects in
Section 4;
Section 5 presents the conclusions of the paper.
3. Methodology for Assessing the Factors
This section describes the methodology for the assessment of the scalability and replicability factors. The methodology consists in collecting data of smart grid project demonstrators by means of a questionnaire to assess and evaluate the identified scalability and replicability factors. The evaluation of the factors allows then quantifying the status quo of on-going and new projects with respect to the scalability and replicability,
i.e., they provide a feedback on to what extent projects take into account these factors and on whether the projects’ results and solutions are actually able to be scaled-up and replicated. The methodology is summarized in
Figure 1.
Whether a smart grid project is scalable and replicable or not depends on how the scalability and replicability factors have been contemplated. The developed methodology consecutively evaluates the technical, economic, and regulatory and social acceptance related factors of projects. For example, if a particular project is inherently scalable due to its technical design but benefits grow slower than costs do when increasing its size, the project is deemed to be potentially not scalable or it is only partially scalable. Similarly, if a particular project of a country is inherently replicable and its business model focuses on loss reduction but the envisaged country doesn’t incentive loss reduction, the project might be potentially not replicable in that country. However, if this business model can be adapted (e.g., renewable feed in), the project might get replicable again. Ideally, all factors should be contemplated, but the importance of a factor might vary from project to project (e.g., in a project studying the deployment of phasor measurement units, the end user acceptance is of less importance).
The evaluation of the factors has been carried out by means of analyses of the received questionnaires [
41]. Project leaders or project coordinators have filled in questionnaires since they have a general view of the project and the actors involved. Answers to the multiple-choice questions have been translated into numerical scores. Whereas scalability and replicability factors already describe the requirements for scalability and replicability, the answers to the questions will show the achievements and barriers of the smart grid projects. It is important to mention that the answers to the questions reflect the projects’ view and results. For instance, when answering the questions related to economic factor profitability on the project’s viability and cost-benefit ratio, the project had to carry out the corresponding analysis in order to answer the questions correctly. The advantage of this approach is that projects provide the information, knowing best their results. A disadvantage resides in the fact that the answers could be biased in order to enhance the final result. This risk has been somehow mitigated by making the answers anonymous, after all since the results could be seen by funding institutions.
The methodology summarized and depicted in
Figure 1 inherently suggests certain priorities and a certain order, which could be translated into weights associated to each factor. For instance, if a project is not technically scalable, it could be deemed as potentially not scalable although it is regulatorily scalable. Each factor could thus to be weighted and a weighted sum for each of the four groups (technical, economic and regulatory and stakeholder acceptance) as well as a total weighted sum (over all four groups) is computed. Whenever possible, the weights should also reflect the participants’ experience,
i.e., the project demonstrators’ knowledge. Finally, a minimum score is established for each factor in order to avoid incongruence within an area (e.g., a very modular project with very poor interface design should not be directly deemed scalable although the mean score is sufficient).
4. Case Study
This section gives an overview of the results of a case study of a wide variety of publicly funded projects within Europe, tackling diverse challenges within the smart grid domain. This case study is performed in order to evaluate the proposed factors. This way, contacted smart grid projects provide a feedback on to what extent they take into account these factors and on whether their results and solutions are actually able to be scaled-up and replicated.
Table 2 shows the projects and the demonstrators that participated in the survey, their status, the network they are connected to (distribution D and/or transmission T), and the main stakeholders involved. All projects include distribution and transmission companies and utilities, manufacturers and research centres. It is interesting that customers or customer associations are underrepresented, which is also true for regulators or policy makers. This can be partially explained by the fact that projects focus on proving feasibility [
42]. Note, however, that customers’ willingness to participate is usually analysed ([
43,
44]).
First, aggregated results of the survey are presented. The use of aggregated results filters somehow the results of particular projects and allows deriving a certain tendency. Equal weights and a minimum score of 0.3 have been used. Second, some challenges and limitations for scalability and replicability detected by the data collection are outlined. Focus is on those scalability and replicability areas and factors, where projects obtained comparatively low scores. Note that although the number of projects is rather small, their answers already give a first impression of what are the major challenges and limitations. Continuous receiving of answered questionnaire will improve this picture, but it will probably also show that challenges and limitations shift.
4.1. Aggregated Results of the Survey
The analysis of the received questionnaires shows that technical, economic, and regulatory and stakeholder related scalability areas score about the same. By contrast, the regulatory and stakeholder related replicability areas score higher than the technical and economic replicability areas. Economic replicability issues seem to have attracted less attention.
4.1.1. Factors
A more detailed picture of the aggregated results can be obtained by analyzing the results on the factor level.
Figure 2 shows and compares the average scores of the scalability and replicability factors and their importance as seen by the participants. The scalability factors technology evolution, economies of scale, and existing infrastructure, and the replicability factors standardization and market design obtained lowest scores. According to the survey, issues for technology evolution arise from expected equipment costs, from collecting and handling data with reduced sampling time, missing standardization of the flow of information and control signals from and to distributed generation, and from IT/data security and reliability (data connections will not be 100% available all the time). Evolutions in smart metering, communication infrastructure, standardization of equipment and communication, and distribution management systems are expected to improve feasibility of smart grid solutions in the near future. Particularly, IT/data security evolutions are especially important for scaling up.
Limitations on existing infrastructure are mainly due to the presence of weak elements such as lines or transformers or due to physical size limitations such as in substations. In some cases, the presence of weak elements was desired to show the performance of proposed solutions (e.g., DSM to maximize the use of installed capacity and to postpone grid reinforcements). With respect to the factor network configuration, limitations for replicability might arise from the fact that certain projects require an existing infrastructure such AMS.
In the case of economy of scale, one reason for having a comparatively low factor score is due to the fact that in many cases a corresponding analysis on the avoided costs has not yet been performed or is not available yet. This finding can be partially explained by the nature of the projects, which are mostly demonstration projects focusing on feasibility. Some projects expect a linear or sublinear increase of cost with increase of size; others expect a stepwise development due to for example the need of a sudden infrastructure upgrade. The linear increase in costs with size is the upper limit for economy of scale. It is important to mention that the sublinear increase of costs is mostly expected for standardized equipment where multi-vendors are available. Software projects are expected to have a small increase of costs (very sublinear) with size, but they might have a high setup cost.
The low score on standardization might indicate potential problems (for example by employing only proprietary solutions and proprietary standards). Nonetheless, these potential problems can be somehow mitigated as long as the solutions are interoperable. Note that only a few projects apply solutions that are not compliant with any standard and that over 60% of all projects apply open, voluntary and/or mandatory standards. Challenges arise from the dependency on service providers imposing their standards/protocols, the difficulty of implementing different protocols simultaneously, or from the ability for a standard-conform implementation of components (e.g., electric vehicles and chargepoles). In some cases, a particular project implemented a solution providing a new service for which standards (and regulation) still need to be defined.
In case of market design, strong dependence on a given market design can be a potential barrier when replicating the proposed solution to another environment where a different market design is in use (e.g., prohibition of providing ancillary services with RES, prohibition of interaction between DSO and TSO and distributed generation, etc.). Similarly, uncertainty on remuneration schemes is a limitation on market design. In some cases, market design has not been analyzed yet. 80% of all project indicate potential regulatory and/or legal barriers and difficulties regarding the replication of their approach and solutions. Regulatory limitations might be mitigated by adapting the regulation, but this is usually a slow process.
Congruently, it seems thus that projects and their demonstrators focused on some technical aspect of scalability in general as well as on profitability and regulation, whereas the economy of scale, existing infrastructure, and technology evolution had less priority. It is actually interesting that the replicability factor acceptance scores significantly higher than the homonymous scalability factor. Stakeholder involvement has been considered rather for replication but less for scaling-up or it seems less problematic for replicability. One the hand, scaling up of current demonstrators seems to require additional support from DSO, TSO and regulators and adaption of the current operation procedures and regulations, respectively. Customer involvement is essential to most projects, depending on the application, but the problems arising from customer involvement are hardly addressed since projects focused on feasibility and viability aspects. On the other hand, projects argue that a positive result of a tested solution eases replication. Apart from stakeholder acceptance, projects and their demonstrators focused on the regulatory aspect and partially on the technical aspect of replicability.
Finally, the comparison shown in
Figure 2 between the average scores of scalability and replicability factors and their importance as seen by the participants is of particular interest too, since diverging results point to possible barriers and limitations. As long as the average score of a factor is high, no problem arises. When the average score is low and the average importance of the factor is low too, the impact is minimum in case of importance-based weights (the score reflects the importance). It is interesting to point out that the scalability factor acceptance has an average to high importance and an average score, whereas the homonymous replicability factor has a high score and a low importance. Again, stakeholder involvement has been rather addressed for replication or it seems less problematic for replicability. However, interface design, computability analysis, regulation, standardization, and market design have a high importance but score comparatively low. Some barriers might arise there.
4.1.2. Distribution vs. Transmission Projects
Although a majority of smart grid projects focus on distribution networks, an increasing number of projects and demonstrators related to the transmission network can be observed.
Figure 3 divides the participants and their answers and corresponding scores according to the network the projects and their demonstrators are connected to.
With regard to scalability, the main difference between distribution and transmission projects are the factors corresponding to economy of scale and existing infrastructure, where distribution projects score clearly worse. It is interesting to see that transmission projects have especially taken into the existing infrastructure, dealing with limits of the infrastructure where a project is deployed at, whereas distribution projects score best for profitability, dealing with the economic benefits of the project. In fact, the scaling-up of distribution projects might be sometimes limited by a weak element of the grid.
In case of replicability, the main differences between distribution and transmission projects can be after all found for the factors standardization, interoperability, and macroeconomics, where transmission projects score clearly better. One reason might be the need for clear standards and interoperability measures, also with regard to the possibility of projects including multiple TSOs and cross-border interactions. Another reason might lie in the nature of the projects. For example, those envisaging the integration and control of wind power generation can count on more established standards. The possibility of multiple TSO in one project might be also the driver for the higher score of macro-economic factors of transmission projects. It is also interesting to see that distribution and transmission projects obtain scores close to the minimum score for market design. One reason might be that so far, projects did not analyze the projects viability under different market designs or the current market design does not include the service (solution) studied and implemented by projects. Varying legislation and regulation among other EU member states (e.g., prohibition of interaction between DSO and TSO and distributed generation, required SAIDI and SAIFI levels, incentives for loss reduction in distribution systems, etc.) further complicates this issue. Finally, it can be seen for both distribution and transmission projects that the scalability factor acceptance scores comparatively low but the homonymous replicability factor acceptance scores comparatively high. Again, this might be because current demonstrators require more support from DSO and TSO and regulators and they need to foster customer involvement to scale up their current solution. Certain participants highlighted the fact that varying distribution networks within Europe require modifications of the projects in order to be replicable.
4.2. Identification of Limitations and Barriers
The detailed analysis of the results of the survey allows identifying main barriers for scalability and replicability. The identified scalability and replicability factors already describe necessary conditions for scaling-up and replication and they represent somehow rules to be contemplated for scalability and replicability. The answers to the questionnaires show the projects’ achievements and barriers with regard to scalability and replicability.
Table 3 summarizes the limitations and challenges perceived and described by the participating smart grid projects.
Table 3 also indicates the degree of difficulty for projects to overcome the limitations by themselves, which follows from the received answers of the survey. The degree of difficulty “relatively easy” means that a project is able to overcome the limitations by its own actions (e.g., technical issues such as communication capacity). “Intermediately easy” means that the project can overcome the limitation but with certain additional technical and economic effort (e.g., the use of proprietary standard or provider-specific applications could raise project costs). “Relatively slow/difficult” finally means that the overcoming the limitation mostly depends on factors/actors outside the project (e.g., technical issues such as demographics or issues related to customer behavior are difficult to influence by the project).
In general, difficulties arise after all from the fact that overcoming the barriers mostly depends on actors outside the project with limited influence of the project (e.g., customer behavior). Other factors might or might not pose a problem depending on the project. Note that the limitations detected for the technical scalability factor interface design and for the technical replicability factor network configuration could not have been conclusively judged. The reason is that it is very project dependent whether a limitation might arise or not. For example, a project focusing on energy management systems (EMS) will certainly use a centralized control scheme, but this might not necessarily put at risk its scalability potential. Similarly, the dependency on a particular resource (e.g., solar photovoltaic) might limit the potential zones for replication of the project but it might not necessarily put at risk its replicability potential.
The degree of difficulty of for example the technical scalability factor technology evolution is in general rather low. This factor modestly scored on importance and on the factor itself. Limitations arising from equipment cost, IT/data security and missing standardization of control signal and information flow from/to distributed generation have been detected. The impact on cost and standardization does not depend on the project itself only. By contrast, IT/data security can be handled by the project. Advances in data handling capacities are likely. Modest score together with the uncertainty of predicting technology evolution reduces the importance of the barriers arising from the limitation of this factor. Similarly, the impact of the barriers of the technical scalability factor interface design is reduced since the factor scores modestly because certain solutions (EMS, distribution management systems (DMS), market, etc.) prefer or require a centralized control. Although this factor has high importance but average score, the factor is project and solution dependent and can be handled by the project in a rather straightforward way. By contrast, the economic replicability factor market design obtains a high importance but it scores modestly, indicating a limitation. Actual limitations arise from the lack of remuneration rules, the lack of rules to provide a service, the general dependency on local regulatory frameworks, or the absence of analysis to this end. Only the last limitation can be directly influenced by the project, whereas its influence on regulatory processes is rather small and changes in legal and regulatory frameworks are usually slow. These limitations and varying legal and regulatory framework also affect the scalability and replicability factors profitability, regulation, and business model. Similarly, the technical replicability factor standardization scored modestly too, indicating that there might be problems (for example by employing only proprietary solution and proprietary standards), but the negative impact of proprietary solutions and standards can be somehow mitigated as long as they are interoperable. The use of standards has a positive impact on costs since multiple vendors can provide offers. Open, voluntary and mandatory standards are advantageous since they reduce the existence of multiple proprietary standards, increasing costs of manufacturers. The absence of any standards (in case of new services) has thus a negative impact and adaptation and/or creation of standards is not immediate. Finally, limitations of the homonymous scalability and replicability factors acceptance arise from the difficulty in changing stakeholder behavior (e.g., customers or system operators) and from stakeholder opposition or hesitancy (customer opposition to temporarily limiting power supply to test solutions, system operators’ mistrust of new security principles or manufacturers’ willingness to implement certain functionalities when the core solution seems to work without them, etc.). Apart from stakeholder involvement, certain rules might be necessary to fully and successfully implement a solution (e.g., will electric vehicle (EV) owners connect their car to the grid even if it is not absolutely necessary for them to charge?).
4.3. Lessons Learnt
This section describes the lessons learnt form the survey. In general, it can be said that barriers arising from technical factors can be most easily overcome by the projects; the influence on the lifting of barriers of economic and regulatory and stakeholder related factors is limited and requires considerable effort. Note that although scalability and replicability are design-dependent and should be addressed from the very beginning of the projects, some actions such as computation power upgrade can be easily undertaken during the project or even during the roll-out phase.
Limited communication capacities, limited computation and processing (memory) capacities or limited big data handling capacities do not seem to pose a major problem to scalability. Although they affect the solution, these issues can be usually overcome by the project owner by upgrading its hardware, through advances in computation power or by using data bases more optimally.
Standardization requires some attention, particularly in cases where no standards exist for a new service to be provided. Challenges also arise from vendor-imposed standards and the ability for a standard-conform implementation of components. The fact that some projects do not apply standards confirms IEC’s conclusion on the lack of awareness of standards. Project owners together with operators and manufacturers need to address these issues, and where necessary involve standardization bodies. Certain projects actively contribute to the European standardization activities with regard to equipment and communication protocols. Interoperability is also important and in this regard plug-and-play characteristics of the applied equipment (easing the adding of new components to the solution) are sought by most projects.
The existing infrastructure might impose a limitation on scalability, but this limitation is rather project dependent. A project dealing with asset deferral makes use of such a limitation by increasing distributed generation penetration for example. Whether or not overcoming this barrier is thus often dependent on the project’s scope and the economic consequences of eliminating the barrier (e.g., the need for an additional transformer at the MV/LV substation to increase the capacity so that more distributed generation can be deployed). Further, some projects highlight that a certain existing infrastructure such as AMS is essential for the project to be feasible. Consequently, projects already depend on the availability of a certain infrastructure, an even more demanding requirement for replication. The network configuration of the target location needs to be carefully analysed.
The attention on the economic potential should be increased by carrying out cost-benefit analysis and by taking into account changing macroeconomic environments. Some projects did actually not carry out any cost-benefit analysis and nearly all of them are currently not viable. Clear guidelines for cost-benefit analysis can be found in [
45]. Ideally, the cost-benefit analysis is started and carried out at the early development stages of the project. Different scenarios of solution sizes, the varying regulatory frameworks and market designs of the possible host countries, their macro-economic data,
etc. need to be taken into account.
Stakeholder involvement (homonymous scalability and replicability factors acceptance) requires an increased attention as the introduction of smart grid may implicate the embracement of potentially something entirely new for most stakeholders. Participants of the reported survey highlight that critical stakeholders are mainly customers, grid operators or manufacturers. High investment costs and unclear benefits seem to be major barriers as also pointed out in [
46]. Attention is needed, in both convincing the stakeholders to participate and in establishing rules to involve and make stakeholders participating, as this is a key to a success. Projects indicate that in general they do not have concrete plans or set of rules to attract a higher number of stakeholders outside the scope of their project. This is particularly important with regard of the expected active involvement of customers, which is still highly uncertain.
The dependency on regulatory frameworks and on market designs as well as the absence of regulation require more attention. On the one hand, the majority of the projects implements their proposed solution on a certain regulatory framework and/or market design. This framework is often not implemented and it is tailor made for the purpose of the project itself, which makes it inherently difficult to replicate or to scale up. For example, the TWENTIES project studied the feasibility of providing secondary frequency regulation by wind farms. Current Spanish regulation and market design do however not allow wind farms to provide such service. Regulation lags behind the technological evolution and the technical feasibility, and both regulation and market design pose important barriers not only for viability but even more for scalability and replicability. Inappropriate regulatory frameworks and market designs also act as an important barrier for stakeholder acceptance (e.g., the uncertainty of remuneration or the lack of rules for interaction) as previously mentioned in [
46]. On the other hand, it seems that projects did not pay a lot of attention to the potential application of their solution under a different regulatory framework. Within the European Union a patchwork of different rules and regulations can be found. More uniformity in economic regulation (similar to the technical regulation) might be envisaged. For example, NordREG has identified the issues that should be harmonized in order to establish a common Nordic end-user market [
37]. Usually, replication in terms of regulation and market design is more difficult outside than inside a national environment.
5. Conclusions
This paper has studied the scalability and replicability of smart grid projects. For this purpose, factors have been sought and identified that influence and condition a project’s scalability and replicability. These factors involve technical, economic, regulatory and stakeholder acceptance related aspects, and they have been chosen based on an in-depth literature review. Briefly, technical factors determine whether the solution developed in a particular project is inherently scalable and/or replicable; economic factors reflect whether it is economically viable to pursue scaling up or replication. Factors related to regulation and stakeholder acceptance reflect the extent to which the current environment is ready to embrace a scaled-up version of a project or whether a new environment is suitable for receiving a project.
The proposed scalability and replicability factors have been applied to a case study performed on on-going European and national smart grid projects in order to evaluate and validate these factors. It seems in general that so far technical, economic, and regulatory and stakeholder-related issues were given the same priority for scalability, whereas regulatory and stakeholder-related issues dominated in replicability. Economic replicability issues seem to have attracted less attention. In fact, the scalability factors technology evolution, economies of scale, and existing infrastructure, and the replicability factors standardization and market design obtained lowest scores. Further, the factors interface design, existing infrastructure, regulation, standardization, and market design have a high importance in comparison to the factor score, bearing some potential risks for scalability and replicability. Finally, barriers mainly arise from those factors of which the detected limitations are rather difficult to overcome since overcoming these limitations mostly depends on actors outside the project with limited influence of the project. Other factors might or might not pose an actual barrier depending on the project. In particular, limitations for scalability and replicability might arise from the absence of standards, the physical limits of the existing infrastructure, the absence of cost-benefit analyses and the neglect of varying macroeconomic factors, stakeholder involvement and from the dependency of projects on regional or national regulatory frameworks and market designs.