3.2. Simulation Results
This section examines the effects of each scenario on grids in urban, suburban, and rural regions. It is crucial to first display the grids’ parameters without the penetration of HPs and EVs through Scenario #1 in order to further evaluate the implications of these additional loads for the LV grids. For Scenario #1, the outcomes of the Low Voltage Load Flow Calculations in the urban, suburban, and rural LV grids are depicted in
Table 5,
Table 6 and
Table 7, respectively; they contain the values of maximum loading, minimum voltage at the final terminal, and total active power for each feeder, while solely considering the residential loads.
Equations (1) and (2) and the assumptions in
Section 2.3.1 were used to determine the total load values in the aforementioned tables. For instance, as shown in
Table 5, the total load in Feeder 1 was 47.3 kW, which was calculated by multiplying 21 residential loads (n = 21), the SF value of 0.28 (g(21)), and 8 kW (
). In an H-configuration, such as Feeders 5 and 6, the value of n was equal to the total number of residential loads connected to both feeders (i.e., n = 48 in this example).
The voltage and the maximum loading values along the feeders were given special attention in order to evaluate the performance of grid structures. A comparison of the Feeders 1 to 3 (150 mm
2 cables) in
Table 5,
Table 6 and
Table 7 revealed the effect of increasing the number of loads and the length of the main lines. When Feeders 1 and 2 were contrasted in
Table 7, it can be observed that increasing the number of house connections by 50% and the feeder’s length by 43% (100 m) could result in a 25% rise in the maximum loading; however, there was a slight reduction in voltage. The maximum loading was increased by 55% when comparing Feeders 1 and 3, while the voltage was decreased from 0.986 p.u. to 0.977 p.u. as a result of doubling the number of house connections and extending the feeder by 86% (200 m). Furthermore, to demonstrate how much the grid’s parameters are enhanced when a cable with a larger cross-section is employed, a comparison was made between Feeders 3 and 4 (150 mm
2 and 240 mm
2 cables); in this regard, the maximum loading was reduced by 24% for each of the three grids, and the voltage rose by 0.005 p.u., 0.007 p.u., and 0.007 p.u. for the urban, suburban, and rural grids, respectively, based on the data in the tables above.
In some German suburban and rural grids, the use of LV overhead lines with a cross-section of 70 mm
2 is common. The effect of using overhead lines instead of underground cables can be observed by comparing the results of Feeder 2 (150 mm
2 cable) with Feeder 5 (70 mm
2 overhead line), since both were subjected to the same total load;
Table 6 and
Table 7 show that, under the same conditions, the use of an overhead line (70 mm
2) resulted in a 32% increase in the maximum loading and a 0.01 p.u. drop in voltage compared to the cable (150 mm
2).
According to the findings of the Low Voltage Load Flow Calculations, the feeders with an H-configuration had the identical values for their variables. The minimum voltage was provided by the longest feeder (such as Feeders 6 and 8 in
Table 5), and the maximum loading was determined by taking the highest loading value observed along both feeders. Feeders 1 and 3 were compared with Feeders 6 and 7 in
Table 6 as an example in order to assess the impact of utilizing the H-configuration; Feeders 1 and 6 and Feeders 3 and 7 had the same number of house connections and lengths, and their cable cross-sections were 150 mm
2. As can be seen in
Table 6, Feeder 3 alone had a maximum loading and voltage of 28.37% and 0.971 p.u., respectively. On the other hand, more consumers led to a lower SF when two feeders were coupled in an H-configuration; this increased the voltage to 0.972 p.u. and reduced the maximum loading to 23.63% in Feeders 6 and 7. Finally, use of the 240 mm
2 cables for Feeders 8 and 9 resulted in even better conditions (i.e., 17.83% maximum loading and 0.98 p.u. voltage).
Transformer overloading is another potential bottleneck in the LV grid, which mainly relies on the network’s total load. Considering the power factor of 1 for the residential loads [
23], the total load in the urban, suburban, and rural grids was 335.9 kVA, 296.7 kVA, and 200 kVA, respectively. Consequently,
Table 8 shows the maximum loading of the transformer in each grid for Scenario #1. With a maximum loading of 74.67%, the 400 kVA transformer in the suburban grid had the highest value among the three grids.
Answers to the Questions 2 and 3 in
Section 2.1 can be found by analyzing the data in
Figure 4,
Figure 5,
Figure 6,
Figure 7,
Figure 8,
Figure 9 and
Figure 10. For this purpose, we initially divided the scenarios into two major categories: (1) Scenarios #2 to #5 (with EV penetration only); (2) Scenarios #6 to #9 (with EV and HP penetrations). Then, every transformer and feeder in each type of grid—urban, suburban, and rural—was monitored. Taking into account two charging rates for EVs, the values of the maximum line loading, minimum voltage, and transformer maximum loading in each of the two main categories of scenarios were recorded and utilized to create
Figure 4,
Figure 5,
Figure 6,
Figure 7,
Figure 8,
Figure 9 and
Figure 10; these values were connected with dotted lines to make it easier to visually follow the behavior of feeders and transformers throughout the scenarios. We did not consider any penetration levels that fell between our predefined scenarios.
The minimum threshold of 0.95 p.u. for the voltage magnitude at the last terminals of feeders, as well as the maximum loading limits of 100% and 120% for the line and transformer, respectively, are indicated by the pink highlights.
The voltage drop and loading of a feeder are greatly influenced by its length, conductor cross-section, connected loads, and use of the H-configuration. As
Figure 4 and
Figure 5 illustrate, Feeder 3 was the weakest structure in all scenarios, having the longest length, the greatest number of house connections, and a cable cross-section of 150 mm
2. In contrast, Feeders 7–8 (H-configuration) and Feeder 4 were the strongest ones owing to the use of cables with a larger cross-section (240 mm
2). In the remaining feeders with 150 mm
2 cables, Feeders 1, 2, and 5–6 (H-configuration) were in the order of the highest voltage values as a result of reducing the number of consumers and cable lengths (
Figure 5). This sequence was different when it comes to maximum line loading;
Figure 4 depicts how the four factors that affect line loading combined to arrange Feeders 2, 1, and 5–6 in the highest maximum loading order in the majority of the scenarios.
Upon closer inspection, with the exception of Feeder 3’s voltage of 0.945 p.u. in Scenario #5, there was no violation in the grid’s bottlenecks up to a penetration of 100% EVs (i.e., Scenarios #2 to #5) when the power of 11 kW was utilized for EV charging, as seen in
Figure 4a,
Figure 5a and
Figure 10. The maximum loadings in Scenario #5 were observed in the transformer and Feeder 3 at 100.9% and 73.7%, respectively, indicating that there was no danger of thermal overloading. More under-voltage problems started when 50% EVs+20% HPs (i.e., Scenario #7) were incorporated into the urban grid; feeders with a cable cross-section of 240 mm
2 and Feeder 1 (150 mm
2 cable) were the only ones that did not go beyond the 0.95 p.u. minimum limit in Scenario #7. For Scenarios #8 and #9, none of the configurations were useful to maintain the voltage within the permissible range. The state of line loading was better than the voltage. The first line overloading occurred in Scenario #8 for Feeder 3 (
Figure 4a). In Scenario #9 (100% EVs+40% HPs), Feeders 2 and 5–6 (both 150 mm
2 cables) were overloaded as well.
When 22 kW chargers were used instead of 11 kW chargers, the total loads of EVs increased, resulting in grid bottleneck violations at lower penetration levels of EVs and HPs, as can be seen in
Figure 4b,
Figure 5b and
Figure 10. Regarding the transformer, the first overloading was observed in Scenarios #7 with 22 kW and #8 with 11 kW chargers.
The urban grid example was used to clarify how to read and analyze the data presented in the figures. To prevent readers from being overwhelmed by the sheer volume of data, only the highlights for the suburban and rural grids are provided below.
Drawn from
Figure 6,
Figure 7,
Figure 8,
Figure 9 and
Figure 10,
Table 9 and
Table 10 summarize the weakest and strongest structures for each bottleneck in the suburban and rural LV grids, respectively; these are based on the first occurrence of violations in each of the two main groups of scenarios (with EV penetration and with EV and HP penetrations). For instance, Feeder 5 (70 mm
2 overhead line) had the highest values of maximum line loading compared to the other feeders in the suburban grid, as shown in
Figure 6; therefore, it was recognized as the weakest structure in terms of line loading in
Table 9, which experienced the first overloading in Scenario #8 with 11 kW chargers, as well as in Scenarios #3 and 6 with 22 kW chargers. Feeder 1 in suburban and rural grids was less adversely affected by under-voltage than the other feeders due to its shorter length, fewer loads, and relatively high cable cross-section (150 mm
2).
To sum up, the DSOs might first discover that their grid topologies match or closely resemble one of our specified structures. Afterwards, the results of this investigation assist them in finding out the proportion of new loads that their existing structures can tolerate, as well as in estimating how their grids will behave in the event that upgrades are made. Using conductors with a higher cross-section as a grid upgrade solution typically leads to an improved voltage profile and reduced thermal line loading. Assuming the identical feeder lengths, an H-configuration with a cable cross-section of 240 mm2 is the most reliable structure and is ideal when a large number of loads are connected to the feeder; in our study, it was overloaded only once at the penetration of 100% EVs+40% HPs in the suburban grid, when EVs were charged with a power of 22 kW. However, this configuration was unable to keep the voltage within its specified boundaries in several scenarios; in this context, employing a voltage-regulated distribution transformer (VRDT) can be an effective strategy. Replacing the transformer with one of higher rated power or connecting transformers in parallel is another upgrade option. This bottleneck is particularly problematic in the suburban grid, which could only handle 25% penetration of EVs with a power of 11 kW; under the other scenarios, the transformer maximum loading went over the 120% threshold.