Risk Handling Responsibilities in Tanzanian Project-Based Organisations
Abstract
:1. Introduction
2. Literature Review
2.1. The Construction Industry in Tanzania: The Context
2.2. Risk Handling Responsibilities of Contractual Parties
3. Research Methodology
3.1. Research Approach and Study Area
3.2. Survey Administration
3.3. Sampling Technique and Sample Size
3.4. Research Instrument: The Questionnaire
- (1)
- Section 1 of the questionnaire aimed at collecting general demographic information of the respondents. The kind of information targeted for collection consisted of: position of respondents in the organization, education, gender, and years of experience. The responses were coded to enable cross comparative analysis which is part of a robust data mining protocol [34].
- (2)
- Section 2 of the questionnaire comprised of the rating of the 10 risk handling responsibilities obtained through literature. The same risk handling responsibilities were asked from both contractors and consultants to indicate their perception and ratings based on the construction phase of the road construction project. The rationale for this is that both contractors and consultants are regarded as key players in the contract. Therefore, the main purpose was to obtain the perceptions of each part between contractor and consultant on the ground of contractors’ and consultants’ (contractual parties) perspectives regarding risk handling responsibilities.
- (3)
- Section 3 captured the rating and ranking of the 10 risk handling responsibilities. Respondents were asked to rate how they perceived their risk handling responsibilities using a five-point Likert scale. For both Section 2 and Section 3, respondents were asked to rate how they perceived their risk handling responsibilities using a five-point Likert scale (1 = very low, 2 = low, 3 = moderate, 4 = high, and 5 = very high). Drawing on Kavishe et al. [35], this scale was adopted due to its ability to detect the feelings that respondents have about their attitudes [36]. In addition to the 10 risk handling responsibilities, open-ended questions were asked to further identify any other risk handling responsibilities that were not included in the list. Unfortunately, none of the contractors or consultants responded to this question.
3.5. Data Analysis
4. Findings
4.1. Reliability Analysis
4.2. Response Rate
4.3. The Characteristics of the Sample
4.3.1. Position of the Respondents in the Civil Construction Firm
4.3.2. Education Level and Gender of Respondents
4.3.3. Experience of the Respondents in the Civil Construction Firms
4.4. The Risk Responsibilities of Contractual Parties
4.5. Ranking of the Risk Responsibilities of Contractual Parties—Contractors
4.6. Ranking of the Risk Responsibilities of Contractual Parties—Consultants
4.7. Differences in the Ranking of the Risk Responsibilities of Contractual Parties—Consultants and Contractors
5. Discussion of Findings
5.1. Risk Handling by Both Parties (Contractors and Consultants)
5.1.1. Safety Project Provision
5.1.2. Ensuring Quality Project Provision
5.2. Consultants’ Risk Handling Responsibilities
5.2.1. Safety Project Provision
5.2.2. The Use of Cost Deviation History to Define Contingency Funds for Future Contracts
5.2.3. To Ensure Quality Project Provision
5.2.4. Creation of a Risk Planning Approach
5.2.5. Review of Knowledge on Budgeting
5.3. Contractors’ Risk Handling Responsibilities
5.3.1. Safety Project Provision
5.3.2. Ensuring Quality Project Provision
6. Conclusions
6.1. Theoretical Implications
6.2. Practical Implications
6.3. Limitations and Future Research
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Acknowledgments
Conflicts of Interest
References
- Ploywarin, S.; Song, Y. Analysis of risk-response based on railroad construction project. Int. J. Manag. Sci. Bus. Res. 2014, 3, 2226–8235. [Google Scholar]
- Sospeter, N.G.; Rwelamila, P.D.; Gimbi, J. Critical success factors for managing post disaster reconstruction projects in Angola. Constr. Econ. Build. J. 2020, 20. [Google Scholar] [CrossRef]
- Kamal, A.; Abas, M.; Khan, D.; Azfar, R.W. Risk factors influencing the building projects in Pakistan: From perspective of contractors, clients and consultants. Int. J. Constr. Manag. 2019. [Google Scholar] [CrossRef]
- Bhosale, A.S.; Kavi, K.; Patil, S.B. Risk Management Maturity Model for Road Construction Projects: Case Study. Int. Res. J. Eng. Technol. 2018, 5, 56–72. [Google Scholar]
- Mohamed, O.; Abd-Karim, S.B.; Roslan, N.H.; Mohd Danuri, M.S.; Zakaria, N. Risk management: Looming the modus operandi among construction contractors in Malaysia. Int. J. Constr. Manag. 2015, 15, 82–93. [Google Scholar] [CrossRef]
- Clyde and Co. Structure of the Construction Industry in Tanzania. 2013. Available online: http://www.inhousecommunity.com/upload/pdf/e03348b1933c78bb6127f679678fe45e.pdf (accessed on 15 March 2019).
- Clough, R.H.; Sears, S.K.; Sears, G.A. Construction Contracting: A Practical Guide to Company Management, 7th ed.; Wiley: London, UK, 2005. [Google Scholar]
- NBS. Integrated Business Survey, 2010 Construction Sector Analytical Report; 2013. Available online: www.nbs.go.tz (accessed on 10 July 2020).
- Kangsoo, K.; Jinoh, K.; Donghyung, Y. Analysis of features affecting contracted rate of return of Korean PPP projects. Sustainability 2021, 13, 3311. [Google Scholar] [CrossRef]
- Perera, B.A.K.S.; Rameezdeen, R.; Chileshe, N.; Hosseini, M.R. Enhancing the effectiveness of risk management practices in Sri Lankan road construction projects: A Delphi approach. Int. J. Constr. Manag. 2014, 14, 1–14. [Google Scholar] [CrossRef]
- Iqbal, S.; Choudhry, R.M.; Holschemacher, K.; Ali, A.; Tamošaitienė, J. Risk management in construction projects. Technol. Econ. Dev. Econ. 2015, 21, 65–78. [Google Scholar] [CrossRef]
- Perera, B.; Dhanasinghe, I. Risk Allocation of Road Projects in Sri Lanka. CIB Int. Conf. Build. Educ. Res. 2008, 2, 83–94. [Google Scholar]
- Chileshe, N.; Kikwasi, G.J. Critical success factors for implementation of risk assessment and management practices within the Tanzanian construction industry. Eng. Constr. Archit. Manag. 2014, 21, 291–319. [Google Scholar] [CrossRef]
- Sy, T.D.; Veerasak, L. Risk Response Strategies of International Construction Joint Venture in Vietnam; Chulalongkorn University: Hyogo, Japan, 2011. [Google Scholar]
- Nobanee, H.; Hamadi, F.Y.; Abdulaziz, F.A.; Abukarsh, L.S.; Algahtani, A.F.; Alsubaey, F.K.; Algahtani, S.F.; Almansoori, H.A. A bibliometric analysis of sustainability and risk management. Sustainability 2021, 13, 3277. [Google Scholar] [CrossRef]
- Kanoglu, A.; Gulen, S. Model for managing the contractual risks of construction firms imposed by the procurement system. Int. J. Archit. Eng. Constr. 2013, 2, 43–54. [Google Scholar] [CrossRef]
- Mulokozi, V.V. Assessing the Application of Risk Handling Strategies in Project Planning by Building Contractors in Tanzania. Master’s Thesis, Building Economics Department-Ardhi University, Dar es Salaam, Tanzania, 2017. [Google Scholar]
- Alex, S.; Elena, D. Guide to Effective Risk Management 3.0, 3rd ed.; SVP & Director, Sedgwick Institute: Nashville, TN, USA, 2017. [Google Scholar]
- Adams, F.K. Construction contract risk management. A study on practices in United Kingdom. Cost Eng. 2014, 50, 22–33. [Google Scholar]
- Perera, B.A.K.S.; Dhanasignhe, I.; Rameezdeen, R. Risk management in road construction: The case of Sri Lanka. Int. J. Strateg. Prop. Manag. 2009, 13, 87–102. [Google Scholar] [CrossRef] [Green Version]
- Phoya, S.; Kikwasi, G.; Sospeter, N.G.; Mikapagaro, N. Selection of risk management strategies in informal construction sector. J. Civ. Eng. Archit. 2018, 12, 408–415. [Google Scholar]
- Andi, D. The importance and allocation of risks in Indonesia construction projects. Constr. Manag. Econ. 2006, 24, 69–80. [Google Scholar] [CrossRef]
- Mak, S.; Picken, D. Using risk analysis to determine construction project contingencies. J. Constr. Eng. Manag. ASCE 2000, 126, 130–136. [Google Scholar] [CrossRef]
- Thompson, P.A.; Perry, J.G. Engineering Construction Risks; Thomas Telford: London, UK, 1992. [Google Scholar]
- Wang, M.T.; Chuo, H.Y. Risk allocation and risk handling of highway projects in Taiwan. J. Manag. Eng. 2003, 19, 60–68. [Google Scholar] [CrossRef]
- Saunders, M.; Lewis, P.; Thornhill, A. Research Methods for Business Students, 7th ed.; Pearson Education Limited: Harlow, UK, 2016. [Google Scholar]
- Creswell, J.W.; Creswell, D. Research Design: Qualitative, Quantitative, and Mixed Methods Approaches, 5th ed.; Sage: Thousand Oaks, CA, USA, 2018. [Google Scholar]
- Contractors Registration Board CRB. 2020. Available online: www.crb.go.tz/classification-contractors (accessed on 4 November 2020).
- Manjira, G. Risk Management Practices. Master’s Thesis, Department of Building Economics, Ardhi University, Dar es Salaam, Tanzania, 2018, (unpublished). [Google Scholar]
- Rowley, J. Designing and using research questionnaires. Manag. Res. Rev. 2014, 37, 308–330. [Google Scholar] [CrossRef]
- Hiyassat, M.A.; Alkasagi, F.; El-Mashaleh, M.; Sweis, G.J. Risk allocation in public construction projects: The case of Jordan. Int. J. Constr. Manag. 2020. [Google Scholar] [CrossRef]
- Chileshe, N.; Edwards, D.J.; Kavishe, N.; Haupt, T.C. Perception on challenges impacting bid decision of indigenous building contractors in Dar Es Salaam, Tanzania. J. Eng. Des. Technol. 2020, 18, 1641–1662. [Google Scholar] [CrossRef]
- Chileshe, N.; Edwards, D.J.; Kavishe, N. Critical factors influencing the bid or no-bid decision of the indigenous small building contractors in Tanzania. Constr. Innov. 2021, 21, 182–202. [Google Scholar] [CrossRef]
- Forza, C. Survey research in operations management: A process-based perspective. Int. J. Oper. Prod. Manag. 2002, 22, 152–194. [Google Scholar] [CrossRef] [Green Version]
- Kavishe, N.; Chileshe, N.; Jefferson, I. Public–private partnerships in Tanzanian affordable housing schemes: Policy and regulatory issues, pitfalls and solutions. Built Environ. Proj. Asset Manag. 2019, 9, 233–247. [Google Scholar] [CrossRef]
- Albaum, G. The Likert scale revisited: An alternate version. J. Mark. Res. 1997, 39, 331–348. [Google Scholar]
- Chang, C.Y.; Ive, G. Rethinking the Multi Attribute Utility Approach Based Procurement Route Selection Technique. Constr. Manag. Econ. 2002, 20, 275–284. [Google Scholar] [CrossRef]
- Reig-Botella, A.; Detaille, S.; Clement, M.; Lopez-Golpe, J.; De-Lange, A. Time perspective and the risk of developing burnout: An empirical study among different blue-collar workers in Spain. Sustainability 2021, 13, 3271. [Google Scholar] [CrossRef]
- Cronbach, L.J. Coefficient alpha and the internal structure of tests. Psychometrika 1951, 16, 297–334. [Google Scholar] [CrossRef] [Green Version]
- Nunnally, J. Psychometric Theory, 2nd ed.; McGraw-Hill: New York, NY, USA, 1978. [Google Scholar]
- Pallant, J. SPSS Survival Manual: A Step by Step Guide to Data Analysis Using Version 12; McGraw-Hill Education Open University Press: London, UK, 2005. [Google Scholar]
- Mrema, E.J.; Ngowi, A.J.; Mamuya, S.H.D. Status of occupational health and safety and related challenges in expanding economy of Tanzania. Ann. Glob. Health 2015, 81, 538–547. [Google Scholar] [CrossRef] [Green Version]
- Peckiene, A.; Komarovska, A.; Ustinovicius, L. Overview of risk allocation between construction parties. Procedia Eng. 2013, 57, 889–894. [Google Scholar] [CrossRef] [Green Version]
- Enshassi, A.; Ayyash, A. Factors affecting cost contingency in the construction industry—Contractors’ perspective. Int. J. Constr. Manag. 2014, 14, 191–208. [Google Scholar] [CrossRef]
- Zou, X.W.; Zhang, G. Managing risks in construction projects: Life cycle and stakeholder perspectives. Int. J. Constr. Manag. 2009, 9, 61–77. [Google Scholar] [CrossRef]
- Tembo Silungwe, C.K.; Khatleli, N. An analysis of the allocation of pertinent risks in the Zambian building sector using Pareto analysis. Int. J. Constr. Manag. 2020, 20, 321–334. [Google Scholar] [CrossRef]
- Perez, D.; Gray, J.; Skitmore, M. Perceptions of risk allocation methods and equitable risk distribution: A study of medium to large Southeast Queensland commercial construction projects. Int. J. Constr. Manag. 2017, 17, 132–141. [Google Scholar] [CrossRef] [Green Version]
- Yirenkyi-Fianko, A.B.; Chileshe, N. An analysis of risk management in practice: The case of Ghana’s construction industry. J. Eng. Des. Technol. 2015, 13, 240–259. [Google Scholar] [CrossRef]
- Shapira, Z. “I’ve got a theory paper-Do you?”: Conceptual, empirical, and theoretical contributions to knowledge in the orgaization sciences. Organ. Sci. 2011, 22, 1312–1321. [Google Scholar] [CrossRef]
- Summers, J.O. Guidelines for conducting research and publishing in marketing: From conceptualization through the review process. J. Acad. Mark. Sci. 2001, 29, 405–415. [Google Scholar] [CrossRef]
- Brown, J.R.; Dant, R.P. On what makes significant contribution to the retailing literature: Editorial. J. Retail. 2008, 84, 131–135. [Google Scholar] [CrossRef]
- Voordijk, H. Contemporary issues in construction in developing countries. Constr. Manag. Econ. 2012, 30, 331–333. [Google Scholar] [CrossRef]
- Tang, Y.; Chen, Y.; Hua, Y.; Fu, Y. Impacts of risk allocation on conflict negotiation costs in construction projects: Does managerial control matter? Int. J. Proj. Manag. 2020, 38, 188–199. [Google Scholar] [CrossRef]
Stakeholders | Class I | Class II | Total | ||
---|---|---|---|---|---|
Foreign | Local | Total | |||
Civil Contractor * | 33 | 34 | 67 | 18 | 85 |
Engineering Consultant | 50 | 153 | 203 | ||
Total | 83 | 187 | 67 | 18 | 288 |
Professional | Civil Contractor | Engineering Consultant | Total | |||
---|---|---|---|---|---|---|
Foreign | Local I | Local II | Foreign | Local | ||
Population | 33 | 34 | 18 | 50 | 153 | 288 |
Proposed Sample size (Nf) | 16 | 16 | 12 | 19 | 25 | 88 |
Stakeholder | Class of Registration | Questionnaires | Response Rate (%) | |
---|---|---|---|---|
Distributed | Returned | |||
Civil contractor | Class I | 33 | 33 | 100 |
Class II | 11 | 11 | 100 | |
Engineering Consulting firms | Local * | 33 | 27 | 81.82 |
Foreign | 11 | 9 | 81.82 | |
Total population | 88 | 80 | 90.91 |
Position | Frequency | Percentage | Cumulative (%) |
---|---|---|---|
Low management level | 38 | 47.50% | 47.50 |
Middle management level | 39 | 48.75% | 96.25 |
Top management level | 3 | 5.00% | 100.00 |
Experience (Years) | |||
1–5 | 6 | 7.50% | 7.50 |
5–10 | 55 | 69.75% | 77.25 |
Above 10 | 19 | 22.75% | 100.00 |
Education | |||
Masters | 34 | 42.5% | 42.50 |
Bachelor | 30 | 37.5% | 80.00 |
Diploma | 16 | 20% | 100.00 |
Gender | |||
Female | 5 | 6.25% | 6.25 |
Male | 75 | 93.75% | 100.00 |
Risk Handling Responsibilities | Mean 1 | SD | Rank |
---|---|---|---|
Safety provision | 3.86 | 1.385 | 1 |
Ensure quality project provision | 3.74 | 1.240 | 2 |
Creation of a risk planning approach * | 3.46 | 1.534 | 3 |
Review of knowledge on budgeting | 3.46 | 1.359 | 4 |
The use of cost deviation history to define contingency funds for future contracts | 3.45 | 1.457 | 5 |
To conduct extensive soil survey | 3.24 | 1.352 | 6 |
Provision of quality design and construction | 3.23 | 1.378 | 7 |
Environmental impact assessment | 3.09 | 1.443 | 8 |
Preparation time contingency (Design and construction) | 3.00 | 1.302 | 9 |
Preparation contingency (Design and construction) | 2.71 | 1.398 | 10 |
Risk Handling Responsibilities | Mean Score | SD | Rank |
---|---|---|---|
Safety provision | 3.52 | 1.486 | 1 |
Ensure quality project provision | 3.50 | 1.229 | 2 |
Review of knowledge on budgeting | 3.41 | 1.499 | 3 |
Provision of quality design and construction | 3.34 | 1.430 | 4 |
Creation of a risk planning approach * | 3.30 | 1.564 | 5 |
To conduct extensive soil survey | 3.23 | 1.379 | 6 |
The use of cost deviation history to define contingency funds for future contracts | 2.95 | 1.539 | 7 |
Environmental Impact assessment | 2.86 | 1.579 | 8 |
Preparation contingency (Design and construction) | 2.73 | 1.468 | 9 |
Preparation time contingency (Design and construction) | 2.73 | 1.404 | 10 |
Risk Handling Responsibilities | Mean | SD | Rank |
---|---|---|---|
Safety provision | 4.28 | 1.137 | 1 |
The use of cost deviation history to define contingency funds for future contracts | 4.06 | 1.094 | 2 |
Ensure quality project provision | 4.03 | 1.207 | 3 |
Creation of a risk planning approach * | 3.67 | 1.493 | 4 |
Review of knowledge on budgeting | 3.53 | 1.183 | 5 |
Environmental impact assessment | 3.36 | 1.222 | 6 |
Preparation time contingency (Design and construction) | 3.33 | 1.095 | 7 |
To conduct extensive soil survey | 3.25 | 1.339 | 8 |
Provision of quality design and construction | 3.08 | 1.317 | 9 |
Preparation contingency (Design and construction) | 2.69 | 1.327 | 10 |
RH 1 | Levene’s Test for Equality of Variances | t-test for Equality of Means | |||||||
---|---|---|---|---|---|---|---|---|---|
F | Sig. | t | df | Sig. (2-Tailed) | Mean Difference | Std. Error Difference | 95% Confidence Interval of the Difference | ||
Lower | Upper | ||||||||
RH1 | 4.790 | 0.032 | −0.387 | 78 | 0.700 | −0.119 | 0.307 | −0.730 | 0.493 |
−0.396 | 77.913 | 0.693 | −0.119 | 0.300 | −0.716 | 0.478 | |||
RH2 | 3.545 | 0.063 | −3.608 | 78 | 0.001 * | −1.101 * | 0.305 | −1.708 | −0.494 |
−3.730 | 76.607 | 0.000 | −1.101 | 0.295 | −1.689 | −0.513 | |||
RH3 | 1.238 | 0.269 | −1.926 | 78 | 0.058 | −0.528 | 0.274 | −1.073 | 0.018 |
−1.930 | 75.417 | 0.057 | −0.528 | 0.274 | −1.073 | 0.017 | |||
RH4 | 0.681 | 0.412 | 0.830 | 78 | 0.409 | 0.258 | 0.310 | −0.360 | 0.875 |
0.837 | 76.859 | 0.405 | 0.258 | 0.308 | −0.355 | 0.870 | |||
RH5 | 8.139 | 0.006 | −2.506 | 78 | 0.014 | −0.755 * | 0.301 | −1.355 | −0.155 |
−2.573 | 77.682 | 0.012 | −0.755 | 0.293 | −1.339 | −0.171 | |||
RH6 | 4.332 | 0.041 | −1.548 | 78 | 0.126 | −0.497 | 0.321 | −1.137 | 0.142 |
−1.588 | 77.790 | 0.116 | −0.497 | 0.313 | −1.121 | 0.126 | |||
RH7 a | 0.025 | 0.874 | −1.078 | 78 | 0.284 | −0.371 | 0.344 | −1.057 | 0.314 |
−1.083 | 76.118 | 0.282 | −0.371 | 0.343 | −1.054 | 0.311 | |||
RH8 | 0.183 | 0.670 | −0.074 | 78 | 0.941 | −0.023 | 0.306 | −0.632 | 0.586 |
−0.075 | 75.695 | 0.941 | −0.023 | 0.305 | −0.630 | 0.585 | |||
RH9 | 4.782 | 0.032 | −2.116 | 78 | 0.038 | −0.606 * | 0.286 | −1.176 | −0.036 |
−2.168 | 77.848 | 0.033 | −0.606 | 0.279 | −1.163 | −0.050 | |||
RH10 | 0.089 | 0.766 | 0.104 | 78 | 0.918 | 0.033 | 0.316 | −0.597 | 0.662 |
0.105 | 77.194 | 0.917 | 0.033 | 0.313 | −0.590 | 0.656 |
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations. |
© 2021 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Sospeter, N.G.; Chileshe, N. Risk Handling Responsibilities in Tanzanian Project-Based Organisations. Sustainability 2021, 13, 8078. https://doi.org/10.3390/su13148078
Sospeter NG, Chileshe N. Risk Handling Responsibilities in Tanzanian Project-Based Organisations. Sustainability. 2021; 13(14):8078. https://doi.org/10.3390/su13148078
Chicago/Turabian StyleSospeter, Nyamagere Gladys, and Nicholas Chileshe. 2021. "Risk Handling Responsibilities in Tanzanian Project-Based Organisations" Sustainability 13, no. 14: 8078. https://doi.org/10.3390/su13148078
APA StyleSospeter, N. G., & Chileshe, N. (2021). Risk Handling Responsibilities in Tanzanian Project-Based Organisations. Sustainability, 13(14), 8078. https://doi.org/10.3390/su13148078