Next Article in Journal
Analysis of Fatal and Injury Traffic Accidents in Istanbul Sarıyer District with Spatial Statistics Methods
Previous Article in Journal
Sustainability Challenge of Eastern Europe—Historical Legacy, Belt and Road Initiative, Population Aging and Migration
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Toward Reducing Construction Project Delivery Time under Limited Resources

by
Hossam H. Mohamed
1,
Ahmed H. Ibrahim
1 and
Asmaa A. Soliman
2,*
1
Construction Engineering & Utilities Department, Faculty of Engineering, Zagazig University, Zagazig 44519, Egypt
2
Civil Engineering Department, Higher Technological Institute (H.T.I), 10th of Ramadan City 44629, Egypt
*
Author to whom correspondence should be addressed.
Sustainability 2021, 13(19), 11035; https://doi.org/10.3390/su131911035
Submission received: 10 September 2021 / Revised: 26 September 2021 / Accepted: 28 September 2021 / Published: 5 October 2021

Abstract

:
One of the most vital construction project aspects is to complete a project in minimum time restricted to the time–cost trade-off. Overlapping activities’ planning and their impact on the project under limited resource constraints should be considered. This study aims to develop a model for optimizing the project schedule and cost regarding overlap activities and their impacts. This study reviews previous studies on changes in past activities likely to produce additional reworking of subsequent activities. In addition, an AHP model is developed to assess the reworking time of subsequent activities based on possible changes in previous activities. In addition, five realistic construction projects are applied. Finally, an optimizing model is developed for optimizing project time and cost using overlapping techniques by using the Java program. The results indicate that the proposed model can be used by project managers easily for solving time and cost optimization problems. In addition, it can be updated to continuously improve its functionality. Finally, it can be updated later to support AI for finding better solutions.

1. Introduction

Rework in construction projects is a widespread problem that affects project performance negatively. First, it is necessary to clarify the definition of reworking, because how it is defined helps to find solutions and reduce risks [1]. Love et al. [2] defined rework as the unnecessary effort to re-implement a process or activity incorrectly carried out the first time regardless of any changes in project scope or design that might lead to additional work. Enshassi et al. [3] defined rework as a serious problem in construction projects in the Gaza Strip, which was one of the main reasons for the delays in schedule and increased construction costs, besides customer dissatisfaction. There are various definitions of rework in the construction management literature, which mainly include quality deviations, quality failures, defects, and non-conformance. Martins et al. [4] introduced a model using cluster analysis to classify risks. Risks are classified according to different risk categories, activity development, sensitivity, production reliability, and constraints on construction projects. The delay in the schedule was defined as completing the construction project after the specified date. This delay is often accompanied by cost overruns. Delays in the schedule include location conditions, slow approval of work permits, design errors, delays in funding and progress payments, owner intervention, improper planning, inadequate subcontractors, and source change orders [5]. Cheng and Darsa [6] developed an ANN model to predict the time delay in a project. Identifying the most important factors affecting a project could reduce delays in the construction schedule.

2. Literature Review

Chaos and complexity dominate construction sites, imposing difficult conditions for the establishment of reliable, robust, and easily controlled schedules [7]. For the past few decades, both the critical path method (CPM) and the program evaluation and review technique (PERT) are the main methods for planning and scheduling construction projects [8]. However, one of the biggest drawbacks of both the CPM and PERT is that they usually assume unlimited resources [9] In addition, the CPM assumes that unlimited resources will be available at any time, when necessary, for implementing project activities; this assumption is unrealistic because activities require quantification of resources and are limited in terms of resources (resources are limited in scheduling). Often, the demand for resources exceeds the maximum number of resources available for a project. To reduce the supply and demand problem, scheduling techniques (RCS) based on priority rules are used. The start date for some activities for which the required resources are not available is postponed [10,11,12]. Construction projects often face a challenge to complete them in the minimum time. Overlapping between construction activities with early information from precedent activities shortens project completion with the expense of rework in downstream activities. However, the expected amount of rework must be properly quantified to decide on the overlapping method. Ballesteros-Pérez et al. [13] stated that the sensitivity of activities measures the importance of the activities in the project schedule. Based on this, highly sensitive activities are those that are likely to increase the volatility of project duration and/or cause project duration extensions. Hossain and Chua [14] stated that reconstruction would lead to physical rework, such as adding more concrete to the foundation or even replacing the existing one with a new one. This rework is costly and may take a long time, delaying the completion of the project. Wasfy [15] indicated that rework results in a cost increase in commercial residential towers from 2% to 30%. It also results in delays in the duration of implementation from the original 10% to 77%. In addition, the rework causes dissatisfaction among clients and contractors. Love et al. [2] introduced a conceptual framework of causality from reworking that focused on errors and violations visually, besides improving the outcomes of safety. Rework negatively affects construction projects and causes risks, such as losses in productivity, stress and fatigue, reputational damage, loss of profit, project delays, disputes, and an increase in the cost of insurance [16]. Lindhard et al. [17] studied the impact of some different sequences of activities on the production gap, crew waiting time, and production delay by simulating work items where the sequence of items was arranged from line to parallel. Pena-Mora and Li [18] proposed a framework for overlap between two parallel activities to reduce the risk of reworking downstream activity using the concept of the upstream evolution rate and the sensitivity of the downstream activity. Hamdi et al. [19] mentioned that traditional project-scheduling methods are widely used as tools to support projects but cannot exploit direct and indirect forms of information flow between activities in projects. Han et al. [20] and Hwang et al. [21] reported that the design error causes up to 79% of the cost of reworking. In addition, reworking contributes to cost overruns of 5% of total construction costs. Wandahl et al. [22] identified the key factors causing time overruns in on-site construction. These factors were construction design, connecting works, external conditions, workforce, components and materials, space, equipment, and machinery. Starting a downstream activity based on unfinished information introduces the risk of rework in the downstream work should there be a change in upstream information. The information exchanged is also associated with a level of uncertainty, depending on this upstream activity. Future upstream information modifications require to rework in the downstream activity to address the changes in the initial information based on which the downstream activity has started. The resulting rework usually consumes resources (e.g., time and money) and disrupts the flow of downstream work. Kyunghwan [23] proposed a general approach to the critical path to limited resources method (RCPM) that helps implement the RCPM regardless of the resource-constrained scheduling (RCS) method applied under multiple resource constraints. Ammar [24] modeled the problems of leveling and allocating resources under the LOB scheme. Considering the maintenance of the continuity of resources and the logical dependency of activities, in addition, a steady rate of progress in the activity has been imposed. Figure 1 shows that the mechanism of overlapping of two dependent activities in the case of rework is probable to take place. Figure 1 was created using the Microsoft Excel program. The probability of rework depends on several factors, such as the type and complexity of overlapped activities, their relation with other activities in the project schedule, and the value of overlapping. The mechanism of activity overlapped is shown in two cases, (A) where there is no overlapping between activities and case (B) where there is overlapping between activities and rework time. Hossam et al. [25] identified the most significant changes and risks that may have occurred in previous activities. These changes lead to the rework of subsequent and dependent activities. The study was conducted through a 100-item questionnaire in Egyptian companies. The top eight important variables were lack of coordination and poor communication, the contractor’s instructions to modify a design, non-compliance with the specification, the owner’s instructions to modify a design, incomplete design at the time of the tender, poor planning and coordination of resources, errors made in the contract documentation, and lack of experience and knowledge of the design and construction process. These variables are used in this study to assess the value of reworking construction projects using the AHP model.

3. Research Objectives

The main objectives of this research are shown in these steps: (1) To develop an analytical hierarchy to predict the value of reworking on subsequent activities based on possible changes in past activities, considering the overlap between dependent activities; (2) To develop a model for optimizing the project schedule and cost under project constraints, such as the overlap of activities, the amount of reworking time because of applying the overlap method, and loss of productivity due to application of the overtime method; and (3) assess the impact of these changes, the time of emergency reworking, the loss of productivity on the project schedule, and the cost by applying the model to a real project.

4. Research Methodology

This paper introduces a four-step process for generating a fast-track mathematical model in Figure 2. The first step is to quantify the category and level of the potential changes in upstream activities. These potential changes caused reworks in downstream activities due to activity overlapping. The second step is to predict the number of reworks in downstream activities. This was developed by using the AHP model depending on the overlapping period and the potential changes in upstream activities. The third step consists of formulating a Java program to derive the minimum duration and cost of the construction project. This was generated by several trials conducted due to overlapping between the critical paths. Then, in each trial, the net benefit of the project was computed by considering the number of overlapping periods, extra costs due to overlapping, indirect costs, and time saving. The fourth and last is the presentation of the conclusion. These assumptions were made to ensure proper implementation of the Java mathematical model:
(1)
The resource requirements of each activity during the execution process remain unchanged.
(2)
The overlapping period is an integer and time reworks added to successor activities in a fraction.
(3)
Work on an activity starts as soon as some information is received from the other dependent activities (the relationship between activities is early to start).
(4)
The study is concerned only with the eight most critical changes in upstream activities.

5. Analytical Hierarchy Model

A questionnaire survey was used to evaluate and predict the amount of rework in downstream activities, depending on activity overlapping and the changes in upstream activities.

5.1. Sample Size

To compute the specified sample size for an infinite population, we used Equation (1) of Bartlett et al. [26]:
N = K2 × P (1 − P)/E2
where N is the required sample size for an infinite population, K is equal to 1.645 when the confidence level is 90%, P is the population proportion (the critical value of P is 0.5), and E is an appropriate margin of error, at 10% for a confidence level of 90%.
By substituting these parameters into Equation (1), the sample size for the infinite population in the specified study was 68, which was the minimum value.

5.2. Survey Analysis

In total 125 questionnaires were administered to professionals and experts in different construction projects, and 100 questionnaires representing 80% of the 125 questionnaires administered were returned. The respondents’ job titles were classified into three categories in construction projects. The first category from a designer viewpoint represented 71%, the second category from a contractor viewpoint represented 89%, and the third category from an owner viewpoint represented 80% of all categories. The respondents to the questionnaire were classified according to their experience, which showed that about 14% of the respondents had an experience of less than 10 years, around 48% had an experience of greater than or equal to 10 years and less than 20 years, around 30% had an experience of greater than or equal 20 years and less than 30 years, and, finally, 8% had an experience of greater than or equal to 30 years.

6. The Analytic Hierarchy Process (AHP) Model

The analytic hierarchy process (AHP) developed by Saaty [27] is a powerful multi-criteria decision-making tool used in numerous applications in various fields of economics, politics, and engineering. This method allows determining the weights of hierarchically non-structured or particular hierarchical-level criteria regarding those belonging to a higher level. The hierarchy of the top important changes causing reworks in downstream activities is shown in Figure 3. The analytic hierarchy process (AHP) steps are shown in Figure 4 by using the Microsoft Excel program. The data were gathered from experts in construction projects in Egypt via Microsoft forms and physical and telephone interviews with senior managers of several construction management teams. The experts performed pairwise comparisons, and then we analyzed the results.
The priority weights of rework time contingency criteria from the AHP model are shown in Table 1.
In addition, the ranking of the main changes and sub-changes is shown in Table 2. The average relative weights of the main changes and sub-changes are shown in Figure 5 and Figure 6, respectively, by using the Microsoft Excel program.

7. AHP Model Verification

To check the accuracy of the estimated time rework contingency (21.44%) that came from the AHP model, data were collected from experts from their previous projects. Table 3 includes the collected data and their analysis for five projects. It was noted that the actual time rework contingency ranged from 0.11 to 0.40 out of the project duration. Thus, the average actual rework time contingency of the five projects was 24.79% close to the value obtained from the developed model (22.44%). From the five real projects, the actual time rework consistency = (original total time (without overlapping) − actual total time (after overlapping))/(original total time (without overlapping)) × 100. Based on Zayed and Halpin [28], two equations were used to verify the developed time contingency model in Equations (6) and (7) as follows:
% Error (Average Invalidity Percent) = (E − A)/A × 100
%Average Validity Percent = 100 − % Error
where E: estimated time rework contingency (output value from the model), A: actual time rework contingency (%)
  • % Error (average invalidity percentage = (21.44−24.79)/(21.44) × 100 = 15.63%)
  • Average validity percentage = 100 − 15.63 = 84.37%
The values of percentage error and average validity percentage showed that the developed model is robust in predicting the values of time rework contingency.

8. AHP Model Validation (Application in Actual Case Studies)

The expected time rework contingency for five case studies of real projects was calculated with the relative weight (Wi) from the AHP model by these steps:
  • Insert the frequency and severity number for each factor to reflect its significance, where 0 indicates the lack of the factor’s effect and 10 indicate the high factor’s effect.
  • Put the relative weight (Wi) = weight of main criteria × weight of sub-criteria, as determined in Table 3 from the AHP model.
  • Calculated the rework time contingency = ∑Wi × Fi × Si.
The expected time rework contingency for project 1 is shown in Table 4. The expected time rework contingency for the other case studies was computed as project 1. Table 5 presents the actual and estimated time rework contingencies calculated by using the model. It shows that the absolute difference in cost contingency ranged from 9% to 14.04%, which is less than the mentioned mean absolute percentage (15.63%). Therefore, the model testing passed successfully.

9. Model Formulation for Applying the Overlapping Method

In this research, an optimizing model was developed for optimizing project time and cost using overlapping techniques by using the Java program.
4.
The objective function was to minimize the total time and optimize the costs.
5.
Decision variables were indexes to choose among different overlapping periods between upstream and downstream activities.
6.
Constraints defined the availability of overlapping time for each activity in integer time, limiting the total time of the project to a deadline, and the resource limit was 10 labor/day. In addition, the predecessor’s logical relationship was a constraint.
The mathematical model was developed using a Java program depending on the following equations. The impact of overlapping time on the project duration, the time saving, indirect saving cost, and net benefit of overlapping are shown in the following Equations (4)–(10):
CI (Downstream activity) = Wi × Fi × Si
Rt (due to overlapping) = CI × OT
Rt (Critical activities) = ∑CI ∗ OT (Critical activities)
Time-Saving of the Project (due to overlapping) = ∑ (OT) Critical Activities − (Rt (Critical activities))
Cost Saving (due to overlapping) = [Time Saving (due to overlapping)] ∗ [Early Completion Cost]
Rc (due to overlapping) = C Successor/unit ∗ Rt (due to overlapping)
Net Benefit of Overlapping = [Cost Saving (due to overlapping)] − Rc (due to overlapping)
where:
  • CI: time rework contingency index in the downstream activity, Wi: relative weight of each problem in an upstream activity and equal to weight of main criteria × weight of sub-criteria, Fi: frequency of each problem (probability of occurrence of rework), Si: severity of each problem causing rework in the downstream activity due to overlapping (impact), OT: overlapping period between the downstream and upstream activities, Rt (due to overlapping): predicted rework time value in the downstream activity, Rc (due to overlapping): cost of rework of the successor activity due to overlapping (overlapping costs), C Successor: total cost of the downstream activity and C Successor/unit: cost of the downstream activity per unit

10. Application Model for Case Study 4 with Limited Resources

The project was assigned to one main contractor and included these works: removal of damaged items, installation of new items, and maintenance of damaged items. A project with seven activities with their description and the technical relationship is shown in Table 6 by using the Microsoft Excel program. The project indirectly cost EGP 500/day; the penalty costs were EGP 400/day. The main objective of the study was to resolve the resource overallocation and meeting the project deadline with minimum cost. The planner’s target was to meet the 135-day deadline, and the resource limit was 10 labor/day.
The initial schedule is shown below in Figure 7 by using the Microsoft Excel program and shows that the total time equaled 135 days. The total cost was equal to the total cost of all activities and early completion cost per day multiplied by the total cost. The total cost was equal to 172,000 + (500 × 135) = EGP 239,500. In addition, the resource over-allocated is shown in Figure 8 by using the Microsoft Office Project program. The resource over-allocation was solved by delaying the task; the simplest way to correct that over-allocation is to delay one task, ideally a task with lower priority than the others. This done using Microsoft Office Project in Figure 9 and Figure 10. We noted that the total time of the project increased from 135 days to 160 days, and the total cost was EGP 252,000. All resources were allocated.

11. Applying the Overlapping Method

The overlapping method can be applied by these steps in Figure 11 using the Microsoft Word program. The activity data after resolving resource constraints using Microsoft Office Project are shown in Figure 10. The steps in applying the mathematical model are shown below.
First, the rework time and cost slope for the overlapping activities were calculated by data from the AHP model in Table 7. If each of the subsequent activities was exposed to all possible changes in the previous activities, then its rework time value was the maximum value of all activities and was equal to 0.2144.
Second, the activity data that included activity name, description, duration, cost, leveling delays, labor number, and precedence were inserted, as shown in Figure 12.
Third, the indirect cost per day, early completion cost per day, and resource limit per day were inserted, finally applying the overlapping method, as shown in Figure 13.

12. Results of Applying the Overlapping Method

From the optimization model, in the first case without applying the overlapping method, the total time was equal to 160 days, the total cost was equal to EGP 252,000, and overlapping costs were equal to zero, as shown in Figure 14.
The second case was of selecting activities that can overlap with dependent activities, considering the lower-cost activity priority and critical activities. One-day overlapping from activity G and 1-day overlapping from activity F. The extra cost equal to EGP 1666.667, the saving time equal to 1.5712 day, a total cost of EGP 252,095.4666, and a net benefit of EGP −881.06666 L.E after computing indirect costs as shown in Figure 15. The next step was repeated for all critical activities, and the number of all tries equaled 20 trials in Figure 16. In each trial, the overlapping activities were selected, the overlapping duration determined, and the extra cost and net benefit determined. The minimum time was 130.9328 days, with a time saving of 29.0672 days.
The results show that the method first determined critical paths that overlapped between downstream activities, depending on upstream potential changes. The rework factor is determined to always depend on the activity. Here, the rework factor was the maximum value for each activity (0.2144) from the AHP model. The rework time amount was determined by the multiplied rework factor and overlapping duration. Then the rework time for each factor was added to its duration. In each trial, the model calculated overlapping costs, total time, time saving, cost saving, and net benefit. Activity G overlapped 19 days with activity F and 18 days with activity E. The minimum reduction time was 130.9328 days, time saving was 29.0672 days, and total cost was EGP 253932.80.

13. Conclusions

The results show that the average rework time contingency of five real projects was 24.79% close to that (22.44%) obtained from the model. The value of percentage error was 15.63%, and the average validity percentage was 84.37%. This study is the first to consider the time rework value. Previous studies have assumed or neglected these values. In this study, overlapping rework values were added to the duration of the downstream activity and to the required hours for the successor task. The calculated hours and cost for each activity were next added to calculate the overall cost of schedule compression. In addition, a new model based on the AHP technique was developed to guide time rework planners in estimating time rework contingencies. A time rework contingency model was developed to predict an appropriate contingency percentage based on the anticipated project’s level of changes occurring in upstream activities. The time rework contingency value resulted from the model (21.44%), not being constant for projects, will change for every project, depending on the value of the frequency and impact of factors affecting cost contingency. The research methodology was performed using a deterministic approach. In the deterministic approach, the average impact and likelihood for each factor were obtained from the survey results. Future research work can improve the model by using stochastic data inputs. In addition, the overlapping method is cheaper than the overtime method; the duration in the calculation is used in hours to increase the accuracy of the model. The model is easy to update, and it is easy to improve its functionality with no limits using the Java programming capabilities. In addition, it is easy to use by project managers for solving time and cost optimization problems.

Author Contributions

Conceptualization, A.A.S., A.H.I. and H.H.M.; methodology, A.H.I. and H.H.M.; software, A.A.S.; validation, A.A.S., A.H.I. and H.H.M.; formal analysis, A.A.S.; investigation, A.H.I.; data curation, H.H.M.; writing—original draft preparation, A.A.S.; writing—review and editing, A.A.S., A.H.I. and H.H.M. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Love, P.E.D.; Edwards, D.J.; Watson, H.; Davis, P. Rework in civil infrastructure projects: Determination of cost predictors. J. Constr. Eng. Manag. 2010, 136, 275–282. [Google Scholar] [CrossRef]
  2. Love, P.E.; Edwards, D.J.; Smith, J. Rework causation: Emergent theoretical insights and implications for research. J. Constr. Eng. Manag. 2016, 142, 1–9. [Google Scholar] [CrossRef]
  3. Enshassi, A.; Sundermeier, M.; Abo Zeiter, M. Factors Contributing to Rework and their Impact on Construction Projects Performance. Int. J. Sustain. Constr. Eng. Technol. 2017, 8, 22–33. [Google Scholar]
  4. Martins, C.; Bogus, M.S.; Valentin, V. Conceptual Quantitative Model to Group Risks in Fast-Track Construction Projects. In Proceedings of the ASCE International Conference on Computing in Civil Engineering, Atlanta, GA, USA, 17–19 June 2019; pp. 507–513. [Google Scholar] [CrossRef]
  5. Zhang, J.; Chen, F.; Yuan, X. Comparison of cost and schedule performance of large public projects under P3 and traditional delivery models: A Canadian study. Constr. Manag. Econ. 2019, 38, 739–755. [Google Scholar] [CrossRef]
  6. Cheng, M.-Y.; Darsa, M.H. Construction Schedule Risk Assessment and Management Strategy for Foreign General Contractors Working in the Ethiopian Construction Industry. Sustainability 2021, 13, 7830. [Google Scholar] [CrossRef]
  7. Lindhard, S.; Wandahl, S. Exploration of the reasons for delays in construction. Int. J. Constr. Manag. 2014, 14, 36–44. [Google Scholar] [CrossRef]
  8. Jain, V.; Sethi, P.; Arya, S.; Verma, R.; Chawla, C. Project Evaluation Using Critical Path Method & Project Evaluation Review Technique. Wesley. J. Res. 2020, 13, 1–9. [Google Scholar]
  9. Bettemir, Ö.H.; Sonmez, R. Hybrid Genetic Algorithm with Simulated Annealing for Resource-Constrained Project Scheduling. J. Manag. Eng. 2015, 31, 04014082. [Google Scholar] [CrossRef]
  10. Lu, M.; Li, H. Resource-activity critical-path method for construction planning. J. Constr. Eng. 2003, 129, 412–420. [Google Scholar] [CrossRef] [Green Version]
  11. Nisar, S.A.; Yamamoto, K.; Suzuki, K. Resource-dependent critical path method for identifying the critical path and the Real floats in resource-constrained project scheduling. J. Jpn. Soc. Civ. Eng. 2013, 69, 97–107. [Google Scholar] [CrossRef] [Green Version]
  12. Pantouvakis, J.-P.; Manoliadis, O.G. A practical approach to resource-constrained project scheduling. Int. J. Oper. Res. 2006, 6, 299–309. [Google Scholar] [CrossRef]
  13. Ballesteros-Pérez, P.; Cerezo-Narváeza, A.M.; Otero-Mateo, M.; Pastor-Fernándeza, A.; Vanhouckeb, M. Performance comparison of activity sensitivity metrics in schedule risk analysis. Autom. Constr. 2019, 106, 1–11. [Google Scholar] [CrossRef]
  14. Hossain, M.A.; Chua, D.K.H. Overlapping design and construction activities and an optimization approach to minimize rework. Int. J. Constr. Proj. Manag. 2013, 32, 983–994. [Google Scholar] [CrossRef]
  15. Wasfy, M.A. Severity and impact of rework, a case study of a residential-commercial tower project in the eastern province-KSA. Master’s Thesis, King Fahd University of Petroleum, Dhahran, Saudi Arabia, 2010. [Google Scholar]
  16. Love, P.E.D.; Smith, J.; Ackermann, F.; Irani, Z. Making sense of rework and its unintended consequence in projects: The emergence of uncomfortable knowledge in practice. Int. J. Constr. Proj. Manag. 2019, 37, 501–516. [Google Scholar] [CrossRef]
  17. Lindhard, S.; Hamzeh, F.; Gonzalez, V.; Wandahl, S.; Ussing, L. Impact of Activity Sequencing on Reducing Variability. J. Constr. Eng. Manag. 2019, 145, 1–9. [Google Scholar] [CrossRef]
  18. Pena-Mora, F.; Li, M. Dynamic planning and control methodology for design/build fast-track construction projects. J. Constr. Eng. Manag. 2001, 127, 1–17. [Google Scholar] [CrossRef]
  19. Hamdi, B.; Udechukwu, O.; Alasdair, M.; Maxwell, C.; Amer, A.Y. The analysis of information flow interdependencies within projects. Prod. Plan. Control. 2020, 31, 1–17. [Google Scholar] [CrossRef]
  20. Han, S.; Love, P.; Peña-Mora, F. A system dynamics model for assessing the impacts of design errors in construction projects. Math. Comput. Model. 2013, 57, 2044–2053. [Google Scholar] [CrossRef]
  21. Hwang, B.; Thomas, S.; Haas, C.; Caldas, C. Measuring the impact of rework on construction cost performance. J. Constr. Eng. Manag. 2009, 135, 187–198. [Google Scholar] [CrossRef]
  22. Wandahl, S.; Neve, H.; Kalsaas, B.T.; Møller, D.E.; Lindhard, S.M. Ranking and comparing key factors causing time-overruns in on-site construction. Int. J. Constr. Manag. 2020, 20, 1–7. [Google Scholar] [CrossRef]
  23. Kim, K. Generalized Resource-Constrained Critical Path Method to Improve Sustainability in Construction Project Scheduling. Sustainability 2020, 12, 8918. [Google Scholar] [CrossRef]
  24. Ammar, M.A. Resource optimization in line of balance schedules. Constr. Manag. Econ. 2019, 38, 715–725. [Google Scholar] [CrossRef]
  25. Hossam, H.M.; Ahmed, H.I.; Asmaa, A.S. Construction Factors that Causing Reworks in Downstream Activities Due to Overlapping. Int. J. Civ. Eng. Technol. 2020, 12, 19–32. [Google Scholar]
  26. Bartlett, J.E.; Kotrlik, J.W.; Higgins, C.C. Organizational Research: Determining Appropriate Sample Size in Survey Research. Inf. Technol. Learn. Perform. J. 2001, 19, 43–50. [Google Scholar]
  27. Saaty, T.L. Axiomatic Foundation of the Analytic Hierarchy Process. Manag. Sci. 1996, 3, 841–855. [Google Scholar] [CrossRef]
  28. Zayed, T.; Halpin, D.W. Deterministic models for assessing productivity and cost of bored piles. Constr. Manag. Econ. 2005, 23, 531–543. [Google Scholar] [CrossRef]
Figure 1. Mechanism of activity overlapping in case (A) and Case (B).
Figure 1. Mechanism of activity overlapping in case (A) and Case (B).
Sustainability 13 11035 g001
Figure 2. Research methodology.
Figure 2. Research methodology.
Sustainability 13 11035 g002
Figure 3. Hierarchy of the top important changes affecting time rework contingency due to overlapping.
Figure 3. Hierarchy of the top important changes affecting time rework contingency due to overlapping.
Sustainability 13 11035 g003
Figure 4. The analytic hierarchy model process (AHP) steps.
Figure 4. The analytic hierarchy model process (AHP) steps.
Sustainability 13 11035 g004
Figure 5. Relative weights of main changes.
Figure 5. Relative weights of main changes.
Sustainability 13 11035 g005
Figure 6. Relative weights of sub-changes.
Figure 6. Relative weights of sub-changes.
Sustainability 13 11035 g006
Figure 7. Snapshot of the initial project schedule using the Microsoft Excel program.
Figure 7. Snapshot of the initial project schedule using the Microsoft Excel program.
Sustainability 13 11035 g007
Figure 8. Resource usage of resources by Microsoft Office Project.
Figure 8. Resource usage of resources by Microsoft Office Project.
Sustainability 13 11035 g008
Figure 9. Project schedule after leveling resources of the activities.
Figure 9. Project schedule after leveling resources of the activities.
Sustainability 13 11035 g009
Figure 10. Activities’ resources after delaying the activities by Microsoft Office Project.
Figure 10. Activities’ resources after delaying the activities by Microsoft Office Project.
Sustainability 13 11035 g010
Figure 11. Overlapping method.
Figure 11. Overlapping method.
Sustainability 13 11035 g011
Figure 12. Activity data after resolving resource constraints using the Java program.
Figure 12. Activity data after resolving resource constraints using the Java program.
Sustainability 13 11035 g012
Figure 13. Applying the overlapping method.
Figure 13. Applying the overlapping method.
Sustainability 13 11035 g013
Figure 14. Output calculations in the first case without applying the overlapping method.
Figure 14. Output calculations in the first case without applying the overlapping method.
Sustainability 13 11035 g014
Figure 15. Output calculations of the second case after applying the overlapping method (1-day overlapping from activity G and 1-day overlapping from activity F).
Figure 15. Output calculations of the second case after applying the overlapping method (1-day overlapping from activity G and 1-day overlapping from activity F).
Sustainability 13 11035 g015
Figure 16. Summary of results of the overlapping method.
Figure 16. Summary of results of the overlapping method.
Sustainability 13 11035 g016
Table 1. Priority weights of rework time contingency criteria from the AHP model.
Table 1. Priority weights of rework time contingency criteria from the AHP model.
CriteriaCriteria WeightSub-CriteriaSub-Criteria WeightRelative Weight (Wi)Frequency (Fi)Severity (Si)Rework Time Contingency
(R t c)
Designer0.14240Incomplete design at the time of the tender0.41770.05950.4440.4860.0128
Errors made in the contract documentation0.56800.08090.4050.5170.0169
Contractor0.46657Design change initiated by the contractor0.22960.10710.3450.4420.0163
Non-compliance with specification0.37630.17560.4630.5150.0419
Poor planning and coordination of resources0.37980.17720.3680.5760.0376
Owner0.37674Lack of coordination and poor communication0.21310.08030.5140.6590.0272
Design change initiated by the owner0.38080.14350.4190.5170.0311
Lack of experience and knowledge of the design and construction process0.39180.14760.4170.4970.0306
Rework time contingency (C) = ∑Wi × Fi × Si.0.2144
Table 2. Ranking of the main changes and sub-changes.
Table 2. Ranking of the main changes and sub-changes.
Changes CategoryTotal WeightPriority VictorRank
aDesigner-related changes9.96820.14243
bContractor-related changes32.65990.46661
cOwner-related changes26.37190.37672
aDesigner-Related Changes
a.1Incomplete design at the time of the tender 29.24070.41772
a.2Errors made in the contract documentation39.75930.56801
bContractor-Related Changes
b.1Design change initiated by the contractor 16.07300.22963
b.2Non-compliance with specifications 26.34320.37632
b.3Poor planning and coordination of resources 26.58370.37981
cOwner-Related Changes
c.1Lack of coordination and poor communication14.91590.21313
c.2Design change initiated by the owner26.65910.38082
c.3Lack of experience and knowledge of the design and construction process27.42500.39181
Table 3. Actual time rework contingency analysis for the five actual construction projects.
Table 3. Actual time rework contingency analysis for the five actual construction projects.
Project No.Project
Description
Changes in Upstream ActivitiesTarget Total Time (Days)Actual Total Time (Days)Actual Time Rework Contingency
(Time Saving/Target Time)
1Primary school (Aswan)Removal of damaged items, installation of new items, and maintenance of some damaged items3002100.30
2A multi-story building (Suez)Modifications from the owner at the Hall of Conferences; several design changes introduced by the owner in a lot of items4804000.17
3Construction of building in 10th Ramadan CityLow experience for certain activities to be constructed and teamwork not qualified9005400.400
4Construction of building in 10th Ramadan CityLack of coordination, poor communication, and design change initiated by the contractor1351200.11
5Construction of governmental garage in CairoChange in the area of the garage by the owner from 200 × 100 m2 to 200 × 150 m2 and addition of inspection rooms4203100.26
Average actual time rework consistency0.247936508
Table 4. Estimated time rework contingency analysis for project 1.
Table 4. Estimated time rework contingency analysis for project 1.
Factor No.Changes in Upstream Activities That Caused Time Rework in Downstream ActivitiesRelative Weight (Wi)Project 1
Frequency (Fi) %Severity (Si) %Estimated Rework Time Contingency
F1Incomplete design at the time of the tender0.0594849360.70.40.0167
F2Errors made in the contract documentation0.0808833280.80.50.0324
F3Design change initiated by the contractor0.1071312750.50.70.0375
F4Non-compliance with specifications0.175584970.40.50.0351
F5Poor planning and coordination of resources0.1771880890.550.30.0292
F6Lack of coordination and poor communication0.0802776630.40.40.0128
F7Design change initiated by the owner0.1434800080.80.50.0574
F8Lack of experience and knowledge of the design and construction process0.1476023830.50.70.0517
Estimated rework time contingency for project 1 = ∑Wi × Fi × Si0.2728
Table 5. Actual and estimated time rework contingency analysis for the five actual construction projects.
Table 5. Actual and estimated time rework contingency analysis for the five actual construction projects.
No.Project DescriptionChanges in Upstream Activities Target Total Time (Days)Actual Total Time (Days)Actual Time Rework Contingency
(Time Saving/Target Time)
Estimated Time Rework Contingency
(from Model)
% Error
(E-A)/A
%
Absolute
1Primary school (Aswan)Removal of damaged items, installation of new items, and maintenance of some damaged items3002100.3000.2728−0.0919.082
2Residential building (Suez)Modifications from the owner at the Hall of Conferences; several design changes introduced by the owner in a lot of items4804000.1670.18700.122212.2211
3Construction of building in 10th Ramadan CityLow experience for certain activities to be constructed and teamwork not qualified9005400.4000.44750.11911.863
4Construction of building in 10th Ramadan CityLack of coordination, poor communication, and design change initiated by the contractor1351200.1110.0955−0.1414.04
5Construction of governmental garage in CairoChange in the area of the garage from 200 × 100 m2 to 200 × 150 m2 and addition of inspection rooms4203100.2620.28550.099.00
Table 6. Initial project data.
Table 6. Initial project data.
IDActivity NameActivity DescriptionPredecessorsDuration (Days)LagCost (EGP)
1AMobilization works……15 22,000
2BSupply of materialsA15 32,000
3CSupply of carpentry and electrical worksA2030 with A10,000
4DExcavation worksA20 22,000
5EPlacing the concrete footingB, D3010 with D36,000
6FPlacing the concrete columnsE30 30,000
7GWall worksC, F30 20,000
Table 7. Rework time and cost slope for the overlapping activities by data from the AHP model.
Table 7. Rework time and cost slope for the overlapping activities by data from the AHP model.
IDDownstream ActivityUpstream ActivitiesOverlapping
Activities
Max.
Overlapping Downstream
Effect of the Upstream Changes on the Upstream Activity Due to 1-Day Overlapping
Time
Rework
Cost Slope (Rework Cost)
1A………………….…….…….
2BAOL (A, B)150.2144686.0714
3CAOL (A, C)150.2144214.3973
4DAOL (A, D)150.2144471.6741
5EBOL (E, B)150.2144771.8303
DOL (E, D)200.2144771.8303
6FEOL (E, F)300.2144643.1919
7GCOL (G, C)200.2144428.7946
FOL (G, F)300.2144428.7946
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Mohamed, H.H.; Ibrahim, A.H.; Soliman, A.A. Toward Reducing Construction Project Delivery Time under Limited Resources. Sustainability 2021, 13, 11035. https://doi.org/10.3390/su131911035

AMA Style

Mohamed HH, Ibrahim AH, Soliman AA. Toward Reducing Construction Project Delivery Time under Limited Resources. Sustainability. 2021; 13(19):11035. https://doi.org/10.3390/su131911035

Chicago/Turabian Style

Mohamed, Hossam H., Ahmed H. Ibrahim, and Asmaa A. Soliman. 2021. "Toward Reducing Construction Project Delivery Time under Limited Resources" Sustainability 13, no. 19: 11035. https://doi.org/10.3390/su131911035

APA Style

Mohamed, H. H., Ibrahim, A. H., & Soliman, A. A. (2021). Toward Reducing Construction Project Delivery Time under Limited Resources. Sustainability, 13(19), 11035. https://doi.org/10.3390/su131911035

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop