1. Introduction
The world energy market is going through a monumental shift from a fossil-fuel-based system to a renewable energy-based system, following the Paris agreement signed in 2015. According to [
1], the share of renewable energy in the power sector would increase from 25% in 2017 to 85% by 2050, mostly through growth in solar and wind power generation. In the Nordic and European power market, the share of solar and wind power is expected to increase from about 20% to over 55% between 2018 and 2040 [
2].
Technological advances in the field of wind turbines, solar panels, and batteries are increasing the efficiency of these systems and thus reducing their levelized unit cost of energy (LCOE). According to [
1], it will be possible to build wind farms at 25 euros/MWh within 10 years. The inclusion of larger amount of wind and solar power causes price volatility due to surplus or deficit of energy at any given time. This also applies for Norway because the share of its regulated production is falling, as the growth in consumption is primarily covered by wind power [
3]. This calls for the need to increase flexibility in operation of the existing power production and storage systems. Flexibility is the ability to make quick changes in operation at any time such that the balance between production and consumption can always be maintained, with lowest possible cost for carrying out such changes. The need for such flexibility can be both short-term, where changes are needed to balance the system within hours, minutes, and seconds, or long-term, in order to balance the system for days or weeks. There are various solutions that compete to provide flexibility, such as hydropower, hydrogen, and batteries. Among these solutions, regulated hydropower can provide both short- and long-term flexibility.
Norway has almost half of the reservoir capacity in Europe [
4], and thus has a great potential for providing the much-needed flexibility for the European power market in the future. Various studies are being conducted to explore this possibility [
5,
6,
7,
8]. The results indicate that a high proportion of hydropower with large reservoirs has so far resulted in relatively low short-term price volatility in the Nordic region. However, the price volatility is currently increasing, and the operation of the hydropower plants is becoming more dynamic. Operating the existing and new power plants with dynamic operational regime comes with various technical challenges and operational risks. The Norwegian Research Centre for Hydropower Technology (HydroCen) [
9] is conducting research in a number of areas to assess such technical difficulties and provide sustainable solutions to meet the future flexibility requirements in Norwegian hydropower system. Its scope of work ranges from long-term stability of structures, electrical and mechanical systems, environmental impacts, and market conditions.
In this article, the authors analyze the production data of some Norwegian power plants to establish some operational trends in order to explore how the operational regimes may influence the long-term stability of unlined hydropower pressure tunnels. Such tunnels constitute the majority of water conveyance system in Norwegian hydropower plants, with a total length of more than 4300 km and pressurized up to 1047 m of water pressure [
10,
11]. Since tunnels are unlined, water is in direct contact with the rock mass and the pressure transients resulting from operational changes directly affect the discontinuities in the rock mass, which in the long-term, cause block falls as a result of cyclic fatigue due to frequent pressure pulsations. Further, the authors analyze a two-year long real-time monitoring data [
12] consisting of tunnel water pressure and rock mass pore pressure from the unlined headrace tunnel of Roskrepp hydropower plant in Southern Norway. The results are discussed, and the implications of powerplant operation regarding block instabilities in the pressure tunnels are discussed. A recommendation to reconsider the shutdown/opening duration is made based on the findings.
4. Discussion
The underlying axiom of block theory is that the failure of an excavation begins at the boundary with the movement of a block into the excavated space [
19]. This implies that the orientation of joints should be conducive to create a wedge in order to cause a block fall. Further, removal of key blocks could result in extended fallouts. The existing block theory is still applicable for assessing the block falls due to tunnel operation, except for the fact that additional destabilizing forces are created during hydropower plant operation. This is not a one-time event but a cumulative effect of many small events, referred to as cyclic fatigue, which occurs over the course of hydropower plant operation. During tunnel excavation, potentially unstable wedges are identified, and adequate support is provided. However, relatively stable and unsupported blocks during construction may be destabilized as a result of weakened joints due to long-term fatigue over the years of hydropower plant operation. In some occasion, the potential rock blocks are not detected during construction. More importantly, some blocks may be held together by an intact rock bridge posing no threat of block falls during construction. Such intact rock bridges can gradually weaken due to the cumulative effect of HI and eventual rupture causing block falls. Similar findings have been highlighted by Preisig et al. [
20] where the rupture of intact rock bridges due to seasonal pore pressure changes are attributed as the cause of progressive failure and fatigue in deep-seated landslides.
Figure 16 shows an example of a block fall witnessed in the TBM section of the 4.5 m diameter unlined headrace tunnel of Ulset power plant, which has been in operation since 1985. Unlined tunnels are generally dewatered for inspection after one year of operation to investigate if there are large block falls which could pose major stability issues in the future. The first inspection of this tunnel was conducted in 1986 after one year of operation, which revealed no major instabilities but showed some minor block falls [
21]. For unlined pressure tunnels, minor block falls are expected during the first inspection because the rock mass is subjected to a new ground water regime and reduced effective stresses after tunnel filling. The washing of joint infilling material also reduces joint stiffness, which further contributes to block falls. The situation stabilizes after a new equilibrium is reached. The second inspection report carried out in 1992 [
22,
23] also does not show any serious instability issues. The last inspection was conducted by the first and third author of this article in 2017. During this inspection, several block falls similar to the one shown in
Figure 16 were observed along the whole TBM tunnel length. From the Roskrepp measurements, it is now evident that additional load or hydraulic impact occurs during load changes. Hence, it is postulated herein that such block falls are the result of rock mass fatigue caused by cumulative HI due to transient events with load changes over the years. It is noted that the operational regime of Norwegian hydropower plants has changed after the deregulation of power market in 1991 [
13]. This is most likely a contributing factor for the observed block falls because the deregulation has resulted in more start/stops and load-change events.
The results presented in previous sections clearly indicate that additional load on rock joints or HI due to hydropower plant operation depends on the shutdown duration and the magnitude of load changes. With the increase in intermittent energy in the future power system, it is very likely that both these parameters will be affected. Results from the analysis of production data show that both the number of starts/stops and frequency and magnitude of load changes will increase in the future. This means that the tunnels will experience stronger transients with increased frequency, causing more transient cycles with higher HI and accelerated fatigue.
The analyses show that hydropower plants with smaller units experience smaller number of load changes every year, but the proportion of large load changes relative to their plant capacities are much higher. This means that their waterways experience more transients with larger amplitudes relative to the static pressure. The minimum design factor of safety against mass oscillations in unlined pressure tunnels is 1.3 [
24], meaning the normal stress acting against a critical joint must be at least 1.3 MPa if the design tunnel static pressure is 1 MPa. A larger load change causes bigger mass oscillation amplitudes which are closer to critical normal stress (or reduced factor of safety). Frequent events with such oscillation pressures close to critical normal stress contribute to accelerating the cyclic fatigue, especially if the transients occur when the tunnel static pressure is close to design static pressure. On the other hand, small transients even though in larger numbers may not necessarily have a higher impact on the rock mass. This could suggest that the rock mass around the tunnel in smaller hydropower plants may experience fatigue at a faster rate, assuming similar rock mass and effective stress conditions. However, it is difficult to ascertain in absolute terms whether a relatively strong transient in hydropower plants with low static head is more damaging than relatively weaker transient in hydropower plant with high static head. It is highlighted that the HI is dependent on the resistance to flow through joints, which is a function of void geometry of joints in the rock mass and the length of flow path, i.e., length between tunnel wall and any particular point in the rock joint inside the tunnel wall. Hence, the HI values presented in the results are specific for the length of joint between tunnel wall and BH1/BH4. The variation of HI along joint length with different rock–mechanical properties such as joint stiffness, friction angle and dilation, and effective stresses is studied in detail by [
16] using numerical simulation.
The analysis shows that shutdown duration is the most dominant parameter affecting hydraulic impact (HI) on rock joints. The results presented in this work are only from shutdown or reduction of load in the hydropower plant. Pressure transients also occur in the system when increasing load or opening the turbine valves, which also cause significant hydraulic impact. It can be inferred that similar to shutdown duration, the duration of opening has a significant impact since it also affects how the mass oscillation pressure develops during the transient.
A larger share of intermittent energy demands for increased flexibility in operation, which may mean that power plants need to change load faster, hence affecting the shutdown duration. However, it is uncertain to what extent the shutdown duration is affected owing to higher flexibility needs. As seen from the measurement and analysis, the current trend of shutdown duration as seen in Roskrepp is still contributing to accelerate the rock mass fatigue, which is explained below.
Based on the results, it would be logical that for larger load changes, both shutdown and opening should be carried out slowly to avoid stronger transients. However, it is dependent on the individual power plant operators due to lack of standard procedure for normal load-change operations. In
Figure 13b, we can see that the shutdown duration is irrespective of head loss before the transient and three distinct clusters of shutdown durations are seen for similar head loss values. As seen in the results, faster shutdown causes significantly larger HI, which could be reduced by a slower shutdown. For example, for head loss of 3 m, the shutdown durations vary from 170 to 65 s, and the HI due to mass oscillation are 3–9 times higher (
Figure 12). This could be avoided by having a slower normal shutdown. The idea is to carry out normal shutdowns/openings based on the magnitude of load changes such that larger load changes take longer shutdown/opening durations. These durations should be long enough for the rock mass pore pressure to closely follow the change in pressure in the tunnel during a transient. The optimum shutdown duration must be decided individually for each hydropower plant since the hydropower plants are unique in terms of parameters such as rock joint conditions in the tunnel contour, design head and discharge, length of the waterway, and number of brook intakes, contributing to different nature of the mass oscillations. As seen from the Roskrepp measurements, shutdown durations larger than 200 s seem to give the lowest possible impact with respect to shutdown from full load and is the recommended shutdown duration from full load for this power plant to reduce the hydraulic impact.
For hydropower plants to be constructed in the future or upgraded, a larger surge tank can be designed to reduce the pressure rise and also the time between start of shutdown and maximum mass oscillation amplitude, i.e., the shutdown duration becomes longer. In the case of pre-existing hydropower plants, slower operation of the units may be the most reasonable solution to reduce the hydraulic impact on rock mass around unlined pressure tunnels.
Slower shutdowns/openings cause lower hydraulic impact on the rock mass, which would help slow down the fatigue process. It is envisaged that such slow shutdowns/openings could be done in two different ways: (1) by standardizing a slow manual loading/de-loading of the units or (2) by using a slow preprogrammed and automated governor operation routine. Such measures may help to reduce the number of block falls and prolong the serviceable lifetime of unlined pressure tunnels and shafts.
Prediction of block falls due to transient events is a challenging issue because of the lack of a governing equation that defines the process of cyclic fatigue due to external (hydraulic) and internal (gravitational, friction and shear) forces that cause the failure of rock joints and intact rock bridges. Large variation in the hydromechanical properties of rock joints and in situ rock stresses add challenges in quantifying the hydraulic impact and the eventual fatigue. Further, the cumulative effect of HI is difficult to quantify in real cases since no monitoring systems are installed to record the pore pressure and long-term deformation in the rock mass. However, back analysis of particular block fall cases may be carried out using advanced numerical modelling with specific input parameters such as joint orientations, hydromechanical properties, in situ stress conditions, and pressure oscillations, which would help to gain more knowledge to address the aforementioned challenges.
5. Conclusions
The production data of some Norwegian hydropower plants shows that there is a large variation of start/stop events for each hydropower plant every year and also between different hydropower plants. The hydropower plants without operational restrictions have average annual start/stop events between 200 and 400 per unit, with a standard deviation up to 150. It is also seen that the number of start/stop events are in increasing order after the year 2009, and this increasing trend is significant for smaller hydropower plants. Further, the study of the magnitude of load changes in these hydropower plants suggests that there are higher numbers of smaller load changes (smaller than 25% of full capacity per hour) and smaller numbers of larger load changes (larger than 75% of full capacity per hour). More importantly, larger load changes are in higher proportion (more than 15% of total load-change events) for smaller power plants as compared to larger hydropower plants. This amounts to about 150–200 large load changes per turbine with installed capacity smaller than 50 MW. The production forecast for Roskrepp hydropower plant suggests that start/stop events and large load changes will increase by 30–45% between 2025 and 2040. From these observations, the authors conclude that dynamic operation of hydropower plants shows an increasing trend which can lead to larger destabilizing forces in the rock joints and accelerated fatigue of the rock mass in the future.
The monitored pressure transients and the pore pressure response in the rock mass during real-time operation at Roskrepp power plant have been used to develop a new method to quantify the effect of hydraulic transients on rock joints, referred to as the hydraulic impact (HI). The hydraulic impact is a destabilizing force that is regarded to be the main driver for instability, rock blocks fall, and potential tunnel collapses caused by hydraulic transients. The authors conclude that the duration of shutdown during a load reduction event is the most dominant parameter regarding the hydraulic impact, followed by the magnitude of load change. The faster the shutdown event, the higher the hydraulic impact, and it is more than 10 times higher when the shutdown duration is halved (i.e., from 130 to 65 s). The measurements show that tunnel dewatering has also caused significant increase in hydraulic impact, indicating irreversible changes in the joint void geometry and increase in the joint permeability, which can contribute to block falls over long-term operation.
It is observed that there is a large variation in shutdown duration, even for similar magnitude of load changes, ranging from 60 s to 200 s, because there is no standard procedure for shutdown duration and is entirely up to the operators to decide. Based on the results in this work, the authors recommend that durations of normal shutdowns/ openings should be longer than current practice so that changes in pore pressure in the rock mass are more gradual. Normal shutdowns/openings should be carried out based on the magnitude of load changes such that larger load changes take longer shutdown/opening durations. Slower shutdowns/openings cause a slower pressure increase in tunnels and shafts and, thus, a lower hydraulic impact on the rock mass, which would help slow down the cyclic fatigue process.