The Current Risk Management Practices and Knowledge in the Construction Industry
Abstract
:1. Introduction
2. Literature Review
3. Materials and Methods
4. Results and Discussions
4.1. Current State of Risk Management Practices
4.2. Current State of Risk Management Practices
4.2.1. Risk Identification Techniques
4.2.2. Risk Analysis Techniques
4.2.3. Risk Response Techniques
5. Conclusions and Recommendations
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Acknowledgments
Conflicts of Interest
References
- Schoonwinkel, S.; Fourie, C.J.; Conradie, P.D.F. A risk and cost management analysis for changes during the construction phase of a project. J. South Afr. Inst. Civ. Eng. 2016, 58, 21–28. [Google Scholar] [CrossRef] [Green Version]
- Owoo, N.S.; Lambon-Quayefio, M.P. The Construction Sector in Ghana. 2018. Available online: https://www.econstor.eu/handle/10419/190166 (accessed on 25 May 2022).
- Urbański, M.; Haque, A.U.; Oino, I. The moderating role of risk management in project planning and project success: Evidence from construction businesses of Pakistan and the UK. Eng. Manag. Prod. Serv. 2019, 11, 23–35. [Google Scholar] [CrossRef] [Green Version]
- Quigley, Q.J.; Dickson, A.; Kirytopoulos, K. Project Complexity and Risk Management (ProCRiM): Towards modelling project complexity driven risk paths in construction projects. Int. J. Proj. Manag. 2016, 34, 1183–1198. [Google Scholar] [CrossRef] [Green Version]
- Bahamid, R.A.; Doh, S.I.; Al-Sharafi, M.A.; Rahimi, A.R. Risk Factors Influencing the Construction Projects in Yemen from Expert’s Perspective. IOP Conf. Ser. Mater. Sci. Eng. 2020, 712, 12007. [Google Scholar] [CrossRef]
- Wu, J.; Zhou, Y. Risk assessment of urban rooftop distributed PV in energy performance contracting (EPC) projects: An extended HFLTS-DEMATEL fuzzy synthetic evaluation. Sustain. Cities Soc. 2019, 47, 101524. [Google Scholar] [CrossRef]
- Choudhry, R.M.; Iqbal, K. Identification of risk management system in construction industry in Pakistan. J. Manag. Eng. 2013, 29, 42–49. [Google Scholar] [CrossRef]
- PMI. A Guide to the Project Management Body of Knowledge (PMBOK Guide), 5th ed.; Project Management Institute, Inc.: Newton Square, PA, USA, 2017. [Google Scholar]
- Boateng, S.; Ameyaw, A.; Mensah, C. Assessment of systematic risk management practices on building construction projects in Ghana. Int. J. Constr. Manag. 2020, 1–10. [Google Scholar] [CrossRef]
- Amani, N.; Safarzadeh, K. Project risk management in Iranian small construction firms. J. Eng. Appl. Sci. 2022, 69, 1–14. [Google Scholar] [CrossRef]
- Elghdban, M.G.; Azmy, N.B.; Zulkiple, A.B.; Al-Sharafi, M.A. A Systematic Review of the Technological Factors Affecting the Adoption of Advanced IT with Specific Emphasis on Building Information Modeling; Springer: Berlin/Heidelberg, Germany, 2021; Volume 295. [Google Scholar] [CrossRef]
- Mills, A. A systematic approach to risk management for construction. Struct. Surv. 2001, 19, 245–252. [Google Scholar] [CrossRef] [Green Version]
- Serpell, A.; Ferrada, X.; Rubio, L.; Arauzo, S. Evaluating Risk Management Practices in Construction Organizations; Elsevier: Amsterdam, The Netherlands, 2015. [Google Scholar]
- Shojaei, S.A.S.; Haeri, P. Development of supply chain risk management approaches for construction projects: A grounded theory approach. Comput. Ind. Eng. 2019, 128, 837–850. [Google Scholar] [CrossRef]
- Taofeeq, K.; Adeleke, D.M.; Hassan, A.Q. Factors Affecting Contractors risk attitude from Malaysia construction industry perspective. Soc. Sci. Humanit. J. 2019, 3, 1281–1298. [Google Scholar]
- Crispim, J.; Silva, L.H.; Rego, N. Project risk management practices: The organizational maturity influence. Int. J. Manag. Proj. Bus. 2019, 12, 187–210. [Google Scholar] [CrossRef]
- Odeh, H.T.; Battaineh, A.M. Causes of construction delay: Traditional contracts. Int. J. Proj. Manag. 2002, 20, 67–73. [Google Scholar] [CrossRef]
- Sambasivan, Y.W.; Soon, M. Causes and effects of delays in Malaysian construction industry. Int. J. Proj. Manag. 2007, 25, 517–526. [Google Scholar] [CrossRef]
- Wang, C.; Tang, Y.; Kassem, M.A.; Ong, H.Y.; Yap, J.B.H.; Ali, K.N. Novel Quality-Embedded Earned Value Performance Analysis Tool for Sustainable Project Portfolio Production. Sustainability 2022, 14, 8174. [Google Scholar] [CrossRef]
- Adeleke, M.W.; Bahaudin, A.Q.; Kamaruddeen, A.Y.; Bamgbade, A.M.; Ali, J.A. An empirical analysis of organizational external factors on construction risk management. Int. J. Suppl. Chain Manag. 2019, 8, 932. [Google Scholar]
- Kassem, M.A.; Khoiry, M.A.; Hamzah, N. Using Relative Importance Index Method for Developing Risk Map in Oil and Gas Construction Projects. J. Kejuruter. 2020, 32, 85–97. [Google Scholar] [CrossRef]
- Renuka, S.M.; Umarani, C.; Kamal, S. A Review on Critical Risk Factors in the Life Cycle of Construction Projects. J. Civ. Eng. Res. 2014, 4, 31–36. [Google Scholar] [CrossRef]
- Ahmad, S.A.; Issa, U.H.; Farag, M.A.; Abdelhafez, L.M. Evaluation of Risk Factors Affecting Time and Cost of Construction Projects in Yemen. Int. J. Manag. IJM 2013, 4, 11. [Google Scholar]
- El-Sayegh, R.; Manjikian, S.M.; Ibrahim, S.; Abouelyousr, A.; Jabbour, A. Risk identification and assessment in sustainable construction projects in the UAE. Int. J. Constr. Manag. 2021, 21, 327–336. [Google Scholar] [CrossRef]
- Issa, U.H.; Farag, M.A.; Abdelhafez, L.M.; Ahmed, A.S. A risk allocation model for construction projects in Yemen. Civ. Environ. Res. 2015, 7, 78–89. [Google Scholar]
- Mukhtar, N.H.; Kassem, A.; Khoiry, M.A. Theoretical review on critical risk factors in oil and gas construction projects in Yemen. Eng. Constr. Archit. Manag. 2020; in press. [Google Scholar] [CrossRef]
- Bahamid, R.A.; Doh, S.I.; Al-Sharaf, M.A. Risk factors affecting the construction projects in the developing countries. IOP Conf. Ser. Earth Environ. Sci. 2019, 244, 012040. [Google Scholar] [CrossRef]
- Banaitiene, N.; Banaitis, A. Risk Management in Construction Projects. In Risk Management—Current Issues and Challenges; InTech Open: London, UK, 2012. [Google Scholar] [CrossRef] [Green Version]
- El-Karim, M.S.B.A.A.; El Nawawy, O.A.M.; Abdel-Alim, A.M. Identification and assessment of risk factors affecting construction projects. HBRC J. 2017, 13, 202–216. [Google Scholar] [CrossRef] [Green Version]
- Kassem, M.A. Risk Management Assessment in Oil and Gas Construction Projects Using Structural Equation Modeling (PLS-SEM). Gases 2022, 2, 33–60. [Google Scholar] [CrossRef]
- Enshassi, A.; Mosa, J.A. Risk Management in Building Projects: Owners ’ Perspective. IUG J. Nat. Eng. Stud. 2008, 16, 95–123. [Google Scholar]
- Augustine, E.; Ajayi, J.R.; Ade, B.A.; Edwin, A.A. Assessment of risk management practices in Nigerian construction industry: Toward establishing risk management index. Int. J. Pure Appl. Sci. Technol. 2013, 16, 20–31. [Google Scholar]
- Bahamid, R.A.; Doh, S.I. A review of risk management process in construction projects of developing countries. IOP Conf. Ser. Mater. Sci. Eng. 2017, 271, 012042. [Google Scholar] [CrossRef]
- Chatterjee, K.; Zavadskas, E.K.; Tamošaitien, J.; Adhikary, K.; Kar, S. A hybrid MCDM technique for risk management in construction projects. Symmetry 2018, 10, 46. [Google Scholar] [CrossRef] [Green Version]
- Rezakhani, P. Classifying Key Risk Factors in Construction Projects. Bull. Polytech. Inst. Jassy Constr. Archit. Sect. 2012, 62, 27–38. [Google Scholar]
- Dutta, E. Study of risk in construction contracts. Int. J. Res. Eng. Technol. 2014, 2, 21–26. [Google Scholar]
- Hansen-Addy, E.; Fekpe, A. Risk Management Knowledge and Practices in the Ghanaian Construction Industry. 2015. Available online: http://www.westeastinstitute.com/wp-content/uploads/2015/07/Andrew-Hansen-Addy.pdf (accessed on 26 May 2022).
- Szymański, P. Risk management in construction projects. Procedia Eng. 2017, 208, 174–182. [Google Scholar] [CrossRef]
- Fan, Y.; Stevenson, M. Reading on and between the lines: Risk identification in collaborative and adversarial buyer–supplier relationships. Supply Chain. Manag. 2018, 23, 351–376. [Google Scholar] [CrossRef]
- Wang, S.Q.; Dulaimi, M.F.; Aguria, M.Y. Risk management framework for construction projects in developing countries. Constr. Manag. Econ. 2004, 22, 237–252. [Google Scholar] [CrossRef]
- Zavadskas, E.K.; Turskis, Z.; Tamošaitiene, J. Risk assessment of construction projects. J. Civ. Eng. Manag. 2010, 16, 33–46. [Google Scholar] [CrossRef] [Green Version]
- Wang, C.; Tang, Y.; Kassem, M.A.; Li, H.; Hua, B. Application of VR technology in civil engineering education. Comput. Appl. Eng. Educ. 2022, 30, 335–348. [Google Scholar] [CrossRef]
- Ismael, D.; Shealy, T. Sustainable construction risk perceptions in the Kuwaiti construction industry. Sustainability 2018, 10, 1854. [Google Scholar] [CrossRef] [Green Version]
- Kassem, M.A.; Khoiry, A.; Hamzah, N. Evaluation of Risk Factors Affecting on Oil and Gas Construction Projects in Yemen. Int. J. Eng. Technol. 2019, 8, 6–14. [Google Scholar] [CrossRef]
- Siang, L.C.; Ali, A.S. Implementation of Risk Management in the Malaysian Construction Industry. J. Surv. Constr. Prop. 2012, 3, 1–15. [Google Scholar] [CrossRef]
- Andi. The importance and allocation of risks in Indonesian construction projects. Constr. Manag. Econ. 2006, 24, 69–80. [Google Scholar] [CrossRef]
- Iqbal, S.; Choudhry, R.M.; Holschemacher, K.; Ali, A.; Tamošaitienė, J. Risk management in construction projects. Technol. Econ. Dev. Econ. 2015, 21, 65–78. [Google Scholar] [CrossRef]
- Kartam, N.A.; Kartam, S.A. Risk and its management in the Kuwaiti construction industry: A contractors’ perspective. Int. J. Proj. Manag. 2001, 19, 325–335. [Google Scholar] [CrossRef]
- Li, X.; Wang, C.; Kassem, M.A.; Alhajlah, H.H.; Bimenyimana, S. Evaluation Method for Quality Risks of Safety in Prefabricated Building Construction Using SEM–SDM Approach. Int. J. Environ. Res. Public Health 2022, 19, 5180. [Google Scholar] [CrossRef] [PubMed]
- El-Sayegh, S.; El-Sayegh, S.M. Project risk management practices in the UAE construction industry. Int. J. Proj. Organ. Manag. 2014, 6, 121–137. [Google Scholar] [CrossRef]
- Hiyassat, M.A.; Alkasagi, F.; El-Mashaleh, M.; Sweis, G.J. Risk allocation in public construction projects: The case of Jordan. Int. J. Constr. Manag. 2022, 22, 1478–1488. [Google Scholar] [CrossRef]
- Alaghbari, W.; Salim, A.; Dola, K.; Ali, A.A.A. Identification of significant factors influencing housing cost in Yemen. Int. J. Hous. Mark. Anal. 2012, 5, 41–52. [Google Scholar] [CrossRef]
- Lyons, M.; Skitmore, T. Project risk management in the Queensland engineering construction industry: A survey. Int. J. Proj. Manag. 2004, 22, 51–61. [Google Scholar] [CrossRef] [Green Version]
- El-Sayegh, S.M.; Mansour, M.H. Risk assessment and allocation in highway construction projects in the UAE. J. Manag. Eng. 2015, 31, 04015004. [Google Scholar] [CrossRef]
- Hatem, Z.M.; Kassem, M.A.; Ali, K.N.; Khoiry, M.A. A New Perspective on the Relationship Between the Construction Industry Performance and The Economy Outcome-A Literature Review. 2022. Available online: https://www.researchgate.net/profile/Zaid-Hatem/publication/359402109_A_New_Perspective_on_the_Relationship_Between_the_Construction_Industry_Performance_and_The_Economy_Outcome-A_Literature_Review/links/623a2e3a2708166c05437280/A-New-Perspective-on-the-Relationship-Between-the-Construction-Industry-Performance-and-The-Economy-Outcome-A-Literature-Review.pdf (accessed on 28 May 2022).
- Loosemore, M.; Raftery, J.; Reilly, C. Risk Management in Projects; Routledge: London, UK, 2006. [Google Scholar]
- Forbes, M.; Smith, D.; Horner, S. Tools for selecting appropriate risk management techniques in the built environment. Constr. Manag. Econ. 2008, 26, 1241–1250. [Google Scholar] [CrossRef]
- Jaafari, A. Management of risks, uncertainties and opportunities on projects: Time for a fundamental shift. Int. J. Proj. Manag. 2001, 19, 89–101. [Google Scholar] [CrossRef]
- Zou, P.X.W.; Zhang, G.; Wang, J. Understanding the key risks in construction projects in China. Int. J. Proj. Manag. 2007, 25, 601–614. [Google Scholar] [CrossRef]
- Tumi, H.K.; Omran, S.A.H.; Pakir, A. Causes of delay in construction industry in Libya. In Proceedings of the International Conference on Economics and Administration, Bucharest, Romania, 14–15 November 2009; pp. 265–272. [Google Scholar]
- Fugar, B.; Agyakwah-Baah, F.D. Delays in building construction projects in Ghana. Australas. J. Constr. Econ. Build. 2010, 10, 128–141. [Google Scholar] [CrossRef] [Green Version]
- Perera, A.K.S.; Rameezdeen, R.; Chileshe, N.; Hosseini, M.R. Enhancing the effectiveness of risk management practices in Sri Lankan road construction projects: A Delphi approach. Int. J. Constr. Manag. 2014, 14, 1–14. [Google Scholar] [CrossRef]
- Pawar, S.; Pagey, A. Survey and analysis of risk management in building construction work. Int. J. Res. Eng. Technol. 2017, 4, 2297–2299. [Google Scholar]
- Mohamed, O.; Abd-Karim, B.; Roslan, H.; Suhaimi, M.; Danuri, M.; Zakaria, N. Risk management: Looming the modus operandi among construction contractors in Malaysia. Int. J. Constr. Manag. 2015, 15, 82–93. [Google Scholar] [CrossRef]
- Perez, M.; Gray, D.; Skitmore, J. Perceptions of risk allocation methods and equitable risk distribution: A study of medium to large Southeast Queensland commercial construction projects. Int. J. Constr. Manag. 2017, 17, 132–141. [Google Scholar] [CrossRef] [Green Version]
- Renault, N.; Agumba, B.; Ansary, J. An exploratory factor analysis of risk management practices: A study among small and medium contractors in Gauteng. Acta Structilia 2018, 25, 1–39. [Google Scholar] [CrossRef] [Green Version]
- Al Mhdawi, M.K.; Motawa, I.; Rasheed, H.A. Assessment of Risk Management Practices in Construction Industry. In Lecture Notes in Mechanical Engineering; Springer: Berlin/Heidelberg, Germany, 2020; pp. 421–433. [Google Scholar] [CrossRef]
- Jepson, J.; Kirytopoulos, K.; Chileshe, N. Isomorphism within risk-management practices of the Australian construction industry. Int. J. Constr. Manag. 2020, 22, 1508–1524. [Google Scholar] [CrossRef]
- Alfen, H.; Kalidindi, S.; Ogunlana, S.; Wang, S. Public-Private Partnership in Infrastructure Development: Case Studies from Asia and Europe; Verlag der Bauhaus-Universität: Weimar, Germany, 2009. [Google Scholar]
- Khodeir, L.M.; Mohamed, A.H.M. Identifying the latest risk probabilities affecting construction projects in Egypt according to political and economic variables. From January 2011 to January 2013. HBRC J. 2015, 11, 129–135. [Google Scholar] [CrossRef] [Green Version]
- Baarimah, A.O.; Alaloul, W.S.; Liew, M.S.; Kartika, W.; Al-Sharafi, M.A.; Musarat, M.A.; Alawag, A.M.; Qureshi, A.H. A Bibliometric Analysis and Review of Building Information Modelling for Post-Disaster Reconstruction. Sustainability 2022, 14, 393. [Google Scholar] [CrossRef]
- Afila, D.; Smith, N.J. Risk management and value management in project appraisal. Proc. Inst. Civ. Eng. Manag. Procure. Law 2007, 160, 63–67. [Google Scholar] [CrossRef]
- Ismail, Y.A.B.; Khoiry, M.A. A Conceptual Model of Delay Factors Affecting Road Construction Projects in Libya. 2017. Available online: http://jestec.taylors.edu.my/Vol%2012%20issue%2012%20December%202017/12_12_12.pdf (accessed on 1 June 2022).
- Tang, W.; Qiang, M.; Duffield, C.F.; Young, D.M.; Lu, Y. Risk Management in the Chinese Construction Industry. J. Constr. Eng. Manag. 2007, 133, 944–956. [Google Scholar] [CrossRef]
- Amoah, P.; Ahadzie, D.K.; Dansoh, A. The factors affecting construction performance in Ghana: The perspective of small-scale building contractors. Ghana Surv. 2011, 4, 41–48. [Google Scholar]
- Zafar, T.; Wuni, I.; Shen, I.Y.; Ahmed, G.Q.; Yousaf, S. A fuzzy synthetic evaluation analysis of time overrun risk factors in highway projects of terrorism-affected countries: The case of Pakistan. Int. J. Constr. Manag. 2019, 22, 732–750. [Google Scholar] [CrossRef]
- Azhar, R.U.; Ginder, S.; Farooqui, W.C. An Assessment of Risk Management Practices in the Alabama Building Construction Industry. 2008. Available online: https://www.academia.edu/5097554/An_Assessment_of_Risk_Management_Practices_in_the_Alabama_Building_Construction_Industry (accessed on 20 May 2022).
- Marzouk, T.I.; El-Rasas, M.M. Analyzing delay causes in Egyptian construction projects. J. Adv. Res. 2014, 5, 49–55. [Google Scholar] [CrossRef] [Green Version]
- Asiedu, H.W.; Alfen, R.O. Understanding the underlying reasons behind time overruns of government building projects in Ghana. KSCE J. Civ. Eng. 2016, 20, 2103–2111. [Google Scholar] [CrossRef]
- PMBOK. A Guide to the Project Management Body of Knowledge, 3rd ed.; American National Standard: Newtown Square, PA, USA, 2004. [Google Scholar]
- Kassem, M.A.; Khoiry, M.A.; Hamzah, N. Using probability impact matrix (PIM) in analyzing risk factors affecting the success of oil and gas construction projects in Yemen. Int. J. Energy Sect. Manag. 2020, 14, 527–546. [Google Scholar] [CrossRef]
- Thomas, R. A General Inductive Approach for Analyzing Qualitative Evaluation Data. Am. J. Eval. 2006, 27, 237–246. [Google Scholar] [CrossRef]
- Del Caño, A.; De La Cruz, M.P. Integrated Methodology for Project Risk Management. J. Constr. Eng. Manag. 2002, 128, 473–485. [Google Scholar] [CrossRef]
- Goh, C.S.; Abdul-Rahman, H. The identification and management of major risks in the Malaysian construction industry. J. Constr. Dev. Ctries. 2013, 18, 19. [Google Scholar]
- Kassem, M.A.; Khoiry, M.A.; Hamzah, N. Assessment of the effect of external risk factors on the success of an oil and gas construction project. Eng. Constr. Archit. Manag. 2020, 27, 2767–2793. [Google Scholar] [CrossRef]
- Mhetre, K.; Konnur, B.A.; Landage, A.B. Risk Management in Construction Industry Article in. Int. J. Eng. Res. 2016, 1, 153–155. [Google Scholar] [CrossRef]
- Alfadil, M.O.; Kassem, M.A.; Ali, K.N.; Alaghbari, W. Construction Industry from Perspective of Force Majeure and Environmental Risk Compared to the COVID-19 Outbreak: A Systematic Literature Review. Sustainability 2022, 14, 1135. [Google Scholar] [CrossRef]
- Ghaleb, H.; Alhajlah, H.H.; Abdullah, A.A.b.; Kassem, M.A.; Al-Sharafi, M.A. A Scientometric Analysis and Systematic Literature Review for Construction Project Complexity. Buildings 2022, 12, 482. [Google Scholar] [CrossRef]
- Ali, K.N.; Alhajlah, H.H.; Kassem, M.A. Collaboration and Risk in Building Information Modelling (BIM): A Systematic Literature Review. Buildings 2022, 12, 571. [Google Scholar] [CrossRef]
Item | Frequency | Percent |
---|---|---|
Profession of Respondents | ||
Engineer | 80 | 46.00 |
Quantity surveyor | 25 | 14.40 |
Architect | 49 | 28.20 |
Others | 20 | 11.50 |
Total | 174 | 100 |
Role of Respondents | ||
Chairman/director | 7 | 4.00 |
Project manager | 39 | 22.40 |
Project consultant | 27 | 15.50 |
Site engineer/Architects | 65 | 37.40 |
Site supervisor | 17 | 9.80 |
Others | 19 | 10.90 |
Total | 174 | 100 |
Years of experience | ||
1–5 years | 36 | 20.70 |
6–10 years | 52 | 29.90 |
11–15 years | 49 | 28.20 |
16–20 years | 17 | 9.80 |
Above 20 years | 20 | 11.50 |
Total | 174 | 100 |
Questions | Overall | |
---|---|---|
Risk management is generally implemented in your projects | 2.34 | Disagree |
It is necessary to implement risk management in construction projects | 3.99 | Agree |
Risks in Yemen construction are allocated to the most appropriate party | 2.68 | Disagree |
You have knowledge of risk management in construction projects | 2.70 | Disagree |
You encounter risks in your projects (e.g., war and political instability, etc.) | 4.01 | Agree |
Risk Identification is implemented in a systematic manner throughout the project | 2.58 | Disagree |
Risk Analysis is implemented in a systematic manner throughout the project | 2.48 | Disagree |
Risk Response is implemented in a systematic manner throughout the project | 2.72 | Disagree |
Risk Identification Techniques | Mean | Ranking |
---|---|---|
Historical Data | 3.14 | 2 |
Checklists | 2.46 | 4 |
Brainstorming | 2.17 | 5 |
Intuition/judgment | 3.30 | 1 |
Interviewing | 2.10 | 6 |
Consulting expert | 2.79 | 3 |
Risk Analysis Techniques | Mean | Ranking |
---|---|---|
Qualitative analysis | 2.72 | 1 |
Quantitative analysis | 1.10 | 3 |
Semiquantitative analysis | 1.56 | 2 |
Risk Response Techniques | Mean | Ranking |
---|---|---|
Reduce the possibility of occurrence (probability) | 3.76 | 2 |
Reduce the consequences (impact) | 3.64 | 3 |
Avoid the risk | 4.47 | 1 |
Transfer risk | 3.46 | 4 |
Interviewing | 2.10 | 6 |
Consulting expert | 2.79 | 3 |
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations. |
© 2022 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Bahamid, R.A.; Doh, S.I.; Khoiry, M.A.; Kassem, M.A.; Al-Sharafi, M.A. The Current Risk Management Practices and Knowledge in the Construction Industry. Buildings 2022, 12, 1016. https://doi.org/10.3390/buildings12071016
Bahamid RA, Doh SI, Khoiry MA, Kassem MA, Al-Sharafi MA. The Current Risk Management Practices and Knowledge in the Construction Industry. Buildings. 2022; 12(7):1016. https://doi.org/10.3390/buildings12071016
Chicago/Turabian StyleBahamid, Rami A., Shu Ing Doh, Muhamad Azry Khoiry, Mukhtar A. Kassem, and Mohammed A. Al-Sharafi. 2022. "The Current Risk Management Practices and Knowledge in the Construction Industry" Buildings 12, no. 7: 1016. https://doi.org/10.3390/buildings12071016
APA StyleBahamid, R. A., Doh, S. I., Khoiry, M. A., Kassem, M. A., & Al-Sharafi, M. A. (2022). The Current Risk Management Practices and Knowledge in the Construction Industry. Buildings, 12(7), 1016. https://doi.org/10.3390/buildings12071016