Estimating the Duration of Construction Works Using Fuzzy Modeling to Assess the Impact of Risk Factors
Abstract
:1. Introduction
- Development of a novel algorithm for estimating construction duration considering additional risk lag time. The risk lag time is determined utilizing a risk matrix and fuzzy set theory. Fuzzy set theory allows for the use of linguistic terms for estimating the level of risk;
- Validation through a practical case study of construction project implementation;
- Analysis of defuzzification methods and their impact on the overall construction duration value;
- Examination of the influence of various risk matrices on the overall construction duration value.
2. Literature Review
3. Fuzzy Approach to Modeling Construction Duration Using Risk Matrix
3.1. Theoretical Aspects of the Proposed Fuzzy Approach
3.1.1. Critical Path Method (CPM)
3.1.2. Basic Concepts of the Fuzzy Sets Theory
- Centroid method. The crisp solution is obtained by taking the center point of the fuzzy area and can be written as Equation (17) and presented in Figure 6a:
- Bisector method. The crisp solution is obtained by taking the domain which has a value from the number of membership values in the fuzzy area and can be written as and presented in Figure 6b:
- Middle of Maximum (MOM) method. The crisp solution is obtained by taking the average value of the domain that has the maximum membership value and can be presented in Figure 7.
- Largest of Maximum (LOM) method. The crisp solution is obtained by taking the largest value from the domain that has the maximum membership value and can be presented in Figure 7.
- Smallest of Maximum (SOM) method. The crisp solution is obtained by taking the smallest value from the domain that has the maximum membership value and can be presented in Figure 7.
3.1.3. Fuzzy Approach to Estimate the Risk Lag Time Using the Level of Influence of the Risk Factors
3.2. Case Study
3.2.1. Input Data
3.2.2. Risk Identification
3.2.3. Risk Analysis and Assessment
3.2.4. Risk Response Approach
4. Results and Discussion
5. Conclusions
- The use of a risk matrix allows for ranking and considering the level of threat, taking into account the experience of the construction project manager or planner. This enables the reduction or increase in the magnitude of the risk lag time relative to the risk lag time determined as a product of probability and impact.
- The defuzzification method influences the output value of the risk lag time for individual tasks, and the difference between the maximum and minimum values can reach 67%. However, the defuzzification method has little significant impact on the output value of the risk lag time, reaching less than 5%. This suggests that any convenient defuzzification method can be chosen to simplify calculations.
- It has been established that the relative deviation between the risk lag time (RxI) and the mean value of the risk lag time is less than 10% for individual tasks. Therefore, to obtain more accurate calculations of the risk lag time using risk matrices, calculations should be performed using five types of defuzzification methods.
- The relative deviation between the risk lag time (RxI) and the mean value of the risk lag time for individual tasks may represent the level of uncertainty with which each task can be implemented. The value of the uncertainty level can be used in constructing the membership function for fuzzy set type 2.
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Conflicts of Interest
References
- Yaseen, Z.M.; Ali, Z.H.; Salih, S.Q.; Al-Ansari, N. Prediction of Risk Delay in Construction Projects Using a Hybrid Artificial Intelligence Model. Sustainability 2020, 12, 1514. [Google Scholar] [CrossRef]
- Sanni-Anibire, M.O.; Mohamad Zin, R.; Olatunji, S.O. Causes of delay in the global construction industry: A meta analytical review. Int. J. Constr. Manag. 2022, 22, 1395–1407. [Google Scholar] [CrossRef]
- Mahdi, I.; Soliman, E. Significant and top ranked delay factors in Arabic Gulf countries. Int. J. Constr. Manag. 2021, 21, 167–180. [Google Scholar] [CrossRef]
- Alsuliman, J.A. Causes of delay in Saudi public construction projects. Alex. Eng. J. 2019, 58, 801–808. [Google Scholar] [CrossRef]
- Plebankiewicz, E.; Wieczorek, D. Prediction of Cost Overrun Risk in Construction Projects. Sustainability 2020, 12, 9341. [Google Scholar] [CrossRef]
- Asiedu, R.O.; Ameyaw, C. A system dynamics approach to conceptualize causes of cost overrun of construction projects in developing countries. Int. J. Build. Pathol. Adapt. 2021, 39, 831–851. [Google Scholar] [CrossRef]
- Jalal, M.P.; Shoar, S. A hybrid SD-DEMATEL approach to develop a delay model for construction projects. Eng. Constr. Arch. Manag. 2017, 24, 29–651. [Google Scholar]
- Johnson, R.M.; Babu, R.I.I. Time and cost overruns in the UAE construction industry: A critical analysis. Int. J. Constr. Manag. 2020, 20, 402–411. [Google Scholar] [CrossRef]
- Asiedu, R.O.; Frempong, N.K.; Alfen, H.W. Predicting likelihood of cost overrun in educational projects. Eng. Constr. Arch. Manag. 2017, 24, 21–39. [Google Scholar] [CrossRef]
- Asiedu, R.O.; Adaku, E. Cost overruns of public sector construction projects: A developing country perspective. Int. J. Manag. Proj. Bus. 2020, 13, 66–84. [Google Scholar] [CrossRef]
- Famiyeh, S.; Amoatey, C.T.; Adaku, E.; Agbenohevi, C.S. Major causes of construction time and cost overruns: A case of selected educational sector projects in Ghana. J. Eng. Des. Technol. 2017, 15, 181–198. [Google Scholar] [CrossRef]
- Annamalaisami, C.D.; Kuppuswamy, A. Reckoning construction cost overruns in building projects through methodological consequences. Int. J. Constr. Manag. 2019, 22, 1079–1089. [Google Scholar] [CrossRef]
- Abbasi, O.; Noorzai, E.; Gharouni Jafari, K.; Golabchi, M. Exploring the causes of delays in the construction industry using a cause-and-effect diagram: Case study for Iran. J. Arch. Eng. 2020, 26, 05020008. [Google Scholar] [CrossRef]
- Prasad, K.V.; Vasugi, V.; Venkatesan, R.; Bhat, N.S. Critical causes of time overrun in Indian construction projects and mitigation measures. Int. J. Constr. Educ. Res. 2019, 15, 216–238. [Google Scholar] [CrossRef]
- Doloi, H.; Sawhney, A.; Iyer, K.C.; Rentala, S. Analysing factors affecting delays in Indian construction projects. Int. J. Proj. Manag. 2012, 30, 479–489. [Google Scholar] [CrossRef]
- Ullah, K.; Abdullah, A.H.; Nagapan, S.; Sohu, S.; Khan, M.S. Measures to mitigate causative factors of budget overrun in Malaysian building projects. Int. J. Integr. Eng. 2018, 10, 66–71. [Google Scholar] [CrossRef]
- Alhammadi, Y.; Al-Mohammad, M.S.; Rahman, R.A. Modeling the Causes and Mitigation Measures for Cost Overruns in Building Construction: The Case of Higher Education Projects. Buildings 2024, 14, 487. [Google Scholar] [CrossRef]
- Biruk, S.; Rzepecki, Ł. A Simulation Model of Construction Projects Executed in Random Conditions with the Overlapping Construction Works. Sustainability 2021, 13, 5795. [Google Scholar] [CrossRef]
- Karcińska, P.; Plebankiewicz, E.; Leśniak, A. A Concise Review of Workforce Planning Methods in Construction Works; Monografia; WSOWL: Wrocłąw, Poland, 2014. [Google Scholar]
- Project Management Institute. A Guide to the Project Management Body of Knowledge (Pmbok® Guide); Project Management Institute: Newtown Square, PA, USA, 2017; ISBN 9781628251845. [Google Scholar]
- PRINCE2 Training: Construction Industry. 2021. Available online: https://www.prince2training.co.uk/blog/prince2-for-the-construction-industry/ (accessed on 20 February 2024).
- Knowledge Train®: PRINCE2® vs. the PMBOK® Guide: A Comparison. 2021. Available online: https://www.knowledgetrain.co.uk/project-management/pmi/prince2-and-pmbok-guide-comparison (accessed on 20 February 2024).
- Murray, A.; Bennett, N.; Bentley, C. Managing Successful Projects with PRINCE2; TSO: London, UK, 2015; ISBN 0113310595. [Google Scholar]
- Jaziri, R.; El-Mahjoub, O.; Boussaffa, A. Proposition of a hybrid methodology of project management. Am. J. Eng. Res. AJER 2018, 7, 113–127. [Google Scholar]
- Faraji, A.; Rashidi, M.; Perera, S.; Samali, B. Applicability-Compatibility Analysis of PMBOK Seventh Edition from the Perspective of the Construction Industry Distinctive Peculiarities. Buildings 2022, 12, 210. [Google Scholar] [CrossRef]
- APM Group. PRINCE2 Case Study. PRINCE2 and PMI/PIMBOK®. A Combined Approach at Getronics; The APM Group Limited: Bucks, UK, 2002; Available online: https://silo.tips/download/contents-4-current-perceptions-of-relative-positioning-of-prince2-and-pmbok-appe (accessed on 20 February 2024).
- Al-Zwainy, F.M.S.; Mhammed, I.A.; Raheem, S.H. Application Project Management Methodology in Construction Sector: Review. Int. J. Sci. Eng. Res. IJSER 2016, 7, 244–253. [Google Scholar]
- Simonaitis, A.; Daukšys, M.; Mockienė, J. A Comparison of the Project Management Methodologies PRINCE2 and PMBOK in Managing Repetitive Construction Projects. Buildings 2023, 13, 1796. [Google Scholar] [CrossRef]
- Björnsdottir, S.H.; Jensson, P.; Thorsteinsson, S.E.; Dokas, I.M.; de Boer, R.J. Benchmarking ISO Risk Management Systems to Assess Efficacy and Help Identify Hidden Organizational Risk. Sustainability 2022, 14, 4937. [Google Scholar] [CrossRef]
- ISO 31000:2018; Risk Management—Principles and Guidelines. ISO: Geneva, Switzerland, 2018.
- Hajdu, M. Network Scheduling Techniques for Construction Project Management; Nonconvex Optimization and Its Applications; Springer: New York, NY, USA, 1997; ISBN 978-0-7923-4309-7. [Google Scholar]
- Kim, K. Generalized Resource-Constrained Critical Path Method to Improve Sustainability in Construction Project Scheduling. Sustainability 2020, 12, 8918. [Google Scholar] [CrossRef]
- Zhou, J.; Love, P.E.; Wang, X.; Teo, K.L.; Irani, Z. A review of methods and algorithms for optimizing construction scheduling. J. Oper. Res. Soc. 2013, 64, 1091–1105. [Google Scholar] [CrossRef]
- Antill, J.M.; Woodhead, R.W. Critical Path Methods in Construction Practice, 4th ed.; Wiley: New York, NY, USA, 1990. [Google Scholar]
- Barraza, G.; Bueno, A. Cost contingency management. J. Manag. Eng. 2007, 23, 140–146. [Google Scholar] [CrossRef]
- Chapman, C.; Ward, S. Project Risk Management; Wiley: Chichester, UK, 1997. [Google Scholar]
- Alshihri, S.; Al-Gahtani, K.; Almohsen, A. Risk Factors That Lead to Time and Cost Overruns of Building Projects in Saudi Arabia. Buildings 2022, 12, 902. [Google Scholar] [CrossRef]
- Al-Gahtani, K.; Shafaay, M.; Ahmed, O.; Alawshan, M. Risk Factors for Time and Cost Overruns of Pipeline Projects in Saudi Arabia. Adv. Civ. Eng. 2023, 2023, 11. [Google Scholar] [CrossRef]
- Lawrence, A.I.; Eziyi, O.I.; Francis, O.U.; Amechi, F.I. Causes of time overrun in fixed price contracts of tertiary education trust fund (TETFund) building projects in Enugu State, Southeast Nigeria. Int. J. Constr. Manag. 2023. [Google Scholar] [CrossRef]
- Leu, S.-S.; Liu, Y.; Wu, P.-L. Project Cost Overrun Risk Prediction Using Hidden Markov Chain Analysis. Buildings 2023, 13, 667. [Google Scholar] [CrossRef]
- Xie, W.; Deng, B.; Yin, Y.; Lv, X.; Deng, Z. Critical factors influencing cost overrun in construction projects: A fuzzy synthetic evaluation. Buildings 2022, 12, 2028. [Google Scholar] [CrossRef]
- Sahu, V.; Sharma, K.N. Study of risks in high rise building projects in India and the mitigation measures. Asian J. Civ. Eng. 2023, 24, 1957–1967. [Google Scholar] [CrossRef]
- Yousri, E.; Sayed, A.E.B.; Farag, M.A.M.; Abdelalim, A.M. Risk Identification of Building Construction Projects in Egypt. Buildings 2023, 13, 1084. [Google Scholar] [CrossRef]
- Farooq, M.U.; Thaheem, M.J.; Arshad, H. Improving the risk quantification under behavioural tendencies: A tale of construction projects. Int. J. Proj. Manag. 2018, 36, 414–428. [Google Scholar] [CrossRef]
- Doungsoma, T.; Pawan, P. Reliable Time Contingency Estimation Based on Adaptive Neuro-Fuzzy Inference System in Construction Projects. IEEE Access 2023, 11, 90430–90448. [Google Scholar] [CrossRef]
- Mahamid, I. Risk matrix for factors affecting time delay in road construction projects: Owners’ perspective. Eng. Constr. Arch. Manag. 2011, 18, 609–617. [Google Scholar] [CrossRef]
- Salem, Z.T.; Suleiman, A. Risk Factors Causing Time Delay in the Jordanian Construction Sector. Int. J. Eng. Res. Technol. 2020, 13, 307–315. [Google Scholar] [CrossRef]
- Abdelaal, A.; Daraghma, Q.; Mahamid, I. Risk Map for Delay Causes in Construction Projects in Palestine: Contractors’ Perspective. Int. J. Constr. Eng. Plan. 2023, 9, 46–56. [Google Scholar]
- Kaczorek, K.; Krzemiński, M.; Ibadov, N. The problem of choosing risk management methodology at the example of railway construction. MATEC Web Conf. 2017, 117, 73. [Google Scholar] [CrossRef]
- Ibadov, N. Determination of the risk factors impact on the construction projects implementation using fuzzy sets theory. Acta Phys. Pol. A 2016, 130, 107–111. [Google Scholar] [CrossRef]
- Ibadov, N.; Kulejewski, J. Selection of technological and organizational solutions for construction works with the use of a fuzzy relation of preferences. Int. J. Environ. Sci. Technol. 2019, 16, 4347–4354. [Google Scholar]
- Ibadov, N.; Farzaliyev, S.; Ladnykh, I. Selection of technological and organizational solutions for construction works with the use of a fuzzy relation of preferences. Arch. Civ. Eng. 2023, 69, 573–589. [Google Scholar]
- Moder, J.J.; Phillips, C.R.; Davis, E.W. Project Management with CPM, PERT, and Precedence Diagramming, 3rd ed.; Van Nostrand Reinhold: New York, NY, USA, 1983; pp. 203–204. [Google Scholar]
- Zadeh, L. Fuzzy sets. Inf. Control 1965, 8, 338–353. [Google Scholar] [CrossRef]
- Zadeh, L. The concept of a linguistic variable and its application to approximate reasoning I. Inf. Sci. 1975, 8, 199–249. [Google Scholar] [CrossRef]
- Rustum, R.; Kurichiyanil, A.M.J.; Forrest, S.; Sommariva, C.; Adeloye, A.J.; Zounemat-Kermani, M.; Scholz, M. Sustainability Ranking of Desalination Plants Using Mamdani Fuzzy Logic Inference Systems. Sustainability 2020, 12, 631. [Google Scholar] [CrossRef]
- The Mathworks Inc. Defuzzification Methods. Available online: https://www.mathworks.com/help/fuzzy/types-of-fuzzy-inference-systems.html (accessed on 20 February 2024).
The Level of Impact Low | The Level of Impact Medium | The Level of Impact High | |
---|---|---|---|
The level of probability Unlikely | The level of threat Low | The level of threat Low | The level of threat Medium |
The level of probability Unlikely | The level of threat Low | The level of threat Medium | The level of threat High |
The level of probability Unlikely | The level of threat Medium | The level of threat High | The level of threat Very High |
Activity | Description of Activity | Normal Duration, Days | Previous Task |
---|---|---|---|
A | Site Investigation and Preparation | 24 | - |
B | Foundation Works on Section 1 | 45 | A |
C | Foundation Works on Section 2 | 45 | A |
D | Construction of Monolithic Building Frame on Section 1 | 39 | B |
E | Construction of Monolithic Building Frame on Section 2 | 39 | C |
F | Masonry Works | 30 | D, E |
G | Finishing Works | 72 | F |
I | Landscaping | 20 | G |
Description of Activity | Risk Event | Risk Factor |
---|---|---|
(A) Site Investigation and Preparation | Bad weather | The amount of rainfall |
(B) Foundation Works on Section 1 | Unreliable soil information | Error from survey team Unexpected underground objects |
(C) Foundation Works on Section 2 | Unreliable soil information | Error from survey team Unexpected underground objects |
(D) Construction of Monolithic Building Frame on Section 1 | Tower crane failure | Lack of maintenance Carry overload |
(E) Construction of Monolithic Building Frame on Section 2 | Misunderstanding of technical documentation by workers | Low language proficiency Lack of technical education |
(F) Masonry Works | Worker absenteeism | Worker illness Rule and regulation |
Activity | Risk Event | Probability, % |
---|---|---|
(A) Site Investigation and Preparation | Bad weather | 38 |
(B) Foundation Works on Section 1 | Unreliable soil information | 46 |
(C) Foundation Works on Section 2 | Unreliable soil information | 29 |
(D) Construction of Monolithic Building Frame on Section 1 | Tower crane failure | 84 |
(E) Construction of Monolithic Building Frame on Section 2 | Misunderstanding of technical documentation by workers | 70.5 |
(F) Masonry Works | Worker absenteeism | 50 |
Activity | Normal Duration, Days | Impact of Risk Event (Lag Time), Days | Impact of Risk Event (IoRE%), % |
---|---|---|---|
(A) Site Investigation and Preparation | 24 | 12 | 50 |
(B) Foundation Works on Section 1 | 45 | 13 | 29 |
(C) Foundation Works on Section 2 | 45 | 6 | 13 |
(D) Construction of Monolithic Building Frame on Section 1 | 39 | 8 | 20 |
(E) Construction of Monolithic Building Frame on Section 2 | 39 | 14 | 36 |
(F) Masonry Works | 30 | 15 | 50 |
The Level of Impact Low B1 | The Level of Impact Medium B2 | The Level of Impact High B3 | |
---|---|---|---|
The level of probability Unlikely A1 | The level of threat is Low D1 | The level of threat is Medium D2 | The level of threat is High D3 |
The level of probability Unlikely A2 | The level of threat is Medium D2 | The level of threat is High D3 | The level of threat is High D4 |
The level of probability Unlikely A3 | The level of threat is High D3 | The level of threat is High D4 | The level of threat is High D4 |
The Level of Impact Low B1 | The Level of Impact Medium B2 | The Level of Impact High B3 | |
---|---|---|---|
The level of probability Unlikely A1 | The level of threat is Low D1 | The level of threat is Low D1 | The level of threat is Medium D2 |
The level of probability Unlikely A2 | The level of threat is Low D1 | The level of threat is Medium D2 | The level of threat is High D3 |
The level of probability Unlikely A3 | The level of threat is Medium D2 | The level of threat is High D3 | The level of threat is High D4 |
Activity | RLTc%, % | ||||
---|---|---|---|---|---|
The Defuzzification Method | |||||
Centroid | Bisector | Middle of Maximum (MOM) | Smallest of Maximum (SOM) | Largest of Maximum (LOM) | |
(A) Site Investigation and Preparation | 57.4 | 61.0 | 66.5 | 59.0 | 74.0 |
(B) Foundation Works on Section 1 | 52.0 | 54.0 | 66.5 | 53.0 | 80.0 |
(C) Foundation Works on Section 2 | 41.1 | 38.0 | 33.5 | 20.0 | 47.0 |
(D) Construction of Monolithic Building Frame on Section 1 | 57.2 | 60.0 | 67.0 | 54.0 | 80.0 |
(E) Construction of Monolithic Building Frame on Section 2 | 58.3 | 61.0 | 67.0 | 54.0 | 80.0 |
(F) Masonry Works | 66.7 | 67.0 | 67.0 | 67.0 | 67.0 |
Activity | RLTc%, % | ||||
---|---|---|---|---|---|
The Defuzzification Method | |||||
Centroid | Bisector | Middle of Maximum (MOM) | Smallest of Maximum (SOM) | Largest of Maximum (LOM) | |
(A) Site Investigation and Preparation | 32.3 | 33.0 | 33.5 | 59.0 | 41.0 |
(B) Foundation Works on Section 1 | 30.4 | 31.0 | 33.5 | 53.0 | 47.0 |
(C) Foundation Works on Section 2 | 25.1 | 20.0 | 6.5 | 20.0 | 13.0 |
(D) Construction of Monolithic Building Frame on Section 1 | 45.4 | 43.0 | 33.0 | 54.0 | 46.0 |
(E) Construction of Monolithic Building Frame on Section 2 | 46.1 | 44.0 | 33.0 | 54.0 | 46.0 |
(F) Masonry Works | 33.3 | 33.0 | 33.0 | 67.0 | 33.0 |
Activity | RLTcd, Days | ||||
---|---|---|---|---|---|
The Defuzzification Method | |||||
Centroid | Bisector | Middle of Maximum (MOM) | Smallest of Maximum (SOM) | Largest of Maximum (LOM) | |
(A) Site Investigation and Preparation | 7 | 7 | 8 | 7 | 9 |
(B) Foundation Works on Section 1 | 7 | 7 | 9 | 7 | 10 |
(C) Foundation Works on Section 2 | 2 | 2 | 2 | 1 | 3 |
(D) Construction of Monolithic Building Frame on Section 1 | 5 | 5 | 5 | 4 | 6 |
(E) Construction of Monolithic Building Frame on Section 2 | 8 | 9 | 9 | 8 | 11 |
(F) Masonry Works | 10 | 10 | 10 | 10 | 10 |
Activity | RLTcd, Days | ||||
---|---|---|---|---|---|
The Defuzzification Method | |||||
Centroid | Bisector | Middle of Maximum (MOM) | Smallest of Maximum (SOM) | Largest of Maximum (LOM) | |
(A) Site Investigation and Preparation | 4 | 4 | 4 | 7 | 5 |
(B) Foundation Works on Section 1 | 4 | 4 | 4 | 7 | 6 |
(C) Foundation Works on Section 2 | 2 | 1 | 0 | 1 | 1 |
(D) Construction of Monolithic Building Frame on Section 1 | 4 | 3 | 3 | 4 | 4 |
(E) Construction of Monolithic Building Frame on Section 2 | 6 | 6 | 5 | 8 | 6 |
(F) Masonry Works | 5 | 5 | 5 | 10 | 5 |
Activity | Normal Duration, Days | The Total Duration for Each Activity and Project, Days | ||||
---|---|---|---|---|---|---|
The Defuzzification Method | ||||||
Centroid | Bisector | Middle of Maximum (MOM) | Smallest of Maximum (SOM) | Largest of Maximum (LOM) | ||
(A) Site Investigation and Preparation | 24 | 31 | 31 | 32 | 31 | 33 |
(B) Foundation Works on Section 1 | 45 | 52 | 52 | 54 | 52 | 55 |
(C) Foundation Works on Section 2 | 45 | 47 | 47 | 47 | 46 | 48 |
(D) Construction of Monolithic Building Frame on Section 1 | 39 | 44 | 44 | 44 | 43 | 45 |
(E) Construction of Monolithic Building Frame on Section 2 | 39 | 47 | 48 | 48 | 47 | 50 |
(F) Masonry Works | 30 | 40 | 40 | 40 | 40 | 40 |
(G) Finishing Works | 72 | 72 | 72 | 72 | 72 | 72 |
(I) Landscaping | 20 | 20 | 20 | 20 | 20 | 20 |
Total project duration | 230 | 259 | 259 | 262 | 258 | 265 |
Activity | Normal Duration, Days | The Total Duration for Each Activity and Project, Days | ||||
---|---|---|---|---|---|---|
The Defuzzification Method | ||||||
Centroid | Bisector | Middle of Maximum | Smallest of Maximum | Largest of Maximum | ||
(A) Site Investigation and Preparation | 24 | 28 | 28 | 28 | 31 | 29 |
(B) Foundation Works on Section 1 | 45 | 49 | 49 | 49 | 52 | 51 |
(C) Foundation Works on Section 2 | 45 | 47 | 46 | 45 | 46 | 46 |
(D) Construction of Monolithic Building Frame on Section 1 | 39 | 43 | 42 | 42 | 43 | 43 |
(E) Construction of Monolithic Building Frame on Section 2 | 39 | 45 | 45 | 44 | 47 | 45 |
(F) Masonry Works | 30 | 35 | 35 | 35 | 40 | 35 |
(G) Finishing Works | 72 | 72 | 72 | 72 | 72 | 72 |
(I) Landscaping | 20 | 20 | 20 | 20 | 20 | 20 |
Total project duration | 230 | 247 | 246 | 246 | 258 | 250 |
Activity | Normal Duration, Days | The Average of the Activity Duration with Risk Lag Time | The Activity Duration with RLTPxI, Days (3) | The Activity Duration with LT, Days | The Differences between (1) and (3), % | The Differences between (2) and (3), % | |
---|---|---|---|---|---|---|---|
For Risk Matrix 1, Days (1) | For Risk Matrix 2, Days (2) | ||||||
(A) Site Investigation and Preparation | 24 | 31.6 | 28.8 | 30 | 36 | 5.3 | 4.0 |
(B) Foundation Works on Section 1 | 45 | 53.0 | 50 | 49 | 58 | 8.2 | 2.1 |
(C) Foundation Works on Section 2 | 45 | 47.0 | 46 | 46 | 51 | 2.2 | 0.0 |
(D) Construction of Monolithic Building Frame on Section 1 | 39 | 44.0 | 42.6 | 41 | 47 | 7.3 | 3.9 |
(E) Construction of Monolithic Building Frame on Section 2 | 39 | 48.0 | 45.2 | 44 | 53 | 9.1 | 2.7 |
(F) Masonry Works | 30 | 40.0 | 36 | 38 | 45 | 5.3 | 5.3 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2024 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Ladnykh, I.A.; Ibadov, N. Estimating the Duration of Construction Works Using Fuzzy Modeling to Assess the Impact of Risk Factors. Appl. Sci. 2024, 14, 3847. https://doi.org/10.3390/app14093847
Ladnykh IA, Ibadov N. Estimating the Duration of Construction Works Using Fuzzy Modeling to Assess the Impact of Risk Factors. Applied Sciences. 2024; 14(9):3847. https://doi.org/10.3390/app14093847
Chicago/Turabian StyleLadnykh, Irene A., and Nabi Ibadov. 2024. "Estimating the Duration of Construction Works Using Fuzzy Modeling to Assess the Impact of Risk Factors" Applied Sciences 14, no. 9: 3847. https://doi.org/10.3390/app14093847
APA StyleLadnykh, I. A., & Ibadov, N. (2024). Estimating the Duration of Construction Works Using Fuzzy Modeling to Assess the Impact of Risk Factors. Applied Sciences, 14(9), 3847. https://doi.org/10.3390/app14093847