Next Article in Journal
A Real-Time Measurement Method of Air Refractive Index Based on Special Material Etalon
Previous Article in Journal
Pursuing High Quality Phase-Only Liquid Crystal on Silicon (LCoS) Devices
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Assessing and Prioritising Delay Factors of Prefabricated Concrete Building Projects in China

1
Department of Civil Engineering, North China University of Technology, Beijing 100043, China
2
School of Architecture and Built Environment, Deakin University, Geelong 3220, Australia
*
Author to whom correspondence should be addressed.
Appl. Sci. 2018, 8(11), 2324; https://doi.org/10.3390/app8112324
Submission received: 17 October 2018 / Revised: 6 November 2018 / Accepted: 14 November 2018 / Published: 21 November 2018

Abstract

:
Prefabricated construction has been widely accepted as an alternative to conventional cast-in-situ construction, given its improved performance. However, prefabricated concrete building projects frequently encounter significant delays. It is, therefore, crucial to identify key factors affecting schedule and explore strategies to minimise the schedule delays for prefabricated concrete building projects. This paper adopts the decision-making trial and evaluation laboratory (DEMATEL) model and analytic network process (ANP) method to quantify the cause-and-effect relationships and prioritise the key delay factors in terms of their importance in the Chinese construction industry. The DEMATEL model evaluates the extent to which each factor impacts other factors. The quantified extents are then converted into a prioritisation matrix through ANP. The delay factors of prefabricated construction projects are selected and categorised based on a literature review and an expert interview. Questionnaires are then implemented to collect the data. The results reveal that the issue of inefficient structural connections for prefabricated components is found to be the most significant factor and most easily affected by other delay factors. This research also suggests prioritising major delay factors, such as ‘lack of communication among participants’ and ‘low productivity’, in the Chinese construction industry during scheduling control. Overall, this research contributes an assessment framework for decision making in the scheduling management of prefabricated construction.

1. Introduction

Prefabricated construction refers to the practice of designing and fabricating building elements in manufacturing factories, transporting the elements to construction sites, and assembling the elements to a greater degree of finish for rapid site assembly compared to traditional piecemeal on-site construction [1,2]. Thus, interchangeable terminologies associated with prefabricated construction in the existing literature include off-site construction [3], off-site prefabrication [4], off-site manufacturing construction [5], and off-site production [6]. Prefabricated concrete construction is considered a widely accepted alternative to conventional cast-in-situ concrete construction since it offers numerous benefits for investors and contractors, such as higher speed of construction, enhanced quality outputs, higher tolerances, lower costs, reduced labour re-works on-site, and safer construction environments [7,8,9]. From the perspective of environmental sustainability, prefabricated concrete construction benefits in waste reduction [10], facilitates the reuse of some components [11] and reduces water consumption [12]. The above-mentioned merits have significantly contributed to improving construction industries in developed and developing countries [13]. In particular, precast technologies have been greatly developed to meet the requirements of sustainability and housing demand in China [14]. China has also embarked on several initiatives to promote prefabrication [15]. However, in comparison to conventional on-site construction, there are also notable disadvantages that should be considered, such as structural changeability, transportation restrictions, and span limits [16]. In particular, prefabricated concrete construction requires increased and more detailed coordination at all stages of a project (because of more construction phases, more complicated construction techniques, and more stakeholders), which increases the difficulty in progress monitoring and planning for construction management tasks.
Unlike the traditional construction methods, researchers and engineers are advised to pay particular attention to schedule risks of prefabrication construction projects before the construction stage [17]. For example, Li et al. [18] utilised a fuzzy analytical hierarchy process approach for ranking project risks associated with modular construction. The results revealed that the control schedule in the design stage is an important factor with respect to project duration owing to a relatively high weighting value. Also, few studies have investigated stakeholder-related risks and their cause-and-effect relationships prior to the construction stage. Therefore, Li et al. [17] employed a social network analysis to recognise and investigate the underlying network of stakeholder-associated risk factors in prefabrication housing construction projects. They emphasised the information-related risks and indicated that the design information gap between designers and manufacturers may result in frequent delay in projects [19]. Moreover, the efficient manufacturing of building elements is vital to delivery deadlines. Taghaddos et al. [20] adopted a simulation-based auction protocol framework to effectively schedule modular construction projects with limited data available. To monitor and visualise the work progress of off-site activities, Building Information Modelling is considered an effective and practical tool [21].
Overall, delays frequently occur on prefabricated concrete building projects, despite enormous efforts toward project schedule estimation and control. Researchers have also realised that construction delay is a primary barrier to the adoption of prefabricated construction in many nations [22]. It is, therefore, worthwhile to explore some strategies for avoiding schedule delays in prefabricated building projects and minimising schedule delay risks in the Chinese construction industry. In addition, previous research confronts several challenges. First, there is a lack of implementing mathematical models in the comprehensive investigation of relevant delay factors in prefabricated building projects, especially in the Chinese construction industry. Second, there is an urgent need to rank the delay factors and quantify relationships among the factors for prefabricated building projects.
Recently, several studies have applied multi-criteria decision making techniques, such as Technique for Order Preference by Similarity, Analytic Hierarchy Process (AHP) and Data Envelopment Analysis, for project risk assessment [23,24,25,26]. Analytic network process (ANP) is a generalisation of AHP, and is capable of making more accurate predictions with better priority calculations in cases of networks with dependent criteria [27]. Clearly, ANP can better provide benefits in calculating criteria priorities and their relations. Meanwhile, decision-making trial and evaluation laboratory (DEMATEL) is a useful method for analysing and quantifying cause-effect relationships. Thus, integrating DEMATEL with ANP can effectively identify the critical attributes of strategy implementation and evaluate weights of the business environment criteria [28]. Consequently, many fields are showing increasing interest in utilising the DEMATEL-ANP method for multi-criteria decision-making. For example, Tseng and Lin [29] adopted a DEMATEL-ANP method to find an appropriate solution regarding municipal solid waste management in metropolitan Manila. In 2011, Tseng [30] developed the DEMATEL-ANP method to evaluate knowledge management capability of a firm, while the same methodology was also used to select health-care organisations [31]. Moreover, Yeh and Huang [32] examined the key factors in determining location selections for wind farms based on the combination method. More recently, the method was also applied in the renewable energy resources selection in Turkey [28]. However, a synthesised risk assessment based on the combination method has not yet been established in construction projects of prefabricated concrete buildings. Thus, this paper adopts the DEMATEL-ANP method to quantify cause-and-effect relationships of delay factors and prioritise them in terms of their importance. The assessment measure can be beneficial for decision makers to minimise schedule delay risks in prefabricated concrete building projects.

2. Schedule Management in Prefabricated Building Projects

2.1. Identification of Project Processes and Phases

To manage the schedule performance of a prefabricated concrete building project, it is essential to investigate its entire project process and highlight the differences with conventional on-site construction. Although prefabricated construction can be categorised into modular, panelised, prefabricated, and processed materials construction in terms of the extent of off-site production [33], their construction processes can be summarised in a flowchart, as presented in Figure 1.
According to the definition of prefabricated construction presented in Section 1 above, a typical project can be divided into four phases: design, off-site manufacture, logistics, and on-site assembly. During the design phase, the schematic design often produces rough drawings of a site plan, floor plans, and elevations. The results are collected and taken one step further to specify components and produce drawings. During the off-site manufacturing phase, steel moulds are cleaned to remove residual contamination and concrete lumps. Steel cages and embedded parts are then placed into moulds after the module assembly. After mixing, the concrete is immediately placed in the moulds and cured. After quality inspection, components are delivered to the storage facility or transported to construction sites. Before the actual erection of the components, several procedures should be carried out, such as the site accessibility check, crane capacity check, and sample measurement. The components are then hoisted to their designated locations and adjusted into their positions. Generally, non-shrink mortar is used to seal any gaps. The joint rebars are then installed and forms are set up to carry out the concrete casting. The temporary bracing is removed after the concrete has cured. Overall, the prefabricated construction process differs greatly from conventional on-site construction.

2.2. Identification of Construction Delay Factors

To explore strategies for minimising schedule delay risks, it is important to identify the main delay factors in prefabricated building projects, prioritise key factors, and quantify their relationships. Therefore, a simple searching procedure is implemented by searching delay-factor-related and schedule-risk-related papers within the high-impact construction journals suggested by Wing [34]. The literature limited to the last ten years (2009–2018) is then summarised in Table 1 and used to identify various delay factors.
Once the delay factors are identified, elements irrelevant to prefabricated concrete building projects and rarely-occurring causes are excluded in this research through an expert interview. Table 2 displays the key factors affecting the schedule of prefabricated concrete buildings from the aspects of construction techniques, workforce, resources, machinery, clients, contractors, and external conditions.
(1)
Construction Techniques: Although off-site construction significantly reduces the on-site construction workload, it is difficult to cope with various prefabricated components. The components are also relatively large and heavy, which requires sufficient site space, and the appropriate schedule control for hoisting and installation. In addition, high-precision installation techniques are crucial for prefabricated construction, especially complicated connection processes [16]. Thus, technique-related risk factors, including inappropriate site management and low-level installation technologies, inevitably affect the project progress of prefabricated buildings.
(2)
Workforce: There is less workforce requirement in prefabricated construction, compared with traditional on-site construction. However, the current prefabricated construction process is not technologically advanced and relies on intensive labour, and the labour requires machine-oriented skills both on site and in the manufacturing process. Inadequate worker experience and poor performance have significant impacts on project progress.
(3)
Resources: Material shortage is a potential source of construction delay. The major cause of material shortage is that demand exceeds supply. Offsite prefabricated systems vary depending on the sizes of prefabricated components, which affect the need for on-site construction. Another cause of material shortage could be damage to stored components.
(4)
Machinery: Lack or unavailability of equipment is a significant factor that contributes to delays. In the construction stage, some contractors may experience the lack of machinery to produce work because of high cost and equipment failure.
(5)
Contractors: Time estimates aim to manage and structure projects. Ineffective planning and scheduling by contractors is another key driver in delaying projects. Poor site management and supervision also contribute to project delays. Large prefabricated sections may require heavy-duty cranes as well as precision measurement and handling to place in position. Clearly, rehandling components greatly impacts the scheduling performance. Occasionally, components are returned to the manufacturers due to design errors and damaged components.
(6)
Clients: Construction delay may occur if clients make changes to the design during the construction period or present additional requirements. In such cases, contractors cannot carry out their work until the updated drawings are issued by architects.
(7)
External Conditions: Weather is a factor that can influence delays throughout the entire project since weather conditions interfere with planned activities such as on-site concreting tasks. Weak regulation and unstable policies are also seen as causes of delay. For example, customs delays at border crossings may occur when transporting components internationally.

3. DEMATEL–ANP Method

In order to quantify their cause-and-effect relationships and prioritise the key delay factors in terms of their importance, the research presented in this paper applies the combination method to the prefabricated construction process.
Step 1: An average direct-relation matrix is produced. Experts are interviewed to provide pairwise comparisons in terms of the direct influence between the criteria with an influence scale of 0 (no influence), 1 (low influence), 2 (medium influence), 3 (high influence), and 4 (very high influence). It is assumed that there are K respondent experts and N factors. A direct-relation matrix of N × N can be produced by each expert, as expressed in Equation (1). A i j represents the influential level of Factor i to Factor j, but its value will be equal to zero for the self-influence of factors when i = j.
A = ( a i j ) n × n = [ a 11 = 0 a 12 a 1 n a 21 a 22 = 0 a 2 n a n 1 a n 2 a n n = 0 ]   ( i   a n d   j 1 ,   2 ,   . n )  
Step 2: The average matrix is normalised. Equation (2) is used to convert the direct-relation matrix to the standardised impact matrix D.
D = z A ,   where   z = min { 1 / m a x i j = 1 n a i j , 1 / m a x j i = 1 n a i j   }  
Step 3: The total influence matrix T is determined, where T = ( t i j ) n × n ,   w h e n   i   a n d   j 1 ,   2 ,   . n . The element t i j denotes the direct and indirect effects of Factor i on Factor j.
  T = lim K ( D + D 2 + D 3 + + D h ) = lim K D ( I D h ) ( I D ) 1 = D ( I D ) 1 , w h e n   lim K D h = [ 0 ] n × n  
where I is defined as the identity matrix.
Step 4: The levels of influence and effects are obtained based on the row sum, r i , and column sum, c j , of the matrix T .
r i = j = 1 n t i j   a n d   c j = i = 1 n t i j  
Here, r i represents the sum of the ith row in the total influence matrix T , and displays the sum the direct and indirect influences that Factor i gives to all other factors. Similarly, c j represents the sum of the jth column in the total influence matrix T , and displays the sum of direct and indirect influences that Factor j receives from all other factors. Furthermore, let i = j and i , j { 1 ,   2 , ,   n } . r i + c i provides an index of the strengths of influences given and received. That is, r i + c i shows the degree of total influences Factor i has in this system. The difference r i c i shows the net effect that Factor i contributes to the problem. Therefore, if r i c i is positive, then Factor i has a net influence on the other factors, and if r i c i is negative, then Factor i is, on the whole, being influenced by the other factors [75,76].
Step 5: The total influence matrix T is divided into T D based on the dimensions and T C based on the factors.
  D 1 C 11 C 1 m 1 D 2 C 21 C 2 m 2 D n C n 1 C n m n T c = D 1 C 1 m 1 C 11 C 12 D 2 C 2 m 2 C 21 C 22 D n C n m n C n 1 C n 2 [ T C 11    T C 12       T C 1 n T C 21    T C 22       T C 2 n          T C n 1    T C n 2       T C n n ]
  T D = [ t D 11 t D 12 t D 1 n t D 21 t D 22 t D 2 n t D n 1 t D n 2 t D n n ]  
Step 6: The total influence matrix T c is normalised by each dimension represented as T C α .
  T C α = [ T C α 11 T C α 12 T C α 1 n T C α 21 T C α 22 T C α 2 n T C α n 1 T C α n 2 T C α n n ]  
Step 7: The unweighted super-matrix, W , of the delay factors affecting the schedule performance of prefabricated construction is obtained.
  W = ( T C α )
Step 8: The weighted normalised super-matrix, W α , is calculated.
T D α = [ t D 11 / d 1 t D 12 / d 1 t D 1 n / d 1 t D 21 / d 2 t D 22 / d 2 t D 2 n / d 2 t D n 1 / d n t D n 2 / d n t D n n / d n ] = [ t D α 11 t D α 12 t D α 1 n t D α 21 t D α 22 t D α 2 n t D α n 1 t D α n 2 t D α n n ]
in which d i = j = 1 n t D i j ,  
  W α = T D α W  
Step 9: The overall priorities are calculated using the limiting process method. The weighted super-matrix can be raised to limiting values until the super-matrix has converged and becomes a long-term, stable super-matrix acquiring global priority vectors with a sufficiently large power, ρ , namely
  lim ρ ( W α ) ρ  

4. Data Collection and Pro-Process

The delay factors of prefabricated construction have been identified in Section 2.2. Regarding the questionnaires, Table 3 shows the demographic information of participants. The DEMATEL does not require a large number of respondents [77], and in this research there are thirty respondents from China’s prefabricated construction industry, namely K = 30, that consist of six academic experts in construction management, five clients, five contractors, eight manufacturing and logistics experts, four experts from construction firms, and two government officers. Various insights with regard to delay factors were considered in this research. The mix of different industrial backgrounds was well proportioned in the sample. Government officers were considered, since local governments also paid much attention to prefabricated construction. Academic experts’ opinions were also taken into account in this research. Moreover, the participants have at least 5 years’ working experience and 20% of the participants have the experience of more than 20 years in prefabricated construction.
First, introductory conversations and email contacts were made with each respondent to explain and make the objectives of the research clear. Second, the experts could discuss with each other and express their opinions before the assessment. Third, each expert made an evaluation for the relative influence of the criteria using pairwise comparisons. As mentioned previously, the responses range from 0 to 4, namely, 0 (no influence), 1 (low influence), 2 (medium influence), 3 (high influence), and 4 (very high influence). Therefore, the average direct-relation matrix can be listed as presented in Table 4.
It can be observed that the delay factors under Dimension 7, including F71, F72, and F32, do not result from other factors from the viewpoints of the experts. For example, weather conditions and power outages are not affected by any procedures of prefabricated construction, but they may result in the shortage of material supply and equipment unavailability. Similarly, few factors possibly produce any effects on Factor 21, ‘inadequate worker experience’.
In addition, the experts consider that the assembly procedures may become time-consuming due to various reasons, such as improper construction planning, irrational schedule design, unfeasible site layout, inadequate worker experience, and insufficient proficiency.

5. Results and Analysis

5.1. DEMATEL Analysis

To determine the influence by degree of the relationships among delay factors, the DEMATEL–ANP procedures are implemented in this research. In terms of Equation (4), the sum of effects of Factor i on all other factors ( r i ) and the sum of effects implemented on Factor i from all other factors ( c i ) are listed in Table 5. Similarly, dimension-related indicators are also listed in Table 5.
As discussed in Section 3, r i + c i indicates the degree of importance that Factor i has in a problem, whereas the difference of r i c i specifies the net effect that Factor i contributes to a problem. An influential network-relationship map for the seven dimensions is depicted in Figure 2 according to values of r + c and r c in Table 5.
The seven dimensions influence mutually. Arrows are pointed to dimensions with low y-axis values from dimensions with high y-axis values. Thus, ‘construction techniques’ (D1) affects ‘workforce’ (D2), ‘external conditions’ (D7), ‘contractors’ (D6), ‘machinery’ (D4), ‘clients’ (D5) and ‘resources’ (D3), namely, D 1 { D 2 ,   D 7 ,   D 6 ,   D 4 ,   D 5 ,   D 3 } . Similarly, D 2 { D 7 ,   D 6 ,   D 4 ,   D 5 ,   D 3 } , D 7 { D 6 ,   D 4 ,   D 5 ,   D 3 } , D 6 { D 4 ,   D 5 ,   D 3 } , D 4 { D 5 ,   D 3 } and D 5 { D 3 } . This finding suggests that among the dimensions that affect the project progress in prefabricated building projects, ‘construction techniques’ (D1) exerted the largest influence on the other six dimensions and ‘resources’ (D3) received the largest influence from the other six dimensions. D1, D2, D6 and D7 are considered cause dimensions, but it is not easy to avoid D1 and D7 at this stage. Strategies can be mainly focused on ‘workforce’ (D2) and ‘contractors’ (D6) to eliminate their impacts on D3, D4 and D5 for improving the schedule performance.
In terms of the dispatched-influence value in the seventh column of Table 5, the delay factors can be ranked in the following order: F21, F65, F61, F64, F23, F63, F13, F11, F62, F12, F41, F32, F22, F66, F72, F51, F73, F69, F42, F52, F71, F67, F68, and F31. Factor 21, ‘inadequate worker experience’, has the most significant impact on the other factors. The results also reveal that ‘information gaps among companies’ (F65), ‘improper construction planning and schedule design’ (F61), ‘lack of communication among participants’ (F64), and ‘insufficient proficiency for workers’ (F23) are more likely to affect the other factors. For example, on-site assembly as a labour-intensive procedure must currently be completed by construction workers. In China, some construction workers may lack the systematic and professional training for assembly techniques in prefabricated projects because of the cost of training courses. Consequently, construction workers lack the insight into potential issues due to little experience in tackling the existing difficulties. Such insufficient proficiency inevitably leads to low productivity and time-consuming procedures in structural connections for prefabricated components. However, Factor 67, ‘inefficient structural connections’, with an r-value of 0.1752 has a low probability for influencing other factors.
In terms of the received-influence value in the eighth column of Table 5, the delay factors can be ranked in the following order: F67, F42, F22, F31, F66, F69, F63, F62, F32, F61, F64, F51, F13, F12, F23, F68, F11, F41, F65, F52, F21, F72, F73, and F71. Factor 67, ‘inefficient structural connections’, is the most easily affected by the most delay factors, especially ‘low-precision installation techniques’ (F11), ‘inadequate worker experience’ (F21), and most contractor-related factors. Apart from F67, ‘vehicle and equipment unavailability’ (F42), ‘low productivity’ (F22), ‘shortage and delay in material supply’ (F31), and ‘rehandling components’ (F66) are also very easily affected by the other investigated factors. A causal diagram is plotted as presented in Figure 3 in terms of the datasets of r + c and r c , which are provided in Table 5.
According to the x-axis values, the delay factors can be ranked in the following order: F67, F22, F66, F42, F61, F64, F31, F21, F63, F65, F62, F13, F69, F23, F32, F12, F11, F51, F41, F72, F68, F73, F52, and F71. ‘Inefficient structural connections’ (F67) is identified as the most import factor as it demonstrates the highest level of interrelationship with other factors. Apart from F67, the figure indicates other core issues for solving the delay problem of prefabricated construction projects, such as ‘low productivity’ (F22), ‘rehandling components’ (F66), ‘vehicle and equipment unavailability’ (F42), ‘improper construction planning and schedule design’ (F61), and ‘lack of communication among participants’ (F64). As presented in Figure 3, the investigated delay factors are divided into two cause-and-effect clusters. The effect cluster comprises F51, F62, F32, F69, F66, F22, F42, F31, and F67 owing to negative values of r c . Other factors, including F21, F65, F64, F61, F23, F13, F11, F41, F72, F12, F73, F71, F52, F63, and F68, are included in the cause cluster owing to positive value of r c . The cause-and-effect clusters indicate that eliminating the effects from effect factors can effectively improve the project schedule performance. The solution could be to determine their corresponding cause factors in order to determine mitigation measures. In particular, Factor 21, ‘inadequate worker experience’, is considered the highest causal factor while Factor 67, ‘inefficient structural connections’, is the highest effect factor in terms of their y-axis values. Thus, F21 has the most significant impact on the other factors. Avoiding F21 is able to greatly decrease the likelihoods of cause factors occurring for improving the schedule performance.

5.2. ANP Analysis

The ANP method is applied for determining and prioritising the key risk factors for prefabricated construction based on the total influence matrix produced by Equation (3). Table 6 lists the influential weights of 7 dimensions and 24 delay factors that affect the schedule performance in the Chinese construction industry.
Columns 2 and 3 of Table 6 indicate that the contractor-related category should be considered as the most important risk issue in scheduling management since its weight value accounts for 36% and ranks first among the dimensions. Figure 3 also illustrates that the factors under this dimension have the relative importance degrees, in terms of the values of r + c . The results reveal that project managers also need to pay particular attention to the workforce-related risk indicators.
To prioritise the risk factors and identify the importance of each factor, a rank of all factors is created according to their final global weights and listed in the rightmost column. The factors under ‘external conditions’ rank 22nd, 23rd, and 24th (the least influential factors). The DEMATEL–ANP analysis indicates that ‘policy uncertainty’ (F71), ‘severe weather’ (F72), and ‘energy and water supply failure’ (F73) are the least influential elements for two reasons: (1) these issues rarely occur in comparison with other factors in prefabricated construction; and (2) new regulations and rules may experience a period before they come into force. Off-site production is rarely affected by poor weather conditions and on-site construction projects may still be progressing under the moderate weather conditions in China.
For the major delay factors, this research strongly suggests giving the factors high priority and including them in the scheduling control. Factor 67, ‘inefficient structural connections’, is considered the most significant indicator due to having the highest global weight. Similarly, Figure 3 also indicates the major driving force for solving the construction delay issue is the time-saving in the assembly procedure. Advanced construction techniques could be introduced and visualisation platforms can be applied to predict potential construction issues. Moreover, ‘rehandling components’ (F66) is shown to be more likely than ‘lack of communication among participants’ (F64) to result in poor scheduling performance within the contractor-related group. The issue that prefabricated components cannot be managed and placed in position on time results in a time-consuming procedure prior to the on-site assembly. Furthermore, in the workforce category, Factor 22, ‘low productivity’, has a higher weight than both the ‘inadequate worker experience’ (F21) and ‘insufficient proficiency’ (F23) factors, since solving the productivity issue in off-site production and on-site construction have a greater direct impact on the scheduling performance. For example, the productivity can be improved by mechanising prefabrication and construction. In addition, for the secondary delay factors, the research suggests including the four delay factors of the global weights between 0.1 and 0.01 in the scheduling control, such as ‘vehicle and equipment unavailability’ (F42) and ‘re-manufacturing owing to component damage’ (F69). These factors are indispensable to solving the poor scheduling issue. The result also indicates that the scheduling control could consider the delay factors with global weights between 0.01 and 0.001. The remaining factors do not have the significant importance and are not very necessary to be prioritised in the scheduling control owing to global weights of less than 0.001.

6. Conclusions

Overall, prefabricated construction has been considered a widely accepted alternative to conventional cast-in-situ concrete construction since it is capable of offering numerous benefits for investors and contractors. However, delays frequently occur in prefabricated concrete building projects, despite strong efforts to improve project schedule estimation and control. Thus, the delay factors of prefabricated construction should be identified and analysed to improve its scheduling performance. As one of the multi-criteria decision making techniques, ANP is capable of making accurate calculation of criteria priorities and their relations. Meanwhile, DEMATEL is a useful method for analysing and quantifying cause-effect relationships. Thus, integrating DEMATEL with ANP can effectively identify the critical attributes and evaluate the weights of criteria. Many fields are showing increasing interest in utilising the DEMATEL-ANP method for multi-criteria decision-making; however, a synthesised risk assessment based on the DEMATEL–ANP method had not yet been addressed in construction projects of prefabricated concrete buildings before this research. This paper utilised the combination method for investigating the cause-and-effect relationships among the delay factors and prioritising the key delay factors in terms of their importance in the Chinese construction industry. The DEMATEL model facilitated the evaluation of the extent to which each factor impacts other delay factors. The quantified extents were then converted into a prioritisation matrix through ANP. Twenty-four risk factors have been selected from a literature review and categorised into seven dimensions. Questionnaires have been chosen as data source to assist in the practical application of the method in the prefabricated construction.
The results reveal that ‘inadequate worker experience’ has the most significant impact on the other factors and ‘inefficient structural connections for prefabricated components’ is the most easily affected by the most delay factors in the Chinese construction industry. In addition, the global weights indicate that ‘inefficient structural connections’ is considered the most significant indicator. Other major delay factors, including ‘lack of communication among participants’ and ‘low productivity’, should also be included in the scheduling control. Overall, this research contributes an assessment framework for decision making in the scheduling management of prefabrication construction. This research is expected to be further improved by incorporating broader data sources and including more delay factors in future research.

Author Contributions

Conceptualization, Y.J., L.Q., Y.L. and X.L.; Methodology, Y.J., L.Q., Y.L., X.L.; H.X.L. and Y.L.; Formal Analysis, L.Q. and Y.L.; Writing-Original Draft Preparation, L.Q. and Y.L.; Writing-Review & Editing, H.X.L. and Y.L.; Funding Acquisition, Y.J.

Acknowledgments

The authors are thankful for the support from the National Key R&D Program of China (2016YFC0701810 in 2016YFC0701800), North China University of Technology Science and Technology Innovation Project (18XN149), and North China University of Technology Yu Jie Talent Development Program (18XN154).

Conflicts of Interest

The authors declare that there is no conflict of interest regarding the publication of this paper.

References

  1. Smit, R.E. Off-Site Construction Implementation Resource: Off-Site and Modular Construction Explained. In Off-Site Construction Council; National Institute of Building Sciences: Washington, DC, USA, 2014. [Google Scholar]
  2. Zhong, R.Y.; Peng, Y.; Xue, F.; Fang, J.; Zou, W.; Luo, H.; Thomas Ng, S.; Lu, W.; Shen, G.Q.P.; Huang, G.Q. Prefabricated construction enabled by the Internet-of-Things. Autom. Constr. 2017, 76, 59–70. [Google Scholar] [CrossRef]
  3. Arashpour, M.; Bai, Y.; Aranda-mena, G.; Bab-Hadiashar, A.; Hosseini, R.; Kalutara, P. Optimizing decisions in advanced manufacturing of prefabricated products: Theorizing supply chain configurations in off-site construction. Autom. Constr. 2017, 84, 146–153. [Google Scholar] [CrossRef]
  4. Mostafa, S.; Chileshe, N.; Abdelhamid, T. Lean and agile integration within offsite construction using discrete event simulation: A systematic literature review. Constr. Innov. 2016, 16, 483–525. [Google Scholar] [CrossRef]
  5. Kolo, S.J.; Rahimian, F.P.; Goulding, J.S. Offsite Manufacturing Construction: A Big Opportunity for Housing Delivery in Nigeria. Procedia Eng. 2014, 85, 319–327. [Google Scholar] [CrossRef]
  6. Wang, Z.; Hu, H.; Gong, J. Framework for modeling operational uncertainty to optimize offsite production scheduling of precast components. Autom. Constr. 2018, 86, 69–80. [Google Scholar] [CrossRef]
  7. Tam, V.W.Y.; Fung, I.W.H.; Sing, M.C.P.; Ogunlana, S.O. Best practice of prefabrication implementation in the Hong Kong public and private sectors. J. Clean. Prod. 2015, 109, 216–231. [Google Scholar] [CrossRef]
  8. Li, Z.; Shen, G.Q.; Xue, X. Critical review of the research on the management of prefabricated construction. Habitat Int. 2014, 43, 240–249. [Google Scholar] [CrossRef] [Green Version]
  9. Blismas, N.; Pasquire, C.; Gibb, A. Benefit evaluation for off-site production in construction. Constr. Manag. Econ. 2006, 24, 121–130. [Google Scholar] [CrossRef] [Green Version]
  10. Matic, D.; Calzada, J.R.; Todorovic, M.S.; Erić, M.; Babin, M. Cost-Effective Energy Refurbishment of Prefabricated Buildings in Serbia. In Cost-Effective Energy Efficient Building Retrofitting; Pacheco-Torgal, F., Granqvist, C.-G., Jelle, B.P., Vanoli, G.P., Bianco, N., Kurnitski, J., Eds.; Woodhead Publishing: Cambridge, UK, 2017; Chapter 16; pp. 455–487. [Google Scholar]
  11. Minunno, R.; O’Grady, T.; Morrison, G.; Gruner, R.; Colling, M. Strategies for Applying the Circular Economy to Prefabricated Buildings. Buildings 2018, 8, 125. [Google Scholar] [CrossRef]
  12. Pons, O. 18-Assessing the sustainability of prefabricated buildings. In Eco-efficient Construction and Building Materials; Pacheco-Torgal, F., Cabeza, L.F., Labrincha, J., de Magalhães, A., Eds.; Woodhead Publishing: Cambridge, UK, 2014; pp. 434–456. [Google Scholar]
  13. Salavatian, S.; D’Orazio, M.; Di Perna, C.; Di Giuseppe, E. Assessment of Cardboard as an Environment-Friendly Wall Thermal Insulation for Low-Energy Prefabricated Buildings. In Sustainable Building for a Cleaner Environment: Selected Papers from the World Renewable Energy Network’s Med Green Forum 2017; Sayigh, A., Ed.; Springer International Publishing: Cham, Switzerland, 2019; pp. 463–470. [Google Scholar]
  14. Hong, J.; Shen, G.Q.; Li, Z.; Zhang, B.; Zhang, W. Barriers to promoting prefabricated construction in China: A cost–benefit analysis. J. Clean. Prod. 2018, 172, 649–660. [Google Scholar] [CrossRef]
  15. Chang, Y.; Li, X.; Masanet, E.; Zhang, L.; Huang, Z.; Ries, R. Unlocking the green opportunity for prefabricated buildings and construction in China. Resour. Conserv. Recycl. 2018, 139, 259–261. [Google Scholar] [CrossRef]
  16. Fenner, A.E.; Razkenari, M.; Hakim, H.; Kibert, C.J. A Review of Prefabrication Benefits for Sustainable and Resilient Coastal Areas. In Proceedings of the 6th International Network of Tropical Architecture Conference, Tropical Storms as a Setting for Adaptive Development and Architecture, Gainesville, FL, USA, 1–3 December 2017. [Google Scholar]
  17. Li, C.Z.; Hong, J.; Xue, F.; Shen, G.Q.; Xu, X.; Mok, M.K. Schedule risks in prefabrication housing production in Hong Kong: A social network analysis. J. Clean. Prod. 2016, 134, 482–494. [Google Scholar] [CrossRef]
  18. Li, H.X.; Al-Hussein, M.; Lei, Z.; Ajweh, Z. Risk identification and assessment of modular construction utilizing fuzzy analytic hierarchy process (AHP) and simulation. Can. J. Civ. Eng. 2013, 40, 1184–1195. [Google Scholar] [CrossRef]
  19. Li, C.Z.; Shen, G.Q.; Xu, X.; Xue, F.; Sommer, L.; Luo, L. Schedule risk modeling in prefabrication housing production. J. Clean. Prod. 2017, 153, 692–706. [Google Scholar] [CrossRef]
  20. Taghaddos, H.; Hermann, U.; AbouRizk, S.; Mohamed, Y. Simulation-Based Multiagent Approach for Scheduling Modular Construction. J. Comput. Civ. Eng. 2014, 28, 263–274. [Google Scholar] [CrossRef]
  21. Salama, T.; Salah, A.; Moselhi, O. Integration of Offsite and Onsite Schedules in Modular Construction. In Proceedings of the 34th International Symposium on Automation and Robotics in Construction, International Association for Automation & Robotics in Construction, Taipei, Taiwan, 28 June–1 July 2017. [Google Scholar]
  22. Mao, C.; Shen, Q.; Pan, W.; Ye, K. Major Barriers to Off-Site Construction: The Developer’s Perspective in China. J. Manag. Eng. 2015, 31, 04014043. [Google Scholar] [CrossRef]
  23. Taylan, O.; Bafail, A.O.; Abdulaal, R.M.S.; Kabli, M.R. Construction projects selection and risk assessment by fuzzy AHP and fuzzy TOPSIS methodologies. Appl. Soft Comput. 2014, 17, 105–116. [Google Scholar] [CrossRef]
  24. Dai, Q.; Li, J. A Single DEA-based Indicator for Assessing the Multiple Negative Effects of Project Risks. Procedia Comput. Sci. 2016, 91, 769–773. [Google Scholar] [CrossRef]
  25. Aminbakhsh, S.; Gunduz, M.; Sonmez, R. Safety risk assessment using analytic hierarchy process (AHP) during planning and budgeting of construction projects. J. Saf. Res. 2013, 46, 99–105. [Google Scholar] [CrossRef] [PubMed]
  26. Wu, D.D.; Olson, D. Enterprise risk management: A DEA VaR approach in vendor selection. Int. J. Prod. Res. 2010, 48, 4919–4932. [Google Scholar] [CrossRef]
  27. Tjader, Y.; May, J.H.; Shang, J.; Vargas, L.G.; Gao, N. Firm-level outsourcing decision making: A balanced scorecard-based analytic network process model. Int. J. Prod. Econ. 2014, 147, 614–623. [Google Scholar] [CrossRef]
  28. Büyüközkan, G.; Güleryüz, S. An integrated DEMATEL-ANP approach for renewable energy resources selection in Turkey. Int. J. Prod. Econ. 2016, 182, 435–448. [Google Scholar] [CrossRef]
  29. Tseng, M.-L.; Lin, Y.H. Application of fuzzy DEMATEL to develop a cause and effect model of municipal solid waste management in Metro Manila. Environ. Monit. Assess. 2008, 158, 519. [Google Scholar] [CrossRef] [PubMed]
  30. Tseng, M.-L. Using a hybrid MCDM model to evaluate firm environmental knowledge management in uncertainty. Appl. Soft Comput. 2011, 11, 1340–1352. [Google Scholar] [CrossRef]
  31. Kahraman, U.A. Analysis of interactions between performance indicators with fuzzy decision making approach in healthcare management. J. Intell. Manuf. 2015, 1–16. [Google Scholar] [CrossRef]
  32. Yeh, T.-M.; Huang, Y.-L. Factors in determining wind farm location: Integrating GQM, fuzzy DEMATEL, and ANP. Renew. Energy 2014, 66, 159–169. [Google Scholar] [CrossRef]
  33. Salama, T.; Salah, A.; Moselhi, O. Alternative scheduling and planning processes for hybrid offsite construction. In Proceedings of the 33rd International Symposium on Automation and Robotics in Construction, International Association for Automation and Robotics in Construction, Auburn, AL, USA, 18–21 July 2016. [Google Scholar]
  34. Wing, C.K. The ranking of construction management journals. Constr. Manag. Econ. 1997, 15, 387–398. [Google Scholar] [CrossRef]
  35. Al-Kharashi, A.; Skitmore, M. Causes of delays in Saudi Arabian public sector construction projects. Constr. Manag. Econ. 2009, 27, 3–23. [Google Scholar] [CrossRef] [Green Version]
  36. Doloi, H.; Sawhney, A.; Iyer, K.C. Structural equation model for investigating factors affecting delay in Indian construction projects. Constr. Manag. Econ. 2012, 30, 869–884. [Google Scholar] [CrossRef]
  37. Yang, J.-B.; Tsai, M.-K. Computerizing ICBF Method for Schedule Delay Analysis. J. Constr. Manag. Econ. 2011, 137, 583–591. [Google Scholar] [CrossRef]
  38. Braimah, N.; Ndekugri, I. Consultants’ Perceptions on Construction Delay Analysis Methodologies. J. Constr. Manag. Econ. 2009, 135, 1279–1288. [Google Scholar] [CrossRef]
  39. Yang, J.-B.; Yin, P.-C. Isolated Collapsed But-For Delay Analysis Methodology. J. Constr. Manag. Econ. 2009, 135, 570–578. [Google Scholar] [CrossRef]
  40. Yap, J.B.H.; Abdul-Rahman, H.; Wang, C. Preventive Mitigation of Overruns with Project Communication Management and Continuous Learning: PLS-SEM Approach. J. Constr. Manag. Econ. 2018, 144, 04018025. [Google Scholar] [CrossRef]
  41. Kadry, M.; Osman, H.; Georgy, M. Causes of Construction Delays in Countries with High Geopolitical Risks. J. Constr. Manag. Econ. 2017, 143, 04016095. [Google Scholar] [CrossRef]
  42. Jung, M.; Park, M.; Lee, H.-S.; Kim, H. Weather-Delay Simulation Model Based on Vertical Weather Profile for High-Rise Building Construction. J. Constr. Manag. Econ. 2016, 142, 04016007. [Google Scholar] [CrossRef]
  43. Ahmadian, F.F.A.; Akbarnezhad, A.; Rashidi, T.H.; Waller, S.T. Accounting for Transport Times in Planning Off-Site Shipment of Construction Materials. J. Constr. Manag. Econ. 2016, 142, 04015050. [Google Scholar] [CrossRef]
  44. González, P.; González, V.; Molenaar, K.; Orozco, F. Analysis of Causes of Delay and Time Performance in Construction Projects. J. Constr. Manag. Econ. 2014, 140, 04013027. [Google Scholar] [CrossRef]
  45. Birgonul, M.T.; Dikmen, I.; Bektas, S. Integrated Approach to Overcome Shortcomings in Current Delay Analysis Practices. J. Constr. Manag. Econ. 2015, 141, 04014088. [Google Scholar] [CrossRef]
  46. Rocha, C.G.d.; Kemmer, S.L. Method to Implement Delayed Product Differentiation in Construction of High-Rise Apartment Building Projects. J. Constr. Manag. Econ. 2013, 139, 05013001. [Google Scholar] [CrossRef]
  47. Mahamid, I. Contractors perspective toward factors affecting labor productivity in building construction. Eng. Constr. Arch. Manag. 2013, 20, 446–460. [Google Scholar] [CrossRef]
  48. Shebob, A.; Dawood, N.; Shah, R.K.; Xu, Q. Comparative study of delay factors in Libyan and the UK construction industry. Eng. Constr. Arch. Manag. 2012, 19, 688–712. [Google Scholar] [CrossRef]
  49. Shahsavand, P.; Marefat, A.; Parchamijalal, M. Causes of delays in construction industry and comparative delay analysis techniques with SCL protocol. Eng. Constr. Arch. Manag. 2018, 25, 497–533. [Google Scholar] [CrossRef]
  50. Agyekum-Mensah, G.; Knight, A.D. The professionals’ perspective on the causes of project delay in the construction industry. Eng. Constr. Arch. Manag. 2017, 24, 828–841. [Google Scholar] [CrossRef] [Green Version]
  51. Mahamid, I. Risk matrix for factors affecting time delay in road construction projects: Owners’ perspective. Eng. Constr. Arch. Manag. 2011, 18, 609–617. [Google Scholar] [CrossRef]
  52. Ansah, R.H.; Sorooshian, S. 4P delays in project management. Eng. Constr. Arch. Manag. 2018, 25, 62–76. [Google Scholar] [CrossRef]
  53. Ballesteros-Pérez, P.; del Campo-Hitschfeld, M.L.; González-Naranjo, M.A.; González-Cruz, M.C. Climate and construction delays: Case study in Chile. Eng. Constr. Arch. Manag. 2015, 22, 596–621. [Google Scholar] [CrossRef]
  54. Adam, A.; Josephson, P.-E.B.; Lindahl, G. Aggregation of factors causing cost overruns and time delays in large public construction projects: Trends and implications. Eng. Constr. Arch. Manag. 2017, 24, 393–406. [Google Scholar] [CrossRef]
  55. Habibi, M.; Kermanshachi, S. Phase-based analysis of key cost and schedule performance causes and preventive strategies: Research trends and implications. Eng. Constr. Arch. Manag. 2018, 25, 1009–1033. [Google Scholar] [CrossRef]
  56. Bagaya, O.; Song, J. Empirical Study of Factors Influencing Schedule Delays of Public Construction Projects in Burkina Faso. J. Manag. Eng. 2016, 32, 05016014. [Google Scholar] [CrossRef]
  57. Larsen, J.K.; Shen, G.Q.; Lindhard, S.M.; Brunoe, T.D. Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. J. Manag. Eng. 2016, 32, 04015032. [Google Scholar] [CrossRef]
  58. Wang, J.; Yuan, H. System Dynamics Approach for Investigating the Risk Effects on Schedule Delay in Infrastructure Projects. J. Manag. Eng. 2017, 33, 04016029. [Google Scholar] [CrossRef]
  59. Perera, N.A.; Sutrisna, M.; Yiu, T.W. Decision-Making Model for Selecting the Optimum Method of Delay Analysis in Construction Projects. J. Manag. Eng. 2016, 32, 04016009. [Google Scholar] [CrossRef]
  60. Santoso, D.S.; Soeng, S. Analyzing Delays of Road Construction Projects in Cambodia: Causes and Effects. J. Manag. Eng. 2016, 32, 05016020. [Google Scholar] [CrossRef]
  61. Gunduz, M.; Nielsen, Y.; Ozdemir, M. Fuzzy Assessment Model to Estimate the Probability of Delay in Turkish Construction Projects. J. Manag. Eng. 2015, 31, 04014055. [Google Scholar] [CrossRef]
  62. Ruqaishi, M.; Bashir, H.A. Causes of Delay in Construction Projects in the Oil and Gas Industry in the Gulf Cooperation Council Countries: A Case Study. J. Manag. Eng. 2015, 31, 05014017. [Google Scholar] [CrossRef]
  63. Braimah, N. Understanding Construction Delay Analysis and the Role of Preconstruction Programming. J. Manag. Eng. 2014, 30, 04014023. [Google Scholar] [CrossRef] [Green Version]
  64. Gündüz, M.; Nielsen, Y.; Özdemir, M. Quantification of Delay Factors Using the Relative Importance Index Method for Construction Projects in Turkey. J. Manag. Eng. 2013, 29, 133–139. [Google Scholar] [CrossRef]
  65. Golob, K.; Bastič, M.; Pšunder, I. Influence of Project and Marketing Management on Delays, Penalties, and Project Quality in Slovene Organizations in the Construction Industry. J. Manag. Eng. 2013, 29, 495–502. [Google Scholar] [CrossRef]
  66. AlSehaimi, A.; Koskela, L.; Tzortzopoulos, P. Need for Alternative Research Approaches in Construction Management: Case of Delay Studies. J. Manag. Eng. 2013, 29, 407–413. [Google Scholar] [CrossRef]
  67. Mahamid, I.; Bruland, A.; Dmaidi, N. Causes of Delay in Road Construction Projects. J. Manag. Eng. 2012, 28, 300–310. [Google Scholar] [CrossRef]
  68. Doloi, H.; Sawhney, A.; Iyer, K.C.; Rentala, S. Analysing factors affecting delays in Indian construction projects. Int. J. Proj. Manag. 2012, 30, 479–489. [Google Scholar] [CrossRef]
  69. Luu, V.T.; Kim, S.-Y.; Tuan, N.V.; Ogunlana, S.O. Quantifying schedule risk in construction projects using Bayesian belief networks. Int. J. Proj. Manag. 2009, 27, 39–50. [Google Scholar] [CrossRef]
  70. Arditi, D.; Nayak, S.; Damci, A. Effect of organizational culture on delay in construction. Int. J. Proj. Manag. 2017, 35, 136–147. [Google Scholar] [CrossRef]
  71. Yang, J.-B.; Kao, C.-K. Critical path effect based delay analysis method for construction projects. Int. J. Proj. Manag. 2012, 30, 385–397. [Google Scholar] [CrossRef]
  72. Kaliba, C.; Muya, M.; Mumba, K. Cost escalation and schedule delays in road construction projects in Zambia. Int. J. Proj. Manag. 2009, 27, 522–531. [Google Scholar] [CrossRef]
  73. Xu, X.; Wang, J.; Li, C.Z.; Huang, W.; Xia, N. Schedule risk analysis of infrastructure projects: A hybrid dynamic approach. Autom. Constr. 2018, 95, 20–34. [Google Scholar] [CrossRef]
  74. Hegazy, T.; Said, M.; Kassab, M. Incorporating rework into construction schedule analysis. Autom. Constr. 2011, 20, 1051–1059. [Google Scholar] [CrossRef]
  75. Dehdasht, G.; Mohamad Zin, R.; Ferwati, M.; Mohammed Abdullahi, M.a.; Keyvanfar, A.; McCaffer, R. DEMATEL-ANP Risk Assessment in Oil and Gas Construction Projects. Sustainability 2017, 9, 1420. [Google Scholar] [CrossRef]
  76. Seker, S.; Zavadskas, E. Application of Fuzzy DEMATEL Method for Analyzing Occupational Risks on Construction Sites. Sustainability 2017, 9, 2083. [Google Scholar] [CrossRef]
  77. Hu, H.-Y.; Lee, Y.-C.; Yen, T.-M.; Tsai, C.-H. Using BPNN and DEMATEL to modify importance–performance analysis model—A study of the computer industry. Expert Syst. Appl. 2009, 36, 9969–9979. [Google Scholar] [CrossRef]
Figure 1. Flowchart of prefabricated construction process.
Figure 1. Flowchart of prefabricated construction process.
Applsci 08 02324 g001
Figure 2. Influential network-relationship map for dimensions.
Figure 2. Influential network-relationship map for dimensions.
Applsci 08 02324 g002
Figure 3. Causal diagram for delay factors in prefabricated construction.
Figure 3. Causal diagram for delay factors in prefabricated construction.
Applsci 08 02324 g003
Table 1. Literature of construction schedule performance within selected journals.
Table 1. Literature of construction schedule performance within selected journals.
JournalsNumber of Reviewed PapersScholarly Publications
Construction Management and Economics2[35,36]
Journal of Construction Engineering and Management10[37,38,39,40,41,42,43,44,45,46]
Engineering, Construction and Architectural Management9[47,48,49,50,51,52,53,54,55]
Journal of Management in Engineering12[56,57,58,59,60,61,62,63,64,65,66,67]
International Journal of Project Management5[68,69,70,71,72]
Automation in Construction2[73,74]
Table 2. Key factors affecting project progress in prefabricated building projects.
Table 2. Key factors affecting project progress in prefabricated building projects.
DimensionsFactors
D1
Construction
Techniques
F11 Low-precision installation techniques
F12 Improper lifting operations
F13 Insufficient site space to layout
D2
Workforce
F21 Inadequate worker experience
F22 Low productivity
F23 Insufficient proficiency
D3
Resources
F31 Shortage and delay in material supply
F32 Damage to stored components
D4
Machinery
F41 Equipment failure
F42 Vehicle and equipment unavailability
D5
Clients
F51 Inefficient decision-making
F52 Additional requirements
D6
Contractors
F61 Improper construction planning and schedule design
F62 Wrong delivery requirements and routes
F63 Poor site layout
F64 Lack of communication among participants
F65 Information gaps among companies
F66 Rehandling components
F67 Inefficient structural connections
F68 Return to manufacturers owing to design errors
F69 Re-manufacturing owing to component damage
D7
External
Conditions
F71 Policy uncertainty
F72 Severe weather
F73 Energy and water supply failure, transportation disruption
Table 3. Demographic information of the participants.
Table 3. Demographic information of the participants.
Experience (Years)Job Background
Description<55–1010–20>20UniversitiesClientsMain ContractorsManufacturing and LogisticsAssembly FirmsGovernment Departments
Number8976655842
Percentage27%30%23%20%20%17%17%26%13%7%
Table 4. Average direct-relation matrix.
Table 4. Average direct-relation matrix.
F11F12F13F21F22F23F31F32F41F42F51F52F61F62F63F64F65F66F67F68F69F71F72F73
F11000010000011122002400000
F12000010000000103004301000
F13000010220300134004001000
F21000044111200444103423000
F22000000300300000100400000
F23000040222200032101401000
F31000000000000000000300000
F32000020400000000003301000
F41000020410400000000301000
F42000030000000000000300000
F51000000300300000020000000
F52000000200200000000200000
F61323030400420030304310000
F62000040300300000004002000
F63044030000300000004400000
F64000040400440334004400000
F65000040300330333404410000
F66000030000000000000403000
F67000000020000000001002000
F68000002000000000000200000
F69000000040000000001200000
F71000000300300000000000000
F72000000300300000000202000
F73000000200200000000202000
Table 5. Sum of influences given to and received from other factors.
Table 5. Sum of influences given to and received from other factors.
Dimensionriciri + ciriciFactorriciri + cirici
D10.77910.00000.77910.7791F110.53240.10990.64230.4225
F120.50600.25070.75660.2553
F130.80860.28731.09590.5214
D21.09020.43061.52080.6596F211.55530.00001.55531.5553
F220.36481.52821.8930−1.1634
F230.88450.16411.04860.7205
D30.38451.16271.5473−0.7782F310.09281.50631.5990−1.4135
F320.41740.55520.9726−0.1378
D40.40530.89431.2996−0.4890F410.47610.08760.56370.3885
F420.20051.53581.7363−1.3353
D50.38450.97121.3558−0.5867F510.30790.32860.6365−0.0207
F520.18260.02920.21180.1533
D61.49951.29882.79830.2007F611.32530.39201.71730.9333
F620.53030.65781.1881−0.1276
F630.81510.68531.50050.1298
F641.28190.34601.62790.9359
F651.41010.06991.48001.3402
F660.32981.44861.7784−1.1188
F670.17522.42922.6043−2.2540
F680.16100.11740.27850.0436
F690.24600.81221.0583−0.5662
D70.21460.00000.21460.2146F710.18110.00000.18110.1811
F720.30850.00000.30850.3085
F730.24810.00000.24810.2481
Table 6. Influential weights of dimensions and delay factors in prefabricated construction.
Table 6. Influential weights of dimensions and delay factors in prefabricated construction.
DimensionInfluential WeightRankingFactorInfluential WeightRanking
D10.114563F110.0001816
F120.0002614
F130.0002615
D20.239922F210.0001617
F220.148863
F230.0000619
D30.113164F310.085456
F320.004669
D40.086985F410.0000520
F420.054627
D50.050116F510.0007413
F520.0000321
D60.363581F610.089335
F620.0022510
F630.0012112
F640.107034
F650.0022211
F660.191582
F670.277011
F680.0001418
F690.033918
D70.031697F710.0000123
F720.0000222
F730.0000124

Share and Cite

MDPI and ACS Style

Ji, Y.; Qi, L.; Liu, Y.; Liu, X.; Li, H.X.; Li, Y. Assessing and Prioritising Delay Factors of Prefabricated Concrete Building Projects in China. Appl. Sci. 2018, 8, 2324. https://doi.org/10.3390/app8112324

AMA Style

Ji Y, Qi L, Liu Y, Liu X, Li HX, Li Y. Assessing and Prioritising Delay Factors of Prefabricated Concrete Building Projects in China. Applied Sciences. 2018; 8(11):2324. https://doi.org/10.3390/app8112324

Chicago/Turabian Style

Ji, Yingbo, Lin Qi, Yan Liu, Xinnan Liu, Hong Xian Li, and Yan Li. 2018. "Assessing and Prioritising Delay Factors of Prefabricated Concrete Building Projects in China" Applied Sciences 8, no. 11: 2324. https://doi.org/10.3390/app8112324

APA Style

Ji, Y., Qi, L., Liu, Y., Liu, X., Li, H. X., & Li, Y. (2018). Assessing and Prioritising Delay Factors of Prefabricated Concrete Building Projects in China. Applied Sciences, 8(11), 2324. https://doi.org/10.3390/app8112324

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop