Because of rapid industrial development in the county, industrial wastewater discharge increases annually; therefore, a sewage treatment plant needs to be established so that the wastewater can be processed and reach the discharge standard. Three optional sites around the county are available, from which one or two sites can be selected. Since the county is located in a flood-prone area, the issue of flood control should not be ignored when building a sewage treatment plant. In addition, some other actual situations of the county should be taken into account, such as, the planned area, the overall layout of principal pipelines, the matched technical process, etc.
3.1. Schemes for Site Selection
Minjiang River runs through the county, which is a resort for holidays, exploration, and recuperation, with abundant tourism resources and national nature reserves. According to the overall sewage quantity of the county, principles of site selection and the specific situation of the county industrial development, the designed process capability of a sewage treatment plant is between 20,000 and 50,000 m3/day. Considering both the construction scale and the surrounding areas, the planning area of the plant is approximately 10,000–50,000 m3. Through a preliminary survey conducted by relevant personnel in the planning process and a solicitation of opinions from involved parties, three relatively satisfactory plans for the location were selected in accordance with the principles and requirements of constructing a sewage plant. The details are as follows:
- Scheme I:
A sewage plant can be built on a mountain slope with a gradient of 40°. Hence, the land requires leveling; thus, the capital cost of earthwork is evaluated as 190 thousand USD.
- Scheme II:
A sewage plant can be built on a river bank with a floodwall, which is used for resolving a flood issue. Due to the reinforced concrete structure of the floodwall, a total of 4800 m3 of reinforced concrete is needed. Calculating the comprehensive cost of the reinforced concrete at 63.49 USD/m3, the required investment is 304.76 thousand USD.
- Scheme III:
A sewage plant can be built on a river bank without a floodwall. In this situation, the processing equipment needs to be adjusted. It is worth noting that this scheme adopts an ICEAS process (an improved SBR technique). Adopting this process can completely avoid the flood control drawbacks of the aeration equipment. Before the flood, we need only to move the ordinary movable elements without worrying about the key equipment in the sewage plant.
All of the capital expenditures of a sewage treatment plant in the schemes above are illustrated in
Table 1. In addition, the proposed reuse rate of the reclaimed water of all schemes is 30%, and the economic benefit of the reclaimed water per unit is 0.19 USD/m
3.
3.4. Total Costs and Solution Procedure
The total cost of a sewage treatment plant consists of an initial investment cost and an operation cost in this study. In addition, the specific forms of the initial investment cost and the operation cost in practical calculation are different.
The initial investment cost of a sewage treatment plant in this case comprises costs mentioned in
Table 1 and the diverse process investment cost in terms of different techniques. For the convenience of calculation, initial investment cost models of three kinds of techniques were borrowed from other literature and were utilized in this case, as shown in
Table 5.
In addition, the operation cost of a sewage plant refers to the expenditure for sewage treatment after the completion of the project. In the operation of a sewage plant, the operating cost mainly focuses on pipeline maintenance, energy consumption, equipment repair and so forth. In addition to the operation cost listed in
Table 6, the sewage treatment costs from different processes are also included.
In this paper, the proposed model is solved by a heuristic algorithm, the Genetic Algorithm (GA), because it is challenging to solve directly.
Figure 4 and
Table A1 illustrate the basic process of the applied genetic algorithm.
3.5. Result Analysis
The parameters for the GA in this problem are as follows: crossover rate 0.2, mutation rate is 0.4, population size is 25 and maximum generation is 500.
Assign weight to the four objective functions in turn:
Through calculation, the optimal result of the multi-objective model in this situation is:
Accordingly, under the optimal solution, the minimum cost is 4.19 × 106 USD; the maximum economic benefit is 2.17 × 104 USD; and the removal rates of COD and ammonia nitrogen are approximately 85.1% and 93.2%, respectively. Because x1 = x2 = 0, which means that schemes I and II are not considered, any arbitrary value assigned to neither the design capacity nor the removal rate of COD and ammonia nitrogen in the model is meaningless.
The results above show that within the planned area of 10,000–50,000 m2, to achieve such goals as reaching the designed capacity of 20,000–50,000 m3/day and meeting the requirements of minimum investment cost, Scheme III should be selected. In Scheme I a method of building a highland sewage treatment plant is adopted, leading to larger investment in earth work and annual operation cost. Through analysis, the paper concludes that Scheme I is not economically feasible. In Scheme II, the sewage plant is surrounded by a flood wall, resulting in a series of problems, such as a large investment and landscape affects. Scheme III adopts provisions to install submersible sewage pumps and jet aeration devices, plan a control room and install the electric transformation and distribution equipment with localized elevation in the building of the sewage plant. Although the investment increases to a certain extent, the overall increase is not too large. Scheme III, therefore, is technically feasible and economically rational.
In terms of techniques, although the improved SBR technique with an ICEAS process is only adopted in Scheme III, it can effectively dispose of pollutants in wastewater and reduce their current content, thereby meeting the requirements of the total discharge control of pollutants. This is attributable to the principal sewage in this area being composed of domestic wastewater, the biodegradability of which is relatively good; meanwhile, the ICEAS process is the secondary biochemical treatment, enabling the COD and ammonia nitrogen removal rate to reach a higher level at 85.1% and 93.2%, respectively. In contrast, even though the optional processes in schemes I and II can achieve the desired effect discussed in the preceding, they are restricted economically due to their higher construction and operation costs.
From the perspective of environmental protection, Scheme III is also based on realistic considerations. The COD and ammonia nitrogen concentrations of the treated sewage are calculated as 35.63 mg/L and 2.39 mg/L, respectively, completely meeting GB18918-2002 “Pollutant Discharge Standard for Municipal Sewage Treatment Plants” primary standard B. Additionally, this scheme locates the treatment plant on the river bank without a flood wall surrounding it. In accordance with the normal requirements, the structural foundation is laid without causing irreversible damage to the surrounding environment (including water, groundwater, cultivated land, forests, aquatic products, landscape, scenic spots, nature reserves, etc.). Moreover, neither is it located in the upper wind zone of urban or residential areas, nor upstream of an urban water resource; therefore, the treatment plant will not affect the residents’ normal life.
According to the importance attached to each target by the decision makers, different weights were assigned to each objective function.
Table 7 illustrates the value of each objective function for the conditions and the optimal decision results.
Construction cost is a primary factor considered when building a treatment plant; therefore, it is generally assigned a greater weight value. In accordance with the importance attached to reclaimed water benefit and pollutant discharge amount the weight is adjusted. It is manifested from
Table 7 that the weight adjustment of the cost and the reclaimed water benefit will significantly affect the decision result, whereas the weight changes of pollutant treatment efficiency or pollutant emission will not substantially affect the decision result.
Based on the actual situation and the development plan of an area we can adjust the parameters, such as modifying the sewage quantity and the reuse rate of reclaimed water. Through such adjustments, we can set up a new situation, establish different multi-objective decision models for constructing a treatment plant and obtain various corresponding results by calculation. Since some parameters in this case were calculated based on those of other towns with the same levels, the relevant data might not precisely match the corresponding data; therefore, a situation could arise where the adjustment of a certain index will not significantly affect the decision result, in contradiction with the real situation. Therefore, decision makers should fully understand the specific characteristics of their practical application because the accuracy of the data determines the accuracy of the model. In the practical applications, however, researchers can adjust this model to a certain extent and use this flexibility with actual conditions that can better reflect the real conditions of a given problem domain.