3.1. General and Adverse Impacts of COVID-19 on the Construction Industry
3.1.1. Disparities across States on Whether Construction Operations Are Essential or Non-Essential
In the first few months of the pandemic, stay-at-home or shelter-in-place orders were being enforced across several states to prevent the spread of the novel coronavirus. However, a few states did not require any such restrictions. In most states, construction businesses were deemed to be essential; however, a few states identified construction operations to be at least partly non-essential. Therefore, there were restrictions for construction operations in some states whereas there were no restrictions in other states. Among the states where construction operations were partly restricted, there was much variability in the degree of restrictions. Accordingly, there were many differences in how construction businesses were impacted across different states.
For example, some of the participants mentioned that there was little impact on their projects and that operations continued as normal; although a number of new safety measures were adopted. However, others mentioned that construction operations had completely ceased in their workplaces. A few participants shared that during the first few days, there was significant confusion on whether their business was deemed essential or non-essential due to the variability in the degree of restrictions across states. More specifically, it was unclear to the participants’ employer whether they can continue operations. There was also much uncertainty on when construction operations will resume in several states where restrictions were in place. In other cases, the participants were concerned whether new restraints would be placed if COVID-19 cases increased in their communities.
In cases where construction operations were considered non-essential, one participant mentioned that the impacts are not limited to only construction businesses. The participant shared that upstream suppliers and the operations of several downstream facilities were also adversely impacted. In addition, the participant mentioned that several other industries that serve the construction industry such as manufacturing will also experience negative impacts.
A few of the participants believed that the restrictions were essential given the risk of the virus spread. Others believed that the economic and adverse impacts far exceeded the risk of the virus spread. One of the participants mentioned that several agencies were advocating for the reopening of construction businesses and to change the status of construction businesses as being essential.
3.1.2. Material Delivery Delays and Shortage of Material
Most of the participants reported experiencing or expecting delays in material delivery. These delays in material delivery were also, in turn, expected to delay overall project progress and cause significant schedule disruptions. The delays were particularly relevant when the supply chain involved material or raw material from overseas. For example, one of the project managers mentioned that several building elements were to be shipped from Europe; however, the manufacturing plants were non-operational in Europe due to the COVID-19 pandemic. Others mentioned similar supply chain disruptions involving material and raw material from China, Mexico, Canada, and other nations.
Even within the U.S., although construction was deemed as an essential business in a number of states, several upstream manufacturing units and trucking companies within the supply chain were deemed non-essential. Accordingly, some of these businesses had to halt operations in response to the pandemic. In another case, a vendor mentioned that material delivery delays can also occur because several truck drivers are hesitant to cross state lines due to fears of contracting the virus and the requirement of quarantining for 14 days as imposed by certain states.
Material shortage was also experienced as a result of the social distancing and quarantining requirements that resulted in a smaller workforce within supply chain organizations. In many cases, the study participants were unable to predict the amount of delays given the number of factors that can impact delivery time in a pandemic situation.
3.1.3. Delays in Inspections and Securing Permits
Significant delays in inspections and securing permits were also reported. For example, one of the interviewed contractors mentioned that as all parties transitioned to the new format of working, there were delays in completing inspections and the certification of work. More specifically, the contractor mentioned that the owner’s representative in many cases was unable to stick to the initial timeframe to complete the certification of completed work. In many cases, several inspection-related meetings had to be canceled and postponed due to the challenges and restrictions of meeting in person.
The participants also shared that there were delays with securing permits from various governmental agencies. These delays were largely due to governmental agencies transitioning to working remotely from home and challenges associated with accessing the necessary information and documentation. In fact, in many cases, designers, architects, and project engineers mentioned that governmental agencies did not have an efficient and working system in place to make such a rapid transition. There were also discussions on the lack of sufficient technology-related support for these agencies as they grappled with making operational changes to the permitting process. In a few cases, the participants mentioned that the permitting processes were suspended temporarily until the governmental agencies were able to set up an online protocol for issuing the necessary permits.
3.1.4. Reduction in Efficiency and Productivity Rates
Productivity rates reportedly suffered across the construction industry. Much of the loss in productivity and efficiency was attributed to the new safety measures that were necessary to protect the workforce as the pandemic continued to progress. In fact, one of the project managers indicated that working safely was the top priority, and productivity took a backseat in the pandemic situation. Reduction in productivity rates also was attributed to shortages in the availability of PPE and the reduction in the number of workers to comply with the social distancing recommendations. In many cases, the participants also mentioned that workers choose to not report to work for a variety of reasons, which also impacted productivity and efficiency. Some of the reasons mentioned included quarantining requirements, caring for children as a result of school closure, and the fear of being infected at work and being carriers of the virus when around family. Recruitment and training of replacement workers also consumed substantial amounts of time.
The staggering of subcontractors in such a way so that they do not work alongside other subcontractors also was mentioned as affecting productivity rates. One of the participants mentioned that such staggering required significant revisions to the initially planned schedule and required much additional work and coordination. Inefficiencies in coordination along with the safety contingencies that were applied yielded lower productivity levels.
Cash flow challenges experienced by contractors and subcontractors were also mentioned as affecting productivity. Cash flow issues were particularly a problem due to escalating material prices and challenges that owners experienced with making timely payments to the contractors. Finally, as already discussed above, delays in material delivery, shortages in material availability, and delays in inspections and permitting were all also associated with productivity losses.
3.1.5. Suspension or Slowing of Ongoing Projects and Delay in the Start Date for New Projects
Given that the pandemic caused widespread economic downturns and uncertainties, owners, investors, and businesses were increasingly wary about investing in construction projects and operations. Therefore, a number of projects were canceled or temporally suspended. For example, one of the participants mentioned that several developers of commercial property, in particular, are increasingly waiting on the commitment from potential tenants before they can begin customized construction operations. However, the volume of potential tenants willing to make a commitment has significantly reduced as a result of the pandemic. In the same manner, one participant mentioned that with the plunge in the price of oil and the drop in the travel demand, a number of projects in the oil and gas sector have been suspended. The participant also mentioned that the budget devoted to oil and gas projects in the near future is expected to dramatically reduce.
In many other cases, the study participants reported that several private owners are citing financial concerns with the broader market and requesting that construction operations be either slowed or stalled. According to one architect, with the increasing number of individuals working, shopping, and studying over the internet, the future of retail and commercial property remains uncertain. The participant also mentioned that it is unlikely for the demand in these sectors to rebound in the immediate future, and hence, it may not be financially prudent to make progress in many of the ongoing projects.
One of the owners asked the contractors to slow the completion of a student apartment since students were not expected to report to the college town as classes were being taught online and cash flow was tight. Several of the owners experienced cash flow issues from existing properties and were unable to fund the completion of additional properties.
New construction projects were particularly impacted. One project engineer working for an industrial contractor reported that nearly 90% of the projects that were in the front-end loading (FEL) phase (i.e., pre-project planning) were put on hold. Moreover, several projects that were in the bidding stage were also canceled or postponed. One of the participants mentioned that fewer projects will be approved and funded as a result of the pandemic compared to previous years.
Another important reason for slowing down ongoing projects was the increase in requests to reassess mechanical ventilation and air filtration systems. One of the architects mentioned that owners were now concerned with whether their mechanical ventilation and air filtration systems would adequately replace contaminated air with clean air. In several cases, owners requested upgrades to the initial design to offer superior occupancy safety. There were also concerns on whether design changes will need to be incorporated in a post-pandemic world in anticipation of future events.
3.1.6. Price Escalations, Additional Costs, Loss of Revenue, and Payment Delays
According to several of the participants, supply chain disruptions resulted in an increase in the cost of construction materials. As discussed earlier, much of the disruption resulted from the closure and reduction in the capacity of manufacturing and processing facilities that are upstream in the supply chain. The increase in the cost of lumber, cement, and concrete products was particularly highlighted by a number of participants. Along with the increase in the cost of material, an increase in the cost of doing business was also reported. In many cases, the participants mentioned that this resulted in unexpected revenue and financial shocks at various points in the supply chain. In some cases, the participants mentioned that construction businesses may have to handle the extra costs themselves unless there is relief from the owners and other stakeholders as per the contractual agreement. This included the additional costs of managing safety, offering pandemic-related safety training, and securing the necessary PPE to sufficiently protect the workforce.
An increase in costs was also experienced since fewer subcontractors were willing to work and travel during the pandemic. According to one of the project managers, subcontractors that had to cross state lines were particularly hesitant to work given that they preferred to stay in their city of residence and avoid the 14-day quarantining requirement imposed by some states. In such cases, subcontractors often had to be offered larger compensations and incentives, which resulted in higher costs and potentially lower quality. An increase in the number of non-performance occurrences among subcontractors was also reported to increase costs.
Several contractors also expressed concerns with respect to additional costs from liquidated damages. The contractor representatives mentioned that the delays caused in the projects can result in these additional liabilities, and this can, in turn, impact the profit margins and the success of the projects.
Contractors were concerned that their staff will spend additional time on projects as a result of the experienced delays. This additional time was expected to translate into additional costs and overhead. Likewise, owners were concerned about the loss of revenue that was expected due to project delays and unoccupied retail and commercial properties. The participants were also concerned regarding the additional costs associated with the planning efforts that were necessary to transition successfully through the pandemic. Others alluded to the cost of shutting down projects and restarting the project as a major cost item that construction businesses will largely have to bear.
As construction operations are delayed, several participants mentioned that payment delays are likely to follow. The participants believed that this can result in cascading cash flow issues, and some contractors may struggle to pay their workforce, subcontractors, and suppliers in a timely manner.
3.1.7. Safety Concerns Regarding Virus Spread in Workplaces
There was much concern regarding the spread of the virus in construction workplaces. The participants were of the opinion that construction work is inherently collaborative and requires that different trades work alongside each other. In many cases, this requires workers to share workspaces and facilities, including portable bathrooms. Therefore, some of the participants believed that the risk of virus spread is significantly high and that robust safety measures were to be adopted to protect workers. However, given the collaborative nature of the work, several participants mentioned that safety guidelines such as social distancing were not very feasible in construction workplaces. In fact, concerns were expressed that the safety measures recommended for adoption in construction workplaces may have been developed without any consultation with construction professionals that are more familiar with construction operations. Additional information on these challenges is presented in greater detail in
Section 3.3.1.
Some of the participants mentioned that the risk of transmission is particularly high given that infected individuals may not particularly experience any symptoms in the early stages of the infection and can be active carriers of the virus. There was also mention that the risk was exacerbated by the fact that tests were not widely available, and even when workers had access to tests, there was usually a delay in receiving the test results. One of the supervisors mentioned that the risk of spread is undoubtedly higher in industries that are identified as essential but experience shortages in PPE and lack effective measures to prevent the virus spread.
Others discussed that several subcontractors work on different sites. Therefore, one of the participants mentioned that these subcontractors can spread the virus from one workplace to the other. In fact, according to one of the project managers, one of the subcontractor employees that newly transitioned into a workplace tested positive for the virus. In response, the project had to be temporarily shut down and the other workers that worked in the proximity of the positively tested worker had to quarantine for 14 days. This resulted in significant paperwork and related challenges. Similar challenges were expected as a result of the transient nature of the workforce including independent contractors. Suppliers and delivery personnel that visit different sites were also expected to pose a higher risk of virus spread.
A few participants shared that Hispanic and Latino workers may particularly be at a heightened risk of infection given their greater involvement in essential work within and outside of the construction industry. Others mentioned that the lower wages, immigration status and associated challenges, social connections with other essential workers, and their role as independent contractors in the industry expose these workers to higher risks.
3.1.8. Expected Increase in Disputes, Litigation, and Claims
Most of the participants expected that there will be a significant increase in the number of disputes, litigations, and claims on their projects and across the industry. They believed that the delays, temporary suspension of work, material shortages, and the additional costs that resulted from the pandemic will likely be the underlying cause for the disputes, litigations, and claims. The majority of the conflicts were expected between contractors and owners for nonperformance and delays. However, disputes were also expected in contractor-subcontractor, contractor-supplier, owner-future tenant, and contractor-insurance entity relationships.
Given the circumstances, the participants mentioned that there will be an increase in the use of the force majeure contractual clause, where contractors and subcontractors claim that the delays experienced were caused by circumstances that were unforeseeable and beyond their control. If contractors and subcontractors are able to successfully offer the relevant evidence, they may be able to secure a time extension and relief from delay-related penalties. In circumstances where a force majeure or another relevant contractual clause is absent in the contractual agreements, the contractors may seek relief in other ways. Disputes and conflicts become particularly likely when there are disagreements between the parties about the cause of the delay or the interpretation of the force majeure-related contractual language. The participants also mentioned that likelihood of disputes and litigation can increase if the owner has a future tenant that has committed to occupying the constructed facility.
Some participants also mentioned that contractors and subcontractors may seek relief for the increase in cost. The likelihood of success in these circumstances is dependent on the pricing mechanism adopted as per the contractual agreement. Contractors and subcontractors will also likely examine the contract to see if there are provisions to claim additional compensation using price escalation clauses. In some situations, there could also be disagreements with insurance agencies on whether the insurance policies offer coverage for a broad array of expected construction risks, including non-performance.
Other areas for conflict that the participants shared included the inability of suppliers to deliver construction materials in a timely manner, suppliers seeking to cancel delivery commitments, and suppliers seeking additional compensation for losses sustained from supply disruptions.
There were also many discussions about disputes related to payments. Because of the market uncertainty, cost overruns, and cash flow challenges, it was expected that owners, contractors, and subcontractors will experience financial hardships. Therefore, the parties involved may struggle with making timely payments and honoring the commitments if cash reserves are unavailable to them. In the context of contractors and subcontractors, one of the participants mentioned that the biggest challenge is going to be cash flow issues. More specifically, the participant shared that contractors and subcontractors will need to pay suppliers after the material is delivered; however, they will receive their payment only once the material is incorporated in the facility under construction. Therefore, contractors and subcontractors were particularly expected to experience cash flow-related challenges and claims.
Regardless of the conflicts and disputes experienced in the current pandemic, several participants mentioned that the pandemic has prompted industry stakeholders to take a closer look at the contractual documents and examine clauses that offer relief in uncertain circumstances. Additional information on some of the risk management efforts planned in the industry is presented in
Section 3.3.2.
3.1.9. Workforce-Related Challenges
The participants shared considerable information about workforce-related challenges. Most participants shared that a large number of furloughs and layoffs are being initiated as the workloads in the construction industry are projected to decrease substantially. In fact, one of the project engineers mentioned that the projected workload reduction will range between 50% and 60% compared to the previous years. In addition, several participants mentioned that contractors and subcontractors are experiencing significant challenges with cash flow and that these furloughs and layoffs are necessary, as these businesses will not be able to make the payroll. Moreover, several participants mentioned that there is much uncertainty in the future and that the demand for craft workers remains unclear given the early stages of the pandemic. Apart from craft workers, project engineers, estimators, administrative employees, and others were also considered likely to be impacted by furloughs and layoffs.
A significant challenge reported by some of the participants was the long-term effects of the pandemic on the construction workforce. For example, several project managers and supervisors alluded to the economic downturn that was previously experienced during the Great Recession when a large number of construction workers abandoned the construction industry to join other industries. These participants mentioned that these workers never returned to the construction industry following the recovery and that this has resulted in a large deficit in the number of skilled workers in the industry. The participants were worried that the current pandemic will further aggravate the situation if the laid-off workers choose to transition to other industries and not return.
Another problem that was discussed was the mental health challenges that workers experience in these uncertain times. For example, a few participants mentioned that a significant portion of the workforce are worried about their future prospects in the industry and the possibility that they may be laid off or furloughed. One participant mentioned that these workers have their own financial obligation, a family to care for, and rent and housing payments to make—which are all significant stressors for the workers. Some others, as discussed earlier, mentioned that workers are anxious that they may be exposed to the virus in the workplace and that many of the safety measures are not realistic to adopt or are not sufficiently enforced in construction workplaces. In addition, as discussed earlier, a supervisor mentioned that workers are often unable to report to work due to childcare unavailability, closure of schools, and caretaking responsibilities for sick family members, and these stressors impact their mental health.
One of the project managers mentioned that the social distancing requirement is also resulting in limited interactions among crewmembers, which may also contribute to mental health challenges. The project manager added that he had come across the term physical distancing, which must replace the use of the term social distancing. The participant believed that such a change would better communicate the intent of the social distancing safety measure and argued that complementary efforts must be adopted to build comradeship between workers during this difficult time.
3.1.10. Increase in Demand from Local Suppliers and Manufacturers
Given that there were significant delays with material delivery, particularly from overseas and across the country, many workplaces began to proactively adopt measures to find alternative material sources to reduce the risk of project delays. Preference was given to alternate local suppliers and manufacturers where the likelihood of delivery on short notice was higher. In many cases, contractors, in consultation with the architects and the designers, were able to identify alternate material and equipment that local suppliers and manufacturers were able to quickly ship. Therefore, these local suppliers experienced a significant spike in demand. More specifically, according to one of the suppliers, their sales substantially increased when compared to previous years. There was also additional demand from local suppliers for supplies such as disinfecting wipes, cleaning supplies, sanitizers and sanitizer stations, and acrylic glass (e.g., Plexiglas) that were necessary as safety measures during the pandemic for offices, retail spaces, and educational institutes.
In addition, because of the stay-at-home orders, a supplier mentioned that a larger proportion of the public began new home improvement and renovation projects. Therefore, there was an increase in demand for material for these small-scale projects. However, the supplier also mentioned that they were running low on stocks since they had not anticipated or planned for a surge in the demand. Moreover, these local suppliers were also unable to receive shipments of the raw material that they needed from outside sources to meet the local demand.
3.1.11. Transition to Work from Home for Non-Site Personnel
In response to the pandemic and to enhance safety, a significant number of non-site professionals were able to transition to working from home. However, several participants mentioned that they experienced a significant number of challenges. For example, businesses did not have the necessary digital infrastructure to make the transition easy in many cases. Therefore, there were significant challenges with gaining access to necessary software packages and other resources, which resulted in much inefficiency. In many cases, the businesses needed to make additional investments into technology to enhance their ability to efficiently work from home. For example, several businesses invested in virtual private networks (VPNs) to gain access to resources and software packages such as computer-aided design (CAD) remotely. Few organizations mentioned that they already had cloud solutions to access licensed software packages and business databases—which made the transition relatively easy.
In several other cases, the participants mentioned that there were additional challenges with making the transition because much of the workforce was not familiar with the newly adopted digital solutions. For example, certain individuals were not familiar with using virtual private networks (VPNs) to connect remotely to the business network. Others experienced challenges with adopting new communication platforms such as Zoom, Microsoft Teams, and Slack. Some employees also found it challenging to connect their business computers to their home network for a variety of reasons. Few participants also mentioned Internet outages and poor Internet quality as major challenges associated with remote working.
Apart from technology-related challenges, a few participants mentioned that there were more distractions at home that interfered with their ability to work effectively. In addition, many of the employees also had additional duties at home such as taking care of their children, given that schools were online and childcare services were not operational.
Because of the many challenges that employees experienced with technology and working from home, a few organizations decided to ask their employees to return to the office after providing safety measures such as acrylic (e.g., Plexiglas) panels between desks, sanitation stations, and sufficient spacing between workspaces.
3.2. New Opportunities as a Result of the COVID-19 Pandemic
3.2.1. Ability to Secure Loans at Low Interest Rates
The participants shared that one of the largest opportunities comes from the low interest rates that are available to owners, contractors, and potential home buyers. For example, one of the project managers indicated that they just secured a new project involving the construction of a hotel as the owner was able to secure a loan with a much lower interest rate than usual. The project manager also mentioned that such low interest rates are rare and that this offers a good opportunity for strong businesses to grow and be prepared to take advantage of the markets when the recovery begins. There were also participants that discussed the availability of the small business loan program, commonly known as PPP loans—the Paycheck Protection Program (PPP)—that small contractors were leveraging to ensure that their employers were paid and that their workforce successfully weathered the ongoing pandemic. According to the U.S. Small Business Administration (SBA), the first draw of PPP loans had an interest rate of 1% [
24].
The participants also mentioned that the demand for new residential construction is likely to increase because potential buyers can secure a low interest rate for the life of the mortgage, which can go up to 30 years. One of the participants mentioned that a few families are expected to spend more on residential expansion projects by leveraging the low interest rates as they will spend more time in their homes, which will benefit small contractors. Furthermore, a few participants mentioned that potential home buyers are moving from rented properties in cities to the suburbs, where they can purchase larger and more spacious homes using the low interest rates; which will also increase sales in the residential sector.
3.2.2. Demand Increase for Transportation, Residential, Fast-Track Medical, and Other Projects
A large number of participants shared that the demand for a variety of construction projects has increased. For example, one of the project managers stated that Departments of Transportation (DOTs) are approving new projects and accelerating ongoing ones to take advantage of the lower traffic volumes following the shelter-in-place orders. The project manager added that this is a rare opportunity to work on infrastructure and highway projects, particularly in urban areas, where high traffic is typically a major concern and can result in much inconvenience and delays to drivers. In fact, one of the contractors from Texas reported that the limited volume of traffic has offered more lane closure opportunities and has allowed for the acceleration of projects. Another project engineer reported that the pandemic has enhanced the safety and productivity of workers as the traffic flow has reduced. Another manager mentioned that the pandemic has offered an opportunity to safely work on infrastructure projects that have been neglected for decades.
In terms of residential projects, apart from the additional demand following the reduction in mortgage and interest rates, demand for new construction was expected to increase as the inventory of homes in the market was expected to reduce. This was because fewer owners of existing homes were expected to list their homes for sale and allow public access to their properties during a pandemic. The shortage of inventory was expected to increase the sale of new homes.
Apart from transportation and residential projects, given the medical emergency that was being experienced due to the pandemic, the participants believed that more fast-track medical and patient care facilities will be built and renovated. Additional construction projects were also expected for building new research centers and medical labs to counter future medical emergencies.
In the commercial sector, many participants believed that there will be an increase in the construction of warehouses and storage units to support the substantial increase in online shopping. The participants mentioned that many retail spaces are also likely to be renovated as new warehouses as the demand for retail space reduces. The demand was further expected to increase as a growing number of businesses were expected to transition into the online shopping space.
Other projects that were expected to increase as a result of the pandemic included renovation work in universities and schools as students were away from campus, office renovations in preparation for employees to return and work safely during a pandemic, utility work as the number of Internet subscribers increased and traffic flow reduced, and renovation of public buildings such as museums and public offices with the decline in the number of visitors.
3.2.3. Recruitment of Skilled Workers
As discussed above, a large number of furloughs and layoffs were expected, not only from the construction industry but also from other industries including retail, manufacturing, and airlines. While this was an adverse outcome for many organizations and workers, a few participants believed that their organizations benefitted from the situation. More specifically, these participants stated that while the industry in the past suffered from a shortage of skilled workers, suddenly, there was a surplus of skilled workers looking for positions in the market. A project manager mentioned that their organization was able to recruit a number of skilled and experienced electricians that were typically difficult to come across in the industry. The project manager mentioned that well-established and financially strong contractors will particularly benefit from their ability to hire a strong workforce.
3.2.4. Conducting Internal Reviews and Improving Existing Systems
With the reduction in the workload experienced in the construction industry and fewer new opportunities, many construction businesses resolved to perform comprehensive evaluations of their processes and systems to identify areas for improvement. According to several participants, their construction businesses began to examine their strategic vision, partnerships, their execution plans, their bidding approach, risk assessment approach, material planning protocol, software resources, and others to identify inefficiencies and strategic efforts that can be adopted to enhance success. According to one participant, these businesses focused on coming out stronger at the end of the pandemic and ready to thrive in a post-pandemic market with improved processes and systems.
Several organizations focused on performing maintenance operations for their construction equipment and tools. Two project managers mentioned that their organizations are examining the prospect of switching a larger number of positions to work-from-home positions. These managers argued that such a change can allow them to transition to a smaller office while reducing overhead costs and improving flexibility. Several businesses resolved to improve their technological infrastructure to better facilitate collaborations between suppliers, subcontractors, and other partners. One of the participants shared that their organization was in the last stages of proposing a new organizational structure to enhance communication channels and accountability.
3.3. Efforts to Manage the Challenges of the COVID-19 Pandemic
3.3.1. New Safety Measures Adopted in the Construction Industry
The participants reported a number of safety measures that were being adopted, along with their implementation challenges. Among others, the use of cloth face coverings was enforced widely in construction workplaces. However, in many cases, there were significant shortages in the availability of face coverings in the market and workplaces. Moreover, workers often forgot to bring their face coverings to work when they returned the next day, which further aggravated the shortage of face masks and coverings in many cases.
Even when face coverings were available, several supervisors reported that it was challenging to enforce the requirements in workplaces. For example, several workers often removed the face coverings due to discomfort and fogging of safety glasses. Workers also often complained of their discomfort with the masks, especially when performing strenuous tasks that were associated with a higher breathing rate and perspiration. Workers also expressed discomfort when working in humid conditions with their face coverings. In many other cases, workers often covered their mouths but did not cover their noses, which limits the effectiveness of cloth face coverings. Another supervisor mentioned that even when workers placed the mask correctly over their nose and the mouth, it often would not stay in place and would fall below the nose as they worked. Another significant challenge was that workers often reused face coverings without rewashing them. However, this was unrealistic to monitor according to one of the supervisors.
Workers and employees were also given instructions to follow social distancing guidelines. In addition to promoting social distancing efforts, several other approaches were adopted to support social distancing among site personnel. These included staggering work crews such that different work crews reported to work at different times to limit the number of workers in the workplace at the same time, posting signage to remind workers of the requirements of social distancing, preventing food trucks from coming into the site that typically encouraged crowding, limiting the number of workers in the breakroom, setting up open public break and lunch spaces, closing the site trailer, use of social distancing floor markers placed 6 ft. apart, encouraging non-essential workers to work from home, asking supervisors to work from their trucks or vehicles, reducing and postponing work in confined spaces, and others. While these efforts were all useful, some participants mentioned that it was unrealistic to maintain the 6 ft. requirement between each of the workers at all times due to the collaborative nature of construction operations, where workers are required to work alongside each other. Moreover, like monitoring the usage of face covering, it was unrealistic for site personnel to monitor that workers always followed social distancing guidelines as work progressed.
One of the supervisors mentioned that when workers used face coverings, many believed that the 6 ft. social distancing requirement no longer applied, as the face covering offered sufficient protection. The supervisor mentioned that this belief is untrue and the recommended practice is to adopt multiple safety measures to limit the likelihood of virus spread. In a number of instances, the supervisor mentioned that safety professionals must intervene were when such behaviors are observed.
Another widely adopted safety measure was offering workers and site personnel training on the safety risks of COVID-19 and the safety measures that are to be adopted. The biggest challenge of delivering these training sessions was that the traditional classroom-type training approaches were no longer safe given the social distancing guidelines. Therefore, new training approaches that comply with the social distancing requirements were necessary. Some of the employers tried to adopt online training sessions. However, technology constraints were a significant issue because workers often did not have access to compatible computers and phones. Computer literacy and access to a good Internet connection were also a challenge in many cases. In several other cases, the contractors and the subcontractors did not have the infrastructure necessary to deliver training programs online given the unexpected demand for online training. Therefore, in some cases, training was offered over conference phone calls. However, trainers struggled with this format of training since the conversations were largely one-sided, with little to no participation from the training participants. In many cases, according to a participant, it was not clear if the workers were actually paying attention to or benefiting from the training. Moreover, the inability to see the facial expressions of the training participants was a challenge for trainers as they were unable to see the facial expressions as would be the case in a classroom-type training setting. To overcome all of these challenges, some of the employers offered the training in open spaces in the workplace while also complying with the social distancing requirements.
Other safety measures that were adopted without much challenge were administering temperature checks prior to entry into the workplace, the placement of sanitizers and hand wash stations at the entrance and various locations in the worksite, disinfecting tools and surfaces, discouraging sharing of tools and equipment, including PPE, encouraging workers with any COVID-19-like symptoms to remain at home, adopting air purification and filtration systems, and others. One concern that was reported by a supervisor regarding the temperature checks was the concern regarding the accuracy of these checks. More specifically, the supervisor was concerned that the temperature checks may be impacted by ambient temperature and environmental conditions if testing was performed in a non-controlled location (e.g., open space at the entrance to the workplace).
3.3.2. Managing Other Project Risks
Given the rapid change in governmental policies during the pandemic, several participants reported that their businesses maintained a task force or team of qualified employees or consultants who were tasked with examining proposed governmental policies and industry patterns to identify best practices for risk management. In many cases, such a task force or team was also delegated the responsibility of identifying and adopting safety measures that were recommended for the safe operation of construction workplaces. The taskforce continuously updated operational plans and offered guidance to the site leadership on managing work in construction workplaces. In one of the projects, while they did not have the resources to support a task force, one of the project managers examined the lessons learned database and past claims to identify possible solutions that were proposed in the past that may apply in the current crisis.
Much of the input that participants shared was related to managing delays on their projects, which appeared to be the largest risk apart from the safety concerns being experienced. Some participants mentioned that delays on their projects were inevitable and only the impacts of the delay can be minimized. Others mentioned that they were reviewing their original schedules to make modifications that may be helpful in reducing delays. For example, some participants mentioned that they were considering the adoption of night and weekend shifts. One of the project managers mentioned that the introduction of additional shifts would also be helpful given that one of their subcontractors was not willing to share the workplace with other trades because of the safety risks during the pandemic. Several other participants mentioned the work of several advocacy groups, trade unions, and associations such as the Associated General Contractors (AGC) of America, North America’s Building Trades Unions (NABTU), and the American Subcontractors Association (ASA) that were urging governmental agencies to render construction activities as being essential for recovery and offering exemption from shelter-in-place orders. According to these participants, if these efforts are successful, significant delays and associated hardships will be alleviated.
Another area that was highlighted was efforts to reduce the impacts of material delivery delays and related challenges. One of the participants mentioned that some businesses that were proactively monitoring the evolving pandemic were able to place material delivery requests prior to when deliveries became more challenging and shortages of supplies were experienced in the market. Some other subcontractors were able to resolve these issues by finding alternate vendors and local suppliers that were able to deliver material on time. Several other contractors were examining their project schedule to identify material that was needed throughout the project cycle and actively contacted vendors to ensure that they will be able to make deliveries as planned. Nonetheless, several workplaces were unable to find alternate approaches to have the materials delivered as per initial plans—particularly when customized products and fabricated elements were necessary.
As projects were experiencing delays and price escalations, several participants mentioned that they began reviewing the contracts to assess expected impacts and provisions that they can use in their defense. Several participants mentioned that they were keeping detailed records of the causes of the delays and price increases with the hope of requesting additional time and compensation. Such records were also expected to be useful to manage the risk of liquidated damages and delay-related penalties. Several of the participants also mentioned that such records will be useful for their defense if disputes or ligations occur on their projects. Apart from these efforts, few project managers mentioned that they were working on notices that were planned to be sent to project owners, alerting them of expected delays and cost escalations.
One of the other major risks that was expected was cash flow issues as a result of price escalations and delayed payments. Several participants mentioned that businesses were taking advantage of various governmental programs and relief plans to alleviate some of the challenges. These included new loans and economic relief plans that were becoming available for small businesses such as the PPP. One of the supervisors mentioned that an employer planned to use these programs to pay their workforce and ensure that they maintain their trained employees and skilled workers despite the pandemic. The supervisor mentioned that this was important for the long-term success of the business, as the construction industry has struggled with labor shortage issues. One of the participants mentioned that their organization maintained a generous contingency and emergency account which will be used to address the experienced cash flow challenges.