Techno-Economic Optimization of an Off-Grid Hybrid Power Generation for SRM IST, Delhi-NCR Campus
Abstract
:1. Introduction
2. Weather Conditions and Load Estimation of the Selected Site
3. Software for Optimization of HPGP
4. Components of HPGP
4.1. Solar PV System
4.2. Energy Storage System—Li-Ion Batteries
4.3. Backup System—Diesel Generator
4.4. Converter
5. Evaluation of Performance and Economic Analysis of HPGP
5.1. Performance Index of SPV System
5.1.1. AC Energy Output, EAC
5.1.2. Array Yield, Yarr
5.1.3. Reference Yield, Yref
5.1.4. Final Yield, Yfin
5.1.5. Performance Ratio, PR
5.1.6. Capacity Factor, CF
5.1.7. Array Capture Loss, Lcap
5.1.8. System Loss, Lsys
5.2. Economic Analysis of HPGP
6. Results and Discussion
6.1. Evaluation of Performance Index
- GHI ranged from 3.52 to 6.42 kWh/m2/day, with an average of 5.05 kWh/m2/day (refer to Figure 8).
- The average DNI was5.78 kWh/m2/day (refer to Figure 8).
- The average DHI was1.65 kWh/m2/day (refer to Figure 8).
- The average CI of the selected site was 0.58 (refer to Figure 7).
- The ratio of direct and diffuse radiation varied between 1.62 and 7.09 (refer to Figure 9).
- The performance index varied as follows (refer to Table 7):
- Yarr between 3.27 and 4.77 per month
- Yref between 4.61 and 6.68 per month
- Yfin between 2.94 and 4.29 per month
- Lcap between 1.30 and 1.92 per month
- Lsys between 0.33 and 0.48 per month
- The average cell temperature ranged from 20.72 to 42.46 °C, and the ambient temperature varied between 13.93 and 35.83 °C (refer to Figure 13).
- Average PR and CF varied between 61.41% and 68.06% and 12.26% and 17.89%, respectively (refer to Table 7).
6.2. Evaluation of Economic Analysis
6.2.1. Technical and Economic Analysis of PV/BSS Configuration
- From 0 to 6th h—during this time, the demand for electricity was zero or minimum. The energy stored in BSS served the load.
- From 6th to 17th h—as the sunlight was available from the 6th h, the SPV system started generating electricity. Now, the SPV system and BSS served the load as the demand for electricity rose during this duration.
- From 17th to 23rd h—in this duration, the demand for electricity dropped, so it was served by BSS. Additionally, during evening and night hours the SPV system cannot generate electricity.
6.2.2. Sensitivity Analysis
6.3. Environmental Impact Assessment
7. Comparison of Proposed HPGP with the Reference Case
- (i)
- The reference case provided an LCOE of $0.93 per kWh, while the proposed configuration provided $0.34 per kWh. This difference is mainly due to the cost of diesel used fuel to generate electricity in the reference case. It is estimated that diesel consumption in the reference case will be $87,284 per year. The diesel cost has a direct impact on LCOE.
- (ii)
- Initial capital investment in the reference case was $54,530, which is low compared with the selected configuration of HPGP ($470,385).
- (iii)
- It was estimated that the reference case will have high NPC ($1,747,678) and a high operating cost ($130,972) as compared with the selected configuration of HPGP (NPC will be $639,981 and the operating cost will be $13,119).
- (iv)
- The O&M cost of the reference case ($250,725) is high compared with the selected configuration of HPGP (24,495).
8. Conclusions
- (i)
- In this paper, a stand-alone HPGP was commissioned for a part of an academic building. The optimal configuration of this stand-alone HPGP is PV(509 kW)/BSS(383 kWh). BSS is required to fulfill the electricity demand either in peak hours or when the SPV system is not able to meet the load demand.
- (ii)
- In this paper, the performance and feasibility of SPV system was analyzed. The performance ratio was 64.49% and the capacity factor was 14.90%. The performance ratio is basically the proportion of the energy available for export to the grid. This value is less than 100% because of energy loss and energy consumption during operation. The energy loss can be due to thermal losses and conduction losses. This means that 64.49% is available for export to grid and the rest is lost in energy loss and energy consumption. CF measures the amount of energy is produced by solar plant in comparison to its maximum output. CF is low in SPV systems due to the intermittent nature of solar energy.
- (iii)
- The meteorological data were taken from the NASA PDAV tool. These data helped to perform the above-mentioned calculations.
- (iv)
- The techno-economic analysis was conducted using HOMER. The initial investment was estimated to be $470,385, while NPC was $639,981. The LCOE was estimated as $0.34 per kWh.
- (v)
- The commissioning of the SPV system will also lead to zero emissions of air pollutants.
Author Contributions
Funding
Conflicts of Interest
References
- Power Sector at a Glance ALL INDIA|Government of India|Ministry of Power. Available online: powermin.gov.in (accessed on 12 October 2021).
- Majority of New Renewables Undercut Cheapest Fossil Fuel on Cost. Available online: https://irena.org/ (accessed on 10 August 2021).
- Aryanpur, A.; Atabaki, M.S.; Marzband, M.; Siano, P.; Ghayoumi, K. An overview of energy planning in Iran and transition pathways towards sustainable electricity supply sector. Renew. Sustain. Energy Rev. 2019, 112, 58–74. [Google Scholar] [CrossRef]
- Ahmadi, A.; Ehyaei, M.A.; Doustgani, A.; Assad, M.e.; Hmida, A.; Jamali, D.H.; Kumar, R.; Li, Z.X.; Razmjoo, A. Recent residential applications of low-temperature solar collector. J. Clean. Prod. 2021, 279, 123549. [Google Scholar] [CrossRef]
- Kreishan, M.Z.; Fotis, G.; Vita, V.; Ekonomou, L. Distributed generation islanding effect on distribution networks and end user loads using the load sharing islanding method. Energies 2016, 9, 956. [Google Scholar] [CrossRef]
- Zafeiropoulou, M.; Mentis, I.; Sijakovic, N.; Terzic, A.; Fotis, G.; Maris, T.I.; Vita, V.; Zoulias, E.; Ristic, V.; Ekonomou, L. Forecasting transmission and distribution system flexibility needs for severe weather condition resilience and outage management. Appl. Sci. 2022, 12, 7334. [Google Scholar] [CrossRef]
- National Portal of India. Available online: https://www.india.gov.in/india-glance/profile (accessed on 17 October 2022).
- Kumar, P.; Sharma, H.; Pal, N.; Sadhu, P.K. Comparative assessment and obstacles in the advancement of renewable energy in India and China. Probl. Ekorozw. 2019, 14, 191–200. [Google Scholar]
- Kumar, R.S.; Raghav, L.P.; Raju, D.K.; Singh, A.R. Customer-oriented energy demand management of grid connected microgrids. Int. J. Energy Res. 2021, 45, 18695–18712. [Google Scholar] [CrossRef]
- Behura, A.K.; Kumar, A.; Rajak, D.K.; Pruncu, C.I.; Lamberti, L. Towards better performances for a novel rooftop solar PV system. Sol. Energy 2021, 216, 518–529. [Google Scholar] [CrossRef]
- Kumar, P.; Pal, N.; Sharma, H. Techno-economic analysis of solar photovoltaic/diesel generator hybrid system using different energy storage technologies for isolated islands of India. J. Energy Storage 2021, 41, 102965. [Google Scholar] [CrossRef]
- Ekonomou, L.; Fotis, G.; Vita, V.; Mladenov, V. Distributed generation islanding effect on distribution networks and end user loads using the master-slave islanding method. J. Power Energy Eng. 2016, 4, 1–24. [Google Scholar] [CrossRef]
- Sambhi, S.; Sambhi, S.; Bhadoria, V.S. IoT based optimized and secured ecosystem for energy internet: The state of the art. In Internet of Things in Business Transformation: Developing an Engineering and Business Strategy for Industry 5.0; Scrivener Publishing LLC: Beverly, MA, USA, 2021; pp. 91–126. [Google Scholar] [CrossRef]
- Praveenkumar, S.; Agyekum, E.B.; Ampah, J.D.; Afrane, S.; Velkin, V.I.; Mehmood, U.; Awosusi, A.A. Techno-economic optimization of PV system for hydrogen production and electric vehicle charging stations under five different climatic conditions in India. Int. J. Hydrog. Energy 2022, in press. [Google Scholar] [CrossRef]
- Vidinopoulos, A.; Whale, J.; Hutfilter, U.F. Assessing the technical potential of ASEAN countries to achieve 100% renewable energy supply. Sustain. Energy Technol. Assess. 2020, 42, 100878. [Google Scholar] [CrossRef]
- William, M.A.; Suárez-López, M.J.; Soutullo, S.; Hanafy, A.A. Building envelopes toward energy-efficient buildings: A balanced multi-approach decision making. Int. J. Energy Res. 2021, 45, 21096–21113. [Google Scholar] [CrossRef]
- Rout, A.; Mainali, B.; Singh, S.; Solanki, C.S.; Bhati, G.S. Assessing the financial sustainability of rural grid electrification pathway: A case study of India. Sustain. Prod. Consum. 2021, 25, 27–42. [Google Scholar] [CrossRef]
- Eshraghi, A.; Salehi, G.; Heibati, S.; Lari, K. An assessment of the effect of different energy storage technologies on solar power generators for different power sale scenarios: The case of Iran. Sustain. Energy Technol. Assess. 2019, 34, 62–67. [Google Scholar] [CrossRef]
- Jawaharlal Nehru National Solar Mission (Phase I, II and III). Available online: https://www.iea.org/policies/4916-jawaharlal-nehru-national-solar-mission-phase-i-ii-and-iii (accessed on 15 September 2021).
- The Paris Agreement. Available online: https://unfccc.int/process-and-meetings/the-paris-agreement/the-paris-agreement (accessed on 15 September 2021).
- What Is Kyoto Protocol? Available online: https://unfccc.int/kyoto_protocol (accessed on 29 September 2021).
- International Solar Alliance. Available online: https://isolaralliance.org/ (accessed on 29 September 2021).
- With 2,245 MW of Commissioned Solar Projects, World’s Largest Solar Park Is Now at Bhadla. Available online: https://mercomindia.com/world-largest-solar-park-bhadla/ (accessed on 12 October 2022).
- India’s Utility-Scale Solar Parks a Global Success Story. Available online: https://ieefa.org/wp-content/uploads/2020/05/Indias-Utility-Scale-Solar-Parks-Success-Story_May-2020.pdf (accessed on 15 September 2021).
- PM Modi to Inaugurate 30-GW Renewable Energy Park at Kutch. Available online: https://www.thehindubusinessline.com/news/national/pm-modi-to-inaugurate-30-gw-renewable-energy-park-at-kutch/article33241348.ece (accessed on 15 September 2021).
- Solar Policy. Available online: http://ipgcl-ppcl.gov.in/renewable.htm (accessed on 12 October 2022).
- Why Despite Touching 1 Degree Celsius in Delhi, Mercury Won’t Touch Zero-Mark. Available online: https://www.indiatoday.in/cities/delhi/story/delhi-sees-record-winter-temperature-drop-imd-1759412-2021-01-15 (accessed on 16 October 2022).
- Google Maps. Available online: https://maps.google.com (accessed on 10 February 2021).
- NASA Power—Data Access Viewer. Available online: https://power.larc.nasa.gov/data-access-viewer/ (accessed on 10 February 2021).
- HOMER Software. Available online: https://www.homerenergy.com (accessed on 20 February 2021).
- Solar Resource Glossary. Available online: https://www.nrel.gov/grid/solar-resource/solar-glossary.html (accessed on 20 February 2021).
- Direct Solar Irradiation. Available online: https://www.sciencedirect.com/topics/engineering/direct-normal-irradiation (accessed on 20 February 2021).
- Solar Azimuth Angle. Available online: https://www.sciencedirect.com/topics/engineering/solar-azimuth-angle (accessed on 20 February 2021).
- HOMER Pro 3.15. Available online: https://www.homerenergy.com/products/pro/docs/latest/index.html (accessed on 15 March 2021).
- Yan, P.; Zhu, Y.; Pan, X.; Ji, H. A novel flame-retardant electrolyte additive for safer lithium-ion batteries. Int. J. Energy Res. 2021, 45, 2776–2784. [Google Scholar] [CrossRef]
- Performance Index. Available online: https://pvpmc.sandia.gov/modeling-steps/5-ac-system-output/pv-performance-metrics/performance-index/ (accessed on 27 March 2021).
- Techno-Economic Analysis. Available online: https://www.nrel.gov/analysis/techno-economic.html (accessed on 30 March 2021).
- NREL—Monotoring System Performance. Available online: https://www.nrel.gov/docs/fy11osti/50643.pdf (accessed on 20 March 2021).
- Kumar, P.; Pal, N.; Sharma, H. Performance analysis and evaluation of 10 kWp solar photovoltaic array for remote islands of Andaman and Nicobar. Sustain. Energy Technol. Assess. 2020, 42, 100889. [Google Scholar] [CrossRef]
- Percis, E.S.; Nalini, A.; Jenish, T.N.; Jayarajan, J.; Bhuvaneswari, S.; Rama, S.T. Design of a self-sustained hybrid renewable energy microgrid for rural electrification of dry lands. Int. J. Energy Res. 2021, 45, 8316–8326. [Google Scholar] [CrossRef]
- Sijakovic, N.; Terzic, A.; Fotis, G.; Mentis, I.; Zafeiropoulou, M.; Maris, T.I.; Zoulias, E.; Elias, C.; Ristic, V.; Vita, V. Active System Management Approach for Flexibility Services to the Greek Transmission and Distribution System. Energies 2022, 15, 6134. [Google Scholar] [CrossRef]
- Kumar, S.P.; Agyekum, E.B.; Qasim, M.A.; Alwan, N.T.; Velkin, V.I.; Shcheklein, S.E. Experimental assessment of thermoelectric cooling on the efficiency of PV module. Int. J. Renew. Energy Res. IJRER 2022, 12, 13087. [Google Scholar] [CrossRef]
- Praveenkumar, S.; Gulakhmadov, A.; Agyekum, E.B.; Alwan, N.T.; Velkin, V.I.; Sharipov, P.; Safaraliev, M.; Chen, X. experimental study on performance enhancement of a photovoltaic module incorporated with CPU heat pipe—A 5E analysis. Sensors 2022, 22, 6367. [Google Scholar] [CrossRef]
- Chabachi, S.; Necaibia, A.; Abdelkhalek, O.; Bourajou, A.; Ziane, A.; Hamouda, M. Performance analysis of an experimental and simulated grid connected photovoltaic system in southwest Algeria. Int. J. Energy Environ. Eng. 2022, 13, 831–851. [Google Scholar] [CrossRef]
- Bhakta, S.; Mukherjee, V. Solar potential assessment and performance indices analysis of photovoltaic generator for isolated Lakshadweep Island of India. Sustain. Energy Technol. Assess. 2016, 17, 1–10. [Google Scholar] [CrossRef]
- Al-Badi, A. Performance assessment of 20.4 kW eco-house grid-connected PV plant in Oman. Int. J. Sustain. Eng. 2020, 13, 230–241. [Google Scholar] [CrossRef]
- Mudgil, K.; Yadav, R.K.; Tiwari, G.N. Performance evaluation of 12 kWP rooftop grid-connected photovoltaic plant installed under net metering in Delhi, India. Int. J. Ambient. Energy 2022, 43, 788–794. [Google Scholar] [CrossRef]
- Mondol, J.D.; Yohanis, Y.; Smyth, M.; Norton, B. Long term performance analysis of a grid connected photovoltaic system in Northern Ireland. Energy Convers. Manag. 2006, 47, 2925–2947. [Google Scholar] [CrossRef]
- Baghel, N.S.; Chander, N. Performance comparison of mono and polycrystalline silicon solar photovoltaic modules under tropical wet and dry climatic conditions in East-Central India. Clean Energy 2022, 6, 165–177. [Google Scholar] [CrossRef]
- Cheruiyot, W.K.; Tonui, J.K.; Limo, S.C. Performance evaluation of 780 Wp rooftop solar PV power backup system in Western Kenya. J. Energy Res. Rev. 2021, 8, 1–9. [Google Scholar] [CrossRef]
- Boddapati, V.; Nandikatti, A.S.R.; Daniel, S.A. Techno-economic performance assessment and the effect of power evacuation curtailment of a 50 MWp grid-interactive solar power park. Energy Sustain. Dev. 2021, 62, 16–28. [Google Scholar] [CrossRef]
- Saxena, A.K.; Saxena, S.; Sudhakar, K. Energy performance and loss analysis of 100 kWp grid-connected rooftop solar photovoltaic system. Build. Serv. Eng. Res. Technol. 2021, 42, 485–500. [Google Scholar] [CrossRef]
- Kymakis, E.; Kalykakis, S.; Papazoglou, T.M. Performance analysis of a grid connected photovoltaic park on the island of Crete. Energy Convers. Manag. 2009, 50, 433–438. [Google Scholar] [CrossRef]
- Falih, H.; Hamed, A.J.; Khalifa, A.H.N. Techno-economic assessment of a hybrid connected PV solar system. Int. J. Air-Cond. Refrig. 2022, 30, 3. [Google Scholar] [CrossRef]
- Oloya, I.T.; Gutu, T.J.L.; Adaramola, M.S. Techno-economic assessment of 10 MW centralised grid-tied solar photovoltaic system in Uganda. Case Stud. Therm. Eng. 2021, 25, 100928. [Google Scholar] [CrossRef]
- Attari, K.; Elyaakoubi, A.; Asselman, A. Performance analysis and investigation of a grid-connected photovoltaic installation in Morocco. Energy Rep. 2016, 2, 261–266. [Google Scholar] [CrossRef]
- De Miguel, A.; Bilbao, J.; Cazorro, J.R.; Martin, C. Performance analysis of a grid connected PV system in a rural site in the Northwest of Spain. In Proceedings of the World Renewable Energy Congress VII, Cologne, Germany, 29 June–5 July 2002. [Google Scholar]
- Praveenkumar, S.; Agyekum, E.B.; Kumar, A.; Ampah, J.D.; Afrane, S.; Amjad, F.; Velkin, V.I. Techno-economics and the identification of environmental barriers to the development of concentrated solar thermal power plants in India. Appl. Sci. 2022, 12, 400. [Google Scholar] [CrossRef]
- Chimtavee, A.; Ketjoy, N.; Sriprapha, K.; Vaivudh, S. Evaluation of PV generator performance and energy supplied fraction of the 120 kWp PV microgrid system in Thailand. Energy Procedia 2011, 9, 117–127. [Google Scholar] [CrossRef]
- Kumar, A.; Singh, A.R.; Deng, Y.; He, X.; Kumar, P.; Bansal, R.C. Integrated assessment of a sustainable microgrid for a remote village in hilly region. Energy Convers. Manag. 2019, 180, 442–472. [Google Scholar] [CrossRef]
- Wu, T.; Zhang, H.; Shang, L. Optimal sizing of a grid-connected hybrid renewable energy systems considering hydroelectric storage. Energy Sources Part A: Recovery Util. Environ. Eff. 2020, 1–17. [Google Scholar] [CrossRef]
- Leithon, J.; Werner, S.; Koivunen, V. Cost-aware renewable energy management: Centralized vs. distributed generation. Renew. Energy 2020, 147, 1164e1179. [Google Scholar] [CrossRef]
- Gebrehiwot, K.; Mondal, A.H.; Ringler, C.; Gebremeskel, A.G. Optimization and cost-benefit assessment of hybrid power systems for off-grid rural electrification in Ethiopia. Energy 2019, 177, 234e246. [Google Scholar] [CrossRef]
- Sherwani, A.F.; Asjad, M.; Haleem, A. Performance evaluation of solar photovoltaic electricity-generating systems: An Indian perspective. Int. J. Sustain. Eng. 2019, 12, 70–75. [Google Scholar] [CrossRef]
- Razmjoo, A.; Kaigutha, L.G.; Rad, M.A.V.; Marzband, M.; Davarpanah, A.; Denai, M. A Technical analysis investigating energy sustainability utilizing reliable renewable energy sources to reduce CO2 emissions in a high potential area. Renew. Energy 2021, 164, 46e57. [Google Scholar] [CrossRef]
- Li, J.; Liu, P.; Li, Z. Optimal design and techno-economic analysis of a solar-wind-biomass off-grid hybrid power system for remote rural electrification: A case study of west China. Energy 2020, 208, 118387. [Google Scholar] [CrossRef]
- Zhang, G.; Xiao, C.; Razmjooy, N. Optimal operational strategy of hybrid PV/wind renewable energy system using Homer: A case study. Int. J. Ambient. Energy 2020, 43, 3953–3966. [Google Scholar] [CrossRef]
- Odou, O.D.T.; Bhandari, R.; Adamou, R. Hybrid off-grid renewable power system for sustainable rural electrification in Benin. Renew. Energy 2020, 145, 1266e1279. [Google Scholar] [CrossRef]
- Ramesh, M.; Saini, R.P. Dispatch strategies based performance analysis of a hybrid renewable energy system for a remote rural area in India. J. Clean. Prod. 2020, 259, 120697. [Google Scholar] [CrossRef]
- Das, S.; Ray, A.; De, S. Optimum combination of renewable resources to meet local power demand in distributed generation: A case study for a remote place of India. Energy 2020, 209, 118473. [Google Scholar] [CrossRef]
Sr. No. | Load | Power (Watts) | Quantity | Usage h | Total Load (Wh) |
---|---|---|---|---|---|
1 | LED light | 24 | 6 | 6 | 864 |
2 | Ceiling fans | 20 | 5 | 6 | 600 |
3 | Airconditioner (1.5 ton) | 1500 | 2 | 6 | 18,000 |
4 | LCD Projector | 280 | 1 | 6 | 1680 |
5 | PA system (microphone, speakers, etc.) | 800 | 1 | 6 | 4800 |
6 | Computer system | 100 | 1 | 6 | 600 |
7 | Mobile charging point | 3 | 2 | 6 | 36 |
The total load for one classroom | 26,580 Wh/day | ||||
The total load for 15 classrooms | 398.7 kWh/day | ||||
(~400 kWh/day) |
Description | Value |
---|---|
Type of panel | Flat plate |
Name (Abbreviation) | PV |
Rated capacity (kWp) | 1 |
Capital cost ($/kW) | 470 |
Replacement cost ($/kW) | 470 |
O&M cost ($/year) | 2.66 |
Lifetime (years) | 25 |
Derating factor (% assumed) | 80 |
Temperature coefficient (per °C) | −0.5 |
Nominal operating cell temperature (°C) | 47 |
Efficiency (%) | 0.13 |
Description | Value |
---|---|
Nominal voltage (V) | 6 |
Nominal capacity (kWh) | 1 |
Maximum charge current (A) | 167 |
Estimated throughput (kWh) | 3000 |
Capital cost ($/kWh) | 535 |
Replacement cost ($/kWh) | 465 |
Lifetime (years) | 10 |
Description | Value |
---|---|
Fuel | Diesel |
Capital cost ($/kW) | 665 |
Replacement cost ($/kW) | 535 |
O&M cost ($/h) | 0.027 |
Fuel price ($/L) | 1.14 |
Lifetime (hours) | 15,000 |
CO (g/L/fuel) | 16.5 |
Unburned HC (g/L fuel) | 0.72 |
Particulates (g/L fuel) | 0.1 |
Fuel sulfur to PM (%) | 2.2 |
NOX (g/L fuel) | 15.5 |
Component | Capital Investment (in $) | Replacement Cost (in $) | O&M Cost (in $/Year) | Life Span (in Years) |
---|---|---|---|---|
SPV array | 470 | 470 | 2.66 | 25 years |
Li-Ion Battery | 535 | 465 | 0 | 10 years |
Converter | 195 | 195 | 4 | 15 years |
Month | Monthly Mean Energy Produced, EDC (in kWh) | Monthly Mean Energy Produced, EAC (in kWh) |
---|---|---|
January | 2150.80 | 1935.72 |
February | 2315.85 | 2084.27 |
March | 2427.75 | 2184.97 |
April | 2239.98 | 2015.98 |
May | 2041.78 | 1837.61 |
June | 1875.17 | 1687.66 |
July | 1687.25 | 1518.52 |
August | 1664.27 | 1497.85 |
September | 1952.78 | 1757.50 |
October | 2182.45 | 1964.21 |
November | 2192.22 | 1973.00 |
December | 2028.91 | 1826.02 |
Average | 2063.27 | 1856.94 |
Month | Yarr (per Month) | Yref (per Month) | Yfin (per Month) | PR (%) | Lcap (per Month) | Lsys (per Month) | CF (%) |
---|---|---|---|---|---|---|---|
January | 4.23 | 5.59 | 3.80 | 68.06 | 1.36 | 0.42 | 15.85 |
February | 4.55 | 6.13 | 4.09 | 66.79 | 1.58 | 0.45 | 15.41 |
March | 4.77 | 6.68 | 4.29 | 64.30 | 1.91 | 0.48 | 17.89 |
April | 4.40 | 6.33 | 3.96 | 62.62 | 1.92 | 0.44 | 15.97 |
May | 4.01 | 5.88 | 3.61 | 61.41 | 1.87 | 0.40 | 15.04 |
June | 3.68 | 5.38 | 3.32 | 61.64 | 1.70 | 0.37 | 13.37 |
July | 3.31 | 4.72 | 2.98 | 63.23 | 1.40 | 0.33 | 12.43 |
August | 3.27 | 4.61 | 2.94 | 63.86 | 1.34 | 0.33 | 12.26 |
September | 3.84 | 5.44 | 3.45 | 63.51 | 1.60 | 0.38 | 13.92 |
October | 4.29 | 5.96 | 3.86 | 64.77 | 1.67 | 0.43 | 16.08 |
November | 4.31 | 5.89 | 3.88 | 65.85 | 1.58 | 0.43 | 15.63 |
December | 3.99 | 5.29 | 3.59 | 67.85 | 1.30 | 0.40 | 14.95 |
Average | 4.05 | 5.66 | 3.65 | 64.49 | 1.60 | 0.41 | 14.90 |
S. No. | Location | Solar PV Array Technology | Yarr (per Month) | Yref (per Month) | Yfin (per Month) | Lcap (per Month) | Lsys (per Month) | CF (%) | PR (%) | Reference |
---|---|---|---|---|---|---|---|---|---|---|
1 | Southwest Algeria | Poly-Si | 5.1 H/d | 4.7 h/d | 84 | [44] | ||||
2 | Lakshadweep | Poly-Si | 4.13–4.29 | 5.79–5.88 | 3.72–3.86 | 1.58–1.66 | 0.41–0.43 | 15.51–16.09 | 64.22–65.83 | [45] |
3 | Oman | Poly-Si | 3.78 | 5.59 | 3.64 | 1.82 | 0.14 | 15 | 67 | [46] |
4 | Delhi, India | Poly-Si | 4.15 h/d | 4.67 h/d | 4.06 h/d | 13.1 | 85–93 | [47] | ||
5 | Raipur, India | Poly-Si | 86 | [48] | ||||||
6 | Western Kenya | Poly-Si | 4.88 kWh/kW | 5.5 kWh/kW | 0.52 kWh/kW | 76.3 | [49] | |||
7 | Mauritania | Micro-a-Si | 2.89–5.06 | 4.51–7.12 | 4.26 | 1.63–2.46 | 0.12 | 11.66–20.54 | 66 | [50] |
8 | Andhra Pradesh, India | Poly-Si | 24 | 80 | [51] | |||||
9 | Bhopal, India | Poly-Si | 19.27 | 80.72 | [52] | |||||
10 | Malaga | Poly-Si | 3.7 | 64.5 | [53] | |||||
11 | Diyala, Iraq | Poly-Si | 3.88 h/d | 6.1 h/d | 3.99 h/d | 66 | [54] | |||
12 | Uganda | Poly-Si | 19.07 | 75.84 | [55] | |||||
13 | Northwest Spain | Mono-Si | 3.70 | 3.23 | 69.8 | [56] | ||||
14 | Thailand | Poly-Si | 4.32 | 5.21 | 3.84 | 0.18 | 0.10 | 73.45 | [57] | |
15 | Andaman and Nicobar | Poly-Si | 3.66–3.90 | 5.08–5.43 | 3.30–3.51 | 1.42–1.53 | 0.37 to 0.39 | 13.73–14.61 | 63.40–64.93 | [39] |
16 | SRM IST, Delhi-NCR campus | Poly-Si | 3.27–4.77 | 4.61–6.68 | 2.94–4.29 | 1.30–1.92 | 0.33–0.48 | 12.26–17.89 | 61.41–68.06 | Present study |
Architecture | Cost | ||||||
---|---|---|---|---|---|---|---|
PV Array (kW) | Diesel Generator (kW) | Li-Ion Battery (kWh) | Converter (kW) | NPC ($) | Cost of Energy ($/kWh) | Operating Cost ($/year) | Initial Capital ($) |
509 | 383 | 135 | 639,981 | 0.34 | 13,119 | 470,385 | |
82 | 94 | 65 | 1,123,152 | 0.60 | 77,787 | 117,560 | |
468 | 82 | 42 | 1,442,095 | 0.76 | 89,692 | 282,602 | |
82 | 1,747,678 | 0.93 | 130,972 | 54,530 | |||
Total solutions simulated | 31,071 | ||||||
Feasible solutions | 24,781 | ||||||
Infeasible solutions due to capacity shortage constraint | 6290 |
Component | Capital ($) | Replacement ($) | O&M ($/Year) | Salvage ($) | Total ($) |
---|---|---|---|---|---|
Battery | 204,905 | 157,336 | 0 | −21,332 | 340,909 |
PV array | 239,068 | 0 | 17,491 | 0 | 256,559 |
Converter | 26,412 | 11,206 | 7004 | −2109 | 42,513 |
System | 470,385 | 168,542 | 24,495 | 23,441 | 639,981 |
Annual Electricity Generation (kWh) | Emission Factor (kgCO2/kWh) | Avoided CO2 Emission (kg of CO2) |
---|---|---|
22,283.31 | 0.8274 | 18,437.21 |
Parameter | DG Only (Reference Case) | PV/BSS Configuration (Selected Configuration) |
---|---|---|
Initial capital ($) | 54,530 | 470,385 |
Operating cost ($) | 130,972 | 13,119 |
O&M cost ($) | 250,725 | 24,495 |
LCOE ($/kWh) | 0.93 | 0.34 |
NPC ($) | 1,747,678 | 639,981 |
Configuration | Total Fuel Consumed (L/Year) | Hours of Operation of DG (Hours) | Carbon Dioxide (kg/Year) | Carbon Monoxide (kg/Year) | Unburned Hydrocarbons (kg/Year) | Particulate Matter (kg/Year) | Sulfur Dioxide (kg/Year) | Nitrogen Oxides (kg/Year) |
---|---|---|---|---|---|---|---|---|
DG only (Reference case) | 76,565 | 8760 | 200,417 | 1263 | 55.1 | 7.66 | 491 | 1187 |
PV/BSS (Selected configuration) | - | - | - | - | - | - | - | - |
Sr. No. | Location | Proposed Hybrid System | NPC ($) | LCOE ($/kWh) | Reference |
---|---|---|---|---|---|
1 | Korkadu, Union territory of Puducherry, India | PV–WTBiogen | $16244.33 | $0.18 | [59] |
2 | Rwanda, East African Country | Hydro–SolarBattery | $41,210.80 | $0.05601 | [39] |
3 | Chamarajanagar district, Karnataka, India | PV–WT–BGG–BMG–FCBattery | $890,013 | $0.214 | [60] |
4 | Jask (near the Gulf of Oman) | PV–WTBattery | $44.1 M | $0.219 | [61] |
Genaveh (near the Persian Gulf) | PV–WTBattery | $46.9 M | $0.233 | ||
Anzali (near the Caspian sea) | PV–WTBattery | $48.8 M | $0.242 | ||
5 | Golbo II village, Ethiopia | PV–DGBattery | $82,734 | $0.207 | [62] |
6 | Mankwadze, Ghana | PV–WT–DGBattery | $8,649,054 | $0.382 | [63] |
7 | Rezwan village, Sudaklen, Iran | PV–WTBattery | $24,662 | $0.322 | [64] |
8 | Leopard beach, Hongsibao, China | PV–WT–BGGBattery | $587,013 | $0.201 | [65] |
9 | Industrial city II, Ardabil, Iran | PV–WT–DGBattery | $304,380 | $0.471 | [66] |
10 | Fouay, Benin republic, Africa | PV–DGBattery | $555,492 | $0.207 | [67] |
11 | Chikmagalur district, Karnataka, India | PV–HydroBattery | $712,975 | $0.16 | [68] |
12 | Singa village, Siang district, Arunachal Pradesh, India | WT–Hydro–DG-Battery | $23,808 | $0.63 | [69] |
13 | Tamilnadu, India | PV–WT–DGBattery | $199,850.80 | $0.2492 | [70] |
14 | Smith | PV–DGBattery | -- | $0.31 | [39] |
Middle Andaman | PV–DGBattery | -- | $0.31 | ||
Baratang | PV–DGBattery | -- | $0.31 | ||
Car Nicobar | PV–DGBattery | -- | $0.31 | ||
Katchal | PV–DGBattery | -- | $0.30 | ||
15 | SRM-IST, Delhi NCR Campus, India | PV–BSS | $639,981 | $0.34 | Present study |
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations. |
© 2022 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Sambhi, S.; Sharma, H.; Kumar, P.; Fotis, G.; Vita, V.; Ekonomou, L. Techno-Economic Optimization of an Off-Grid Hybrid Power Generation for SRM IST, Delhi-NCR Campus. Energies 2022, 15, 7880. https://doi.org/10.3390/en15217880
Sambhi S, Sharma H, Kumar P, Fotis G, Vita V, Ekonomou L. Techno-Economic Optimization of an Off-Grid Hybrid Power Generation for SRM IST, Delhi-NCR Campus. Energies. 2022; 15(21):7880. https://doi.org/10.3390/en15217880
Chicago/Turabian StyleSambhi, Shilpa, Himanshu Sharma, Pankaj Kumar, Georgios Fotis, Vasiliki Vita, and Lambros Ekonomou. 2022. "Techno-Economic Optimization of an Off-Grid Hybrid Power Generation for SRM IST, Delhi-NCR Campus" Energies 15, no. 21: 7880. https://doi.org/10.3390/en15217880
APA StyleSambhi, S., Sharma, H., Kumar, P., Fotis, G., Vita, V., & Ekonomou, L. (2022). Techno-Economic Optimization of an Off-Grid Hybrid Power Generation for SRM IST, Delhi-NCR Campus. Energies, 15(21), 7880. https://doi.org/10.3390/en15217880