2. Materials and Methods
This study is a qualitative, exploratory approach that aims at mapping practices and views held by senior individuals that represent a broad set of perspectives on construction projects. The systematic research process is shown in
Figure 1. The ambition was to understand what makes an infrastructure project and collaborative contract successful.
This study started with a roundtable held in Sydney in November 2019. We selected respondents based on two strategies: first, each participating organization recruited 1–2 respondents within their own staff, and secondly, we directly contacted individuals that have or have had key positions related to collaborative projects. Both strategies lead to experienced individuals with relevant knowledge and experience.
Two different types of interviews were performed, although the same questions were asked: One set of interviews were case based. The questions were answered from the perspective of one particular project—a given context. Six single cases were represented in the interviews. Following this, there were supplementary interviews with key individuals with long experience and knowledge of the questions seen from several perspectives and positions. These interviews add nuances and depth to the analysis. There are five such interviews.
This research includes interviews with eleven individuals representing different organizations (except for two individuals that represent the same public organization). All interviewees are senior practitioners with more than 20 years of experience. Seven interviewees operate actively in a role as sponsor or project manager. Three interviewees are experts in facilitating and coaching collaborative projects. One interviewee represents a private contractor.
Each respondent received several documents before the interview: an introduction to the topic, brief information on their rights as contributors to research, and a consent form to be completed, signed, and returned. Those that worked in a project also received an additional note on complexity with a complexity measuring tool that they filled in and returned to the authors.
The tool selected for assessing the level of complexity of the projects was the GAPPS CIFTER [
33]. Of the many tools available for measurement of the complexity of projects (e.g., [
34,
35,
36,
37,
38]) the CIFTER has the advantage of specifically addressing the management complexity of projects, it has been described as “the most researched model” [
39], and it is the simplest to complete, having only seven factors against which complexity is assessed. Other instruments have over 50 items requiring completion [
35,
38,
40], making them unwieldy for the purpose of this study. The instrument was developed by practitioners [
41] and is therefore couched in terms that have meaning for those involved in project delivery. Research has confirmed a high level of agreement between self-assessed and independent assessor ratings [
42].
The interviews had an average length of 70 min. All interviews were taped with consent from the interviewee, transcribed using the digital tool Otter.ai, analyzed individually, and sent back to the interviewee to give them opportunity for comments and confirmation.
A cross-case analysis systemized the input from the interviews related to each research question. The analysis itself was done manually, with some deductive—but mainly inductive reasoning. A main task in this research was text analysis, structuring and composing the essence of all the fragments offered by the interviewees. To help complete and check the contents of the interviews, a set of theoretical frameworks were used to support the analysis. Relevant framework models are described in the introduction.
3. Results
Interviews were made across New South Wales, Victoria, and Western Australia over a period of two months. The case-based interviews covered buildings for the housing, health, and university sectors, as well as road and railway infrastructure projects. The supplementary interviews were of a general nature covering all sectors and project types. Each interview resulted in a specific checklist that described the process of preparing for a collaborative contract. All these checklists were then combined into one generic checklist. This generic version is illustrated in
Figure 2.
Six of the interviews represented the preparations in real-life projects in specific contexts. These checklists are of particular interest in the analysis in this article. There were several differences between individual checklists mirroring the different types of projects, situations, organizations, and goals defined for each project. This was as expected. There were also many similarities, illustrating that across all types of projects and situations, the pre-contract process comes down to the communication and clarifications between the people involved. The structure given by the eight steps in
Figure 2 defines a common multiple of all interviews in this study. One of the given qualities of this checklist is meeting the formal requirements given in procurement regulations for public sector.
Given that we try to identify consequences rooted in aspects of complexity, it was crucial to have some sort of assessment of the degree of complexity for each of these cases. Complexity was self-assessed by the respondents using the CIFTER framework developed by GAPPS [
33]. The CIFTER forms part of a framework for performance-based competency standards for two levels of project managers: Level 1 for “normal” projects and Level 2 for complex projects. The framework is intended to be used to assess threshold competency—demonstration of the ability to do something at a standard considered acceptable in the workplace. In this study, we use the tool, not to assess the competency requirements, but rather the perceived degree of complexity in the situation in which the project manager is working.
Figure 3 shows the level of complexity across all case projects. In the CIFTER framework, a score below 11 signifies a simple project, a score of 11–18 is moderately complex, and above 19 is highly complex. In this paper, an additional category was added to signify two extremely complex projects, with scores of 24 or above. None of the cases analyzed in this study were classified as simple. The projects were classified as moderately, highly, or extremely complex. In this research, we explored whether there was a difference in the way the interviewees prepared for collaborative contracts, levels of complexity, and why these differences occur.
The six case projects show a wide array of different situational characteristics, as is illustrated by the yellow markings of respondents’ assessment. For example, most of the projects are operating in a stable context—except the extremely complex ones. Almost all projects have a high number of disciplines, magnitude of implications, and strategic importance. The expected financial impact varies considerably and seems to mirror the size of the projects. Perhaps the two most interesting factors for this study are the stakeholder cohesion and number and variety of interfaces. There is variation in this sample, but the number of and variety of interfaces seem to follow the level of complexity. Stakeholder cohesion is the most interesting characteristic of case 1—the smallest in financial terms but still extremely complex.
3.1. The Difference Between Being Collaborative in a Contract and Using a Collaborative Contract
We started this research with the assumption that collaboration is wanted and necessary to deliver successful projects. The literature referred in the introduction confirmed this. The interviews pointed to the same but nuanced the premise on one point: There is a distinction between being collaborative in a contract and using a collaborative contract. This may be explained by referring to Walker and Lloyd-Walker [
17], as shown in Figure 25 on page 108.
First- and second-order collaboration represents traditional and transaction-based models. These build on contracts that are not classified as collaborative but as competition driven. Third- and fourth-order collaboration represents models that are more relation-based, and contracts are classified as collaborative. This does not imply that there is no room for or will to be collaborative in a traditional contract. On the contrary, all the case-based interviews made in New South Wales represent the use of traditional contract forms with an explicit ambition and wish to be collaborative. These indications are also evident in the NSW Government Action Plan [
43] whereby the Government’s Construction Leadership Group (CLG) and its member agencies commit to work together to “procure and manage projects in a more collaborative way” (p. 3).
Interviews conducted in this research also include cases and general experience from explicitly collaborative models including program alliances (Western Australia and Victoria). In other words, both interpretations, “collaborative in a contract” and “in a collaborative contract” are included in this research. Both are valid positions and share the awareness that collaboration is a key to success.
3.2. The Effect of Complexity on the Process
Even though there are moderate differences in the level of complexity within the case projects, the results show striking differences. The contrast between case 4 (the least complex) and case 6 (the most complex) illustrates perhaps the most important consequence of the complexity. The authors compared the way preparations were done before a contract is formalized in these two projects. At the stage where the client identified and checked out potential partners and concluded with a shortlist of possible contractors, the work has a different character:
In the project with the lowest degree of complexity, the process had a distinct characteristic of gathering and structuring information. This goes both ways in sequence; information from the client to potential bidders, and the requested information from competing bidders. Dialogue is kept to a minimum. The process had some resemblance to “going by the textbook”, even though this project had a rather high degree of complexity. In the project with the highest degree of complexity, the process had a very strong characteristic of iterative process in which the client develops a framework for collaboration in dialogue with the bidders. The process was less structured and harder to overlook.
Going further into detail, the analysis revealed that in the project with the lowest level of complexity, there was a particularly strong focus on checks and balances, formal routines, and gateways. The process had a strong focus on analytical tasks and structured planning activities. In the projects classified as having a medium to high level of complexity, the focus was on checking the potential partner’s experience and understanding. The focus was on the selection of partners that could be aligned with the client’s objectives, and then the parties developed these further together until the parties reached a level of common understanding that was adequate for signing the formal agreement. In projects classified as having a very high level of complexity, the focus was on developing the project together with potential contractors. Obviously, some necessary planning was done up front to make shortlisting of candidates possible, but the real development happened after the best partner has been identified and selected.
All interviews resulted in a separate checklist for preparations to enter contract. An additional meta-analysis of the resulting checklists from the interviews in projects with different levels of complexity is shown in
Figure 4. Here, the checklists for three steps toward signing a collaborative contract are compared. The steps are (1) Shortlisting of candidates, (2) Selection of winner, and (3) Formalizing the contract. Note the tendency to have fewer, but bigger, issues on the checklist as complexity increases.
In the context of a project assessed as very complex, the collaboration must be very open and dynamic. The basis consists of major issues described by less precise definitions and specifications. This keeps open a wide room for improvement and innovation but also requires a high degree of integration to succeed. These processes are to a large degree experiments where practice must emerge as development unfolds.
For a project assessed as complex, the situation is generally similar, but it is possible to achieve more precision up front in definitions and specifications. If that possibility is used, then the room for innovation is reduced and the need for integration is reduced, too. However, there is no doubt left among the interviewees in this study that openness and close collaboration through all steps are necessary regardless of whether the project is complex or very complex. These complex projects develop their own frameworks and practice guidelines.
In situations assessed as less complex, the big issues are already clarified up front, and those moderate issues that remain are well understood. This makes it possible to define the scope and requirements clearly. Such clarity makes it possible to use delivery strategies that include allocating risk and payment in some detail up front. This makes traditional contracts and delivery models more appropriate, and the level of integration may be kept low. Execution may follow best practice guidelines.
3.3. Fundamental Roles, Risks, and Opportunities
The fundamental positions or perspectives may be defined as being owner (client), user, contractor (supplier), and wider society [
44]. All these groups of stakeholders may be divided into detailed classifications, but that is not needed for this analysis. When we look at the success of projects, all these fundamental positions must be considered, but in a contract, the positions as client and contractor are the only ones involved.
Interviews show that in the tendering process, the different positions of clients and contractors must be understood and respected. They come from different places and have different stakes in the process. One example is that information does not mean the same thing seen from the two positions. What the client needs to communicate is that “this is an attractive project and an opportunity the contractors should go for” (Interviewee 3). Clients want tough competition to secure lower prices in the bidding process.
What the contractor needs to hear is what shall be delivered and where the challenges and obstacles are hidden. They need this understanding to give the right price offer in the bidding. On the face of it, this may be read as a conflict of interest. “Provide for us to assess and price, and to base our proposal around, the drivers that you’re facing and if the challenges and hurdles you’re facing aren’t clearly identified and truthful, then it is very hard to progress with a good relationship and feel like you’re part of a team.” (Interviewee 11). The interviewees that mentioned this issue highlighted that in reality, there is a common interest in understanding the exposure to risks and challenges so that the right assumptions are made about the future project. All other alternatives will cost more during the process if not identified up front.
Taking the bigger picture into consideration, the collaboration will not be truly successful unless it produces stakeholder value [
45]. The stakeholders that are not directly involved in the contract are the ones that hold the key to understanding values represented by relevance and sustainability [
46]. If the solution developed and delivered by the project is not in line with the users’ needs and priorities, the client’s investment will fail, and there is no reconciliation in that the contractor might have made money in the process.
Given the emphasis on this in the literature, it was rather surprising to establish that a broader stakeholder perspective was hardly mentioned by the interviewees. Even if the setting specifically focused the contract on areas other than stakeholder value, the interview questions were in the context of success, and it was surprising that this context did not lead interviewees to discuss other key stakeholders. Only one of the interviewees put the user as the center of attention, as shown in
Figure 5.
It is worthwhile exploring this case in more depth, as it illustrates a perspective that was not found in the other cases. This interview described an extremely complex case involving a geographically distributed program of smaller projects. The visual summary in
Figure 5 is multidimensional. Circles may indicate levels of government (or not). The primary message is: Put the user at the center of attention. This is supported in theory by the acknowledgement that success depends on the ability to create value for stakeholders. Here, the user is the key stakeholder, the one stakeholder that the initiative exists for.
Three secondary messages are also indicated in the visual summary:
Blue message (arrow top down to center): You need to understand the politics of your own sector and the corresponding governance and decision making. It also implies there is a need to understand business in the host sector and think long term. This points to:
Red message (arrow from center horizontally to the right): You need to work with the users and local community in order to secure long-term value. Sustainability is measured in environmental, social, and economic terms and the project will not be a success unless all three aspects of sustainability are taken care of. This includes building competences and developing long-term asset management, which points to:
Green message (circular arrow on left hand side): The solution depends on what happens in other sectors, too. Thus, it is necessary to keep an open dialogue across all relevant sectors to make sure experience is exchanged, assumptions are consistent, and resources are well utilized across sectors. This tells us: Collaborative practice depends on breaking with the silo-thinking tradition.
There was little evidence in the interview transcripts or meta-analysis of the process to indicate that there was a significant focus on users and society, except in one interview. Interviews in this study show a high level of focus on strategic perspectives and major decisions along the timeline from start to when the formal agreement is signed. The owners’ perspective dominates at the start and at the end of this time sequence, as key decisions are identified. The supplier perspective (contractor’s position) is a main focus of all interviews. This is no surprise, given that all the respondents from case-projects are active sponsors or project managers. This represents key issues concerning their own responsibility and expertise.
Consideration of the users’ perspective was surprisingly missing during the majority of the interviews. Analysis of the interviews identified only a few items representing the users’ perspective. This is surprising, as it is the use of what is developed and delivered by the project that represents the purpose of the project. Benefits such as potential for income, return on investment, or simply solving the problem at hand lies in the users’ perspective but it received little attention. Only two interviewees explicitly talked about users. Similarly, there is little focus on the public perspective once the project has started. At the start of the project, the public perspective was in focus as a check of external preconditions at the outset. This may be noted as a strong argument for having a gateway process with checks and balances on behalf of society. However, this was only mentioned by one interviewee.
4. Discussion
Projects are fundamentally about creating value for stakeholders. In this context, contracts are fundamentally about regulating the relationship between two or more parties that choose to collaborate in that project in order to maximize that value. The contract defines the rules of the game and may significantly influence planning, engineering, and production processes. Some might say that the obvious thing to do in preparing for entering such a contract is to hedge your own position, securing your share of the output without investing more than you have to.
Economic theory informs us that the more competition, the lower the unit price and more advantageous bids [
47]. Game theory will set this up as potential for winning or losing, depending on how you play. Contract theory will tell you it is a matter of identifying risks upfront and allocating them to the party that is best positioned to manage them [
48]. This will minimize the risk premium and thus give the lowest total cost for the client. These theories have formed the basis for best practice projects over decades. However, this has not made projects particularly successful [
49]. Actors that do not see beyond short-term business are not preparing for a successful project [
50], unless perhaps when the project is not particularly complex. As Snowden and Boone [
51] told us: in a simple situation, the leader may identify and categorize the issues and choose the response prescribed in guidelines. They also gave us an understanding of what is needed to handle the complexity, probe, sense, and respond. It is about recognizing emerging patterns and responding to them, not about pre-identifying order.
4.1. Complexity and the Selection of Contract Type
An effect of complexity is that the process becomes unclear, unpredictable, and unmanageable. Assumptions are diffuse, responses are unknown, solutions are debatable, and everything is more uncertain. The parties involved need more competence, flexibility, and resilience to play this kind of game. The process becomes emergent; it cannot be described in detail upfront. Consequently, the parties involved become more dependent on each other, they need to iterate to find optimal solutions and processes that enable them to make decisions and manage design and production.
Transactional contracts are built on the assumption of predefined order. In a simple situation, the client knows what he wants to buy, how to specify it, who can deliver it, and what a reasonable price is. Everything you need to identify and describe upfront can be handled in a structured way. The supplier knows exactly what is wanted and how to deliver it. Strong competition on the supplier side will push the suppliers to be productive and offer the delivery at a competitive price. In such situations, there is no reason to look for other forms of contracts.
Often, the situation is more complex than this. From the position of working in a less complex situation with transactional contracts, the first step toward handling complexity is to act collaboratively in contract. In more complex situations, the assumption of predefined order is no longer valid, but the contracts may still be open for some flexibility to handle the emergence.
There must be room for collaborative behavior to accommodate complexity and/or uncertainty. How this flexibility is used is a leadership matter. In a situation with a significant degree of complexity, transactional leadership makes the game into a win–lose or even a lose–lose game. When the need for upfront identification and allocation of risks results in suboptimal contracts, it will lead to imbalance between the parties and potentially to loss and conflict. If there is no way of identifying upfront the critical issues, there is no way to assess and allocate the risks and rewards up front, either. Bids will not be correctly priced, and decisions are made on the wrong basis. The way this will develop is highly predictable.
4.2. Complexity and the Room for Flexibility
When there is insufficient room in the transactional contract for collaborative behavior to handle the complexity, using a collaborative contract may be the best option. These contracts start with the awareness that there is need for dialogue and integration between the parties. This helps them to manage the consequences of complexity—to identify and understand the developing patterns. Developing a collaborative contract involves setting up a framework for collaboration that can accommodate the dynamics and emerging nature of the process and stimulate the collaboration by building trust. Good leadership will potentially be able to turn this into a win–win situation.
At what level of complexity does the situation shift from allowing for collaboration in (transactional) contracts to requiring collaborative contracts? The data from this study are insufficient to give a good answer to this question, but the outcome of the interviews presents a remarkably clear message. The six cases in this study are all complex, as shown in
Figure 3. However, even though they are all public sector projects, developing physical infrastructure, and are delivered in Australia by professional project owners, they show significant differences on several complexity dimensions. The analysis in
Figure 4 shows distinctly different results despite relatively small differences in levels of complexity. The category with the lowest CIFTER score has an average score of 18, while the next category has an average level of 20, and the highest category has an average score of 25. How can this be explained?
The important difference between the two lowest categories is not only the value itself but where this difference comes from.
Figure 3 shows it is in the assessment of either the stability of context (case 4 vs. case 5) or a combination of factors that comes out slightly higher (case 4 vs. case 2 and 3). The middle category includes three projects with quite different characteristics in terms of complexity factors. This complicates the comparison. Comparing the lowest category with the highest category, the difference is more significant and points out stability in context in combination with stakeholder cohesion when comparing case 4 against case 1. In addition, the financial impact in case 6 is a lot bigger in financial terms than any of the other cases. So, what can be seen when comparing the checklist that sums up the preparations for entering a collaborative contract for the three categories?
In the case with the lowest CIFTER score (case no. 4), the process can be described as collecting and structuring known information. Every item on the list is well defined and the terms to describe them are precise. The process described in the interview included little dialogue between the contract parties (client and supplier) before the contract was signed, representing a low degree of integration. This does not mean there was little dialogue between the client and other stakeholders such as users and operators prior to the preparation of the contract. On the contrary, these were included in preparations through detailed discussion on requirements and premises for the process, which in this case included developing a new building amid an ongoing operation.
In the cases with the higher CIFTER score (case nos. 2, 3, and 5), the process included more dialogue leading up to the contract being formalized. In these cases, the focus of the dialogue included users and operator’s requirements and expectations, as well as regulating authorities and the wider context. In addition, there was significant dialogue with potential suppliers leading up to the shortlisting and choice of contract partner. This was followed by a moderate level of integration between the parties in the period leading up to the formal contract. Another characteristic observed is that the definitions and descriptions were partly less precise, leaving more room for adaptation later. Still, the total impression of the process was one of trying to identify and allocate all relevant risks upfront. One particular observation is that the two cases no. 2 and 3 were similar in nature and owned by the same public project owner. They went through similar processes and used similar contracts. Still, they had slightly different complexity characteristics. Case number 3 had challenges with stakeholder cohesion and was considered a failure in terms of the collaborative process, whereas number 2 was a success.
In the cases with the highest CIFTER scores (case no. 1 and 6), the process included a high degree of dialogue and integration between client and supplier even before the formalization of the contract. In these processes, it seemed to be intentional that the descriptions were left as diffuse descriptions rather than precise descriptions, the focus being on understanding and describing goals and measurement methods to assess the degree of success rather than identifying and allocating specific risks. The process can be described as developing a common framework within which effective collaboration can be generated and matured. Thus, it was also logical to leave lots of room to maneuver within the formalized contract. The upcoming development was simply not very well known at the outset, and in both cases, the interviewees talked about significant changes and additions later (during the contracted works) that were handled within these framework contracts.
4.3. Setting Up for Successful Collaboration
The industry and size of the project seems not to represent any relevant signal about the nature of the process. All of the projects involved some aspect of construction, and in the sample, examples of infrastructure projects were classified as both highly and extremely complex. The two cases with the highest CIFTER score were the smallest and the biggest in financial terms. However, looking beyond industry of project, it is worth considering that although all of these cases were referred to by the interviewees as a “project”, perhaps “project” is not the best term for some of these activities. The smallest case in financial terms could also have been described as a complex program of many small building projects in a highly complex context with a long-term perspective and particular social implications. The biggest case had a completely different scale in terms of financial impact but could also have been thought of more as a complex program than a complex project, being conducted in a complex environment and with long-term social, environmental, and economic implications.
The type of contract that the parties intend to enter has a significant importance for these processes. Cases number 1, 2, 3, and 4 used a traditional contract based on transactional logic but with an ambition to be collaborative within the limits of such contract. Case number 5 is a Public–Private Partnership (PPP) contract. PPP contracts are based on traditional logic but include a wider range of scope elements than typical delivery projects. This introduces the opportunity to include more aspects of collaboration and a more long-term perspective to the process. Case number 6 is a program alliance. This is the only “pure” collaborative contract in this study. Here, the whole logic is based on creating a sustainable environment for collaboration over the long-term and with a scope that emerges and develops as the process unfolds. Obviously, this study has too few cases to draw wide-ranging conclusions.
This analysis points toward one key to successful projects, especially in complex cases: leaving out the user and society perspectives poses a very strong risk to the projects’ success. The opportunities that represent increased stakeholder value and thus ultimate success and sustainability for the project are found in these perspectives. Interviews exposed that these perspectives are given little attention in the preparations, even for collaborative contracts. This results in a rather critical analysis.
On the surface of it, there seems to be significant weaknesses in the basic logic from identifying needs in the beginning, developing this into a solution, planning for benefits realization through to securing the intended effect from use of the result. Clients and contractors that are short-sighted and narrow in their assessment of value and preparations for contract will risk focusing on the wrong things and end up with the wrong solution and a failed project, even when the process is well played and the contract fulfilled perfectly.
However, the interviews did not explicitly expose the whole truth. Many of the user-focused issues are present when interviewees mention objectives, requirements, specifications, and scope. However, they are only implicitly present in these interviews. Obviously, the interviewees would have talked more about these issues if asked directly about them. On the other hand, they were not asked to focus any of the other perspectives, either.
The resulting impression is probably very close to what the real focus is in these processes. The parties involved in preparations for contracts are closest to their own perspectives, even in collaborative contracts. There is a danger that the core logic—embedded in the users’ perspective—is left to someone else (delegated to designers and consultants perhaps) or lost in the dominating focus on productivity (suppliers’ perspective) and economic/financial focus of the owner/investor perspective.
5. Conclusions
5.1. Answers to Research Questions
The research questions addressed in this study can be answered from the results of the interviews:
Complexity makes it impossible to identify and allocate all risks up front. Thus, the very foundation for the transactional contracts are challenged. In situations with a low degree of complexity, the transactional logic may still produce good results. The power of competition in keeping cost down should not be underestimated. This study clearly indicates that the power of collaboration in handling the complexity is needed when the degree of complexity gets high. As shown in this study, there is a measurable limit to the degree of complexity (measured by CIFTER score) where the transactional logic meets some sort of limit. The level that seems to mark this limit is a CIFTER score of about 20–21.
Based on the checklists that resulted from the interviews (see
Figure 2), before starting the procurement process, the owner must establish a basis for actually working in a collaborative way. Without it, any attempt will be futile. The execution strategy for the proposed project must be in place and resources and other preconditions to start. The preparation stage is about making the project attractive, but at the same time ensuring the bidders are able to give realistic price bids. The degree of precision and detail in the information at this stage mirrors the level of complexity—understanding this, and its implications, is important for all stakeholders. In complex situations, the initial screening for partners is not a question of finding the bidder with the lowest price but rather the bidders that are able to align with the owner’s goals and ambitions. The best fitted potential partners are shortlisted and invited to deliver initial bids. Depending on the level of complexity, there has to be a phase of dialogue between the client and bidders to establish that the mutual understanding and realistic expectations are established. This becomes distinctly more important when complexity rises. After receiving and evaluating the final bids, the winner is invited to further develop the more detailed plans and conceptual solutions together before finalizing the formal contract. This period is characterized by a high degree of integration between the client and the supplier in very complex cases. The process uses language and definitions that maintain a significant room open for interpretation and handling emerging aspects in the following process of design, production, and delivery. In short—the preparation for a collaborative contract in a highly complex situation is more similar to developing a framework for managing the process together than an upfront identification and allocation of risks between the parties. Complex projects require freedom of interpretation only gained by allowing wide and less precise expressions.
The major issue in securing stakeholder value is to make sure the stakeholders are involved and taken into consideration at the right stages of development. What this study documents is that the parties involved in preparations for a contract focus on their own and the specific partners’ positions explicitly, but for a large part, they leave other stakeholders out or only implicitly include them in developing objectives, requirements, and specifications. We believe a more explicit strategy toward stakeholders is purposeful in the front-end of projects and even necessary when the complexity is extremely high. This will help keep focus on the most important issues that represent opportunities and risks related to stakeholder value.
5.2. Limitations, Generalization of This Analysis, and Future Research
All cases in this study are found in Australia and are not representative for all sorts and sizes of projects. However, the issues discussed here are highly relevant to public and private sector projects all over the globe. There is reason to believe these findings are fairly representative for medium to large, complex projects in industrialized countries. Although not to be taken literally in every single case, the principles and tendencies shown here are considered generalizable.
There are several limitations to this analysis, since this research was done without any form of financing or external resources over a short span of time. First, the number of cases is too limited to lead to generalizable findings. Second, there was only one key individual interviewed per case, and thus, there is potentially a high degree of subjective opinion in these sources. Third, the CIFTER-scoring was done as a self-assessment and thus may not be consistent across cases. The differences are small, so this may be a source of error that puts cases in the wrong category. However, the differences in CIFTER score are well tuned in to the differences observed in resulting checklists in
Figure 4.
All interviews were transcribed and returned for control by the source with no or very small changes as result. However, a potential cause of error is the influence of each informant’s communication style and level in structure when describing their preparations.
Future research may strengthen or challenge the findings of this study by posing similar questions to a larger population of cases in other countries. All interview guides are available, and all interviews are well documented enabling duplication of this study, to determine whether similar patterns emerge in other parts of the world. However, that would not be enough. It is important to make sure the understanding of the causalities is developed further. Triangulation, using other research methodologies and types of analysis would offer potential for greater insight.
5.3. Contribution to Research and Practice
The findings illustrate and support tendencies that are reported in previous literature, clarifying differences that can be identified and the reasons behind them. The results seem to offer a reasonably precise and robust set of explanations of the effect of complexity.
There are insights from this research that can readily be applied in practice. The generic checklist provided in
Figure 2 can be used as a guide and as the basis for a more detailed checklist that would apply to preparation for collaborative contracts in specific contexts. The CIFTER was found to be an easily used tool for assessment of a level of complexity that has face validity with practitioners.
Figure 4 provides a useful summary of key differences that come into play at different levels of complexity. At lower levels of complexity, there tends to be more focus on clear definitions, process, routines, and gateways, and collaboration may occur within traditional contracts. At higher levels of complexity, the process becomes more iterative, less transactional, requiring mutual understanding. There tends to be higher tolerance for ambiguity, more conversation and opportunity for co-creation, and under these conditions, there is a greater need for specifically collaborative contracts that allow sufficient flexibility to accommodate experimentation, innovation, and emergent practice.
To enable the delivery of sustainable stakeholder value, there is evidence of the need for consideration and focus on users throughout the process, rather than just at the start when identifying requirements. When preparing for collaboration within contracts, or for collaborative contracts, the client and contractor perspectives appear dominant, and there is potential for a more sustainable delivery of value to all stakeholders if other perspectives such as those of the user are given greater and more sustained attention.