Next Article in Journal
Benthic Community Assessment of Commercial Oyster (Crassostrea virginica) Gear in Delaware Inland Bays
Previous Article in Journal
Linking Conservation, Community Knowledge, and Adaptation to Extreme Climatic Events: A Case Study in Gorongosa National Park, Mozambique
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Sustainable Allocation Model of Construction Workforce for Work Resumption during COVID-19

1
School of Management, Xi’an University of Architecture & Technology, Xi’an 710055, China
2
Department of Civil & Environmental Engineering, School of Planning, Design and Construction, Michigan State University, East Lansing, MI 48824, USA
3
School of AnDe, Xi’an University of Architecture & Technology, Xi’an 710311, China
*
Author to whom correspondence should be addressed.
Sustainability 2021, 13(11), 6481; https://doi.org/10.3390/su13116481
Submission received: 19 April 2021 / Revised: 31 May 2021 / Accepted: 3 June 2021 / Published: 7 June 2021

Abstract

:
COVID-19 has posed challenges for the construction industry, such as precise pandemic control, sustainable labor relations, and loss minimization. In response to these challenges, this study has developed a decision model that optimizes workforce allocation for projects to achieve sustainable workforce management, a tradeoff between pandemic prevention and work resumption. The priority of project resumption was evaluated using basic characteristics, the long- and short-term strategies, and the regional pandemic situation. The energy level of skilled workers was graded according to construction team size, skill level, and experience. Sustainable allocation principles and paths were explored to target four different types of work resumption plans. We used the cellular automaton (CA) technique to simulate the sustainable allocation model. We also analyzed the similarity function of energy levels and the time-cost function of allocation. The case study of the SGJ Construction demonstrates that this allocation model can accurately simulate work resumption and provide a sustainable allocation decisions and tools under pandemic. Also, it implies balanced interests and concerns between construction companies and the society for work resumption during COVID-19.

1. Introduction

In late 2019 and early 2020, the COVID-19 breakout pressed the pause button for work and life in China. The pandemic affected various industries including the construction industry, which has high requirements on project scheduling and cost control. To mitigate losses due to work suspension, construction companies paid attention to local disease control policies in project areas and planned for work resumption when possible.
However, when and how to resume projects is challenging for project management. It is known that construction companies often carry out several projects at the same time, which has been called project pool in this paper. The widespread pandemic has affected project pool in different locations and nearby labor recruitment centers. A sustainable work-resumption plan should consider both project characteristics and local pandemic situation when allocating resources.
The construction industry always lacks stock of skilled workers due to the gradual withdrawal of the older generation, unrefined vocational and technical education, and insufficient reserve of young skilled workers [1]. The pandemic makes the problem of workforce shortage worse because skilled workers are locked down and unable to move to the workplace. The construction industry is labor intensive, and this problem severely harms work resumption for construction companies. The post-pandemic recovery process requires the whole society to stabilize labor relations, support the efforts for business and production resumption, and maintain a balance between business development and worker rights [2].
The object of this paper is to develop a model to allocate skilled construction workers for during and post-pandemic work resumption. The model considers the situation of precise pandemic prevention and control, orderly work resumption, and legitimate protection of worker rights and interests. The following research questions listed below are those that construction companies must systematically analyze:
  • The work resumption prioritization: that is, what projects should resume first and what can resume later?
  • The work resumption scheduling: that is, how to return available and skilled workers to full employment?
  • How to stabilize the labor relationship and improve the construction company’s resumption simultaneously during the pandemic period.
A feasible way to answer these questions is to utilize the principle of temporal and spatial coordination to gradually achieve work resumption, give priority to the construction of key projects and those in regions with mild pandemic, and allocate existing skilled workers in an orderly manner whenever possible.

2. Literature Review

This paper follows two kinds of languages to aggregate the final collection of papers. One was English literature with the following subject headings in CNKI: “TS=(manpower* AND allocation * AND construction) or TS=(labor* AND allocation* AND construction) or TS=(worker* AND allocation* AND construction) or TS=(workforce* AND allocation* AND construction)” or “TS=(manpower* AND allocation* AND project) or TS=(labor* AND allocation* AND project) or TS=(worker* AND allocation* AND project) or TS=(workforce* AND allocation* AND project)” as search terms in WOS. The other was Chinese literature with “TS=(manpower* AND allocation* AND construction) or (worker* AND allocation* AND construction)” Or “TS=(manpower* AND allocation* AND project) or (worker* AND allocation* AND project)”. There are a great deal of Chinese papers; thus, we only chose papers published within the last five years for relevance. Then, 39 English articles and 28 Chinese articles that were closely relevant to topic were selected and analyzed.
Research on the workforce allocation of the construction industry includes topics of single project and project pool.
The workforce allocation in single projects has been extensively discussed for a long time [3]. Many of them focus on construction factors such as cost, time, technique, etc., that affect project staffing assignments. In the classical research by K. R. Persad et al., the working time of a single construction project was predicted by establishing a regression analysis model, and it was concluded that the project cost and project category are the key factors for the prediction of the manpower requirements of the project to realize optimal personnel allocation [4]. S. W. Whang et al. identified and ranked the critical design-management factors for design teams to understand how appropriate designer allocation can positively affect project performance and profit [5]. Zhang Xizheng, Luo Wen, and Cai Yueyue proposed a multi-objective task allocation model with minimum project duration, lowest cost, and minimum number of contractors [6]. W. J. Yang and Y. S. Kim presented a method for improving the accuracy of construction-site engineer allocation by site technological risks, according to data analysis from 31 case projects [7]. The other articles pay more attention to workforce elements, such as society, cognitive behavior, career development, etc., that play a powerful role in allocative efficiency. For example, Ballesteros–Pérez et al. proposed that project managers should focus on social interaction when screening workers from a given repository to achieve the highest work efficiency [8]. P. C. Liao et al. used SEM to identify the cognitive structure of steel workers and elevator workers and found that there were significant differences between them, indicating that in terms of manpower allocation, more attention should be paid to the team leader or foreman of mechanical workers and correspondingly more self-supporting capability for rebar crews [9]. B. Shahbazi et al. used the balance construction corporate objectives, such as maximizing productivity and objectives of construction workers’ career development needs in the future, based on the use of Pareto Optimality and Pareto Curve, to create a double-target model so as to build a new allocation dimension of construction workers [10].
At present, the research on the perspective of workforce allocation in project pool is popular. Some scholars prefer to take multiple projects as the core and allocate qualified construction workers for them. Project priority has been defined to more effective workforce allocation in a multi-project environment. Mats Engwall et al. believed that multi-projects running in parallel are interdependent, and the priority definition of project pool needs to consider many factors dynamically, and the workforce allocation among projects could reconstruct organizational structure [11]. Masataka et al. used a project optimization system to find the project portfolio with the largest total revenue and the optimal manpower allocation method in such a portfolio [12]. Chen Junjie et al. established a multi-project evaluation system based on a multi-level fuzzy comprehensive evaluation method [13]. El-Abbasy et al. presented an optimization model for multiple construction projects to solve the problems of prioritizing projects under resource-conflict conditions, allocating limited workforce, and optimizing all the projects’ multiple objectives under certain funding limits [14]. Some scholars focus on the form and characteristics of labor force to achieve efficient allocation in project pool. Zhong Yong et al. discussed the causal relationship between resource availability and work operability and found significant differences between labor and other resource allocation via a system dynamics model in multiple projects [15]. Y. H. Hou et al. targeted project managers’ optimization for multi-project with period-equilibrium and minimization of total labor cost and built a two-stage optimization model based on a linear programming algorithm and the greedy algorithm to demonstrate the effectiveness of optimal allocation [16]. L. Florez established a system for efficient crew allocation in the masonry industry formulated as a mixed-integer program and showed the substantial impact on reducing the completion time to build the walls, maximizing the utilization of masons, and outlining opportunities for concurrent work [17]. Yunjeong Mo et al. created a machine-learning model that read labor request texts and predicted priority and then automatically assigned workforce through the technique of natural language processing (NLP) [18]. Some studies have extended personnel allocation in project pool to worker teams. C. Koch and J. Marton described a Scandinavian model in which construction teams with a number of multi-skilled workers were extensively cultivated and used in the construction sites [19]. H. R. Thomas and M. J. Horman. cited fundamental principles related to labor performance of site construction management and discussed the strategies to improve construction team productivity [20]. M. Walter and J. Zimmermann realized that large project teams come along with productivity losses due to increased coordination effort and social loafing between projects and thus formulated a mixed-integer linear program that minimized average project team size [21]. L. I. Wenhua, L. Peng, and D. Zhang found that the heterogeneity of team leaders made a difference in construction team performance, and their competency was affected by their educational background and service types [22]. Y. Anoshkina and F. Meisel analyzed the problem of composing worker teams and routing and scheduling these teams under goals-expressing service-, fairness-, and cost-objectives in different locations by an optimization model and provided a bi-level decomposition scheme [23]. In addition, allocation of multi-skilled workers played a more and more important role among multiple projects. Drezet and Billaut comprehensively considered the role of multi-capability in the allocation of human resources to a project, constructed an integer-programing model under this constraint, and used the greedy algorithm and TABU search method to find the optimal solution [24]. A. Nasirian et al. paid great attention to multiskilling to introduce configuration, strategy, collateral effects, context, and mainstream research on the multiskilling in the construction industry and in the mean-time to the dynamic reallocation of multi-skilled labors in prefabricated construction with multitasking [25,26]. M. Sarihi et al. proposed a simulation framework for assigning multi-skilled workforces across multiple projects on the basis of workers’ competency status toward minimizing resource and costs and maximizing social sustainability [27].
From the above, some things could be found. First of all, excavation and evaluation of the project and labor force is the foundation of effective allocation among construction projects. Additionally, many studies mentioned the priorities and ranking in project pool. Then, the development of allocation model is an important means and method to deal with management performance between them. However, the following problems existed in previous studies: (1) most construction project pools utilized multi-objective planning to consider the effective allocation of workforce and did not consider the allocation of labors in severe disturbance (e.g., suffering a pandemic); (2) the allocation models were mainly focused on the benefits of cost and schedule, and insufficient attention was paid to the long-term strategy and social responsibility of construction companies. Therefore, this paper emphasizes the balance between pandemic prevention and work resumption. Both strategic-level objectives and sustainable employment responsibilities are comprehensively considered to provide systematic management ideas for the orderly work resumption of skilled workers in project pools of construction companies.

3. Indicator System Design

The assessment model considers two principles: (i) prioritizing work resumption in regions of mild pandemic situations and postponing that in regions of severe pandemic situations; and (ii) matching project needs with worker skills measured by the energy-level metrics. The first step is to determine the priority of each project in the construction company’s project pool (U) and the energy level of the skilled workers and then to consider the impact of the pandemic. Among them, energy level has been defined as the amount of energy and the level of ability of skilled workers or construction teams to complete construction tasks. The amount of energy indicates the size and quantity, while the level of ability emphasizes experience and quality.

3.1. Prioritization of the Projects in a Project Pool during a Pandemic

3.1.1. Indicators for Project Prioritization

In this paper, evaluation indicators of the project priority were determined by comprehensively using the methods of literature induction and expert interview. From the literature review, many studies mentioned the priorities and ranking in project pool (details in Section 2). All the basic assessment indicators were collected, and the main factors, such as construction area, contract amount, profit, duration, total cost, financing cost, quality, technical, and strategies, were selected in the perspective of a construction company. We took into consideration that the priority of projects is influenced by different dimensions, which have been divided into the operational level and strategic level. The operational level should consider not only the scale and profit of the project but also the specific requirements of the project, such as its duration, quality, and technology. For the strategic level, it is necessary to respectively consider the long- and short-term needs. Then five construction specialists, as detailed in Table 1, were initially invited to find out the suitable and available indicators as well as to supplement, correct, and improve them. According to their experience, the specialists then discussed and presented the final indictors and the evaluation criteria. As a result, remaining contract amount (A1), profit per unit of time (A2), remaining duration (A3), quality (A4), level of technical complexity (A5), impact of the project on short-term enterprise strategies (A6), and impact of the project on long-term enterprise strategies (A7) were confirmed. The average level of each indictor was adjusted according to the overall situation of the construction project pool, and a five-level scoring method was referred. The evaluation indictors and criteria are presented in Table 2.

3.1.2. Pandemic Impact Indicators for Project Priorities

In a pandemic, the contract performance, cost, and schedule of each project will be affected to a different degree. Therefore, in addition to the basic evaluation indicators, it is also necessary to consider the pandemic indicators of the project location. The time point of 29 February 2020 was selected. According to the data released by the China National Health and Wellness Commission, the BAIDU Pandemic Map provides information on the pandemic situation of each area, and the pandemic level of each province (municipalities directly under the authority of the central government and autonomous regions) is determined by the cumulative number of confirmed cases [28]. For details, see Figure 1.
At the request of the State Council of China, the risk was calculated based on the cumulative number of confirmed cases, the proportion of local cases, the number of clustered pandemic cases, and the newly confirmed cases in consecutive days in each county (district) under the jurisdiction of the province (municipality directly under the authority of the central government or autonomous region) as the unit, and the pandemic situation in each region was regularly announced [29]. The classification of most provinces was collected, and the severity of the pandemic was categorized as high risk, relatively high risk, medium risk, relatively low risk, or low risk. The pandemic impact on the project priority was based on the condition of the pandemic in the project location; C i indicates the degree of the pandemic impact on the priority of project i. The evaluation criteria are presented in Table 3. Among them, the pandemic impact indicators take into account the current situation of the pandemic in the province (municipality directly under the authority of the central government or autonomous region) where the project is located as well as the pandemic differences among different counties (districts) in the same province (municipality directly under the authority of the central government or autonomous region). The calculation formula is as follows:
C i = C i P r o v .   × C i C T Y . C i 0.1 × 0.1 ,   0.9 × 0.9

3.1.3. Assessment Models for Project Priorities in a Pandemic

The most important characteristics of construction projects are their uniqueness, environmental impact, heterogeneity, and complexity. Due to individual characteristics and external demands, the evaluation indexes of projects in a project pool exhibit differences. To characterize these differences more objectively, the entropy-weighting method is used in this paper to determine the weights of project priority indicators. Different from other evaluation methods, such as analytic hierarchy process and fuzzy comprehensive evaluation method, the priority of a project is the relative priority obtained by comparing with others in the project pool, which is consistent with the theory of the entropy-weighting method. For the theoretical basis and implementation steps, readers can refer to the related literature [30,31].
During the process, the assessment value of each project indicator is determined jointly by project and enterprise managers with rich technical experience and management experience. In view of their different understandings of the operational- and strategic-level indicators, the operational-level indicators rely more on the scores of project-level managers, while the strategic-level indicators are more dependent on the scores of enterprise-level managers. Let the number of project-level managers in a survey of project i be ū, let the number of management personnel at the enterprise level be ῡ, and let the scores of the evaluation indexes of project i by project- and enterprise-level experts be x i j u and x i j v , respectively. Then, the average comprehensive score X i j of indicator j for item i is
X i j = α u u = 1 ū x i j u / ū + α v v = 1 x i j v / ,
where α u is the weight of expert ratings at the project level, α v is the weight of expert ratings at the enterprise level, and α u + α v = 1 . When calculating the comprehensive score of operational-level indicators (A1, A2, A3, A4, A5), α u > α v ; when calculating the comprehensive score of enterprise-level indicators (A6, A7), α u < α v .
The comprehensive score X i j of each sub-item is substituted into the initial decision matrix, and the weight W j of each index is obtained by the entropy-weight method. Then, it is substituted into the priority evaluation model together with the weights to obtain the comprehensive score of the basic priority of each project. In other words, the foundation priority scores for project i are:
I i = W 1 X i 1 + W 2 X i 2 + W 3 X i 3 + W 4 X i 4 + W 5 X i 5 + W 6 X i 6 + W 7 X i 7
Because the impact of a pandemic is comprehensive, the pandemic impact indicators act on the overall priority score of each project. Moreover, the more serious the pandemic, the lower the expectation of the projects to resume production and the lower their priority score. In other words, the revised priority score for project i in a pandemic is.
I i = I i / ( e C i )
The priorities of each project of project pool U can be ranked and numbered according to their basic and modified scores:
P a = m a x I i m i n I i ,
( P a ) = m a x I i m i n I i ,
where   1 a n a N , where n is the number of projects in the pool of a construction company, P a represents the project priority in a general state, and ( P a ) represents the project priority when taking into account the impact of a pandemic.

3.2. Energy Level Assessment of Skilled Workers in a Project Pool

The term energy level was first derived from physics and later introduced into human resource management, thereby forming the principle of energy-level proportionality. It was used to emphasize that workforce should be assigned work responsibilities and work content according to maximize their abilities and achieve management objectives [16]. For a project pool of a construction company, each project has different project characteristics and requires different types of workers. Most skilled workers currently arrange and settle work tasks with the construction team as a unit, which considers that the contract signed by an individual is actually performed by the construction team in China. Therefore, a construction team is considered a basic unit when measuring the energy level of skilled workers, which is the skill set of the group [23]. By definition of energy level, assessment model of construction workforce has referred not only to size of construction teams, but also to the richness of their construction experience and quality. After literature review and discussing with specialists, the size of the construction team would be expressed by the number of team members [20]; the experience is mainly examined with the average working years of construction teams and the number of similar projects completed by the team [19]; the skill level would describe quality and mainly be measured by the proportion of senior skilled workers in the construction team.
The energy-level assessment indicator system of a construction team in a project pool is presented in Figure 2.
Considering that home building comprises the largest proportion of skilled workers in the construction industry, only housing construction is considered as an example in this paper to study the energy levels of workforce in the project pool. According to China’s Occupational Classification Dictionary and the Catalogue of Occupational Skills Appraisal Standard Work Types issued by the Ministry of Housing and Construction, the main technical work types in housing construction projects include carpentry, plasterers, masonry workers, reinforcement workers, erectors, plumbers, mounters, earthwork machinery operators, vertical transport machinery operators, etc., which are expressed as G_b (b∈[1, m]), where m is the number of technical jobs in the project pool [32].
According to the energy-level assessment indicator of the construction team, the configuration of the construction team of type G b of project P a can be expressed as T b a :
T b a = B 1 b a B 2 b a B 3 b a B 4 b a     o r     T b a = B 1 b a B 2 b a B 3 b a B 4 b a
  • B 1 b a N
  • B 2 b a —the level of skilled workers recognized by the state shall prevail for the senior skilled workers; if there is no relevant national certification, the comprehensive evaluation of the enterprise shall prevail;
  • B 3 b a —the average year of the construction team after removing the minimum and maximum;
  • B 4 b a —similar projects involving more than 50% of the construction team members shall prevail, and the participants must include the team leader [22].

4. Allocation Model Development

To focus on work resumption, it is assumed that the initially allotted skilled workers in a project pool before a pandemic are qualified, i.e., the energy level of the construction team well matches the needs of the project. The initial allocation matrix is shown in Table 4.

4.1. Basic Steps of Sustainable Allocation for Work Resumption in a Pandemic

In a pandemic, the top priority is pandemic prevention, and the priority of projects change due to the consideration of the pandemic. The work resumption or recruitment of construction teams is also controlled by the areas from which labor services are exported and must occur in areas where they are allowed to be released. Therefore, the system configuration of a construction team in project pool U should take into account the pandemic situation at the locations of the project and skilled workers. A construction company is required to resume work in their project pool according to the two basic principles outlined in Section 3. The basic sustainable allocation steps are as follows.
Step 1: Check the work resumption of each project and its construction team. When a pandemic situation stabilizes and improves, the construction teams of some projects will resume work or confirm their intention and time frame for resuming work via communication tools. During the investigation, as long as the team leader of the construction team and the main senior technician workers confirm that they are returning to the original site, the construction team is considered to be unchanged. Other general workers are allowed to be dynamically adjusted according to the pandemic situation to effectively avoid the interruption of the whole construction team resuming work due to the loss of individual non-critical workers. Moreover, the skilled workers in the construction team generally come from the same geographical location or family, for which the pandemic situation is similar; thus, the district location conditions for the work resumption of the construction team can only be constructed by the team leader.
Based on various circumstances, there are four types of projects and work resumption of their construction teams, as detailed in Table 5; U = U I + U I I + U I I I + U I V .
Considering situations II, III, and IV, the two starting points are as follows: conditions are in place to resume projects and failure to meet conditions for the resumption of projects. The lost construction teams for the projects that meet the conditions for resumption ( U I I ) are replenished on the basis of the project priority of the general state P a ; a qualified construction team is prepared for the projects that fail to meet the conditions for resumption ( U I I I + U I V ) on the basis of the project priority under the impact of the pandemic ( P a ) . During the survey, the construction teams that were committed to resuming work during the pandemic waiting period are recorded, as is the estimated waiting time for work resumption (subject to documents issued by the local government, the transportation time for returning to work, etc.). For the construction teams that have met the conditions for work resumption but have been stranded because the project does not meet the conditions for work resumption, the waiting time is expressed as a negative number. The construction teams that have confirmed to have not resumed work during the pandemic waiting period are highlighted and then listed as lost construction teams. The energy level of each project corresponding to the lost construction team has been determined.
Step 2: Search for construction teams with similar energy levels for situation II . For U I I , the project priority ranking is P 1 I I , P 2 I I ,   , P a I I ,   , P n I I . Accordingly, search for construction teams with similar energy levels from highest to lowest in G I I I . The finite set of the results is G k I I I , where k is the project number in U I I I . Let Sim T b a I I , T b k I I I be the energy similarity function, the value of which is s k . The corresponding projects of construction teams with similar energy levels in G I I I are:
k | m a x s k , K *   =   k | m a x s k
where 1 < a n I I   and   1 < k n I I I . When n I I n I I I , considering the social responsibility to sustain labor relations and the scarcity of skilled workers during the pandemic period, select construction teams with similar energy levels in G I I I for the projects in U I I to the greatest possible extent, and the remaining construction teams in G I I I are described as k 0 . When n I I > n I I I , if k = 0 , the shortfall is to be compensated for by the external market.
Considering the moment before the pandemic as t 0 , the corresponding construction teams of projects in U I I according to the project priority are as follows:
T b 1 T b 2 T b a T b n I I
Considering the moment of the pandemic waiting period as t 1 , the construction team K * with the greatest similarity in energy level in G I I I is configured to match U I I by the ranking P 1 I I , P 2 I I ,   , P a I I ,   , P n I I , which fails to meet the conditions for the resumption of construction teams; the insufficient team from G I I I is considered to be obtained from the labor market and is recorded as T Z . At this point, the construction team state r1 can be expressed as follows:
r 1 =   T b k 1 T b k 2   T b n I I I     T Z     T b n I I   T b k G I I I
Step 3: Prepare construction teams with similar energy levels for situations III and IV. For U I I I + U I V , the priority of projects in a pandemic is P 1 I I I + I V , P 2 I I I + I V ,   , P a I I I + I V ,   , P n I I I + I V . The construction team K * with the greatest similarity in energy level in G I I + G k I I I ¯ + G I V is allocated to U I I I + U I V by the priority of projects that lost construction teams during the pandemic (adding to II is also considered a loss); the shortfall is considered to be compensated for by the labor market and is recorded as T Z .
At t 0 , the corresponding construction teams of projects in ( U I I I + U I V ) during a pandemic according to the project priority are as follows:
T b 1 T b 2 T b a T b n I I I + n I V
At t 1 , if T b a is lost, the construction teamwith the greatest similarity in energy level in   G I I + G k I I I ¯ + G I V is prepared in advance to U I I I + U I V by the ranking P 1 I I I + I V , P 2 I I I + I V ,   , P a I I I + I V ,   , P n I I I + I V , which fails to meet the coitions for the resumption of projects. At this point, the construction team state r 1 can be expressed as follows (Figure 3):
r 1 =   T b 1 T b 2   T b k 1   T b k 2   T b k 3   T b n I I + k + n I V T Z

4.2. Model Establishment and Sustainable Allocation Parametric Analysis Based on Cellular Automaton

4.2.1. Establishment of the Allocation Model for Work Resumption Based on Cellular Automaton

Cellular automaton (CA) originated from von Neumann’s simulation of the self-replicating behavior of organisms and is defined as a dynamic system that has certain rules in cellular space and evolves in a discrete time dimension [33]. Structurally, it can be expressed as a quadratic group: CA = Ω ,   R ,   Φ ,   f , where Ω denotes a cellular space, which is a collection of discrete spatial grids, R represents a finite set of cell states, Φ denotes the set of neighboring cells that influence the state value of the initial cell at the next moment, and f represents the local state-transition function, namely the evolution law [34].
As a computational model, the input of CA is the state of all cells in cell space Ω at t0 (representing the past), and its state at t1 (representing the present) is calculated as the output via the evolution law [35].
One-dimensional CA is generally considered to be capable of generalized computation [36]. Its structural features and computational principles have strong adaptability in form and connotation with the sustainable allocation of skilled workers in a project pool. In view of this, this paper is based on the theoretical framework of one-dimensional CA to construct a model for the sustainable allocation of work resumption. The theoretical model can be defined as follows.
Hypothesis 1 (H1).
The set of the construction field space of each project Pa in the project pool is taken as cellular space Ω.
Hypothesis 2 (H2).
The set of allocation states that for each project and work type in the pool taken as R, R =   0 , 1 , 2 , where 0   means that the current construction team is lost but can be dispatched from projects within a specific range (see Section 4.1, Step 2 for details) or projects with lower priority (see Section 4.1, Step 3 for details); 1   means that the project and construction team are eligible for direct resumption without reconfiguration; 2   means that the current construction team is lost and must be recruited from the labor market. Moreover, S(k) = 0 means that the specific scope is too narrow and there are no more available teams, or that the project has the lowest priority, and there are no dispatchers.
Hypothesis 3 (H3).
The set of energy level of lower-priority (or range-specific) project’s construction team is taken as Φ.
Hypothesis 4 (H4).
The energy similarity function (SIM, and the time-cost function (Min(t)) are used as the core content in the local state-conversion function f. Based on the project priority, the energy similarity function SIM mainly solves two problems: (i) ensuring that the requirements of the project progress and the quality of the professional ability of the construction team are met; and (ii) considering the impacts of both the project priorities and pandemic in the project location on the priorities. The use of the time-cost function Min(t) mainly ensures the possibility and convenience of the allocation of the CA machine system [37]. The possibility is mainly reflected in the length of the pandemic waiting period for the main skilled workers in the construction team to resume work, while the convenience is mainly reflected in the speed of the transportation time for the main skilled workers of the construction team to resume work.

4.2.2. Parametric Analysis of the Allocation Model

The following discussion focuses on the energy similarity function, SIM, and the time-cost function, Min(t).

Energy Similarity Function: SIM

By examining the connotation and application scope of various similarity functions, the weighted Euclidean distance F(k) was chosen to determine the energy similarity; it is calculated as
F k   = k = a + 1 n φ B T b a T b k 2   ( a , k N , a < k n , )
where φ B refers to the weight vector of the energy-level index of the construction team. It is generally believed that the greater the difference of the energy-level index of each construction team in the project pool, the greater its influence on the energy level and the greater the proportion of weight and vice versa. Therefore, the weight can be characterized by the coefficient of variation of each indicator value, i.e., the standard deviation divided by the absolute value of the mean value.
φ B = 1 n 1 a = 1 n T b a 1 n a = 1 n T b a 2 / 1 n a = 1 n T b a   a N , a n
The shorter the weighted Euclidean distance, the greater the energy similarity s k . Based on the substitution of Equation (8), the corresponding projects for construction teams with similar energy levels are as follows:
K * =   k | m i n F k
To achieve a more comprehensive understanding of the energy level and similarity of the project pool, the weighted Euclidean distance between all projects can be calculated using the energy similarity matrix F G i K * . When two or more projects have high s k values for both the available and lost construction teams, and F k is smaller and multiple F k   are similar in value, K * is not unique. In this case, there will be multiple target-project construction teams that can be invoked.

Time-Cost Function: Min(t)

In this paper, the decision-making issues of allocation or recruitment are discussed from the time-as-cost perspective after matching projects with construction team of comparable energy levels.
Assume that tμ denotes the scheduling time and tz denotes the recruitment time. Consider that the starting point is a specific range (corresponding to situation II) or scheduling from a lower priority (corresponding to situations III and IV); the scheduling time is tμ = tμ1 + tμ2 + tμ3, where tμ1 represents the waiting time for the construction team to resume work (for situation II, let the waiting time for work resumption be 0), tμ2 represents the travel time (based on the public transportation time) for the construction team to be dispatched from a specific range or low-priority project to a project of an equivalent energy level, and tμ3 represents the time for adaptation to the work environment after the construction team reaches the project with an equivalent energy level. In the case of recruitment from the labor market, the actual recruitment time includes the recruitment search time, the net recruitment time, and the training and probation time, which are denoted as tz. Consider each time that an energy level-equivalent project is found: when tμ     tz, dispatch occurs; when tμ > tz, dispatch does not occur, and the recruitment of workers from the labor market is based on the energy level of the lost working group. In particular, tz is related to the difficulties of recruitment in the labor market and the severity and control of the pandemic in each region. In a pandemic situation, considering that some regions will not yet have fully allowed the free movement of personnel, the future trend is subject to further observation. It is therefore preferable to solve the problem of the work resumption of personnel in high-priority projects of construction company in a short time via systematic scheduling and then to compensate for the shortfall from the external market.
Considering the complexity of the sustainable allocation of skilled workers for the work resumption in the pool, two more scenarios must be discussed.
  • Allocation of the lost workers in a project construction team for work resumption. At moment t1, if Δ F k 10 % ,   10 % , K * is not unique, and multiple dispatch routes will be generated, and the route with the minimum combined number of dispatching instances of a project is regarded as the optimal route. When the comprehensive dispatching time is the same for both routes, the route with the fewest dispatching instances N is optimal. At this time, the mathematical expression for the decision function of the optimal route of the work resumption of construction teams in a project pool is:
    M I N t μ + t z = M I N ( t μ 1 + t μ 2 + t μ 3 ) + t z ,
    where tμ1 depends on the status of the pandemic and the degree of pandemic control at the location of the dispatched team (or potential dispatched team) at a given time (if the conditions for the resumption of construction teams are met, t μ 1 = 0 ; if the conditions for the resumption of construction teams are met, but those for the resumption of projects are not met, t μ 1 < 0 ). Moreover, tμ2 depends on the traffic and spatial distance between the project site and the location of the construction team at a certain time during the pandemic, and tμ3 is the controllable reference time, which is set as a constant empirical value. The pandemic situation and site environment at the project location at a certain moment will affect the recruitment search time tz. The decision function of the optimal route when the number of dispatching instances is equal to N is:
    M I N t μ 1 + t μ 2 + N t μ 3 + t z
    In the case of multiple routes, the route with a lower pandemic level, less frequent dispatching, and local dispatching should be chosen as the optimal route.
  • Allocation for certain types of construction teams for the resumption of projects for which the construction team has been lost. At t1, there may be several lost construction teams of the same type in the project pool (the number of such teams is L). According to the priority of L projects with lost construction teams and the basic steps outlined in Section 4.1, it is possible to allocate them independently. However, if the lost team still faces multiple K * at a certain time, there may be mutual interference among the L lost construction teams in the process of independent systematic allocation. Thus, the decision function of the optimal route is extended as:
M I N l μ t μ l + L t z
In summary, the evolutionary law of the CA of the project pool can be defined as
f 1 a , b   = f 0 a , b + 1 R a , b   *   T b k i , M i n t
where a and b, respectively, denote the numbers of projects and work types:
R a , b   =   0   1   2
Moreover, the energy level of the systematic allocation cells is as follows:
T b k i =   T b k i + 1   T z       i 0   and   i N

5. Case Study and Demonstration

5.1. Case Overview and Prioritization Evaluation of the SGJ Construction

A provincial capital city enterprise, SGJ Construction, was selected as the object of research. During the COVID-19 pandemic, the company had five projects under construction that were halted, the codes of which are respectively SX1, SX2, HB, SC, and GS. Based on online research and the compilation of data of the five projects in seven areas, including the remaining contract amount, profit per unit of time, remaining duration, quality, technical complexity, and impacts on short- and long-term strategies, as well as the combined opinions of project managers and corporate managers, the results were obtained as detailed in Table 6.
According to Equations (2) and (3), the weight value W j of each priority indicator was obtained by MATLAB 2015a software as follows:
W j =   0.4532   0.1527   0.1496   0.0978   0.0127   0.0529   0.0811
Moreover, the relative priority of each project was calculated as follows:
I i =   0.2197   0.1519   0.1778   0.1837   0.2669
From these results, it is evident that the five projects of SGJ Construction that were halted during the pandemic are not very difficult to construct, so the indicator of technical complexity was found to have the lowest weight. The indicator of the remaining contract amount was found to have the highest weight due to the variety of projects and the large differences in the remaining contract amounts. Moreover, the profit per unit of time and duration requirements are related, and their weights are equal. Finally, the impact on long-term strategies was found to have a higher index weight than the impact on short-term strategies.
The five projects of SGJ Construction at moment t 0 (before pandemic control) were initially ranked according to Equation (5), as shown in Table 7.
The pandemic impact indicators of the places where the projects were located at moment t 1 (after pandemic control; 29 February 2020) were obtained according to Equation (1), as presented in Table 8. Then, according to Equations (4) and (6), the five projects of SGJ Construction during the pandemic were ranked, as reported in Table 9.

5.2. Sustainable Allocation of the SGJ Construction Teams for Work Resumption

The sizes, skill levels, and experience values of the main in-service work types and construction teams of the five projects at moment t 0 (before pandemic control) were investigated, and the results are exhibited in Table 10. The sustainable allocation of the SGJ Construction teams to resume work was subsequently analyzed by taking reinforcement workers as an example.
The work resumption of the reinforcement workers for each project at moment t 1 (29 February 2020) is presented in Table 11.
According to Equations (11) and (12), MATLAB was employed to calculate the weighted Euclidean distance of each reinforcement worker ( G 2 ) for each project under the initial and corrected priority rankings, respectively.
F G 2 K *   = 0 1.9324 3.2093 2.7602 2.6053 1.9324 0 4.4344 4.5692 3.8199 3.2093 4.4344 0 1.9874 0.6247 2.7602 4.5692 1.9874 0 1.8867 2.6053 3.8199 0.6247 1.8867 0
F G 2 K *   = 0 1.9324 2.6053 3.2093 2.7602 1.9324 0 3.8199 4.4344 4.5692 2.6053 3.8199 0 0.6247 1.8867 3.2093 4.4344 0.6247 0 1.9874 2.7602 4.5692 1.8867 1.9874 0
For situation II, according to Equation (13), a construction team in G I I I with a high energy similarity (minimum weighted Euclidean distance) is selected out with the rank of project priority, which is GS ( P 1 ) followed by SX2 P 2 . Based on F G 2 K * , the reinforcement construction team T 24 should first be allocated to the project GS ( P 1 ), which has already met the conditions for the resumption of projects; then, the reinforcement construction team T 23 of project SC ( P 3 ) should be allocated to project SX2 ( P 5 ), which has already met the conditions for the resumption of projects. For situation III, based on the order of correction priority in the pandemic, the construction teams from G I I with high energy similarity (minimum weighted Euclidean distance) should be prepared for projects that have not yet met the resumption conditions, such as SC ( P 4 ) and HB ( P 5 ) . Based on F G 2 K * , first, the reinforcement construction team T 25 in the pandemic waiting period should be prepared for the project GS ( P 4 ), which has not met the conditions for resumption; then, the reinforcement construction team T 21 in the pandemic waiting period should be prepared for the project GS ( P 5 ), which has not met the conditions for resumption.
In this process,   Δ F k 10 % ,   10 % , K * is unique, and multi-routines and the time-cost function Min(t) are not considered.
In summary, among the five projects of SGJ Construction, two meet the conditions for project resumption, but not the conditions for the resumption of the previous construction team, which is a contrary situation to that of the two other projects. These opposing groups can complement each other. To stabilize employment, considering that t μ < t z is fully met, no external recruitment should be considered at this time. Based on the allocation model of work resumption in project pools, the following results can be obtained:
  • The cells involved in the sustainable allocation include G 2 (T21, T25; T23, T24 )   and   G 2 (T23, T24; T25, T21);
  • The energy level of each cell involved in the sustainable allocation is G 2 (T21 = T23; T25 = T24) and G 2 (T23 = T25; T24 = T21);
  • The evolution process of the cellular matrix is as follows.
A C 1 = 1 1 1 1 1 0 1 1 1 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 A C 1 = 1 1 1 1 1 1 1 0 0 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 A C 1 = 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1
The evolution of this cellular matrix is the process of the sustainable allocation of skilled workers for the work resumption in project pools of the SGJ Construction.

5.3. Result and Discussion

Results demonstrate the post-pandemic work resumption of five ongoing projects in SGJ Construction. Figure 4 and Figure 5 display the initial project prioritization and the optimized project prioritization in pandemic, respectively. Zones with darker colors show higher priority of project resumption. Figure 6 and Figure 7 present the work resumption situation without and with sustainable allocation of reinforcement workers. Green indicates the resumption of project and construction teams in this area. The red marks indicate that the workers are temporarily unable to resume work.
The comparison between Figure 4 and Figure 5 confirms that pandemic has affected project prioritization. There are two reasons for that. One is due to compulsory administrative order to shut down by the local government; the other is from a voluntary close as corporate social responsibility. For example, Project HB ran with medium priority for SGJ in Figure 4. But, under pandemic with high risk, the government’s mandatory lockdown measures continued until early April 2020. It was almost impossible to resume work in the immediate period (t1). Therefore, Project HB degraded to the lowest priority during pandemic in Figure 5. Project SC ran with higher priority for SGJ in Figure 4. Under pandemic with medium risk, local government agreed to work resumption of construction on 17 February. But considering the rise of raw materials and long-distance migration of major skilled workers, the SGJ decided to delay the start. Thus, Project SC degraded to the medium priority during pandemic in Figure 5.
The comparison between Figure 6 and Figure 7 shows that our allocation model improves the work resumption for SGJ and makes it sustainable. Construction teams that meet conditions for work resumption should be fully employed. Construction teams that fail conditions for work resumption should be allocated for the projects that did not start in the immediate period (t1). For example, Project SX1 is the only project that qualified for both resumption of production and resumption of reinforcement workers in Figure 6. Through sustainable allocation (Section 4), reinforcement construction teams T23 and T24 can be dispatched to Project GS and SX2 separately. Workers stranded due to the pandemic in T21 and T25 should be prepared for future resumption. Then, Project SX1, GS and SX2 should resume construction, and Teams T22, T23, and T24 should resume work in Figure 7.

6. Conclusions

The World Health Organization (WHO) states that impacts from COVID-19 will last for some time. Countries will have to repeat the control-resumption-control cycle to tackle the pandemic influence until it is completely over. Industries should achieve a balance between pandemic prevention and work resumption. Optimal decisions to production resumption and workforce allocation are primary for construction companies in the new normal.
This paper reports a workforce allocation model that considers four types of work resumption, the availability of construction teams, and the general project priority. The model produces optimal construction-team allocation plans. The model can guide the deployment of sustainable production resumption and abides by pandemic prevention and control policies. The model provides implications for other countries or other industries on sustainable allocation of work resumption during the pandemic.
This paper has some limitations. First, the evaluation index and allocation model can reflect on the systematic evolution of the work resumption in a project pool. Their robustness needs further case validation in practice. Second, the allocation model emphasizes the allocation method of sustainable employment in regard to social responsibility but lacks in-depth analysis on the allocation efficiency and allocation cost from the perspective of construction companies. Some factors are not included, for example, the willingness of skilled workers or government subsidies. Third, this paper uses a medium-sized construction company for case study whose results may not apply to smaller or bigger companies.
Future research can refine the allocation model to include data from other construction companies, which may lead different types of projects to work resumption. Future research can also investigate the social and economic benefits of sustainable allocation from the perspective of government and construction company under pandemic, focusing on time, cost, and labor reserve in different regions.

Author Contributions

Conceptualization, L.W.; methodology, L.W.; software, L.W.; validation, D.Z.; formal analysis, L.W.; investigation, L.W.; resources, L.W.; data curation, L.W.; writing—original draft preparation, L.W.; writing—review and editing, Y.Z.; visualization, L.W.; supervision, D.Z.; project administration, L.W.; funding acquisition, L.W. All authors have read and agreed to the published version of the manuscript.

Funding

This work was supported by the Provincial fund of Shaanxi in China under grant number 2020Z182 and New Urbanization Special Research Fund “COVID-19 Emergency Study” Special Project (number XGYJ202006).

Institutional Review Board Statement

The study was conducted according to the guidelines of the Declaration of Helsinki, and Institutional review board approval of our university was obtained for this study.

Informed Consent Statement

Informed consent was obtained from all subjects involved in the study.

Data Availability Statement

The data of pandemic comes from the link https://voice.baidu.com/act/newpneumonia/newpneumonia/; the data of Chinese policies come from the links http://www.mohrss.gov.cn/gkml/zcfg/gfxwj/202002/t20200207_358328.html and http://www.gov.cn/xinwen/2020-02/18/content_5480514.htm; the data of example come from the head of SGJ Construction.

Acknowledgments

Thanks to Shaanxi Department of Housing and Construction for its support on “COVID-19 Emergency Study” project, and thanks to SGJ Construction for its data sharing.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Liu, J.; Liu, Y.S.; Chen, X. An analysis of the influencing factors, development trend and countermeasures of labor cost rising in construction industry. J. Beijing Jiaotong Univ. 2015, 14, 45. [Google Scholar]
  2. Ministry of Human Resources and Social Security of the People’s Republic of China. Opinions on Doing a Good Job in Stabilizing Labor Relations during the Prevention and Control of the Covid-19 Pandemic and Supporting Enterprises to Work Resumption. Available online: http://www.mohrss.gov.cn/gkml/zcfg/gfxwj/202002/t20200207_358328.html (accessed on 29 February 2020).
  3. Castillo-Salazar, J.A.; Landa-Silva, D.; Qu, R. Workforce scheduling and routing problems: Literature survey and computational study. Ann. Oper. Res. 2016, 239, 39–67. [Google Scholar] [CrossRef] [Green Version]
  4. Persad, K.R.; O’Connor, J.T.; Varghese, K. Forecasting engineering manpower requirements for highway preconstruction activities. J. Manag. Eng. 1995, 11, 41–47. [Google Scholar] [CrossRef]
  5. Whang, S.W.; Flanagan, R.; Kim, S.; Kim, S. Contractor-led critical design management factors in high-rise building projects involving multinational design teams. J. Constr. Eng. Manag. 2016, 143, 06016009. [Google Scholar] [CrossRef]
  6. Zhang, X.; Luo, W.; Cai, Y. Assigning crowdsourcing project to crowdsourcing workers: A risky multi-objective optimization model. Syst. Eng. 2018, 36, 53–60. [Google Scholar]
  7. Yang, W.J.; Kim, Y.S. Manpower allocation model for construction site office engineers based on inherent technical risks. KSCE J. Civ. Eng. 2019, 23, 947–957. [Google Scholar] [CrossRef]
  8. Ballesteros-Pérez, P.; González-Cruz, M.C.; Fernandez-Diego, M. Human resource allocation management in multiple projects using sociometric techniques. Int. J. Proj. Manag. 2012, 30, 901–913. [Google Scholar] [CrossRef]
  9. Liao, P.C.; Liu, B.; Wang, Y.; Wang, X.; Ganbat, T. Work paradigm as a moderator between cognitive factors and behaviors—A comparison of mechanical and rebar workers. KSCE J. Civ. Eng. 2017, 21, 2514–2525. [Google Scholar] [CrossRef]
  10. Shahbazi, B.; Akbarnezhad, A.; Rey, D.; Fini, A.; Loosemore, M. Optimization of job allocation in construction organizations to maximize workers’ career development opportunities. J. Constr. Eng. Manag. 2019, 145, 04019036. [Google Scholar] [CrossRef] [Green Version]
  11. Mats, E.; Anna, J. The resource allocation syndrome: The prime challenge of multi-project management. Int. J. Proj. Manag. 2003, 21, 403–409. [Google Scholar]
  12. Yoshimura, M.; Fujimi, Y.; Nishiwa-Ki, S. Human resource allocation optimization for multiple development projects. Trans. Jpn. Soc. Mech. Eng. 2005, 71, 677–684. [Google Scholar] [CrossRef] [Green Version]
  13. Chen, J.; Wang, S. Method research for dynamic multi-project human resource allocation based on multidimensional model. In Proceedings of the 2011 International Conference on Information Management, Innovation Management and Industrial Engineering, Shenzhen, China, 26–27 November 2011; Volume 3, pp. 78–81. [Google Scholar]
  14. El-Abbasy, M.S.; Elazouni, A.; Zayed, T. Generic scheduling optimization model for multiple construction projects. J. Comput. Civ. Eng. 2017, 31, 04017003. [Google Scholar] [CrossRef]
  15. Yong, Z.; Zhigao, C.; Zhong, Z. Resource allocation model and strategy research of large-scale construction projects: System dynamics modeling and simulation. Chin. Manag. Sci. 2016, 24, 125–132. [Google Scholar]
  16. Hou, Y.H.; Rao, W.Z.; Hao, M. Study on multi-project human resources allocation of engineering construction enterprise-based on the perspective of competence and two-level optimization. Oper. Res. Manag. Sci. 2017, 26, 192–199. [Google Scholar]
  17. Florez, L. Crew allocation system for the masonry industry. Comput. Aided Civ. Infrastruct. Eng. 2017, 32, 874–889. [Google Scholar] [CrossRef] [Green Version]
  18. Mo, Y.; Zhao, D.; Du, J.; Syal, M.; Aziz, A.; Li, H. Automated staff assignment for building maintenance using natural language processing. Autom. Constr. 2020, 113, 103150. [Google Scholar] [CrossRef]
  19. Koch, C.; Marton, J. Implementing multi-skilled teams on a construction site-Developing a Scandinavian model? In Proceedings of the 18th Annual ARCOM Conference, Newcastle upon Tyne, UK, 2–4 September 2002; pp. 247–256. [Google Scholar]
  20. Thomas, H.R.; Horman, M.J. Fundamental principles of workforce management. J. Constr. Eng. Manag. 2006, 132, 97–104. [Google Scholar] [CrossRef]
  21. Walter, M.; Zimmermann, J. On a multi-project staffing problem with heterogeneously skilled workers. Oper. Res. Proc. 2012, 127, 489–494. [Google Scholar]
  22. Li, W.; Peng, L.; Zhang, D. Analysis on the mechanism of the heterogeneity of project construction team leaders affecting post competence. J. Railw. Sci. Eng. 2019, 16, 1857–1864. [Google Scholar]
  23. Anoshkina, Y.; Meisel, F. Technician teaming and routing with service-, cost- and fairness-objectives. Comput. Ind. Eng. 2019, 135, 868–880. [Google Scholar] [CrossRef]
  24. Drezet, L.; Billaut, J. A project scheduling problem with labor constraints and time-dependent activities requirements. Eur. J. Oper. Res. 2008, 112, 217–225. [Google Scholar]
  25. Nasirian, A.; Arashpour, M.; Abbasi, B.; Zavadskas, E.K.; Akbarnezhad, A. Skill set configuration in prefabricated construction: Hybrid optimization and multicriteria decision-making approach. J. Constr. Eng. Manag. 2019, 145, 04019050. [Google Scholar] [CrossRef]
  26. Nasirian, A.; Arashpour, M.; Abbasi, B. Critical literature review of labor multiskilling in construction. J. Constr. Eng. Manag. 2019, 145, 04018113. [Google Scholar] [CrossRef]
  27. Sarihi, M.; Shahhosseini, V.; Banki, M.T. Multiskilled project management workforce assignment across multiple projects regarding competency. J. Constr. Eng. Manag. 2020, 146, 04020134. [Google Scholar] [CrossRef]
  28. Baidu. Real-Time Big Data Report of the Pandemic. Available online: https://voice.baidu.com/act/newpneumonia/newpneumonia/ (accessed on 29 February 2020).
  29. State Council of the Central People’s Government of the People’s Republic of China. Guidance Opinions on the Prevention and Control of New Coronary Pneumonia Pandemic through Scientific Prevention and Precise Measures in Zones and Grades. Available online: http://www.gov.cn/xinwen/2020-02/18/content_5480514.htm (accessed on 29 February 2020).
  30. Shannon, C.E. Prediction and Entropy of Printed English; Oxford University Press: Oxford, UK, 1951. [Google Scholar]
  31. Bi, A.; Luo, Z.; Wang, X.; Sun, Y. Extension model weighted by vague sets and entropy method and its engineering application. Syst. Eng. 2018, 36, 112–120. [Google Scholar]
  32. Wang, L.-Y. A research to build and operate the BIM-L database for supply-side reform of skilled workers in construction industry. J. Xi’an Univ. Arch. Tech. 2020, 39, 67–73. [Google Scholar]
  33. Chao, X.; Yang, Y.; Zhou, Z. Simulation of risk transfer in enterprise group based on Cellular Automaton. Chin. J. Manag. Sci. 2012, 20, 144–150. [Google Scholar]
  34. Wolfram, S. Statistical mechanics of Cellular Automaton. Rev. Mod. Phys. 1983, 55, 601–643. [Google Scholar] [CrossRef]
  35. Rong, L.; Zhou, P.; Rong, Z. A consequence deduction model of emergency based on one-dimensional cellular automata. Oper. Res. Manag. Sci. 2015, 24, 158–160. [Google Scholar]
  36. Lindgren, K.; Mats Nordahl, G. Universal computation in simple one-dimensional Cellular Automaton. Complex Syst. 1990, 4, 299–318. [Google Scholar]
  37. Bosurgi, G.; Pellegrino, O.; Sollazzo, G. Project duration evaluated using affine arithmetic. Period. Polytech. Civ. Eng. 2017, 61, 412–420. [Google Scholar] [CrossRef] [Green Version]
Figure 1. A map of the nationwide COVID-19 pandemic in China.
Figure 1. A map of the nationwide COVID-19 pandemic in China.
Sustainability 13 06481 g001
Figure 2. Energy-level assessment indicator system of a construction team in a project pool.
Figure 2. Energy-level assessment indicator system of a construction team in a project pool.
Sustainability 13 06481 g002
Figure 3. Allocation state at t 1 .
Figure 3. Allocation state at t 1 .
Sustainability 13 06481 g003
Figure 4. The initial project prioritization.
Figure 4. The initial project prioritization.
Sustainability 13 06481 g004
Figure 5. The optimized project prioritization in pandemic.
Figure 5. The optimized project prioritization in pandemic.
Sustainability 13 06481 g005
Figure 6. Work resumption without sustainable allocation of the reinforcement workers during pandemic.
Figure 6. Work resumption without sustainable allocation of the reinforcement workers during pandemic.
Sustainability 13 06481 g006
Figure 7. Work resumption with sustainable allocation of the reinforcement workers during pandemic.
Figure 7. Work resumption with sustainable allocation of the reinforcement workers during pandemic.
Sustainability 13 06481 g007
Table 1. Introduction to specialists.
Table 1. Introduction to specialists.
Work UnitTitleNumberAge (Avg.)Work Experience (Avg.)Method
UniversitiesProfessor2408Face-to-face
Construction companiesManager34512Online (WeChat)
Table 2. The basic indicators and evaluation criteria for priorities of projects in a project pool.
Table 2. The basic indicators and evaluation criteria for priorities of projects in a project pool.
Indicator SystemEvaluation Criteria
0.8–10.6–0.80.4–0.60.2–0.40–0.2
Remaining contract amount
A1
Very largeLargeAverageSmallVery small
More than 50% of the total remaining amount of the annual
contract of the
enterprise
30–50% of the total remaining amount of the annual contract of the enterprise10–30% of the total remaining amount of the annual contract
of the enterprise
5–10% of the total remaining amount of the annual contract of the enterpriseLess than 5% of the total remaining amount of the annual
contract of the enterprise
Profit per unit of time
A2
Very largeLargeAverageSmallVery small
More than 50% above the average enterprise level10–50% above the average enterprise levelWithin 10% of the average enterprise level10–50% below the average enterprise levelMore than 50% below the average enterprise level
Remaining duration
A3
Very highHighNormalLowVery low
More than 20% longer than the normal duration of similar projects10–20% longer than the normal duration of similar projectsWithin 10% of the normal duration of similar projects 10–20% shorter than the normal duration of similar projectsMore than 20% shorter than the normal duration of similar projects
Quality
A4
Very highHighNormalLowVery low
Exceeding the enterprise quality
standards and
proposing to apply for national awards
Exceeding the
enterprise quality standards and
proposing to apply for awards in the administration region
Meeting corporate quality standardsLower than the
quality standards of the enterprise and higher than national and local standards
Lower than local standards, higher than mandatory
national standards
Level of technical complexity
A5
Very highHighAverageLowVery low
The technical
difficulty factor is much higher than the average for similar projects
The technical
difficulty factor is slightly higher than the average for
similar projects
The technical
difficulty factor is at the average level of similar projects
The technical difficulty factor is slightly lower than the average for
similar project
The technical
difficulty factor is well below the
average for similar projects
Impact of the project on short-term
enterprise strategies
A6
SignificantLargeGeneral SmallVery small
Project success or failure is a sufficient condition for the achievement of short-term strategiesProject success or failure is a necessary condition for the achievement of short-term strategiesProject success or failure is a condition for the achievement of short-term
strategies
Project success or failure has less
impact on short-term strategies
Project success or failure has no impact on short-term
strategies
Impact of the project on long-term
enterprise strategies
A7
SignificantLargeGeneralSmallVery small
Project success or failure is the only basis for adjusting long-term strategiesProject success or failure is an
important criterion for adjusting long-term strategies
Project success or failure is one of the bases for adjusting long-term strategiesProject success or failure has less
impact on short-term strategies
Project success or failure has no impact on long-term
strategies
The average level of the contract amount can be adjusted according to the overall situation of the project pool (); replacing the contract amount with the remaining contract amount is favorable for transferring quality resources from projects nearing completion to new or longer projects during the construction process. Replacing the total construction period with the remaining construction period is conducive for the system to grasp the current situation of the delay or advance of the construction period. Enterprise quality standards are generally higher than local standards and mandatory national standards.
Table 3. Pandemic impact indicators and evaluation criteria of projects.
Table 3. Pandemic impact indicators and evaluation criteria of projects.
Indicator System Evaluation Criteria
0.90.70.50.30.1
Pandemic levels of the province (municipality directly under the
authority of the central government or
autonomous region)
C i P r o v .
High risk Relatively high risk Medium risk Relatively low risk Low risk
Cumulative number of confirmed cases ≥10,000Cumulative number of confirmed cases between 1000–9999Cumulative number of confirmed cases between 100–999Cumulative number of confirmed cases between 10–99Cumulative number of confirmed cases between 1–9
Local pandemic level
C i C T Y .
High risk Relatively high riskMedium risk Relatively low riskLow risk
The pandemic risk level of each county or city (district) published during the reporting period shall prevail (adjusted every 14 days)
Table 4. The initial allocation matrix of construction teams before (without) a pandemic in a project pool.
Table 4. The initial allocation matrix of construction teams before (without) a pandemic in a project pool.
Type of WorkProject Prioritization (from Highest to Lowest)
P1P2PaPn
G1T11T12T1aT1n
G2T21T22T2aT2n
GbTb1Tb2TbaTbn
GmTm1Tm2TmaTmn
Table 5. The analysis of the work resumption for a project and its construction team in a pandemic.
Table 5. The analysis of the work resumption for a project and its construction team in a pandemic.
SituationResumption of
Projects
Resumption of Construction TeamsTotal NumberProject SetConstruction Team SetAnalysis
IConditions are in place to resume
projects
Conditions are in place to resume construction teams n I U I G I Direct work resumption without
reallocation
IIConditions are in place to resume
projects
Failure to meet
conditions for the
resumption of
construction teams
n I I U I I G I I The main allocations
IIIFailure to meet
conditions for the resumption of
projects
Conditions are in place to resume construction teams n I I I U I I I G I I I The construction team is allocated into II in time
IVFailure to meet
conditions for the
resumption of
projects
Failure to meet
conditions for the
resumption of
construction teams
n I V U I V G I V Make pre-arrangements for the work resumption of subsequent projects and waiting workers
Table 6. Aggregate scores of priority indicators for each project in the SGJ.
Table 6. Aggregate scores of priority indicators for each project in the SGJ.
Priority IndicatorProject Pool
SX1SX2HBSCGS
A10.660.220.380.270.70
A20.500.400.600.850.72
A30.300.700.500.500.50
A40.500.500.500.800.70
A50.500.600.500.500.55
A60.600.450.500.550.70
A70.500.700.500.700.80
Table 7. The initial prioritization ranks of projects in the SGJ.
Table 7. The initial prioritization ranks of projects in the SGJ.
Initial Prioritization Rank of Project Pools
GSSX1SCHBSX2
P 1 P 2 P 3 P 4 P 5
Table 8. Pandemic impact indicators and revised priority score for the SGJ Construction locations.
Table 8. Pandemic impact indicators and revised priority score for the SGJ Construction locations.
Project CodeSX1SX2HBSCGS
C i 0.050.050.810.250.03
I i 0.2090 0.1445 0.0791 0.1431 0.2590
Table 9. The revised priority ranking of projects in the SGJ during pandemic.
Table 9. The revised priority ranking of projects in the SGJ during pandemic.
Revised Prioritization Ranking of Project Pools
GSSX1SX2SCHB
( P 1 ) ( P 2 ) ( P 3 ) ( P 4 ) ( P 5 )
Table 10. The initial allocation of the SGJ Construction teams to the energy level of the main work.
Table 10. The initial allocation of the SGJ Construction teams to the energy level of the main work.
Type of WorkProject Pool
GS ( P 1 ) ( P 1 ) SX 1 ( P 2 ) ( P 2 ) SC ( P 3 ) ( P 4 ) HB ( P 4 ) ( P 5 ) SX 2 ( P 5 ) ( P 3 )
Carpenter, G1T11T12T13T14T15
Reinforcement worker, G2T21T22T23T24T25
Concrete worker, G3T31T32T33T34T35
Masonry worker, G4T41T42T43T44T45
Plasterer, G5T51T52T53T54T55
Scaffolder, G6T61T62T63T64T65
Table 11. The work resumption of the reinforcement workers in project pool during pandemic.
Table 11. The work resumption of the reinforcement workers in project pool during pandemic.
SituationResumption of ProjectsResumption of Construction TeamsProject SetConstruction Team Set
IConditions are in place to resume projectsConditions are in place to resume construction teams U I   = {SX1} G I   = {T22}
IIConditions are in place to resume projectsFailure to meet conditions for the resumption of construction teams U I I   = {GS, SX2} G I I   = {T21, T25}
IIIFailure to meet conditions for the resumption of projectsConditions are in place to resume construction teams U I I I   = {SC, HB} G I I I   = {T23, T24}
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Wang, L.; Zhao, D.; Zhong, Y. Sustainable Allocation Model of Construction Workforce for Work Resumption during COVID-19. Sustainability 2021, 13, 6481. https://doi.org/10.3390/su13116481

AMA Style

Wang L, Zhao D, Zhong Y. Sustainable Allocation Model of Construction Workforce for Work Resumption during COVID-19. Sustainability. 2021; 13(11):6481. https://doi.org/10.3390/su13116481

Chicago/Turabian Style

Wang, Layin, Dong Zhao, and Yanqi Zhong. 2021. "Sustainable Allocation Model of Construction Workforce for Work Resumption during COVID-19" Sustainability 13, no. 11: 6481. https://doi.org/10.3390/su13116481

APA Style

Wang, L., Zhao, D., & Zhong, Y. (2021). Sustainable Allocation Model of Construction Workforce for Work Resumption during COVID-19. Sustainability, 13(11), 6481. https://doi.org/10.3390/su13116481

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop