1. Introduction
Aerial work with helicopters has been conducted in the construction industry for many decades. Its introduction into practice resulted from the successful development of a previously unknown type of aircraft with rotating wings—the helicopter. Serial production of the first type of helicopter began during World War II, in 1942. This historic milestone was the start of a qualitatively different stage in the development of helicopters, which were no longer just an experiment, but at that time a perfect serial aircraft that allowed for various uses in military and civilian spheres [
1]. In Slovakia, or in the territory of the former Czechoslovakia, aerial work using helicopters in the construction industry began in 1957 [
2] (
Figure 1). Despite its relatively long history, the technology of aerial work using helicopters has not been surpassed in many respects to the present.
Nowadays, sustainability is becoming a fundamental requirement in almost every field of human activity, and helicopter aerial technology-based work is invaluable in sustainability terms, especially in an environmental context. Its extremely specific character provides diverse possibilities for use, mainly outside built-up areas and especially in mountainous areas, which comprise a substantial part of the territory of Slovakia. In mountainous locations, there are often legally protected areas, such as national parks, protected landscapes, or nature reserves, particularly vulnerable to any human intervention [
3]. However, such areas are sometimes found outside mountain units, in flat landscapes. Unlike the conventional, ground-based construction method, the land and ecosystem are not disturbed during such aerial work [
4,
5], meaning there is no need to establish or extend access roads [
6,
7]. In addition to the inevitable accompanying construction traffic, these may also contribute to the deforestation of the landscape with their possible concomitant consequences. There is no need for the establishment of material stockpiles or other components of site equipment (these will only be constructed at a location when it is advantageous and permissible), and there is no need for significant ground disturbance.
Aerial work in which helicopters are used is also proving its benefits in areas with less or no nature protection, such as the densely built-up inner zones of large cities. They are also used in the reconstruction of existing buildings [
8]. As a result of the above side effects, construction work carried out by helicopters can be cheaper than it would be with conventional ground technology, and its time duration can be shorter. Therefore, we can also talk about economic sustainability—characteristic for aerial work that it is carried out in a three-dimensional space (the atmosphere), which is strongly influenced by the current weather conditions primarily [
9]. Thus, the very nature of aerial work naturally implies that its preparation is more demanding compared to that of conventional technologies [
8]. Therefore, it is necessary to choose such means and methods that will help to ensure (to some extent) not only the obvious environmental sustainability, but also the real economic and practical benefits of this technology, and thus, ultimately, the legitimacy of its existence and the long-term sustainability of this method of construction.
The concept of this article is based on the following assumptions: (1) Helicopters are a suitable alternative for work under difficult natural conditions in terms of environmental and economic sustainability, (2) the use of helicopters is significantly affected by weather conditions, and (3) the preparation of aerial work using helicopters is demanding and requires the use of more complex tools, such as simulation modeling.
Helicopters are used in the construction industry in many countries, but it is a very demanding technology. Its use depends on several factors associated with the design of the helicopter itself, its mode of movement, and the specific, especially weather, conditions in which it can operate.
In Slovakia, the use of helicopters is currently diverse. For example, in 2011–2012, construction of the connection between the northern and southern sides of Chopok Peak in the Low Tatras by cableways commenced. This demanding construction project posed a logistical challenge, and helicopters played a significant role in its successful implementation. Helicopters were used in the concrete and assembly processes on the difficult-to-access construction site, situated on both sides of the mountain ridge and just below the summit of Chopok at an altitude of 2003 m above sea level.
Helicopters are also used in the Czech Republic, where, for example, from 2011 to 2014 a new cableway was built to the highest Czech mountain, Sněžka (1603 m above sea level) [
10]. The construction site was, for the most part, located in the first zone of the Krkonoše National Park. It is an area of arctic–alpine tundra, which is very sensitive to any human activities. Construction work in this area cannot be carried out using conventional heavy construction equipment, so the use of helicopters was an acceptable solution.
Around the world, the work of helicopters in construction is handled by several specialized companies that use various types of helicopters from renowned manufacturers. One of the best-known companies is the Swiss company Heliswiss International AG, which operates mainly in the Alpine countries and in Western Europe. The company operates Kamov KA 32 and AS 332 helicopters.
Helicopters have been used in the United States of America (USA) in the construction of many electrical transmission lines. Helicopters allow construction work to be completed in terrain, where the deployment of conventional equipment is problematic for technical and environmental reasons. Construction of the “Susquehanna to Roseland Electric Reliability Project” is one of many such projects. The objective of the project was to construct a 500 kV transmission line from Pennsylvania to New Jersey [
6]. The projected route of the power line crossed a freshwater wetland at the Troy Meadows site, which is protected by the U.S. Environmental Protection Agency. In this 12.5 km
2 area, seven poles of the original 230 kV line were located and needed to be replaced with new poles for the proposed 500 kV line.
Helicopter construction technology eliminated the risks associated with the construction and maintenance of access roads with a minimum area of 10,000 m
2 and paved work areas with an additional area of 11,000 m
2, which also posed a threat to protected plant and animal species. Thanks to the technology used, the implementation of the project was carried out with minimal impact on the surrounding environment of the Troy Meadows Conservation Area [
6].
In some situations, the responsible authorities may even prohibit the use of ground-based technology altogether, as was the case with the construction of the 161 kV “Jack Rabbit—Big Sky” power transmission line. The terrain conditions, especially the environmental protection measures, again did not allow the construction of access roads, so most of the construction work (installation of masts, including equipment, backfilling, stretching, and installation of wires) was carried out by helicopters [
7].
The extensive portfolio of helicopter constructions of this type in the USA has been complemented by the “230 kV Northern Intertie Transmission Line” project, which dealt with the construction of a 154 km-long electric transmission line running through the subarctic zone of Alaska [
11]. It has also been complemented by the replacement of two damaged poles of the 138 kV “Koolau–Pukele” line in Hawaii, under the extreme terrain and weather conditions of the mountain ridge [
12]. Helicopters also find application in diametrically different areas of construction; for example, in the project to replace the suspension cables on the Luling Bridge (Luling, LA, USA), they enabled elegant elimination of inappropriate loading of the bridge deck by heavy truck cranes [
13].
Thorough construction–technological preparation is required for aerial work using helicopters because during the construction preparation stage, it is still possible to significantly influence the overall concept and organization of the construction of such projects. Due to the complexity of aerial work using helicopters, which are subject to a number of random influences (especially variable weather conditions), it is necessary to use more complex tools during preparation, such as simulation modeling. This can perfectly prepare the course of helicopter work even under difficult construction conditions, while taking into account technical, technological, economic, and environmental aspects.
The influence of weather conditions on construction is of interest to many authors. To assess the severity of this impact, several authors have successfully used a simulation approach (such as Lee et al. [
14] and Jung et al. [
15]). The authors AbouRizk and Wales [
16], who investigated the influence of weather on the completion of earthworks using neural networks, also dealt with considerations for weather conditions in the planning of the construction process. Their research took into account the influence of three meteorological elements: precipitation activity and the maximum and minimum daily air temperatures. The authors did not deal with the influence of other factors or with the possible change in their influences due to changing seasons. Muhabie et al. [
17] investigated the simulation of the process of constructing unconventional structures, such as offshore wind farms, which, in addition to weather conditions, also simulated the sea level.
Based on an analysis of the impact of weather conditions on labor productivity, Lee et al. [
14] stated that weather conditions have a significant impact on labor productivity, with some meteorological elements having a greater impact than others. Jung et al. [
15] described a simulation model based on a future weather generator at the construction site of high-rise buildings. The basis of the simulation model is a weather generator, on the basis of which the expected construction delay relative to the impact of adverse weather conditions can be determined and incorporated into the construction schedule.
Weather generators are based on the values of meteorological elements, measured at ground level. However, according to the authors, this can be a problem in the construction of high-rise buildings because weather conditions change with increasing height; changing conditions may therefore affect the course of construction of the upper floors of a high-rise building. To solve this problem, the authors proposed a simulation model that took into account the correlation between altitude and weather conditions. The proposed model was verified on a 50-story office building. The simulation results pointed out several facts, namely: that without taking into account the influence of altitude, there are significant differences in estimating the degree of dependence of the construction process on weather conditions; that observed differences increase with the height of the structure; that time series of meteorological elements, especially wind speeds, do not appear in the one-year seasonal component; that seasonality is natural for the values of meteorological elements [
15].
The main element of such simulation models is a weather generator. This is classified among the numerical models, “artificially” creating the values of individual meteorological elements on a daily basis. These data have the same probability distribution as the historical weather data entered into the generator [
18]. Generators are used in the creation of simulation models in various areas of industries, e.g., in agriculture, ecology, and in the generation of electricity in wind power plants [
19]. A statistical set of historical data on weather conditions in the area is entered into the generator. Based on such, using probability theory and mathematical statistics, the generator simulates the values of individual meteorological elements such as precipitation, temperature and relative humidity, and wind speed. These are variables that ultimately affect labor productivity and costs, and they may even interrupt work [
20].
The simulation of future weather conditions at the construction site, carried out on the basis of historical data, is associated with a certain degree of inaccuracy. According to Kim and Augenbroe [
21], these computational models do not adequately capture the randomness and uncertainty associated with weather forecasting. Other differences may also occur in connection with gradual climate change [
22]. Our research shows that it is possible to increase the accuracy of the data entering the simulation model and, thus, increase the rate of approximation to the actual conditions at the construction site by using one of the commercially available numerical weather forecasting models. These models provide the necessary short-term forecast (e.g., [
23]). We applied this approach in our next solution (
Section 2.3).
Partial conclusion: According to the analysis, research in the field of simulation modeling in the preparation of buildings is only in its infancy, and several authors have emphasized the need to publish other works using the simulation approach. In their works, many of them have already dealt with simulating future weather conditions and evaluating their impact on the construction process, but only conventional processes have been simulated, especially using conventional cranes and other common construction equipment.
Helicopters have long been used in various areas of construction and today are a tool without which construction work would not be possible to complete efficiently, or at all in some cases. They are applied to a broad spectrum of activities in mountain and developed areas. In Slovakia, however, the preparation of aerial work is still carried out in a traditional way. The key parameter, which is the helicopter payload capacity, is determined manually by means of its load capacity nomogram in paper form (
Section 2.2).
In the case of designing a construction process to be performed by a helicopter, the effectiveness of the final solution becomes the key criterion. Due to the specifics of these aerial works and their susceptibility to many factors, it is more difficult to predict their actual course using traditional deterministic models. Any resulting inaccuracy in time and cost planning will then negatively affect the entire construction process. A suitable tool for determining the optimal variant is simulation modeling, which adequately represents the authenticity of variable conditions in real-world construction practice. Balakchina and Shalenny [
8], in their work, pointed out the need to verify various variants of technological procedures in aerial work using simulation modeling.
The elaboration of such a topic will make it possible to verify the potential applications of the simulation approach in another little-explored area of the construction industry, which will ultimately contribute to the wider application of progressive simulation modeling tools in construction practice. It will also create a framework for developing institutional education in simulation. It is these areas that several contemporary authors have described as being the most problematic.
The results of such a solution could be usable in the future outside the construction industry, especially in logistics. Applied knowledge from the use of various numerical weather forecasting models can also be beneficial for the field of numerical meteorology. The idea of an interdisciplinary approach is in line with the recommendations of various authors around the world, including, for example, Lee et al. [
24].
3. Results
As part of the solution of this research task, a simulation program was designed, which was subsequently verified using the examples of the construction of cableway systems in Poland and Slovakia.
When processing the case study that focused on the construction of the U Kowalskiego—Hala Skrzyczeńska (Szczyrk, Poland) cableway via aerial work technology, the simulation model, due to the nature of aerial works in the construction industry, was based on the principles of discrete simulation. In technical terms, it was a standard mass-produced single-cab cableway pertaining to the circulatory system, with detachable carriers. Due to the fact that most of the input data were discrete in nature, the model was designed directly in the MATLAB environment in the form of a so-called live script, which represents direct writing of the algorithm using MATLAB’s own programming language but enriched with interactive controls and interpretation of the algorithm’s outputs in real time. This method, due to its illustrative nature and relative simplicity, is also very advantageous from a pedagogical point of view. By choosing this option, it simultaneously responds to the opinion of some authors pointing out the need to include the issue of simulation in university curricula, e.g., [
24].
When assessing the severity and overall impact of individual factors on helicopter operation, we also relied on the knowledge and experience of aviation practice. Therefore, factors that show a low or negligible level of significance were not considered in the solution of the simulation model. Due to this reason, the issue of head and tail winds was narrowed down to general wind speeds in accordance with planning procedures in aviation practice and in accordance with the capabilities of the used numerical weather prediction models. A key part of the simulation model is the provision of meteorological input data. This part was designed on the basis of several follow-up steps with successive approximation of the data using different numerical weather prediction models, provided by the SHMÚ.
Relevant numerical weather forecasts are under steady-state conditions within 10 days at most. Therefore, in this section, a two-step procedure was proposed, with the first one being the planning of the implementation of the aerial works at a maximum of 10 days before the requested date. In the second step, from three days before the planned event to its expected date, local models with a higher resolution were used. Thanks to these models, it is possible to confirm the expected nature of the weather and to specify the actual date and duration of implementation. In this interval, it is possible to re-evaluate decisions made every six hours—at 00:00, 06:00, 12:00, and 18:00 UTC, or every one to three hours in the case of rapid update models.
The input data on the loads, their number, and their weight were taken from the weight tables provided to the contractor by the manufacturer of the cableway. The loads were the individual parts of the tubular shafts of the track supports. Information on the length of the transport route for each load was obtained from the longitudinal profile drawing of the cableway route. The transport distance of the load was determined as the so-called developed length between the lower station and the implemented structure (track support). A total of 25 loads were transported in this way. This stage of the research represented the verification of the simulation model, while the simulation results themselves were in line with the assumptions and confirmed the logical and factual correctness of the proposed simulation model.
In this step of the solution, the outputs from the ALADIN prediction model were modified in cooperation with the SHMÚ for use in the simulation model in the form of a data file with a defined format. Thus, the discrete data in a computer-processable form for a specific raster point (the construction site) were obtained. The SHMÚ currently generates this data file in the aforementioned interval of every six hours. The interpretation of the new forecast and its impact on the construction work thus only becomes a matter of relaunching the simulation model with the appropriate data file at the input.
In the case of a wider application of the proposed concept, even more advanced automation can be applied as well, and the data file can be downloaded and loaded automatically from the forecast provider. An example of graphically interpreted input data from the ALADIN numerical prediction model for the needs of the simulation model in the Bachledova dolina location (Slovakia) is shown in
Figure 7.
Figure 7a shows the predicted air temperature over the next 72 h at various altitude levels of the Earth’s atmosphere.
Figure 7b expresses, by analogy, the predicted course of the wind speed.
The possibilities of practical use of the simulation were then shown in the example of the construction of the Bachledova dolina–Malá Poľana cableway (Slovakia). From a technical point of view, it was the same type of cableway as in the previous case. Both facilities are similar in terms of technical parameters—the developed length is 1518.57 m, the elevation of the route is 264.40 m, and there are nine supports along the route. Two variants of the assembly process were assessed, which differed only in the start time of the work. In variant 1, the start of assembly was planned within 50 h of the beginning of the validity of the forecast in use; in variant 2, this period was 10 h of the beginning of its validity, which corresponds to a difference of approximately 1.5 days. The resulting values of the individual variants of the aerial work on this construction differed mainly in the duration of unfinished work (0 vs. 73.40 min), which was caused mainly by changing weather conditions at the construction site (
Figure 7a,b) and, thus, the inability of the helicopter to fly in, in certain cases, due to its maximum load capacity at the given time.
We consider the results obtained by the simulation to be credible because they are very close to those that are usually achieved in practice in the case of this type of construction and also fully justify the use of a simulation in the preparation of aerial works in the construction industry. An example of one of the possible graphic outputs of the simulation in the form of a histogram of work durations for the two process variants is shown in
Figure 8a,b and analogously in the form of a box plot in
Figure 9a,b.
The presented analysis shows that the determined capacity of a helicopter by its manufacturer may not be easy to achieve in practice, so it is necessary to respect the influence of randomly changing construction conditions and, at the same time, the specific conditions of the helicopter’s work during the preparation of the construction processes implemented by the helicopter. The complexity of such a system can therefore be appropriately modeled using the above simulation models.
4. Discussion
This work can be considered a loose continuation of the work [
15], which dealt with the influence of weather conditions on the construction of high-rise buildings. The construction work carried out by helicopters can, in a sense and after some simplification, be considered as an analogy for carrying out construction work on such type of buildings. In contrast to the mentioned work, in which the weather forecast at the construction site was obtained using a weather generator, we used the numerical weather prediction model, which provided a vertical weather profile automatically without the need to calculate it. We believe that, in the case of work performed by helicopters, this method is more suitable, especially in connection with the high sensitivity of a helicopter to changes in weather conditions that affect its basic technological properties. Another advantage of this method is the ability to predict weather conditions that have not occurred in the past, which is especially important in the context of climate change [
15,
22].
The basic idea of simulation modeling in the preparation of buildings is to replicate as closely as possible the situation at the intended real construction site. The importance of this step is emphasized by Balakchina and Shalenny [
8], who stated that the number of flight hours and the price per flight hour of a helicopter are often the main factors influencing the cost of the process; therefore, it is appropriate to verify the proposed process by simulation and choose the most advantageous among the different variants. Thus, when setting up the simulation model for helicopter work, other specific issues that must be addressed for the use of a helicopter at a construction site have emerged and are the subject of discussion:
On what basis does a helicopter pilot make decisions in relation to the overall organization of aerial work?
How and at what intervals is the refueling of a helicopter fuel tank handled during the execution of this work?
How do the slenderness of the load and its area affect the flight of a helicopter, especially with respect to wind loads or rotation of the load in the helicopter’s undercarriage?
Which aspects determine the deployment of a particular type of helicopter at a particular construction site?
Which activities before, during, and after aerial work can be considered negligible for simulation purposes, and which cannot be considered so?
With the intention of capturing the course of helicopter work as authentically as possible, and thus increasing the value of the simulation model, we also consulted these points in reference to aviation practice. However, despite the efforts made, it is possible that the simulation model may need to be corrected slightly (refined) for its eventual wider use. Within the framework of the performed case study, but as well as during the verification of the model, we focused on the solution of the construction of cableway supports, i.e., on the assembly process. This focus resulted, on the one hand, from the available possibilities of capturing actual projects within a permissible timeframe and, on the other hand, from the availability of the necessary documentation that was available to the authors of the article due to their professional backgrounds. The presented issue is quite extensive; therefore, these examples are seen more as clues that point the way to the possible further use of both simulation models and numerical weather prediction at the present level in the preparation of any type of building.
The simulation model can be further extended and refined in the future. It seems to be an interesting idea to consider three important points during the helicopter flight instead of one, taking into account the expected weather conditions. These points are the helicopter’s home airfield (often located hundreds of kilometers from the construction site, sometimes in a neighboring country), the helicopter’s take-off area in the field, and the construction site itself. Using current numerical weather prediction capabilities, attention can also be focused on the solution of the entire helicopter flight path and altitude profile, both during the overflight to the construction site and during the actual construction. This brings the simulation even closer to objective reality, where the boundary conditions change naturally over time [
24].
The design and implementation of the simulation model was performed in the sense of the greatest possible future flexibility, so the model can be used in any construction process, including important and technologically more complicated concrete processes. Simulation of the concreting process would be carried out in an analogous way to the assembly process, in principle, with only one difference: the input weights of the loads must be given to take into account the weight of the concrete basket together with the weight of the fresh concrete itself in the basket. In this case, it is advisable to add to the simulation model the continuous monitoring of the duration of the stay of the truck mixer with fresh concrete at the site and the subsequent alert in case the total processing time of the fresh concrete at the site exceeds its permissible workability time. In the case of the assembly process, it is possible to address the priority of the transported loads so that the assembly of horizontal load-bearing structures does not precede the assembly of vertical load-bearing structures. In the simulation model, this situation can occur, e.g., by omitting flight with a vertical structure due to adverse weather.
The issue of the weight of the fuel in the tanks, the amount of which in practice is unique for each building project, also proves to be extremely interesting. Refining the amount of fuel and its effect on a helicopter’s payload capacity at a particular site may represent a noteworthy direction for future research, which involves not only the economic plane, but also the environmental one. However, due to its nature (the flight part), it must be carried out in close cooperation with the airline operator, which alone has the necessary know-how. In this context, we state that, in the field of aerial work with helicopters in construction, there is a lack of professional literature, and cooperation with companies is therefore the only real way to obtain important information.
In addition to the Mi-8 helicopter type, the database of input data can be supplemented with other frequently used helicopter types (especially the Mi-17 type under the conditions of the Central Europe region), and the simulation solution can also consider various random phenomena occurring in practice and a suitable way of taking them into account—particularly the randomness of helicopter malfunctions, the randomness of traffic complications, and other phenomena that could have an impact on the course of the solved process. Depending on their degree of significance, they can be solved using appropriate coefficients (deterministically) or stochastically. The input data can be checked qualitatively using appropriate statistical methods, e.g., normality tests. In terms of outputs, it is possible to extend the statistical indicators or graphs offered.
The outputs of the proposed simulation model can be automatically implemented in the future in the processes of construction–technological preparation. This means that the basic technological documents (construction schedule, financial plan, etc.), nowadays usually processed on a computer using specialized software, can, as a result of their optimization on the basis of the simulation model outputs, more accurately replicate the reality of construction, especially in the area of defining the necessary time and financial reserves and the resulting technological impacts. This approach would also allow these documents to be updated in real time according to the work actually being carried out, which will significantly increase their level of practical usability. At the same time, this also fulfils one of the main requirements for any type of planning, namely, the necessity of keeping plans up to date, which is often problematic.
Thus, the output can be an operational (short-term) time plan, which brings benefits not only to the general contractors and subcontractors of aerial works, but also to the investors and the public. Construction contractors will appreciate the knowledge of the exact situation, especially in the coordination of construction processes, where the model will help project managers. Airline operators will obtain an automated system that will save time compared to manual processing and will allow the ability to verify alternative scenarios in the event of operational delays due to adverse weather, which, in practice, occurs very often. Balakchina and Shalenny [
8] noted that the achievement of efficiency in aerial work using a helicopter directly depends on the ability of the construction contractor to take into account the characteristics of the helicopter and the overall quality level of construction technology preparation, with regard to the technological and organizational regularities of such work. We share this view. The optimization of schedules and financial plans and the determination of necessary reserves with the application of simulation outputs could, in practice, contribute to the elimination of helicopter downtime in the field, e.g., due to adverse weather or the incorrect sequence of works, to the minimization of the required number of flights to the construction site and various loss times, or to the determination of the optimal amount of aviation fuel to be transported to the construction site by tanker truck, and thus to maximize the efficiency of this method of construction implementation.
Thanks to the advanced preparation of the construction work, the investors, as well as the public, will also appreciate the accompanying environmental aspect. This aspect is of particular importance in the case of helicopter work, both in mountainous areas (minimizing the negative impact on protected natural areas) and in built-up areas (minimizing the unavoidable accompanying noise characteristic of helicopter operations). Thanks to this approach, investors and contractors can also ultimately prove that they apply the philosophy of corporate social responsibility (CSR). At present, this means an indisputable benefit on the market, especially in the interest of sustainable development. It also helps to build a positive image of the organization.
At the same time, the economic efficiency of the aerial work achieved should allow this environmentally friendly technology to be used wherever it represents a technically ideal solution and not substituted by ground-based alternatives with a higher risk of impact on the surrounding environment solely due to price ranges. We are of the opinion that a similar approach, using simulations, could find application again in a broader context beyond aerial work, using helicopters in a time of gradual digitalization of the construction industry in the spirit of Industry 4.0 ideas. In connection with the used concept of the simulation model, based on various types of numerical weather forecast models, we consider it appropriate to mention that, even in the case of a fully automatic decision-making system designed in this way, in practical terms, we recommend consulting a professional meteorological service in the 48 or 24 h preceding actual implementation of a work plan. Under the conditions of Slovakia, it is therefore advisable to contact the Slovak Hydrometeorological Institute, which deals with current weather 24 h a day.
Lee et al. [
24] emphasized the benefits of teaching simulation at universities because simulation allows students to model problems from everyday life, experiment with different scenarios and variants, and observe changes. We share this view; we think that it is the variety of solutions that simulation provides in principle that can lead students to an analytical way of thinking, and thus an understanding of how to solve real-world problems in engineering practice, which normally requires making a choice from different options based on established criteria.
On the other hand, simulation tools have relatively high demands on computing power, which may not be easy to provide, especially from a financial point of view. Another problem associated with teaching can be the considerable amount of time needed to build the simulation model and logistical and financial complexity in obtaining input data. Knowledge of programming was also required to build the simulation model in our work. However, from a practical point of view, it is possible (both in teaching and in practice) to build the model using software that is based on prepared building blocks. In this way, the compilation of the model is accelerated, and the focus of the work can be devoted to experimenting with it, and thus finding the optimal variant of the process, which students will appreciate, especially in engineering practice.