Eco-Economic Performance Estimation Method for Pretensioned Spun High-Strength Concrete Pile Installation
Abstract
:1. Introduction
1.1. Research Background
1.2. Research Aim and Scope
2. Literature Review
3. Eco-Economic Performance Estimation System for PHC Pile Installation
3.1. System Structure and Components
- Simulation modeling and system setting (input variables: Resources and tasks, system and datasheets)
- Simulation execution (processing and calculation)
- Results analysis (finding probabilities under limitations)
3.2. System Process
3.2.1. Simulation Modeling and Input Variables for Modeling Component
- Cement and water mixture is used for grouting and additional grouting and is subsequently removed from the system.
- The PHC pile is moved to the work spot by the payloader, connected to the crawler crane, and installed at the location. When a rebound check is performed, it is removed from the system.
- The mixer, payloader, and excavator each perform a single task of mixing, moving piles, and removing slime, respectively. The pump injects cement paste during grouting and performs additional grouting tasks.
- The crew performs axis adjustment, pile connection, and rebound check in a cyclical manner.
- The crawler crane cyclically performs axis adjustment, drilling, removing the auger, pile connection, pile erection, removing casing, rebound check, and moving to another axis.
3.2.2. Simulation Execution and Result Analysis
4. Test Case
4.1. Simulation Modeling of the PHC Pile Installation Process
4.2. Simulation Experiment Results and Discussion
5. Conclusions
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Conflicts of Interest
Appendix A
Appendix A.1. Duration Calculation
Appendix A.2. Emission Calculation
Appendix A.3. Cost Calculation
- Drilling
- 1.1
- Machine Cost
- 1.1.1
- Crane
- 1.1.2
- Auger
- 1.1.3
- Electricity Generator
- 1.2
- Crew Cost
- Inserting Piles
- Hammering Piles
- Transporting Piles
- Grouting
- 5.1
- Pump
- 5.2
- Mixer
- 5.3
- Electricity Generator
- Desliming
- Subtotal
References
- Babu, S.S.; Kathirvel, M.; Nayak, V.N. Study and Analysis of Pile Foundation Supported on Sandwich Soil Strata under Dynamic Condition. Mater. Today Proc. 2020, 37, 861–867. [Google Scholar] [CrossRef]
- Misra, A.; Basu, D. A Sustainable Approach to Foundation Design. In Proceedings of the 13th PanAmerican Conference on Soil Mechanics and Geotechnical Engineering and 64th Canadian Geotechnical Conference, Toronto, ON, Canada, 2–6 October 2011. [Google Scholar]
- Zayed, T.M.; Halpin, D.W. Deterministic Models for Assessing Productivity and Cost of Bored Piles. Constr. Manag. Econ. 2005, 23, 531–543. [Google Scholar] [CrossRef]
- Ametepey, O.; Aigbavboa, C.; Ansah, K. Barriers to Successful Implementation of Sustainable Construction in the Ghanaian Construction Industry. Procedia Manuf. 2015, 3, 1682–1689. [Google Scholar] [CrossRef]
- Masih-Tehrani, M.; Ebrahimi-Nejad, S.; Dahmardeh, M. Combined Fuel Consumption and Emission Optimization Model for Heavy Construction Equipment. Autom. Constr. 2020, 110, 103007. [Google Scholar] [CrossRef]
- Wu, B.; Xuan, K.; Shen, X.; Zhao, Q.; Shi, Y.; Kong, L.; Hu, J.; Li, X.; Zhang, H.; Cao, X.; et al. Non-Negligible Emissions of Black Carbon from Non-Road Construction Equipment Based on Real-World Measurements in China. Sci. Total Environ. 2022, 806, 151300. [Google Scholar] [CrossRef]
- Tu, R.; Li, T.; Meng, C.; Chen, J.; Sheng, Z.; Xie, Y.; Xie, F.; Yang, F.; Chen, H.; Li, Y.; et al. Real-World Emissions of Construction Mobile Machines and Comparison to a Non-Road Emission Model. Sci. Total Environ. 2021, 771, 145365. [Google Scholar] [CrossRef]
- Lee, D.-E.; Yi, C.-Y.; Lim, T.-K.; Arditi, D. Integrated Simulation System for Construction Operation and Project Scheduling. J. Comput. Civ. Eng. 2010, 24, 557–569. [Google Scholar] [CrossRef]
- Ahn, C.; Pan, W.; Lee, S.H.; Peña-Mora, F. Enhanced Estimation of Air Emissions from Construction Operations Based on Discrete-Event Simulation. In Proceedings of the EG-ICE 2010—17th International Workshop on Intelligent Computing in Engineering, Leuven, Belgium, 30 June–3 July 2019; Volume 30. [Google Scholar]
- Ahn, C.; Xie, H.; Lee, S.H.; Abourizk, S.; Peña-Mora, F. Carbon Footprints Analysis for Tunnel Construction Processes in the Preplanning Phase Using Collaborative Simulation. In Proceedings of the Construction Research Congress 2010: Innovation for Reshaping Construction Practice—Proceedings of the 2010 Construction Research Congress, Banff, AB, Canada, 8–10 May 2010; pp. 1538–1546. [Google Scholar]
- González, V.; Echaveguren, T. Exploring the Environmental Modeling of Road Construction Operations Using Discrete-Event Simulation. Autom. Constr. 2012, 24, 100–110. [Google Scholar] [CrossRef]
- Yi, C.Y.; Gwak, H.S.; Kim, B.S.; Lee, D.E. Stochastic Multi-Variate Performance Trade-off Method for Technical Tender Evaluation. KSCE J. Civ. Eng. 2018, 22, 4240–4253. [Google Scholar] [CrossRef]
- Park, Y.J.; Yi, C.Y. Resource-Based Quality Performance Estimation Method for Construction Operations. Appl. Sci. 2021, 11, 4122. [Google Scholar] [CrossRef]
- Kumara, H.P.S.G.S.; Zainudeen, N.; Jayasanka, T.A.D.K.; Waidyasekara, K.G.A.S. Barriers in Implementing Sustainable Piling Construction Practices in Sri Lanka. In Proceedings of the 9th World Construction Symposium, Moratuwa, Sri Lanka, 9–10 July 2021; pp. 147–159. [Google Scholar] [CrossRef]
- Shan, M.; Hwang, B.G.; Zhu, L. A Global Review of Sustainable Construction Project Financing: Policies, Practices, and Research Efforts. Sustainability 2017, 9, 2347. [Google Scholar] [CrossRef]
- Abhijit, G.; Samriddhi, S. Site Investigation Techniques for Ground Improvement. Int. J. Res. Appl. Sci. Eng. Technol. 2017, 5, 35–39. [Google Scholar]
- Ojo, E.M.; Mbohwa, C.; Akinlabi, E.T. Greening the Construction Industry. In Proceedings of the Proceedings of the 2015 International Conference on Operations Excellence and Service Engineering, Orlando, Florida, USA, 10–11 September 2015; pp. 581–591. [Google Scholar]
- Salimi, S.; Mawlana, M.; Hammad, A. Performance Analysis of Simulation-Based Optimization of Construction Projects Using High Performance Computing. Autom. Constr. 2018, 87, 158–172. [Google Scholar] [CrossRef]
- Pujadas-Gispert, E.; Sanjuan-Delmás, D.; de la Fuente, A.; Moonen, S.P.G.; Josa, A. Environmental Analysis of Concrete Deep Foundations: Influence of Prefabrication, Concrete Strength, and Design Codes. J. Clean. Prod. 2020, 244, 118751. [Google Scholar] [CrossRef]
- Pujadas-Gispert, E.; Sanjuan-Delmás, D.; Josa, A. Environmental Analysis of Building Shallow Foundations: The Influence of Prefabrication, Typology, and Structural Design Codes. J. Clean. Prod. 2018, 186, 407–417. [Google Scholar] [CrossRef]
- Saravanan, V. Cost Effective and Sustainable Practices for Piling Construction in the UAE Thesis. Master’s Thesis, Heriot Watt University, Edinburgh, UK, 2011; pp. 1–97. [Google Scholar]
- Luo, W.; Sandanayake, M.; Zhang, G. Direct and Indirect Carbon Emissions in Foundation Construction—Two Case Studies of Driven Precast and Cast-in-Situ Piles. J. Clean. Prod. 2019, 211, 1517–1526. [Google Scholar] [CrossRef]
- Yeung, A.T. Innovative Installation Techniques for PHC Piles. In Proceedings of the ICE HKA Annual Conference 2015 Thinking out of the Box in Infrastructure Development Andretrofitting, Hong Kong, China, 24 April 2015; Volume 75, pp. 279–286. [Google Scholar]
- Kaplan, H.; Elburg, A.; Tommelein, I.D. Analysis of Variability in Precasting and Installation of Pile Foundations. In Proceedings of the Construction Research Congress 2005: Broadening Perspectives—Proceedings of the Congress, San Diego, CA, USA, 5–7 April 2005; pp. 23–32. [Google Scholar]
- Zayed, T.M. Productivity and Cost Assessment for Continuous Flight Auger Piles. J. Constr. Eng. Manag. 2005, 131, 677–688. [Google Scholar] [CrossRef]
- Zayed, T.M.; Halpin, D.W. Quantitative Assessment for Piles Productivity Factors. J. Constr. Eng. Manag. 2004, 130, 405–414. [Google Scholar] [CrossRef]
- Zayed, T.M.; Halpin, D.W. Simulation of Bored Pile Construction. In Proceedings of the Winter Simulation Conference Proceedings, Orlando Florida, USA, 14–18 December 2000; IEEE: Piscataway, NJ, USA, 2001; Volume 2, pp. 1495–1503. [Google Scholar]
- Zayed, T.M.; Halpin, D.W. Simulation as a Tool for Pile Productivity Assessment. J. Constr. Eng. Manag. 2004, 130, 394–404. [Google Scholar] [CrossRef]
- Zayed, T. Stochastic Productivity Assessment of Continuous Flight Auger Piles. Archit. Sci. Rev. 2009, 52, 17–27. [Google Scholar] [CrossRef]
- Zayed, T.M.; Halpin, D.W. Concrete Bored Piles Construction Productivity Assessment Using Regression Analysis. In Proceedings of the Annual Conference—Canadian Society for Civil Engineering, Montreal, QC, Canada, 5–8 June 2002; Volume 2002, pp. 415–423. [Google Scholar]
- Zayed, T.M.; Halpin, D.W. Productivity and Cost Regression Models for Pile Construction. J. Constr. Eng. Manag. 2005, 131, 779–789. [Google Scholar] [CrossRef]
- Zayed, T.M.; Halpin, D.W. Pile Construction Productivity Assessment. J. Constr. Eng. Manag. 2005, 131, 705–714. [Google Scholar] [CrossRef]
- Zayed, T.M.; Halpin, D.W. Process versus Data Oriented Techniques in Pile Construction Productivity Assessment. J. Constr. Eng. Manag. 2004, 130, 490–499. [Google Scholar] [CrossRef]
- Misra, A. A Multicriteria Based Quantitative Framework for Assessing Sustainability of Pile Foundations. Master’s Thesis, University of Connecticut, Storrs, CT, USA, 2010; p. 124. [Google Scholar]
- Misra, A.; Basu, D. A Quantitative Sustainability Indicator System for Pile Foundations. In GeoCongress 2012: State of the Art and Practice in Geotechnical Engineering; ASCE: Reston, VA, USA, 2012; pp. 4252–4261. ISBN 9780784412121. [Google Scholar]
- Halpin, D.; Riggs, L. PLanning and Analysis of Construction Operations.Pdf; John Wiley & Sons: Hoboken, NJ, USA, 1994; ISBN 047155510X. [Google Scholar]
- Hu, J.; Sun, C. 3D Geological Modeling Based on Boreholes Data and Application in Underground Engineering. In Proceedings of the 3rd International Symposium on Information Science and Engineering, ISISE. Shanghai, China, 24–26 December 2010; IEEE: Piscataway, NJ, USA, 2010; pp. 409–411. [Google Scholar]
- Zhang, X.; Zhang, J.; Tian, Y.; Li, Z.; Zhang, Y.; Xu, L.; Wang, S. Urban Geological 3d Modeling Based on Papery Borehole Log. ISPRS Int. J. Geo-Inf. 2020, 9, 389. [Google Scholar] [CrossRef]
- Zang, F. Application of 3D Geological Modeling in Geological Exploration. In Frontier Computing; Lecture Notes in Electrical Engineering; IEEE: Piscataway, NJ, USA, 2022; Volume 827, pp. 1021–1025. [Google Scholar]
- Penman, J.; Gytarsky, M.; Hiraishi, T.; Irving, W.; Krug, T. 2006 IPCC—Guidelines for National Greenhouse Gas Inventories. Directrices para los Inventar. Nac. GEI 2006, 2, 12. [Google Scholar]
Type | Model | Fuel (L/h) | Cost (KRW */h) |
---|---|---|---|
Crawler crane | Pile driver (DHP-80), auger (100 P), drop hammer (3 ton) | 28 | 341,588 |
Excavator | 02 (ec55c) | 8 | 43,345 |
Payloader | FR 15 | 11 | 41,731 |
Pump | Electricity generator (350 kw) and compressor (Ingersoll-Rand 825) | 10 | 29,133 |
Mixer | Plant (2000 × 4800 × 3200) and bulk silo (40 ton) | 15 | 30,000 |
Components | Predecessor | Successor | Time Delay Function * or Entity Initialization | Involved Resource(s) | ||
---|---|---|---|---|---|---|
ID | Name | Type | ||||
1 | Crawler crane | Cyclic resource queue | 31 | 3 | 1 | Crawler crane |
2 | Crew | Cyclic resource queue | 29, 22 | 3, 29 | 1 | Crew |
3 | Axis adjustment | Combi | 1, 2 | 14, 20 | Normal (0.88, 0.18) | Crawler crane Crew |
4 | PHC pile | Noncyclic resource queue | - | 6 | 299 | PHC pile |
5 | Payloader | Cyclic resource queue | 6 | 6 | 1 | Payloader |
6 | Moving pile | Combi | 4, 5 | 5, 21 | Normal (1.06, 0.05) | Payloader PHC pile |
7 | Cement | Noncyclic resource queue | - | 10 | 299 | Cement |
8 | Water | Noncyclic resource queue | - | 10 | 299 | Water |
9 | Mixer | Cyclic resource queue | 10 | 10 | 1 | Mixer |
10 | Mixing | Combi | 7, 8, 9 | 9, 11, 12 | Normal (4.18, 0.48) | Mixer Cement Water |
11 | Grouting ready | Idle queue | 10 | 16 | - | Grout |
12 | Additional grouting ready | Idle queue | 10 | 27 | - | Add. Grout |
13 | Pump | Cyclic resource queue | 16, 27 | 16, 27 | 1 | Pump |
14 | Drilling | Normal | 3 | 15 | According to ground Level and types | Crawler crane |
15 | Ready for grouting | Idle queue | 14 | 16 | - | Crawler crane |
16 | Removing auger and grouting | Combi | 11, 13, 15 | 13, 24 | Normal (1.11, 0.15) | Crawler crane Pump Grout |
17 | Ready for desliming | Idle queue | 29 | 19 | - | Soil |
18 | Excavator | Cyclic resource queue | 30 | 19 | 1 | Excavator |
19 | Desliming | Combi | 17, 18 | 30 | Normal (11.5, 1.23) | Excavator Soil |
20 | Ready for pile Connection | Idle queue | 3 | 22 | - | Crew Crawler crane PHC pile |
21 | Pile available | Idle queue | 6 | 22 | - | PHC pile |
22 | Pile connection | Combi | 20, 21 | 2, 23 | Normal (0.52, 0.01) | Crew Crawler crane PHC pile |
23 | Pile ready | Idle queue | 22 | 25 | - | Crawler crane PHC pile |
24 | Crane ready | Idle queue | 16 | 25 | - | Crawler crane |
25 | Pile erection and Placement | Combi | 23, 24 | 26 | Normal (1.04, 0.10) | Crawler crane |
PHC pile | ||||||
26 | Ready for Additional grouting | Idle queue | 25 | 27 | - | Crawler crane |
27 | Removing casing & Additional grouting | Combi | 12, 13, 26 | 13, 28 | Normal (1.63, 0.22) | Crawler crane Pump Add. Grout |
28 | Ready for Rebound check | Idle queue | 27 | 29 | - | Crawler crane |
29 | Rebound check | Combi | 2 | 28 | Normal (1.36, 0.12) | Crawler crane Crew |
30 | Counter | Counter | 19 | 18 | - | - |
31 | Move to another axis | Normal | 29 | 1 | Normal (3.62, 0.95) | Crawler crane |
Pile Number | Ground (meter) | Soil (meter) | Drilling (meter) | Drilling Task Time (minutes) |
---|---|---|---|---|
1 | 0.6522 | 11.0952 | 11.7475 | 11.13 |
2 | 0.6559 | 10.9824 | 11.6383 | 11.03 |
3 | 0.6567 | 10.8516 | 11.5083 | 10.90 |
4 | 0.6575 | 10.7303 | 11.3877 | 10.79 |
5 | 0.6582 | 10.6080 | 11.2662 | 10.67 |
… | … | … | … | … |
295 | 1.8542 | 8.5922 | 10.4464 | 9.62 |
296 | 1.9883 | 8.5647 | 10.5530 | 9.69 |
297 | 2.1272 | 8.5362 | 10.6634 | 9.77 |
298 | 2.2189 | 8.5063 | 10.7252 | 9.81 |
299 | 2.2613 | 8.5087 | 10.7700 | 9.84 |
Performance | PDF & Parameters | Minimum | Maximum | Limitation | Probability |
---|---|---|---|---|---|
Duration (min) | Normal (mu = 5653.37 sigma = 29.26) | 5593 | 5724 | 5700 | 95.91% |
Cost (KRW) | Normal (mu = 45,792,009.78 sigma = 206,076.23) | 45,286,330 | 46,348,105 | 46,000,000 | 84.36% |
Emission (kgCO2) | Gamma (a = 58,984.36 b = 0.21) | 12,107 | 12,366 | 12,200 | 30.97% |
Category | Duration (day) | Cost (KRW) | Emissions (ton) |
---|---|---|---|
Simulation (average) | 11.8 * | 45,792,009 | 12.23 ** |
CSPR and IUC | 8.5 | 27,577,938 | 13.35 *** |
Contract | 15 | 46,412,076 | - |
Site results | 17 (12) | 46,412,076 | - |
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations. |
© 2022 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Yi, C.-Y.; Park, J.-Y.; Park, C.-Y.; Lee, J.-C.; Park, Y.-J. Eco-Economic Performance Estimation Method for Pretensioned Spun High-Strength Concrete Pile Installation. Sustainability 2022, 14, 11990. https://doi.org/10.3390/su141911990
Yi C-Y, Park J-Y, Park C-Y, Lee J-C, Park Y-J. Eco-Economic Performance Estimation Method for Pretensioned Spun High-Strength Concrete Pile Installation. Sustainability. 2022; 14(19):11990. https://doi.org/10.3390/su141911990
Chicago/Turabian StyleYi, Chang-Yong, Jin-Young Park, Chan-Young Park, Jun-Cheol Lee, and Young-Jun Park. 2022. "Eco-Economic Performance Estimation Method for Pretensioned Spun High-Strength Concrete Pile Installation" Sustainability 14, no. 19: 11990. https://doi.org/10.3390/su141911990
APA StyleYi, C. -Y., Park, J. -Y., Park, C. -Y., Lee, J. -C., & Park, Y. -J. (2022). Eco-Economic Performance Estimation Method for Pretensioned Spun High-Strength Concrete Pile Installation. Sustainability, 14(19), 11990. https://doi.org/10.3390/su141911990