Settlement Analysis of Ground Surface and Adjacent Building Caused by Driving and Expansion Excavation of Shield Tunnel Using Artificial Freezing Method
Abstract
:1. Introduction
2. Project Overview
2.1. Project Overview and Freezing Parameters
2.2. Geological Situation
- (1)
- The strata are mainly composed of quaternary loose sediments, the underlying bedrock is buried deep, and the quaternary overburden thickness is larger, all of which are over 50 m.
- (2)
- Artificial accumulation layer: the surface layer along the project is covered with artificial accumulation layer, which is mainly sandy silt fill and miscellaneous fill.
- (3)
- Quaternary alluvium: It is distributed under the artificial accumulation layer. The lithology is mainly clay, silt, and sand layers, and the stratigraphic distribution is relatively stable.
2.3. Monitoring Scheme
3. Numerical Model Establishment and Excavation Simulation
3.1. Geometry and Boundary Conditions
3.2. Material Properties
3.3. Excavation Simulation
- (1)
- In the initial stage, only gravity load is applied to generate the initial stress field of the stratum.
- (2)
- In the freezing construction, the displacement caused by each stage in the early stage is cleared. The stress field is retained and the corresponding parameters of the designed freezing zone outside the tunnel are changed to frozen soil parameters.
- (3)
- When the shield is excavated for one ring, the surface load of the excavation face is activated to act as the earth pressure to maintain the balance of the excavation face.
- (4)
- When the shield machine continues to excavate, the first ring segment is activated. When the shield machine is driven to the second ring, the surface load of the excavation face at the first ring is frozen. Meanwhile, the surface load of the excavation face at the second ring is activated.
- (5)
- Cycle steps (3) and (4) until excavation to the 44th ring.
4. Effects of Freezing Excavation of Shield Tunnel on Segments, Soil Layer, and Vertical Displacement of Buildings
4.1. Deformation Analysis of Shield Segment
4.1.1. Deformation of Shield Segment in Frozen Layer
- (1)
- The frozen layer strengthened the elastic modulus and stability of the soil, and the soil disturbance caused by tunnel excavation was reduced accordingly. The displacement of segments in the frozen layer was analyzed using numerical simulation. The maximum settlement value of the segment caused by tunnel excavation was 3.1 mm, and the maximum settlement point was located at the crown of the segment, close to the connection between the frozen layer and the nonfrozen layer. The maximum heave value of the segment was 2.9 mm, and the maximum heave point was located at the bottom of the segment, which is also near the connection between the frozen layer and the nonfrozen layer.
- (2)
- In general, the frozen layer plays an important role in reducing the soil disturbance caused by shield excavation. The maximum settlement and heave occurred at the junction of the frozen and nonfrozen layers because the elastic modulus and integrity of the soil in the nonfrozen layer were weakened. The maximum settlement value and the maximum heave value of the segment were used to calculate the convergence of the segment in the limit state. The convergence value of the ultimate clearance was 6 mm, which meets the control value of 12.4 mm clearance convergence required by the standard [23].
4.1.2. Deformation of Shield Segment in Nonfrozen Layer
- (1)
- When excavation is carried out in the nonfrozen layer, because of the lack of reinforcement of the frozen layer, the soil disturbance increases the displacement of the segment. The displacement of segments in the nonfrozen layer was analyzed using numerical simulation. The maximum settlement value of segment caused by tunnel excavation was 8.6 mm, and the maximum settlement point was located at the crown of segment. The maximum heave value of the segment was 10 mm, and the maximum heave point was located at the bottom of the segment.
- (2)
- The maximum settlement value and the maximum heave value of the segment were used to calculate the convergence of the segment in the limit state. The convergence value of the ultimate clearance was 18.6 mm, which did not meet the control value of 12.4 mm clearance convergence required by the standard [23]. The main reason is that synchronous grouting was not considered in the numerical simulation, which caused the displacement of the segment to be too large.
- (1)
- The segment displacement caused by the shield in the frozen layer is within the reasonable range controlled by the standard [23]. The main reason for the large displacement of pipe segments caused by excavation in the nonfrozen layer is that the effect of grouting was not considered in the numerical simulation. Supervision should be strengthened in field construction to avoid construction accidents.
- (2)
- During excavation, the segment displacement of the frozen layer is about one-third of that of the nonfrozen layer. The frozen layer effectively improves the stability of the soil; the elastic modulus of the soil is increased by about 5–10 times. The segment displacement caused by shield tunneling is effectively reduced.
4.2. Surface Settlement Analysis
- (1)
- The strata were uniformly arranged horizontally when the model was established, and the inclined strata were not set.
- (2)
- The effect of grouting was not considered in the numerical simulation.
- (3)
- The assumption that the lining is an elastic material led to differences from the field situation.
- (1)
- Except for the surface settlement data from DBC-4, the surface displacement above the frozen layer is mainly upward heave. Because of the good stability of the frozen layer, it is difficult to deform the soil downward. However, in the process of shield excavation, the face pressure leads to the overall upward deformation of the frozen layer, and finally the surface displacement becomes a state of heave.
- (2)
- In the process of shield excavation, the soil disturbance is further reduced because the frozen layer is close to the underground diaphragm wall of the station. The surface settlement is within the allowable range of the standard [23]. The frozen layer effectively controls the surface settlement.
4.3. Vertical Displacement Analysis of Buildings
- (1)
- JGC-1, JGC-3, and JGC-5 are vertical displacement monitoring points of buildings near the tunnel. Before the tenth step, the three monitoring points produced heave, and the heave value of JGC-1 was the largest, with a maximum of 10 mm. The main cause of the heave was the disturbance of the soil in front of the shield face pressure. After the tenth step, the settlement of JGC-1 occurred rapidly, and the maximum settlement value was 15 mm. The maximum settlement value of JGC-3 and JGC-5 did not exceed 5 mm. The main reason is that the frozen layer strengthens the soil, and the surface settlement of JGC-1 and JGC-3 near the frozen layer is also relatively small.
- (2)
- JGC-2, JGC-4, and JGC-6 are vertical displacement monitoring points of buildings away from the tunnel. A large heave occurred at JGC-4, with a maximum heave value of 14.7 mm. The main reason was that the elastic modulus of soil at the boundary of the frozen layer and nonfrozen layer became smaller, and the soil stability became worse. At this time, JGC-4 was rapidly heaved under the influence of the shield face’s pressure. The other two measuring points mainly experienced settlement displacement, and the maximum settlement value was 11.9 mm.
- (3)
- JGC-5 and JGC-6 are in the same cross-section but at different distances from the frozen layer. The maximum settlement value of JGC-6 was 9.8 mm. The maximum settlement value of JGC-5 was 4.9 mm. JGC-5 is located above the frozen layer, which strengthens the surrounding soil and restrains the deformation of the soil. JGC-6 is far away from the frozen layer, the formation disturbance caused by excavation was obvious, and the strengthening effect of the frozen layer was weak. Finally, the settlement velocity and value of JGC-6, which is far away from the frozen layer, were greater than that of JGC-5.
- (4)
- The maximum vertical settlement difference between JGC-1 and JGC-2 was 14.8 mm. The maximum vertical settlement difference between JGC-3 and JGC-4 points was 14.1 mm. The maximum vertical settlement difference between JGC-5 and JGC-6 points was 13.9 mm. These data were less than 15 mm, within the range required by the standard [23]. The differential settlement of the buildings meets the requirements.
5. The Influence of Frozen Layer, Soil, and Vertical Displacement of Building Caused by Frozen Expansion of Shield Tunnel
5.1. Support Design Parameters
5.2. Tunnel Freezing Expansion Simulation
- (1)
- The full-face frozen excavation method
- (2)
- The partial face frozen excavation method
5.3. Frozen Expansion Results of Shield Tunnel
5.3.1. The Full-Face Frozen Excavation Method
5.3.2. The Partial Face Frozen Excavation Method
- (1)
- Deformation analysis of frozen layer
- (2)
- Analysis of land surface settlement
- (1)
- DBC-9 to DBC-11 is located directly above the initial expansion part. Surface settlement occurred at the beginning of excavation, the surface settlement gradually increased to 2.5 mm, and then the soil disturbance gradually stabilized. As the frozen layer strengthened the soil, the surface settlement did not increase.
- (2)
- DBC-4 to DBC-8 is directly above the middle of the expansion section. At the beginning of excavation, surface heave occurred, and the surface heave value gradually increased to 1.6 mm. With the progress of excavation, the disturbance of excavation to soil gradually increased, and the surface displacement gradually changed from heave to settlement. When the surface settlement value reached 2.5 mm, the surface settlement tended to be stable and no longer increased.
- (3)
- DBC-1 to DBC-3 is at the end of the expansion section. At the beginning of excavation, the monitoring point was relatively far away from the excavation tunnel. The surface displacement was mainly heave, and the maximum heave value was less than 1 mm. The three monitoring points are located at the boundary between the frozen and nonfrozen layers. With the progress of excavation, the disturbance of soil increased. The surface displacement gradually changed from heave to settlement, and the maximum settlement value reached 2.7 mm. There was no stable trend of surface settlement.
- (3)
- Vertical displacement of buildings
- (1)
- JGC-1, JGC-3, and JGC-5 are vertical displacement monitoring points of buildings near the tunnel. JGC-5 is closest to the expanded tunnel, and the soil disturbance is the most intense. The settlement of JGC-5 was severe in the whole process of expansion. The maximum settlement value was 8.3 mm and then tended to be stable. The settlement trends of JGC-3 and JGC-1 were basically the same, and the maximum settlement value was 6.2 mm. The settlement displacements of the three monitoring points were all within the allowable range of the standard [23], which proves the practicability of the partial face frozen excavation method.
- (2)
- JGC-2, JGC-4, and JGC-6 are the vertical displacement monitoring points of buildings away from the tunnel. JGC-6 rapidly settled with a maximum settlement value of 8.1 mm. JGC-2 and JGC-4 were heaves with maximum bulges of 4 mm.
- (3)
- JGC-5 and JGC-6 are in the same cross-section of the frozen layer but at different distances. Before step 10, JGC-6 settled relatively quickly. The maximum settlement value was 4.1 mm. Before step 10, JGC-5 settled slowly. The maximum settlement value was 2.2 mm. The main reason is that JGC-5 is close to the frozen layer, which strengthens the surrounding soil and restrains the deformation of the soil. Although JGC-6 is farther away than JGC-5, the hardening effect of the frozen layer is weaker, and the soil disturbance is more obvious.
- (4)
- Among the six measuring points, the largest building settlement difference was 12.3 mm. These data were less than 15 mm, within the range required by the standard [23]. The differential settlement of the buildings meets the requirements.
5.4. Construction Safety Control Measures
- (1)
- In the process of excavation, temporary steel supports should be set in time. Horizontal and vertical reinforcement supports should be set.
- (2)
- Grouting behind the freezing wall should be performed in time after excavation.
- (3)
- The top of the frozen soil should be set up with pressure relief holes. According to the monitoring of surface settlement, grout should be injected during settlement and released during heave.
- (4)
- Real-time dynamic monitoring of the temperature of the frozen pipe and the melting of frozen soil should be implemented, and emergency plans should be made.
6. Recommendations and Limitations
- (1)
- Surface settlement or vertical displacement of buildings at the boundary between frozen and nonfrozen layers should be strictly monitored.
- (2)
- The surface settlement or vertical displacement of buildings far away from the same cross-section of the frozen layer should be strictly monitored.
- (3)
- For the expansion of large diameter shield tunnel, the partial face excavation method should be preferred.
- (1)
- This study is for water-rich sand strata, and the conclusions drawn may not be applicable to rock strata.
- (2)
- In the numerical simulation, the lining and shield are regarded as linear elastic materials, and the soil is regarded as a uniform elastic–plastic material. These assumptions lead to some errors between the numerical model and the actual project.
- (3)
- The numerical simulation does not consider the influence of grouting and the freeze–thaw cycle. It can be added to the numerical simulation in future research to further improve the accuracy of the numerical model.
7. Conclusions
- (1)
- The deformation of the lining in the nonfrozen layer is about three times that of the lining in the frozen layer. The convergence of the ultimate clearance of the lining in the nonfrozen layer is 1.5 times that of the lining in the frozen layer. The maximum deformation value of the frozen layer in full section excavation scheme is 4.5 times that of the frozen layer in partial excavation. Through these data, it can be found that the freezing layer has an obvious effect on limiting the displacement of the lining.
- (2)
- When the tunnel is excavated normally, the surface settlement value above the frozen layer is within 2 mm. The surface settlement values above the frozen layer are all within 3 mm when the subdivision is extended. The frozen layer improves the integrity and mechanical parameters of the soil, and with the reinforcement of the underground diaphragm wall, the surface settlement is effectively reduced.
- (3)
- The vertical settlement of the building on the side away from the frozen layer is greater than that on the side near the frozen layer. The main reason is that the frozen layer strengthens the surrounding soil, but this strengthening effect decreases with increasing distance. In the numerical simulation of partial face frozen excavation, the maximum vertical settlement value of the building was 9.8 mm, and the difference value of the maximum vertical settlement was 12.3 mm. All these data prove that the excavation is feasible.
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Conflicts of Interest
References
- Jones, J.S. State-of-the-art report—Engineering practice in artificial ground freezing. Eng. Geol. 1981, 18, 313–326. [Google Scholar] [CrossRef]
- Afshani, A.; Akagi, H. Artificial ground freezing application in shield tunneling. Jpn. Geotech. Soc. Spec. Publ. 2015, 3, 71–75. [Google Scholar] [CrossRef]
- Russo, G.; Corbo, A.; Cavuoto, F.; Autuori, S. Artificial ground freezing to excavate a tunnel in sandy soil. measurements and back analysis. Tunn. Undergr. Space Technol. 2015, 50, 226–238. [Google Scholar] [CrossRef]
- Li, S.; Lai, Y.; Zhang, M.; Zhang, S. Minimum ground pre-freezing time before excavation of guangzhou subway tunnel. Cold Reg. Sci. Technol. 2006, 46, 181–191. [Google Scholar] [CrossRef]
- Han, L.; Ye, G.L.; Li, Y.H.; Xia, X.H.; Wang, J.H. In-situ monitoring of frost heave pressure during cross passage construction using ground freezing method. Can. Geotech. J. 2016, 53, 530–539. [Google Scholar] [CrossRef]
- Zhou, J.; Zhao, W.; Tang, Y. Practical prediction method on frost heave of soft clay in artificial ground freezing with field experiment. Tunn. Undergr. Space Technol. 2021, 107, 103647. [Google Scholar] [CrossRef]
- Liu, J.; Ma, B.; Cheng, Y. Design of the Gongbei tunnel using a very large cross-section pipe-roof and soil freezing method. Tunn. Undergr. Space Technol. 2018, 72, 28–40. [Google Scholar] [CrossRef]
- Zhang, D.M.; Chen, C.C.; Zhang, D.M. Ground surface movement of Shallow-Buried Large-Sectional tunnel under Full-Ring Pipe-Jacking roof and ground freezing. Tunn. Undergr. Space Technol. 2022, 127, 104600. [Google Scholar] [CrossRef]
- Cai, H.; Hong, R.; Xu, L. Frost heave and thawing settlement of the ground after using a freeze-sealing pipe-roof method in the construction of the Gongbei Tunnel. Tunn. Undergr. Space Technol. 2022, 125, 104503. [Google Scholar] [CrossRef]
- Ding, Z.; Wei, X.J.; Wei, G. Prediction methods on tunnel-excavation induced surface settlement around adjacent building. Geomech. Eng. 2017, 12, 185–195. [Google Scholar] [CrossRef]
- Zheng, L.; Gao, Y.; Zhou, Y. A practical method for predicting ground surface deformation induced by the artificial ground freezing method. Comput. Geotech. 2021, 130, 103925. [Google Scholar] [CrossRef]
- Xiang, H.; Zhang, G.; Cheng, P. Analyses of the Ground Surface Displacement under Reinforcement Construction in the Shield Tunnel End Using the Artificial Ground Freezing Method. Appl. Sci. 2023, 13, 8508. [Google Scholar] [CrossRef]
- Ren, J.; Wang, Y.; Wang, T. Numerical Analysis of the Effect of Groundwater Seepage on the Active Freezing and Forced Thawing Temperature Fields of a New Tube–Screen Freezing Method. Sustainability 2023, 15, 9367. [Google Scholar] [CrossRef]
- Zhu, C. Surface Settlement Analysis Induced by Shield Tunneling Construction in the Loess Region. Adv. Mater. Sci. Eng. 2021, 2021, 5573372. [Google Scholar] [CrossRef]
- Fang, Q.; Zhang, D.; Wong, L.N.Y. Shallow tunnelling method (STM) for subway station construction in soft ground. Tunn. Undergr. Space Technol. 2012, 29, 10–30. [Google Scholar] [CrossRef]
- Bai, Q.; Zhang, Y.; Zhao, W. Construction of subway station using the small pipe roof-beam method: A case study of Shifu Road station in Shenyang. Tunn. Undergr. Space Technol. 2023, 135, 105000. [Google Scholar] [CrossRef]
- Wang, B.; Li, Z.P.; Wang, T.; Zheng, H. A study of key construction technology on metro station constructed by enlarging large diameter shield tunnel. Chin. Civ. Eng. J. 2015, 48 (Suppl. S1), 373–377. [Google Scholar]
- Xu, X.; Li, Z.; Fang, Q. Challenges and countermeasures for using pile-beam-arch approach to enlarge large-diameter shield tunnel to subway station. Tunn. Undergr. Space Technol. 2020, 98, 103326. [Google Scholar] [CrossRef]
- Liu, J.; Qi, T.; Wu, Z. Analysis of ground movement due to metro station driven with enlarging shield tunnels under building and its parameter sensitivity analysis. Tunn. Undergr. Space Technol. 2012, 28, 287–296. [Google Scholar] [CrossRef]
- Li, Z.P.; Wang, T.; Zheng, H. Controlling measurements for metro station construction on enlarging large diameter shield tunnel. Chin. J. Rock Mech. Eng. 2015, 34, 1869–1876. [Google Scholar]
- Li, X.W.; Zheng, H.; Wang, Q.H. Safety analysis for metro station constructed by enlarging large diameter shield tunnel with mining method. Chin. Civ. Eng. J. 2016, 49, 96–102. [Google Scholar]
- Lv, J.B.; Li, X.L.; Fu, H.L.; Tang, Y.; Li, Z.R.; Zhao, H. Influence of Shield Tunnel Construction on Ground Surface Settlement under the Condition of Upper-Soft and Lower-Hard Composite Strata. J. Vibroeng. 2021, 22, 1126–1144. [Google Scholar] [CrossRef]
- GB 50911-2013; Code for Monitoring Measurement of Urban Rail Transit Engineering. National Standard of the People’s Republic of China: Beijing, China, 2014.
Material | Density (kg/m3) | Elastic Modulus (kN/m3) | Poisson Ratio |
---|---|---|---|
Shield tunnel segment | 2700 | 3.1 × 107 | 0.1 |
Floor | 2500 | 2.21 × 107 | / |
Number | Stratum | Density (kg/m3) | Elastic Modulus (MPa) | Secant Modulus (MPa) | Unloading Modulus (MPa) | Cohesive Forces (kPa) | Angle of Friction (°) | Permeability Coefficient (m/d) |
---|---|---|---|---|---|---|---|---|
1 | Fill | 1850 | 5 | 5 | 25 | 10 | 15 | 0.5 |
2 | Fill of Sand | 1750 | 5 | 5 | 25 | 15 | 18 | 0.5 |
3 | Sandy silt | 1910 | 9.2 | 9.2 | 27.6 | 17 | 23 | 0.5 |
4 | Clayey silt | 1990 | 6.3 | 6.3 | 31.5 | 24 | 16 | 0.05 |
5 | Silt | 2050 | 20 | 20 | 60 | 0 | 28 | 4 |
6 | Fine sand | 2070 | 25 | 25 | 75 | 0 | 32 | 5 |
7 | Silty clay 1 | 2000 | 6.4 | 6.4 | 32 | 31 | 21 | 0.05 |
8 | Silty clay 2 | 1960 | 7.2 | 7.2 | 36 | 34 | 22 | 0.05 |
9 | Silty clay 3 | 1960 | 8.2 | 8.2 | 41 | 36 | 24 | 0.05 |
10 | Frozen soil | 2000 | 100 | 38.46 | 134.6 | 200 | 5 | 0.5 |
Materials | Density (kg/m3) | Elastic Modulus (kN/m3) | Poisson’s Ratio |
---|---|---|---|
Primary lining | 2500 | 3.08 × 107 | 0.2 |
Secondary lining | 2500 | 3.15 × 107 | 0.2 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2023 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Guan, X.; Wang, R.; Fu, H.; Feng, W.; Jin, X.; Li, S.; Xu, S.; Li, J. Settlement Analysis of Ground Surface and Adjacent Building Caused by Driving and Expansion Excavation of Shield Tunnel Using Artificial Freezing Method. Sustainability 2023, 15, 14166. https://doi.org/10.3390/su151914166
Guan X, Wang R, Fu H, Feng W, Jin X, Li S, Xu S, Li J. Settlement Analysis of Ground Surface and Adjacent Building Caused by Driving and Expansion Excavation of Shield Tunnel Using Artificial Freezing Method. Sustainability. 2023; 15(19):14166. https://doi.org/10.3390/su151914166
Chicago/Turabian StyleGuan, Xiaoming, Ruohui Wang, Hongxian Fu, Wei Feng, Xin Jin, Shuqin Li, Shaohui Xu, and Jiguang Li. 2023. "Settlement Analysis of Ground Surface and Adjacent Building Caused by Driving and Expansion Excavation of Shield Tunnel Using Artificial Freezing Method" Sustainability 15, no. 19: 14166. https://doi.org/10.3390/su151914166
APA StyleGuan, X., Wang, R., Fu, H., Feng, W., Jin, X., Li, S., Xu, S., & Li, J. (2023). Settlement Analysis of Ground Surface and Adjacent Building Caused by Driving and Expansion Excavation of Shield Tunnel Using Artificial Freezing Method. Sustainability, 15(19), 14166. https://doi.org/10.3390/su151914166