The significant data for the model assessing machine cost-effectiveness in earthworks is the machine’s actual productivity assessment. Estimating the actual productivity of construction machines is very challenging [
34]. Knowing the actual productivity, one can obtain the expected duration for completing the activity for a given amount of work [
35]. The actual productivity of construction machines (e.g., excavators, dump/tipper trucks, etc.) plays an essential role in the progress of earthworks [
36]. Productivity assessment is a significant issue because productivity assessment manuals provide averaged values, data collection from the construction site is demanding, and various unexpected situations and problems may arise [
37].
Figure 1.
Model for machine cost-effectiveness in earthworks with protocol proposal by Šopić et al. [
38] (image created by the first author).
The third step consists of applying a comparative analysis of methodologies from prominent books, such as that of Peurifoy et al. [
41], Nunnally [
42], Nichols and Day [
43], and manuals from global machine manufacturers, such as Komatsu’s specifications and application handbook [
44] and Caterpillar’s performance handbook [
45], for evaluating the productivity of excavators and tipper trucks. The methodologies should be corrected with actual data from the construction site to improve the accuracy of the actual productivity assessment of excavators and tipper trucks for the observed construction site. Applying the mentioned methodologies, to a greater or lesser extent, will result in different values for the productivity estimates. The methodologies must be ranked according to the criteria of precision (the compliance of the actual productivity assessment of excavators and tipper trucks with the realistic/feasible number of tipper truck daily laps to the unloading place) and practicality (a subjective evaluation of simplicity and unambiguity when choosing coefficient values for assessing the productivity of excavators and tipper trucks).
Figure 2 presents the components of the protocol proposal [
38] and the model for machine cost-effectiveness in earthworks.
3.1. First Step: Early Warning System
Applying an Early warning system should provide reliable information on the operation of excavators and tipper trucks. Data on the productivity assessment of machines, together with the costs of the machines working hour, the contracted unit prices for the machine work, the amount of work performed, the time spent, and the cost per unit of performed earthworks, constitute the input data of the Early warning system.
The output data of the Early warning system should provide the early detection of the cost-effectiveness and profitability threshold of the operation of excavators and tipper trucks. They also include an assessment of the minimum required daily laps per tipper truck. These output data should ensure that potential negative cost effects are identified and addressed as soon as possible. The following section will describe in more detail the application of the Early warning system.
Cost-effectiveness can be expressed as a ratio of total revenues and total costs, which gives an indicator of cost-effectiveness [
17]:
where the indicator of cost-effectiveness must be greater than 1 for positive financial effects. In addition, the cost-effectiveness of machines can be calculated using the following formula [
17,
46]:
where
EK—machine cost-effectiveness [0, ∞)
QT—performed amount of work per unit of time [bank cubic meters, BCM];
pcss—the cost of the machine’s working hour [EUR/h];
c—unit price contract [EUR/ BCM];
Uv—time spent [h].
At the same time, if the indicator of cost-effectiveness has a value:
- -
EK > 1, machine utilization is cost-effective;
- -
EK = 1, machine utilization is at the marginal cost-effectiveness;
- -
E < 1, machine utilization is not cost-effective.
The cost of earthworks depends on the type of soil and rock, the use of machines, and the organization of machine work [
41]. The operation of the machines must also be expressed through the unit cost per unit of material removed [
45]. The goal is to choose the machine or combination of machines with the lowest cost per unit of material removed [
43]. The cost per unit of performed earthworks, i.e., the proportional cost, can be calculated as follows [
42]:
The profitability threshold (i.e., the break-even point) is defined as the level of capacity utilization below which a business entity must not operate because it would operate at a loss [
17]. By operating at the profitability threshold, there is no gain or loss; that is, the financial result of the business is zero. The profitability threshold of the machine can be calculated using the following formula [
17,
46]:
where
QK—product quantity at the profitability threshold [BCM/h];
pcss—the cost of the machine’s working hour [EUR/h];
c—unit price contract [EUR/BCM];
v—proportional cost [EUR/BCM].
The product quantity at the profitability threshold represents the minimum required hourly amount of work necessary for cost-effective operation. The minimum required daily amount of work can be calculated using the following formula:
where
QTmin—minimum required daily amount of work [BCM/day];
QK—product quantity at the profitability threshold (i.e., minimum-required hourly amount of work) [BCM/h];
TDAY—number of working hours in a day [h].
After calculating the minimum required daily amount of work, the minimum required tipper truck daily laps can be calculated using the following formula:
where
QTmin—minimum required daily amount of work [BCM/day];
nTT—number of tipper trucks on the construction site;
QTT—volume of material loaded into the tipper truck per lap [loose cubic meters, LCM].
Figure 3 shows the flow of activities when applying the Early warning system. As previously emphasized, significant information for applying the Early warning system is the actual productivity of construction machines (achieved during earthworks at the observed construction site). The protocol proposal by Šopić et al. [
38] is used to assess the actual productivity of excavators and tipper trucks. Data collection should be conducted within a few days (about 3 to 7 days during the entire working time).
Based on the actual productivity assessment, cost-effectiveness, and profitability threshold for excavators, tipper trucks, and machine groups (consisting of excavators and tipper trucks), it can be determined whether the contracted unit prices for earthworks (excavation and removal of materials) are favorably for the contractor.
Moreover, based on the profitability threshold, the value of the minimum required daily amount of work that an excavator, a tipper truck, or a machine group (consisting of excavator and tipper trucks) must perform can be obtained. In addition, the value of the minimum required daily laps per tipper truck can be calculated. Clearly, the goal is to have a higher number of tipper truck daily laps than the minimum and, consequently, a higher amount of completed work than the minimum required.
In a situation where the use of construction machines turns out to be non-cost-effective, it is imperative to reorganize the work of machines on the construction site according to the available possibilities to prevent further losses (for the contractor).
3.2. Second Step: Status of the Previous Work Period
The application of the Early warning system at the selected construction site must be compared with the data from the (time-depended) temporary reports to obtain a final assessment (i.e., Status) of the cost-effectiveness of excavators and tipper trucks for the previous work period (i.e., for the past month or a longer period, following the issuance of a temporary report). In addition, it is important to compare the actual time spent on excavation and removal of materials with the optimal and maximum permitted duration. The following section will describe in more detail the application of the Status of the previous work period.
Temporary reports are usually issued monthly or after a longer time. They must contain data on the actual volume of excavated material of the construction site. The actual volume of excavated material, for this research, needs to be achieved by a precise geodetic survey and measurement on the construction site. From the construction site diary, the number of days of the previous work period when excavation and removal of materials were carried out can be obtained (i.e., the actual time spent). On the other hand, the duration of work can be calculated by applying the following formula [
47]:
where
T—duration of work [h];
Q—amount of work [BCM];
P—machine productivity [BCM/h].
An estimate of the optimal duration of work can be obtained based on the actual (optimal/desired) productivity of machine group (consisting of excavator and tipper trucks). Furthermore, an estimate of the maximum permitted duration can be obtained based on the profitability threshold of machine group. However, the goal is to have a shorter duration than the maximum permitted to achieve positive financial benefits.
Suppose the use of excavators and tipper trucks was satisfactorily cost-effective in the previous work period, and the work was carried out within the desired duration. In that case, it is necessary to continue with the same intensity, while considering potential additional improvements.
On the other hand, suppose using excavators and tipper trucks was not cost-effective in the previous work period (despite the Early warning system indicating otherwise at the time of use). In that case, it is crucial to investigate the causes of such a situation.
Figure 4 shows the flow of activities for assessing the Status of excavator and tipper trucks used during the previous work period.