Formation of Rational Sets of Machines for Excavation Work in Urban Areas
Abstract
:1. Introduction
2. Methods of Research
- Grading and levelling of areas;
- Making an excavation and compacting its bottom;
- Excavation backfilling.
- Machine capacity (x1)
- Cost of a set of machines (x2)
- Type of soil (x3)
- Excavator boom reach (x4)
- Backhoe bucket capacity (x5)
- Work cycle time (x6)
- Volume of earth to be relocated (x7)
- Maximum speed in the loaded condition (x8)
- Maximum speed when empty (x9)
- Body volume (x10)
- Cutting width (x11)
- Cutting depth (x12)
- Maximum travel speed (x13)
- Availability of a ripper (x14)
- Type of the excavator bucket (x15)
- Excavation pattern (x16)
105,622.557∙x6 − 1,491,979.0636∙x7 + 1237.2075∙x10 − 100.6329∙x11 +
2388.921∙x12 − ………… − 0.0159∙x13
3. Result and Discussion
- Stripping;
- Cutting and filling;
- Grading;
- Using a self-propelled roller to compact soil.
- Excavation performed by an excavator;
- Transportation of earth in dump trucks;
- Using a bulldozer to clean the excavation pit bottom;
- Soil compaction.
- Using vibrating pile hammers to drive piles at the edge of the excavation;
- Backfilling of excavation pit hollows to be followed by compacting
- Using a bulldozer to deliver backfill soil;
- Soil a plate compactor to compact soil.
4. Conclusions
- When sets of machines for excavation works are selected, the principles of the multi-criteria approach are not applied, and sets are made according to two parameters only, they are the capacity and cost of sets. As a result, the current methods do not take into account several features of the urban development and, therefore, they cannot be considered as effective.
- The authors propose a principally new approach to the formation of sets of machines for excavation works, based on the identification of objective correspondence between the parameters of the technological processes and the structure of machines, with the maximum account taken of the characteristics of urban conditions in the course of leveling and grading, making and backfilling excavation pits.
- There are 16 parameters that can influence the choice of kits. An expert survey was conducted in order to determine the significant parameters and their weight coefficients.
- The correlation between the cost of a set of machines for excavation works and significant parameters was identified in the form of an equation of multiple regression, and its high degree of reliability was proven. As a result, a toolkit was devised for the development of a model and an algorithm for selecting a rational set of machines for excavation works in urban areas.
- The authors developed a new methodology for making a rational set of machines for excavation works in urban environments, which includes the main types of work, the set of parameters limiting the choice of machines, the step-by-step analysis of the set of machines, which includes sieving the unsuitable machines, scoring the parameters of sets of machines according to Harrington’s psychophysical scale, selecting sets of machines according to four criteria and identifying a rational set.
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Conflicts of Interest
References
- Tijanić, K.; Šopić, M.; Marović, I.; Car-Pušić, D. Analysis of the Construction Machinery Work Efficiency as a Factor of the Earthworks Sustainability. IOP Conf. Ser. Earth Environ. Sci. 2019, 222, 012009. [Google Scholar] [CrossRef]
- Liu, Q.; Duan, Q.; Zhao, P.; Ren, H.; Duan, H.; Liu, G.; Wang, Z.; Duan, Z.; Qin, L. Summary of calculation methods of engineering earthwork. J. Phys. Conf. Ser. 2021, 1802, 032002. [Google Scholar] [CrossRef]
- Chebanova, S.A.; Polyakov, V.G.; Azarov, A.V. Designing of organizational and technological solutions for construction in constrained urban environments. IOP Conf. Ser. Mater. Sci. Eng. 2019, 687, 044004. [Google Scholar] [CrossRef] [Green Version]
- Oleinik, P.P.; Efimov, V.V. The system of limitations of a set of machines for earthworks in the conditions of urban renovation. Constr. Prod. 2020, 4, 58–62. (In Russian) [Google Scholar]
- Kuzmina, T.K.; Efimov, V.V. Choosing the optimal earthmoving and transport machine for vertical planning of a construction site. BST Bull. Constr. Equip. 2018, 1, 62–64. (In Russian) [Google Scholar]
- Jeřábek, K.; Helebrant, F.; Jurman, J.; Voštová, V. Machines for Earthwork. Road Machines; Scientific Publication, Grafis: Opava, Czech Republic, 1996; 468p. [Google Scholar]
- Isakov, A.L.; Kuznetsova, K.S.; Kuznetsov, S.M. Optimization of the machine complex. Econ. Railw. 2013, 1, 85–91. (In Russian) [Google Scholar]
- Ivanov, V.N.; Salikhov, R.F. Optimization of the structure of the fleet, maintenance and repair of road construction machines. News Univ. Constr. 2002, 12, 70–74. (In Russian) [Google Scholar]
- Oleinik, P.P. Scientific and Technical Progress in Construction Production; Scientific Publication, ASV: Moscow, Russia, 2019; 442p. (In Russian) [Google Scholar]
- Demidov, D.V. The use of nomograms to determine the number of leading earthmoving and transport vehicles and the length of the gripper for the construction of logging highways. News Univ. For. Mag. 2005, 3, 72–77. (In Russian) [Google Scholar]
- Kuznetsov, S.M. Improving the Efficiency of the Use of Machines and Mechanisms in Construction; Scientific Publication Direct-Media: Moscow, Russia, 2015; p. 203. (In Russian) [Google Scholar]
- Kuznetsov, S.M.; Legostaeva, O.A. Organizational and technological reliability of excavator sets. News High. Educ. Inst. Constr. 2005, 10, 62–69. (In Russian) [Google Scholar]
- Isakov, A.L.; Kuznetsova, K.S.; Kuznetsov, S.M. Optimization of the work of a complex of machines in the construction of facilities. News High. Educ. Inst. Constr. 2012, 1, 52–57. (In Russian) [Google Scholar]
- Bchemyan, A.K. Methods of Forming a Fleet of Construction Machines and Monitoring Its Use; Scientific Publication MISI: Moscow, Russia, 1980; 41p. (In Russian) [Google Scholar]
- Ershov, M.N.; Lapidus, A.A.; Telichenko, V.I. Technological Processes in Construction. Book 2. Technological Processes of Soil Processing; Scientific Publication, ASV: Moscow, Russia, 2016; 112p. (In Russian) [Google Scholar]
- Akhmadulina, N.R.; Galiev, I.H.; Ibragimov, R.A. Mini-excavators—Means of small mechanization in construction. Mech. Autom. Constr. Samara 2021, 54–59. (In Russian) [Google Scholar]
- Klyuchnikova, O.V.; Tsybulskaya, A.A.; Shapovalova, A.G. Basic principles of choosing the type and quantity of construction machines for complex production of works. Eng. Bull. Don 2016, 3, 154. (In Russian) [Google Scholar]
- Kabanov, V.N.; Mikhailova, E.V. Definition of organizational and technological reliability of a construction organization. Constr. Econ. 2012, 4, 67–78. (In Russian) [Google Scholar]
- Efimov, V.V. Identification of the significance of the parameters necessary to select the optimal set of machines for the production of earthworks in urban development. Eng. Bull. Don 2021, 7, 320–328. (In Russian) [Google Scholar]
- Zagorskya, A.V.; Lapidus, A.A. Application of methods of expert evaluation in scientific research. The required number of experts. Constr. Prod. 2020, 3, 21–34. (In Russian) [Google Scholar]
- Evlanov, L.G. Theory and Practice of Decision–Making; Scientific Publication, Economics: Moscow, Russia, 1984; 175p. (In Russian) [Google Scholar]
- Evlanov, L.G.; Kutuzov, V.A. Expert Assessments in Management; Scientific Publication, Economics: Moscow, Russia, 1978; 133p. (In Russian) [Google Scholar]
- Oleynik, P.P. Organization of Construction Production; Scientific Publication, ASV: Moscow, Russia, 2010; 576p. (In Russian) [Google Scholar]
- Oleinik, P.P.; Efimov, V.V. Determination of significant parameters and factors for the selection of sets of machines for earthworks. Constr. Prod. 2022, 2, 42–45. (In Russian) [Google Scholar] [CrossRef]
- Efimov, V.V. Justification of a Rational Set of Machines for Earthworks in Urban Development; Candidate of Technical Sciences, National Research Moscow State University of Civil Engineering: Moscow, Russia, 2023. (In Russian) [Google Scholar]
- Cherednichenko, N.; Kuzmina, T.; Efimov, V. Decision-making theory methods as a tool for choosing construction technology. IOP Conf. Ser. Mater. Sci. Eng. 2020, 869, 062021. [Google Scholar] [CrossRef]
№ | Method | Principle | Weaknesses |
---|---|---|---|
1 | System of machines software developed by the Institute | The software offers a science-based parametric series of machines for different types of work. | 1. Determines the structure of the fleet for one single contractor |
2 | Selection according to the “capacity vs. cost” principle | A number of major machines, whose capacity is about 85–110% of the design value, is selected and the cheapest option is chosen to meet the pre-set requirements. In the same way, minor machines are selected to match the major machine. | 1. The set is not considered as a whole 2. Selection is made on the basis of the two parameters; therefore, this procedure cannot be called multi-criteria choice 3. The capacity range is too large |
3 | Formation of the set by setting the target function as well as the material and engineering reliability (MER) of the subset of the set | When sets of machines are selected, all the possible options are considered for which the value of the target function and MER of the construction machines is determined. According to the minimum value of the latter, the final choice of the set of machines is made. | 1. Determines the structure of the fleet for one single contractor 2. Multi-criteria choice is made individually for each subset, while the set is not considered as a whole |
Expert | 1 | 2 | 3 | 4 | 5 | 6 | 7 | 8 | 9 | 10 | 11 | 12 | 13 | 14 | 15 | 16 | 17 | 18 | Sum of Ranks | d | d2 | |
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Parameters | ||||||||||||||||||||||
x1 | 15 | 15 | 15 | 16 | 16 | 16 | 16 | 16 | 15 | 15 | 16 | 16 | 15 | 15 | 14 | 15 | 16 | 15 | 277 | 124 | 15,376 | |
x2 | 16 | 16 | 16 | 14 | 14 | 15 | 14 | 15 | 14 | 14 | 14 | 14 | 14 | 14 | 15 | 16 | 15 | 16 | 266 | 113 | 12,769 | |
x3 | 14 | 14 | 14 | 15 | 15 | 14 | 15 | 14 | 16 | 16 | 15 | 15 | 16 | 16 | 16 | 14 | 14 | 14 | 267 | 114 | 12,996 | |
x4 | 12 | 13 | 13 | 13 | 13 | 13 | 13 | 13 | 13 | 13 | 13 | 13 | 12 | 12 | 11 | 12 | 12 | 13 | 227 | 74 | 5476 | |
x5 | 13 | 11 | 12 | 12 | 11 | 12 | 11 | 10 | 10 | 10 | 10 | 11 | 11 | 11 | 12 | 13 | 11 | 12 | 203 | 50 | 2500 | |
x6 | 11 | 10 | 11 | 10 | 10 | 11 | 12 | 12 | 12 | 11 | 11 | 12 | 13 | 13 | 10 | 11 | 10 | 10 | 200 | 47 | 2209 | |
x7 | 10 | 12 | 10 | 11 | 12 | 10 | 10 | 11 | 11 | 12 | 12 | 10 | 10 | 10 | 13 | 10 | 13 | 11 | 198 | 45 | 2025 | |
x8 | 1 | 2 | 2 | 2 | 2 | 2 | 2 | 2 | 3 | 4 | 4 | 5 | 4 | 5 | 4 | 4 | 1 | 5 | 54 | −99 | 9801 | |
x9 | 2 | 1 | 1 | 1 | 1 | 1 | 1 | 1 | 5 | 5 | 5 | 3 | 5 | 4 | 5 | 5 | 4 | 3 | 53 | −100 | 10,000 | |
x10 | 9 | 9 | 9 | 8 | 9 | 9 | 9 | 6 | 6 | 8 | 7 | 7 | 7 | 7 | 8 | 8 | 7 | 7 | 140 | −13 | 169 | |
x11 | 8 | 8 | 8 | 7 | 8 | 6 | 8 | 7 | 9 | 9 | 6 | 9 | 6 | 6 | 6 | 6 | 6 | 6 | 129 | −24 | 576 | |
x12 | 7 | 6 | 7 | 6 | 6 | 7 | 7 | 8 | 8 | 7 | 8 | 8 | 8 | 8 | 7 | 9 | 8 | 9 | 134 | −19 | 361 | |
x13 | 6 | 7 | 6 | 9 | 7 | 8 | 6 | 9 | 7 | 6 | 9 | 6 | 9 | 9 | 9 | 7 | 9 | 8 | 137 | −16 | 256 | |
x14 | 4 | 5 | 4 | 3 | 5 | 3 | 4 | 4 | 2 | 2 | 1 | 4 | 3 | 3 | 1 | 3 | 2 | 2 | 55 | −98 | 9604 | |
x15 | 5 | 3 | 5 | 5 | 4 | 5 | 5 | 5 | 1 | 1 | 2 | 2 | 1 | 1 | 3 | 1 | 5 | 1 | 55 | −98 | 9604 | |
x16 | 3 | 4 | 3 | 4 | 3 | 4 | 3 | 3 | 4 | 3 | 3 | 1 | 2 | 2 | 2 | 2 | 3 | 4 | 53 | −100 | 10,000 | |
∑ | 136 | 136 | 136 | 136 | 136 | 136 | 136 | 136 | 136 | 136 | 136 | 136 | 136 | 136 | 136 | 136 | 136 | 136 | 2448 | 103,722 |
Parameters | Sum of Ranks | % | Parameter Weight |
---|---|---|---|
x1 | 277 | 100 | 0.113 |
x2 | 266 | 96 | 0.109 |
x3 | 267 | 96.4 | 0.109 |
x4 | 227 | 81.9 | 0.093 |
x5 | 203 | 73.3 | 0.083 |
x6 | 200 | 72.2 | 0.082 |
x7 | 198 | 71.5 | 0.081 |
x8 | 54 | 19.5 | 0.022 |
x9 | 53 | 19.1 | 0.022 |
x10 | 140 | 50.5 | 0.057 |
x11 | 129 | 46.6 | 0.053 |
x12 | 134 | 48.4 | 0.055 |
x13 | 137 | 49.5 | 0.056 |
x14 | 55 | 19.9 | 0.022 |
x15 | 55 | 19.9 | 0.022 |
x16 | 53 | 19.1 | 0.022 |
Parameters | x1 | x2 | x3 | … | x(n−1) | xn | |
---|---|---|---|---|---|---|---|
Sets | |||||||
1 | x1;1 | x2;1 | x3;1 | … | x(n−1);1 | xn;1 | |
2 | x1;2 | x2;2 | x3;2 | … | x(n−1);2 | xn;2 | |
3 | x1;3 | x2;3 | x3;3 | … | x(n−1);3 | xn;3 | |
… | … | … | … | … | … | … | |
m−1 | x1;m−1 | x2;m−1 | x3;m−1 | … | x(n−1); m−1 | xn;m−1 | |
m | x1;m | x2;m | x3;m | … | x(n−1); m | xn;m |
Quantitative Grade on the Scale of Desirability | Psychophysical Scoring |
---|---|
1.00–0.80 | 1 |
0.80–0.63 | 2 |
0.63–0.37 | 3 |
0.37–0.20 | 4 |
0.20–0.00 | 5 |
Parameters | x1 | x2 | x3 | … | x(n−1) | xn | |
---|---|---|---|---|---|---|---|
Sets | |||||||
1 | F1;1 | F2;1 | F3;1 | … | F(n−1);1 | Fn;1 | |
3 | F1;3 | F2;3 | F3;3 | … | F(n−1)3 | Fn;3 | |
… | … | … | … | … | … | … | |
132 | F1;132 | F2;132 | F3;132 | … | F(n−1);132 | Fn;132 | |
… | … | … | … | … | … | … | |
m−1 | F1;m−1 | F2;m−1 | F3;m−1 | … | F(n−1); m−1 | Fn;m−1 | |
m | F1;m | F2;m | F3;m | … | F(n−1); m | Fn;m |
Parameters | x1 | x2 | x3 | … | x(n−1) | xn | |
---|---|---|---|---|---|---|---|
Sets | |||||||
1 | F1;1 × W1 | F2;1 × W2 | F3;1 × W3 | … | F(n−1);1 × W(n−1) | Fn;1 × Wn | |
3 | F1;3 × W1 | F2;3 × W2 | F3;3 × W3 | … | F(n−1);3 × W(n−1) | Fn;3 × Wn | |
… | … | … | … | … | … | … | |
132 | F1;132 × W1 | F2;132 × W2 | F3;132 × W3 | … | F(n−1);132 × W(n−1) | Fn3;132 × Wn | |
… | … | … | … | … | … | … | |
m−1 | F1;m−1 × W1 | F2;m−1 × W2 | F3;m−1 × W3 | … | F(n−1);(m−1) × W(n−1) | Fn;(m−1) × Wn | |
m | F1;m × W1 | F2;m × W2 | F3;m × W3 | … | F(n−1); m × W(n−1) | Fn;m × Wn |
Maximin | Maximax | Multiplication | of Savage | |
---|---|---|---|---|
113 | F3;113 × W3 | F(n−1);113 × W(n−1) | (F1;113 × W1) × (F2;113 × W2) × (F3;113 × W3) × … × (F(n−1);113 × W(n−1)) × ( Fn;113 × Wn) | F(n−1);113 × W(n−1) − F3;113 × W3 |
124 | Fn;124 × Wn | F33;124 × W3 | (F1;124 × W1) × (F2;124 × W2) × (F3;124 × W3) × … × (F(n−1);124 × W(n−1)) × (Fn;124 × Wn) | F(n−1);124 × W(n−1) − F3;124 × W3 |
125 | Fn;125 × Wn | F23;125 × W2 | (F1;125 × W1) × (F2;125 × W2) × (F3;125 × W3) × … × (F(n−1);125 × W(n−1)) × (Fn125 × Wn) | F(n−1);125 × W(n−1) − Fn;3125 × Wn |
126 | Fn;126 × Wn | F13;126 × W1 | (F1;126 × W1) × (F2;126 × W2) × (F3;126 × W3) × … × (F(n−1);126 × W(n−1)) × (Fn;126 × Wn) | F(n−1);126 × W(n−1) − F1;126 × W1 |
128 | Fn;128 × Wn | F13;128 × W1 | (F1;128 × W1) × (F2;128 × W2) × (F3;128 × W3) × … × (F(n−1);128 × W(n−1)) × ( Fn;128 × Wn) | Fn;3128 × Wn − F13;128 × W1 |
713 | Fn;713 × Wn | F(n−1);713 × W(n−1) | (F1;713 × W1) × (F2;73 × W2) × (F3;713 × W3) × … × (F(n−1);713 × W(n−1)) × (Fn;713 × Wn) | F3;713 × W3 − Fn;3713 × Wn |
Maximin | Maximax | Multiplication | of Savage | ∑ | |
---|---|---|---|---|---|
113 | 1 | 1 | 0 | 0 | 2 |
124 | 0 | 0 | 0 | 1 | 1 |
125 | 0 | 0 | 0 | 1 | 1 |
126 | 0 | 0 | 0 | 1 | 1 |
128 | 0 | 0 | 1 | 0 | 1 |
713 | 1 | 1 | 1 | 1 | 4 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2023 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Lapidus, A.; Topchiy, D.; Kuzmina, T.; Efimov, V. Formation of Rational Sets of Machines for Excavation Work in Urban Areas. Appl. Sci. 2023, 13, 7023. https://doi.org/10.3390/app13127023
Lapidus A, Topchiy D, Kuzmina T, Efimov V. Formation of Rational Sets of Machines for Excavation Work in Urban Areas. Applied Sciences. 2023; 13(12):7023. https://doi.org/10.3390/app13127023
Chicago/Turabian StyleLapidus, Azariy, Dmitriy Topchiy, Tatyana Kuzmina, and Vladimir Efimov. 2023. "Formation of Rational Sets of Machines for Excavation Work in Urban Areas" Applied Sciences 13, no. 12: 7023. https://doi.org/10.3390/app13127023
APA StyleLapidus, A., Topchiy, D., Kuzmina, T., & Efimov, V. (2023). Formation of Rational Sets of Machines for Excavation Work in Urban Areas. Applied Sciences, 13(12), 7023. https://doi.org/10.3390/app13127023