Next Article in Journal
Face Keypoint Detection Method Based on Blaze_ghost Network
Previous Article in Journal
Effects of Fatigue and Tension on the Physical Characteristics and Abilities of Young Air Traffic Controllers
Previous Article in Special Issue
Research on the Characteristics of Internet Public Opinion and Public Sentiment after the Sichuan Earthquake Based on the Perspective of Weibo
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

A Novel Risk Assessment for Cable Fires Based on a Hybrid Cloud-Model-Enabled Dynamic Bayesian Network Method

1
Research Institute of Macro-Safety Science, University of Science and Technology Beijing, Beijing 100083, China
2
China National Institute of Standardization, Beijing 100088, China
3
Key Laboratory of Product Defect and Safety for State Market Regulation, Beijing 100088, China
*
Author to whom correspondence should be addressed.
Appl. Sci. 2023, 13(18), 10384; https://doi.org/10.3390/app131810384
Submission received: 17 August 2023 / Revised: 9 September 2023 / Accepted: 12 September 2023 / Published: 17 September 2023
(This article belongs to the Special Issue Advances in Disaster Risk Sciences in the Era of Big Data)

Abstract

:
The fire risk of cables constantly changes over time and is affected by the materials and working conditions of cables. To address its internal timing property, it is essential to use a dynamic analysis method to assess cable fire risk. Meanwhile, data uncertainty resulting in the deviation of risk values must also be considered in the risk assessment. In this regard, this study proposes a hybrid cloud model (CM)-enabled Dynamic Bayesian network (DBN) method to estimate the cable fire risk under uncertainty. In particular, the CM is initially applied to determine the membership degrees of the assessment data relative to different states of the root nodes; then, these degrees are considered the prior probabilities of DBN, where the dynamic risk profiles are reasoned. Subsequently, the Birnbaum and Fussell–Vesely importance measures are constructed to identify the key nodes for risk prevention and control, respectively. Moreover, a case study of the Chongqing Tobacco Logistics Distribution Center is conducted, the computational results of which indicate the proposed method’s decision-making effectiveness. Finally, a comparison of the reasoning results between the proposed and traditional methods is performed, presenting strong evidence that demonstrates the reliability of the proposed method.

1. Introduction

Wires and cables play a pivotal role as crucial conduits for both power and information transmission. In contemporary society, cables find widespread application across diverse industrial settings, including but not limited to chemical plants [1], industrial warehouses [2], nuclear power plants [3], wind farms [4], and many other industrial places [5]. Simultaneously, fires resulting from wire- and cable-related disasters exhibit the highest incidence rates compared to other categories of electrical products [6]. In the United States, an estimated 24% of industrial or manufacturing fires are attributable to electrical issues, predominantly stemming from cable failures [7]. Cable fires and their subsequent propagation can give rise to catastrophic disasters [6,8]. Undoubtedly, cable fires represent a substantial menace to industrial production safety. Consequently, it is imperative to mitigate cable fire risks and guarantee the secure operation of cables.
Risk analysis and assessment serve as the foundational pillars for the implementation of effective risk control and safety management. In the context of cable fire risk analysis, scholars have centered their focus on comprehending the underlying mechanisms responsible for cable fire incidents [9,10,11,12,13]. The combustion characteristics of wires and cables are intricately linked to the combustion attributes of their constituent materials and structural compositions, which are further influenced by operational conditions and environmental factors [11]. The cause factors of cable fire [10] include cable core overheating, external heating, arc fault, loose cables, wire insulation moisture absorption, cable aging, etc. The influencing factors and evolution mechanisms of cable fires studied so far have established an important foundation for cable fire risk analysis. However, applying these results to the prevention and control of cable fires in the working process has more practical significance.
Fire risk assessment stands as a fundamental decision-making tool within the realm of risk control and safety management, providing potential risk information before the onset of a fire event. Presently, research endeavors in the field of cable fire risk assessment predominantly revolve around static analytical methodologies, including the weighted fuzzy Petri [14], the survey scoring method [15], and BN [16]. These methods integrate historical monitoring data and expert assessment data relative to risk factors to realize quantitative risk assessments based on multi-source information fusion [14,17]. However, extant studies have regrettably overlooked several pivotal issues: (1) As the factors influencing cable safety undergo temporal variations, the evolution of cable fire risks inherently exhibits dynamic characteristics. Consequently, static risk assessment methodologies fall short of capturing the nuanced and evolving nature of cable fire risks, rendering them unsuitable for dynamic risk monitoring and the timely implementation of prevention and control measures. (2) Faced with the uncertainty in dynamic monitoring data [18,19,20] and the vagueness associated with expert experiential data [21], the development of a cable fire risk assessment model should focus on the stochastic and imprecise aspects of converting quantitative values and qualitative standards. Therefore, the establishment of a dynamic cable fire risk assessment methodology that takes into account the influence of uncertainty in the assessment process is indispensable.
It is well-established that a dynamic Bayesian network (DBN) offers distinct advantages for dynamic risk analysis. It not only elucidates the intricate structure of risk transmission but also tracks the evolving probabilities associated with risk over time [22,23]. Thus far, DBN has found widespread application in dynamic risk assessment across various domains [24,25,26]. Nevertheless, the utilization of DBN in the context of cable fire risk assessment remains uncharted territory. Given the critical consequences of cable fires, exploring this research gap is of paramount importance. Moreover, when addressing data uncertainty in the risk assessment process, the cloud model (CM) [27] emerges as a potent tool. It has introduced an innovative bidirectional conversion method that bridges qualitative fuzzy concepts and quantitatively precise data. The cloud model adeptly considers both fuzziness and randomness within the evaluation process and has found extensive use in tackling problems involving uncertainty conversion [28,29]. Accordingly, the application of the hybrid CM-enabled DBN method in cable fire dynamic risk assessments is warranted.
With the identified research gaps highlighted above, only a limited number of approaches have previously attempted to tackle the aforementioned problem. Given the dynamic nature of cable fire risk assessment of uncertainty, the primary objective of this study is to present a dynamic risk assessment methodology and subsequently evaluate the probability of cable fires, taking into account both randomness and fuzziness within the assessment process. Notably, this study pioneers the utilization of dynamic Bayesian networks (DBNs) in determining the dynamic risk probability of cable fires. To enhance the precision of this assessment, the CM is applied to calculate membership degrees, characterizing the dynamic data with respect to various states of the root nodes. These membership degrees are then integrated into the DBN as prior probabilities for the root nodes. Additionally, the Birnbaum (BM) importance measure [30] and Fussell–Vesely (FV) importance measure [31] are introduced to offer valuable insights for dynamic risk prevention and control strategies. Ultimately, the viability and rationality of the proposed methodology are substantiated via a comprehensive case study involving a cable located in a low-voltage distribution room at the Chongqing Tobacco Logistics Distribution Center.
The remainder of this paper is organized as follows. Section 2 presents the framework of cable fire risk assessment and the hybrid CM-enabled DBN method proposed in this study. Section 3 first describes the primary concerns of the case study and then provides the computational results obtained from the case study to validate the effectiveness of the proposed fire risk assessment method. The fire risk assessment results and a comparison between the proposed method and the traditional DBN method are presented in Section 4. Finally, Section 5 concludes the study by providing valuable managerial insights and future directions.

2. Hybrid CM-Enabled DBN Method

2.1. Dynamic Risk Assessment Framework for Cable Fires

The dynamic framework proposed for cable fire risk assessment is presented in Figure 1 and includes the following three modules:
Establishment of the DBN for cable fires: According to the cable characteristics and working environment conditions, the basic risk factors are identified, and the risk evolution mechanism of cable fires is analyzed. Subsequently, a DBN is built for specific circumstances based on the risk evolution mechanism of cable fires.
Data processing based on CM: The standard cloud characteristic parameters are defined with reference to the range of states of the root node. Meanwhile, the cloud parameters of data are extracted from multisensory monitoring and dynamic expert scoring using data transformation in CM. Thereafter, the membership degrees of the dynamic data were calculated for the standard clouds of each state.
Dynamic risk probability reasoning: The membership degree is taken as the prior probability of each evaluation state of the root node in the DBN. Subsequently, the dynamic risk profiles of cable fires and the changes in BM importance and FV importance are determined based on the dynamic reasoning of the DBN. Finally, we assessed the dynamic risk of cable fires by analyzing the important factors for risk prevention and control.

2.2. Dynamic Bayesian Network

A BN is a type of probabilistic reasoning network based on Bayesian conditional probability and graph theory [32]. A BN assumes the form of a directed acyclic graph, as visually illustrated in Figure 2, wherein nodes symbolize random variables, and directed arcs delineate the causal relationships among these variables. In this context, a node responsible for generating an arc is denoted as the parent node, while the node receiving the directed arc is referred to as the child node [33]. The conditional dependencies between child nodes and their parent nodes were characterized using conditional probability tables (CPTs). Considering the conditional dependencies of variables, the joint probability distribution P(X) of variable X = {X1, …, Xn} in the BN can be expressed as follows:
P ( X ) = i = 1 n P ( X i | P a ( X i ) )
where Pa(Xi) indicates the parent set of Xi for any i = 1, …, n; P(Xi|Pa(Xi)) represents the conditional probability of variable Xi, and the chain rule of probability and the property of conditional independence have been extensively adopted [34].
Compared to the traditional static BN, the DBN is a derivative of the BN, which introduces the influence of the internal time series. The dependencies between nodes in a DBN can be distinguished into two types: (i) conditional dependencies under the same time slice and (ii) conditional dependencies across different time slices [22]. A DBN can be defined within a double variable (B0, B) framework, where B0 is a BN that defines the probability distribution P(X0) at the initial time, and B is called a “two-slice temporal Bayesian network (2TBN),” which defines the conditional distribution among variables between two time slices according to the following equation [35,36]:
P ( X t | X t 1 ) = i = 1 n P ( X i , t | P a ( X i , t ) )
where X i , t denotes the i-th node at time t, P a ( X i , t ) indicates the parent node of X i , t for the previous and same time slices, and n indicates the number of nodes in the network.
Meanwhile, a DBN typically follows two assumptions: (1) the Markov hypothesis, which is the probability that the nodes in time t are only affected by time t − 1, independent of the time segment before t − 1; and (2) the stationary hypothesis, which states that the conditional probability in B does not change with time [37]. According to the initial probability distribution in B0 and the conditional distribution between adjacent time slices in B, the joint probability distribution of the nodes from time t = 0 to t = T can be expressed as follows:
P ( X 0 : T ) = t = 0 T i = 1 n P ( X i , t | P a ( X i , t ) )
where X0:T represents all nodes from time slice t = 0 to t = T.
Figure 3a presents the initial network B0 of a DBN, where all variables are static. Figure 3b depicts 2TBN B, where the virtual arcs represent the conditional dependencies of the nodes under different time slices. Extending B to a certain number of time slices yields a complete DBN. To simplify the structure, an abstract form of the DBN is generally used [38], as shown in Figure 3c. The dotted lines in the image refer to the corresponding nodes in the preceding and following time periods.

2.3. Cloud Model Theory

2.3.1. Cloud Model

CM is a bidirectional cognitive model that combines probability theory and fuzzy set theory to deal with problems under uncertainty [27,39]. Three characteristic parameters are utilized to characterize the qualitative concepts in CM: Ex (expectation), En (entropy), and He (hyperentropy). Ex is the measure of the basic certainty of the qualitative concept, which is the most representative point of the qualitative concept. En is a measure of the uncertainty of qualitative concepts, which is determined by the fuzziness and randomness of qualitative concepts, and He reflects the uncertainty of entropy. Forward cloud transformation (FCT) and backward cloud transformation (BCT) algorithms are utilized to realize the bidirectional conversion of qualitative concepts and quantitative values.
The FCT is used to transform the qualitative concept into multiple cloud drops with respect to three characteristic parameters (Ex, En, and He), which involves the following four steps [39,40]:
Step 1. To generate a normal random number Enn~N(En, He2);
Step 2. To generate a normal random number xi~N(Ex, Enn2);
Step 3. The Gaussian certainty degree related to the qualitative concept is calculated using Equation (4):
μ ( x i ) = e ( x i E x ) 2 2 E n n 2
Step 4. Steps 1, 2, and 3 are repeated until the total number of cloud drops is generated.
The BCT transforms a group of cloud drops into three characters (Ex, En, and He) using the following equation:
{ E x = 1 m d = 1 m X d E n = π 2 × 1 m d = 1 m | X d E x | H e = S 2 E n 2
where Xd indicates the data series (d = 1, 2, …, m), m denotes the number of data series, and S symbolizes the variance in Xd.
The bidirectional conversion using CM is illustrated in Figure 4.

2.3.2. CM-Based Membership Degree

In the context of this study, the process of assessing the risk of cable fires necessitated the fusion of information from multiple sources. To extract valuable insights from this amalgamated data, each foundational risk factor is subdivided into distinct states, serving as benchmarks for evaluation. To mine useful information from multi-source data, each basic risk factor can be further divided into different states as a reference standard for evaluation, and the membership degrees of the data for assessment at different states should be calculated [18]. The calculation steps emphasized by Guo, Amin [41] are as follows.
(1) Define the standard cloud characteristic parameters ( E x ,   E n ,   and   H e ) for each state using the following equation [19,42]:
{ E x = ( x max + x min ) 2 E n = ( x max x min ) 6 H e = k
where x m a x and x m i n represent the upper and lower boundaries of each state, respectively, and the boundary is determined by expert experience or existing criteria. k indicates a constant value, which can be adjusted according to the characteristics of the variable itself. In practice, for a state with only one boundary, such as ( , x m a x ) or ( x m i n , + ), default boundary parameters or expectations can be defined according to the actual upper and lower limits of the variable [43].
(2) The cloud feature parameters of the discrete data to be evaluated are extracted using Equation (5).
(3) n cloud drops (i.e., n = 3000) are generated using FCT, and the certainty degrees of each cloud drop are calculated relative to the evaluation standard cloud, with the average value of all results as the membership degree   μ j (j = 0, 1, …, m).
(4) Membership degree   μ j is standardized, and the final membership degree of the data to be evaluated for the j-th state is as follows:
μ j = μ j j = 0 m μ j

2.4. Importance Measure

Importance measures serve as valuable metrics for gauging the significance of individual components within a system. Importance measures are instrumental tools in identifying system weaknesses and determining the priority of reliability improvement activities [30,44]. In the field of risk assessment, importance measures can be used to analyze the impact of specific risk factors on the evolution of an entire risk system [34,45]. In this study, BM and FV importance measures are introduced to analyze the risk factors of cable fires in terms of risk prevention and control, and they are calculated based on Bayesian reasoning.
In a multi-state case, BM importance can represent the probability change in the target risk event caused by influencing factor Xi from the normal state to the dangerous states [30,34], which can be expressed as follows:
B M ( X i ) = j = 0 m | P ( φ ( X ) = 1 | X i = b i j ) P ( φ ( X ) = 1 ) | X i = b i 0 ) | | b i | 1
where b i j represents the j-th state of Xi, b i 0 represents the normal state of Xi, P ( φ ( X ) = 1 ) | X i = b i j ) represents the probability of the target risk event when Xi is in the j-th state, and | b i | is the number of states for Xi.
FV importance is often interpreted as a measure of relative risk reduction in the field of the risk analysis of complex systems [31], and the calculation formula is given as follows:
F V ( X i ) = P ( φ ( X ) = 1 ) P ( φ ( X ) = 1 | X i = b i 0 ) P ( φ ( X ) = 1 )
The larger the BM(Xi) value, the greater the importance of factor Xi in terms of risk prevention, and the larger the FV(Xi) value, the greater the importance of factor Xi in terms of risk control.

3. Case Study

To demonstrate the practicality of the methods proposed in this study, we conducted a comprehensive assessment of cable fire risk within a low-voltage power distribution room of the Chongqing Tobacco Logistics Distribution Center. The distribution center can be divided into sorting areas, elevated storage areas, business operation rooms, and underground operating spaces. The sorting area is equipped with a total of 15 lines. The elevated storage area has 21 lines. The business operation rooms and underground operating spaces are centrally wired and also have many lines. This facility is characterized by an extensive array of electrical components, necessitating numerous distribution boxes and an extensive network of distribution cables to facilitate power distribution. This underscores the paramount significance of cable fire prevention measures within this region. The single-core cables for internal wiring (60227 IEC 05 (BV)) with a nominal cross-sectional area of 0.75 mm2 were selected as the subject to be evaluated. This type of cable has a strong representativeness relative to its presence in factory areas, with the largest amount of wiring and the most intensive production. Table 1 lists the cable’s parameters and specifications. The impact load limit of the cable is 17 A, the conductive material comprises solid copper, and the working voltage is 380 V. Subsequently, a risk assessment was implemented based on the proposed assessment framework. Additionally, all calculations in this case are implemented using GeNIe 4.0 Academic (software dedicated to Bayesian modeling), and all experiments were executed on a computer with an Intel(R) Xeon(R) Gold 6230R CPU @ 2.10 GHz under the Windows Server 2019 Standard.

3.1. DBN Establishment

3.1.1. Basic Risk Factors Identification and Risk Evolution Mechanism Analysis

The combustion characteristics of wires and cables are related to the combustion characteristics of component materials and their structures, and they are affected by operating conditions and environmental factors. A comprehensive evaluation of the factory’s working and wiring conditions revealed that the fundamental risk factors associated with cable fires predominantly stem from three key aspects: (i) abnormal electrical condition, (ii) poor line condition, and (iii) adverse operation environment. Abnormal electrical conditions refer to overvoltage or overcurrent, which may be caused by the abnormal load of electrical components; poor line condition refers to insulation damage, insulation aging, poor connection, or insufficient laying spacing for cables, which mainly result from cable performance and manual operation; adverse operation environment refers to high ambient temperature or humidity for cables.
Upon pinpointing the fundamental risk factors and referring to relevant research [16,46], we have illustrated the cable fire risk evolution mechanism within the power distribution room, as depicted in Figure 5. This mechanism comprises two stages: early risk transmission and fire formation. The risk emanates from the foundational risk factors, traverses through intermediate risk factors, and ultimately culminates in the occurrence of a cable fire. The interpretation of the concept of risk varies across different contexts. Generally, risk is commonly defined as the likelihood of an undesirable event occurring or as a combination of the probability and severity of adverse effects. Various disciplines provide differing definitions of risk for their final quantified values, encompassing concepts such as the probability of occurrence, objective uncertainty, the amalgamation of probability and severity, and more. Although the precise forms of these definitions may differ, the consideration of the probability of risk occurrence remains a central aspect for the majority of scholars [47,48]. In this paper, for the sake of simplicity, risk corresponds to the probability of an event in this case.

3.1.2. Network Structure and Parameter Determination

The factors and logical relationships in the proposed risk evolution mechanism were mapped onto a DBN, as shown in Figure 6. According to their dependencies, the nodes in the DBN are divided into three categories: (i) root nodes, (ii) intermediate nodes, and (iii) leaf nodes. The solid arrows represent risk transfer between different nodes, and the dashed arrows represent risk transfer within the same node.
The assessment states for each node have been systematically categorized based on cable performance and real-world operational conditions (see Table 2). In particular, each root node is divided into three states, S0, S1, and S2, which indicate that the basic risk factors represented by the root nodes are in the optimal, relatively unfavorable, and most unfavorable states, respectively. Moreover, within this set of eight root nodes, the assessment states for X1 to X4 are delineated based on quantitative monitoring data, whereas those for X5 to X8 are determined using expert evaluations that employ a scale ranging from 0 to 10.
The DBN segments continuous time into discrete time slices. However, the evolution degree of the risk is different for time slices with different lengths. Therefore, before determining the CPT of the DBN, the length of the time slice must first be determined. Generally, the cable (60227 IEC 05 (BV)) reaches a balanced temperature increase within 2 min. To proactively mitigate risks at the earliest opportunity, the time slice length of the DBN in this case was defined as 1 min, serving as the foundation for determining the CPT.
The CPT in a DBN can generally be determined using parameter learning or expert knowledge, and parameter learning is based on a large amount of statistical data. Due to a lack of available data, the CPTs of the nodes were primarily determined by expert knowledge and referred to the CPT data from Chen, Huang [16]. For example, the CPT of leaf node Z is listed in Table 3. The system model’s factors correspond to the various represented root node factors. Based on the structure and parameters of the DBN, we can instantiate the DBN. With the principles of DBN introduced in Section 2, we performed dynamic inference using the GeNle software, and a modeling schematic is shown in Figure 7.

3.2. Collection of Processing Data Based on CM

We opted to conduct a dynamic risk assessment for cable fires in the power distribution room during the operational hours between 2 P.M. and 3 P.M. on 22 November 2021, during which data processing took place. The assessment data for root nodes X1–X4 were derived from the continuous monitoring data collected by four sensors, with readings recorded every three seconds. The fluctuations in these four sets of monitoring data are visually depicted in Figure 8. In addition, the evaluation data of root nodes X5–X8, which can be updated irregularly, were obtained using dynamic expert scoring. Given the brief time frame of this case study, the expert scores remained unaltered throughout the hour, as detailed in Table 4. The expert scoring method is a technique employed to quantify qualitative descriptions, wherein experts assign scores based on their experience and evaluation criteria. In this paper, X5–X8 (insufficient laying spacing, insulation aging, insulation damage, and poor connection quality) are not real-time data and cannot be measured multiple times in a short period. Instead, their risk levels are derived from experts’ observations and accumulated work experience. These four risk factors exhibit minimal changes over short timeframes, resulting in scoring results with extended validity that do not necessitate frequent updates. Consequently, based on the aforementioned factors, it can be inferred that the absence of updates within a 60 min interval would not significantly impact the results.

3.2.1. Evaluation Standard Cloud Determination

Prior to computing membership using the CM, it is imperative to convert the initial evaluation state into evaluation standard clouds for precise quantitative interpretation. The standard cloud characteristic parameters ( E x ,   E n ,   H e ) for the states of the root nodes in Table 2 are defined by Equation (6), as listed in Table 5.

3.2.2. State Membership Degree Calculation

The assessment period was divided into 60 discrete slices, with each lasting 1 min. Within each of these time slices, the state membership degrees of the datasets were fed into the DBN as prior probabilities. Initially, the cloud characteristic parameters of the data were extracted using Equation (5), and cloud drops were generated via the FCT for comparisons with the evaluation standard clouds of node states. Considering the cloud conversion in the first minute as an example, Figure 9 shows a comparison of the cloud distribution between the root node data and evaluation standards. The membership degree calculation was based on Equations (4) and (7). Figure 10 shows the membership changes in the monitoring data of nodes X2 and X4 relative to different states within 60 min, while the membership degrees of node X1 and X3 data for state S0 are always one. Moreover, because expert scoring data are not updated within 60 min, the state membership degrees of the nodes from X5 to X8 remain unchanged. Table 6 lists the cloud characteristic parameters and the state membership degrees of the expert scoring data.

3.3. Dynamic Risk Reasoning and Analysis

3.3.1. Dynamic Risk Profiles

Upon the completion of data processing using the CM, the state membership degrees of the datasets were input into the established DBN framework for dynamic cable fire risk assessments. By realizing probabilistic reasoning using the GeNIe program, we inquired about the state progression of intermediate nodes over the course of the 1 h monitoring period, as depicted in Figure 11. The dynamic risk profile for cable fires was also obtained (see Figure 12), and the risk assessment results were expressed in terms of safety or risk probability. Intermediate nodes serve as the direct factors responsible for igniting fires. Therefore, analyzing the evolution of intermediate node states helps us understand the interactions among various root nodes and the impacts they bring. Furthermore, it offers valuable insights into the potential numerical states of intermediate nodes once they reach various risk levels, facilitating the more effective implementation of safety measures in subsequent stages.
As depicted in Figure 11, except for Y3 (loose contact) and Y4 (poor heat dissipation), the risk status of the intermediate node primarily changes with the membership degree of X2 nodes in Figure 10, and the risk transmission path of these dynamic change nodes is Y2→Y6→Y7→Y1→Y5. As the S1 state value of X2 first increased and then decreased, the S1 state values of Y2 and Y6 also increased first and then decreased, whereas the S1 state values of Y7, Y1, and Y5 entered a relatively stable status around the 40th minute following a rapid increment (see Figure 10). This is because material pyrolysis and the subsequent reduction in insulation capacity are irreversible, leading to related risks are cumulative. Meanwhile, in nodes Y5–Y7, which directly affect the fire risk, the S1 and S2 values (i.e., 0.534 and 0.051, respectively) of node Y7 were the highest during this 60 min.
According to Figure 12, the development of the cable fire risk within 60 min can be divided into three phases. The first phase is 0–16 min, with a slow increase in fire risk; the second phase is 17–37 min when the risk value rapidly reaches the peak of 0.230 and exceeds a Level 1 Warning, thus necessitating the consideration of measures for risk control in this phase; the third phase is 38–60 min, with the risk value steadily decreasing to approximately 0.1. Meanwhile, the changing trend of the overall fire risk was roughly consistent with the changing trend of the S1 value of node X2 in Figure 10.
In this study, our primary goal is to evaluate the fire risk of cables by considering various external risk factors through a risk assessment lens rather than addressing the reliability issues of the electrical system itself. As a result, we have not extensively explored the multivariate models of the terminal situation of energy flow transmission and associated equations.

3.3.2. Dynamic Importance Analysis

The networks (i.e., the risk evolution mechanism and DBN structure) presented in Figure 5 and Figure 6 indicate that numerous risk factors may lead to cable fires in the distribution rooms. To pinpoint the critical basic factors that influence cable fires, we designated node Z (Fire) as the target node for the importance analysis of the root nodes. The significance of risk control was gauged using FV importance, while the importance of risk prevention was assessed via the BM’s significance.
During the ascending phase of risk, the pivotal imperative is the timely control of risk. Consequently, we focused on assessing the significance of risk control for the second phase of rapid risk escalation, as depicted in Figure 12. The FV importance of the root nodes in the second phase is calculated according to Equation (9), and the results are presented in Figure 13. It can be observed that the FV importance values of nodes X7, X8, and X2 are consistently significantly larger than those of other nodes, which means that improving the status of these nodes will reduce fire risks. Meanwhile, it is worth mentioning that the total FV importance value of the root nodes decreases from approximately 70% to approximately only 30% during this phase, which may be caused by the irreversible increase in the risks of intermediate nodes Y5 and Y7, which directly affect the fire risk (see Figure 11). Therefore, effectively reducing the risk level by controlling the risk factors of the root node is insufficient. As the risk exhibits an upward trend, the earlier prevention and control measures are taken, the lower the risk control effect. The power supply should be cut off as soon as possible to check for the pyrolysis of the cable, and the unqualified cable should be replaced in a timely manner.
According to Equation (8), BM importance across multiple states is determined by assessing the influence of each individual state change on the target node. Consequently, we initially examined the impact of various states of each root node on target node Z (Fire). Assuming that all root nodes are in their optimal states (S0 = 1) at the initial time (t = 0), we employed DBN reasoning to observe the alteration in cable fire risk probability over 10 time slices when the root node changes to two different states, as illustrated in Figure 14. In the S1 state, nodes X1 and X7 have the greatest impact on the probability of cable fire risk, and the impact of X7 increases with time. In the S2 state, nodes X1, X5, X2, X7, and X6 have a significant influence on cable fire risk probability, and the fire risk probability reaches one at the tenth time slice.
The BM importance values within 10 time slices of each root node were then obtained using Equation (8), as depicted in Figure 15. The order of the BM importance values from the largest to smallest at the 10th time slice was X7 (0.887), X1 (0.75), X5 (0.6), X6 (0.549), X2 (0.498), X3 (0.271), X4 (0.03), and X8 (0), whereas the values of X7, X6, X2, and X3 increased over time. The greater the BM importance value, the higher the fire risk caused by the node. Therefore, the risk factors corresponding to nodes X7, X1, X5, X6, X2, and X3 in cable fire risk prevention should receive more attention.

4. Discussion

4.1. Discussion on Dynamic Risk Reasoning and Importance Analysis

The landscape of cable fire risk factors is typically intricate, with a complex evolutionary mechanism. Through the construction of a DBN, the interplay between these risk factors is succinctly captured via directed arcs and conditional probabilities, as visually presented in Figure 6 and Table 3. Moreover, probability-based reasoning within the DBN empowers us to quantify risk and provide a lucid portrayal of risk evolution over time, as demonstrated in Figure 11 and Figure 12. Hence, it is conducive to grasping the dynamic risk profiles of cable fires using the DBN. Furthermore, because the cable fire risk evolution is a continuous and dynamic process, the states of the intermediate nodes may be affected by the previous moment, such as Y6 (Overheating risk) and Y7 (pyrolysis risk). The DBN associates nodes between adjacent moments by introducing Markov chains, whereas the traditional BN cannot reflect the influence of nodes at different times. Therefore, it is reasonable to use a DBN for the dynamic risk reasoning of cable fires.
The purpose of risk assessment is to prevent and control risks over time. Thus, after obtaining quantitative dynamic risk profiles, it is necessary to analyze the key factors of risk prevention and control. As presented in Figure 12 and Figure 14, FV importance reflects the degree of risk reduction caused by root node state improvement, and BM importance reflects the degree of risk increase caused by root node state deterioration. Therefore, introducing FV and BM into DBN can provide a dynamic and targeted reference for risk prevention and control.

4.2. Comparison with Traditional DBN Method

To address the uncertainty in the evaluation process, the data to be assessed underwent a conversion process using the CM, as depicted in Figure 6 and Table 4. The resultant membership degrees were subsequently employed as the prior probabilities for the root node within the DBN. To compare the difference between the CM-enabled DBN and traditional DBN methods in dealing with data uncertainty, the DBN reasoning result of the cable fire risk probability under the traditional threshold method [49] is shown in Figure 16. It is evident that the trends of the reasoning results of the two methods are almost identical. However, on the one hand, the fire risk probability using the traditional DBN is consistently lower than that of the proposed method. On the other hand, the fire probability of the first phase (0~16 min) obtained by the traditional DBN is always zero, which is inconsistent with reality. This result may be due to the rough division of the data, which makes the threshold method less sensitive to uncertain data. The traditional DBN employs a frequency-based statistical method, where the occurrence frequency of assessment data in different states over a period of time is used as the prior probability input for root nodes. This represents a simplistic and rough division at the data level, consequently leading to final inference results of 0. Accordingly, compared with the traditional threshold method, CM can obtain more information in monitoring data and expert scoring data, and the reasoning results based on CM-enabled DBN are more sensitive and reliable.

4.3. Limitations of the Proposed Method

As previously mentioned, the feasibility and reasonability of the proposed method for the dynamic risk assessment of cable fires were verified in this study. However, this study has several considerable limitations. In the assessment case, the fire risk factors of the cables in the power distribution room, including 15 risk factors at two levels, were determined. However, due to some risk factors, such as external fire sources existing in the distribution room, the identified risk factors may not be sufficiently comprehensive. Furthermore, due to the lack of sufficient data, the risk transfer mechanism and CPTs were primarily determined by referring to experts’ opinions and the relevant literature. Thus, a certain degree of subjectivity is inevitable in risk assessment. To reduce the subjective influence, structural learning and parameter learning [50,51] can be used in actual assessments to further improve the DBN. Moreover, the fire risk associated with cables is intrinsically connected to energy fluctuations within the electrical system and the reliability of equipment. To mitigate the subjectivity in fire risk assessment and bolster the quantitative interpretation and analysis of risks, we intend to include multivariate models of the terminal energy flow transmission situation and associated equations within our future research endeavors. Moreover, we only analyzed the importance of single-node risks for risk control, and investigating the importance of risk control in multi-node joint cases will be a focus of our future research.

5. Conclusions

Considering the dynamic evolution characteristics of cable fire risk and the uncertainty of the evaluation data, this study proposes a hybrid CM-enabled DBN method for cable fire risk assessment. First, a dynamic fire risk assessment framework was developed, where three modules were proposed: (i) cable fire DBN establishment, (ii) CM-based data processing construction, and (iii) dynamic fire risk reasoning and analysis. Subsequently, a DBN was applied to determine the dynamic risk probability of cable fires, and a CM was applied to deal with the uncertainty of the evaluation data. Subsequently, the BM and FV importance measures were introduced to provide a reference for dynamic risk prevention and control. Furthermore, a case study of the cable of a low-voltage distribution room at the Chongqing Tobacco Logistics Center was implemented to validate the proposed method. Dynamic risk profiles and importance changes were obtained, and the risk reasoning results were also discussed, which illustrates the feasibility and rationality of the proposed method. Finally, the assessment results of the proposed method and the traditional DBN method were compared, which confirmed that the results based on the proposed hybrid CM-enabled DBN method are more reliable. According to the results and discussion, the primary contributions of the proposed method are as follows:
  • For the first time, DBN was applied to the dynamic risk assessment of cable fires, which not only realized the dynamic reasoning of fire risk values but also clearly depicted the state changes in risk factors.
  • CM was used to convert sensor monitoring data and expert scoring data into the state membership degrees of the root node; then, the membership degrees were input into the DBN as a prior probability. Using CM-based data processing, randomness and fuzziness are emphasized in the risk assessment process, and additional information can be mined from the data.
  • BM and FV importance was introduced to identify the key nodes from the two dimensions of risk prevention and risk control, respectively. Dynamic importance analysis can be realized based on its associated reasoning, which is conducive to reasonable risk prevention and timely risk control.
Given the above explanations, this study enables a dynamic risk assessment for cable fires by considering the uncertainty of the evaluation data. Based on the proposed framework, reasonable structure learning and parameter learning methods can be introduced in the future to develop a more scientific DBN, and investigating the importance of risk prevention and control in multi-node joints will be the focus of future research. Moreover, the proposed method can provide support for the real-time risk assessment of cable fire risk, and the assessment is expected to achieve wider application value in industrial fire prevention and risk management by integrating it with Internet of Things (IoT) technology.

Author Contributions

Conceptualization, Z.X.; Methodology, Z.X.; Software, Z.X.; Formal analysis, Y.Y.; Investigation, G.H. and X.G.; Writing—original draft, S.G.; Writing—review & editing, X.G.; Supervision, G.H., Y.Y. and X.G.; Project administration, G.H.; Funding acquisition, X.G. All authors have read and agreed to the published version of the manuscript.

Funding

This work was supported by the Interdisciplinary Research Project for Young Teachers of USTB (Fundamental Research Funds for the Central Universities) (No. FRF-IDRY-21-016) and the Central Basic Research Fund project (No. 282022Y-9462).

Data Availability Statement

The data used in this study has been provieded in this article.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Shiohara, K.; Sugane, H.; Sato, M.; Adachi, K.; Nakanishi, T.; Mido, N.; Aoki, Y.; Hasegawa, T.; Ota, T.; Ogawa, M. Demonstration of a triaxial superconducting cable in a private chemical plant. IEEE Trans. Appl. Supercond. 2021, 31, 4801804. [Google Scholar] [CrossRef]
  2. Zhang, F.; Shang, W.; Zhang, B.; Cong, S. Design optimization of redundantly actuated cable-driven parallel robots for automated warehouse system. IEEE Access 2020, 8, 56867–56879. [Google Scholar] [CrossRef]
  3. Zhao, H.; Tong, J.; Zhao, J.; Wu, J. Failure characteristic of class 1E electrical cable used in the nuclear power plant exposed to fire. Prog. Nucl. Energy 2022, 150, 104292. [Google Scholar] [CrossRef]
  4. Liu, S.; Kopsidas, K. Risk-based underground cable circuit ratings for flexible wind power integration. IEEE Trans. Power Deliv. 2020, 36, 145–155. [Google Scholar] [CrossRef]
  5. Ak, M.F.; Yucesan, M.; Gul, M. Occupational health, safety and environmental risk assessment in textile production industry through a Bayesian BWM-VIKOR approach. Stoch. Environ. Res. Risk Assess. 2022, 36, 629–642. [Google Scholar] [CrossRef]
  6. Huang, X.; Nakamura, Y. A review of fundamental combustion phenomena in wire fires. Fire Technol. 2020, 56, 315–360. [Google Scholar] [CrossRef]
  7. Huang, P.; Chen, M.; Chen, K.; Zhang, H.; Yu, L.; Liu, C. A combined real-time intelligent fire detection and forecasting approach through cameras based on computer vision method. Process Saf. Environ. Prot. 2022, 164, 629–638. [Google Scholar] [CrossRef]
  8. Huang, X.; Zhu, H.; He, L.; Peng, L.; Cheng, C.; Chow, W. Improved model for estimating sidewall effect on the fire heat release rate of horizontal cable tray. Process Saf. Environ. Prot. 2021, 149, 831–838. [Google Scholar] [CrossRef]
  9. Xie, Q.; Zhang, H.; Tong, L. Experimental study on the fire protection properties of PVC sheath for old and new cables. J. Hazard. Mater. 2010, 179, 373–381. [Google Scholar] [CrossRef]
  10. Shea, J.J. Identifying causes for certain types of electrically initiated fires in residential circuits. Fire Mater. 2011, 35, 19–42. [Google Scholar] [CrossRef]
  11. Babrauskas, V. Electric arc explosions—A review. Fire Saf. J. 2017, 89, 7–15. [Google Scholar] [CrossRef]
  12. Zhu, H.; Ji, J.; Nie, J. Early fire evolution and alarm characteristics of cable fires in long and narrow spaces. Fire Saf. J. 2022, 131, 103627. [Google Scholar] [CrossRef]
  13. Li, Y.; Sun, Y.; Gao, Y.; Sun, J.; Lyu, H.-F.; Yu, T.; Yang, S.; Wang, Y. Analysis of overload induced arc formation and beads characteristics in a residential electrical cable. Fire Saf. J. 2022, 131, 103626. [Google Scholar] [CrossRef]
  14. He, L.; Ma, G.; Hu, Q.; Cai, Q.; Bai, Y.; Tang, S.; Tan, J. A novel method for risk assessment of cable fires in utility tunnel. Math. Probl. Eng. 2019, 2019, 2563012. [Google Scholar] [CrossRef]
  15. Kim, M.O.; Kim, K.; Yun, J.H.; Kim, M.K. Fire risk assessment of cable bridges for installation of firefighting facilities. Fire Saf. J. 2020, 115, 103146. [Google Scholar] [CrossRef]
  16. Chen, X.; Huang, G.; Gao, X.; Ou, S.; Li, Y.; Hezam, I.M. BN-RA: A Hybrid Model for Risk Analysis of Overload-Induced Early Cable Fires. Appl. Sci. 2021, 11, 8922. [Google Scholar] [CrossRef]
  17. Singh, R.S.; Cobben, S.; Ćuk, V. PMU-based cable temperature monitoring and thermal assessment for dynamic line rating. IEEE Trans. Power Deliv. 2020, 36, 1859–1868. [Google Scholar] [CrossRef]
  18. Xie, S.; Chen, Y.; Dong, S.; Zhang, G. Risk assessment of an oil depot using the improved multi-sensor fusion approach based on the cloud model and the belief Jensen-Shannon divergence. J. Loss Prev. Process Ind. 2020, 67, 104214. [Google Scholar] [CrossRef]
  19. Li, J.; Lu, G.; Niu, T.; Zhang, J. Developing an online air quality warning system based on streaming data for dynamic environmental management. J. Clean. Prod. 2020, 273, 122953. [Google Scholar] [CrossRef]
  20. Wu, X.; Duan, J.; Zhang, L.; AbouRizk, S.M. A hybrid information fusion approach to safety risk perception using sensor data under uncertainty. Stoch. Environ. Res. Risk Assess. 2018, 32, 105–122. [Google Scholar] [CrossRef]
  21. Wang, L.; Yan, F.; Wang, F.; Li, Z. FMEA-CM based quantitative risk assessment for process industries—A case study of coal-to-methanol plant in China. Process Saf. Environ. Prot. 2021, 149, 299–311. [Google Scholar] [CrossRef]
  22. Guo, X.; Ji, J.; Khan, F.; Ding, L.; Tong, Q. A novel fuzzy dynamic Bayesian network for dynamic risk assessment and uncertainty propagation quantification in uncertainty environment. Saf. Sci. 2021, 141, 105285. [Google Scholar] [CrossRef]
  23. Raveendran, A.; Renjith, V.; Madhu, G. A comprehensive review on dynamic risk analysis methodologies. J. Loss Prev. Process Ind. 2022, 76, 104734. [Google Scholar] [CrossRef]
  24. Ropero, R.F.; Nicholson, A.E.; Aguilera, P.A.; Rumí, R. Learning and inference methodologies for hybrid dynamic Bayesian networks: A case study for a water reservoir system in Andalusia, Spain. Stoch. Environ. Res. Risk Assess. 2018, 32, 3117–3135. [Google Scholar] [CrossRef]
  25. Wang, C.; Liu, Y.; Yu, C.; Zheng, Y.; Wang, G. Dynamic risk analysis of offshore natural gas hydrates depressurization production test based on fuzzy CREAM and DBN-GO combined method. J. Nat. Gas Sci. Eng. 2021, 91, 103961. [Google Scholar] [CrossRef]
  26. Meng, H.; An, X. Dynamic risk analysis of emergency operations in deepwater blowout accidents. Ocean Eng. 2021, 240, 109928. [Google Scholar] [CrossRef]
  27. Li, D.; Liu, C.; Gan, W. A new cognitive model: Cloud model. Int. J. Intell. Syst. 2009, 24, 357–375. [Google Scholar] [CrossRef]
  28. Wang, P.; Xu, X.; Huang, S.; Cai, C. A linguistic large group decision making method based on the cloud model. IEEE Trans. Fuzzy Syst. 2018, 26, 3314–3326. [Google Scholar] [CrossRef]
  29. Shan, B.; Guo, S.; Wang, Y.; Li, H.; Guo, P. Vine copula and cloud model-based programming approach for agricultural water allocation under uncertainty. Stoch. Environ. Res. Risk Assess. 2021, 35, 1895–1915. [Google Scholar] [CrossRef]
  30. Ramirez-Marquez, J.E.; Coit, D.W. Composite importance measures for multi-state systems with multi-state components. IEEE Trans. Reliab. 2005, 54, 517–529. [Google Scholar] [CrossRef]
  31. Kowal, K. Lifetime reliability and availability simulation for the electrical system of HTTR coupled to the electricity-hydrogen cogeneration plant. Reliab. Eng. Syst. Saf. 2022, 223, 108468. [Google Scholar] [CrossRef]
  32. Hanea, A.M.; Gheorghe, M.; Hanea, R.; Ababei, D. Non-parametric Bayesian networks for parameter estimation in reservoir simulation: A graphical take on the ensemble Kalman filter (part I). Comput. Geosci. 2013, 17, 929–949. [Google Scholar] [CrossRef]
  33. Heckerman, D.; Geiger, D.; Chickering, D.M. Learning Bayesian networks: The combination of knowledge and statistical data. Mach. Learn. 1995, 20, 197–243. [Google Scholar] [CrossRef]
  34. Han, Y.; Zhen, X.; Huang, Y. Hybrid dynamic risk modelling for safety critical equipment on offshore installations. Process Saf. Environ. Prot. 2021, 156, 482–495. [Google Scholar] [CrossRef]
  35. Murphy, K.P. Dynamic Bayesian Networks: Representation, Inference and Learning; University of California, Berkeley: Berkeley, CA, USA, 2002. [Google Scholar]
  36. Kammouh, O.; Gardoni, P.; Cimellaro, G.P. Probabilistic framework to evaluate the resilience of engineering systems using Bayesian and dynamic Bayesian networks. Reliab. Eng. Syst. Saf. 2020, 198, 106813. [Google Scholar] [CrossRef]
  37. Liu, Z.; Ma, Q.; Cai, B.; Shi, X.; Zheng, C.; Liu, Y. Risk coupling analysis of subsea blowout accidents based on dynamic Bayesian network and NK model. Reliab. Eng. Syst. Saf. 2022, 218, 108160. [Google Scholar] [CrossRef]
  38. Li, Z.; Wang, T.; Ge, W.; Wei, D.; Li, H. Risk analysis of earth-rock dam breach based on dynamic Bayesian network. Water 2019, 11, 2305. [Google Scholar] [CrossRef]
  39. Wang, G.; Xu, C.; Li, D. Generic normal cloud model. Inf. Sci. 2014, 280, 1–15. [Google Scholar] [CrossRef]
  40. Xie, X.; Zhang, J.; Lian, Y.; Lin, K.; Gao, X.; Lan, T.; Luo, J.; Song, F. Cloud model combined with multiple weighting methods to evaluate hydrological alteration and its contributing factors. J. Hydrol. 2022, 610, 127794. [Google Scholar] [CrossRef]
  41. Guo, Q.; Amin, S.; Hao, Q.; Haas, O. Resilience assessment of safety system at subway construction sites applying analytic network process and extension cloud models. Reliab. Eng. Syst. Saf. 2020, 201, 106956. [Google Scholar] [CrossRef]
  42. Gao, P.; Li, W.; Sun, Y.; Liu, S. Risk assessment for gas transmission station based on cloud model based multilevel Bayesian network from the perspective of multi-flow intersecting theory. Process Saf. Environ. Prot. 2022, 159, 887–898. [Google Scholar] [CrossRef]
  43. Yang, Z.; Huang, X.; Fang, G.; Ye, J.; Lu, C. Benefit evaluation of East Route Project of South to North Water Transfer based on trapezoid cloud model. Agric. Water Manag. 2021, 254, 106960. [Google Scholar] [CrossRef]
  44. Ramirez-Marquez, J.E.; Coit, D.W. Multi-state component criticality analysis for reliability improvement in multi-state systems. Reliab. Eng. Syst. Saf. 2007, 92, 1608–1619. [Google Scholar] [CrossRef]
  45. Li, M.; Wang, D.; Shan, H. Risk assessment of mine ignition sources using fuzzy Bayesian network. Process Saf. Environ. Prot. 2019, 125, 297–306. [Google Scholar] [CrossRef]
  46. Zhang, J.; Zhang, B.; Wang, L.; Fan, M.; Li, W. The state of the art of combustion behavior of live wires and cables. Mater. Rev. 2017, 31, 1–9. [Google Scholar]
  47. Campbell, S. Determining overall risk. J. Risk Res. 2005, 8, 569–581. [Google Scholar] [CrossRef]
  48. Aven, T. The risk concept—Historical and recent development trends. Reliab. Eng. Syst. Saf. 2012, 99, 33–44. [Google Scholar] [CrossRef]
  49. Zhou, T.; Dong, Z.; Chen, X.; Ran, Q. Decision support model for ecological operation of reservoirs based on dynamic Bayesian Network. Water 2021, 13, 1658. [Google Scholar] [CrossRef]
  50. Bregoli, A.; Scutari, M.; Stella, F. A constraint-based algorithm for the structural learning of continuous-time Bayesian networks. Int. J. Approx. Reason. 2021, 138, 105–122. [Google Scholar] [CrossRef]
  51. Sajid, Z. A dynamic risk assessment model to assess the impact of the coronavirus (COVID-19) on the sustainability of the biomass supply chain: A case study of a US biofuel industry. Renew. Sustain. Energy Rev. 2021, 151, 111574. [Google Scholar] [CrossRef]
Figure 1. Dynamic risk assessment framework for cable fires.
Figure 1. Dynamic risk assessment framework for cable fires.
Applsci 13 10384 g001
Figure 2. Simple Bayesian network.
Figure 2. Simple Bayesian network.
Applsci 13 10384 g002
Figure 3. Sample composition diagram of DBN.
Figure 3. Sample composition diagram of DBN.
Applsci 13 10384 g003
Figure 4. Bidirectional conversion of the cloud model.
Figure 4. Bidirectional conversion of the cloud model.
Applsci 13 10384 g004
Figure 5. Risk evolution mechanism of cable fires in the power distribution room.
Figure 5. Risk evolution mechanism of cable fires in the power distribution room.
Applsci 13 10384 g005
Figure 6. DBN structure of cable fire in the power distribution room.
Figure 6. DBN structure of cable fire in the power distribution room.
Applsci 13 10384 g006
Figure 7. Schematic diagram of GeNIe-based DBN modeling.
Figure 7. Schematic diagram of GeNIe-based DBN modeling.
Applsci 13 10384 g007
Figure 8. Monitoring data for nodes X1–X4.
Figure 8. Monitoring data for nodes X1–X4.
Applsci 13 10384 g008
Figure 9. Comparison of cloud distribution between the root node data and the evaluation standards in the first minute.
Figure 9. Comparison of cloud distribution between the root node data and the evaluation standards in the first minute.
Applsci 13 10384 g009
Figure 10. Membership degree changes of monitoring data of nodes.
Figure 10. Membership degree changes of monitoring data of nodes.
Applsci 13 10384 g010
Figure 11. State evolution of the intermediate nodes.
Figure 11. State evolution of the intermediate nodes.
Applsci 13 10384 g011
Figure 12. Dynamic risk profile for cable fires.
Figure 12. Dynamic risk profile for cable fires.
Applsci 13 10384 g012
Figure 13. Dynamic FV importance of the root nodes.
Figure 13. Dynamic FV importance of the root nodes.
Applsci 13 10384 g013
Figure 14. Change in cable fire probability with time under different states of the root nodes.
Figure 14. Change in cable fire probability with time under different states of the root nodes.
Applsci 13 10384 g014
Figure 15. Dynamic BM importance of the root nodes within 10 time slices.
Figure 15. Dynamic BM importance of the root nodes within 10 time slices.
Applsci 13 10384 g015
Figure 16. Comparison of the fire risk probability obtained using different methods in monitoring time.
Figure 16. Comparison of the fire risk probability obtained using different methods in monitoring time.
Applsci 13 10384 g016
Table 1. Main parameters and performance of type 60227 IEC 05(BV) cables.
Table 1. Main parameters and performance of type 60227 IEC 05(BV) cables.
Inner ConductorInsulating MaterialInsulation Thickness (mm)Rated Voltage (V)Working Temperature (°C)
Bare copper wirePVC0.6300/500−25~70
Table 2. The state division of each node.
Table 2. The state division of each node.
NodeDescriptionStatesNodeDescriptionStates
X1VoltageS0: safety (0~300 V)
S1: mild overload (300~345 V)
S2: severe overload (>345 V)
Y1Insulating capacityS0: good
S1: general
S2: bad
X2CurrentS0: safety (0~10 A)
S1: mild overload (10~18 A)
S2: severe overload (>18 A)
Y2Temperature rise degreeS0: low
S1: general
S2: high
X3Ambient temperatureS0: normal (0~40 °C)
S1: relatively high (40~70 °C)
S2: very high (>70 °C)
Y3Loose contactS0: false
S1: true
X4Ambient humidityS0: normal (30~65%)
S1: relatively high (65~85%)
S2: very high (>85%)
Y4Poor heat dissipationS0: false
S1: true
X5Damage degreeS0: slight (0~2)
S1: medium (2~5)
S2: severe (5~10)
Y5Insulation breakdown riskS0: low
S1: medium
S2: high
X6Aging degreeS0: low (0~2)
S1: medium (2~5)
S2: severe (5~10)
Y6Overheating riskS0: low
S1: medium
S2: high
X7Connection qualityS0: good (8~10)
S1: general (5~8)
S2: bad (0~5)
Y7Pyrolysis riskS0: low
S1: medium
S2: high
X8Laying spacingS0: sufficient (8~10)
S1: relatively small (5~8)
S2: very small (0~5)
ZFireS0: false
S1: true
Table 3. A simplified CPT sample about node Z.
Table 3. A simplified CPT sample about node Z.
Y5Y6Y7Z
FalseTrue
S0S0S01.0000.000
S0S0S11.0000.000
S0S0S21.0000.000
S0S1S00.7950.205
S0S1S10.6530.347
S0S1S20.5000.500
S0S2S00.3020.698
S0S2S10.1620.838
S0S2S20.0001.000
S1S0S00.5000.500
S1S0S10.3110.689
S1S0S20.0001.000
S1S1S00.2120.788
S1S1S10.0001.000
S1S1S20.0001.000
S1S2S00.0001.000
S1S2S10.0001.000
S1S2S20.0001.000
S2S0S00.0001.000
S2S0S10.0001.000
S2S0S20.0001.000
S2S1S00.0001.000
S2S1S10.0001.000
S2S1S20.0001.000
S2S2S00.0001.000
S2S2S10.0001.000
S2S2S20.0001.000
Table 4. Expert scores for nodes X5~X8.
Table 4. Expert scores for nodes X5~X8.
NodesEight Expert Scores
X50.80.71.00.91.21.51.01.5
X61.00.80.70.80.90.70.80.5
X78.28.58.08.58.58.08.28.0
X86.05.06.05.56.05.06.55.5
Table 5. Standard cloud characteristic parameters for different states of root nodes.
Table 5. Standard cloud characteristic parameters for different states of root nodes.
NodesS0S1S2
( E x ,   E n ,   H e ) ( E x ,   E n ,   H e ) ( E x ,   E n ,   H e )
X1(1.000, 0.333, 0.100)(3.500, 0.500, 0.100)(7.500, 0.833, 0.100)
X2(1.000, 0.333, 0.100)(3.500, 0.500, 0.100)(7.500, 0.833, 0.100)
X3(9.000, 0.333, 0.100)(6.500, 0.500, 0.100)(2.500, 0.833, 0.100)
X4(9.000, 0.333, 0.100)(6.500, 0.500, 0.100)(2.500, 0.833, 0.100)
X5(277.500, 7.500, 1.000)(322.500, 7.500, 1.000)(367.500, 7.500, 1.000)
X6(5.000, 1.667, 0.200)(14.000, 1.333, 0.200)(22.000, 1.333, 0.200)
X7(20.000, 6.670, 0.500)(55.000, 5.000, 0.500)(85.000, 5.000, 0.500)
X8(47.500, 5.833, 0.500)(75.000, 3.330, 0.500)(92.500, 2.500, 0.500)
Table 6. Cloud characteristic parameters and state membership degrees of the expert scoring data.
Table 6. Cloud characteristic parameters and state membership degrees of the expert scoring data.
Nodes ( E x ,   E n ,   H e ) Membership Degrees
S0S1S2
X5(1.075, 0.305, 0.051)0.9950.0050.000
X6(0.775, 0.133, 0.066)0.9990.0010.000
X7(8.238, 0.247, 0.082)0.9490.0510.000
X8(5.688, 0.548, 0.139)0.0000.9810.019
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

Gao, S.; Huang, G.; Xiang, Z.; Yang, Y.; Gao, X. A Novel Risk Assessment for Cable Fires Based on a Hybrid Cloud-Model-Enabled Dynamic Bayesian Network Method. Appl. Sci. 2023, 13, 10384. https://doi.org/10.3390/app131810384

AMA Style

Gao S, Huang G, Xiang Z, Yang Y, Gao X. A Novel Risk Assessment for Cable Fires Based on a Hybrid Cloud-Model-Enabled Dynamic Bayesian Network Method. Applied Sciences. 2023; 13(18):10384. https://doi.org/10.3390/app131810384

Chicago/Turabian Style

Gao, Shenyuan, Guozhong Huang, Zhijin Xiang, Yan Yang, and Xuehong Gao. 2023. "A Novel Risk Assessment for Cable Fires Based on a Hybrid Cloud-Model-Enabled Dynamic Bayesian Network Method" Applied Sciences 13, no. 18: 10384. https://doi.org/10.3390/app131810384

APA Style

Gao, S., Huang, G., Xiang, Z., Yang, Y., & Gao, X. (2023). A Novel Risk Assessment for Cable Fires Based on a Hybrid Cloud-Model-Enabled Dynamic Bayesian Network Method. Applied Sciences, 13(18), 10384. https://doi.org/10.3390/app131810384

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop