Automated Schedule and Cost Control Using 3D Sensing Technologies

by
Ahmed R. ElQasaby
*,
Fahad K. Alqahtani
* and
Mohammed Alheyf
Department of Civil Engineering, College of Engineering, King Saud University, P.O. Box 800, Riyadh 11421, Saudi Arabia
*
Authors to whom correspondence should be addressed.
Appl. Sci. 2023, 13(2), 783; https://doi.org/10.3390/app13020783
Submission received: 29 November 2022 / Revised: 25 December 2022 / Accepted: 29 December 2022 / Published: 5 January 2023
(This article belongs to the Topic Advances in Construction and Project Management)

Abstract

:
Nowadays, many construction projects in KSA still struggle with cost overruns and delay in activities. Therefore, automatic monitoring approaches are needed in the construction progress monitoring domain (CPM) to address these concerns. Thus, this paper proposed a system integrating a BIM-planned model with site laser scans, as laser scanners showed massive potential in the CPM domain. The algorithms of the proposed system recognized 3D objects based on the intersection between models, alignment accuracy, and Lalonde features. The proposed system combined 3D object recognition technology with 5D information data into a 5D progress tracking system using earned value (EV) principles. The reason behind that is a lack of research regarding conducting a 5D assessment integrated BIM with 3D sensing technology in the CPM domain. The proposed system was verified using field data from a superstructure construction project where the object recognition indicators showed a 98% recall and 99% precision in recognizing 3D objects. The proposed system also used a color-coding system to address the condition of each element based on its recognition and scheduling state and address any occlusions while calculating the recognized objects. The results also revealed an automatically updated status of the project’s progress in terms of schedule(4D) and cost(5D). The automated results were also validated with a manual calculation, where a slight variation (1.35%) was observed between those calculations. This system demonstrates a degree of accurate progress tracking, automatically exceeding manual performance with less computational time.

1. Introduction

The success of projects is evaluated through project completion within constraints of time, scope, cost, and quality. According to the KSA vision 2030 report, in 2017 alone, approximately 60% of construction projects were 20% behind schedule. In addition, more than 35% of the project time was spent collecting and analyzing data [1]. Further, approximately 15% of the construction cost was for rework activities. Therefore, time and cost were wasted in collecting and analyzing data, making as-built plans, monitoring the project, and fixing errors [1]. Therefore, researchers turned their attention to automated inspection to increase the response time of delayed activity rather than manual inspection [2,3]. Another example is that researchers were inclined to use automation methods to track and monitor the construction progress for better visualization after 2007 [4].
In this context, the construction progress monitoring domain (CPM) has developed massively in the last two decades. The exponential increase in computational capacities has allowed the architectural, engineering, and construction (AEC) industry to develop and implement automated methods in the CPM field. Lately, the development of the CPM field has depended on two primary methods: building information modeling (BIM) and 3D sensing technologies. BIM is focused on accurately establishing “as planned” 3D models. An as-planned model can also generate a spatial representation of project components. Then, integrating a 3D model with the project’s information could produce an accurate 3D BIM-based model [5,6]. The four-dimensional model was also recognized as the schedule model (4D). The scheduling model has been designated to establish the activities’ sequence over time. Cost information on the project’s activities is another dimension of BIM known as 5D BIM. Activities’ completion and cost over time have been simulated in a virtual environment. There have been limitations to the current BIM-based cost model, such as the cash flow analysis [7]. Some researchers also identified the sixth dimension as the facility phase. However, other studies referred to the sixth dimension as sustainability and its implementation in smart cities [8].

2. Previous Studies

3D sensing technologies are another crucial aspect that improved immensely track and monitor the progress of construction components. These technologies included radio frequency identification (RFID), an ultra-wideband system (UWB), a global positioning system (GPS), image processing methods, and laser scanners (LS) [9]. Previously, researchers managed to assemble “as-built” models [10], where a developed as-built model was created to restore, record, and improve historic buildings. Another study investigated integrating BIM and remote sensing instruments where a BIM-based model with a laser scanner was integrated for quality control in real-time to reduce schedule and cost overrun [11].
Among the 3D sensing technologies, A laser scanner, also known as Light Detection and Ranging (LiDAR), is one of the AEC industry’s most recognized technology. Laser scanning aims to map 3D objects into point cloud datasets [12]. Similarly, researchers monitored and controlled the infrastructure components using as-built data using a laser scanner [13]. Laser-based methods have also been used in recognizing construction applications such as workspace modeling, asset management, and worker tracking [14]. Another laser scanner application tracks buildings’ temporary or secondary components [15]. Although there are other 3D sensing technologies, laser scanners (LS) are one of the best-fitted technologies to track and monitor the 3D status of projects accurately [16,17,18,19]. In addition, researchers used automated methods as they have lesser limitations and could save much work and time in assessing the progress of construction projects [16].
3D spatial technologies were used to monitor and control the progress in the CPM domain. Some researchers applied the RFID system to form an as-built model, while others used UWB systems [20,21]. The image processing technology was also used in the CPM field using digital images or UAVs of construction activities [22,23]. Point cloud data sets were similarly used to evaluate the progress in construction buildings through laser scanning technology [19,24]. However, researchers used more than one sensing technology for more robustness and better results; for example, a study conducted by [25] used more than one 3D sensing technology (UWB system and laser scanner). Another study used a combination of RFID and laser scanning technology [26]. Other studies have used a fusion of image processing methods and laser scanners [24,27,28,29].
Furthermore, some latest review articles discussed different insights to recognize knowledge gaps and recommend future directions in the CPM field. For example, the methodology in [4] applied scientometric analysis to point out a broad picture of CPM. Another example is a systematic literature survey conducted to automate indoor progress monitoring [30]. The 3D model reconstruction and geometry quality inspection were also discussed comprehensively using the point cloud datasets [31]. Meta-analysis was estimated to review the quality of studies of object recognition performance indicators in the CPM field between 2007 and 2021 [32]. Previous studies recommended the usage of 5D assessment for future research to address the gap in the BIM integrated with 3D sensing technologies in CPM applications.
Therefore, the contribution of this paper is to propose an automated construction progress tracking system for schedule and cost control. The reason behind that is the lack of research on conducting 5D assessment in the CPM domain using EV principles [4,19,30,31,32]. The proposed system automatically implements a 5D assessment: progress feedback regarding schedule and cost per scan. The 5D assessment enables reviewing the progress and states the project condition through EV principles (schedule performance index, cost performance index). The proposed system outcomes were also compared to the manual system to validate the accuracy of the proposed system.

3. Methodology

This paper illustrates an automated progress tracking system in construction progress monitoring to assess the updated information in schedule and cost. A BIM-planned model was established from 2D shop drawings. Then, the as-built model was established by collecting scans using laser scanning technology, processing them, and registering them to a common coordinate system. The as-built model would also be evaluated and assessed to determine the quality of point cloud sets based on three KNN searching algorithms: a fixed number of nearest neighbors, a fixed neighborhood radius, and an adaptive neighborhood radius. Once the integration between those models was automatically established, two algorithms were designed and developed to recognize the as-built objects. Another two algorithms were developed to review the progress in terms of schedule and cost (4D, 5D) using EV principles. The flowchart of the proposed approach is shown in Figure 1. Further explanation of the methodological steps is provided in the following sections.

3.1. Tools

In order to apply the methodology mentioned above, a set-up of a BIM-planned model and an as-built model was crucial to be established. Revit interface was used to establish the BIM-planned model by converting 2D shop drawings to 3D models. Then, the planned schedule and cost models were manually established based on material, equipment, and labor costs for each project milestone. Material costs include supplies or materials purchased for the project, such as concrete, walls, and rebars. The transportation and storage cost is also included in the cost of materials.
The data acquisition was conducted on-site using a laser scanner Faro Focus3D because laser scanners are mainly accurate and efficient [33,34] (See Section 3.3). Then, datasets were processed, the scattered points were transformed into a range image, and laser scans were registered using project reference points from one of the local coordinate systems of multiple scans to a common coordinate system [35,36]. Iteratively closest point (ICP) was then used in registration where correspondences between points of a scan called the source and points of another called the target was established to minimize the spatial distance between points in each pair. The reason behind using ICP was to achieve satisfactory registration results [37]. The outcome of the previous procedures was to generate the as-built model.
Once the as-built model was established, the next step was to indicate the strength or the weakness of the spatial distribution of the datasets by feeding the as-built model with K-nearest neighbors search algorithms (fixed number of nearest neighbors (Method I), fixed neighborhood radius (Method II), and adaptive neighborhood radius (Method III)) [38,39]. One million points were used as a reasonable sample because using the original point clouds is not computationally feasible. Firstly, the KNN algorithm based on a fixed number of neighboring points was set as [500, 5000] with an interval of 50. Secondly, the KNN algorithm based on a fixed neighborhood radius was explored using a neighborhood threshold between 5 cm–50 cm with a step length of 5 cm. The neighborhood threshold considered the further analysis of geometric features of columns, beams, and slabs when setting the threshold radius. Finally, the KNN method based on adaptive radius was set between 1–30 cm with an interval of 1cm by calculating the information entropy of the neighboring point cloud set [40]. The chosen lower band was set based on the point cloud noise, density, sensor specification, and computational constraints. However, the chosen upper band was set based on the most significant object in the scene (facades for LS-data sets) [41]. The geometric features shown in Table 1 were obtained to illustrate the spatial distribution of the datasets based on the KNN searching algorithms [41,42,43].

3.2. Methods

3.2.1. Three-Dimensional Object Recognition

As soon as the point cloud assessment was completed, the as-built model was incorporated into the Revit interface. Therefore, a transformation matrix was established where a planned model was fixed. The point cloud model was then transformed to match the reference model automatically. It was stated that the point cloud was clumsy enough to be recognized. Thus, the point cloud set was transformed into a geometry-based model, as mentioned thoroughly in Algorithm 1.
Algorithm 1: Transformation of point cloud model into geometry-based model
Input: Point cloud P, Point cloud model whereP  ϵ  PM,
Output:  Object O, Geometry-based model GM, Structural elements E,
1Get  Pointcloud Instance From P file
2If pointCloudInstancenull
3Then
4P = pointCloudInstance.GetPoint()
5For Each P in PM
6 O = CreateSphereSolid(P)
7 ObjectsList = append(O)
8 End GM = DirectShape.CreateElement (ObjectList)
9End If
10End
After the geometry-based model was established, the proposed approach was introduced to initiate this recognition system representing the correspondence between the BIM-planned model and the as-built model. The proposed approach depended on three main aspects. Firstly, the alignment accuracy between the two models was vital to object recognition. Secondly, the recognition approach was based on three distinctive features called the Lalonde features [44]. It was also used for the linerarness, surfaceness, and scatterness of a 3D point cloud set [45,46]. Finally, at least 95% of an element would intersect with the geometry model to be considered a recognized element, as declared thoroughly in Algorithm 2. In other words, Algorithm 2 searches through the BIM-planned model to find the closest geometry to each BIM-placed object. If the BIM-planned object is found, the actual component is classified based on the object type in the BIM-planned model.
Algorithm 2: Comparison between the geometry-based model and BIM-planned elements
Input: Geometry-based model GM, BIM-planned model BIMM
Output: Structural elements E, Linkstructural elements LE
1Get E from P file
2Get LE from P file
3For Each E in BIMM
4 If E does not intersect with GM
5 Set Elementcolor RED
6 RedList = append (E)
7 End If
8End
9For Each LE in BIMM
10 If E does not intersect with LE and LE intersects with GM
11 Set Elementcolor Green
12 GreenList = append (LE)
13 End If
14End
15 If E does not intersect with LE and LE does not intersect with GM
16 Set Elementcolor Yellow
17 YellowList = append (LE)
18 End If
19End
20 If YellowList >> GreenList Then
21 Set Elementcolor Blue
22 Bluelist = append (LE)
23 End If
24End
Then, a color-coding system was established to demonstrate the condition of each element based on its recognition and scheduling state, as illustrated in Table 2. Each color would represent the recognition and scheduling state and determine whether it would be included in the calculation for automated schedule and cost.

3.2.2. Automated Schedule and Cost Control

To update the project’s status in terms of schedule and cost (4D, 5D), the authors developed two algorithms based on the results of the object recognition system. On one hand, Algorithm 3 calculated the 4D updated status based on the BCWS and BCWP estimated from the BIM-planned model and the geometry-based model, respectively, where budgeted unit cost was inserted into the algorithm. The element’s color would also determine whether its cost would be included. Then, the schedule performance index (SPI) was calculated automatically to review the schedule status of a project.
Algorithm 3: Calculate the automated schedule progress
Input:Structural elementsE, Linkstructural elementsLE,Budget unit cost BCost
Concrete Volume Vc
Output: Geometry Model Cost GM Cost, BIM-planned model total cost BIMM TC, SPI
1For Each Category in E
2 Get Vc For category
3 Calculate Category cost From BCost and Vc
4 BIMM TC = Category Cost
5End
6For Each L in Redelement
7 Calculate Red TC From BCost and Vc Red
8End
9For Each LE in Greenelement
10 Calculate Green TC From BCost and Vc Green
11End
12For Each LE in Yellowelement
13 Calculate Yellow TC From BCost and Vc Yellow
14End
15GM Cost = BIMM TC − Red TC + Green TC + Yellow TC
16SPI = GM Cost/BIMM TC
17IfSPI > 1
18 Then Print “Ahead of schedule.”
19Else If SPI < 1
20 Print “Behind schedule.”
21Else Print “Within schedule.”
22End If
23End
On the other hand, Algorithm 4 calculated the 5D updated status based on the BCWP and ACWP estimated from the geometry-based model and the revised BIM-planned model, respectively, where the actual unit cost was inserted into the algorithm. The element’s color would determine whether its cost would be included. Then, the cost performance index (CPI) was calculated automatically to review the cost status of the project.
Algorithm 4: Calculate the automated Cost progress
Input: Structural elements E, Actual unit cost ACost, Geometry Model Cost GM Cost
Output: Actual Total cost Actual TC, CPI
1For Each Category in E
2 Get VC For Category
3 Calculate Category cost From ACost and VC
4 Actual TC = Category Cost
5CPI = GM Cost/Actual TC
6If CPI > 1
7 Then Print “Under Budget”
8Else If CPI < 1
9 Then Print “Over Budget”
10Else Print “On Budget”
11End If
12End

3.3. Case Study

The data comprises a set of four field laser scans obtained from an investment building in The Rawda Administration Center, mainly consisting of reinforced concrete frame structure and Hardy slabs. The project location is [24.795813, 46.839646] beside Shaikh Isa Bin Salman Al Khalifah Rd, Al Maizilah, Riyadh. The site image of the case study is shown in Figure 2.
The construction site was scanned using Faro Focus3D [47] between 25 December 2020 and 20 January 2021. The weather on the days of the survey was hot; however, with a clear sky and low wind.

4. Results and Discussions

4.1. Point Cloud Characteristics

Regarding the evaluation of registration quality, the point cloud characteristics should be thoroughly discussed. Table 3 summarizes the dataset’s characteristics in all scans. The findings showed a relatively high average result of RMSE. The first reason behind that is Faro Focus 3D usually has a higher ranging error [+2 mm at 10 m and 25 m each at 90% and 10% reflectivity excluding the noise], according to the data from the manual of Faro Focus3D [47]. The second reason for a higher RMSE is that fewer tie points were not scanned when the scans were conducted initially. As a result, manual point matching was used, leading to a relatively higher registration error, as previously confirmed by [33]. However, the RMSE results in [19] showed a lower RMSE/Scan of 1.68 mm than the registration results conducted in this paper due to the usage of signalized targets on presurveyed site control points.
The noise of the point cloud revealed an average of 3.6 mm, within the threshold of the range noise. The results also showed a minimum overlap of more than 30% for the four scans. The inclinometer mismatch error of all scans also indicated lower results, implying a good-quality scan registration within the sensor specification.

4.2. Point Cloud Assessment

KNN search algorithms were used to evaluate the quality of the point cloud datasets by extracting specific geometric features (linear index Lλ, planar index Pλ, and scattered index Sλ). Table 4 illustrates the geometric features obtained from the KNN search algorithms (see Section 3.1). The sample set was calculated respectively based on the eigenvalues. The results of a method I revealed that the salience features of the sample points were (linear, planar = 42.9%). However, the salience feature changed to (planar = 50%) and (planar = 74%) in methods II and III, respectively. The feature extraction values in Method III were more accurate than in Method I and Method II due to the use of entropy information that led to less unpredictability of data (more distribution).
Therefore, the results showed that the majority of the sample sets were classified as linear and planar with a small index of scattereness, which was reflected in the robust distribution of the datasets. However, previous studies pointed out that the sample set on forests was divergent, where the salience feature changed based on the type of objects. Some objects, such as stems, exhibited a linear index or planar index, while others, such as leaves, exhibited a scatterness index [39,43]. Similarly, in this paper, the results of the geometric features indicated the structure of the sample set where most structural elements were classified as linear or planar.

4.3. Three-Dimensional Object Recognition

The proposed approach’s object recognition results were demonstrated using recall and precision rates for two incorporated scans. The recall and precision results achieved exceptionally satisfactory performance, 98%, and 99%, respectively, on average between scans. The minor errors result from objects with only a few points acquired in the scans or temporary objects with a few points wrongly recognized (false negative and false positive rates).
Figure 3 shows the object recognition results obtained from the scan on 25 December 2020, where the foundations were not recognized because the data acquisition date was after the backfilling activities, making the foundations invisible for the laser to recognize. As a result, the foundations were colored red. However, the second-floor columns showed visible progress in the schedule as the work performed exceeded the schedule; hence they are colored green. Some of these columns failed to be recognized because of occlusions; hence they are colored yellow.
Similarly, from Figure 4, it was observed that the object recognition results obtained from the scan on 20 January 2021, where the foundations were not recognized, as mentioned in the previous paragraph. Nevertheless, the second-floor slab showed modest progress in the schedule; hence they are colored green. While the second-floor slab is not yet fully constructed; therefore, they are colored blue.
Three-dimensional object recognition is built mainly on the similarities between the attributes and properties in as-planned and as-actual models. Therefore, researchers used various approaches to recognize the 3D point clouds. Therefore, the case study findings and previous studies regarding object recognition results [17,19,37] are compared. The case study findings show a higher precision and recall than those presented by [17,37]. However, it is in agreement with the findings reported by [19].

4.4. Schedule and Cost Control

The proposed system generates a user interface where the calculation of the progress tracking for schedule and cost can be measured. The user interface estimates the progress of schedule and cost based on the principles of EV using the budgeted cost of work scheduled (BCWS), Budgeted cost of work performed (BCWP), and Actual cost of work performed (ACWP). Figure 5 shows the progress tracking results for the scan acquired on 25 December 2020 using the schedule and cost of concrete work in the case study. Figure 5 also shows the total cost from unrecognized elements in BCWS, BCWP, and ACWP.
However, as previously illustrated, the foundations were considered the only unrecognized elements in this case study. They must be included in the schedule and cost estimation because construction activities depend on the foundations’ completion. In this case study, due to the 100% completion of the unrecognized elements (the foundations), BCWS is equivalent to BCWP as presented below Cost (5D) in Figure 5.
Table 5 demonstrates the results of the 4D progress for the case study, including the costs of unrecognized elements. Using the calculated SPI, the schedule performance of the whole project at chosen scans was determined. The results showed a fast-track project where the two scans were ahead of schedule, as the SPI was larger than one in both scans. Fewer studies were conducted to update the schedule automatically [15,27,37]. These studies mainly depended on the construction schedule to show the progress. Meanwhile, this paper demonstrates the automation of an updated schedule based on the visible recognized elements and their budget unit cost to calculate the schedule performance index.
In addition, Table 6 demonstrates the results of the 5D progress for the case study, including the costs of unrecognized elements. The cost performance of the whole project was obtained using the calculated SPI. The results showed a saving project where the two scans were under budget, as the CPI was larger than one. To the author’s best knowledge, this paper is the first to address the 5D assessment in the CPM domain integrated with BIM because previous studies indicated the lack in this field, as presented in [30,31,32].

4.5. Comparison between Manual and Automated Calculations

To validate the accuracy of the automated user interface, the authors compare manual and automated techniques in progress calculations. Figure 6a,b show the comparison results between the manual and automated calculations on 25 December 2020 and 20 January 2021. Firstly, on 25 December 2020, the calculations are approximately similar in BCWS, but they differ in both BCWP and ACWP calculations due to the included cost of formwork and steel fixed rebar of stairs on the second floor in manual calculations. The same issue happened on 20 January 2021, where the manual result of BCWP and ACWP was slightly higher than the automated result because the manual results included the cost of the formwork of the third-floor slab.
The proposed system does not calculate the objects that are not fully constructed (colored in blue) but takes the occlusion objects that failed to be recognized (colored in yellow) into account in its estimation formula. The automated results differ only by 1.35% from the manual calculation. This variation comprises only the objects that are not fully constructed and the wrongly recognized objects.
Further, Table 7 compares manual and automated calculations regarding SPI and CPI, where the results showed a slight difference in SPI results between manual and automated calculations, even though it does not affect the project’s status. At the same time, the CPI results showed approximate results between manual and automated calculations. The study findings above prove the validity of the proposed system. Hence, this system can be adapted to construction projects, enhancing the monitoring and controlling process as well as increasing the efficiency of schedule and cost updates with less time. This system can be developed outside the Autodesk platform, expanding the knowledge beyond one platform. Additionally, this system can be expanded to incorporate more domain knowledge (sustainability 6D, facility management 7D). Further, this system can be conducted in different types of projects, which could highlight other factors for improvement.

5. Conclusions

This paper presented an automated progress-tracking system that integrates 5D information data with laser scanning using the data collected from a superstructure construction project. The proposed system algorithms were based on the intersection percentage between models, alignment accuracy, and Lalonde features. The proposed system also automatically estimates the construction progress and updates the project status in schedule and cost with less computational time. The main findings of the case study revealed that the object recognition indicators (recall and precision) achieved a remarkably decent performance of 98% and 99%, respectively. The proposed system also uses a color-coding system to address the different conditions of elements. Additionally, it also considers occlusions when calculating the recognized progress.
The proposed system also shows that the automated calculations of updated schedules and costs can improve progress estimation results compared to manual calculations, where there is a slight variation of only (1.35%) between manual and automated calculations. The reason is that the current system’s estimation formula does not consider the cost of not fully constructed objects until they are completed. Thus, as future work, the current system should be evaluated in other construction buildings to declare a guideline and improvement. The authors acknowledge that the current approach has some limitations (i.e., the system is only available via the Autodesk Revit platform, and the laser scanner needs experienced labor). However, there is sufficient improvement using this approach to monitor the progress along with Earned Value principles.

Author Contributions

Conceptualization, A.R.E., F.K.A. and M.A.; methodology, A.R.E.; software, A.R.E.; validation, A.R.E., F.K.A. and M.A.; formal analysis, A.R.E., investigation, A.R.E., resources, A.R.E., F.K.A. and M.A.; data curation, A.R.E.; writing—original draft preparation, A.R.E.; writing—review and editing, A.R.E., F.K.A. and M.A.; visualization, A.R.E.; supervision, F.K.A. and M.A.; project administration, F.K.A. and M.A.; funding acquisition, F.K.A. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by the Researchers Supporting Project number (RSP2023R264), King Saud University, Riyadh, Saudi Arabia.

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

The data presented in this study are available on request from the corresponding author. The data are not publicly available due to privacy or ethical restrictions.

Acknowledgments

The authors extend their appreciation to the Researchers Supporting Project number (RSP2023R264), King Saud University, Riyadh, Saudi Arabia for funding this work.

Conflicts of Interest

The authors declare no conflict of interest.

Abbreviations

List of abbreviations and acronyms used in the paper.
AECArchitectural, Engineering, and Construction
BIMBuilding Information Modeling
LSLaser scanner
LiDARLight Detection and Ranging
GPSGlobal Positioning System
RFIDRadio Frequency Identification
UWBUltra-wideband
CPMConstruction Progress Monitoring
KNNK-nearest neighborhood
UAVUnmanned Aerial Vehicle
ICPIteratively Closest Point
PCAPrincipal Component Analysis
RMSERoot Mean Square Error
EVEarned Values
SPISchedule Performance Index
CPICost Performance Index
ACWPActual Cost Work Performed
BCWPBudgeted cost of work Performed
BCWSbudgeted cost of work Scheduled

References

  1. KSA Vision 2030. Available online: https://www.vision2030.gov.sa/ar/ (accessed on 28 December 2022).
  2. Yi, W.; Chan, A.P. Critical review of labor productivity research in construction journals. J. Manag. Eng. 2014, 30, 214–225. [Google Scholar] [CrossRef] [Green Version]
  3. Zavadskas, E.K.; Vilutienė, T.; Turskis, Z.; Šaparauskas, J. Multi-criteria analysis of Projects’ performance in construction. Arch. Civ. Mech. Eng. 2014, 14, 114–121. [Google Scholar] [CrossRef]
  4. Patel, T.; Guo, B.H.; Zou, Y. A scientometric review of construction progress monitoring studies. Eng. Constr. Archit. Manag. 2021, 29, 3237–3266. [Google Scholar] [CrossRef]
  5. Azhar, S. Building information modeling (BIM): Trends, benefits, risks, and challenges for the AEC industry. Leadersh. Manag. Eng. 2011, 11, 241–252. [Google Scholar] [CrossRef]
  6. Kensek, K.M. Building Information Modeling, 1st ed.; Routledge: London, UK, 2014. [Google Scholar]
  7. Lu, Q.; Won, J.; Cheng, J.C. A financial decision-making framework for construction projects based on 5D Building Information Modeling (BIM). Int. J. Proj. Manag. 2016, 34, 3–21. [Google Scholar] [CrossRef]
  8. Alqahtani, F.K.; El Qasaby, A.R.; Abotaleb, I.S. Urban Development and Sustainable Utilization: Challenges and Solutions. Sustainability 2021, 13, 7902. [Google Scholar] [CrossRef]
  9. Alizadehsalehi, S.; Yitmen, I. A concept for automated construction progress monitoring: Technologies adoption for benchmarking project performance control. Arab. J. Sci. Eng. 2019, 44, 4993–5008. [Google Scholar] [CrossRef]
  10. Baik, A.H.A.; Yaagoubi, R.; Boehm, J. Integration of Jeddah historical BIM and 3D GIS for documentation and restoration of historical monument. Int. Soc. Photogramm. Remote Sens. (ISPRS) 2015, XL-5/W7, 29–34. [Google Scholar]
  11. Wang, J.; Sun, W.; Shou, W.; Wang, X.; Wu, C.; Chong, H.Y.; Liu, Y.; Sun, C. Integrating BIM and LiDAR for real-time construction quality control. J. Intell. Robot. Syst. 2015, 79, 417–432. [Google Scholar] [CrossRef]
  12. Zhang, C.; Arditi, D. Automated progress control using laser scanning technology. Autom. Constr. 2013, 36, 108–116. [Google Scholar] [CrossRef]
  13. Son, H.; Bosché, F.; Kim, C. As-built data acquisition and its use in production monitoring and automated layout of civil infrastructure: A survey. Adv. Eng. Inform. 2015, 29, 172–183. [Google Scholar] [CrossRef]
  14. Chen, J.; Cho, Y.K. Point-to-point comparison method for automated scan-vs-bim deviation detection. In Proceedings of the 2018 17th International Conference on Computing in Civil and Building Engineering, Tampere, Finland, 5–7 June 2018; pp. 5–7. [Google Scholar]
  15. Turkan, Y.; Bosché, F.; Haas, C.T.; Haas, R. Tracking secondary and temporary concrete construction objects using 3D imaging technologies. In Computing in Civil Engineering, Proceedings of the ASCE International Workshop on Computing in Civil Engineering, Los Angeles, CA, USA, 23–25 June 2013; American Society of Civil Engineers: Reston, VA, USA, 2013. [Google Scholar]
  16. Cheok, G.S.; Stone, W.C.; Lipman, R.R.; Witzgall, C. Ladars for construction assessment and update. Autom. Constr. 2000, 9, 463–477. [Google Scholar] [CrossRef]
  17. Turkan, Y.; Bosche, F.; Haas, C.T.; Haas, R. Automated progress tracking using 4D schedule and 3D sensing technologies. Autom. Constr. 2012, 22, 414–421. [Google Scholar] [CrossRef]
  18. Bosché, F.; Ahmed, M.; Turkan, Y.; Haas, C.T.; Haas, R. The value of integrating Scan-to-BIM and Scan-vs-BIM techniques for construction monitoring using laser scanning and BIM: The case of cylindrical MEP components. Autom. Constr. 2015, 49, 201–213. [Google Scholar] [CrossRef]
  19. Maalek, R.; Lichti, D.D.; Ruwanpura, J.Y. Automatic recognition of common structural elements from point clouds for automated progress monitoring and dimensional quality control in reinforced concrete construction. Remote Sens. 2019, 11, 1102. [Google Scholar] [CrossRef] [Green Version]
  20. Fang, Y.; Cho, Y.K.; Zhang, S.; Perez, E. Case study of BIM and cloud-enabled real-time RFID indoor localization for construction management applications. J. Constr. Eng. Manag. 2016, 142, 05016003. [Google Scholar] [CrossRef]
  21. Rashid, K.M.; Louis, J.; Fiawoyife, K.K. Wireless electric appliance control for smart buildings using indoor location tracking and BIM-based virtual environments. Autom. Constr. 2019, 101, 48–58. [Google Scholar] [CrossRef]
  22. Golparvar-Fard, M.; Peña-Mora, F.; Savarese, S. D4AR–a 4-dimensional augmented reality model for automating construction progress monitoring data collection, processing and communication. J. Inf. Technol. Constr. 2009, 14, 129–153. [Google Scholar]
  23. Dimitrov, A.; Golparvar-Fard, M. Vision-based material recognition for automated monitoring of construction progress and generating building information modeling from unordered site image collections. Adv. Eng. Inform. 2014, 28, 37–49. [Google Scholar] [CrossRef]
  24. Kim, H.E.; Kang, S.H.; Kim, K.; Lee, Y. Total variation-based noise reduction image processing algorithm for confocal laser scanning microscopy applied to activity assessment of early carious lesions. Appl. Sci. 2020, 10, 4090. [Google Scholar] [CrossRef]
  25. Shahi, A.; Safa, M.; Haas, C.T.; West, J.S. Data fusion process management for automated construction progress estimation. J. Comput. Civ. Eng. 2015, 29, 04014098. [Google Scholar] [CrossRef]
  26. Hajian, H.; Becerik-Gerber, B. A research outlook for real-time project information management by integrating advanced field data acquisition systems and building information modeling. In Computing in Civil Engineering, Proceedings of the ASCE International Workshop on Computing in Civil Engineering, Austin, TX, USA, 24–27 June 2009; Caldas, C.H., O’Brien, W.J., Eds.; American Society of Civil Engineers: Reston, VA, USA, 2009; pp. 83–94. [Google Scholar]
  27. Han, K.K.; Golparvar-Fard, M. Appearance-based material classification for monitoring of operation-level construction progress using 4D BIM and site photologs. Autom. Constr. 2015, 53, 44–57. [Google Scholar] [CrossRef]
  28. Teizer, J. Status quo and open challenges in vision-based sensing and tracking of temporary resources on infrastructure construction sites. Adv. Eng. Inform. 2015, 29, 225–238. [Google Scholar] [CrossRef]
  29. Han, K.; Degol, J.; Golparvar-Fard, M. Geometry-and appearance-based reasoning of construction progress monitoring. J. Constr. Eng. Manag. 2018, 144, 04017110. [Google Scholar] [CrossRef] [Green Version]
  30. Ekanayake, B.; Wong, J.K.W.; Fini, A.A.F.; Smith, P. Computer vision-based interior construction progress monitoring: A literature review and future research directions. Autom. Constr. 2021, 127, 103705. [Google Scholar] [CrossRef]
  31. Wang, Q.; Kim, M.K. Applications of 3D point cloud data in the construction industry: A fifteen-year review from 2004 to 2018. Adv. Eng. Inform. 2019, 39, 306–319. [Google Scholar] [CrossRef]
  32. ElQasaby, A.R.; Alqahtani, F.K.; Alheyf, M. State of the Art of BIM Integration with Sensing Technologies in Construction Progress Monitoring. Sensors 2022, 22, 3497. [Google Scholar] [CrossRef]
  33. Bosche, F.; Haas, C.T.; Akinci, B. Automated recognition of 3D CAD objects in site laser scans for project 3D status visualization and performance control. J. Comput. Civ. Eng. 2009, 23, 311–318. [Google Scholar] [CrossRef]
  34. Kopsida, M.; Brilakis, I.; Vela, P.A. A review of automated construction progress monitoring and inspection methods. In Proceedings of the 32nd CIB W78 Conference, Eindhoven, The Netherlands, 27–29 October 2015; Volume 2015, pp. 421–431. [Google Scholar]
  35. Alheyf Aldosari, M.D. Mobile LiDAR for Monitoring MSE Walls with Smooth and Textured Precast Concrete Panels. Ph.D. Dissertation, Purdue University Graduate School, West Lafayette, IN, USA, 2020. [Google Scholar]
  36. Bosché, F. Plane-based registration of construction laser scans with 3D/4D building models. Adv. Eng. Inf. 2012, 26, 90–102. [Google Scholar] [CrossRef]
  37. Kim, C.; Son, H.; Kim, C. Automated construction progress measurement using a 4D building information model and 3D data. Autom. Constr. 2013, 31, 75–82. [Google Scholar] [CrossRef]
  38. Liang, X.; Kankare, V.; Yu, X.; Hyyppä, J.; Holopainen, M. Automated stem curve measurement using terrestrial laser scanning. IEEE Trans. Geosci. Remote Sens. 2013, 52, 1739–1748. [Google Scholar] [CrossRef]
  39. Xia, S.; Wang, C.; Pan, F.; Xi, X.; Zeng, H.; Liu, H. Detecting stems in dense and homogeneous forests using single-scan TLS. Forests 2015, 6, 3923–3945. [Google Scholar] [CrossRef]
  40. Brodu, N.; Lague, D. 3D terrestrial lidar data classification of complex natural scenes using a multi-scale dimensionality criterion: Applications in geomorphology. ISPRS J. Photogramm. Remote Sens. 2012, 68, 121–134. [Google Scholar] [CrossRef] [Green Version]
  41. Demantké, J.; Mallet, C.; David, N.; Vallet, B. Dimensionality based scale selection in 3D lidar point clouds. Laserscanning 2011. [Google Scholar] [CrossRef] [Green Version]
  42. Lin, Y.J.; Benziger, R.R.; Habib, A. Planar-based adaptive down-sampling of point clouds. Photogramm. Eng. Remote Sens. 2016, 82, 955–966. [Google Scholar] [CrossRef]
  43. Lin, W.; Fan, W.; Liu, H.; Xu, Y.; Wu, J. Classification of handheld laser scanning tree point cloud based on different knn algorithms and random forest algorithms. Forests 2021, 12, 292. [Google Scholar] [CrossRef]
  44. Lalonde, J.F.; Vandapel, N.; Huber, D.F.; Hebert, M. Natural terrain classification using three-dimensional ladar data for ground robot mobility. J. Field Robot. 2006, 23, 839–861. [Google Scholar] [CrossRef]
  45. Himmelsbach, M.; Luettel, T.; Wuensche, H.J. Real-time object classification in 3D point clouds using point feature histograms. In Proceedings of the IEEE/RSJ International Conference on Intelligent Robots and Systems, St. Louis, MO, USA, 11–15 October 2009; pp. 994–1000. [Google Scholar]
  46. Nguyen, K.; Jain, A.K.; Allen, R.L. Automated gland segmentation and classification for gleason grading of prostate tissue images. In Proceedings of the 20th International Conference on Pattern Recognition, Istanbul, Turkey, 23–26 August 2010; pp. 1497–1500. [Google Scholar]
  47. FARO Technologies Inc. _Faro_Laser_Scanner_Focus3D_Manual Faro Focus 3D, Lake Mary. October 2011. Available online: https://downloads.faro.com/index.php/s/CY5BS9Jd2JEf8YY (accessed on 28 December 2022).
Figure 1. Steps of Methodology.
Figure 1. Steps of Methodology.
Applsci 13 00783 g001
Figure 2. Site Image of the case study.
Figure 2. Site Image of the case study.
Applsci 13 00783 g002
Figure 3. The object recognition results between models on 25 December 2020.
Figure 3. The object recognition results between models on 25 December 2020.
Applsci 13 00783 g003
Figure 4. The object recognition results between models on 20 January 2021.
Figure 4. The object recognition results between models on 20 January 2021.
Applsci 13 00783 g004
Figure 5. The proposed system’s user interface Calculation of SPI and CPI on 25 December 2020.
Figure 5. The proposed system’s user interface Calculation of SPI and CPI on 25 December 2020.
Applsci 13 00783 g005
Figure 6. The results between manual and automated calculations on two selected dates: (a) 25 December 2020, (b) 20 January 2021.
Figure 6. The results between manual and automated calculations on two selected dates: (a) 25 December 2020, (b) 20 January 2021.
Applsci 13 00783 g006
Table 1. Definitions of geometric features.
Table 1. Definitions of geometric features.
Geometric FeatureEquationDefinition
Linear Index Lλ λ 1 - λ 2 λ 1 represents the linear features of the neighboring point cloud clusters
Planar Index Pλ λ 2 - λ 3 λ 1 represents the planar features of the neighboring point cloud clusters
Scatter Index Sλ λ 3 λ 1 represents the scattering features of the neighboring point cloud clusters
Table 2. Color Coding of elements according to Algorithm 2.
Table 2. Color Coding of elements according to Algorithm 2.
RecognizedNot Recognized
Constructedthe color of the materialRed
Not yet ConstructedGreenYellow
Not yet fully constructedBlueBrown
Table 3. Datasets characteristics in the case study.
Table 3. Datasets characteristics in the case study.
ScansScan DateStations/ScanPoint Cloud (Millions)Standard
Deviation 𝜎 (mm)
RMSE (mm)Min Overlap (%)Inclinometer Mismatch (°)
Scan 125 December 20201114.73.074.5241.260.012
Scan 26 January 20211311.723.746.3040.10.021
Scan 314 January 2021119.823.73631.70.0735
Scan 420 January 20211111.223.715.535.470.021
Table 4. Geometric Features Extraction according to KNN methods.
Table 4. Geometric Features Extraction according to KNN methods.
MethodsLλPλSλ
Method I (K = 5000)0.4290.4290.143
Method II (r = 50cm)0.3330.500.168
Method III0.200.7400.060
Table 5. Result of the earned value (SPI) to determine the project’s 4D progress (Including cost from unrecognized elements).
Table 5. Result of the earned value (SPI) to determine the project’s 4D progress (Including cost from unrecognized elements).
Scan DateBCWS ($)BCWP ($)SPI4D Performance
25 December 20208549738686551.016Ahead
20 January 20218882508941711.007Ahead
Table 6. Result of the earned value (CPI) to determine the project’s 5D progress (Including cost from unrecognized elements).
Table 6. Result of the earned value (CPI) to determine the project’s 5D progress (Including cost from unrecognized elements).
Scan DateBCWP ($)ACWP ($)CPI5D Performance
25 December 20208686553970992.188Under Budget
20 January 20218941714087632.188Under Budget
Table 7. The results of manual and automated calculation in terms of SPI and SPI.
Table 7. The results of manual and automated calculation in terms of SPI and SPI.
Scan DateManualAutomated
SPICPISPICPI
25 December 20201.0372.1831.0162.188
20 January 20211.0342.1831.0072.188
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content.

Share and Cite

MDPI and ACS Style

ElQasaby, A.R.; Alqahtani, F.K.; Alheyf, M. Automated Schedule and Cost Control Using 3D Sensing Technologies. Appl. Sci. 2023, 13, 783. https://doi.org/10.3390/app13020783

AMA Style

ElQasaby AR, Alqahtani FK, Alheyf M. Automated Schedule and Cost Control Using 3D Sensing Technologies. Applied Sciences. 2023; 13(2):783. https://doi.org/10.3390/app13020783

Chicago/Turabian Style

ElQasaby, Ahmed R., Fahad K. Alqahtani, and Mohammed Alheyf. 2023. "Automated Schedule and Cost Control Using 3D Sensing Technologies" Applied Sciences 13, no. 2: 783. https://doi.org/10.3390/app13020783

APA Style

ElQasaby, A. R., Alqahtani, F. K., & Alheyf, M. (2023). Automated Schedule and Cost Control Using 3D Sensing Technologies. Applied Sciences, 13(2), 783. https://doi.org/10.3390/app13020783