1. Introduction
The conventional Volt/Var control aims to find appropriate coordination between the on-load tap changer (OLTC) and all of the switched shunt capacitors (Sh.Cs) in the distribution networks. The main goal of a VVC system is to achieve an optimum voltage profile over the distribution feeders and optimum reactive power flows in the system [
1,
2,
3]. Recently, because of the integration of various types of Distributed Generations (DGs), some challenging issues have emerged in distribution system operation. Generally, DGs are expected to increase the number of switching operations of conventional voltage control devices, such as OLTCs and Sh.Cs [
4]. At present, inverters coupled with DG units can provide both active and reactive power based on the DSO request. Hence, by growing DG penetration into distribution systems, DG units could incorporate daily VVC.
Nowadays, all studies of VVC can be classified into two main frameworks:
centralized offline control and
real-time control. Studies on centralized offline control aim to determine dispatching schedules of VVC devices according to the day-ahead load forecast. In these studies, various objective functions such as total energy cost offered by generation units, electrical energy losses, voltage deviations, and total emission of generation units have been adopted as the methodologies for managing VVC. In [
5] an Ant Colony Optimization (ACO) algorithm has been adopted to optimize the total cost of electrical energy generated by Distribution Companies (Discos) and DGs in the daily VVC problem. In [
6] a fuzzy price-based compensation methodology has been proposed to solve the daily VVC problem in distribution systems in the presence of DGs. In [
7] a new optimization algorithm based on a Chaotic Improved Honey Bee Mating Optimization (CIHBMO) has been implemented to determine control variables including the active and reactive power of DG units, reactive power values of capacitors, and tap positions of transformers for the next day. Also, in [
8] a Fuzzy Adaptive Chaotic Particle Swarm Optimization (FACPSO) has been introduced to solve the multi-objective optimal operation management of distribution networks including fuel-cell power plants. In [
9], minimization of active power losses and micro-generation shedding have been suggested as a methodology for optimized and coordinated voltage support in distribution networks with large integration of DGs and micro-grids. In [
10], an analytic hierarchy process (AHP) strategy and Binary Ant Colony Optimization (BACO) algorithm have been employed to solve the multi-objective daily VVC in distribution systems. In [
11] a multi-objective θ-Smart Bacterial Foraging Algorithm (Mθ-SBFA) has been used for daily VVC, considering environmental and economic aspects as well as technical issues of distribution networks. According to progress in the Wind Turbine (WT) technology, Discos have paid attention to WTs more than any other Renewable Energy Sources (RESs). The stochastic nature of the wind speed may cause a fluctuation of electrical power in the distribution systems. Thus, a probabilistic analysis of distribution systems is required to cope with all uncertainties caused by the wind speed variations and load fluctuations [
12,
13]. The ability of doubly fed induction generator (DFIG)-based wind farms to deliver multiple reactive power objectives considering variable wind conditions is examined in [
14].
On the other hand, studies on real-time control methods have helped to control the VVC equipment based on real-time and local measurements and experiences. The second framework of VVC requires a higher level of distribution system automation and more hardware and software supports [
15]. This control methodology generally provides no coordination between devices, and is often limited to a unidirectional power flow. Furthermore, it is very difficult for a real-time controller to take into account the overall load change as well as the constraints of the maximum allowable daily operating times of switchable equipment. Based on SCADA capabilities and communication infrastructure, in [
16,
17], a real-time reactive power control has been implemented to optimally control the switched capacitors in distribution systems in order to minimize system losses and maintain admissible voltage profile. In [
18], a new real-time voltage control method has been discussed, using load curtailment as a part of demand response programs to regulate voltage of the distribution feeders within their allowable ranges.
However, few studies have been done about the daily VVC problem in distribution systems, in which the cost of reactive power support by various types of DERs has been considered. Hence, the establishment of a fair payment method for reactive power ancillary service of DER is necessary. Also, the reactive power capability (Q-capability) of DERs, especially the Q-capability of WTs considering wind speed fluctuations, has not been taken into account in previous studies of the VVC problem. These deficiencies motivated us to formulate a new pricing model for reactive power service from DERs, including synchronous machine-based DGs and WTs. This article also presents a new day-ahead active power market to minimize the electrical energy costs and the gas emissions of generation units. Along with this active power market, a novel reactive power dispatch framework is introduced to minimize the total cost of the following components: adjustment of the initially scheduled active powers, total active power losses, reactive power provided by DERs and Disco, and depreciation cost of the switchable facilities such as OLTC and Sh.Cs in order to achieve an economic plan for the daily VVC problem. Due to the presence of control devices such as DERs, OLTCs, Sh.Cs, etc., the daily VVC of a distribution system is a Mixed Integer Nonlinear Programming (MINLP) optimization problem. The complexity of solving this nonlinear optimization problem comprising integer variables and a great number of continuous variables forced us to employ decomposition techniques, such as the Benders decomposition algorithm.
The innovative contributions of this paper are summarized as follows:
A new methodology is presented to determine the cost of reactive power support provided by DERs.
The Q-capabilities of DGs and renewable energy sources are involved in the daily VVC problem.
A novel reactive power dispatch framework is developed for daily VVC.
The remainder of this paper is organized as follows:
Section 2 describes the cost of reactive power production from DERs. In
Section 3, the day-ahead active power market is introduced. The proposed daily VVC model is presented in
Section 4.
Section 5 presents the Benders decomposition algorithm, which is used as a solution methodology to solve the proposed reactive power dispatch model. The simulation results are discussed in
Section 6, and the conclusions of this paper are reported in
Section 7.
3. Day-Ahead Active Power Market
In the day-ahead active power market, an Initial Active Power Dispatch (IAPD) will be obtained by the MO for the forecasted load demand. This issue represents a bi-objective optimization problem in order to minimize the electrical energy costs and the gas emissions related to DERs and Disco. The generation units send their hourly selling bids, which consist of coupled quantity and price, to the MO. The total electrical energy costs generated by generation units are defined as:
One of the most important emissions from the electricity sector is CO
2, which is represented by released pollution in terms of tons per MW. In order to economically illustrate the harmful effects of the emissions from the electricity sector activities on the environment, different techniques, such as penalties through carbon taxes or cap-and-trade technique, have been adopted [
23]. In this study, the penalty cost function of the CO
2 emissions related to Disco, DGs, and WTs is calculated as follows:
Hence, the total penalty cost of CO
2 emissions produced by generation units is expressed as:
The MO runs the IAPD problem, which can be modeled by Equations (30)–(34), as a uniform price auction and determines the accepted selling bids and active power market schedule for the next day. The hourly market clearing price (MCP) is determined as the maximum selling bid price accepted for each hour.
Equations (31)–(34) represent the limits on generation and Equation (34) represents the constraint of demand/supply balance. The result of the initial schedule is submitted to the DSO to examine it from a technical viewpoint.
5. Benders Decomposition Algorithm
The proposed daily VVC model addressed in this paper is formulated as an MINLP problem. The complexity of solving nonlinear optimization problems with integer variables and a great number of continuous variables motivates us to implement decomposition techniques, such as the Benders decomposition algorithm. The general MINLP problem has been divided by means of the Benders decomposition algorithm into two structures, master and slave, which provides an iterative procedure between both structures in order to achieve an optimal solution [
25]. The proposed solution methodology is modeled in GAMS software using the CPLEX solver for solving the Mixed Integer Programming (MIP) of the master problem and the CONOPT solver for solving the Non-Linear Programming (NLP) of the slave problem.
The Benders decomposition algorithm is described as follows:
Master Problem: The master problem decides on tap setting of OLTC, steps of Sh.Cs, and values of binary variables related to the cost of reactive power provided by DGs and WTs in order to minimize the costs of switching operations. The master problem solution is transferred to the slave problem. The objective function of master problem minimizes:
Subject to the constraints Equations (46)–(50) and the Benders linear cuts as:
where
v is the iteration counter. The only real variable
in Equations (51) and (52), which contain the infeasibility costs, is an underestimation of the slave problem costs. The Benders linear cuts, which are updated for every iteration, join the master and slave problems. An additional cut is added to the master problem at each iteration with information about the objective value of slave problem in the previous iteration and the dual variables associated with the decision variables fixed by the master problem in the previous iteration. This information helps the master problem to make a new decision and reach the optimal solution.
Because of the absolute (ABS) function included in the master problem, this model expresses a NLP model with discontinuous derivatives (DNLP). The only reliable way to solve a DNLP model is to reformulate it as an equivalent smooth model. The standard reformulation approach for the ABS function is to replace the ABS function with the auxiliary positive variables,
and
, as follows:
providing that:
Therefore, the discontinuous derivative from the ABS function has disappeared and the part of the model shown here is smooth. So, the master problem is formulated as a MIP problem.
Slave problem: The slave problem formulation is nearly similar to the main problem in that all the integer variables are fixed to given the value obtained by the master problem. However, there could be some cases where the master problem’s solution makes the NLP slave problem infeasible. To avoid these cases at each iteration, artificial variables are added to some constraints and embedded in the objective function so that the objective function minimizes the technical infeasibilities of operation [
26]. Therefore, the slave problem not only verifies the technical feasibility of the master problem solution but also gives the optimal dispatches of generation units. At the last iteration, the final solution of the problem has to be feasible and optimal, that is all of these artificial variables should be equal to zero. The slave problem is formulated below:
It is subject to the constraints of Equations (42)–(45) as well as the following constraints:
where
and
are the positive artificial variables of optimization problem and
M is a large enough positive constant. The constraints of Equations (58)–(61) demonstrate the dual variables (sensitivities) associated with the discrete variables specified previously by the master problem. These dual variables and the objective value computed by the slave problem are applied to create new Benders cuts for the subsequent iteration.
Figure 3.
Flowchart of the optimization problem based on the Benders decomposition algorithm.
Figure 3.
Flowchart of the optimization problem based on the Benders decomposition algorithm.
Stopping Criterion
The Benders decomposition algorithm ends when (a) the solution created by the master problem is feasible; and (b) the slave problem costs computed through the slave problem (upper bound) and the variable (lower bound) computed through the master problem are close enough.
The procedure of the Benders decomposition algorithm for the proposed two stage model of daily VVC is shown in
Figure 3.
According to the flowchart of the Benders decomposition algorithm, the following steps are implemented:
Step 1: Initialization. Initialize the iteration counter, ν = 1. Solve the initial MIP master problem with objective function Equation (51) and subject to Equations (46)–(50). Its solution provides , , , , and . In this step, Equation (52) is not considered for initialization.
Step 2: Slave problem solution. Solve the NLP slave problem for all hours. The solution of this problem is the optimal dispatches of generation units, i.e. , , , , , , , , and , with dual variable values , , , and .
Step 3: Convergence checking. If the convergence criterion is satisfied, the optimal solution is the last values attained for variables. Otherwise, the algorithm continues with the next step.
Step 4: Master problem solution. Update the iteration counter, ν = v + 1. Solve the MIP master problem with objective function Equation (51) and subject to Equations (46)–(50) and (52).
The algorithm continues with Step 2.
6. Simulation Results
The 22 bus 20-kV radial distribution test system [
17] is modified and used for this study. The single line diagram of the test distribution network is shown in
Figure 4. The system data are given in the
Appendix. The HV/MV tap changing transformer has 11 tap positions and each tap ratio is 0.01 p.u. The maximum permissible daily number of operations of the transformer is 20. Voltage limits are considered to be ±5% of nominal voltage. The capacitor banks 1 and 2 have the capacity of 1000 kVAr with five switching steps of 200 kVAr. Three DERs including two DGs and a WT are connected at the distribution buses, as shown in
Figure 4. General parameters such as the capacity, location, and CO
2 emissions of generation units have been reported in
Table 1. The values of
and
are assumed to be 0.1 (ton/MWh) and 40 ($/ton), respectively [
27].
Figure 4.
The single line diagram of a 22-bus distribution test system.
Figure 4.
The single line diagram of a 22-bus distribution test system.
Table 1.
Capacity, location, and emissions of generation units.
Table 1.
Capacity, location, and emissions of generation units.
neration Unit | Capacity | Location | CO2 (ton/MWh) |
---|
Disco | 20 MVA | - | 0.927 |
DG1 | 400 kW | Bus 11 in feeder 2 | 0.489 |
DG2 | 1000 kW | Bus 9 in feeder 1 | 0.724 |
WT | 500 kW | Bus 8 in feeder 1 | 0 |
Table 2 shows the generation unit selling bids, including the blocks of bid power and the generation bid prices.
Table 2.
Selling bids offered by generation units.
Table 2.
Selling bids offered by generation units.
Generation Unit | Hour | Block Number | Quantity (kW) | Price ($/kWh) |
---|
DG1 | 1–24 | 1 | 200 | 0.045 |
2 | 100 | 0.05 |
3 | 100 | 0.06 |
DG2 | 1–24 | 1 | 400 | 0.042 |
2 | 400 | 0.05 |
3 | 200 | 0.06 |
WT | 1–6 | 1 | 100 | 0.041 |
7–10 | 1 | 366 | 0.041 |
11–15 | 1 | 442 | 0.041 |
16–18 | 1 | 500 | 0.041 |
19–22 | 1 | 480 | 0.041 |
23–24 | 1 | 100 | 0.041 |
Disco | 1–8 | 1 | 8000 | 0.04 |
9–10 | 1 | 8000 | 0.045 |
11–13 | 1 | 8000 | 0.05 |
14–15 | 1 | 8000 | 0.052 |
16 | 1 | 8000 | 0.053 |
17 | 1 | 8000 | 0.054 |
18–19 | 1 | 8000 | 0.053 |
20–22 | 1 | 8000 | 0.052 |
23–24 | 1 | 8000 | 0.05 |
6.1. Active Power Market Schedule Obtained by the MO
The linear programming of IAPD is programmed in the GAMS and solved by the solver CPLEX. The output of this program provides the hourly MCP and the accepted bid power of each generation unit for the next day, as indicated in
Table 3. The schedule of each generation unit is sent to the DSO for verifying technical validation.
6.2. Daily Optimal Dispatches of VVC Devices
Table 4 and
Table 5 present the data of DERs, including information characterizing the capability diagrams of the generator, components of offered prices of reactive power, the generator adjustment price, and the maximum admitted change as a percentage of its IAPD. The cost of reactive power generated by Disco, corresponding adjustment price, and maximum admitted change in its IAPD are 0.022 ($/kVArh), 0.09 ($/kWh), and 40%, respectively. The mandatory power factor (
) has been taken to be 0.95. The maximum variability of the actual hourly wind power from the forecasted value is considered to be 10% of the forecasted value.
Table 3.
Initial active power schedule.
Table 3.
Initial active power schedule.
Hour | (kW) | (kW) | (kW) | (kW) | ($/kWh) | Hour | (kW) | (kW) | (kW) | (kW) | ($/kWh) |
---|
1 | 422.62 | 300 | 400 | 100 | 0.05 | 13 | 4264.6 | 400 | 800 | 442 | 0.06 |
2 | 76.12 | 300 | 400 | 100 | 0.05 | 14 | 2056.3 | 400 | 1000 | 442 | 0.06 |
3 | 468.89 | 300 | 400 | 100 | 0.05 | 15 | 260.66 | 400 | 1000 | 442 | 0.06 |
4 | 626.39 | 300 | 400 | 100 | 0.05 | 16 | 187.89 | 400 | 1000 | 500 | 0.06 |
5 | 659.85 | 300 | 400 | 100 | 0.05 | 17 | 2008.1 | 400 | 1000 | 500 | 0.06 |
6 | 691.35 | 300 | 400 | 100 | 0.05 | 18 | 5069.76 | 400 | 1000 | 500 | 0.06 |
7 | 488.35 | 300 | 400 | 366 | 0.05 | 19 | 5897 | 400 | 1000 | 480 | 0.06 |
8 | 801.39 | 300 | 400 | 366 | 0.05 | 20 | 5756.23 | 400 | 1000 | 480 | 0.06 |
9 | 1375.4 | 400 | 800 | 366 | 0.06 | 21 | 4646.8 | 400 | 1000 | 480 | 0.06 |
10 | 4003.9 | 400 | 800 | 366 | 0.06 | 22 | 2925.01 | 400 | 1000 | 480 | 0.06 |
11 | 4651.49 | 400 | 800 | 442 | 0.06 | 23 | 598.89 | 400 | 800 | 100 | 0.06 |
12 | 4758.8 | 400 | 800 | 442 | 0.06 | 24 | 80.12 | 400 | 800 | 100 | 0.06 |
Table 4.
Characteristics of the DGs.
Table 4.
Characteristics of the DGs.
R | (kW) | (kVAr) | (kVAr) | (kVAr) | ($) | ($/MVArh) | ($/MVArh) | ($/kWh) | |
---|
DG1 | 400 | 400 | −400 | 400 | 0.6 | 23 | 23 | 0.08 | 50% |
DG2 | 1000 | 1000 | −600 | 800 | 0.8 | 30 | 30 | 0.075 | 50% |
Table 5.
Characteristics of the WT.
Table 5.
Characteristics of the WT.
DER | (p.u.) | (p.u.) | X (p.u.) | (kVAr) | ($) | ($/kWh) | | | |
---|
WT | 1.4 | 1.24 | 0.2 | −250 | 0.9 | 0.095 | 10.14 | 0.003 | 50% |
In order to calculate the depreciation cost of OLTC, the installation cost of an OLTC is assumed to be
as reported in [
26]. The total number of acceptable switching operations of each OLTC can be 143,080 times (=20 steps/day × 365 days/year × 20 years × 0.98 availability factor). Thus, the depreciation cost for each step change
is $2.79. Also, the installation cost for each Sh.C is $11,600
as given in [
26]. Each Sh.C can be operated 71,540 times (=10 switching operations/day × 365 days/year × 20 years × 0.98 availability factor). Therefore, the depreciation cost for each switching operation of Sh.C
is equal to $0.162.
The daily VVC problem proposed in this paper will be tested on three different cases, as follows:
6.2.1. Case 1 (Base Case) and Implementing the Benders Decomposition Algorithm
By implementing the Benders decomposition algorithm,
Figure 5 shows the hourly optimal dispatch results of the Sh.Cs for case 1. The number of switching operations for C1 and C2 is 9 and 7, respectively, which is less than the maximum allowable daily number of operations (10). Moreover, because of the high depreciation cost of OLTC, the tap position of OLTC is fixed at 1.04 pu during the whole day.
Table 6 shows the optimal dispatch of generation units. In this case, the change in the IAPD corresponding to operation or security enforcements is not necessary. So, all
variables are zero. Regarding the
variables, these variables are zero for DG1 and WT for all hours. Hence, the power losses of network are balanced in the two buses using Disco and DG2. The voltage profiles at the buses of feeders 1 and 2 are illustrated in
Figure 6. In this figure, the voltages of buses are brought back to the acceptable range of 0.95 to 1.05 pu for 24 h.
Figure 5.
Daily optimal dispatches of the Sh.Cs for case 1.
Figure 5.
Daily optimal dispatches of the Sh.Cs for case 1.
Figure 6.
Voltage profile of feeders 1 and 2 after Volt/Var control for case 1.
Figure 6.
Voltage profile of feeders 1 and 2 after Volt/Var control for case 1.
6.2.2. Case 2: Considering Functions , , . and Implementing the DICOPT Solver
In order to validate the results obtained by the proposed approach, the same problem has been tested by relaxing all constraints of the daily number of switching operations. In this case, since the optimal dispatch results of OLTC and Sh.Cs for each hour are not correlated with the solutions of the other hours, the daily VVC problem can be solved separately for each hour using the DICOPT solver. The daily optimal dispatch results of OLTC and Sh.Cs corresponding to the objectives of
to
are illustrated in
Figure 7 and
Figure 8, respectively. As seen in
Figure 8, the number of operations of C1 and C2 are 12 and 16, respectively, which is higher than the acceptable maximum.
Table 7 provides the optimal reactive power dispatch of generation units in case 2. In order to confirm the effectiveness of the proposed method based on the Benders decomposition algorithm,
Table 8 provides a comparison between the results of cases 1 and 2. From the comparison of results shown in
Table 8, it has been observed that despite the limited switching operations included in the Benders decomposition-based proposed method, the total cost decreases to $449.26, compared to $477.761 when no restriction is imposed on the switched devices; this confirms the effectiveness of Benders decomposition. On the other hand, when the limitation on switching operations of control devices is not considered, the active power loss has decreased from 998.134 kW to 954.506 kW. This is due to the fact that an unlimited number of switching operations provides a more flexible control of the power flow to regulate the voltage within its admissible range and to fulfill the operational constraints.
Table 6.
Daily optimal dispatch of generation units for case 1.
Table 6.
Daily optimal dispatch of generation units for case 1.
Hour | Disco | DG1 | DG2 | WT |
---|
(kW) | (kW) | Q (kVAr) | (kW) | (kW) | Q (kVAr) | (kW) | (kW) | Q (kVAr) | (kW) | (kW) | Q (kVAr) |
---|
1 | 2.31 | 0 | 0 | 0 | 0 | 52.64 | 0 | 0 | −23.82 | 0 | 0 | −32.87 |
2 | 2.93 | 0 | 0 | 0 | 0 | −53.89 | 0 | 0 | −131.48 | 0 | 0 | −32.87 |
3 | 2.30 | 0 | 0 | 0 | 0 | 98.61 | 0 | 0 | −35.10 | 0 | 0 | −32.87 |
4 | 2.88 | 0 | 0 | 0 | 0 | −35.58 | 0 | 0 | 131.48 | 0 | 0 | 32.87 |
5 | 0 | 0 | 0 | 0 | 0 | 59.91 | 2.72 | 0 | 44.53 | 0 | 0 | 32.87 |
6 | 3.07 | 0 | 0 | 0 | 0 | −7.21 | 0 | 0 | 131.48 | 0 | 0 | 32.87 |
7 | 0 | 0 | 0 | 0 | 0 | 12.60 | 3.77 | 0 | 63.91 | 0 | 0 | 120.30 |
8 | 0 | 0 | 0 | 0 | 0 | 98.61 | 4.38 | 0 | 132.92 | 0 | 0 | 171.89 |
9 | 10.51 | 0 | 0 | 0 | 0 | −30.40 | 0 | 0 | 262.96 | 0 | 0 | 120.30 |
10 | 0 | 0 | 1043.76 | 0 | 0 | 131.48 | 63.38 | 0 | 283.79 | 0 | 0 | 471.50 |
11 | 0 | 0 | 1432.18 | 0 | 0 | 395.42 | 89.31 | 0 | 292.32 | 0 | 0 | 384.72 |
12 | 0 | 0 | 1515.26 | 0 | 0 | 400.00 | 94.75 | 0 | 294.10 | 0 | 0 | 384.72 |
13 | 0 | 0 | 1223.6 | 0 | 0 | 313.03 | 73.41 | 0 | 287.09 | 0 | 0 | 384.72 |
14 | 17.01 | 0 | 0 | 0 | 0 | 131.48 | 0 | 0 | 265.07 | 0 | 0 | 275.70 |
15 | 12.31 | 0 | 0 | 0 | 0 | 131.48 | 0 | 0 | −223.85 | 0 | 0 | −145.29 |
16 | 12.99 | 0 | 0 | 0 | 0 | 131.48 | 0 | 0 | −219.35 | 0 | | |
17 | 16.99 | 0 | 0 | 0 | 0 | 131.48 | 0 | 0 | 328.70 | 0 | 0 | 157.86 |
18 | 111.50 | 0 | 1854.32 | 0 | 0 | 400.00 | 0 | 0 | 328.70 | 0 | 0 | 366.61 |
19 | 161.90 | 0 | 2472.03 | 0 | 0 | 400.00 | 0 | 0 | 328.70 | 0 | 0 | 366.61 |
20 | 162.84 | 0 | 2648.13 | 0 | 0 | 131.48 | 0 | 0 | 328.70 | 0 | 0 | 366.61 |
21 | 99.95 | 0 | 1850.04 | 0 | 0 | 131.48 | 0 | 0 | 328.70 | 0 | 0 | 366.61 |
22 | 33.50 | 0 | 560.77 | 0 | 0 | 131.48 | 0 | 0 | 328.70 | 0 | 0 | 366.61 |
23 | 0 | 0 | 0 | 0 | 0 | 131.48 | 6.50 | 0 | 265.10 | 0 | 0 | 28.26 |
24 | 6.94 | 0 | 0 | 0 | 0 | −28.98 | 0 | 0 | 93.81 | 0 | 0 | 32.87 |
Figure 7.
Daily optimal tap positions of OLTC for case 2.
Figure 7.
Daily optimal tap positions of OLTC for case 2.
Figure 8.
Daily optimal dispatches of the Sh.Cs for case 2.
Figure 8.
Daily optimal dispatches of the Sh.Cs for case 2.
Table 7.
Daily optimal reactive power dispatches of generation units for case 2.
Table 7.
Daily optimal reactive power dispatches of generation units for case 2.
Hour | Disco (kVar) | DG1 (kVar) | DG2 (kVar) | WT (kVar) | Hour | Disco (kVar) | DG1 (kVar) | DG2 (kVar) | WT (kVar) |
---|
1 | 0 | 87.86 | 41.02 | 66.65 | 13 | 1228.46 | 307.42 | 286.66 | 384.72 |
2 | 0 | 65.16 | 77.62 | 37.94 | 14 | 0 | 131.48 | 264.96 | 275.53 |
3 | 0 | 93.53 | 57.34 | 79.36 | 15 | 0 | 131.48 | 112.66 | 115.30 |
4 | 0 | 98.61 | 105.25 | 124.29 | 16 | 0 | 131.48 | 166.54 | 246.82 |
5 | 0 | 98.57 | 110.98 | 127.49 | 17 | 0 | 131.48 | 318.69 | 366.61 |
6 | 0 | 98.61 | 120.54 | 137.52 | 18 | 1852.32 | 400 | 328.70 | 366.61 |
7 | 0 | 98.61 | 132.63 | 165.34 | 19 | 2469.08 | 400 | 328.70 | 366.61 |
8 | 0 | 98.61 | 95.55 | 209.17 | 20 | 2368.11 | 400 | 328.70 | 366.61 |
9 | 0 | 131.48 | 190.22 | 229.27 | 21 | 1848.24 | 131.48 | 328.71 | 366.61 |
10 | 1013.82 | 160.49 | 283.26 | 471.50 | 22 | 560.19 | 131.48 | 328.70 | 366.61 |
11 | 1436.91 | 389.77 | 291.78 | 384.72 | 23 | 0 | 131.48 | 109.34 | 183.21 |
12 | 1514.24 | 400.00 | 293.51 | 384.72 | 24 | 0 | 131.48 | 235.04 | 130.39 |
Table 8.
Comparison of optimal results in cases 1 and 2.
Table 8.
Comparison of optimal results in cases 1 and 2.
Different Parts of Objective Function | Case 1 | Case 2 |
---|
Benders Decomposition | DICOPT Solver |
---|
Number of switching operations of OLTC | 0 | 4 |
Number of switching operations of C1 | 9 | 12 |
Number of switching operations of C2 | 7 | 16 |
Total active power losses (kWh) | 998.134 | 954.506 |
Depreciation cost of OLTC ($) | 0 | 11.16 |
Depreciation cost of Sh.Cs ($) | 2.592 | 4.536 |
Total cost of active power losses ($) | 59.64 | 57.07 |
Total cost of reactive power ($) | 387.03 | 404.995 |
Total cost ($) | 449.26 | 477.761 |
6.2.3. Case 3: Stressed Operation for Peak Hours and Implementing the Benders Decomposition Algorithm
In this case, due to the operational issues, the maximum reactive power of Disco was limited to peak hours (18–21) to get a more stressed operation situation. The maximum reactive power of Disco was decreased by 1300 kVAr, 1920 kVAr, 1860 kVAr, and 1050 kVAr at hours 18, 19, 20, and 21, respectively.
Table 9 presents the results obtained for reactive power dispatches of generation units for peak hours. As indicated in
Table 9, the
variable is not zero for Disco and DG2. Also, the reactive power of DG1 is increased by 400 kVar (maximum reactive power capability) at hours 20 and 21. Furthermore, since the active and reactive power values are coupled via the capability diagram, a reduction in the active power generation of DG2 takes place to adjust for the reactive power requirements of the system. The other results of daily optimal dispatches of generation units, OLTC, and Sh.Cs are not changed. Concerning the objective function, its final value is $714.99. This value is much greater than that of case 1 because it comprises the adjustment costs of the initially scheduled active powers.
Table 9.
Daily optimal reactive power dispatches of generation units for peak hours for case 3.
Table 9.
Daily optimal reactive power dispatches of generation units for peak hours for case 3.
Hour | Disco | DG1 | DG2 | WT |
---|
(kW) | (kW) | Q (kVar) | (kW) | (kW) | Q (kVar) | (kW) | (kW) | Q (kVar) | (kW) | (kW) | Q (kVar) |
---|
18 | 125.73 | 478.79 | 1300 | 0 | 0 | 400 | 0 | −478.79 | 895.76 | 0 | 0 | 366.61 |
19 | 174.714 | 461.01 | 1920 | 0 | 0 | 400 | 0 | −461.01 | 892.20 | 0 | 0 | 366.61 |
20 | 147.39 | 172.38 | 1860 | 0 | 0 | 400 | 0 | −172.38 | 834.48 | 0 | 0 | 366.61 |
21 | 96.68 | 286.48 | 1050 | 0 | 0 | 400 | 0 | −286.48 | 857.3 | 0 | 0 | 366.61 |