Next Article in Journal
The Device Using a Polydimethylsiloxane Membrane and the Phase Transition of Water
Next Article in Special Issue
A Novel Method for Joining Steel/Al Tube Parts Based on Electromagnetic Force by Flat Coil
Previous Article in Journal
Carbon Dot/Polymer Composites with Various Precursors and Their Sensing Applications: A Review
Previous Article in Special Issue
Numerical Simulation and Parameter Analysis of Electromagnetic Riveting Process for Ti-6Al-4V Titanium Rivet
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Design of a Fast Temporary Fastener with the Labor-Saving and Reversible Ability

1
School of Intelligent Engineering, Shaoguan University, Shaoguan 512023, China
2
School of Electromechanical Engineering, Guangdong University of Technology (GDUT), Guangzhou 510006, China
3
College of Mechanical Engineering, Zhejiang University, Hangzhou 310027, China
*
Author to whom correspondence should be addressed.
Coatings 2021, 11(9), 1101; https://doi.org/10.3390/coatings11091101
Submission received: 28 July 2021 / Revised: 3 September 2021 / Accepted: 9 September 2021 / Published: 12 September 2021

Abstract

:
Aircraft panel assembly mainly includes the pre-joining process and the riveting process. In addition, the traditional pre-joining process is mainly executed by bolts, which has problems such as the large tightening torque, inconvenient bilateral tightening, heavy workload, and inconvenient loading and unloading. To solve the above-mentioned problems, a research of new temporary fastener is performed deeply from three levels of quick installation, labor-saving, and reversible ability. This involves (a) employing the lever mechanism and the rapid expansion anchor to implement the rapid clamping and disassembly of working processes by labor-saving; (b) integrating the adjusting spring to overcome the tolerances of parts; and (c) building up the space-cross slide rails to provide the axial clamping forces and the reversible forces. The application of designed fasteners was employed into the production of aircraft panel, and the error between theoretical and experimental values was less than 10%. Besides this, the result showed the good effect in panel clamping and the reliable processes of loading and unloading installation, and will greatly reduce the complexity of pre-joining process, the difficulty of installation, and the comprehensive cost.

1. Introduction

Aircraft panel assembly mainly includes two stages: the pre-joining process and the riveting process [1]. Panels usually require a certain number of temporary fasteners to make the pre-joining before riveting, to reduce the initial clearance of assembly, and to fix the relative position of each part. The traditional pre-joining process is mainly fastened by bolts, and this kind of fasteners adopts the method of bilateral fastening when clamping [2]. Namely, bolts and nuts need to be installed on both sides of the panel. The length and width of aircraft panel being generally more than 1000 mm will lead to the low installation efficiency, the large labor intensity, and the poor man-machine friendliness.
In a society with highly developed technology, the industrial field put forward the concept of “intelligent manufacturing”, and the development of industrial design will develop towards automation, intelligence, and so on [3,4,5,6]. As an important part in the field of mechanical design, fasteners are used to ensure the normal assembly and processing of parts. Therefore, higher requirements will be put forward for its efficiency and performance.
In the field of aviation assembly, temporary fasteners play a key role in improving the initial conditions of drilling and riveting in the next step. The research on temporary fasteners has important academic value and engineering application value [7].
In the aspect of panel pre-joining processing, Yang Di and Liu Gang et al. [8,9,10,11] focused on the problems of excessive number and inappropriate position of pre-joining holes, established a model on deformation of pre-joining, and proposed a method of equivalent clearances calculation to realize the rapid prediction of residual gap after pre-joining. To improve the efficiency of pre-joining process, Zhou Shuyang et al. [12] improved the simulated annealing algorithm, applied it to the layout of pre-joining holes, and saved a lot of work time. Liu Xia et al. [13] studied the influence of clamping force of fasteners on the deformation of aircraft panel assembly, established deformation analysis method of aircraft panel based on the positioning process of parts, and proposed a more accurate and reliable prediction of part deformation. The above literatures have studied the aspects of pre-joining deformation and efficiency. However, they did not research the innovative design of temporary fasteners for pre-joining.
In terms of fasteners, Xiaodong Huang and Quan Wang [14] theoretically designed a pre-joining fastener model and an end-effector for automatic installation of aircraft assembly, which used the expansion bolts principle, a screw transmission structure, and an automatic installation system to achieve fastening connection. However, in this design, there are problems, such as it being expensive, complicated, time-consuming, and labor-consuming. The experimental research was also not carried out. Cheng Yalong et al. [15] proposed a fast assembly method for fasteners with feature recognition, but this method still uses bolts for bilateral fastening, and does not optimize the installation efficiency of the fasteners themselves. Camacho Javier et al. [16] designed an online detection method for blind fasteners that were installed incorrectly based on the sensor signal during the installation process. The results show that the method can identify the torque diagrams, whether the installation process is normal or not. The system is an automatic and accurate detection system, and has the ability to automatically recognize and classify installation process. Wilson et al. [17] designed a surface acoustic strain sensor to apply into the fault detection of aircraft fasteners, which could successfully detect the failure of a single fastener, but there was no structural design of fastener related to this sensor. In order to improve the connection strength and study the optimization of connection structure, Li Yan et al. [18] analyzed the repair of connection round hole damage based on the elastic–plastic finite element method, and also displayed the connection load of all rivets under the three different patch shapes. These results have demonstrated that the strength of aircraft skin after riveting can be significantly improved by using the circular patch structure, compared with the rectangular patch and the rounded rectangular patch, under the same materials, riveting parameters, and process equipment. Nevertheless, the strength problem after pre-joining for them was not studied.
In order to solve the problems of high cost and low precision for the pre-joining process of a traditional aircraft panel, this paper designs a temporary fastener for pre-joining with single-side installation as well as labor-saving and reversible ability, combining the lever principle, the anchor expansion mechanism, the adjusting spring, and the space-cross slide rails.

2. Innovative Design of Temporary Fastener

2.1. Functional and Structural Innovative Design

To achieve the requirement of the unilateral quick installation and disassembly in the pre-joining process of aircraft panels, the following functions and their innovative structures are designed in Table 1.
And their specific structure is illustrated in Figure 1.
Assembly process of the temporary fastener is as follows. First, the expansion anchor and the chute table are connected by thread, and then the expansion anchor is inserted into the stepped hole of the chute table. Secondly, a matching relationship is made between the expansion shaft and the expansion anchor, i.e., a transition fit, and the expansion shaft is inserted from the lower end of the expansion anchor into the corresponding position, so that the expansion shaft, expansion anchor, and the chute table complete the connection process. Then, the pin shaft is passed through the holes of the expansion shaft and the lever, and the connection process is completed. In this phase, the expansion shaft, the expansion anchor, the chute table, and the lever are connected. Afterwards, spring and the adjusting plate from the bottom one by one are installed, the spring between the adjustment plate and the chute table is clamped, and the bolts inserted into the adjusting plate and the chute table are adjusted in turn. Finally, the two chute table are covered, and the nuts of the two adjusting bolts are screwed on to complete the assembly of the whole device.

2.2. Apply Method of Temporary Fasteners on Aircraft Panel

2.2.1. Preparation Action

The work-pieces are placed with holes on top of each other, then the expansion shaft and expansion anchor are passed through the hole to complete the preparation action, as shown in Figure 2.

2.2.2. Clamping Process

The whole clamping process is divided into two stages.
  • The first stage is the upward expansion stage. In this stage, the lever is rotated to drive the expanding shaft to lift up. The lifting resistance caused by the expansion of the expansion anchor is small, and it is not enough to overcome the resistance of the spring to compress it, so no clamping force is generated between the two workpieces.
  • The second stage is the clamping stage. In the first stage, the expansion anchor is stretched by the expansion shaft until it contacts the workpiece. Therefore, in this stage, the lever mechanism continues to rotate, and the force is transmitted to the chute table through the lateral convex platform of the short part of the lever. Next, the pin shaft is employed as the fulcrum to press down the chute table, so that the spring between the chute table and the adjusting plate is compressed to produce elastic force. Then, the adjust plate cooperates with the expanded anchor to produce clamping force. Finally, the clamping force is the largest at the time when the lever is in the vertical position, and the fastening action is completed. It can be seen from the above that the device has the advantages of simple operation and reliable structure.

2.2.3. Disassembly Process

The disassembly process is also divided into two stages. In the first stage, the lever is rotated slightly and the spring gradually recovers from the compressed state to the pre-compressed state. Consequently, the contact point of the chute table cover and the short convex head is used as the fulcrum to press down the shaft, and the expansion anchor recovers from the expanded state and completes the disassembly process.

3. Relationship Analysis of Temporary Fastener

3.1. Analysis of Geometric Relationship

Assume that Ls in Figure 3 represents the distance from the middle hole of the lever to the bottom. Take Ls as a stage flag, the whole working process is divided into the upward expansion stage and the downward clamping stage. Because the upward expansion stage does not produce clamping force, the analysis of geometric relations is the beginning of the downward clamping stage:
At the clamping stage, the bottom of the lever moves from position ① to position ②, making circular motion with the fulcrum as the sports center. The angle between the horizontal line and the center line of the lever at the beginning of the clamping stage is θ, and α is the angle between the center line of the lever and the vertical line.
If α is too small, it may cause the lever to sway during processing and tightening failure. If α is too large, the tightening process will be inconvenient.
θ and α have the following relationship:
θ = π 2 α
R represents the radius of the rail arc of the chute table, and x0 represents the theoretical compressed amount of the spring, x represents the actual compressed amount of the spring. Affected by the arc of the chute, the actual compressed amount will be slightly smaller than the theoretical compressed amount.
In the clamping stage, the lever uses the pin as a fulcrum to compress the spring, and the ideal compression amount of the spring in this process is x0.
x0 can be calculated:
x 0 = L s · ( 1 cos θ )
x can be calculated:
x = L s · ( 1 cos θ ) R + R 2 ( L s · sin α ) 2
The relation between x0 and x is:
x 0 x = R R 2 ( L s · sin α ) 2 x
In order to make a reliable fastening, the angle α should not be too small, i.e., about 45°. To make the tightening process smooth, R should take a larger value. Therefore, in the tightening process, the influence of the rail arc on the compression of the spring can be ignored, and the difference between x0 and x is negligible. Approximately replace x with x0 for calculation.
Δh represents the tolerance of the thickness of the two plates during processing, and Fj represents the clamping force, and k represents the elastic coefficient of the spring
As obtained from Hooke’s law, when the compression amount of the spring is x0, Fj can be calculated:
F j = k · ( x 0 + Δ h )
Theorem 1.
Hooke’s law.
Δh is positive when the thickness of the plate is greater than the standard value; in this case, the adjusting nut should be tightened before clamping the plate, so that the adjusting spring can compress to overcome the positive tolerance. Since the adjustment spring increases the amount of pre-compression, the actual clamping force is slightly bigger than calculated by k·Δh.
Δh takes a negative value when the thickness of the plate is less than the standard value; in this case, in order to compensate the negative tolerance, it is necessary to loosen the adjusting nut before clamping the plate. Since the adjustment spring decreases the amount of pre-compression, the actual clamping force is slightly less than calculated by k·Δh.

3.2. Analysis of Mechanical Relationship

  • The weight of the lever has limited influence on the whole process, so that it is negligible. The follows analyze the force on the lever.
Figures a and b in Figure 4 respectively show the force on the lever during the clamping process and the balance state.
Fn——User’s tightening force;
F0——The counterforce on the lever from the chute table;
Fj——The counterforce on the lever from the pin shaft.
Assuming that the contact point between the user and the lever is at the head of the lever, the direction is perpendicular to the lever axis and diagonally upward. The reaction force of the chute table acting on the short part of the lever was decomposed into F01 and F02. The direction of the Fj is vertical downward, and the Fj is considered to be the resultant force of the lever from the pin shaft.
The force analysis of the contact point between the bottom of the lever and the chute table is enlarged, as follows:
In Figure 5, β can be calculated by the law of cosines:
β = arccos L s 2 + R 2 ( R L s · sin θ Δ x ) 2 2 L s · R
γ is the angle between component force F02 and the horizontal line:
γ = π 2 θ β = π 2 θ arccos L s 2 + R 2 ( R L s · sin θ Δ x ) 2 2 L s · R
Substitute it into Equation (1), and the difference between the theoretical compression amount and the actual compression amount of the spring x0-x is too small to be ignored:
γ = α arccos L s 2 + R 2 ( R L s · cos α ) 2 2 L s · R
2.
Force analysis of the device:
To better analyze the force situation, in Figure 5, the reaction force of the chute table acting on the short part of the lever was decomposed into F01 and F02.
The angle between F01 and the horizontal line is the sum of θ and β, and the angle between F02 and the horizontal line is γ.
Figure 6 shows the force of the device, from the perspective of the force balance of the device, it can be derived:
F 01 · sin γ = F n · cos α + F 02 cos γ
F j = F 01 · cos γ + F 02 sin γ + F n · sin α
The moment balance equation of the lever fulcrum is as follows:
F n · L l = F 01 · L s · sin β + F 02 · L s · cos β
Simultaneous Equations (9)–(11) obtain the relationship between tightening force and clamping force:
F n = 2 · F j sin ( β + π 4 ) K 1 · cos γ + sin α · ( sin β + 1 ) + cos α tan γ
where K1 represents the length ratio of the long part to the short part of the lever L l L s , α, β, and γ can be calculated by Equations (1), (6), and (8), respectively. Fj can be calculated by Equation (5).
The amount of tightening force should be taken into account in the design to avoid excessive tightening force.

4. Materials and Methods

4.1. Experimental Procedure

  • An experimental platform was set up, as shown in Figure 7.
In order to facilitate the force measurement, the experimental device was placed vertically. The base of this device was made of metal, the tension meter produced by Wei Du company was used to measure the force of the lever, and the clamping force between the two plate parts was measured with a pressure meter produced by Arizon company.
2.
The pressure gauge and the tension gauge was installed, and the pressure gauge on the experimental platform was fastened with fasteners;
3.
The tension gauge was perpendicular to the lever, and the tension was applied through the tension gauge until the fastener locked the plate parts;
4.
The values displayed by the tension gauge and pressure gauge was recorded;
5.
The tests were repeated 5 times and an average was calculated;

4.2. Main Parameters of Parts

In order to verify the validity of the theoretical method, we assume that the related values of materials and sizes were determined and illustrated in Table 2.

5. Results and Discussion

5.1. Theoretical Calculation

Through the spring compression experiment, the spring coefficient of elasticity was 52.3 N/mm, Ls = 19.77 mm. At the beginning of the clamping phase, the angle θ between the lever and the horizontal line was measured to be 45°, R = 80 mm. The free length of the spring was 20.2 mm, the compressed length was 17.1 mm, and so the compressed amount was 3.1 mm. By substituting the above parameters into Equation (5), and assuming that Δh was 0, Fj was:
F j = k · ( x 0 + Δ h ) = 52.3 × 3.1 = 162.13 N
The tightening force was calculated, and the theoretical clamping force was taken as 162.13 N and the tightening angle α as 30°. The above parameters were substituted into Equations (6) and (7):
β = arccos 19.77 2 + 80 2 ( 80 19.77 × cos 30 ° ) 2 2 × 19.77 × 80 = 26.37 °
γ = α β = 30 26.37 = 3.63 °
The angle β and γ was 26.37° and 3.63°, respectively.
By supposing that K1 was the ratio of the length of the long part to the short part of the lever, K 1 = L l L s = 113.93 19.77 = 5.76 . The above parameters were then substituted into Equation (11):
F n = 2 · F j sin ( β + π 4 ) K 1 · cos γ + sin α · ( sin β + 1 ) + cos α tan γ
The theoretical tightening force was 10.8 N.

5.2. Data Comparison

As the lever was affected by gravity, the device had an initial pulling force during measurement, which is shown in Figure 7. The measurement results of the tension gauge and pressure gauge are shown in Figure 8:
The comparison between the theoretical and actual values for the tension and pressure was as follows.

5.3. Discussion

It could be found from Table 3 that there was a difference between the theoretical calculation value and the actual value. Because there were errors in the various dimensions of the parts, as well as error values in the instrument measurement process, the errors were accumulated. Besides this, when calculating the theoretical clamping force, we believed that there was no relative displacement between the expansion anchor and the plate. However, in fact, due to the plasticity of the expansion anchor, the expansion anchor was squeezed to produce elasticity reaction force when the pin was pressed down by the lever. This caused an increase in the actual clamping force. Meanwhile, in the analysis, the small gravity of the lever and the friction force between the actual lever and the chute table were ignored, which caused the actual tightening force to be greater than the theoretical tightening force.
At the same time, the following three advantages shown in Table 4 of this device can be seen from the experimental process of Figure 7 and Figure 8.

6. Conclusions

To solve the problems of low efficiency and high cost caused by the bilateral installation of the traditional pre-joining process, this paper proposed a new fastener which is suitable for unilateral pre-joining process of the aircraft panels.
In contrast to bolts by bilateral fastening with time-consuming, labor-intensive, and low-efficiency characteristics, the fastener has many advantages: low comprehensive cost, convenient operation, and quick disassembly.
For this fastener, the clamping force was provided by combining it with the lever mechanism, expansion shaft, and clamping spring. Furthermore, the amount of pre-compression of spring could be adjusted according to the different needs of clamping force. Therefore, it could provide reliable clamping force for pre-joining process. Meanwhile, the fastener combined with lever mechanism could realize the labor-saving in operation. In this fastener, spring was adapted to overcome the tolerance of workpiece, and the reversal function of the device was realized by the elastic expansion anchor and a space cross groove of the chute table.
After the fasteners were applied to the panel assembly process, the results showed that the fasteners could be assembled and disassembled only by rotating back and forth at a small angle with a small force.
In the process of design and experiment, a difference between the theoretical calculation value and the actual value could be found. The theoretical clamping force was 162.13 N, when the actual clamping force was 182.26 N. The error ratio between them was 8.9%, because, when calculating the theoretical clamping force, we ignored the compressibility of expansion anchors that would cause the increasement of the actual clamping force. The theoretical tightening force was 10.8 N, while the actual tightening force was 14.08 N. The error ratio between them was 7.6%, because in the analysis, the small gravity of the lever and the friction force during the tightening process were ignored, which caused the actual tightening force to be greater than the theoretical tightening force.
There are also some disadvantages associated with this fasteners. The elasticity of the expansion anchor could be weakened after used for a several times, which may bring inconvenience in use. When the adjusting spring is employed to adapt the tolerances, the pre-compression amount on the clamping force may hardly change. The above two points could be the direction of further research.

Author Contributions

Conceptualization, W.T. and W.Q.; methodology, W.T.; val-idation, Y.Y.; formal analysis, X.X.; investigation, X.X.; resources, W.T.; data cura-tion, Y.Y.; writing—original draft preparation, X.X.; writing—review and editing, W.T.; visualiza-tion, X.X.; supervision, W.T.; project administration, W.T. and W.Q.; funding acquisition, W.T. All authors have read and agreed to the published version of the manuscript.

Funding

This research was funded by Shaoguan City Science and Technology Planning Project (No. 2019 sn067) and Educational Research Project for Young and Middle-aged Teachers of Fujian Education Department (No. JAT170193).

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Liu, J.T.; Zhao, A.; Liu, Y.; Dong, H.Y.; Bi, Y.B. Numerical and experimental investigation on the rivet head flushness in automatic countersunk riveting. Int. J. Adv. Manuf. Technol. 2020, 110, 395–411. [Google Scholar] [CrossRef]
  2. Qu, W.W.; Lu, X.G.; Yang, D. Influence of pre-joining scheme on panel dynamic characteristic. J. Zhejiang Univ. (Eng. Sci.) 2017, 51, 336–343. (In Chinese) [Google Scholar]
  3. Zeba, G.; Dabić, M.; Čičak, M.; Daim, T.; Yalcin, H. Technology mining: Artificial intelligence in manufacturing. Technol. Forecast. Soc. Change 2021, 171, 120971. [Google Scholar] [CrossRef]
  4. Xie, Y. The “Intelligent Revolution” Transcends the “Industrial Revolution”. Inf. China 2019, 12, 43–46. (In Chinese) [Google Scholar]
  5. Yang, Q.H. Promote industrial upgrading with smart manufacturing as the starting point. Macroecon. Manag. 2021, 3, 78–90. (In Chinese) [Google Scholar]
  6. Liu, Y. Thoughts and Suggestions on the Development Strategy of China’s Manufacturing Supply Chain. Sci. Technol. China 2020, 9, 8–12. (In Chinese) [Google Scholar]
  7. Qi, Z.C.; Wang, M.; Cheng, W.L.; Wang, W. Optimization of Pre-Tightening Arrangement for One-Side Pressed Hole Making Between Aircraft Frames. Aeronaut. Manuf. Technol. 2019, 62, 58–63. (In Chinese) [Google Scholar]
  8. Yang, D.; Qu, W.W.; Ke, Y.L. Evaluation of residual clearance after pre-joining and pre-joining scheme optimization in aircraft panel assembly. Assem. Autom. 2016, 36, 376–387. [Google Scholar] [CrossRef]
  9. Gang, L.; Tang, W.; Ke, Y.L.; Chen, Q.L.; Bi, Y.B. Modeling of fast pre-joining processes optimization for skin-stringer panels. Assem. Autom. 2014, 34, 323–332. [Google Scholar]
  10. Gang, L.; Tang, W.; Ke, Y.L.; Chen, Q.L.; Chen, X.M. Pre-joining process planning model for a batch of skin-stringer panels based on statistical clearances. Int. J. Adv. Manuf. Technol. 2015, 78, 41–51. [Google Scholar]
  11. Qu, W.W.; Tang, W.; Ke, Y.L. Pre-joining processes optimization method for panel orienting to the clearances suppression of units and the clearances flow among units. Int. J. Adv. Manuf. Technol. 2018, 94, 1357–1371. [Google Scholar] [CrossRef]
  12. Zhou, S.Y.; Han, Z.R.; Guo, X.F.; Liang, W.X. Application of Simulated Annealing Algorithm in Arrangement of Pre-connected Hole. Mech. Sci. Technol. Aerosp. Eng. 2019, 38, 959–962. (In Chinese) [Google Scholar]
  13. Liu, X.; An, L.L.; Wang, Z.G.; Tan, C.B.; Wang, X.P.; Yu, S.X. Assembly Variation Analysis of Aircraft Panels under Part-to-part Locating Scheme. Int. J. Aerosp. Eng. 2019, 2019, 19-128-20191016. [Google Scholar] [CrossRef]
  14. Huang, X.D.; Wang, Q. Desing of end effector for pre-connected fasteners automatic installation in aircraft assembly. Manuf. Technol. Mach. Tool 2017, 9, 17–20. (In Chinese) [Google Scholar]
  15. Cheng, Y.L.; Mei, Q.Y. Research of Rapid Assembly Approach for Fasteners Based on Feature Recognition. Electro-Mech. Eng. 2016, 32, 42–45. (In Chinese) [Google Scholar]
  16. Camacho, J.; Veiga, F.; Penalva, M.L.; Diez-Olivan, A.; Deitert, L.; López de Lacalle, N. On-Line Monitoring of Blind Fastener Installation Process. Materials 2019, 12, 1157. [Google Scholar] [CrossRef] [PubMed] [Green Version]
  17. Wilson, W.C.; Rogge, M.D.; Fisher, B.H.; Malocha, D.C.; Atkinson, G.M. Fastener Failure Detection Using a Surface Acoustic Wave Strain Sensor. IEEE Sens. J. 2012, 12, 1993–2000. [Google Scholar] [CrossRef]
  18. Li, Y.; Cao, J.B.; Li, X.L. Optimization Design of Patch Shape for Rivet Repair of Aircraft Skin. Intell. Syst. Appl. Mater. 2012, 466, 1000–1005. [Google Scholar] [CrossRef]
  19. Jiang, C.J.; Sun, J.H.; Li, L. The Influence of Assembly design of Automobile Parts on Assembly Efficiency. Technol. Innov. Manag. 2017, 38, 383–388. (In Chinese) [Google Scholar]
Figure 1. (a) Two-dimensional diagram of new temporary fasteners. 1—Adjusting bolt; 2—Adjusting nut; 3—Leverage; 4—Expansion shaft; 5—Pin shaft; 6—Chute cover; 7—Chute table; 8—Expansion anchor; 9—Spring; 10—Adjustment board; 11—Workpiece; (b) Three-dimensional diagram of temporary fasteners.
Figure 1. (a) Two-dimensional diagram of new temporary fasteners. 1—Adjusting bolt; 2—Adjusting nut; 3—Leverage; 4—Expansion shaft; 5—Pin shaft; 6—Chute cover; 7—Chute table; 8—Expansion anchor; 9—Spring; 10—Adjustment board; 11—Workpiece; (b) Three-dimensional diagram of temporary fasteners.
Coatings 11 01101 g001
Figure 2. Preliminary installation process.
Figure 2. Preliminary installation process.
Coatings 11 01101 g002
Figure 3. (a) Geometric relationship of temporary fasteners. (b) Geometric relationship analysis.
Figure 3. (a) Geometric relationship of temporary fasteners. (b) Geometric relationship analysis.
Coatings 11 01101 g003
Figure 4. (a) Force analysis of the clamping process. (b) Balanced state.
Figure 4. (a) Force analysis of the clamping process. (b) Balanced state.
Coatings 11 01101 g004
Figure 5. Force decomposition at the bottom of the lever.
Figure 5. Force decomposition at the bottom of the lever.
Coatings 11 01101 g005
Figure 6. Force on lever.
Figure 6. Force on lever.
Coatings 11 01101 g006
Figure 7. Experimental test platform.
Figure 7. Experimental test platform.
Coatings 11 01101 g007
Figure 8. Experimental setup.
Figure 8. Experimental setup.
Coatings 11 01101 g008
Table 1. Functions and corresponding innovative structures.
Table 1. Functions and corresponding innovative structures.
FunctionsCorresponding Innovative Structure
Labor savingBased on the lever principle, a new lever mechanism with a movable fulcrum is designed to achieve the purpose of labor saving in the working process.
Reversible abilityA expansion anchor mechanism with strong elastic materials is designed for this function, which could be recovered to the original shape after the clamping process.
Consideration of component tolerancesGenerally in the pre-joining process of aircraft panels, there is a tolerance for the thickness of workpiece. To solve this problem, an adjustment mechanism is designed by adjusting the pre-compression of the spring to overcome the tolerance in the actual work.
Unilateral fasteningMost of the existing fastening methods are bilateral fastening with bolt connections, and the production efficiency is not high [19]. In order to solve this problem, an anchor-expanding mechanism is designed; that is, employ the expansion anchors and the moving expansion shafts to cooperate to achieve unilateral fastening.
Table 2. Main parameters of parts.
Table 2. Main parameters of parts.
ComponentsLeverChute TableSpringAdjustment BoardWorkpiece
Materialaluminum alloy 606145 steel55 SiCr alloy steel45 steel45 steel
Related sizetotal length 133.70 mmthickness 5.95 mmouter diameter 18 mmthickness 5.98 mmthickness 3.10 mm
short handle length 19.77 mmchute radius 80.00 mminner diameter 9 mmcenter aperture 6.93 mmcenter aperture 7.18 mm
long handle length 113.93 mmcenter aperture 4.94 mmfree length 20.20 mm
compression rate 40%
Table 3. Comparison of results.
Table 3. Comparison of results.
Theoretical Value (N)Actual Value (N)Error Rate
Pressure162.13182.268.9%
Tension10.814.087.6%
Table 4. Advantages of fast temporary fasteners.
Table 4. Advantages of fast temporary fasteners.
Rapid AssemblyLabor-SavingReversible Ability
Tightening and disassembly can be completed by simply moving the lever.The lever mechanism is matched with the expansion anchor mechanism to reduce the tightening force and to make a reliable clamping process.Adopt the elastic expansion anchor and spatial cross track to realize the reversible ability.
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Tang, W.; Xie, X.; Ye, Y.; Qu, W. Design of a Fast Temporary Fastener with the Labor-Saving and Reversible Ability. Coatings 2021, 11, 1101. https://doi.org/10.3390/coatings11091101

AMA Style

Tang W, Xie X, Ye Y, Qu W. Design of a Fast Temporary Fastener with the Labor-Saving and Reversible Ability. Coatings. 2021; 11(9):1101. https://doi.org/10.3390/coatings11091101

Chicago/Turabian Style

Tang, Wei, Xincheng Xie, Yukang Ye, and Weiwei Qu. 2021. "Design of a Fast Temporary Fastener with the Labor-Saving and Reversible Ability" Coatings 11, no. 9: 1101. https://doi.org/10.3390/coatings11091101

APA Style

Tang, W., Xie, X., Ye, Y., & Qu, W. (2021). Design of a Fast Temporary Fastener with the Labor-Saving and Reversible Ability. Coatings, 11(9), 1101. https://doi.org/10.3390/coatings11091101

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop