Next Article in Journal
Soft-Decision Low-Complexity Chase Decoders for the RS(255,239) Code
Next Article in Special Issue
A Quasi-Average Estimation Aided Hierarchical Control Scheme for Power Electronics-Based Islanded Microgrids
Previous Article in Journal
Partial Isolation Type Saddle-FinFET(Pi-FinFET) for Sub-30 nm DRAM Cell Transistors
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Operation Flexibility Evaluation and Its Application to Optimal Planning of Bundled Wind-Thermal-Storage Generation System

1
School of Electrical Engineering and Automation, Hefei University of Technology, Hefei 230009, China
2
State Grid Zhejiang Changxing Country Power Supply Co., Ltd., Changxing 313100, China
*
Author to whom correspondence should be addressed.
Electronics 2019, 8(1), 9; https://doi.org/10.3390/electronics8010009
Submission received: 13 November 2018 / Revised: 29 November 2018 / Accepted: 17 December 2018 / Published: 21 December 2018
(This article belongs to the Special Issue Beyond Smart Grid: Power Quality, Reliability and Security Challenges)

Abstract

:
The growing penetration of wind power in a power system brings great challenges to system operation flexibility. For generation planning in presence of high wind power penetration, it is essential to take the operation flexibility of the system into account. Firstly, this paper developed the system operation flexibility metrics through considering the flexibility contribution of thermal generating units (TGUs) by operational state transition. Secondly, a planning model for the bundled wind-thermal-storage generation system (BWTSGS) that considers the operation flexibility constraints is proposed. The planning model is used to determine the power and energy rating of an energy storage system (ESS) as well as the type and number of TGUs. A daily scheduling simulation model of a BWTSGS is proposed to calculate the operation cost for the planning model and consider the sequential operation characteristics of the BWTSGS. Further, in order to accelerate the computation, a wind power sequential clustering technique based on the discrete Fourier transform (DFT) method is developed for improving the computational efficiency. Case studies have been conducted on a 1000-MW wind farm to demonstrate the validity and effectiveness of the proposed model.

1. Introduction

The development of wind power has been accelerating in recent years to cope with the growing energy consumption as well as the environmental deterioration [1]. Two common ways are available to integrate wind power to the grid. One is distributed integration, in which wind power is accommodated by the local electric distributed network directly [2]. Another is centralized integration, in which most of the wind powers is delivered from wind farms directly to load centers [3]. For areas with rich wind resources, but geographically far from high-demand load centers, light load demand severely restricts the consumption level of wind power. As a result, a significant amount of wind energy may be wasted. For such areas, it would be economically efficient to transmit the wind power to load centers [4].
However, the small equivalent capacity and high volatility of wind power makes the direct transmission of large-scale wind power cost ineffective, and poses challenges to the receiving power system [5]. Since the wind-rich areas are usually close to areas with rich coal reserves, recent researches have proposed the idea of bundled wind-thermal generation systems (BWTGS) [6]. Scheduling thermal generating units (TGUs)to mitigate the variability of wind power can increase the capacity factor of the transmission facilities and alleviate the risk of the receiving system [6].
In addition, the high penetration of wind power in a power system brings great challenges to system adequacy, security, and operation flexibility. The operation flexibility describes the ability of a power system to deploy its resources in response to the changes in system load and variable generations (VGs) [7]. With increased wind power penetration, system flexibility has become a critical factor to maintain the load generation balance for system operators. It is also important to consider the flexibility in generation planning in presence of high wind power penetration [8].
Many studies have been conducted on the BWTGS and the evaluation of operation flexibility.
By investigating the uncoordinated development of wind power and the lagging development of transmission systems, Ni and Yang [6] concluded that the planning of BWTGS is an effective way to develop the wind energy resources. In [9], Xie et al. proposed an optimal BWTGS planning method that considered the operational constraints of matched TGUs and generation system. The planning of HVDC-based bundled wind-thermal generation and transmission system has also been investigated [5]. Chen et al. [10] investigated the transient characteristics of AC/DC transmitted BWTGS under the case of a DC block fault, and the results obtained provides valuable information for the future search of transient stability of the wind-thermal bundled transmission system. In [11], a model to optimize the generation maintenance schedule for BWTGS is proposed. The probabilistic production simulation technique was employed to calculate the system costs, and a sequential probabilistic method was utilized to capture the sequential and stochastic nature of wind power. Although researches regarding the BWTGS have been well studied, to the best of our knowledge, no previous work has been reported on the consideration of operation flexibility in BWTGS planning.
A number of researches on the system operation flexibility have also been reported. In [7], the insufficient ramping resource expectation (IRRE) metric has been developed to assess power system flexibility from a probabilistic viewpoint. A flexibility index that reflects the individual generating unit and the whole system was proposed for incorporation into the unit construction and commitment model [12]. The flexibility envelope that describes the flexibility potential dynamics of a power system and individual resources was introduced in [13]. The flexibility of aggregated demands for retail consumers was studied and an optimization model was built to determine the load scheduling for aggregated demands [14].
Most of the flexibility related researches for generation planning were conducted based on the spinning reserve requirement, and did not consider the state transition of generating units. Yet in practice, the high penetration of renewable energy resources (RESs)could lead to the frequent start-up and shut-down of generating units [14]. Assuming that only the synchronized generators are able to respond to the fluctuation of variable generations (VGs), the operation and planning cost of generating units would be thereby increased. Thus it is inappropriate to evaluate the system flexibility without considering the state transition of generating units.
The bundled delivery of wind and thermal power is an effective way for the utilization of wind energy resources. However, the matched TGUs in BWTGS may have difficulty coping with the volatile wind power. Under this circumstance, more TGUs are required, resulting in the increased operation and planning costs [15]. The energy storage system (ESS) can store and release electric energy quickly [16] and can mitigate the variability of renewable energy resources (RESs). The integration of ESS into the bundled generation system may alleviate the operation difficulty that is encountered by the matched TGUs and make the bundled delivery more efficient. Figure 1 depicts the configuration of a bundled wind-thermal-storage generation system (BWTSGS).
Many researches have been conducted on the operation and planning of ESS. In [15], a storage control policy to the limit ramp rates of wind power was studied so as to reduce the required amount of ancillary services. A planning approach was proposed to calculate the optimal location and size of an ESS considering the uncertainty of wind power [17]. A model that determined the optimal size of an ESS in a micro-grid with reliability constraints was developed [18]. A nondeterministic model for joint transmission and ESS expansion planning was examined in [19].
In this paper, firstly, the system operation flexibility metrics are developed. The flexibility contribution of TGUs by operational state transition is taken into account. Secondly, an optimal planning model of the BWTSGS considering operation flexibility constraints is proposed to determine the optimal power and energy rating of an ESS as well as the type and number of TGUs. A daily scheduling simulation model based on linear programming is also proposed to take into account the sequential operation characteristics of a BWTSGS. The operation flexibility constraints are devised to guarantee the security operation of a BWTSGS. In addition, a wind power sequential clustering technique based on the discrete Fourier transform (DFT) method is developed to improve the computation efficiency. Case studies using the historical wind data are presented to illustrate the effectiveness of the proposed model. The impacts of multiple factors, such as the flexibility constraints, ESS integration, target flexibility, and ESS cost, on the optimal planning scheme and operation cost of BWTSGS are also evaluated in this paper.

2. Power System Operation Flexibility

2.1. Definition of Power System Operation Flexibility Metrics

The operation flexibility of power system is defined as the ability to respond to the variability and uncertainty in power system, where the variability and uncertainty usually arise from the variable generations and the load demand.
For a BWTSGS, the transmission power (i.e., the load demand) is usually set as a constant to raise the utilization of the facilities. As shown in Figure 2, if the system operates without sufficient flexibility resources to respond to the variability and uncertainty of wind power, the system operator would be compelled to curtail the power output of wind energy or transmission power to keep the balance between the generation and the load demand.
A BWTSGS can be considered as a relatively isolated power system. The operation flexibility metrics for BWTSGS are proposed to measure the ability of a BWTSGS to cope with the variability and uncertainty of wind power. As the hourly variability of wind power contains abundant information of importance in the context of generation operation and planning [12], the flexibility metrics in this paper are on an hourly basis.
In practice, wind power at the next hour is uncertain and depends on the initial condition [20]. Thus, given the wind power at hour t, wind power at the next hour can be represented by a random variable. Its probability distribution function (PDF) could be obtained by the statistical analysis of historical wind data based conditional probability method [20]. It is supposed that the PDF of wind power at the next hour is f W κ + 1 ( P W ( t + 1 ) ) , as shown in Figure 2. Thereby, the system operation flexibility metrics are defined as follows.
Upward Operation Flexibility Insufficient Probability (OFIPup) is the probability that the system upward flexibility resources cannot cope with the wind power decline leading to the decrease of transmission power. OFIPup can be calculated by Equation (1)
O F I P up ( t ) = 0 P W ( t ) F sys up ( t ) f W t + 1 ( x ) d x ,
where PW(t) is the wind power at hour t; F sys up ( t ) is the system upward flexibility resources at hour t (MW); and f W t + 1 ( x ) is the PDF of wind power in the next hour.
Equation (1) can be also expressed as
O F I P up ( t ) = Pr { P W ( t + 1 ) P W ( t ) F sys up ( t ) } ,
where P W ( t + 1 ) is the random wind power at hour t + 1.
Downward Operation Flexibility Insufficient Probability (OFIPdo) is the probability that the system downward flexibility resources cannot cope with the wind power increase resulting in the curtailment of wind power. OFIPdo can be calculated by Equation (3)
O F I P do ( t ) = P W ( t ) + F sys do ( t ) + f W t + 1 ( x ) d x ,
where F sys do ( t ) is the system downward flexibility resources at hour t (MW).
Equation (3) can be also expressed as,
O F I P do ( t ) = Pr { P W ( t + 1 ) P W ( t ) + F sys do ( t ) } .

2.2. Evaluation of Power System Operation Flexibility

For a BWTSGS, the ESS and TGUs constitute the flexible resources responding to the variable high share of wind power. The flexibility contributed by the TGUs through transitioning operating states is considered in this paper.

2.2.1. TGU Flexibility Contribution

TGUs respond to the variable wind power either by performing in a spinning reserve manner or by changing their operating states via starting up or shutting down. The high share of wind power would make TGUs start up and shut down frequently to provide flexibility and response to the variability of wind power. The upward flexibility contributed by the ith TGU at hour t can be expressed as
F i up ( t ) = P ¯ i + 1 ( t ) P i ( t )
0 P ¯ i + 1 ( t ) P i , r max
P ¯ i + 1 ( t ) P i ( t ) + R U i · U i ( t ) + S U i × [ U ¯ i + 1 ( t ) U i ( t ) ]
U ¯ i + 1 ( t ) U i ( t ) + 1 T i , off min × [ T i , off min n = 0 T i , off min 1 U i ( t n ) ]
U ¯ i + 1 ( t ) U i ( t ) + ( 1 + 1 T i startup | 1 T i startup | ) / 2
P ¯ i + 1 ( t ) is a nonnegative variable that represents the maximum available power output of the ith TGU in the next hour. P ¯ i + 1 ( t ) is bounded above by the rated capacity of the TGU as shown in Equation (6) and by the ramp-up rate (when Ui(t) = 1) and start-up rate (when Ui(t) = 0) in (7). Equations (8) and (9) models the unit’s minimum down time and start up time constraints respectively. U ¯ i + 1 ( t ) is a binary variable indicating the available maximum state variable of the ith TGU at the next hour. If a TGU is online in the current hour, i.e., Ui(t) = 1, then U ¯ i + 1 ( t ) can be 1. Otherwise, if Ui(t) = 0, U ¯ i + 1 ( t ) still can be 1 only when the minimum down time constraint is satisfied and this TGU is able to start up in an hour. When Ui(t) = 0 and the minimum down time constraint is not satisfied, the binary constraint can still limit U ¯ i + 1 ( t ) to 0.
Similarly, the downward flexibility contributed by the ith TGU at hour t can be expressed as
F i do ( t ) P i ( t ) P i ,   r min · U _ i + 1 ( t )
F t do ( t ) R D i · U _ i + 1 ( t ) + S D i × [ U i ( t ) U _ i + 1 ( t ) ] + P i ,   r min × [ 1 U i ( t ) ]
n = 0 T i , on min 1 U i ( t n ) T i , on min × [ U i ( t ) U _ i + 1 ( t ) ]
where U _ i + 1 ( t ) is the available minimum state variable of the ith TGU at the next hour.

2.2.2. ESS Flexibility Contribution

Characteristics of electric energy storage and delivery make an ESS respond to changes in wind generation rapidly. Suppose that the ESS is required to maintain the charging (discharging) state for at least one hour. The flexibility contributed by the ESS can be mathematically described as,
F ESS up ( t ) P ESS + P ch ( t ) P d ( t )
F ESS up ( t ) η d ( E ESS ( t ) E ESS min ) / Δ t + P ch ( t ) P d ( t )
F ESS do ( t ) P ESS + P d ( t ) P ch ( t )
F ESS do ( t ) [ E ESS max E ESS ( t ) ] / ( η ch · Δ t ) + P d ( t ) P ch ( t )

2.2.3. Calculation of Operation Flexibility Metrics

The total system flexibility resources can be calculated according to the contribution of TGUs and ESS. The upward and downward flexibility metrics of system are calculated by Equations (17) and (18) respectively.
F sys up ( t ) = i G Ther F i up ( t ) + F E S S up ( t )
F sys do ( t ) = i G Ther F i do ( t ) + F E S S do ( t )
Therefore, the system flexibility metrics can be determined according their definitions.

3. BWTSGS Planning Formulation

In bundled generation systems, the matched TGUs may have difficulty following the volatile wind power. Thus, more TGUs would be required, and the operation cost and planning cost increase dramatically. ESS can store and release electric energy quickly when needed. The integration of an ESS into the bundled generation system may alleviate the operation difficulty encountered by TGUs [17] and enable efficient bundled delivery. The high share of wind power in a BWTSGS increases the variability and uncertainty in a power grid. Unlike traditional power system, volatile wind power makes the system operators deal with the high magnitudes and rates of variability in a short available lead time. Therefore, system operation flexibility is becoming a useful tool for the accurate planning of a BWTSGS. Moreover, considerations of system operation flexibility in the planning of BWTSGS can improve the operation security when facing high variability and uncertainty.
In this paper, an optimal planning model for BWTSGS considering the operation flexibility constraints is proposed to find the optimal configuration of the ESS and TGUs to alleviate the operation difficulty. The proposed planning model is shown in Figure 3. It contains two sub-models. One is the daily scheduling simulation model, and the other is the optimal planning model. The former considers the sequential operation characteristics of a BWTSGS and the system operation flexibility constraints in order to calculate the operation cost. The system operation flexibility constraints are devised in the daily scheduling simulation model to guarantee the optimal operation. The flexibility constraints are built from a probabilistic viewpoint, and fully consider the volatility and uncertainty of wind power. Moreover, the flexibility by operational state transition offers great benefits for TGUs to cope with frequent start-ups and shut-downs.
Figure 3 also shows that the proposed planning model generates candidate planning schemes and determines the planning scheme that minimizes the total cost of a BWTSGS. The planning scheme contains the power and energy rating of an ESS, as well as the number of TGUs for each candidate type. The candidate schemes are evaluated by the daily scheduling simulation model in order to obtain the operation cost. A wind power sequential clustering technique based on DFT is developed to improve the computation efficiency, since the computational cost for calculating the whole year’s operation costs is extremely high

4. Daily Scheduling Simulation Model Considering Operation Flexibility Constraints

Due to the complicated operation characteristics of wind power and ESS, it is necessary to evaluate the sequential operation of wind power and ESS in the optimal planning model for BWTSGS [17]. A daily scheduling simulation model considering the operation flexibility constraints is proposed to calculate the operation cost of a BWTSGS. To reduce the computation cost, the simulation model is formulated as a mixed integer linear programming (MILP) problem.

4.1. Objective Function

The scheduling simulation model intends to determine the on/off status, the output of TGUs, and the charge or discharge power of ESS to minimize the operation cost of BWTSGS. The operation cost includes the operation cost of TGUs and ESS, the environmental pollutant cost as well as the financial penalty for wind power curtailment. The objective function can be expressed as
min   F = t = 1 T { i G Ther [ F i ( P i ( t ) ) + E i ( P i ( t ) ) + C i SU ( t ) + C i SD ( t ) ] + C O ,   ESS · P d ( t ) + C CW · P C W ( t ) · Δ t } .
where F denotes the total operation cost in a day. Fi(·) and Ei(·) are the production cost and the environmental pollutant cost function of the ith TGU. Both costs depend on the power output Pi(t). C i SU ( t ) is the startup cost and C i SD ( t ) the shutdown cost of the ith TGU at hour t. C O ,   ESS is the operation cost of the ESS ($/MWh) and P d ( t ) is the discharging power of the ESS at hour t. ESS operation cost is related to the discharging energy [17]. The product C CW · P C W ( t ) · Δ t represents the financial penalty for wind power curtailment.
The operation cost of TGUs includes the production, startup, and shutdown costs, which are usually expressed as nonlinear (quadratic or exponential) functions. According to [21], all these cost functions can be approximated by a series of piecewise linear functions. Enough segments can express the original functions accurately.
The emission of NOx, CO2, CO and SO2 should be restricted in electric power production. Their environmental pollutant costs are modeled by linear function of TGU power output [22],
E i ( P i ( t ) ) = k = 1 N E u k · ε k , i · P i ( t ) · Δ t
where the emission coefficient of the kth gas is related to the type of TGU [22].

4.2. Operation Flexibility Constraints

According to the definitions of operation flexibility metrics, the operation flexibility constraints are formulated as Equations (21) and (22) according to the target system flexibility σ.
O F I P up ( t ) = Pr { P W ( t + 1 ) P W ( t ) F sys up ( t ) } < σ
O F I P do ( t ) = Pr { P W ( t + 1 ) P W ( t ) + F sys do ( t ) } < σ
Constraints (21) and (22) can be transferred to a deterministic form,
P W ( t ) F sys up ( t ) < F W ( t + 1 ) ( σ )
P W ( t ) + F sys do ( t ) > F W ( t + 1 ) ( 1 σ )
where F W ( t + 1 ) ( · ) is the inverse function of wind power PDF at hour t + 1.

4.3. Operation Constraints of BWTSGS

Constraints related to the operational characteristics of a BWTSGS are expressed as
i G Ther P i ( t ) P ch ( t ) + P d ( t ) + P W ( t ) = P Tran + P WC ( t )
0 P WC ( t ) P W ( t )
{ i G Ther S i up ( t ) + F ESS up ( t ) B S R ( t ) + β % [ P W ( t ) P W C ( t ) ] i G Ther S i do ( t ) + F ESS up ( t ) β % [ P W ( t ) P W C ( t ) ] B S R ( t ) α % [ P Tran P W ( t ) + P W C ( t ) ] S i up ( t ) U i ( t ) · P i ,   r max P i ( t ) S i up ( t ) U i ( t ) · R U i S i do ( t ) P i ( t ) U i ( t ) · P i ,   r min S i do ( t ) U i ( t ) · R D i
Constraint (25) represents the power balance constraint and (26) the wind power curtailment limits.
Although the spinning reserve has been considered in the operation flexibility constraints, the flexibility constraints focus on the system security in coping with the changes in wind power between hours. Thus, the spinning reserve constraint is modeled as Equation (27) to ensure the system security against uncertainties such as component outages and intra-hour fluctuations of wind power [23].

4.4. Operation Constraints of ESS

Constraint (28) describes the operational characteristics of an ESS. The binary charging U ch ( t ) and discharging U d ( t ) variables are inserted to represent the ESS charging and discharging state. These variables cannot be 1 at the same time.
{ 0 U ch ( t ) + U d ( t ) 1 0 P ch ( t ) U ch ( t ) · P ch max 0 P d ( t ) U d ( t ) · P d max E ESS ( t ) = E ESS ( t 1 ) P d ( t ) · Δ t / η d + P ch ( t ) · η ch · Δ t E ESS min E ESS ( t ) E ESS max
In addition, constraints related to the operational characteristic of TGUs are also considered yet are not given here. These constraints have been discussed in [21].

5. Optimal Planning for BWTSGS

For areas with rich wind resource, but far from load centers, the light load demand severely restricts the consumption level of wind power. A great amount of wind power has been wasted thereby [4]. This paper develops an optimal planning model for BWTSGS in order to deliver the large-scale wind power to load centers and boost the consumption level of wind power. The model minimizes the total cost and determines the optimal power and energy rating of an ESS and the number of TGUs for each candidate type under the assumption that the wind power farm has been built.
The proposed scheduling simulation model can calculate the operation cost of a BWTSGS, but takes unacceptable computational cost for a year’s simulation. The common remedy of existing methods employs typical days to approximate the wind power sequential nature, but they overly concentrate on the wind power fluctuation and overestimate the annual production cost. In this paper, a DFT based sequential wind power clustering method is developed to calculate the production cost of a BWTSGS with a high accuracy and reasonable computation cost.

5.1. Objective Function

The objective function of the proposed optimal planning model for BWTSGS consists of the investment, operation, and maintenance costs of ESS and TGUs over the planning period. All of the costs are transformed to the present value considering the discount rate. Since it is assumed that the wind farm has been built, costs related to wind turbine generators (WTGs) are not considered. The objective function is expressed as
C I & O & M = C I ( G Ther , E ESS , P ESS ) + C O ( G Ther , E ESS , P ESS ) + C M ( G Ther , E ESS , P ESS ) .
In addition to the initial investment cost, the total investment cost should contain the replacement cost when some facilities reach their lifetimes in that lifetimes differ among various facilities. An ESS has a shorter lifetime than a TGU. Suppose that only the ESS would reach its lifetime during the planning period which is an integer multiple of ESS lifetimes. Then, the investment cost can be expressed as
C I = i G Ther C I i + 1 ( 1 + r ) Y 1 ( 1 + r ) L ESS × ( C ESS ,   E E ESS + C ESS ,   P P ESS )
where the replacement cost of an ESS is equal to its investment cost.
The maintenance cost of TGUs could be a certain percentage of their investment cost [5]. The maintenance cost of an ESS depends on its power rating [16]. The maintenance of a BWTSGS can be expressed as
C M = 1 ( 1 + r ) Y 1 ( 1 + r ) 1 × ( τ × i G Ther C I i + C M ,   ESS · P ESS ) .
Since the production costs of a BWTSGS for different years are very close, the annual operation costs over the planning period are assumed to be identical. Then the total operation cost can be expressed as:
C O =   1 ( 1 + r ) Y 1 ( 1 + r ) 1 F A ( G Ther , E ESS , P ESS ) .
FA represents the annual operation cost of a planning scheme.

5.2. Constraints of Optimal Planning Model

The constraints of the proposed planning model include the TGUs’ capacity constraint and wind power penetration constraint.

5.2.1. TGUs Capacity Constraint

The total capacity of the TGUs in a BWTSGS should satisfy the transmission power even without wind power.
i G Ther P i , r max P Tran

5.2.2. Wind Power Penetration Constraint

The aim of building a BWTSGS is to make full use of the wind power and reduce the emission, thus the share of wind power should be ensured.
P W , r i G Ther P i , r max + P W , r   ρ ,
where ρ is the minimum wind power penetration ratio.

5.3. Accelerating Technique

This section describes a sequential wind power clustering technique to speed up the computation process. Discrete Fourier transform (DFT) can well represent the sequential fluctuation of wind power by transforming time sequence to the frequency domain [24]. In order to reduce the computational cost and estimate the annual operation cost accurately, a DFT based sequential wind power clustering technique is developed. The main steps are given below.
  • Partition the historic wind power data into diurnal wind power sequences (DWPSs). Each DWPS contains 24 sequential wind power points.
  • Convert each DWPS into frequency domain data using DFT.
  • Classify DWPSs into different clusters by the k-means cluster [25] method based on their spectra.
  • Use the DWPS that is randomly selected from each cluster to represent the cluster. Calculate the annual operation cost by
    F A = 365 × j = 1 N C [ N S j N S × F ( G Ther , P ESS , E ESS , P j Rand ) ]
    where NS is the total number of recorded DWPSs, NSj is the DWPS number of the jth cluster, and NC is the cluster number. F(GTher, PESS, EESS, P j Rand ) is the daily operation cost calculated by the scheduling simulation model with the planning schemes of GTher, PESS, EESS, and the DWPS P j Rand .
The number of clusters impacts the accuracy and computational cost of the proposed model. More clusters imply that DWPSs in the same cluster are closer to each other. Thus, the calculated annual operation cost is more accurate, but at the expense of longer time to complete the calculation. A proper number of clusters could be selected by the elbow technique [26] using historic wind speed data. 30-year wind speed data from 1984 to 2013 collected at Valkenburg, Netherlands are adopted in the study [27].
Figure 4 shows the box plot of the percentage differences between the annual operation cost obtained with clustering and the cost obtained using the 30-year wind speed data directly. Clustering is carried out by partitioning 30-year data into 2 to 30 clusters and randomly selecting one day’s DWPS in the cluster as the DWPS of that cluster. Each + denotes one of the calculated annual operation cost differences of a typical planning scheme for BWTSGS. It is observed from Figure 4 that the average difference and its deviation decrease as the number of clusters increases. When the number of clusters is 16 or higher, the average difference and deviation only decrease in a very insignificant manner. Therefore, an NC value equal to 16 is adopted in the case study.

6. Case Studies

Several case studies have been conducted to illustrate the feasibility and effectiveness of the proposed optimal planning model for BWTSGS. All of the case studies intend to build matched facilities to make full use of wind power based on a 1000 MW wind farm. The rated capacity of WTG is 2 MW. The cut-in, the rated, and the cut-out speeds are 3.33 m/s, 8.33 m/s, and 15.28 m/s, respectively [28]. The transmission power of the bundled generation system is fixed at 2000 MW [9]. The planning period and the lifetime of the ESS are respectively 20 years and 10 years.
Four types of TGUs are chosen as the candidate units, and the parameters are shown in Table 1 [29,30]. Table 2 lists the environmental pollution cost for each greenhouse gas. The parameters of ESS based on the compressed air energy storage (CAES) case are shown in Table 3 [17,31]. Assume that in the scheduling simulation model the coefficients of basic and additional spinning reserve requirement are 0.1 and 0.2 [9,23]. The rest parameters are set as Table 4. The statistical hourly wind speed data of the Valkenburg station from 1984 to 2013 [27] are adopted as wind speed data of the given wind farm.
The bacterial foraging optimization algorithm is adopted to solve the proposed model [32]. The decision variables constitute a bacteria as θ = [PESS, EESS, N1, … N4], referring to the power and energy rating of an ESS, and the number of each TGU type. MATLAB and GUROBI solver are adopted to solve the daily scheduling simulation model.

6.1. Case 1: Effect of Flexibility Constraints

The effect of flexibility constraints is investigated. This case study is conducted with three scenarios of a BWTGS without an ESS. The goal is to transport wind power to remote load centers by bundling delivery wind and thermal power.
  • Scenario 1.1: Ignore the flexibility constraints.
  • Scenario 1.2: Consider the flexibility constraints but ignore the flexibility contributed by the TGUs through transitioning operating states.
  • Scenario 1.3: Consider the flexibility constraints and the flexibility contributed by the TGUs through transiting operating states.
Table 5 presents the results of the optimal scheme, cost, and flexibility for each scenario. Among the results of the three scenarios, the downward flexibility is much less than the upward flexibility, which is in good agreement with the results in [6]. This phenomenon indicates that deficiency of the upward flexibility resources is the leading cause limiting the integration of wind power.
Close examination of Table 5 reveals that, due to the flexibility constraints, more TGUs are required. Thus, the total costs in scenarios 1.2 and 1.3 increase compared with that of scenario 1.1, while the flexibility metrics in scenarios 1.2 and 1.3 decrease. This phenomenon implies that the risk of coping with the variability of wind power is reduced. The results of scenario 1.2 and 1.3 indicate that considering the state transition of TGUs reduces the total cost and flexibility metrics. It is also observed from Table 5 that more U4s are installed in scenario 1.3. This shows that the proposed model is capable of considering the TGUs with different minimum on/off times. Hence, the proposed model enables an efficient configuration of different types of TGUs in the bundled generation system.

6.2. Case 2: Effect of ESS Integration

The benefit of integrating an ESS into bundled generation system is investigated. This case study is conducted with two scenarios. In this case study, both the flexibility constraints and the flexibility contributed through the TGU state transition are considered.
  • Scenario 2.1: Build a bundled wind-thermal generation system (BWTGS) without an ESS.
  • Scenario 2.2: Build a bundled wind-thermal-storage generation system (BWTSGS).
Table 6 shows the optimal schemes and Table 7 lists the cost of each optimal scheme for both scenarios. It is observed from Table 6 that the number of U4 in scenario 2.2 is much smaller than that in scenario 2.1. But the reduction of matched TGU capacity in scenario 2.2 from scenario 2.1 is not obvious. This illustrates that an ESS can lower the demand of rapid start/shut down generators, which have higher operation costs. As a result, the operation cost of the TGU drops from $2.9895 × 108 in scenario 2.1 to $2.8370 × 108 in scenario 2.2. BWTSGS can lift the operation difficulty of matched TGUs in BWTGS and lower the operation cost.
An ESS also greatly reduces the wind power curtailment as can be seen from the financial penalty for wind power curtailment. Table 7 shows that the financial penalty for wind power curtailment is reduced by more than 90%. The total cost decreases from $6.1712 × 109 to $6.0149 × 109 which is a 2.53% reduction. This indicates that the integration of an ESS with the bundled delivery of wind and thermal power is economically favorable.

6.3. Case 3: Impact of Target Flexibility

This case investigates the impact of system target flexibility on the optimal planning scheme and planning costs of BWTSGS. The operation flexibility constraints of Equations (21)–(24) state that the system operation flexibility must satisfy the target flexibility at all times. Stringent flexibility (small σ ) could improve system operation security, but planning and operation costs would increase. The selection of proper target flexibility would benefit BWTSGS planning.
The optimal planning scheme, total cost, and financial penalty for different target flexibility values are shown in Table 8. It is observed from Table 8 that the smaller target flexibility demands larger ESS or more TGUs to satisfy the increased flexibility requirement. This leads to higher total cost. Nonetheless, the wind power curtailment is not lowered. The financial penalty for wind power curtailment with the 0.005 target flexibility is much higher than that with target flexibility of 0.01 and 0.015. This may be the case that the increased ESS or TGU capacity due to stringent flexibility is too expensive. Thus, the system curtails the wind power so as to warrant the system flexibility requirement and enhance the system operation security.

6.4. Case 4: Effect of ESS Cost

The ESS cost may influence the benefit of ESS integration. Sensitivity analysis is carried out on ESS cost in this case study. The planning of BWTSGS is conducted under various ESS costs. They are 0.8, 1.0, 1.2, 1.4, and 2 times of the ESS cost considered in case 2.
Table 9 shows the optimal schemes and costs for the TGUs and ESS. The total cost of a BWTSGS increases with the increase of ESS cost. It can be seen from Table 9 that when the ESS cost is 0.8 times of that in case 2, an ESS with larger optimal energy and power rating is required, but U4 is not needed. An increase of EES capacity cuts down wind power curtailment so that the financial penalty gradually declines to zero. Nonetheless, the planning of ESS is not sensitive to the increase of ESS cost. Up to a 20% higher ESS cost does not change the optimal scheme of a BWTSGS. When the ESS cost increases by 40%, the energy rating of an ESS in the optimal scheme decrease from 120 MWh to 100 MWh, while the planning result of TGUs does not change. ESS cost higher than this level does not affect the optimal planning of ESS. It can be concluded that the cost of an ESS has only a slight impact on the benefit of building a BWTSGS.

7. Conclusions

For generation planning including large-scale wind power integration, it is essential to take the system operation flexibility into account. Firstly, this paper develops the system operation flexibility metrics for generation planning through considering the flexibility contribution of TGUs by operational state transition. Secondly, an optimal planning model for the bundled wind-thermal-storage generation system (BWTSGS) considering the operation flexibility constraints is proposed. The proposed BWTSGS planning model determines the power and energy rating of an ESS as well as the type and number of TGUs considering the sequential operation characteristics of wind power and ESS. The integration of an ESS enables the system to alleviate the challenges faced by TGUs and to reduce the operation and planning costs. A daily scheduling simulation model of BWTSGS has been developed to take into account the sequential operation characteristics of BWTSGS. The model considers the system operation flexibility constraints and the operational state transition of TGUs. A wind power sequential clustering technique based on DFT has also been presented for efficient computation of the proposed planning model.
The BWTSGS method provides an effective means of bundling the delivery of wind and thermal power for areas with abundant wind resources yet geographically far away from heavy load centers. Results from case studies have demonstrated the following:
1)
The integration of an ESS lessens the requirement of quick start/shut down generators so that the operation and planning costs of bundled delivery of wind and thermal power are reduced. The cost of the ESS in the proposed model is not an issue.
2)
More TGUs are required to meet the system operation flexibility constraints. The target flexibility should be set appropriately.

Author Contributions

Conceptualization, methodology, investigation, Y.M.; Methodology, writing—original draft preparation, H.Y; Writing—original draft preparation, D.Z.; Writing—review and editing, Q.N.

Funding

This research was funded by the National Natural Science Foundation of China (No. 51607051) and Anhui Provincial Natural Science Foundation (1708085ME107).

Conflicts of Interest

The authors declare no conflict of interest.

Nomenclature

CONSTANTS
A,B,CCoefficients of the quadratic production cost function of thermal generating unit (TGU)BSRBasic spinning reserve requirement without considering wind power penetration
CCWFinancial penalty for wind curtailment, ($/MWh)CESS,EEnergy rating cost of energy storage system (ESS) facility, ($/MWh)
CESS,PPower rating cost of ESS facility, ($/MWh)CM, ESSFixed operation and maintenance of ESS ($/MWh/year)
CO, ESSOperation cost of ESS, ($/MWh)CIiInvestment cost of the ith TGU
E ESS max / E ESS min Maximum/minimum energy state of ESSLESSLifetime of ESS facility
NENumber of gas types P ch max / P d max Maximum charging/discharging power of ESS
P i , r max / P i , r min Maximum/minimum rated power output of the ith TGUPW,rWind power capacity
PTranTransmission power of the bundled wind–thermal–storage generation system (BWTSGS)THours considering in scheduling simulation model
T i , off min / T i , on min Minimum off/on time of the ith TGU T i startup Start-up time of the ith TGU
YNumber of years in planning periodrDiscount rate
ukEnvironmental pollution cost for the kth gas, ($/kg)ΔtTime duration, Δt = 1 h
α%Coefficient of basic spinning reserve requirementβ%Coefficient of additional up/down spinning reserve requirement
εk, iEnvironmental pollution of the ith TGU for the kth gas, (kg/MWh)ηch/ηdCharging/discharging efficiency of ESS
ρMinimum wind power penetrationσTarget system flexibility
τRatio of maintenance cost to TGU capital cost
Variables
CI/CO/CMInvest/operation/maintenance cost of the BWTSGS over the planning periodCI&O&MTotal cost of the BWTSGS over the planning period
C i SD ( t ) / C i SU ( i ) Shut-down/start-up cost of the ith TGU at hour tEESSEnergy rating of ESS
EESS(t)Energy state of ESS at hour tFTotal operation cost in a day
FAAnnual operation cost of the BWTSGS F ESS do ( t ) / F ESS up ( t ) Downward/upward flexibility contributed by ESS at hour t
F i do ( t ) / F i up ( t ) Downward/upward flexibility contributed by the ith TGU at hour t F sys do ( t ) / F sys up ( t ) Downward/upward system flexibility at hour t
NCNumber of clustersNSTotal number of recorded diurnal wind power sequences (DWPSs)
NSjNumber of DWPS in the jth clusterOFIPupUpward operation flexibility insufficient probability
OFIPdoDownward operation flexibility insufficient probabilityPCW(t)Power of wind curtailment at hour t
Pch(t)/Pd(t)Charging/discharging power of ESS at hour tPESSPower rating of ESS
Pi(t)Power output of the ith TGU at hour t P ¯ i + 1 ( t ) Maximum available power output of the ith TGU at hour t + 1
PW(t)Wind power at hour tRDi/RUiRamp-down/ramp-up limit for the ith thermal generating unit (TGU)
S i do ( t ) / S i up ( t ) Down/up spinning reserve contributed by the ith TGUSUi/SDiStart-up/shut-down ramp limit of the ith TGU
Uch(t)Charging state of ESS at hour t (1: charging, 0: otherwise)Ud(t)Discharging state of ESS at hour t (1: discharging, 0: otherwise)
Ui(t)State of the ith TGU at hour t (1: on, 0: off) U ¯ i + 1 ( t ) /   U ¯ i + 1 ( t ) Available maximum/minimum state variable of the ith TGU at hour t + 1
P j Rand DWPS selected from the jth cluster randomly P W ( t + 1 ) Random wind power at hour t + 1
Sets
GTherSet of the TGUs
Functions
f W t + 1 ( · ) Probability density function (PDF) of wind power at next hour F i ( · ) / E i ( · ) Production/environmental pollution cost function of the ith TGU
F W ( t + 1 ) ( · ) Inverse function of wind power probability distribution at hour t+1
Abbreviations
BWTGSBundled wind–thermal generation systemBWTSGSBundled wind–thermal–storage generation system
DFTDiscrete Fourier transformDWPSDiurnal wind power sequences
ESSEnergy storage systemTGUThermal generating units
PDFProbability distribution functionWTGWind turbine generator

References

  1. Jung, C.; Schindler, D.; Laible, J.; Buchholz, A. Introducing a system of wind speed distributions for modeling properties of wind speed regimes around the world. Energy Convers. Manag. 2017, 144, 181–192. [Google Scholar] [CrossRef]
  2. Mokryani, G.; Hu, Y.F.; Pillai, P.; Rajamani, H.-S. Active distribution networks planning with high penetration of wind power. Renew. Energy 2017, 104, 40–49. [Google Scholar] [CrossRef]
  3. Dong, J.; Xie, K.; Hu, B. Optimal planning of bundled wind-thermal generation systems: A case study of China. J. Renew. Sustain. Energy 2016, 8, 013308. [Google Scholar] [CrossRef]
  4. Ni, M.; Yang, Z. By leaps and bounds lessons learned from renewable energy growth in China. IEEE Power Energy Mag. 2012, 10, 37–43. [Google Scholar] [CrossRef]
  5. Xie, K.; Dong, J.; Tai, H.-M.; Hu, B.; He, H. Optimal planning of HVDC-based bundled wind–thermal generation and transmission system. Energy Convers. Manag. 2016, 115, 71–79. [Google Scholar] [CrossRef]
  6. Zhang, L.; Ye, T.; Xin, Y.; Han, F.; Fan, G. Problems and measures of power grid accommodating large scale wind power. Proc. CSEE 2010, 30, 1–9. [Google Scholar]
  7. Lannoye, E.; Flynnm, D.; O’Malley, M. Evaluation of power system flexibility. IEEE Trans. Power Syst. 2012, 27, 922–931. [Google Scholar] [CrossRef]
  8. Lannoye, E.; Flynn, D.; O’Malley, M. The role of power system flexibility in generation planning. In Proceedings of the Power and Energy Society General Meeting (PES), Detroit, MI, USA, 24–29 July 2011. [Google Scholar]
  9. Xie, K.; Dong, J.; Singh, C.; Hu, B. Optimal capacity and type planning of generating units in a bundled wind–thermal generation system. Appl. Energy 2016, 164, 200–210. [Google Scholar] [CrossRef]
  10. Chen, D.; Ma, S.; Song, Y.; Wang, N.; Fang, P.; Ren, J. Research on transient stability under HVDC block fault in wind-thermal-bundled power base transmitted by AC/DC system. In Proceedings of the 2014 International Conference on Power System Technology (POWERCON 2014), Chengdu China, 20–22 October 2014; pp. 2884–2890. [Google Scholar]
  11. Ma, Y.; Xie, K.; Dong, J.; Tai, H.M.; Bo, H. Optimal Generation Maintenance Schedule for Bundled Wind–Thermal Generation System. J. Energy Resour. Technol. 2018, 140, 1–7. [Google Scholar] [CrossRef]
  12. Ma, J.; Silva, V.; Belhomme, R.; Kirschen, D.S.; Ochoa, L. Evaluating and planning flexibility in sustainable power systems. In Proceedings of the Power and Energy Society General Meeting (PES), Vancouver, BC, Canada, 21–25 July 2013. [Google Scholar]
  13. Nosair, H.; Bouffard, F. Flexibility envelopes for power system operational planning. IEEE Trans. Sustain. Energy 2015, 6, 800–809. [Google Scholar] [CrossRef]
  14. Ayón, X.; Gruber, J.K.; Hayes, B.P.; Usaola, J.; Prodanović, M. An optimal day-ahead load scheduling approach based on the flexibility of aggregate demands. Appl. Energy 2017, 198, 1–11. [Google Scholar] [CrossRef]
  15. Lee, D.; Kim, J.; Baldick, R. Stochastic optimal control of the storage system to limit ramp rates of wind power output. IEEE Trans. Smart Grid 2013, 4, 2256–2265. [Google Scholar] [CrossRef]
  16. Hemmati, R.; Saboori, H.; Saboori, S. Assessing wind uncertainty impact on short term operation scheduling of coordinated energy storage systems and thermal units. Renew. Energy 2016, 95, 74–84. [Google Scholar] [CrossRef]
  17. Xiong, P.; Singh, C. Optimal planning of storage in power systems integrated with wind power ge505 neration. IEEE Trans. Sustain. Energy 2016, 7, 232–240. [Google Scholar] [CrossRef]
  18. Bahramirad, S.; Reder, W.; Khodaei, A. Reliability constrained optimal sizing of energy storage system in a microgrid. IEEE Trans. Smart Grid 2012, 3, 2056–2062. [Google Scholar] [CrossRef]
  19. Dehghan, S.; Amjady, N. Robust transmission and energy storage expansion planning in wind farm-integrated power systems considering transmission switching. IEEE Trans. Sustain. Energy 2016, 7, 765–774. [Google Scholar] [CrossRef]
  20. Thapa, S.; Karki, R. Reliability benefit of energy storage in wind integrated power system operation. IET Gener. Transm. Distrib. 2016, 10, 807–814. [Google Scholar] [CrossRef]
  21. Carrión, M.; Arroyoé, J.M. A computationally efficient mixed-integer linear formulation for the thermal unit commitment problem. IEEE Trans Power Syst 2006, 21, 1371–1378. [Google Scholar] [CrossRef]
  22. Hemmati, R.; Saboori, H.; Jirdehi, M.A. Multistage generation expansion planning incorporating large scale energy storage systems and environmental pollution. Renew. Energy 2016, 97, 636–645. [Google Scholar] [CrossRef]
  23. Chen, C.-L. Optimal wind–thermal generating unit commitment. IEEE Trans. Energy Convers. 2008, 23, 273–280. [Google Scholar] [CrossRef]
  24. Agrawal, R.; Faloutsos, C.; Swami, A. Efficient similarity search in sequence databases. In Proceedings of the 4th International Conference on Foundations of Data Organization and Algorithms, Chicago, IL, USA, 13–15 October 1993; pp. 69–84. [Google Scholar]
  25. Yang, H.; Wang, L.; Zhang, Y.; Tai, H.M.; Ma, Y.; Zhou, M. Reliability Evaluation of Power System Considering Time of Use Electricity Pricing. IEEE Trans. Power Syst. 2018. Early Access. [Google Scholar] [CrossRef]
  26. Ketchen, D.J.; Shook, C.L. The application of cluster analysis in strategic management research: An analysis and critique. Strateg. Manag. J. 1996, 17, 441–458. [Google Scholar] [CrossRef]
  27. Royal Netherlands Meteorological Institute. Available online: http://www.knmi.nl/klimatologie/onderzoeksgegevens/potentiele_wind/index.cgi?language=eng (accessed on 23 March 2018).
  28. Xie, K.; Billinton, R. Determination of the optimum capacity and type of wind turbine generators in a power system considering reliability and cost. IEEE Trans. Energy Convers. 2011, 26, 227–234. [Google Scholar] [CrossRef]
  29. Yamayee, Z.; Sidenblad, K.; Yoshimura, M. A computationally efficient optimal maintenance scheduling method. IEEE Trans. Power Appar. Syst. 1983, 102, 330–338. [Google Scholar] [CrossRef]
  30. Tekiner, H.; Coit, D.W.; Felder, F.A. Multi-period multi-objective electricity generation expansion planning problem with Monte-Carlo simulation. Electric Power Syst. Res. 2010, 80, 1394–1405. [Google Scholar] [CrossRef] [Green Version]
  31. National Assessment of Energy Storage for Grid Balancing and Arbitrage Phase II, Volume 2: Cost and Performance Characterization. Available online: http://energyenvironment.pnnl.gov/pdf/National_Assessment_Storage_PHASE_II_vol_2_final.pdf (accessed on 26 November 2018).
  32. Das, S.; Biswas, A.; Dasgupta, S.; Abraham, A. Bacterial foraging optimization algorithm: Theoretical foundations, analysis, and applications. Found. Comput. Intell. 2009, 3, 23–55. [Google Scholar] [CrossRef]
Figure 1. Configuration of a bundled wind-thermal-storage generation system (BWTSGS).
Figure 1. Configuration of a bundled wind-thermal-storage generation system (BWTSGS).
Electronics 08 00009 g001
Figure 2. Schematic of operation flexibility for the BWTSGS.
Figure 2. Schematic of operation flexibility for the BWTSGS.
Electronics 08 00009 g002
Figure 3. The proposed optimal planning model for a BWTSGS.
Figure 3. The proposed optimal planning model for a BWTSGS.
Electronics 08 00009 g003
Figure 4. Statistical analysis on the differences of calculated annual operation costs.
Figure 4. Statistical analysis on the differences of calculated annual operation costs.
Electronics 08 00009 g004
Table 1. Parameters of thermal generating units (TGUs).
Table 1. Parameters of thermal generating units (TGUs).
U1U2U3U4
P r max (MW)64055514058
P r min (MW)3202807030
A ($/h)13001000700660
B ($/MW h)15.616.1916.725.95
C ($/MW2 h)0.000420.00480.0020.00413
T i on (h)8651
T i off (h)8651
Hot start cost ($)6000450055030
Cold start cost ($)12,0009000110060
Cold start hours (h)5440
Emission coefficients (kg/MWh)NOx3.5073.5943.9764.101
CO2805.483810.559832.954840.240
CO0.1010.1080.1380.147
SO20.3030.3400.5010.553
Table 2. Cost coefficient of pollutant emission.
Table 2. Cost coefficient of pollutant emission.
Greenhouse GasNOxCO2COSO2
Pollutant cost coefficients ($/kg)1.4280.0050.1661.000
Table 3. Parameters of energy storage system.
Table 3. Parameters of energy storage system.
Capital costCapacity cost3000 $/MWh
Power cost560,000 $/MW
O&M costMaintenance cost1200 $/MWh/year
Operation cost1.5 $/MWh
EfficiencyCharge0.9
Discharge0.875
Table 4. Other parameters used in case studies.
Table 4. Other parameters used in case studies.
ParametersτCCWrρσ
Value2.2%160 $/MWh0.080.30.001
Table 5. Optimal schemes and costs on the effect of reliability constraints.
Table 5. Optimal schemes and costs on the effect of reliability constraints.
ScenarioOptimal SchemeTotal Cost ($ × 109)Costs for TGUsFinancial Penalty ($ × 106) O F I P up O F I P do
U1U2U3U4Investment Cost ($ × 109)Maintenance Cost ($ × 108)Production Cost ($ × 109)Emission Cost ($ × 109)
Scenario 1.130206.01021.38293.15542.80661.377012.8231.33 × 10−32.11 × 10−5
Scenario 1.221236.19691.43883.28312.91941.391811.8495.18 × 10−41.72 × 10−5
Scenario 1.321156.17121.42373.24872.98951.38894.41014.39 × 10−41.52 × 10−6
Table 6. Optimal schemes on the effect of an ESS.
Table 6. Optimal schemes on the effect of an ESS.
ScenarioPESS(MW)EESS(MWh)U1U2U3U4TGU Capacity (MW)
Scenario 2.1--21152265
Scenario 2.24012030212258
Table 7. Costs regarding the effect of an ESS.
Table 7. Costs regarding the effect of an ESS.
ScenarioTotal Cost ($ × 109)Costs for TGUsCosts for ESSFinancial Penalty ($ × 105)
Investment Cost ($ × 109)Maintenance Cost ($ × 108)Production Cost ($ × 109)Emission Cost ($ × 109)Investment Cost ($ × 107)Maintenance Cost ($ × S106)Operation Cost ($ × 105)
Scenario 2.16.17121.42373.24872.98951.3889---44.101
Scenario 2.26.01491.41933.23862.83701.38523.33021.49364.79144.1851
Table 8. Results on the impact of target flexibility.
Table 8. Results on the impact of target flexibility.
Target FlexibilityOptimal SchemeTotal Cost ($ × 109)Financial Penalty ($ × 105)
PESS (MW)EESS (MWh)U1U2U3U4
0.00124060030226.24120
0.0058022030216.073830.676
0.014012030216.01494.1851
0.0157016030206.003613.875
Table 9. Results on the effect of ESS cost.
Table 9. Results on the effect of ESS cost.
ESS CostOptimal SchemeTotal Cost ($ × 109)Costs for TGUsCosts for ESSFinancial Penalty ($ × 105)
PESS (MW)EESS (WMh)U1U2U3U4Investment Cost ($ × 109)Maintenance Cost ($ × 108)Production Cost ($ × 109)Emission Cost ($ × 109)Investment Cost ($ × 107)Maintenance Cost ($ × 106)Operation Cost ($ × 105)
0.810022030205.99721.38293.15542.83371.39556.63232.190510.68710
1.04012030216.01491.41933.23862.83701.39523.33021.49364.79144.1851
1.24012030216.02191.41933.23862.83701.39523.99631.79235.74974.1851
1.44010030216.02901.41933.23862.83821.39604.65001.74255.40484.2251
2.04010030316.04981.41933.23862.83761.39526.64292.48937.58644.1851

Share and Cite

MDPI and ACS Style

Ma, Y.; Yang, H.; Zhang, D.; Ni, Q. Operation Flexibility Evaluation and Its Application to Optimal Planning of Bundled Wind-Thermal-Storage Generation System. Electronics 2019, 8, 9. https://doi.org/10.3390/electronics8010009

AMA Style

Ma Y, Yang H, Zhang D, Ni Q. Operation Flexibility Evaluation and Its Application to Optimal Planning of Bundled Wind-Thermal-Storage Generation System. Electronics. 2019; 8(1):9. https://doi.org/10.3390/electronics8010009

Chicago/Turabian Style

Ma, Yinghao, Hejun Yang, Dabo Zhang, and Qianyu Ni. 2019. "Operation Flexibility Evaluation and Its Application to Optimal Planning of Bundled Wind-Thermal-Storage Generation System" Electronics 8, no. 1: 9. https://doi.org/10.3390/electronics8010009

APA Style

Ma, Y., Yang, H., Zhang, D., & Ni, Q. (2019). Operation Flexibility Evaluation and Its Application to Optimal Planning of Bundled Wind-Thermal-Storage Generation System. Electronics, 8(1), 9. https://doi.org/10.3390/electronics8010009

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop