Next Article in Journal
System Criticality of Road Network Areas for Emergency Management Services—Spatial Assessment Using a Tessellation Approach
Next Article in Special Issue
A Study on the Integration of Resilience and Smart City Concepts in Urban Systems
Previous Article in Journal
Climate Emergency Adaptation and Sustainable Management Strategies in Rural and Agricultural Landscapes
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Automated Construction Progress and Quality Monitoring for Commercial Buildings with Unmanned Aerial Systems: An Application Study from Switzerland

by
Clemens Kielhauser
*,
Raul Renteria Manzano
,
Jeffrey J. Hoffman
and
Bryan T. Adey
Department of Civil, Environmental and Geomatic Engineering, University ETH Zürich, 8092 Zurich, Switzerland
*
Author to whom correspondence should be addressed.
Infrastructures 2020, 5(11), 98; https://doi.org/10.3390/infrastructures5110098
Submission received: 28 September 2020 / Revised: 9 November 2020 / Accepted: 9 November 2020 / Published: 11 November 2020
(This article belongs to the Special Issue Smart, Sustainable and Resilient Infrastructures)

Abstract

:
Unmanned Aerial Systems (UASs), which have become a key tool in remote sensing in recent years, have also rapidly entered the practice of Architecture, Engineering, Construction, and Operations (AECO). This paper presents an application study of a methodology for monitoring construction progress and quality using real-time data from a commercial building during the execution phase and the results of an analysis of the costs and benefits of monitoring construction progress and quality with and without a UAS. The methodology used consists of three parts: (1) automated data collection at the construction site, (2) data processing, in which the collected data are processed to generate the outputs necessary for the data analysis, and (3) data analysis to monitor construction progress and quality. The method is based on the detection of structural elements, combined with four principles: the sectional approach, the calculation of the concrete volume, the height-distance measurement, and the detection of defects by visual comparisons. The cost-benefit analysis considers three cases: monitoring of progress (1) by the construction company using the UAS, (2) by external contractors using the UAS, and (3) by the construction company without using the UAS. We show that the in-house operation of the UAS is associated with medium costs. However, a return on investment can be achieved quickly if the strategy for the operation of the UAS is clearly defined. In summary, the use of a UAS for the automated monitoring of the construction progress and quality of commercial buildings is practicable, which can quickly lead to a return on investment. We also show that there is great potential for further improvements.

1. Introduction

Unmanned Aerial Systems (UASs) have rapidly entered the practice of Architecture, Engineering, Construction, and Operations (AECO) in recent years, and forecasts indicate that their use in these areas will continue to increase in the foreseeable future [1,2]. Especially for infrastructure objects, their large number opens up a wide range of potential applications [3].
Currently, however, the main direction of development in the AECO industry is moving towards Building Information Model (BIM) technology and data management, as BIM enables efficient data management and data analysis compared to more traditional methods [4,5]. However, BIM has even greater potential and can be further enriched with advanced tools that could integrate all the components already present in the construction sector and, thus, further improve the productivity and quality of construction projects [6,7].
A significant window of opportunity for such improvement lies in the area of project management [8,9]. Currently, BIM is mainly used within project management to manage resources, while other essential aspects such as monitoring progress and quality during the execution phase using real-time data are given less priority. The same is true for UASs, which play a significant role in safety-related applications for infrastructures, but less in the area of project management [10].
However, since the primary goal of a construction project manager should always be to complete the project on time, to specification, and within budget, on-site data management and analysis is very important.
The main objective of this paper is to show how UASs enable tracking the progress and quality of a construction project against a baseline by collecting, analyzing, and evaluating real-time data during the execution phase of a commercial building. The case study building is currently under construction in Zurich, Switzerland, and was provided by research partner Implenia Schweiz AG.
In addition, the case study also compares costs with traditional project management methods, while trying to identify limitations, benefits, risks, and a practical application framework that can be implemented in the construction industry within the existing platforms.
The rest of this paper is structured as follows: First, a literature review summarizes the current state of research and positions this work within it, including information on the legal situation of UAS operation and case studies in the construction industry on this topic. The case study itself is illuminated from two sides: First, the general method of the case study is presented, which is divided into three phases: data collection, data processing, and data analysis. Then, the section on the case study presents the specifics and the setup of the hardware and software, the results obtained, as well as an assessment of the time and cost reduction. Finally, conclusions and further recommendations are presented.

2. Literature Review

In this section, the relevant literature pertaining to (1) the usage of UASs in construction and (2) the applicable UAS regulations in the area of the case study are presented.

2.1. UAS Usage in Construction

In construction, the main use of UASs is based on security, safety, and documentation, e.g., in [11], where UASs were applied to replace a safety manager on-site, or in [2], where the visual assets produced by the UAS were used to inspect the construction site for safety conditions. Regular inspections of built objects, especially in the infrastructure area, are also a primary usage area of UASs. For example, Reference [12] presented a method of visual inspection based on aerial photos of concrete structures taken by UASs. A cost-effectivity study was presented in [13], which assessed whether UASs provide a cost-effective and safe method for remotely performing visual inspections of bridges. The practical implications of such a UAS-based bridge inspection were addressed in [14]. Another safety-related use of UASs was presented in [15], where a UAS was used to provide the data basis to estimate the hydraulic risk of bridges after flooding events. A possible use of UASs to capture excavation geometry was presented in [16]. The accuracy of UASs in gathering survey data was discussed in [17] and was deemed less accurate than a total station, but better in terms of the price-performance ratio. In terms of project management, Reference [18] showed in an interview-based exploratory paper that project managers would find aerial assets taken by UASs very useful, and they were deemed a relevant opportunity to explore. First steps have been taken, for example, in [19] or [20], where UASs were used to assess progress and quality on a linear rail construction site, with both suggesting to extend their work to general construction sites that are non-linear and therefore more complex to monitor.

2.2. UAS Regulations

In Switzerland, the area of the case study, the main legal document governing the use of UASs at the time of performing the UAS flights is the SR.748.941 DETEC Ordinance of 24 November 1994 on Special Category Aircraft (OSCA). Section 6 covers the operation of UASs over 30 kg (66 lbs):
Unmanned aircraft, in particular manned kites, paragliders, tethered balloons, free-flying balloons and model aircraft that weigh more than 30 kg may only be flown with authorization from FOCA (Federal Office of Civil Aviation). The FOCA shall specify the requirements for authorization and the operating conditions on a case-by-case basis.
In other words, the operation of UASs over 30 kg is decided on a case-by-case basis, and therefore a tedious and time-consuming process. Section 7 of the OSCA covers unmanned aircraft up to 30 kg (66 lbs), a category in which most UASs fall. The main points of the rules can be summarized as:
  • Mandatory:
    -
    Direct line-of-sight during operation
    -
    Yield to all other aircraft
    -
    Insurance coverage of a min. of one million CHF
  • Prohibited:
    -
    Flying near emergency services
    -
    Flying closer than 5000 m (5460 yd) to airports
    -
    Flying higher than 150 m (492 ft) in controlled traffic areas
    -
    Flying closer than 100 m (110 yd) to groups of people (i.e., 24 persons or more)
    -
    Flying in protected wildlife zones
Additionally, local authorities may temporarily impose further restrictions.

2.3. Literature Summary

In summary, the usage of UASs in construction is focused on security and safety-related tasks together with routine inspection, with a trend towards experimenting with other uses. The literature sees potential for development and recommends further research in the area of construction management. This paper provides a case study addressing this, by presenting an application study of a method for monitoring construction progress and quality using real-time data from a commercial building during the execution phase of the construction.

3. Method

In this section, the methods that enable construction managers to improve upon their current situation using UAS-based automated progress and quality tracking are presented. The goal of this section is to describe the methods used through process charts. Figure 1 shows the general process of the method. The process is drawn using BPMN 2.0, a standardized graphical language for processes [21].
Figure 1 also shows the corresponding inputs and outputs for each subprocess. The data collection subprocess uses the site specifications and the legal regulations as the input, as both set boundaries for the UAS flight, which is the core part of the data collection. The result of the data collection is the UAS dataset, which is handed over to the data processing subprocess, where an orthomosaic and a point cloud are generated, which are needed as an input for the final subprocess, the data analysis. With additional input from the BIM and the schedule, a progress and quality report can be created.
The remainder of this section is divided into three parts, corresponding to the three subprocesses of the method as shown in Figure 1: (1) the data collection, (2) the data processing, and (3) the data analysis.

3.1. Data collection

The subprocess of data collection defines how the data collection procedure is executed and serves as a bridge between the need for data, the legal regulations, and the specifics of the construction site. Figure 2 shows the process in detail.
First, the area of the site from which data should be collected has to be defined. The area might change due to different phases in the construction plan (e.g., if there is no work performed in a certain area, it can be excluded from the mapping or, on the contrary, if there is non-postponable work that might interfere with the UAS flight, such as pouring concrete with a concrete pump). By defining the data collection area, the UAS software is able to create a flight plan that covers the area to be investigated, taking into account the characteristics of the optical system (e.g., camera angle, field of view, etc.).
Then, the next step is to analyze the weather and safety conditions, taking into account the legal regulations (e.g., maximum allowable wind speed for UAS flight, temporary flight restrictions), with a final decision about whether it is safe to fly. If not, the data collection has to be postponed or canceled. If the conditions are safe, the UAS can be prepared for flight using the appropriate checklists and procedures.
In parallel, the present state (i.e., shortly before take-off) of the construction site has to be analyzed and verified for obstacle clearances that might have gone unnoticed during the site area definition, as construction sites can be fast-changing environments.
Next, the autonomous flight mission can be created (in most situations, this will encompass only slight modifications to the general “standard” flight plan) and uploaded to the prepared UAS.
Then, the UAS will automatically fly two missions: first, a flight mission with a course angle (the angle between the primary direction of movement and the centerline of the UAS’s optical system) of 0 and, then, a course angle of 90 , as shown in Figure 3. This ensures that the images overlap on the long side (0 ), respectively on the short side (90 ). Simply put, with a course angle of 0 , the UAS primarily moves “forward and back”, and with a course angle of 90 , the UAS primarily moves “left and right”.
Finally, the collected data from the UAS are downloaded and stored in an appropriate data storage.
In summary, in the subprocess of data collection, the area from which data should be collected is defined, the necessary safety and obstacle checks are performed, the automated UAS flight is planned and executed, and the collected data are stored for further use.

3.2. Data Processing

The subprocess of data processing prepares and transforms the data for later analysis. The process follows a standard photogrammetry workflow and is depicted in Figure 4.
First, the UAS dataset (i.e., georeferenced images) is imported from the data storage. Then, the images are aligned, i.e., points that occur in multiple images are marked as being the same point. With this, the relative location of all images can be determined, and all individual images can be joined into a puzzle-like big picture, using standard photogrammetry procedures. The expected relative accuracy (i.e., the dimensions and distances within aligned images) is about 0.3 to 0.5 times the ground pixel size (i.e., the size that a pixel on the image sensor will have on the observed area, if back-projected through the optical system).
The aligned images, which contain the GPS coordinates from the UAS, are then referenced to a subset of reference points (i.e., to points whose coordinates are known precisely from surveying), in order to place the aligned images accurately in space, as in contrast to the relative accuracy of the images, the absolute accuracy of placement in space without referencing is reduced to the accuracy of the GPS, which strongly varies depending on the location and available satellites and can be in the order of 0.3 to 5 m (1 to 16 ft). The remaining reference points are then used for accuracy control, i.e., the known coordinates are compared to the coordinates calculated from the UAS dataset. If the accuracy is insufficient, the referencing procedure should be repeated until an acceptable accuracy is reached.
Then, a dense point cloud is calculated, using the referenced images and information about the optical system of the UAS, such as sensor size, focal length, angular resolution, and lens distortion. The individual points from the dense point cloud are then connected to form a mesh (i.e., a surface). From the mesh, an orthomosaic (i.e., a geometrically corrected photo that is used to measure true distances and angles, having been adjusted for topographic relief, lens distortion, and camera tilt) is created.
Finally, the data are sent back to the data storage. The point cloud is saved as an .XYZ file, i.e., a list of each point with its X, Y, and Z-coordinates and other properties of the point. The orthomosaic is stored as an uncompressed .TIFF file in order to preserve all details.
In summary, the subprocess of data processing uses the collected images from the UAS to create a digital three-dimensional representation of the construction site at the time of data collection.

3.3. Data Analysis

The data analysis process, which combines all data sources and produces the progress and quality report, is shown in Figure 5.
First, all different data sources (i.e., the orthomosaic, the point cloud, and BIM and schedule information) are retrieved from the data store. Then, the whole dataset is split into manageable sections to enable efficient processing. This is especially advantageous if multi-processor parallel computing is available. Then, within two subprocesses, progress and quality are monitored. These two subprocesses are explained in more detail below. With the data from the progress and quality monitoring, the BIM, and schedule information, a report is produced that is then displayed in a prototype tracking software that was created to facilitate the tracking of the whole construction process. Details of the tracking software are explained in more detail in the case study section.

3.3.1. Progress Monitoring

The process of progress monitoring calculates the difference between the scheduled progress and the actual progress as recorded by the UAS. Figure 6 shows the process.
First, a digital volume of the building at the time of data collection is created, which reflects the state of construction that the site would be in, according to the BIM and the schedule. At the same time, a digital volume of the building is created from the collected data, i.e., the “as-is” state of the construction. Both volumes are then compared, and the difference in volume is then transformed into a difference in schedule. A small example is shown in Table 1.
In the first line, the task “Section A” has a total concrete volume of 30 m 3 and should be 100% complete according to the schedule, i.e., 30 m 3 of concrete should be present. The UAS-based digital volume is 27 m 3 , i.e., only 27 m 3 / 30 m 3 = 90 % complete. Therefore, the Δ in time is (90%–100%) · 5 d = 0.5 d , meaning that this task is half a day late. Section B should be at 6 m 3 or 20% according to the schedule, but is in reality at 21 m 3 , i.e., already 21 m 3 / 30 m 3 = 70 % complete. Therefore, the difference Δ in time is (70%–20%) · 5 d = 2.5 d , meaning that this task is two and a half days ahead of time.
In summary, the process of progress monitoring compares the as-planned volume of the construction task to the as-is volume of the construction tasks and calculates the difference in time for each task from the schedule. Negative Δ numbers signify late tasks, and positive Δ numbers signify tasks ahead of time.

3.3.2. Quality Monitoring

The process of quality monitoring calculates the difference between the planned building dimensions and the actual dimensions as recorded by the UAS. Figure 7 shows the process.
First, a digital volume of the building at the time of data collection is created, which reflects the state of construction that the site would be in, according to the BIM and the schedule. At the same time, a digital volume of the building is created from the collected data, i.e., the “as-is” state of the construction. Both volumes are then overlaid, and the areas where the volumes differ are then marked and listed. A small example is shown in Table 2. Note that while differences can be listed, the reason for the difference has to be confirmed by hand, as the reasoning for why a quality deviation is present is outside the capability of automated processing.
Table 2 shows two lines: In the first line, the issue shown is a vertical deviation in Section C. In the second line, a volume location issue for Section D is shown. It is important to note that this step can only show that discrepancies between the BIM (i.e., “as-planned”) and the “as-is” exist, but cannot give an interpretation of why the difference exists.
A vertical deviation signifies that in the specified section, the top height of the as-is deviates from the top height as-planned. A volume location issue for Section D signifies that the as-planned volume is equal to the as-is volume in Section D, but it is at different locations. Although it is not possible to automatically give reasons for why both these quality issues occurred, a vertical deviation could hint at a measurement error or the wrong amount of concrete poured, and a volume location error could hint at a construction element placed wrongly, e.g., a window opening at the wrong location.
In summary, the process of quality monitoring compares the as-planned volume to the as-is volume of the construction tasks and marks deviations from each other. Although the reasons for why the quality issues exist cannot be determined automatically, the types of issues may hint at certain quality issues nonetheless.

3.4. Method Summary

A method is presented that formalizes the process of data collection, data processing, and data analysis for UAS-based automated progress and quality tracking on construction sites. The process makes use of the existing schedule and BIM information and merges this with UAS-captured on-site data in order to provide a real-time situational overview to assist the construction project manager to complete the project on time, to specification, and within budget.

4. Implementation

In this section, the case study construction site is presented. The section is structured as follows: First, the construction project, the construction site and its surroundings, as well as the local regulations, that influence the operation of UASs are described. Then, the hardware and software setup is described. Next, the results are presented, followed by a cost analysis of the use of UASs in this particular setup. The section on “Key Operational Findings” presents valuable information on the operation of UASs that has been gained during the practical execution phase of the UAS flights. Finally, the case study is summarized. Conclusions drawn from the results of the case study are discussed in the Conclusion (Section 6).

4.1. Case Study Description

The construction project used for this case study was the Preola-Areal Logistics Builidng in Zurich, Switzerland. The 25,000 m 2 (270,000 ft 2 ) building will be mainly used as the new headquarters of a electrical industry wholesaler and will contain a warehouse, offices (some of which will also be rented out to other companies), showrooms, and a shop. The authors were given access to the construction site for a period of four weeks to perform the on-site data collection.
The construction site was located in the City of Zurich, next to a railway line, a railway station, and the highway. Figure 8 shows a map of the surroundings.
It can be seen that the construction site (orange) is situated directly next to a six-track electrified railway line (red ellipse) and a railway station (red circle), as well as a highway (red lines). Additionally, the area is in a Controlled Traffic Region (CTR)) zone from Zurich International Airport. The CTR stretches across the whole map image.
This has the following implications for the operation:
  • Due to the CTR, the maximum allowable altitude Above the Ground Level (AGL) for UAS operation is 150 m (492 ft).
  • The catenary from the railway line might cause electromagnetic fields that interfere with remote control.
  • Although legally permitted, the closeness to the highway, railway line, and railway station might cause concerns for the citizens that will cause interruptions to the UAS operation.
The concerns were addressed by the following measures:
  • The maximum AGL was properly set in the UAS software.
  • Special attention was given to the pre-flight phase and during flight on the stability of the radio link quality between the UAS and remote control.
  • The spokesperson and the foremen of the construction site were informed about the UAS operation and were given appropriate information on addressing citizens’ concerns.
In summary, the construction project was a standard commercial building of medium size, with the surroundings being suitable for UAS operation, although with some restrictions and some concerns that needed to be addressed.

4.2. Hardware and Software Setup

In this section, the hardware and software setup is described that was used in the case study. No endorsement of a particular hardware or software is intended.

4.2.1. UAS

The UAS used in the case study was a DJI Inspire 1. Technical details of the UAS are listed in Table 3.

4.2.2. Software Flowchart

Figure 9 shows a flowchart of the software used in the case study that describes the data and information flow between the proprietary software used in the implementation. It can be seen as a combination of Figure 1, Figure 2, and Figure 4 applied to the available software.
First, in the step of flight planning, DJI GS Pro was used in order to set the flight plan, the flight restrictions, and the adaptations necessary for the local obstacles, as explained in Section 3.1 and in Figure 2. Then, the flight plan was uploaded to the UAS, and the flight was performed. After the flight, the data processing, as explained in Section 3.2 and in Figure 4, was performed using AgiSoft Metashape Pro, a photogrammetry and image processing software. The iterative referencing procedure according to Section 3.2 was halted when an average accuracy of 0.8 cm was reached. The software also created the .XYZ file and the orthomosaic necessary for the next steps. For data analysis, the data were merged from different sources, as the available data were delivered in several different data formats. The .XYZ file from the data collection was processed with Autodesk Recap 3D; the CAD model of the building was processed in Rhino 3D. Both software generated output that was finally merged with the BIM in Autodesk Navisworks, where the data join and the measurements were performed.
Both quality and progress measurements were then transformed into Microsoft Excel, in order to perform the schedule calculations. Finally, the results were transferred to the custom-made software Track to go, which linked the output of the schedule and quality calculation to the orthomosaic, and thus presented the results in a user-friendly way on mobile devices and tablets.

4.3. Results

In this section, the results of the method are presented, based on a four-week period of progress and quality monitoring on the construction site.

4.3.1. Progress Monitoring

Progress monitoring in the case study was performed during Weeks 13 to 16 of the baseline schedule provided by the research partner, Implenia. In Table 4, a comparison between the planned concrete volume according to schedule and the concrete volume detected by the UAS is shown.
The table shows the tasks (the construction of Wall Sections 2 and 3 and Slab Sections 2 and 3) that were planned within the four weeks on the left. The columns to the right show for each Week (W13, W14, W15, W16) (a) the percentage completion planned for the respective week, (b) the progress captured by the UAS in percent, and (c) the difference Δ in days, according to Section 3.3.1 and Table 1. For Wall Section 2, it can be seen that the task was behind schedule (negative Δ ) in Weeks 13 and 14, but it could be completed in time in Week 15. For Wall Section 3, the task was ahead of time in Weeks 13, 14, and 15, but could not be completed in time in Week 16. Slab Section 2 was also ahead of time in Weeks 13–15 and was almost complete in Week 16, with a delay of only 0.1 day. Slab Section 3 was, following the schedule, not started until Week 16. It was, however, ahead of time with a Δ of 3.8 days at the end of Week 16.

4.3.2. Quality Monitoring

As mentioned in Section 3.3.2, the process of correctly identifying quality errors had to be made manually. Table 5 shows an example of such a quality monitoring report.
It can be seen that three quality issues were identified. The first issue was a vertical deviation of Interior Walls 9 and 10. Most likely, this stemmed either from a miscalculation or a mismeasurement of the poured concrete level. The second issue was a column placement deviation of 1422 mm (56 in). After a deeper investigation, the source for the quality issue was the failure to update the BIM data that were provided. The repositioning of the column was marked in the plans for the contractor, but not updated in the BIM data used to determine the correct location of the column. The third quality issue was based on the same issue as before; the new window opening was not inserted in the baseline document, only in the contractor plans.

4.3.3. Cost Analysis

In this section, three different scenarios are evaluated to see whether the use of the UAS was financially feasible compared to the traditional method. The cost analysis considered all steps shown in Section 3. The costs were calculated using the local currency (Swiss Francs (CHF)) and local prices. First, the total cost per data collection flight was calculated for each scenario. Then, the total cost of using drones for the whole construction of the Preola Building was calculated in order to compare the financial feasibility of UAS-based progress and quality measurement.
The first scenario was the in-house operation of the UAS by the construction company. Table 6 shows all the elements required and the total investment cost, as for the setup used in this case study. The total cost per data collection flight is shown in Table 7, assuming a conservative UAV lifetime of 80 flights (one flight per week, 40 weeks with appropriate weather conditions, 2 year UAS lifetime) and the hourly costs of a construction worker with specialized training. The estimates for the time required in Table 7 stem from the authors’ own experience. The hourly costs for the data processing were reduced by 50%, as some of the processing could be performed unattended (e.g., over night).
The second scenario is outsourced operation of the UAS. The investment costs remained the same, but the costs per flight were slightly modified, as shown in Table 8. For the planning, data processing, and data analysis stage, the same hourly estimates as in Scenario 1 were used. For the data collection process, a higher hourly cost was assumed, based on the assumption that a UAS operating company will have the highest license for UAS pilots (which is not needed for pure construction site flights, but for other UAS operations) and, therefore, charge higher hourly rates for their pilots. However, the depreciation was calculated with the assumption that the UAS operating company would have more flights in the lifetime of the UAS, estimated as 80 days with both suitable weather and pending assignments per year.
The third scenario was using traditional methods to measure progress and quality. A summary is shown in Table 9. For the hourly cost, a certified quality control person was assumed. The investment depreciation was estimated using the internal rental costs for the equipment necessary for the manual data collection (measurement equipment, total station).
In summary, it can be noted that the traditional progress and quality measurement was the least expensive, under the assumption that there are no additional benefits of the UAS data collection. Compared to the outsourced data collection, the in-house data collection was approximately 15% less expensive.

5. Discussion

5.1. Key Operational Findings

In this section, key operational findings are provided that were deemed important lessons learned by the authors. They are intended to help the reader to learn from the challenging situations that occurred and were overcome during this case study.

5.1.1. Magnetic Fields

During the execution of one automated flight, the UAS was started to record a new area, in which the rebaring was in progress. Shortly after the UAS took off, it started an emergency landing procedure. In this phase, the pilot had no control over the UAS and was not able to abort the landing. Finally, the UAS landed in a freshly concreted area. From there, it could be manually flown back to the take-off point. After looking into the flight data recorder, a fluctuation of the magnetic field (black line in Figure 10) was discovered.
Investigation of the zone where the incident happened revealed that the rebar in the concrete was magnetized, leading to a distortion of the local natural magnetic field. This in turn caused a sensor disagreement (i.e., the inertial measurement sensor and the magnetic orientation sensor suddenly showed different directions as “upwards”). With the flight control software being unable to determine which input was the correct one, an emergency automated landing was initiated. After investigating the local area with a magnetometer, which confirmed this situation and also showed that the distortion was only present close above the surface of the take-off spot, it was decided to use two tables stacked on top of each other as a takeoff spot to successfully address the problem.

5.1.2. Construction Site Tidiness, Uncluttering

The second valuable lesson learned during the case study was that clutter and other objects dispersed around the construction site were impacting the automatic image recognition capabilities of the image processing software. For example, objects lying around the construction site, such as tools, tarps, unused auxiliary material (e.g., lumber for makeshift construction) obscured the surface, or in the case of tarps, might move in the wind. This led to the areas underneath said objects not being able to be processed automatically. Manual correction had to be used in such areas, but could have been avoided if the construction site were tidy and uncluttered.

5.2. Case Study Summary

In general, the case study showed that it is feasible to measure progress and quality with UASs. Delay times could be calculated, and quality issues could be detected. However, some of the quality issues stem from non-updated data sources, and some delay times might be caused by non-recorded changes in the schedule. The cost analysis showed that at the moment, the traditional method is more cost-effective than the UAS-based method. This will be discussed in the Conclusion section. Valuable lessons were also learned in the case study that could prove helpful for further research or practical applications.
In general, the overall method presented in this paper is feasible to measure progress and quality with UASs, but also very time consuming, and thus less cost-effective than the traditional method. The data collection process discussed in this paper leads, aside from the data necessary for the quality and progress measurement, to useful images about the actual state of the construction site at the time of data collection. This additional benefit has not been considered in the comparison of the different scenarios, but might sway the decision in the direction of using UASs, as the cost difference between in-house UAS operation (1232 CHF/flight) and the traditional method (1135 CHF/flight) was only 8.5%.
The data processing step was the most time-consuming part, requiring 22 h for the processing (see Table 7. This, however, can be improved by using parallel computing and GPU-based calculation, which will make the process faster.
The data analysis step in this method is feasible, but time consuming and not automatized. Developing a programmed code that would automate the proposed processes in a commercial building for measuring quality and time seems enormously difficult, as the construction site changes very fast. To fully automate the proposed processes to measure progress and quality, an artificial intelligence solution would likely need to be employed. Knowing the maximum inaccuracies (vertical and horizontal) of the point cloud model is especially useful for knowing which elements’ quality measures are reasonable. If, for example, the target height of a wall deviates from the actual height (looking at the the point cloud) by only a few millimeters, this may be within the error range of the point cloud model, and it remains therefore unknown whether it is an inaccuracy of the model or a wall actually built inaccurately in height. For the calculation of progress, the error in the order of the magnitude of the inaccuracy of the point cloud model plays a minor role, since the cumulative volumes of the stages would only change slightly.
There is a considerable potential for optimization and development based on this research and its results. The process requires improvement, especially in image processing. This process is the most crucial aspect of the entire method since the data analysis and its results are strongly dependent on the data input. A better understanding of the software would enable gaining a more profound knowledge of the reconstruction of the 3D model and its individual process steps to achieve the best possible results. The computing time of image processing is a tedious process; thus, a more efficient process is desired.
Furthermore, the efficiency and automatization of data analysis have still more potential. The better implementation of BIM would be an enormous benefit by enabling the benchmarking of measured and target values, as at the time, a dedicated schedule was used, which was not included in the BIM. If the measured model in the BIM can be automatically overlapped and compared with the designed construction site, deviations could be identified and displayed immediately.

6. Conclusions

The main objective of this paper was to show how UASs enable tracking the progress and quality of a construction project against a baseline by collecting, analyzing, and evaluating real-time data during the execution phase of a commercial building. This paper contributes to scientific knowledge by presenting a case study that demonstrates the main objective and furthermore gives additional insight on key operational findings that were deemed important lessons learned by the authors. They are intended to help the reader to learn from the challenging situations that occurred and were overcome during this case study. Additionally, the cost analysis shows that the additional benefits might sway the decision into the direction of using UASs, as the cost difference, not taking into account the additional benefits, was only 8.5% and should therefore be further investigated.

Author Contributions

Conceptualization, C.K., R.R.M., and J.J.H.; methodology, R.R.M.; writing, original draft preparation, C.K.; writing, review and editing, C.K., R.R.M., and B.T.A.; visualization, R.R.M.; supervision, C.K, J.J.H., and B.T.A.; project administration, C.K. and J.J.H.; funding acquisition, R.R.M. All authors read and agreed to the published version of the manuscript.

Funding

The contribution of R.R.M. was supported by a scholarship for R.R.M.’s Master Program, provided by CONACYT (the Mexican National Council of Science and Technology) and SENER (Secretary of Energy in Mexico).

Acknowledgments

The authors would like to thank Implenia Schweiz AG and all the people involved in this project, especially Johannes Müller for allowing access to the Preola-Areal Building in order to collect data with the UAS and for providing all the construction drawings, quality standards, and baseline documents for the research, as well as all the support and valuable information exchange.

Conflicts of Interest

The funders had no role in the design of the study; in the collection, analyses, or interpretation of data; in the writing of the manuscript; nor in the decision to publish the results. The hardware and software used in the case study are listed solely for the purposes of completeness and open communication. No endorsement of a particular hardware or software is intended.

Abbreviations

The following abbreviations are used in this manuscript:
AECOArchitecture, Engineering, Construction, and Operations
AGLAltitude above Ground Level
BIMBuilding Information Model
BPMN 2.0Business Process Modeling Notation Version 2.0
DETECFederal Department of the Environment, Transport, Energy, and Communications
CTRControlled Traffic Region
FOCAFederal Office of Civil Aviation
OSCAOrdinance on Special Category Aircraft
SRSystematische Rechtssammlung des Bundes (Classified Law and Ordinance Collection of the Swiss Federation)
UASUnmanned Areal Systems

References

  1. Eschmann, C.; Kuo, C.M.; Kuo, C.H.; Boller, C. Unmanned Aircraft Systems for Remote Building Inspection and Monitoring. In Proceedings of the 6th European Workshop on Structural Health Monitoring, Dresden, Germany, 3–6 July 2012; Volume 36, p. 13. [Google Scholar]
  2. De Melo, R.R.S.; Costa, D.B.; Álvares, J.S.; Irizarry, J. Applicability of unmanned aerial system (UAS) for safety inspection on construction sites. Saf. Sci. 2017, 98, 174–185. [Google Scholar] [CrossRef]
  3. Flammini, F.; Pragliola, C.; Smarra, G. Railway infrastructure monitoring by drones. In Proceedings of the 2016 International Conference on Electrical Systems for Aircraft, Railway, Ship Propulsion and Road Vehicles & International Transportation Electrification Conference (ESARS-ITEC), Toulouse, France, 2–4 November 2016; pp. 1–6. [Google Scholar] [CrossRef]
  4. Ramaji, I.J.; Memari, A.M. Interpreted Information Exchange: Systematic Approach for BIM to Engineering Analysis Information Transformations. J. Comput. Civ. Eng. 2016, 30, 04016028. [Google Scholar] [CrossRef]
  5. Eastman, C.M.; Jeong, Y.S.; Sacks, R.; Kaner, I. Exchange Model and Exchange Object Concepts for Implementation of National BIM Standards. J. Comput. Civ. Eng. 2010, 24, 25–34. [Google Scholar] [CrossRef] [Green Version]
  6. Gökgür, A. Current and Future Use of BIM in Renovation Projects. Master’s Thesis, Chalmers University, Gothenburg, Sweden, 2015. [Google Scholar]
  7. Dupont, Q.F.; Chua, D.K.; Tashrif, A.; Abbott, E.L. Potential applications of UAV along the construction’s value chain. Procedia Eng. 2017, 182, 165–173. [Google Scholar] [CrossRef]
  8. Rokooei, S. Building information modeling in project management: Necessities, challenges and outcomes. Procedia-Soc. Behav. Sci. 2015, 210, 87–95. [Google Scholar] [CrossRef] [Green Version]
  9. Chan, A.P.; Ma, X.; Yi, W.; Zhou, X.; Xiong, F. Critical review of studies on building information modeling (BIM) in project management. Front. Eng. Manag. 2018, 5, 394–406. [Google Scholar]
  10. Zhipeng, Z.; Javier, I.; Ying, L. A Multidimensional Framework for Unmanned Aerial System Applications in Construction Project Management. J. Manag. Eng. 2018, 34, 04018004. [Google Scholar] [CrossRef]
  11. Irizarry, J.; Gheisari, M.; Walker, B.N. Usability assessment of drone technology as safety inspection tools. J. Inf. Technol. Constr. (ITcon) 2012, 17, 194–212. [Google Scholar]
  12. Hallermann, N.; Morgenthal, G.; Rodehorst, V. Vision-based monitoring of heritage monuments: Unmanned Aerial Systems (UAS) for detailed inspection and high-accuracy survey of structures. WIT Trans. Built Environ. 2015, 153, 621–632. [Google Scholar]
  13. Gillins, M.N.; Gillins, D.T.; Parrish, C. Cost-effective bridge safety inspections using unmanned aircraft systems (UAS). In Proceedings of the Geotechnical and Structural Engineering Congress 2016, Phoenix, Arizona, 14–17 February 2016; pp. 1931–1940. [Google Scholar]
  14. Kielhauser, C.; Romer, F.B.; Adey, B.T. Preliminary estimates of the viability of UAV-based bridge inspections. In Proceedings of the SMAR 2017 Conference, EMPA Materials Science and Technology, Zurich, Switzerland, 13–15 September 2017. [Google Scholar]
  15. Hackl, J.; Adey, B.T.; Wozniak, M.; Schümperlin, O. Hydraulic Risk Assessment of Bridges Using UAV Photogrammetry. In Proceedings of the EGU General Assembly Conference Abstracts, Vienna, Austria, 23–28 April 2017; Volume 19, p. 3129. [Google Scholar]
  16. Fleming, K.L.; Hashash, Y.M.; McLandrich, S.; O’Riordan, N.; Riemer, M. Novel technologies for deep-excavation digital construction records. Pract. Period Struct. Des. Constr. 2016, 21, 05016002. [Google Scholar] [CrossRef]
  17. Moser, V.; Barišić, I.; Rajle, D.; Dimter, S. Comparison of different survey methods data accuracy for road design and construction. In Proceedings of the International Conference on Road and Rail Infrastructure CETRA, Sibenik, Croatia, 23–25 May 2016. [Google Scholar]
  18. Irizarry, J.; Costa, D.B. Exploratory study of potential applications of unmanned aerial systems for construction management tasks. J. Manag. Eng. 2016, 32, 05016001. [Google Scholar] [CrossRef]
  19. Ulrich, J. Investigation of the Use of Drone Technology to Assess Progress on a Light Rail Infrastructure Project. Master’s Thesis, ETH Zurich, Zurich, Switzerland, 2018. [Google Scholar]
  20. Scherer, P. Investigation of the Use of Drone Technology to Assess Quality Control on a Light Rail Infrastructure Project. Master’s Thesis, ETH Zurich, Zurich, Switzerland, 2018. [Google Scholar]
  21. Allweyer, T. BPMN 2.0: Introduction to the Standard for Business Process Modeling; BoD–Books on Demand: Hohenwarsleben, Germany, 2010. [Google Scholar]
Figure 1. General process.
Figure 1. General process.
Infrastructures 05 00098 g001
Figure 2. Data collection workflow.
Figure 2. Data collection workflow.
Infrastructures 05 00098 g002
Figure 3. Course angle description (top view).
Figure 3. Course angle description (top view).
Infrastructures 05 00098 g003
Figure 4. Data processing workflow.
Figure 4. Data processing workflow.
Infrastructures 05 00098 g004
Figure 5. Data analysis workflow.
Figure 5. Data analysis workflow.
Infrastructures 05 00098 g005
Figure 6. Progress monitoring workflow.
Figure 6. Progress monitoring workflow.
Infrastructures 05 00098 g006
Figure 7. Progress monitoring workflow.
Figure 7. Progress monitoring workflow.
Infrastructures 05 00098 g007
Figure 8. Construction site and surroundings.
Figure 8. Construction site and surroundings.
Infrastructures 05 00098 g008
Figure 9. Case study software setup.
Figure 9. Case study software setup.
Infrastructures 05 00098 g009
Figure 10. Magnetic field fluctuation.
Figure 10. Magnetic field fluctuation.
Infrastructures 05 00098 g010
Table 1. Schedule difference calculation.
Table 1. Schedule difference calculation.
TaskDuration (d)Total Volume m3Schedule (Planned)UAS (As-Is) Δ (d)
Status (-)Volume m 3 Progress %Volume m 3 Progress %
Section A530complete301002790−0.5
Section B530in progress62021702.5
Table 2. Quality monitoring example.
Table 2. Quality monitoring example.
No.SectionIssue
1Section CVertical deviation
2Section DVolume location
Table 3. UAS technical specifications.
Table 3. UAS technical specifications.
ParameterValue
Weight3060 g (6.74 lbs)
Wind resistance10 m/s (19 kts)
Max. flight time18 min
Operating temp.−10 C to 40 C
(14 F–104 F)
Resolution12.4 MPix
FOV94
Table 4. Concrete volume progress monitoring. W, Week.
Table 4. Concrete volume progress monitoring. W, Week.
TaskW13  W14  W15  W16
Schedule
(%)
UAS
(%)
Δ
(d)
Schedule
(%)
UAS
(%)
Δ
(d)
Schedule
(%)
UAS
(%)
Δ
(d)
Schedule
(%)
UAS
(%)
Δ
(d)
Wall sect.250.025.2−2.5 50.029.6−2.0 100.0100.00.0 ---
Wall sect. 314.348.14.7 35.761.23.6 35.773.05.2 100.077.2−3.2
Slab sect. 217.675.99.9 29.475.97.9 29.488.810.1 100.099.5−0.1
Slab sect. 3--- --- --- 33.396.93.8
Table 5. Quality monitoring result.
Table 5. Quality monitoring result.
ElementTimeProblemImage
Interior wall 9&10W14vertical deviation 27 mm ( 1 1 / 16 in) Infrastructures 05 00098 i001
Column 25W14column placement deviation 1422 mm (56 in) Infrastructures 05 00098 i002
Exterior wall 1W14new window opening not in baseline documents Infrastructures 05 00098 i003
Table 6. UAS investment costs.
Table 6. UAS investment costs.
ItemCost (CHF)
UAS3983
Camera system2199
Remote control579
Desktop hardware and software licenses16369
Flight training and license2000
Insurance3000
Sum28130
Table 7. UAS in-house costs per flight.
Table 7. UAS in-house costs per flight.
StageTime
(h)
Unit Cost
(CHF/h)
Cost
(CHF)
Planning24080
Data collection24080
Data processing2220440
Data analysis640240
Documentation14040
Investment depreciation--352
Sum 1232
Table 8. UAS outsourced costs per flight.
Table 8. UAS outsourced costs per flight.
StageTime
(h)
Unit Cost
(CHF/h)
Cost
(CHF)
Planning24080
Data collection2160320
Data processing2220440
Data analysis640240
Documentation14040
Investment depreciation--176
Profit margin 10% 130
Sum 1425
Table 9. Traditional progress and quality measurement cost.
Table 9. Traditional progress and quality measurement cost.
StageTime
(h)
Unit Cost
(CHF/h)
Cost
(CHF)
Planning15555
Data collection855440
Data analysis655330
Documentation255110
Investment depreciation--200
Sum 1135
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Kielhauser, C.; Renteria Manzano, R.; Hoffman, J.J.; Adey, B.T. Automated Construction Progress and Quality Monitoring for Commercial Buildings with Unmanned Aerial Systems: An Application Study from Switzerland. Infrastructures 2020, 5, 98. https://doi.org/10.3390/infrastructures5110098

AMA Style

Kielhauser C, Renteria Manzano R, Hoffman JJ, Adey BT. Automated Construction Progress and Quality Monitoring for Commercial Buildings with Unmanned Aerial Systems: An Application Study from Switzerland. Infrastructures. 2020; 5(11):98. https://doi.org/10.3390/infrastructures5110098

Chicago/Turabian Style

Kielhauser, Clemens, Raul Renteria Manzano, Jeffrey J. Hoffman, and Bryan T. Adey. 2020. "Automated Construction Progress and Quality Monitoring for Commercial Buildings with Unmanned Aerial Systems: An Application Study from Switzerland" Infrastructures 5, no. 11: 98. https://doi.org/10.3390/infrastructures5110098

APA Style

Kielhauser, C., Renteria Manzano, R., Hoffman, J. J., & Adey, B. T. (2020). Automated Construction Progress and Quality Monitoring for Commercial Buildings with Unmanned Aerial Systems: An Application Study from Switzerland. Infrastructures, 5(11), 98. https://doi.org/10.3390/infrastructures5110098

Article Metrics

Back to TopTop