Identifying the Input Uncertainties to Quantify When Prioritizing Railway Assets for Risk-Reducing Interventions
Abstract
:1. Introduction
2. Methodology
- the reasonable best estimate, xbest, and the reasonable high estimate, xhigh,
- the reasonable best estimate, xbest, and the reasonable low estimate, xlow, and the reasonable best estimate, xbest, and the samples from skewed normal distributions, x, built assuming the high and low estimates, xhigh and xlow, encompassed the 95% confidence interval and the best estimate, xbest, was the mean value (). Figure 1 shows the probability density function of a skewed normal distribution, P(x), that was built using the best, xbest, low, xlow, and high, xhigh, estimates of the input value x. This is a right-skewed distribution because it has a longer tail on the left.
3. Case Study
3.1. Assets and Hazards
- like-new,
- slightly deteriorated,
- significantly deteriorated, and
- severely deteriorated
- extreme heat affecting the track sections and switches, and
- river flooding affecting the bridge B14 (see Figure 2)
3.2. Risks
3.3. Costs and Effects on Service of Risk-Reducing Interventions
- no damages occur on the site due to the execution of the risk-reducing interventions,
- no accidents occur due to the execution of the risk-reducing interventions, and
- the risk-reducing interventions are executed with the least possible traffic restrictions.
3.4. Variables
- the best estimate
- the reasonable low estimate, and
- the reasonable high estimate.
3.5. Results
3.5.1. Initial Ranking Using Best Estimates
3.5.2. Effect of Input Variable Uncertainties on Asset Rank
- Group A consists of input variables where the use of extreme values and value distributions resulted in a high number of weighted position changes, i.e., the highest-ranked assets are likely to change if the input uncertainties associated with these variables are considered.
- Group B consists of input variables where the use of extreme values and distributions of values resulted in a high number of position changes but with a low number of weight position changes, i.e., the rank of the lowest-ranked assets is likely to change if the input uncertainties associated with these variables are reduced. However, this does not occur in the rank of the highest-ranked assets. The effect of these input uncertainties is more prominent when low or high values are considered than when distributions of values are considered.
- Group C consists of input variables where the use of extreme values and distributions of values resulted in very few changes to the ranking. Considering the input uncertainties associated with these variables is unlikely to change the ranking of assets; therefore, the use of best estimates is sufficient in order to prioritize the assets for risk-reducing interventions accurately.
- 24 assets change their rank
- the first three assets with net benefit above €100,000, namely the bridges B16 and B38 and the track section T9, maintain their rank
- there are no changes in the rank of the assets with a positive net benefit
- track sections T1 and T2 have, on average, the most significant change in the ranking (6 positions).
- assets T1 and T2 have the largest number of changes in rank (more than 10 positions)
- 15 switches change between one and five positions
- 56 assets change one position or less in the rank.
4. Discussion
5. Conclusions
Supplementary Materials
Author Contributions
Funding
Conflicts of Interest
Appendix A
Load Event Type | Notation | Description | ||
---|---|---|---|---|
Track | Switches | Bridges | ||
Traffic load | le|TR | Annual tonnage on the track section based on the timetable | Annual wheel load on the switches due to train movements based on the timetable | Normalized annual traffic loads due to the daily traffic based on the timetable |
Level 1 load due to natural hazard | le1|NH | Thermal stresses on the track section caused by 17 °C ambient temperature | Neglectable thermal stresses on the switch elements | Neglectable increase in river flow speed |
Level 2 load due to natural hazard | le2|NH | Thermal stresses on the track section caused by 25 °C ambient temperature | Moderate thermal stresses on the switch elements | River flow speed that corresponds to a 25-year flood event |
Level 3 load due to natural hazard | le3|NH | Thermal stresses on the track section caused by 40 °C ambient temperature | High thermal stresses on the switch elements | River flow speed that corresponds to a 50-year flood event |
Level 4 load due to natural hazard | le4|NH | Thermal stresses on the track section caused by 43 °C ambient temperature | Thermal stresses beyond the designed level on switch elements | River flow speed that corresponds to a 100-year flood event |
Level 4 load due to natural hazard | le5|NH | Thermal stresses on the track section caused by 60 °C ambient temperature | - | - |
Infrastructure Event Type | Notation | Description | ||
---|---|---|---|---|
Track | Switches | Bridges | ||
No damage | ie1 | No noticeable damages on the track section due to the load event | No noticeable damages on the switch due to the load event | No noticeable damages on the bridge due to the load event |
Minor damage | ie2 | Damages that partially affect the track geometry or the rail condition | Damages that partially affect either the condition of the elements or the operation of the switch | Damages that partially affect the structural stability |
Severe damage | ie3 | Potential lack of stability of the track section to support the dynamic wheel load according to the required speed | Damages that significantly affect either the condition of the elements or the operation of the switch | Potential lack of structural stability |
Network Use Event Type | Notation | Description | ||
---|---|---|---|---|
Track | Switches | Bridges | ||
Normal use | ne1 | Fully operational track section | Fully operational block | Fully operational block |
Maximum speed restriction | ne2 | The operation of the track section is possible only when the speed is less than 40 km/h | The operation of all affected blocks is possible only with speed below 40 km/h | The operation of the block where the bridge is located is possible only with speed below 40 km/h |
Closure | ne3 | Closure of track section and all the blocks located in this track section | Closure of switch and all the affected blocks | Closure of the bridge and all the affected blocks |
Notation | Description | Notation | Description |
---|---|---|---|
se1 | No accident; no restoration at the site and no intervention; no traffic restriction | se8 | Accident; minor restoration at the site, rail replacement and tamping of the track section; traffic restrictions due to restoration, rail replacement, and tamping |
se2 | No accident; no restoration at the site and no intervention; maximum speed restriction for 24 hours | se9 | Accident; minor restoration at the site and renewal of the track section; traffic restrictions due to restoration and track section replacement, and maximum speed restriction for a week after renewal |
se3 | No accident; no restoration at the site and track section renewal after a month; maximum speed for a month until track section replacement and for a week after the renewal | se10 | No accident; minor restoration at the site and tamping of the track section; maximum speed restriction until the restoration of the site is complete, and the track section is tamped |
se4 | No accident; minor restoration at the site and tamping of the track section; traffic restrictions due to restoration and tamping | se11 | No accident; minor restoration at the site, and rail replacement and tamping of the track section; maximum speed restriction until the restoration of the site is complete, and the rail is replaced, and the track section is tamped |
se5 | No accident; minor restoration at the site and rail replacement and tamping of the track section; traffic restrictions due to restoration and rail replacement | se12 | No accident; minor restoration at the site and track section renewal; maximum speed restriction until the restoration of the site is complete, the track is renewed and for a week after renewal |
se6 | No accident; minor restoration at the site and renewal of the track section; traffic restrictions due to restoration and track section replacement and maximum speed restriction for a week after renewal | se13 | Accident; minor restoration at the site and tamping of the track section; maximum speed restriction until the restoration of the site is complete, and the track section is tamped |
se7 | Accident; minor restoration at the site and tamping of the track section; traffic restrictions due to restoration and tamping | se14 | Accident; minor restoration at the site and rail replacement and tamping of the track section; maximum speed restriction until the restoration of the site is complete, the rail is replaced, and the track section is tamped |
Notation | Description | Notation | Description |
---|---|---|---|
se15 | Accident; minor restoration at the site and track section renewal; maximum speed restriction until the restoration of the site is complete, the track section is renewed, and for a week after renewal | se19 | No accident; major restoration at the site and track section renewal; traffic restrictions until the restoration of the site is complete, and the track section is renewed; maximum speed restriction for a week after renewal |
se16 | No accident; minor restoration at the site and tamping of the track section; closure of the section until the restoration of the site is complete, and the track section is tamped | se20 | Accident; major restoration at the site and track section renewal; traffic restrictions until the restoration of the site is complete, and the track section is renewed; maximum speed restriction for a week after renewal |
se17 | No accident; minor restoration at the site, and rail replacement and tamping of the track section; closure of the section until the restoration of the site is complete, the rail is replaced and the track is tamped | se21 | No accident; major restoration at the site and track section renewal; closure of the section until the restoration of the site is complete, and the track section is renewed; maximum speed restriction for a week after renewal |
se18 | No accident; minor restoration at the site and track section renewal; closure of the section until the restoration of the site is complete, and the track section is renewed; maximum speed restriction for a week after renewal |
Notation | Description | Notation | Description |
---|---|---|---|
se1 | No accident; no restoration at the site and no intervention; no traffic restriction | se9 | No accident; minor restoration at the site and switch renewal; maximum speed restriction until the restoration of the site is complete, and the switch is renewed |
se2 | No accident; no restoration at the site and no intervention; maximum speed restriction for 24 hours | se10 | Accident; minor restoration at the site and welding or grinding of the switch; maximum speed restriction until the restoration of the site is complete, and welding or grinding is performed on the switch |
se3 | No accident; no restoration at the site and switch renewal after a month; maximum speed for a month until switch renewal | se11 | Accident; minor restoration at the site and switch renewal; maximum speed restriction until the restoration of the site is complete, and the switch is renewed |
se4 | No accident; minor restoration at the site and welding or grinding of the switch; traffic restrictions due to restoration and interventions | se12 | No accident; minor restoration at the site and welding or grinding of the switch; closure of the section until the restoration of the site is complete, and the switch is welded or ground |
se5 | No accident; minor restoration at the site and switch renewal; traffic restrictions due to restoration and switch renewal | se13 | No accident; minor restoration at the site and switch renewal; closure of the section until the restoration of the site is complete, and the switch is renewed |
se6 | Accident; minor restoration at the site and welding or grinding of the switch; traffic restrictions due to restoration and welding or grinding | se14 | No accident; major restoration at the site and switch renewal; traffic restrictions until the restoration of the site is complete, and the switch is renewed |
se7 | Accident; minor restoration at the site and switch renewal; traffic restrictions due to restoration and switch renewal | se15 | Accident; major restoration at the site and switch renewal; traffic restrictions until the restoration of the site is complete, and the switch is renewed |
se8 | No accident; minor restoration at the site and welding or grinding of the switch; maximum speed restriction until the restoration of the site is complete, and the switch is welded or ground | se16 | No accident; major restoration at the site and switch renewal; closure of the section until the restoration of the site is complete, and the switch is renewed |
Notation | Description | Notation | Description |
---|---|---|---|
se1 | No accident; no restoration at the site and no intervention; no traffic restriction | se9 | No accident; minor restoration at the site and bridge renewal; maximum speed restriction until the restoration of the site is complete, and the bridge is renewed |
se2 | No accident; no restoration at the site and no intervention; maximum speed restriction for 24 hours | se10 | Accident; minor restoration at the site and strengthening of the bridge; maximum speed restriction until the restoration of the site is complete, and the bridge is strengthened |
se3 | No accident; no restoration at the site and bridge renewal after a month; maximum speed for a month until bridge renewal | se11 | Accident; minor restoration at the site and bridge renewal; maximum speed restriction until the restoration of the site is complete, and the bridge is renewed |
se4 | No accident; minor restoration at the site and strengthening of the bridge; traffic restrictions due to restoration and interventions | se12 | No accident; minor restoration at the site and strengthening of the bridge; closure of the section until the restoration of the site is complete, and the bridge is strengthened |
se5 | No accident; minor restoration at the site and renewal of the bridge; traffic restrictions due to restoration and bridge renewal | se13 | No accident; minor restoration at the site and bridge renewal; closure of the section until the restoration of the site is complete, and the bridge is renewed |
se6 | Accident; minor restoration at the site and strengthening of the bridge; traffic restrictions due to restoration and intervention on the bridge | se14 | No accident; major restoration at the site and bridge renewal; traffic restrictions until the restoration of the site is complete, and the bridge is renewed |
se7 | Accident; minor restoration at the site and renewal of the bridge; traffic restrictions due to restoration and bridge renewal | se15 | Accident; major restoration at the site and bridge renewal; traffic restrictions until the restoration of the site is complete, and the bridge is renewed |
se8 | No accident; minor restoration at the site and strengthening of the bridge; maximum speed restriction until the restoration of the site is complete, and the bridge is strengthened | se16 | No accident; major restoration at the site and bridge renewal; closure of the section until the restoration of the site is complete, and the bridge is renewed |
References
- Koks, E.E.; Rozenberg, J.; Zorn, C.; Tariverdi, M.; Vousdoukas, M.; Fraser, S.A.; Hall, J.W.; Hallegatte, S. A global multi-hazard risk analysis of road and railway infrastructure assets. Nat. Commun. 2019, 10, 2677. [Google Scholar] [CrossRef] [Green Version]
- Macciotta, R.; Martin, C.D.; Cruden, D.M.; Hendry, M.T.; Edwards, T. Rock fall hazard control along a section of railway based on quantified risk. Georisk Assess. Manag. Risk Eng. Syst. Geohazards 2017, 11, 272–284. [Google Scholar] [CrossRef]
- Dikanski, H.; Hagen-Zanker, A.; Imam, B.; Avery, K. Climate change impacts on railway structures: Bridge scour. Proc. Inst. Civ. Eng. Eng. Sustain. 2016, 170, 237–248. [Google Scholar] [CrossRef]
- Zampieri, P.; Zanini, M.A.; Modena, C. Simplified seismic assessment of multi-span masonry arch bridges. Bull. Earthq. Eng. 2015, 13, 2629–2646. [Google Scholar] [CrossRef]
- Hong, L.; Ouyang, M.; Peeta, S.; He, X.; Yan, Y. Vulnerability assessment and mitigation for the Chinese railway system under floods. Reliab. Eng. Syst. Saf. 2015, 137, 58–68. [Google Scholar] [CrossRef]
- Chang, S.E.; Nojima, N. Measuring post-disaster transportation system performance: The 1995 Kobe earthquake in comparative perspective. Transp. Res. Part A Policy Pract. 2001, 35, 475–494. [Google Scholar] [CrossRef]
- Baker, C.J.; Cheli, F.; Orellano, A.; Paradot, N.; Proppe, C.; Rocchi, D. Cross-wind effects on road and rail vehicles. Veh. Syst. Dyn. 2009, 47, 983–1022. [Google Scholar] [CrossRef]
- Baker, C.J. A framework for the consideration of the effects of crosswinds on trains. J. Wind Eng. Ind. Aerodyn. 2013, 123, 130–142. [Google Scholar] [CrossRef]
- Arkell, B.P.; Darch, G.J.C. Impact of climate change on London’s transport network. Proc. Inst. Civ. Eng. Munic. Eng. 2006, 159, 231–237. [Google Scholar] [CrossRef]
- Lambert, J.H.; Sarda, P. Terrorism scenario identification by superposition of infrastructure networks. J. Infrastruct. Syst. 2005, 11, 211–220. [Google Scholar] [CrossRef]
- Dobney, K.; Baker, C.J.; Chapman, L.; Quinn, A.D. The future cost to the United Kingdom’s railway network of heat-related delays and buckles caused by the predicted increase in high summer temperatures owing to climate change. Proc. Inst. Mech. Eng. Part F J. Rail Rapid Transit 2010, 224, 25–34. [Google Scholar] [CrossRef]
- Argyroudis, S.; Kaynia, A.M. Analytical seismic fragility functions for highway and railway embankments and cuts. Earthq. Eng. Struct. Dyn. 2015, 44, 1863–1879. [Google Scholar] [CrossRef]
- Nielsen, J.C.O.; Li, X. Railway track geometry degradation due to differential settlement of ballast/subgrade – Numerical prediction by an iterative procedure. J. Sound Vib. 2018, 412, 441–456. [Google Scholar] [CrossRef]
- Lamb, R.; Aspinall, W.; Odbert, H.; Wagener, T. Vulnerability of bridges to scour: Insights from an international expert elicitation workshop. Nat. Hazards Earth Syst. Sci. 2017, 17, 1393–1409. [Google Scholar] [CrossRef] [Green Version]
- Jamshidi, A.; Faghih-Roohi, S.; Núñez, A.; Babuska, R.; Schutter, B.D.; Dollevoet, R.; Li, Z. Probabilistic defect-based risk assessment approach for rail failures in railway infrastructure. IFAC PapersOnLine 2016, 49, 73–77. [Google Scholar] [CrossRef]
- Ghodrati, B.; Famurewa, S.; Hoseinie, S.H. Railway switches and crossings reliability analysis. In Proceedings of the IEEE International Conference on Industrial Engineering and Engineering Management (IEEM), Bali, Indondesia, 4–7 December 2016; pp. 1412–1416. [Google Scholar]
- Pams Capoccioni, C.; Nivon, D.; Amblard, J.; De Cesare, G.; Ghilardi, T.; Jafarnejad, M.; Battisacco, E. Analysis of ballast transport in the event of overflowing of the drainage system on high speed lines. La Houille Blanche 2015, 4, 39–45. [Google Scholar] [CrossRef]
- Ferdous, W.; Manalo, A. Failures of mainline railway sleepers and suggested remedies—Review of current practice. Eng. Fail. Anal. 2014, 44, 17–35. [Google Scholar] [CrossRef]
- Remennikov, A.M.; Kaewunruen, S. Experimental load rating of aged railway concrete sleepers. Eng. Struct. 2014, 76, 147–162. [Google Scholar] [CrossRef] [Green Version]
- Zerbst, U.; Beretta, S. Failure and damage tolerance aspects of railway components. Eng. Fail. Anal. 2011, 18, 534–542. [Google Scholar] [CrossRef]
- Malm, R.; Andersson, A. Field testing and simulation of dynamic properties of a tied arch railway bridge. Eng. Struct. 2006, 28, 143–152. [Google Scholar] [CrossRef]
- Park, J.; Towashiraporn, P. Rapid seismic damage assessment of railway bridges using the response-surface statistical model. Struct. Saf. 2014, 47, 1–12. [Google Scholar] [CrossRef]
- An, M.; Huang, S.; Baker, C.J. Railway risk assessment—the fuzzy reasoning approach and fuzzy analytic hierarchy process approaches: A case study of shunting at Waterloo depot. Proc. Inst. Mech. Eng. Part F J. Rail Rapid Transit 2007, 221, 365–383. [Google Scholar] [CrossRef]
- Dick, T.C.; Barkan, C.P.L.; Chapman, E.R.; Stehly, M.P. Multivariate statistical model for predicting occurrence and location of broken rails. Transp. Res. Rec. J. Transp. Res. Board 2003, 1825, 48–55. [Google Scholar] [CrossRef] [Green Version]
- Sussmann, T.R.; Ruel, M.; Chrismer, S.M. Source of ballast fouling and influence considerations for condition assessment criteria. Transp. Res. Rec. J. Transp. Res. Board 2012, 2289, 87–94. [Google Scholar] [CrossRef]
- Holický, M.; Marková, J.; Sýkora, M. Forensic assessment of a bridge downfall using Bayesian networks. Eng. Fail. Anal. 2013, 30, 1–9. [Google Scholar] [CrossRef]
- Benn, J. Railway bridge failure during flooding in the UK and Ireland. Proc. Inst. Civ. Eng. Forensic Eng. 2013, 166, 163–170. [Google Scholar] [CrossRef]
- Liu, X.; Saat, M.R.; Barkan, C.P.L. Analysis of causes of major train derailment and their effect on accident rates. Transp. Res. Rec. J. Transp. Res. Board 2012, 2289, 154–163. [Google Scholar] [CrossRef]
- Dinh, V.N.; Kim, K.D.; Warnitchai, P. Dynamic analysis of three-dimensional bridge–high-speed train interactions using a wheel–rail contact model. Eng. Struct. 2009, 31, 3090–3106. [Google Scholar] [CrossRef]
- Barkan, C.P.L.; Dick, T.C.; Anderson, R.T. Railroad derailment factors affecting hazardous materials transportation risk. Transp. Res. Rec. J. Transp. Res. Board 2003, 1825, 64–74. [Google Scholar] [CrossRef]
- Liu, X.; Barkan, C.P.L.; Saat, M.R. Analysis of derailments by accident cause. Transp. Res. Rec. J. Transp. Res. Board 2011, 2261, 178–185. [Google Scholar] [CrossRef] [Green Version]
- Jafarian, E.; Rezvani, M.A. Application of fuzzy fault tree analysis for evaluation of railway safety risks: An evaluation of root causes for passenger train derailment. Proc. Inst. Mech. Eng. Part F J. Rail Rapid Transit 2012, 226, 14–25. [Google Scholar] [CrossRef]
- Liu, X. Statistical temporal analysis of freight train derailment rates in the United States. Transp. Res. Rec. J. Transp. Res. Board 2015, 2476, 119–125. [Google Scholar] [CrossRef]
- Liu, X.; Saat, M.R.; Barkan, C.P.L. Freight-train derailment rates for railroad safety and risk analysis. Accid. Anal. Prev. 2017, 98, 1–9. [Google Scholar] [CrossRef]
- Chen, D. Derailment risk due to coupler jack-knifing under longitudinal buff force. Proc. Inst. Mech. Eng. Part F J. Rail Rapid Transit 2010, 224, 483–490. [Google Scholar] [CrossRef]
- Evans, A.W. Estimating transport fatality risk from past accident data. Accid. Anal. Prev. 2003, 35, 459–472. [Google Scholar] [CrossRef]
- Zhao, W.; Martin, U.; Cui, Y.; Liang, J. Operational risk analysis of block sections in the railway network. J. Rail Transp. Plan. Manag. 2017, 7, 245–262. [Google Scholar]
- Corman, F. Interactions and equilibrium between rescheduling train traffic and routing passengers in microscopic delay management: A game theoretical study. Transp. Sci. 2020, 54, 785–822. [Google Scholar] [CrossRef]
- Ćirović, G.; Pamučar, D. Decision support model for prioritizing railway level crossings for safety improvements: Application of the adaptive neuro-fuzzy system. Expert Syst. Appl. 2013, 40, 2208–2223. [Google Scholar] [CrossRef]
- Morcous, G.; Lounis, Z. Maintenance optimization of infrastructure networks using genetic algorithms. Autom. Constr. 2005, 14, 129–142. [Google Scholar] [CrossRef]
- Burkhalter, M.; Adey, B.T. A Network flow model approach to determining optimal intervention programs for railway infrastructure networks. Infrastructures 2018, 3, 31. [Google Scholar] [CrossRef] [Green Version]
- Burkhalter, M.; Adey, B.T. Determining optimal intervention programs for large railway infrastructure networks using a genetic algorithm. In Proceedings of the 12th World Congress on Railway Research, Tokio, Japan, 28 October–1 November 2019. [Google Scholar]
- Guler, H. Decision support system for railway track maintenance and renewal management. J. Comput. Civ. Eng. 2013, 27, 292–306. [Google Scholar] [CrossRef]
- Gaudry, M.; Lapeyre, B.; Quinet, É. Infrastructure maintenance, regeneration and service quality economics: A rail example. Transp. Res. Part B Methodol. 2016, 86, 181–210. [Google Scholar] [CrossRef] [Green Version]
- Azad, N.; Hassini, E.; Verma, M. Disruption risk management in railroad networks: An optimization-based methodology and a case study. Transp. Res. Part B Methodol. 2016, 85, 70–88. [Google Scholar] [CrossRef]
- Jaiswal, P.; Van Westen, C.J.; Jetten, V. Quantitative assessment of landslide hazard along transportation lines using historical records. Landslides 2011, 8, 279–291. [Google Scholar] [CrossRef]
- Bemment, S.D.; Goodall, R.M.; Dixon, R.; Ward, C.P. Improving the reliability and availability of railway track switching by analysing historical failure data and introducing functionally redundant subsystems. Proc. Inst. Mech. Eng. Part F J. Rail Rapid Transit 2018, 232, 1407–1424. [Google Scholar] [CrossRef] [PubMed] [Green Version]
- Bartram, D.; Burrow, M.P.N.; Yao, X. A computational intelligence approach to railway track intervention planning. In Studies in Computational Intelligence; Yu, T., Davis, L., Baydar, C., Roy, R., Eds.; Springer: Berlin/Heidelberg, Germany, 2008; pp. 163–198. [Google Scholar]
- Jaroszweski, D.; Fu, Q.; Easton, J. A data model for heat-related rail buckling: Implications for operations, maintenance and long-term adaptation. In Proceedings of the 12th World Congress on Railway Research, Tokyo, Japan, 28 October–1 November 2019. [Google Scholar]
- Jamshidi, A.; Faghih-Roohi, S.; Hajizadeh, S.; Núñez, A.; Babuska, R.; Dollevoet, R.; Schutter, B.D. A big data analysis approach for rail failure risk assessment. Risk Anal. 2017, 37, 1495–1507. [Google Scholar] [CrossRef] [PubMed] [Green Version]
- Santamaria, J.; Vadillo, E.G.; Gomez, J. Influence of creep forces on the risk of derailment of railway vehicles. Veh. Syst. Dyn. 2009, 47, 721–752. [Google Scholar] [CrossRef] [Green Version]
- Bana e Costa, C.; Oliveira, C.; Vieira, V. Prioritization of bridges and tunnels in earthquake risk mitigation using multicriteria decision analysis: Application to Lisbon. Omega 2008, 36, 442–450. [Google Scholar] [CrossRef]
- Zhao, J.; Chan, A.H.C.; Burrow, M.P.N. Probabilistic model for predicting rail breaks and controlling risk of derailment. Transp. Res. Rec. J. Transp. Res. Board 2007, 1995, 76–83. [Google Scholar] [CrossRef]
- Podofillini, L.; Zio, E.; Vatn, J. Risk-informed optimisation of railway tracks inspection and maintenance procedures. Reliab. Eng. Syst. Saf. 2006, 91, 20–35. [Google Scholar] [CrossRef]
- Aven, T. Misconceptions of Risk; John Wiley & Sons: Chichester, UK, 2010. [Google Scholar]
- Scholten, L.; Schuwirth, N.; Reichert, P.; Lienert, J. Tackling uncertainty in multi-criteria decision analysis—An application to water supply infrastructure planning. Eur. J. Oper. Res. 2015, 242, 243–260. [Google Scholar] [CrossRef] [Green Version]
- Patra, A.P.; Söderholm, P.; Kumar, U. Uncertainty estimation in railway track life-cycle cost: A case study from Swedish National Rail Administration. Proc. Inst. Mech. Eng. Part F J. Rail Rapid Transit 2009, 223, 285–293. [Google Scholar] [CrossRef]
- Washington, S.P.; Oh, J. Bayesian methodology incorporating expert judgment for ranking countermeasure effectiveness under uncertainty: Example applied to at grade railroad crossings in Korea. Accid. Anal. Prev. 2006, 38, 234–247. [Google Scholar] [CrossRef] [PubMed]
- Wang, L.; An, M.; Qin, Y.; Jia, L.M. A risk-based maintenance decision-making approach for railway asset management. Int. J. Softw. Eng. Knowl. Eng. 2018, 28, 453–483. [Google Scholar] [CrossRef]
- Hohl, M.; Brem, S.; Balmer, J.; Schulze, T.; Holthausen, N.; Vermeulen, E.; Bohnenblust, H.; Zulauf, C. A Method for Risk Analysis of Disasters and Emergencies in Switzerland; Federal Office for Civil Protection: Bern, Switzerland, 2013. [Google Scholar]
- Braband, J.; Schäbe, H. Propagation of uncertainty in railway signaling risk analysis. In Safety and Reliability of Complex Engineered Systems; CRC Press: Zurich, Switzerland, 2015; pp. 2623–2626. [Google Scholar]
- Rama, D.; Andrews, J.D. A reliability analysis of railway switches. Proc. Inst. Mech. Eng. Part F J. Rail Rapid Transit 2013, 227, 344–363. [Google Scholar] [CrossRef]
- Quiroga, L.M.; Schnieder, E. Monte Carlo simulation of railway track geometry deterioration and restoration. Proc. Inst. Mech. Eng. Part O J. Risk Reliab. 2012, 226, 274–282. [Google Scholar] [CrossRef]
- Ghazel, M. Using stochastic petri nets for level-crossing collision risk assessment. IEEE Trans. Intell. Transp. Syst. 2009, 10, 668–677. [Google Scholar] [CrossRef]
- Macciotta, R.; Martin, C.D.; Morgenstern, N.R.; Cruden, D.M. Quantitative risk assessment of slope hazards along a section of railway in the Canadian Cordillera—A methodology considering the uncertainty in the results. Landslides 2016, 13, 115–127. [Google Scholar] [CrossRef]
- Andrews, J.D. A modelling approach to railway track asset management. Proc. Inst. Mech. Eng. Part F J. Rail Rapid Transit 2013, 227, 56–73. [Google Scholar] [CrossRef]
- Patra, A.P. Maintenance Decision Support Models for Railway Infrastructure Using RAMS & LCC Analyses. Ph.D. Thesis, Luleå University of Technology, Luleå, Sweden, 2009. [Google Scholar]
- Andrade, A.R. Renewal decisions from a Life-cycle Cost (LCC) Perspective in Railway Infrastructure: An integrative Approach Using Separate LCC Models for Rail and Ballast Components. Ph.D. Thesis, Universidade Técnica de Lisboa, Lisbon, Portugal, 2008. [Google Scholar]
- Andrews, J.D.; Prescott, D.; De Rozières, F. A stochastic model for railway track asset management. Reliab. Eng. Syst. Saf. 2014, 130, 76–84. [Google Scholar] [CrossRef]
- Feng, D.; He, Z.; Lin, S.; Wang, Z.; Sun, X. Risk index system for catenary lines of high-speed railway considering the characteristics of time–space differences. IEEE Trans. Transp. Electrif. 2017, 3, 739–749. [Google Scholar] [CrossRef]
- Qiu, S.; Sallak, M.; Schön, W.; Cherfi-Boulanger, Z. Availability assessment of railway signalling systems with uncertainty analysis using Statecharts. Simul. Model. Pract. Theory 2014, 47, 1–18. [Google Scholar] [CrossRef]
- Bickel, P.; Friedrich, R. ExternE: Externalities of Energy: Methodology 2005 Update; Office for Official Publications of the European Communities: Luxembourg, 2005. [Google Scholar]
- Wheat, P.; Smith, A.S.J.; Nash, C. CATRIN (Cost Allocation of TRansport INfrastructure cost), Deliverable 8—Rail Cost Allocation for Europe; Sixth Framework Programme: Stockholm, Sweden, 2009. [Google Scholar]
- Barker, K.; Haimes, Y.Y. Uncertainty analysis of interdependencies in dynamic infrastructure recovery: Applications in risk-based decision making. J. Infrastruct. Syst. 2009, 15, 394–405. [Google Scholar] [CrossRef]
- Cholette, M.E.; Ma, L.; Buckingham, L.; Allahmanli, L.; Bannister, A.; Xie, G. A Decision support framework for prioritization of engineering asset management activities under uncertainty. In Proceedings of the World Congress on Engineering Asset Management (WCEAM), Pretoria, South Africa, 28–31 October 2014; pp. 49–60. [Google Scholar]
- Zampetakis, L.A.; Moustakis, V.S. Quantifying uncertainty in ranking problems with composite indicators: A Bayesian approach. J. Model. Manag. 2010, 5, 63–80. [Google Scholar] [CrossRef]
- Ellis, J.; Smith, E.; Spouge, J. Research on Risk models at European Level—Final Report; Det Norske Verital Limited (DNV GL): London, UK, 2016. [Google Scholar]
- Papathanasiou, N.; Adey, B.T. Usefulness of quantifying effects on rail service when comparing intervention strategies. Infrastruct. Asset Manag. 2020, 1–20. [Google Scholar] [CrossRef] [Green Version]
- Hudson, W.; Haas, R.; Uddin, W. Infrastructure Management: Integrating Design, Construction, Maintenance, Rehabilitation, and Renovation; McGraw-Hill: New York, NY, USA, 1997. [Google Scholar]
- Adey, B.T.; Hajdin, R.; Brühwiler, E. Supply and demand system approach to development of bridge management strategies. J. Infrastruct. Syst. 2003, 9, 117–131. [Google Scholar] [CrossRef]
- Adey, B.T.; Martani, C.; Papathanasiou, N.; Burkhalter, M. Estimating and communicating the risk of neglecting maintenance. Infrastruct. Asset Manag. 2019, 6, 109–128. [Google Scholar] [CrossRef] [Green Version]
- Spearman, C. The proof and measurement of association between two things. Am. J. Psychol. 1904, 15, 72. [Google Scholar] [CrossRef]
- Kumar, R.; Vassilvitskii, S. Generalized distances between rankings. In Proceedings of the 19th International Conference on World Wide Web (WWW), New York, NY, USA, 26–30 April 2010; p. 571. [Google Scholar]
- National Transport Authority. National Heavy Rail Census; National Transport Authority: Dublin, Ireland, 2019. [Google Scholar]
- ISO. Guide 73: Risk Management—Vocabulary; ISO copyright office: Geneva, Switzerland, 2009. [Google Scholar]
- ISO. ISO 31010—Risk Management—Risk Assessment Techniques; ISO copyright office: Geneva, Switzerland, 2009. [Google Scholar]
- Papathanasiou, N.; Adey, B.T. Making comparable risk estimates for railway assets of different types. Infrastruct. Asset Manag. 2020. (under review). [Google Scholar]
- Adey, B.T.; Hajdin, R.; Brühwiler, E. Effect of common cause failures on indirect costs. J. Bridg. Eng. 2004, 9, 200–208. [Google Scholar] [CrossRef]
- Bukhsh, Z.A.; Stipanovic, I.; Connolly, L.; Adey, B.; Papathanasiou, N.; Gavin, K.; Martinovic, C.; Ramdas, V.; Barett, A.; Schoebel, A. Report on Decision Support Tool; DESTination RAIL Deliverable D3.3: Enschede, The Netherlands, 2017. [Google Scholar]
- Connolly, L.; O’Connor, A.J. Guideline for Probability Based Multi Criteria Performance Optimisation of Railway Infrastructure; DESTination RAIL Deliverable 2.1: Dublin, Ireland, 2017. [Google Scholar]
- Barrett, A.; Ramdas, V. Report on the Network Whole Cost Model; DESTination RAIL Deliverable D4.3: Wokingham, UK, 2018. [Google Scholar]
- Papathanasiou, N.; Adey, B.T.; Burkhalter, M. Risk Assessment Methodology; DESTination RAIL Deliverable D3.6: Brussels, Belgium, 2018. [Google Scholar]
- Aksentijevic, J.; Blieberger, J.; Stefan, M.; Schöbel, A. Report on Traffic Flow Model; DESTination RAIL Deliverable D4.2: Vienna, Austria, 2017. [Google Scholar]
- Stenström, C.; Norrbin, P.; Parida, A.; Kumar, U. Preventive and corrective maintenance—Cost comparison and cost–benefit analysis. Struct. Infrastruct. Eng. 2016, 12, 603–617. [Google Scholar] [CrossRef]
- Ghofrani, F.; He, Q.; Goverde, R.M.P.; Liu, X. Recent applications of big data analytics in railway transportation systems: A survey. Transp. Res. Part C Emerg. Technol. 2018, 90, 226–246. [Google Scholar] [CrossRef]
- Neuhold, J.; Landgraf, M. From data-based condition analysis to sophisticated asset management for railway tracks. In Proceedings of the 12th World Congress on Railway Research, Tokyo, Japan, 28 October–1 November 2019. [Google Scholar]
- Lu, C.-L.; Lai, Y.-C. Optimal rail system design with multiple layers of fault and event trees. J. Transp. Saf. Secur. 2019, 1–22. [Google Scholar] [CrossRef]
- Lidén, T. Railway Infrastructure Maintenance—A Survey of Planning Problems and Conducted Research. Transp. Res. Procedia 2015, 10, 574–583. [Google Scholar] [CrossRef] [Green Version]
- You, X.; Tonon, F. Event tree and fault tree analysis in tunneling with imprecise probabilities. In Proceedings of the GeoCongress, Oakland, CA, USA, 25–29 March 2012; pp. 2885–2894. [Google Scholar]
- Sadler, J.; Kit, O.; Austin, J.; Griffin, D. A tool to predict environmental risk to UK rail infrastructure. Proc. Inst. Civ. Eng. Transp. 2018, 171, 115–124. [Google Scholar] [CrossRef]
Assets | Net Benefit | Rank | Weight of Position Change | Position Weight |
---|---|---|---|---|
Equation (1) | Equation (5) | Equation (5) | ||
a1 | 100 | 1 | 1.00 | 0.0 |
a2 | 20 | 2 | 0.47 | 1.0 |
a3 | 0 | 3 | 0.33 | 1.5 |
a4 | −50 | 4 | 0.00 | 1.8 |
Assets | Net Benefit | Rank | No. of Position Changes | Position Weight | No. of Weighted Position Changes |
---|---|---|---|---|---|
Equation (1) | Equation (2) | Equation (5) | Equation (3) | ||
a1 | 120 | 2 | 1 | 1.0 | 1.00 |
a2 | 150 | 1 | 1 | 0.0 | 1.00 |
a3 | 50 | 3 | 0 | 1.5 | 0.00 |
a4 | 0 | 4 | 0 | 1.8 | 0.00 |
Sum | 2 | 2.00 |
Assets | Net Benefit | Rank | No. of Position Changes | Position Weight | No. of Weighted Position Changes |
---|---|---|---|---|---|
Equation (1) | Equation (2) | Equation (5) | Equation (3) | ||
a1 | 150 | 1 | 0 | 0.0 | 0.0 |
a2 | 120 | 2 | 0 | 1.0 | 0.0 |
a3 | 50 | 4 | 1 | 1.8 | 0.6 |
a4 | 100 | 3 | 1 | 1.5 | 0.6 |
Sum | 2 | 1.11 |
Type | Notation | Description | Example of Event Used in the Case Study for the Track Section T1 1 |
---|---|---|---|
Hazard | h | An event that may lead to a change in the load and stress level applied on a railway asset | Traffic |
Load | le | An event that may change the load and stress levels applied on a railway asset | Annual tonnage on the track section T1 based on the timetable (1043 trains during a weekday and 318 trains during the weekend) |
Infrastructure | ie | An event that may change the structural or functional properties of a railway asset | Damages that partially affect the geometry or the rail condition of the track section T1 |
Network use | ne | An event that may change the level at which the railway network is used | The operation of the track section T1 is possible only when the speed is less than 40 km/h |
Societal | se | An event that may change the level of the railway service provided to the stakeholders | Track section T1 is renewed, and its operation is possible only when the speed is less than 40 km/h until the renewal is complete |
Variable | Value Depends on | Description | Estimates | ||
---|---|---|---|---|---|
Best | Low | High | |||
Probability of load event (P[Fle]) | Asset type (g) and the hazards (TR or NH) considered | Probability of annual traffic tonnage based on the timetable to be applied on a track section of type 1 | 1 | 0.8 | 1 |
Probability of infrastructure event (P[Fie]) | Asset type (g), the state of the asset (o) and the hazards (TR or NH) considered | Probability of minor damage to occur on a metal bridge in state 4 due to traffic loads | 0.00005 | 0.00004 | 0.00006 |
Probability of network use event (P[Fne]) | Probability of closure of a block section due to a switch being severed damaged from extreme heat | 0.8 | 0.64 | 1 | |
Probability of societal event (P[Fse]) | Asset type (g) and the state of the asset (o) | Probability of accident to occur due to severe damage of a track section of type 1 in state 3 due to traffic | 0.8 | 0.76 | 0.84 |
Cost of restoration intervention (CQI) | Asset type (g) and the type of restoration intervention (QI) | Renewal of 1 m track section of type 1 to restore it after damage | €1200 | €1080 | €1320 |
Cost of risk-reducing intervention (Ci|k) | Asset type (g) and the risk-reducing intervention (k) | Renewal of 1 m track section of type 1 to reduce the risk | €1200 | €1080 | €1320 |
Cost of site restoration (CQS) | Asset type (g) and the restoration work due to damages or accidents at the site (QS) | Cost of site restoration after severe damage of a switch | €4000 | €2000 | €12,000 |
Duration of traffic restriction due to intervention (DDI) | Asset type (g), the type of restoration (QI) or risk-reducing (k) intervention and the traffic restrictions (D) considered | Duration in hours of speed restriction due to the renewal of 1 m of a type 1 track section | 168 | 168 | 168 |
Variable | Value Depends on | Description | Estimates | ||
---|---|---|---|---|---|
Best | Low | High | |||
Duration of traffic restriction due to site restoration (DDQS) | Asset type (g), the restoration work due to damages or accidents at the site (QS) and the traffic restrictions (D) considered due to the intervention the asset type (g), damages or accidents at the site (QS) | Duration in hours of closure due to site restoration after the failure of a concrete bridge | 120 | 30 | 360 |
Number of fatalities and injuries (Z) | Asset type (g), the type of restoration (QI) or risk-reducing (k) intervention | Number of fatalities due to an accident occurring by minor damage of a switch | 0.027 | 0.023 | 0.034 |
Cost of the environmental impact of interventions (Ce|I) | Cost of the environmental impact of executing a minor restoration on 1m of type 1 track section | €10 | €5 | €20 | |
Cost of the environmental impact of site restoration (CE|QS) | Asset type (g), the restoration work due to damages or accidents at the site (QS) | Cost of the environmental impact of site restoration due to failure of 1m of type 1 track section | €29 | €24 | 39 |
Asset dimensions (l) | Asset ID (a) | Deck surface area in m2 of bridge B1 | 720 | 718 | 722 |
Additional travel time (DT) | Asset ID (a), and the traffic restrictions (D) considered | Cumulative additional travel time in minutes due to one-hour closure of the block sections where switch S1 is located during a day in the weekday | 4735 | 3788 | 9470 |
The unit cost of time (ut) | Location of the network (v) | Cost of one minute of delay in Dublin | €0.515 | €0.34 | €1.03 |
The unit cost of fatalities and injuries (UZ) | Location of the network (v) | Cost of one fatality in Dublin | €1.5 million | €1 million | €3 million |
Variable | No. of Position Changes in the Ranking due to the Use of | |||||
---|---|---|---|---|---|---|
Low Estimates | High Estimates | Skewed Normal Distributions of Estimates | ||||
Without (w/o) Weights | Weighted | W/o Weights | Weighted | W/o Weights | Weighted | |
Probability of load event (P[Fle]) | 8 | 18 | 0 | 0 | 3 | 5 |
Probability of infr. event (P[Fie]) | 118 | 19 | 64 | 4 | 41 | 10 |
Probability of network use event (P[Fne]) | 202 | 84 | 68 | 59 | 71 | 27 |
Probability of societal event (P[Fse]) | 228 | 106 | 108 | 43 | 110 | 53 |
Cost of restoration int. (CQI) | 32 | 52 | 8 | 18 | 12 | 20 |
Cost of risk-reducing int. (Ci|k) | 32 | 52 | 8 | 18 | 12 | 20 |
Cost of site restoration (CQS) | 8 | 15 | 116 | 257 | 22 | 48 |
Duration of traffic restriction due to int. (DDI) | 0 | 0 | 28 | 49 | 10 | 17 |
Variable | No. of Position Changes in the Ranking due to the Use of | |||||
---|---|---|---|---|---|---|
Low Estimates | High Estimates | Skewed Normal Distributions of Estimates | ||||
W/o Weights | Weighted | W/o Weights | Weighted | W/o Weights | Weighted | |
Duration of traffic restriction due to site restoration (DDQS) | 0 | 0 | 16 | 31 | 2 | 8 |
Number of fatalities and injuries (Z) | 84 | 218 | 72 | 4 | 30 | 41 |
Cost of the environmental impact of int. (Ce|I) | 16 | 31 | 0 | 0 | 6 | 11 |
Cost of the environmental impact of site restoration (CE|QS) | 0 | 0 | 0 | 0 | 0 | 0 |
Asset dimensions (l) | 16 | 31 | 0 | 0 | 6 | 11 |
Additional travel time (DT) | 310 | 161 | 107 | 232 | 41 | 73 |
Unit cost of time (ut) | 18 | 11 | 84 | 237 | 19 | 43 |
Unit cost of fatalities and injuries (UZ) | 36 | 68 | 108 | 38 | 54 | 36 |
© 2020 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (http://creativecommons.org/licenses/by/4.0/).
Share and Cite
Papathanasiou, N.; Adey, B.T. Identifying the Input Uncertainties to Quantify When Prioritizing Railway Assets for Risk-Reducing Interventions. CivilEng 2020, 1, 106-131. https://doi.org/10.3390/civileng1020008
Papathanasiou N, Adey BT. Identifying the Input Uncertainties to Quantify When Prioritizing Railway Assets for Risk-Reducing Interventions. CivilEng. 2020; 1(2):106-131. https://doi.org/10.3390/civileng1020008
Chicago/Turabian StylePapathanasiou, Natalia, and Bryan T. Adey. 2020. "Identifying the Input Uncertainties to Quantify When Prioritizing Railway Assets for Risk-Reducing Interventions" CivilEng 1, no. 2: 106-131. https://doi.org/10.3390/civileng1020008
APA StylePapathanasiou, N., & Adey, B. T. (2020). Identifying the Input Uncertainties to Quantify When Prioritizing Railway Assets for Risk-Reducing Interventions. CivilEng, 1(2), 106-131. https://doi.org/10.3390/civileng1020008