Additional Costs of Public Works Contracts in Portugal—Descriptive Statistical Analysis in Light of the Quality of Information
Abstract
:1. Introduction
2. Materials and Methods
- (a)
- Obtain publicly accessible data.
- (b)
- Construction of a descriptive statistical analysis of the data obtained.
- (c)
- Analysis and evaluation of extracted information.
- (d)
- Proposal for improvement and quality of information.
3. Case Studies
Database
- The public contracts portal is intended to disseminate public information about public contracts subject to the Public Contracts Code regime.
- The public procurement portal also constitutes the central instrument for producing statistical information on national public procurement, particularly for the purposes of preparing statistical reports to be sent to the European Commission.
- The operating and management rules of the public contracts portal are approved by the order of the members of the Government responsible for the areas of finance and public works.
- Type of procedure: All.
- Type of contract: Among the research options are the acquisition of real estate, the concession of public works, the concession of public services, the leasing of movable assets and, finally, the interest of this study: PUBLIC WORKS CONTRACTS.
- Price: There are only two options in this cell: effective and contractual price. The use of the contractual price was due to the possibility of a detailed analysis of the data, with the works divided according to the definition contained in Table 1, in which the types of procedure, except for permitted exceptions, are limited by the base price values. Therefore, following this same logic, we also decided to obtain the following data from the stratification defined in the CCP:
- (a)
- Public works with a contractual price of up to EUR 30,000.00.
- (b)
- Public works with a contractual price of EUR 30,000.00 to EUR 150,000.00.
- (c)
- Public works with a contractual price of EUR 150,000.00 to EUR 5,350,000.00.
- (d)
- Public works with a contractual price above EUR 5,350,000.00.
- Dates: Options include contract date, publication date and closing date. The closing date (understood as the date of payment of the last invoice accepted by the public contractor) was chosen as the objective is to analyse completed works. Works with a closing date between 1 January 2022 and 31 December 2022 were defined, that is, works with a closing date in the year 2022.
- Finally, there is the execution location, where the option of country, district and municipality can be inserted. We chose to define only the country (PORTUGAL) since the file extracted from the research contains district and municipality information.
- Object of the contract.
- Type of procedure.
- CPV contract types.
- COGS Type.
- COGS Designation.
- COGS Value.
- Contracting entity(ies).
- Contracting entity(ies).
- Contract price.
- Publication date.
- Date of conclusion of the contract.
- Lead time.
- Place of execution.
- Rationale.
- Cause of contract termination.
- Contract closing date.
- Effective total price.
- Reason for changing the deadline.
- Causes of price change.
- State.
- Framework agreement registration number.
- Description of the framework agreement.
- Centralized procedure.
- Link to procedure parts.
- List of suppliers (contractors).
- Acquisition under the framework agreement of another EU Member State.
- Special Measures.
- Regime.
- Material Criteria.
- CCP.
- Group Members.
- The object of the contract only provides the name of the work; therefore, it cannot contribute to statistical analysis.
- The group CPV contract types, CPV Type, CPV Designation and CPV Value were also excluded since the CPVs analysed correspond indiscriminately to a global presentation for different objects.
- Contracting entity and Contracting entity were also omitted from the data since for each district, there is a considerable number of entities. Therefore, depending on the filters used, for a meaningful analysis, the sample size of the same entity (contractor or adjudicator) would not be sufficient to endorse a correct interpretation of the data. In this case, we chose to use the district as a discrete variable.
- The date of publication and the date of signing the contract are similar data. In this case, we chose to analyse only the information on the date of signing the contract.
- The justification is also excluded since for all data, there is the information: “Article 19, paragraph (d) of the Public Contracts Code”. In other words, it deals with the basis for choosing the procedure for forming public works contracts.
- The initial filter that conditions the presentation of results only for works with a closing date in the year 2022 presupposes the presentation of only completed works. Therefore, the cause for the termination of the contract for all data is “Full compliance with the contract”, which is why this column was also deleted.
- As the contract closing date is 2022 for all data, this information was also excluded.
- The causes of term and price changes, according to the model presented by the base portal, are qualitative information, with general and global descriptions. Therefore, it could not be used in the analysis.
- In the files extracted from the base portal, the Status column does not contain any information, so there is nothing to analyse.
- In the columns Registration number of the framework agreement and Description of the framework agreement, for works that do not derive from a framework agreement, the text “not applicable” is filled in. In turn, when dealing with a procedure derived from a framework agreement, the first column has an identification number, while the second has an explanatory text about the contracted object. The types of procedures already contain information according to the framework; therefore, these columns do not contain data that can be statistically analysed.
- The existence of centralized procedures or not and the correlation analysis with the occurrence of additional costs could be carried out. However, in the centralized procedures column, all data appear as “FALSE”.
- The Link to procedure parts column, when completed, has a link with the electronic address to access information about the procedure. This information was not connected to the statistical analysis.
- The Supplier List column has all data filled in as “FALSE”.
- The Acquisition under the framework agreement of another EU member state column is not completed.
- Special measures, in most cases, are not completed. When completed, the source of origin of the resources is described, such as Projects Financed or Co-financed by European funds or the Recovery and Resilience Plan—PRR.
- The data in the Regime column only contains the information that it is the Public Contracts Code Regime.
- Material Criteria, in turn, are fulfilled, with very rare exceptions as false for all data.
- The CCP column has true and false options; practically all data have the FALSE option. The purpose of this information is unclear, which is why it was also deleted.
- Finally, the group members column does not contain any information, that is, no data are provided in this column.
- Base price: The base portal does not present a column with this information, so it was necessary to access each work individually and check the base price value. Not all procedures were able to identify such information.
- Deviation from the base price and percentage of deviation from the base price corresponds to the difference between the base price and the contractual price. These data are important as they may indicate greater or lesser differences between the predicted price and the actually contracted price and may highlight occurrences of price deviations in public works. A company can, hypothetically, as a competition strategy, reduce the proposal for the work with the aim of winning the competition. However, this relies on the subsequent incidence of additional costs to cover the differences in the initial proposal.
- Price deviation and percentage of price deviation: This information is the most important in the analysis, as it derives from the difference between the total effective price and the contractual price. Whenever this difference is positive, it indicates that the work had a higher cost than that initially contracted. Likewise, negative results mean the prevalence of less work during the execution of the contract. A positive or negative result of this equation does not mean that there was no more work, less work or price revision, it just means that there was a prevalence of one of these elements in relation to the others. The base portal does not identify individual cost elements, only the final value of the work.
- Regarding the deadlines for the work, the date of signing the contract, the execution period in days and the closing date of the work are included. The latter does not refer to the end of the work, just the date of payment of the last invoice. The base portal does not indicate whether there has been a deviation from deadlines, it only allows those responsible for transmitting information to freely describe the occurrence of a deadline deviation and the cause of this deviation in the same cell. Therefore, to approximate information about the end of the work, we agree to call it the administrative execution of the contract, which is the result of the equation of the closing date minus the date of signing the contract. This result indicates how many days the administrative execution of the contract takes.
- Knowing the number of days of administrative execution of the contract minus the deadline for carrying out the work, it was possible to obtain a deviation from the deadline for the work. It is important to highlight that this is not a real deviation, as we do not know the start date of the work, which is not the same as the date of signing the contract and, in the same way, we do not know the end date of the work, which coincides with the date of provisional reception of the work. Therefore, the deadline deviation discussed here is only an indication of the time elapsed between the administrative execution of the work and the execution deadline.
- Type of procedure.
- District.
- Base price.
- Contract price.
- Deviation from base price: (Base price—Contract price).
- Percentage of deviation from the base price: (Base price—Contract price)/Base price.
- Effective total price.
- Price deviation: (Total effective price—contractual price).
- Percentage of price deviation: (Total effective price—Contract price)/Contract price.
- Date of conclusion of the contract.
- Contract closing date (year)
- Execution time (days).
- Administrative execution of the contract (days): (Contract closing date—Contract conclusion date).
- Deviation of deadline (days): (Administrative execution of the contract—Execution period).
- Percentage of deadline deviation: (Administrative execution of the contract—Execution deadline)/Execution deadline.
4. Results
4.1. Continuous Variables
4.2. Discrete Variables
4.3. Descriptive Statistical Analysis
5. Data Limitations and Improvement Proposals
- ✓
- How many works were carried out through division into lots?
- ✓
- What was the value of additional works for construction in Portugal?
- ✓
- What were the values of additional works carried out by a specific public entity, contractor or designer?
- ✓
- How much less work was carried out by a given public entity, contractor or designer?
- ✓
- What price review values were paid in Portugal?
- ✓
- What method was used in the price review?
- ✓
- How many works used the auction mechanism?
- ✓
- How many works used the negotiation mechanism?
- ✓
- How many works have a deadline deviation?
- ✓
- What is the average value in the number of days of deadline deviation?
- ✓
- How many works were diverted in a given district?
- ✓
- Which district had the highest number of cost and deadline deviations?
- ✓
- How many projects were not provided with a deposit and what was the reason?
- ✓
- How many works were carried out with mixed contracts?
- ✓
- How many and which procedures used the participation system for micro and small companies?
- ✓
- Was the execution of the work suspended? Partial or total? What is the justification?
- ✓
- Was there an extension of the deadline for the execution of the work? For how many days? What is the justification?
- ✓
- Were contractual sanctions applied? What is the justification? Who was responsible for the payment?
- ✓
- What was the base price of the work?
- ✓
- Was the winning proposal part of a group of entities?
- ✓
- Were there any plans for reserved contracts?
- ✓
- Was any entity identified that was prevented from participating in the procedure?
- ✓
- Were errors and omissions identified in the specifications?
- ✓
- Was there a request for document classification?
- ✓
- Was there a proposal in which prices were considered abnormally low?
- ✓
- What were the award criteria? Monofactor or Multifactor?
- ✓
- Was the procedure derived from a previous procedure?
- ✓
- Was there a deposit provided and reinforcement of the deposit? If so, what percentage was defined? Or if not, what was the justification?
- ✓
- Was the contract reduced to writing? If not, what was the justification?
- ✓
- Was there a price advance? If so, what was the justification?
- ✓
- Was there a payment of premiums for early compliance? If so, what was the basis?
- ✓
- Was the work inspection contracted or was it internal?
- ✓
- Was there a transfer of the contractual position? If so, what was the basis?
- ✓
- Was there subcontracting? If so, what was the basis?
- ✓
- Were there expropriations, easements and occupations of public buildings? If yes, were there any compensation payments?
- ✓
- Was there a request for a financial balance because of increased costs in carrying out the work? If so, what was the amount paid?
- ✓
- Was there a need to change the work plan and payment plan? What was the justification?
- ✓
- What was the start and end date of the work?
- ✓
- Were there objective changes to the contract?
- ✓
- What was the date of the provisional reception?
- ✓
- What was the PSS approval date?
- ✓
- What was the Consignment date?
- ✓
- What was the date of contract signing?
- ✓
- What was the award date?
- ✓
- Was there a delay in carrying out the work? How long? Was there a contractual sanction applied?
- ✓
- What was the origin of the sources of price and term deviation?
6. Conclusions
Solutions and Proposals
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
References
- Atkinson, R. Project management—Cost, time and quality, two best guesses and a phenomenon, its time to accept other succes criteria. Int. J. Proj. Manag. 1999, 17, 337–342. [Google Scholar] [CrossRef]
- Fidan, G.; Dikmen, I.; Tanyer, A.M.; Birgonul, M.T. Ontology for Relating Risk and Vulnerability to Cost Overrun in International Projects. J. Comput. Civ. Eng. 2011, 25, 302–315. [Google Scholar] [CrossRef]
- Jacques de Sousa, L.; Simões, M.L.; Poças Martins, J.; Sanhudo, L.; Moreira da Costa, J. Statistical Descriptive Analysis of Portuguese Public Procurement Data from 2015 to 2022. CivilEng 2023, 4, 808–826. [Google Scholar] [CrossRef]
- Senouci, A.; Ismail, A.; Eldin, N. Time Delay and Cost Overrun in Qatari Public Construction Projects. Procedia Eng. 2016, 164, 368–375. [Google Scholar] [CrossRef]
- Adam, A.; Josephson PE, B.; Lindahl, G. Aggregation of factors causing cost overruns and time delays in large public construction projects: Trends and implications. Eng. Constr. Archit. Manag. 2017, 24, 393–406. [Google Scholar] [CrossRef]
- Alinaitwe, H.; Apolot, R.; Tindiwensi, D. Investigation into the Causes of Delays and Cost Overruns in Uganda’s Public Sector Construction Projects. J. Constr. Dev. Ctries. 2013, 18, 33. [Google Scholar]
- Alhammadi, A.S.A.M.; Memon, A.H. Ranking of the factors causing cost overrun in infrastructural projects of use. Int. J. Sustain. Constr. Eng. Technol. 2020, 11, 204–211. [Google Scholar] [CrossRef]
- Alnuaimi, A.S.; Taha, R.A.; Al Mohsin, M.; Al-Harthi, A.S. Causes, Effects, Benefits, and Remedies of Change Orders on Public Construction Projects in Oman. J. Constr. Eng. Manag. 2010, 136, 615–622. [Google Scholar] [CrossRef]
- Simushi, S.; Wium, J. Time and cost overruns on large projects: Understanding the root cause. J. Constr. Dev. Ctries. 2020, 25, 129–146. [Google Scholar] [CrossRef]
- Shane, J.S.; Molenaar, K.R.; Anderson, S.; Schexnayder, C. Construction Project Cost Escalation Factors. J. Manag. Eng. 2009, 25, 221–229. [Google Scholar] [CrossRef]
- Durdyev, S. Review of construction journals on causes of project cost overruns. Eng. Constr. Archit. Manag. 2020, 28, 1241–1260. [Google Scholar] [CrossRef]
- PMI. Um Guia do Conhecimento em Gerenciamento de Projetos: PMBOK Guide, 5th ed.; Project Management Institute, Inc.: Newtown Square, PA, USA, 2013. [Google Scholar]
- Miranda, T.A.C. Controlo Económico de Obras: Proposta de Método. Master’s Thesis, Universidade do Porto, Porto, Portugal, 2011. [Google Scholar]
- Asiedu, R.O.; Adaku, E. Cost overruns of public sector construction projects: A developing country perspective. Int. J. Manag. Proj. Bus. 2020, 13, 66–84. [Google Scholar] [CrossRef]
- Huo, T.; Ren, H.; Cai, W.; Shen, G.Q.; Liu, B.; Zhu, M.; Wu, H. Measurement and Dependence Analysis of Cost Overruns in Megatransport Infrastructure Projects: Case Study in Hong Kong. J. Constr. Eng. Manag. 2018, 144, 05018001. [Google Scholar] [CrossRef]
- Rosenfeld, Y. Root-Cause Analysis of Construction-Cost Overruns. J. Constr. Eng. Manag. 2014, 140, 04013039. [Google Scholar] [CrossRef]
- Olawale, Y.A.; Sun, M. Cost and time control of construction projects: Inhibiting factors and mitigating measures in practice. Constr. Manag. Econ. 2010, 28, 509–526. [Google Scholar] [CrossRef]
- Praticò, F.G.; Astolfi, A.; Fedele, R. Analysis and modelling of the main causes of unsatisfactory quality of transportation infrastructures. In Eleventh International Conference on the Bearing Capacity of Roads, Railways and Airfields; CRC Press: Boca Raton, FL, USA, 2021; Volume 1, pp. 325–334. [Google Scholar] [CrossRef]
- Larsen, J.K.; Shen, G.Q.; Lindhard, S.M.; Brunoe, T.D. Factors Affecting Schedule Delay, Cost Overrun, and Quality Level in Public Construction Projects. J. Manag. Eng. 2016, 32, 04015032. [Google Scholar] [CrossRef]
- Decreto-Lei n.º 111-B/2017. de 31 de Agosto. Available online: https://diariodarepublica.pt/dr/detalhe/decreto-lei/111-b-2017-108086621 (accessed on 10 January 2024).
- Portaria n.º 318-B/2023, de 25 de Outubro. Available online: https://diariodarepublica.pt/dr/detalhe/portaria/318-b-2023-223338607 (accessed on 10 January 2024).
- Decreto-Lei nº 18/2008, de 29 de janeiro. Available online: https://diariodarepublica.pt/dr/detalhe/decreto-lei/18-2008-248178 (accessed on 10 January 2024).
- IBM Corp. IBM SPSS Statistics for Windows; Version 29.0.2.0; IBM Corp: Armonk, NY, USA, 2023. [Google Scholar]
- Love, P.E.D.; Irani, Z.; Smith, J.; Regan, M.; Liu, J. Cost performance of public infrastructure projects: The nemesis and nirvana of change-orders. Prod. Plan. Control. 2017, 28, 1081–1092. [Google Scholar] [CrossRef]
- Famiyeh, S.; Amoatey, C.T.; Adaku, E.; Agbenohevi, C.S. Major causes of construction time and cost overruns: A case of selected educational sector projects in Ghana. J. Eng. Des. Technol. 2017, 15, 181–198. [Google Scholar] [CrossRef]
Choosing the procedure for forming public works contracts (Article 19, CCP) | Type of Procedure | Condition |
Public competition or competition limited by prior qualification, with publication of an announcement in the Official Journal of the European Union | Whatever the value of the contract | |
Public competition or competition limited by prior qualification, without publication of an advertisement in the Official Journal of the European Union | When the value of the contract is lower than the threshold referred to in paragraph (a) of paragraph 3 of Article 474 (EUR 5,350,000.00) | |
Prior Consultation, with an invitation to at least three entities | When the contract value is less than EUR 150,000.00 | |
Direct fit | When the contract value is less than EUR 30,000.00 |
Descriptive Statistics | |||||
---|---|---|---|---|---|
N | Minimum | Maximum | Average | Standard Deviation | |
Base Price | 1240 | 4670.06 | 18,500,000.00 | 405,602.89 | 1,025,923.67 |
Contract Price | 1652 | 2113.79 | 17,443,880.00 | 314,126.92 | 850,740.46 |
Deviation from Base Price | 1240 | 0.00 | 4,518,578.41 | 45,382.31 | 184,573.36 |
Percentage Deviation from Base Price | 1240 | 0.00 | 63.15 | 7.33 | 9.32 |
Total Effective Price | 1652 | 2186.76 | 20,566,838.71 | 340,594.45 | 923,605.37 |
Price Deviation | 1652 | 0.01 | 3,122,958.71 | 26,467.52 | 97,437.68 |
Deviation Percentage | 1652 | 0.00% | 71.04% | 8.13% | 8.64% |
Execution Deadline (Days) | 1652 | 5 | 1095 | 147.87 | 143.04 |
Administrative Execution of the Contract (Days) | 1652 | 20 | 4557 | 553.92 | 385.80 |
Deadline Deviation (Days) | 1652 | −414 | 4257 | 406.05 | 338.04 |
Deadline Deviation Percentage | 1652 | −77.78% | 14,140.00% | 534.2309% | 804.65% |
Frequency | Percentage | Cumulative Percentage | |
---|---|---|---|
Aveiro | 92 | 5.6 | 5.6 |
Beja | 41 | 2.5 | 8.1 |
Braga | 37 | 2.2 | 10.3 |
Bragança | 14 | 0.8 | 11.1 |
Castelo Branco | 33 | 2.0 | 13.1 |
Coimbra | 70 | 4.2 | 17.4 |
Évora | 13 | 0.8 | 18.2 |
Faro | 115 | 7.0 | 25.1 |
Guarda | 30 | 1.8 | 26.9 |
Leiria | 67 | 4.1 | 31.0 |
Lisboa | 264 | 16.0 | 47.0 |
Portalegre | 45 | 2.7 | 49.7 |
Porto | 313 | 18.9 | 68.6 |
Santarém | 89 | 5.4 | 74.0 |
Setúbal | 144 | 8.7 | 82.7 |
Viana do Castelo | 41 | 2.5 | 85.2 |
Vila Real | 89 | 5.4 | 90.6 |
Viseu | 108 | 6.5 | 97.2 |
Região Autonoma da Madeira | 24 | 1.5 | 98.6 |
Região Autonoma dos Açores | 21 | 1.3 | 99.9 |
Portugal | 2 | 0.1 | 100.0 |
Total | 1652 | 100.0 |
Frequency | Percentage | Cumulative Percentage | |
---|---|---|---|
Direct Fit | 231 | 14.0 | 14.0 |
Prior Consultation | 548 | 33.2 | 47.2 |
Public Tender | 793 | 48.0 | 95.2 |
Framework Agreement | 72 | 4.4 | 99.5 |
Competition Limited by Prior Qualification | 8 | 0.5 | 100.0 |
Total | 1652 | 100.0 |
Frequency | Percentage | Cumulative Percentage | |
---|---|---|---|
Works up to EUR 30,000.00 | 300 | 18.2 | 18.2 |
Works from EUR 30,000.00 to EUR 150,000.00 | 703 | 42.6 | 60.7 |
Works from EUR 150,000.00 to EUR 5,350,000.00 | 642 | 38.9 | 99.6 |
Works above EUR 5,350,000.00 | 7 | 0.4 | 100.0 |
Total | 1652 | 100.0 |
Price Group | Total | |||||
---|---|---|---|---|---|---|
Works up to EUR 30,000.00 | Works from EUR 30,000.00 to EUR 150,000.00 | Works from EUR 150,000.00 to EUR 5,350,000.00 | Works Above EUR 5,350,000.00 | |||
Direct Fit | Count | 199 | 21 | 9 | 2 | 231 |
% in Procedure Type | 86.1% | 9.1% | 3.9% | 0.9% | 100.0% | |
% in Price Group | 66.3% | 3.0% | 1.4% | 28.6% | 14.0% | |
Consultation Preview | Count | 60 | 473 | 15 | 0 | 548 |
% in Procedure Type | 10.9% | 86.3% | 2.7% | 0.0% | 100.0% | |
% in Price Group | 20.0% | 67.3% | 2.3% | 0.0% | 33.2% | |
Contest Public | Count | 16 | 185 | 589 | 3 | 793 |
% in Procedure Type | 2.0% | 23.3% | 74.3% | 0.4% | 100.0% | |
% in Price Group | 5.3% | 26.3% | 91.7% | 42.9% | 48.0% | |
Agreement Frame | Count | 25 | 23 | 24 | 0 | 72 |
% in Procedure Type | 34.7% | 31.9% | 33.3% | 0.0% | 100.0% | |
% in Price Group | 8.3% | 3.3% | 3.7% | 0.0% | 4.4% | |
Contest Limited by Prior Qualification | Count | 0 | 1 | 5 | 2 | 8 |
% in Procedure Type | 0.0% | 12.5% | 62.5% | 25.0% | 100.0% | |
% in Price Group | 0.0% | 0.1% | 0.8% | 28.6% | 0.5% | |
Total | Count | 300 | 703 | 642 | 7 | 1652 |
% in Procedure Type | 18.2% | 42.6% | 38.9% | 0.4% | 100.0% | |
% in Price Group | 100.0% | 100.0% | 100.0% | 100.0% | 100.0% |
Price Deviation | |||||
---|---|---|---|---|---|
N Valid | Minimum | Maximum | Average | Standard Deviation | |
Direct Fit | 231 | 0.40 | 528,697.78 | 5567.70 | 37,316.58 |
Prior Consultation | 548 | 0.01 | 88,189.57 | 6199.88 | 8364.02 |
Public Tender | 793 | 0.01 | 787,573.58 | 43,383.39 | 79,450.34 |
Framework Agreement | 72 | 20.00 | 89,401.67 | 9670.32 | 19,146.76 |
Competition Limited by Preliminary Qualification | 8 | 12,979.78 | 3,122,958.71 | 492,672.84 | 1,067,626.65 |
Price Deviation | ||||||
---|---|---|---|---|---|---|
N Valid | Percentage | Minimum | Maximum | Average | Standard Deviation | |
Aveiro | 92 | 5.6 | 0.39 | 418,415.62 | 26,861.54 | 68,495.18 |
Beja | 41 | 2.5 | 218.67 | 96,722.56 | 16,730.32 | 24,116.59 |
Braga | 37 | 2.2 | 382.49 | 185,281.01 | 34,094.78 | 41,427.90 |
Bragança | 14 | 0.8 | 1912.42 | 141,955.35 | 27,859.59 | 37,876.14 |
Castelo Branco | 33 | 2.0 | 201.80 | 787,573.58 | 55,459.89 | 160,911.51 |
Coimbra | 70 | 4.2 | 0.04 | 172,463.36 | 22,244.08 | 35,791.58 |
Évora | 13 | 0.8 | 0.31 | 325,583.20 | 67,994.52 | 98,651.32 |
Faro | 115 | 7.0 | 0.01 | 203,617.59 | 17,013.98 | 30,716.18 |
Guarda | 30 | 1.8 | 262.36 | 389,515.57 | 29,029.27 | 71,581.33 |
Leiria | 67 | 4.1 | 0.01 | 88,163.76 | 11,815.00 | 19,856.52 |
Lisboa | 264 | 16.0 | 177.03 | 709,645.96 | 25,345.88 | 77,957.51 |
Portalegre | 45 | 2.7 | 208.80 | 142,127.30 | 14,266.56 | 27,915.07 |
Porto | 313 | 18.9 | 11.91 | 357,935.55 | 21,548.15 | 45,863.36 |
Santarém | 89 | 5.4 | 188.19 | 360,412.41 | 26,796.17 | 59,932.95 |
Setúbal | 144 | 8.7 | 63.50 | 416,939.04 | 32,282.22 | 65,748.67 |
Viana do Castelo | 41 | 2.5 | 0.02 | 3122958.71 | 117196.25 | 487675.95 |
Vila Real | 89 | 5.4 | 239.91 | 330,464.71 | 22,991.82 | 58,046.81 |
Viseu | 108 | 6.5 | 62.63 | 144,044.05 | 13,743.57 | 21,674.44 |
Região Autonoma da Madeira | 24 | 1.5 | 230.01 | 330,021.80 | 29,741.52 | 69,847.99 |
Região Autonoma dos Açores | 21 | 1.3 | 526.57 | 417,091.44 | 40,919.91 | 91,994.49 |
Portugal | 2 | 0.1 | 270.00 | 4941.68 | 2605.84 | 3303.38 |
TOTAL | 1652 | 100.00 |
Deviation Percentage | |||||
---|---|---|---|---|---|
N Valid | Minimum | Maximum | Average | Standard Deviation | |
Aveiro | 92 | 0.00% | 36.95% | 7.76% | 7.42% |
Beja | 41 | 0.48% | 47.76% | 9.15% | 10.71% |
Braga | 37 | 0.51% | 59.03% | 10.69% | 9.91% |
Bragança | 14 | 0.78% | 12.72% | 5.35% | 3.63% |
Castelo Branco | 33 | 0.10% | 23.18% | 7.07% | 5.85% |
Coimbra | 70 | 0.00% | 57.40% | 9.10% | 10.98% |
Évora | 13 | 0.00% | 30.50% | 10.50% | 8.33% |
Faro | 115 | 0.00% | 39.60% | 8.21% | 6.51% |
Guarda | 30 | 0.73% | 32.34% | 9.22% | 8.98% |
Leiria | 67 | 0.00% | 43.47% | 5.39% | 6.52% |
Lisboa | 264 | 0.14% | 50.68% | 8.03% | 8.17% |
Portalegre | 45 | 0.15% | 29.22% | 4.96% | 4.74% |
Porto | 313 | 0.03% | 71.04% | 7.90% | 9.15% |
Santarém | 89 | 0.23% | 37.65% | 6.61% | 6.53% |
Setúbal | 144 | 0.22% | 49.78% | 10.24% | 9.97% |
Viana do Castelo | 41 | 0.00% | 42.98% | 9.47% | 9.06% |
Vila Real | 89 | 0.65% | 45.10% | 7.69% | 8.32% |
Viseu | 108 | 0.28% | 50.00% | 10.54% | 11.09% |
Região Autonoma da Madeira | 24 | 0.24% | 7.12% | 2.48% | 1.91% |
Região Autonoma dos Açores | 21 | 1.03% | 18.18% | 6.36% | 5.07% |
Portugal | 2 | 0.15% | 3.11% | 1.63% | 2.09% |
Type of Procedure | ||||||||||
---|---|---|---|---|---|---|---|---|---|---|
Direct Fit | Prior Consultation | Public Tender | Framework Agreement | Limited Preview Contest Qualification | ||||||
Count | % of N of the Line | Count | % of N of the Line | Count | % of N of the Line | Count | % of N of the Line | Count | % of N of the Line | |
Aveiro | 8 | 8.7% | 38 | 41.3% | 46 | 50.0% | 0 | 0.0% | 0 | 0.0% |
Beja | 4 | 9.8% | 22 | 53.7% | 15 | 36.6% | 0 | 0.0% | 0 | 0.0% |
Braga | 4 | 10.8% | 4 | 10.8% | 29 | 78.4% | 0 | 0.0% | 0 | 0.0% |
Bragança | 0 | 0.0% | 2 | 14.3% | 12 | 85.7% | 0 | 0.0% | 0 | 0.0% |
Castelo Branco | 8 | 24.2% | 7 | 21.2% | 18 | 54.5% | 0 | 0.0% | 0 | 0.0% |
Coimbra | 9 | 12.9% | 23 | 32.9% | 37 | 52.9% | 0 | 0.0% | 1 | 1.4% |
Évora | 1 | 7.7% | 2 | 15.4% | 10 | 76.9% | 0 | 0.0% | 0 | 0.0% |
Faro | 17 | 14.8% | 42 | 36.5% | 56 | 48.7% | 0 | 0.0% | 0 | 0.0% |
Guarda | 5 | 16.7% | 11 | 36.7% | 14 | 46.7% | 0 | 0.0% | 0 | 0.0% |
Leiria | 16 | 23.9% | 20 | 29.9% | 31 | 46.3% | 0 | 0.0% | 0 | 0.0% |
Lisboa | 21 | 8.0% | 95 | 36.0% | 147 | 55.7% | 1 | 0.4% | 0 | 0.0% |
Portalegre | 14 | 31.1% | 15 | 33.3% | 16 | 35.6% | 0 | 0.0% | 0 | 0.0% |
Porto | 47 | 15.0% | 77 | 24.6% | 116 | 37.1% | 71 | 22.7% | 2 | 0.6% |
Santarém | 12 | 13.5% | 37 | 41.6% | 40 | 44.9% | 0 | 0.0% | 0 | 0.0% |
Setúbal | 21 | 14.6% | 55 | 38.2% | 67 | 46.5% | 0 | 0.0% | 1 | 0.7% |
Viana do Castelo | 2 | 4.9% | 13 | 31.7% | 25 | 61.0% | 0 | 0.0% | 1 | 2.4% |
Vila Real | 7 | 7.9% | 29 | 32.6% | 53 | 59.6% | 0 | 0.0% | 0 | 0.0% |
Viseu | 23 | 21.3% | 44 | 40.7% | 41 | 38.0% | 0 | 0.0% | 0 | 0.0% |
Região Autonoma da Madeira | 3 | 12.5% | 10 | 41.7% | 8 | 33.3% | 0 | 0.0% | 3 | 12.5% |
Região Autonoma dos Açores | 9 | 42.9% | 0 | 0.0% | 12 | 57.1% | 0 | 0.0% | 0 | 0.0% |
Portugal | 0 | 0.0% | 2 | 100.0% | 0 | 0.0% | 0 | 0.0% | 0 | 0.0% |
Year | Frequency | Percentage | Cumulative Percentage |
---|---|---|---|
2010 | 1 | 0.1 | 0.1 |
2011 | 2 | 0.1 | 0.2 |
2015 | 3 | 0.2 | 0.4 |
2016 | 4 | 0.2 | 0.6 |
2017 | 22 | 1.3 | 1.9 |
2018 | 56 | 3.4 | 5.3 |
2019 | 147 | 8.9 | 14.2 |
2020 | 418 | 25.3 | 39.5 |
2021 | 840 | 50.8 | 90.4 |
2022 | 159 | 9.6 | 100.0 |
Total | 1652 | 100.0 |
Deviation Percentage | ||||||
---|---|---|---|---|---|---|
N Valid | Minimum | Maximum | Average | Standard Deviation | ||
Years | 2019 | 147 | 0.00% | 71.04% | 6.49% | 8.77% |
2020 | 418 | 0.00% | 47.76% | 7.87% | 7.66% | |
2021 | 840 | 0.00% | 57.40% | 8.53% | 8.63% | |
2022 | 159 | 0.08% | 59.03% | 8.20% | 10.21% |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2024 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Almeida, Y.; Calejo, R. Additional Costs of Public Works Contracts in Portugal—Descriptive Statistical Analysis in Light of the Quality of Information. CivilEng 2024, 5, 1089-1109. https://doi.org/10.3390/civileng5040053
Almeida Y, Calejo R. Additional Costs of Public Works Contracts in Portugal—Descriptive Statistical Analysis in Light of the Quality of Information. CivilEng. 2024; 5(4):1089-1109. https://doi.org/10.3390/civileng5040053
Chicago/Turabian StyleAlmeida, Ygor, and Rui Calejo. 2024. "Additional Costs of Public Works Contracts in Portugal—Descriptive Statistical Analysis in Light of the Quality of Information" CivilEng 5, no. 4: 1089-1109. https://doi.org/10.3390/civileng5040053
APA StyleAlmeida, Y., & Calejo, R. (2024). Additional Costs of Public Works Contracts in Portugal—Descriptive Statistical Analysis in Light of the Quality of Information. CivilEng, 5(4), 1089-1109. https://doi.org/10.3390/civileng5040053