Next Article in Journal
NOx Emissions and Nitrogen Fate at High Temperatures in Staged Combustion
Next Article in Special Issue
Theoretical Design and Analysis of the Waste Heat Recovery System of Turbine Exhaust Steam Using an Absorption Heat Pump for Heating Supply
Previous Article in Journal
A Model-Based Design of Distributed Automation Systems for the Smart Grid: Implementation and Validation
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Dynamic Simulation and Thermoeconomic Analysis of a Trigeneration System in a Hospital Application

by
Francesco Calise
,
Francesco Liberato Cappiello
*,
Massimo Dentice d’Accadia
,
Luigi Libertini
and
Maria Vicidomini
Department of Industrial Engineering, University of Naples Federico II, 80125 Naples, Italy
*
Author to whom correspondence should be addressed.
Energies 2020, 13(14), 3558; https://doi.org/10.3390/en13143558
Submission received: 1 June 2020 / Revised: 1 July 2020 / Accepted: 7 July 2020 / Published: 10 July 2020

Abstract

:
Hospitals are very attractive for Combined Heat and Power (CHP) applications, due to their high and continuous demand for electric and thermal energy. However, both design and control strategies of CHP systems are usually based on an empiric and very simplified approach, and this may lead to non-optimal solutions. The paper presents a novel approach based on the dynamic simulation of a trigeneration system to be installed in a hospital located in Puglia (South Italy), with around 600 beds, aiming to investigate the energy and economic performance of the system, for a given control strategy (electric-load tracking). The system includes a natural gas fired reciprocating engine (with a rated power of 2.0 MW), a single-stage LiBr-H2O absorption chiller (with a cooling capacity of around 770 kW), auxiliary gas-fired boilers and steam generators, electric chillers, cooling towers, heat exchangers, storage tanks and several additional components (pipes, valves, etc.). Suitable control strategies, including proportional–integral–derivative (PID) and ON/OFF controllers, were implemented to optimize the trigeneration performance. The model includes a detailed simulation of the main components of the system and a specific routine for evaluating the heating and cooling demand of the building, based on a 3-D model of the building envelope. All component models were validated against experimental data provided by the manufacturers. Energy and economic models were also included in the simulation tool, to calculate the thermoeconomic performance of the system. The results show an excellent economic performance of the trigeneration system, with a payback period equal to 1.5 years and a profitability index (ratio of the Net Present Value to the capital cost) equal to 3.88, also due to the significant contribution of the subsidies provided by the current Italian regulation for CHP systems (energy savings certificates).

1. Introduction

Cogeneration (or CHP, Combined Heat and Power) represents a mature and well-known technology, able to ensure remarkable energy and economic savings, due to the combined production of thermal end electric energy, from a single primary energy input [1,2]. Trigeneration systems are CHP units whose thermal waste energy is also used to drive a thermally-driven chiller. Such systems are often referred to as Combined Cooling, Heat and Power (CCHP) systems [3]. CCHP systems can be also used to produce other products (e.g., hydrogen, alcohols, glycerine), configuring a polygeneration system [4].
CHP and CCHP are based on the recovery of the exhaust heat rejected by an engine, also called the prime mover (PM) [5]. Such thermal energy may be used for heating, process, production of sanitary hot water, etc., and/or to drive a thermally-driven chiller to produce cooling energy [1,6]. The main advantages of CHP/CCHP systems are: (i) energy and economic savings and reduction of greenhouse gas emissions with respect to the separate production of the same amounts of energy with conventional technologies [1]; (ii) higher flexibility in power dispatch [5]; (iii) scalability [5]; (iv) energy reliability [5].
CCHP/CHP systems exhibit good economic, energy and environmental performance for a large number of applications, such as: large-sized industries [7]; chemical industries [8]; hospitals [9]; food industries [10], paper mills [11].
The literature is rich of papers dealing with cogeneration, also investigating several aspects of CHP/CCHP operating conditions [12] and control strategies [5].
Ref. [13] deals with a combined cycle CCHP supplying a university campus. The CCHP layout is based on two gas turbines, each with a rated power of 11 MWe. Moreover, a backpressure steam turbine is installed, providing additional 5.5 MWe of power. This study proves that CCHP systems are useful for reducing the primary energy consumption of the campus [13].
In Ref. [14], a 425 kWe trigeneration system, based on an internal combustion engine, is coupled with a 355.2 kWth single effect absorption chiller (ACH). The system, installed in a Brazilian University, is simulated using the software COGMCI, comparing two control strategies: full load mode and electrical load tracking mode.
The dynamic simulation model of a 65 kWe microturbine was developed in Ref. [15], using Matlab. The aim of this work is to describe in detail a microturbine performance, including transient effects. The validation of the proposed model was performed using real measured data, provided by the microturbine installed at the Savona Campus of the University of Genova (Italy).
A polygeneration system based on a combined cycle was analysed in Ref. [16]. The waste heat of the combined cycle is exploited to generate steam and hot water, delivered to a hospital. The developed plant consists of a 46.6 MWe gas turbine and a 28.6 MWe steam turbine. A simulation model in ASPEN PLUS is developed to select the most profitable operating strategy [16]. An optimization tool was adopted in Ref. [17], aiming to define the best layout and operating strategy of a trigeneration plant supplying a hotel. Measured data were employed to model the energy demand of the building. In particular, this paper considers three system layouts: (i) reciprocating engine and single stage ACH; (ii) reciprocating engine and double stage ACH; (iii) gas turbine and double effect ACH. Several sensitive analyses were performed, also analysing the effects of a moderate tax exemption and those of a reduction of the fuel cost on the economic profitability of the systems [18].
In conclusion, many works are available in literature dealing with cogeneration/trigeneration technologies and applications, but only few papers implement a thermoeconomic analysis based on dynamic simulations, aiming to determine the optimal design and operating strategy of the system under evaluation. Such approach is adopted in the present paper, analysing a real case, represented by the CCHP system to be installed in a hospital located in Puglia, South Italy.
The system was designed by an ESCO (Energy Service COmpany), in the framework of an Energy Performance Contract, using a conventional engineering approach, based on standard steady state algorithms. The system was designed to cover a part of the thermal, cooling and power load of the complex. Conventional auxiliary systems are used to match the hospital demand when the CCHP unit is off and/or when its capacity is lower than the demand, namely electric chillers for cooling, condensing boilers for heating and public grid for power.
Since the system under analysis is an existing one, the simulation model was not used to investigate its optimal design, but rather to analyse its energy and economic performance in detail and to evaluate its optimal operating strategy. All design data used in the analysis correspond to the equipment selected by the ESCO for installation.

2. Plant Layout

In Figure 1, the layout of the CCHP system under consideration is represented. The system is based on a natural gas-fueled internal combustion engine, coupled with a single effect LiBr-H2O absorption chiller. The trigeneration system, in an exercise from December 2019, was integrated into the existing heating and cooling systems, which are still used as back-up and auxiliary systems; the system operates in parallel with the external public grid, to match the power demand when the engine is off and/or its capacity is not sufficient to this scope. The demand for thermal energy includes the production of sanitary hot water, steam, space heating and cooling. The electric energy is used for lights, machinery, medical devices, pumps, fans. An electrical load tracking mode was selected by the company who manage the system, and the maximum electric power of the CHP system is lower than the maximum power demand, in order to reduce the capital cost of the system and the running time in part load conditions. Therefore, when the power demand is lower than the cogenerator maximum capacity, such demand is fully supplied by the CHP unit; in other cases, the cogeneration unit operates at full load and a certain amount of power must be imported from the public grid. As a consequence, the availability of waste heat for heating and/or cooling purposes varies, according to the operating conditions of the engine. At any rate, the heat demand is usually much higher than the capacity of the CHP system, so that the auxiliary heaters are always active, and the same happens for the cooling demand.
The heat recovery system includes various loops, as described in the following. In the Exhaust Gases Loop (EGL), the Exhaust Gases (EG) leaving the engine (at a temperature of about 411 °C) are used to produce steam in the Steam–Exhaust Gas heat exchanger (S–EG-HE), evolving within the Steam Loop (SL); afterwards, in the EG-JW-HE, the exhaust gases are used to enhance the temperature of the engine jacket water (JW), flowing within the JW Loop (JWL), and finally leave the heat exchange section at a temperature of at least 120 °C (to avoid acid condensation phenomena inside the heat exchangers).
As described in Figure 2, if the vapor produced in S–EG-HE (Qsteam,S-EG-HE) is lower than the hospital demand (Qsteam), the remaining amount of steam is produced by the auxiliary steam generator (SG). In particular, to this end, a suitable amount of water is sent from TKs to SG, by means of the pump PS2. The steam flows produced by S–EG-HE and/or SG are mixed in the steam collector (SColl), and finally are made available to the end users.
For the JW Loop, two different operation strategies are adopted, for heating and cooling periods, respectively. During the cooling period, the jacket water is primarily supplied to the absorption chiller (ACH), as shown in Figure 3; subsequently, the JW leaving the ACH is supplied to the JW-HW-HE (Figure 1) to provide heat to the heating water Loop. As shown in Figure 4, if the jacket water temperature decreases below 80 °C, the diverter D4 addresses the flow to the mixer M4, keeping the JW temperature within the range suggested by the engine manufacturer [19]. Conversely, if temperature of the jacket water rises over 80 °C, the dissipator unit is activated, preventing engine overheating. Clearly, if the cooling energy demand is null, the JW directly heats the heating Loop through the HE-H. Finally, JW cools down the engine oil in the HE-O1 exchanger.
The engine lubricating oil, flowing in the Oil Loop (OL), is cooled in HE-O1, supplying heat to jacket water, and in and HE-O2, where low temperature heat is dissipated in the heat exchanger DISS.
The Engine Water Cooling Loop (EWCL) is used to cool the second stage of intercooling (IC2) and the engine oil (HE-O2)—since the temperature within this loop is too low, the thermal energy of the loop is entirely dissipated in the dissipator (DISS).
The heating water Loop (HWL) consists of the water heated in JW-HW-HE, which supplies thermal energy for building space heating and domestic hot water (DHW). In particular, in JW-HW-HE the heat exchange between JW and heating water (HW) is performed, increasing the temperature of HW. Subsequently, HW is supplied to the heating water collector (Coll 1). Note that the setpoint temperature of HWL is 85 °C. If the temperature of HWL is below 85 °C, the auxiliary condensation boiler (CB) is activated, raising such temperature to 85 °C (Figure 5). The HWL is managed by pump P2, which is turned on only when there is a demand for space heating and/or the top temperature of the domestic hot water tank (Ttop,TKDHW) decreases below 45 °C (Figure 6). In particular, when Ttop,TKDHW decreases below 45 °C, the pump P7 is also switched on, supplying thermal energy to TKDWH. The pump P7 is switched off when Ttop,TKDHW reaches the value of 60 °C.
The Domestic Hot Water Loop (DHWL) refers to the sanitary hot water required by the hospital. When the DHW demand is not null, the pump P8 is switched on. Thus, a proper amount of water flows through the heat exchanger towards the tank TKDHW, heating the water from 15 °C (tap water) to 45 °C.
The Building space Heating loop (BHL) refers to the hot water supplied to the fain-coils inside the hospital. In the heating period, the pump P5 is switched on, keeping the indoor temperature equal to the its setpoint value (Table 2).
The Building space Cooling Loop (BCL) is used to provide space cooling by means of Chilled Water (CW), supplied to fan coils located in the building. The cooling demand is matched by the ACH, as far as possible; when the ACH capacity is not sufficient, the auxiliary electric chillers (CH) are activated.
The Cooling Tower Water Loop (CTWL) is used to cool all the chillers included in the plant (ACH and CH); therefore, when ACH and/or CH are running, the pump P4 must be activated.
As mentioned before, an electric load tracking operating strategy was adopted for the system under evaluation. The engine can work with a partial load ratio (Rel, defined as the ratio of the power demand on the maximum rated power) ranging between 50% and 100%; when Rel falls below 50%, the engine must be switched off.

3. Simulation Model

The system presented was modelled in TRNSYS 17 environment. TRNSYS is widely employed in the academic community, because of its high accuracy and reliability; moreover, a large library of user-developed models and experimentally validated built-in components [20] is included in this software. The model includes several components (engine, heat exchangers, tanks, pumps, etc). Some of these models are based on thermodynamic models and they are mainly taken from TRNSYS library, being previously validated against experimental data and successfully used in several works. The Type 56 (Building) is considered a reference in the field of building dynamic simulation. The 3D geometric model of the hospital was built with the Google SketchUp TRNSYS 3d plug-in; such geometric model was then imported in the Type 56.
The main TRNSYS libraries used in this work are described below.
  • Ÿ Type 56: this library dynamically models the energy performance of the building considering its 3D geometry, thermophysical proprieties of the envelope, dynamic weather conditions (i.e., solar radiation, ambient temperature, wind velocity, relative humidity, etc.); further details are available in Ref. [21].
  • Ÿ Type 907: this library describes the performance of internal combustion engines, considering oil cooling water, after-cooling water, jacket water, and using inlet air temperature as a parameter. The mass and thermal balance performed by this library are based on manufactured data [18]. For the sake of brevity, the equations of this model not are described here, but a detailed description is available in Ref. [1].
  • Ÿ Type 107: this library models the performance of a single-effect LiBr-H2O absorption chiller. The library adopts a normalized catalogue data look-up principle [22]. Thus, the performance of ACH is evaluated by using an operating map provided by manufacturers [23]. Further details are reported in Ref. [1].

3.1. Energy Analysis

A comparison between the Proposed System (PS) described above and a conventional, Reference System (RS) was carried out. The energy comparison was performed by evaluating the Primary Energy consumptions (PE) of both RS and PS, and the corresponding Primary Energy Saving (PES) achieved by the PS. In particular, PE and PES were calculated as follows:
P E R S = [ ( E e l , L O A D + E t h , c o o l C O P ) η e l + ( E t h , h e a t + E t h , D H W ) η C B + E t h , v a p o r η S G ] t P E P S = t [ P E C H P + E e l , f r o m G R I D η e l + E t h , a u x C B η C B + E t h , a u x S G η S G ] t P E S P S =   P E R S P E P S P E R S
Here, Eel,load is the overall electric energy demand of the hospital, Eth,cool and Eth,heat are the thermal energy demand for space cooling and heating, respectively, Eth,DHW is the thermal energy demand for sanitary hot water production, Eth,steam is the thermal energy needed for steam production, Eel,fromGRID is the electric energy withdrawn from the grid, Eth,CB and Eth,SG are the thermal energy provided by auxiliary boilers and steam generators, respectively; the remaining terms in Equation (1) are explained in Table 1.

3.2. Economic Analysis

The yearly operating cost (C) of RS and PS are calculated as follows:
C R S = [ J e l , f r o m G R I D ( E e l , L O A D + E t h , c o o l C O P ) + J N G ( E t h , h e a t + E t h , D H W ) η C B + J N G E t h , v a p o r η S G ] t C P S = ( E t h , a u x C B η C B + E t h , a u x S G η S G ) J N G + C C H P + E e l , f r o m G R I D J e l , f r o m G R I D J E S C E S C + M C H P C C H P = V C H P L H V N G J N G , C H P
Table 1 explains the main terms of these equations. The subsidies available in Italy for cogeneration (Energy Saving Certificates, ESC) were considered; they are proportional to the primary energy saving acknowledged as “High-Efficiency cogeneration” units, and can be calculated with an algorithm described in Ref. [1].
The economic performance of the proposed system was evaluated by means of the following economic parameters: (i) yearly economic savings ( Δ C ); (ii) Simple payback period (SPB) of the investment; (iii) net present value (NPV); and (iv) profitability index (PI):
Δ C = C R S C P S C R S S P B =   C i n v Δ C P I P S   = Δ C A F C i n v C i n v N P V =   P I C i n v
Here, Cinv is the capital cost of the cogeneration plant, equal to 2.0 M€, and AF is the annuity factor, assumed equal to eight years (based on a discount rate of 5% and a time horizon of 10 years—Table 1).

4. Hospital Energy Loads

The system described above is to be installed in the “F. Miulli" hospital, located in Acquaviva delle Fonti, near Bari, in South Italy (Figure 7 and Figure 8). The facility has 603 beds and a gross volume of 370 × 103 m3.
To limit the computational cost of the simulations, while keeping the accuracy high, the complex of buildings was thermally modelled by defining four thermal zones (Table 2 and Figure 7), characterized by similar features and destination (Figure 7): Zone A includes the operating rooms, Zone B the resting rooms, Zone C offices and clinic rooms, Zone D technical rooms.
The occupancy schedule of such thermal zones is reported in Table 2. Here, data about the main geometric characteristics, ventilation, setpoint temperatures and heating and cooling periods for each thermal zone are reported, too. The elements of the building envelope are described in Table 3. Note that, as it is well-known, the thickness and U-value of each element affect the energy performance of the building in terms of space heating and cooling energy consumption. The hospital is located in the Italian weather zone D (1.610 heating degree-day, Table 2). It is useful to remember that the heating degree-days of a site are defined as the sum of the difference (considered only if positive) between the indoor setpoint temperature and the mean daily outdoor temperature of that site. In the heating season, such parameter is commonly used to estimate the energy consumption for space heating of buildings.
According to the Italian legislation about healthcare facilities, no restrictions are present concerning the duration of the heating periods.
Presently, the energy needs of the facility are matched as follows: electric air-to-air chillers, natural gas-fueled steam generators, for steam, and condensing boilers for sanitary hot water preparation and space heating; electric energy and natural gas; this configuration was adopted as the Reference System for the energy and economic analyses of the new CCHP system presented in the next section.
The hospital consumes about 15.89 GWh/y of electric energy and 1.76 × 106 Sm3 of natural gas. Figure 9 shows the current electric energy and natural gas consumptions on a monthly basis.
In particular, three 3 MW TRANE CVGF1000 electric chillers combined with four 3.5 MW cooling towers are included for the production of chilled water; one chiller is used as a backup system. The power absorbed by each chiller is equal to equal to 504 kW. The total electric consumption of chillers and cooling towers is estimated at around 2909 MWh/year.
The Heating, Ventilation and Air Conditioning (HVAC) systems are responsible for the consumption of about 27 GWh/year, equal to 52% the total consumption. The 25 circulation pumps (including the spare ones) have a consumption of about 1566 MWh/year. The overall lighting consumption is equal to 8490 MWh/year (16% of the total consumption). A total of 37 lifts, covering six floors, consume around 350 MWh/year (1.5% of the total consumption). The two natural gas steam generators (model 2.1 MW HOVAL HG-E-240) consume about 1,080,000 Sm3/year. The thermal energy demand for space heating and domestic hot water is covered by three natural gas boilers (model 3.5 MW HOVAL MAX-3), with a consumption of 685,000 Sm3/year and 160,000 Sm3/year, for heating and DHW, respectively.
The layout of the cogeneration system to be installed was already presented in Figure 1. The CHP unit is an internal combustion engine model ABB Ecomax 20, with a rated power of 2.00 MW and a thermal capacity of 1.95 MW [18] (Table 4); the nominal electric efficiency is 44.1%, the thermal one 43.0%; therefore, the global efficiency is equal to 87.1%.
According to the indications provided by the ESCO, who designed the plant, an electric load tracking operating strategy was adopted. Table 4 also displays the characteristics of other devices included in the layout under analysis. Note that the existing devices, such as steam generators and condensing boilers, are employed as auxiliary systems, see Figure 1.
In conclusion, the case study presented above was solved in the TRNSYS environment, selecting an equation-resolution time step of 0.05 h, as shown in Table 2.

5. Results

In this section, the calibration of the building model is presented as well as the results of the simulations carried out are discussed. The calibration is performed using the data regarding the energy bills. In particular, for each month of the year, the comparison between the real data of thermal energy demand for space heating and domestic hot water and the simulated value by the implementation of the building model is presented (Figure 10). The same comparison is presented also for the total electric demand, including also the electric consumption to supply the electric chillers for the hospital space cooling. Figure 10 clearly shows a good agreement between the numerical results and real data. Therefore, the building model resulted to be calibrated.

5.1. Daily Results

Figure 11 displays the dynamic performance of the CCHP under evaluation. The power (Pel,CHP) varies over the hours, due to the control strategy assumed (electric load tracking). In particular, in the case shown in the figure, Pel,CHP is constantly equal to the power demand of the hospital (Pel,LOAD). The latter, in fact, is never higher than the maximum power of the CCHP system. Moreover, Figure 11 displays the thermal control strategy adopted, aiming at keeping the jacket water temperature entering the engine (TJW,inCHP) equal to about 80 °C.

5.2. Weekly Results

Figure 12 displays the weekly energy performance of the proposed layout. According to the operating strategy adopted for the system, it is able to constantly match the electric energy demand of the hospital (Figure 11 and Figure 12—left side). Note that some weeks are characterized by zero or limited energy production, due to scheduled maintenance interventions. Clearly, when the engine is switched off, the public grid is used as a backup system, meeting the electric energy demand of the hospital. The electric energy delivered to the auxiliary systems is very low, achieving the maximum value of 10 MWh/week (Figure 12—left side). The thermal energy recovered by the engine (Eth,CHP) is equal to about 281-310 MWhth/week (Figure 12—right side). In particular, the medium temperature thermal energy (Eth,CHP,MT) ranges between 281–310 MWhth/week, whereas the high temperature one (Eth,CHP,HT) ranges between 109 and 129 MWhth/week (Figure 12—right side).
Figure 13 displays the performance of the Steam Loop (SL), and, in particular, the thermal energy required for steam production (Eth,Steam), and the ratio of the thermal energy provided by the steam generator (SG) and by the CHP system to the overall request, Eth,Steam (RSG and RCGP,HT, respectively). From Week 28 to week 35 (summer period), the thermal energy provided by SG for producing steam is about null, i.e., RSG is equal to zero. This trend is due to the reduction of the demand of steam during these weeks. During the remaining weeks, the CHP system is able to meet a limited share of Eth,Steam: RCGP,HT ranges between 42% and 57%, except the weeks in which the programmed maintenance operations occur (weeks 17 and 44).
Figure 14 displays the weekly energy balance regarding the cooling service; in particular, the following quantities are shown: cooling energy demand (Eth,cool), ratio of the cooling energy provided by ACH on Eth,cool (RACH), and ratio of cooling energy provided by the electric-driven auxiliary chiller on Eth,cool (RCH). When the cooling demand is high (weeks from 25 to 36), the ACH is able to match the major share of cooling energy demand (RCH ranging from 56% to 76%).

5.3. Yearly Results

Table 5 summarizes the yearly performance of the proposed layout. CHP produces 13.74 GWh/year of electric energy, achieving an electric efficiency of 42%. The proposed system exhibits a limited energy saving (PES equal to 9%). This is mainly due to the fact that the energy saving was calculated with respect to the overall primary energy consumption of the reference scenario, whereas the Proposed System only covers a part of such consumption. in particular, the share of thermal energy produced by the CHP on the overall request is only 41% (Table 6). Should the energy saving be calculated for the cogeneration system only, it would be significantly higher.
In any case, from the economical point of view, the Proposed System achieves significant results, with an SPB of 1.5 years and an NPV of 7.10 M€ (Table 5). The economic results are mainly due to two elements: first, the proposed CHP is able to achieve a remarkable amount of energy savings certificates (ESC), whose market value amounts to 0.207 M€/year; second, energy prices are considerably high in Italy, therefore self-production causes significant economic savings. Therefore, even if the primary energy saving is moderate (about 9%), the economic profitability is excellent.

6. Conclusions

The paper presents the energy and economic analysis of a trigeneration system, installed in a hospital located in South Italy. In this scope, a detailed dynamic simulation model was developed in TRNSYS, in order to analyse the behaviour of the proposed system, whereas real data were used about the energy consumption, people scheduling and thermophysical characteristics of the hospital.
The main results are summarized below:
  • Ÿ the trigeneration system produces about 13.74 GWh/year of electric energy with an electric efficiency of 42%; in particular, 92% of the electric energy demand of the hospital is met by the system;
  • Ÿ a limited share of the overall thermal energy demand of the hospital is matched by the cogeneration unit (41%); this is due to the fact that the size of the system was mainly selected on the basis of the power demand of the hospital (much lower than the thermal one), to avoid: (i) the production of excess electric energy (in case of full-load operation or thermal load tracking); (ii) the need for continuous part-load operation, in case of electric load tracking (this latter represents the option actually selected for the system under consideration);
  • Ÿ in spite of a limited primary energy savings index (about 9%), mainly due to the limited share of thermal energy covered by the cogeneration system, excellent economic performance was highlighted by the simulations (payback period equal to 1.5 years, profitability index of 3.88), also due to the significant contribution of the subsidies provided by the current Italian regulation for CHP systems (energy savings certificates, with a market value of 0.207 M€/years).
Further analyses will be carried out, aiming to investigate the influence of the design choices on the performance of the system and the opportunities for improving the efficiency of the trigeneration system, as well as that of the hospital, as a whole.

Author Contributions

All authors provide equality contribute. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Conflicts of Interest

The authors declare no conflict of interest.

Nomenclature

Eenergy (kWh/MWh/GWh)
ESCenergy savings certificates (-)
Jcapital cost (€)
NPVnet present value (€) electric power (kW)
Pelectric power (kW)
PEprimary energy per year (GWh/year)
PESprimary energy saving index (-)
PIprofitability index (-)
SPBsimple payback period (years)
Ttemperature (°C)
Uoverall heat transfer coefficient (W m−2 K−1)
Vvolume of natural gas (Sm3)

Greek Symbols

Δdifference (-)
ηefficiency (-)
ρdensity (kg m−3)
ρssolar reflectance (-)

Subscripts

ACHabsorption chiller
CBcondensing boiler
CHelectric chiller
CHPcombined heat and power system
CCHPcombined cooling, heat and power system
coolcooling
EHWdomestic hot water
elelectric
LOADthe electric energy demand of the user
from GRIDelectric energy withdrawn from the public grid
heatheating
HTthe high temperature thermal energy
MTthe medium temperature thermal energy
NGnatural gas
PSproposed system
RSreference system
treferred to a generic time step
ththermal
SGsteam generator
Steamsteam

References

  1. Calise, F.; Dentice d’Accadia, M.; Libertini, L.; Quiriti, E.; Vanoli, R.; Vicidomini, M. Optimal operating strategies of combined cooling, heating and power systems: A case study for an engine manufacturing facility. Energy Convers. Manag. 2017, 149, 1066–1084. [Google Scholar] [CrossRef]
  2. Faramarzi, G.R.; Khodakarami, M.; Shabani, A.; Saen, R.F.; Azad, F. New network data envelopment analysis approaches: An application in measuring sustainable operation of combined cycle power plants. J. Clean. Prod. 2015, 108, 232–246. [Google Scholar] [CrossRef]
  3. Jiang, J.; Gao, W.; Wei, X.; Li, Y.; Kuroki, S. Reliability and cost analysis of the redundant design of a combined cooling, heating and power (CCHP) system. Energy Convers. Manag. 2019, 199, 111988. [Google Scholar] [CrossRef]
  4. Murugan, S.; Horák, B. Tri and polygeneration systems - A review. Renew. Sustain. Energy Rev. 2016, 60, 1032–1051. [Google Scholar] [CrossRef]
  5. Al Moussawi, H.; Fardoun, F.; Louahlia-Gualous, H. Review of tri-generation technologies: Design evaluation, optimization, decision-making, and selection approach. Energy Convers. Manag. 2016, 120, 157–196. [Google Scholar] [CrossRef]
  6. Chicco, G.; Mancarella, P. From cogeneration to trigeneration: Profitable alternatives in a competitive market. Ieee Trans. Energy Convers. 2006, 21, 265–272. [Google Scholar] [CrossRef]
  7. Gonzales Palomino, R.; Nebra, S.A. The potential of natural gas use including cogeneration in large-sized industry and commercial sector in Peru. Energy Policy 2012, 50, 192–206. [Google Scholar] [CrossRef]
  8. Szklo, A.S.; Soares, J.B.; Tolmasquim, M.c.T. Economic potential of natural gas-fired cogeneration—Analysis of Brazil’s chemical industry. Energy Policy 2004, 32, 1415–1428. [Google Scholar] [CrossRef]
  9. Gimelli, A.; Muccillo, M.; Sannino, R. Optimal design of modular cogeneration plants for hospital facilities and robustness evaluation of the results. Energy Convers. Manag. 2017, 134, 20–31. [Google Scholar] [CrossRef]
  10. Bianco, V.; De Rosa, M.; Scarpa, F.; Tagliafico, L.A. Implementation of a cogeneration plant for a food processing facility. A case study. Appl. Therm. Eng. 2016, 102, 500–512. [Google Scholar] [CrossRef] [Green Version]
  11. Shabbir, I.; Mirzaeian, M. Feasibility analysis of different cogeneration systems for a paper mill to improve its energy efficiency. Int. J. Hydrog. Energy 2016, 41, 16535–16548. [Google Scholar] [CrossRef]
  12. Calise, F.; Dentice d’Accadia, M.; Libertini, L.; Quiriti, E.; Vicidomini, M. A novel tool for thermoeconomic analysis and optimization of trigeneration systems: A case study for a hospital building in Italy. Energy 2017, 126, 64–87. [Google Scholar] [CrossRef]
  13. do Espirito Santo, D.B. An energy and exergy analysis of a high-efficiency engine trigeneration system for a hospital: A case study methodology based on annual energy demand profiles. Energy Build. 2014, 76, 185–198. [Google Scholar] [CrossRef]
  14. Espirito Santo, D.B. Energy and exergy efficiency of a building internal combustion engine trigeneration system under two different operational strategies. Energy Build. 2012, 53, 28–38. [Google Scholar] [CrossRef]
  15. Bracco, S.; Delfino, F. A mathematical model for the dynamic simulation of low size cogeneration gas turbines within smart microgrids. Energy 2017, 119, 710–723. [Google Scholar] [CrossRef]
  16. Zheng, L.; Furimsky, E. ASPEN simulation of cogeneration plants. Energy Convers. Manag. 2003, 44, 1845–1851. [Google Scholar] [CrossRef]
  17. Piacentino, A.; Gallea, R.; Cardona, F.; Lo Brano, V.; Ciulla, G.; Catrini, P. Optimization of trigeneration systems by Mathematical Programming: Influence of plant scheme and boundary conditions. Energy Convers. Manag. 2015, 104, 100–114. [Google Scholar] [CrossRef]
  18. Available online: https://www.gruppoab.com/it/ (accessed on 12 January 2019).
  19. Klein, S.A. TRNSYS-A Transient System Simulation Program; Engineering Experiment Station Report; University of Wisconsin-Madison: Madison, WI, USA, 1988; pp. 12–38. [Google Scholar]
  20. Murray, M.C.; Finlayson, N.; Kummert, M.; Macbeth, J. Live Energy Trnsys—Trnsys Simulation within Google Sketchup. In Proceedings of the 475 Eleventh International IBPSA Conference, Glasgow, Scotland, 27–30 July 2009. [Google Scholar]
  21. Buonomano, A.; Calise, F.; Palombo, A.; Vicidomini, M. BIPVT systems for residential applications: An energy and economic analysis for European climates. Appl. Energy 2016, 184, 1411–1431. [Google Scholar] [CrossRef]
  22. Handbook, A. HVAC Systems and Equipment; American Society of Heating, Refrigerating, and Air Conditioning Engineers: Atlanta, GA, USA, 1996; pp. 1–10. [Google Scholar]
  23. Available online: http://www.enea.it/it (accessed on 22 December 2019).
Figure 1. Layout of the Combined Cooling, Heat and Power (CCHP) system under analysis.
Figure 1. Layout of the Combined Cooling, Heat and Power (CCHP) system under analysis.
Energies 13 03558 g001
Figure 2. Steam Loop control strategy.
Figure 2. Steam Loop control strategy.
Energies 13 03558 g002
Figure 3. Control strategy regarding absorption chiller (ACH) and JW-HW-HE (Figure 1).
Figure 3. Control strategy regarding absorption chiller (ACH) and JW-HW-HE (Figure 1).
Energies 13 03558 g003
Figure 4. Control strategy of Jacket Water Loop.
Figure 4. Control strategy of Jacket Water Loop.
Energies 13 03558 g004
Figure 5. Hot Water Loop control strategy.
Figure 5. Hot Water Loop control strategy.
Energies 13 03558 g005
Figure 6. Control strategy regarding building space heating and Domestic Hot Water (DHW).
Figure 6. Control strategy regarding building space heating and Domestic Hot Water (DHW).
Energies 13 03558 g006
Figure 7. Building model, front side (left), back side (right).
Figure 7. Building model, front side (left), back side (right).
Energies 13 03558 g007
Figure 8. Miulli hospital.
Figure 8. Miulli hospital.
Energies 13 03558 g008
Figure 9. Electric energy and Natural gas monthly demand.
Figure 9. Electric energy and Natural gas monthly demand.
Energies 13 03558 g009
Figure 10. Calibration: thermal and electric energy demand of the hospital. Simulated data vs. real data.
Figure 10. Calibration: thermal and electric energy demand of the hospital. Simulated data vs. real data.
Energies 13 03558 g010
Figure 11. Dynamic performance of the cogeneration system—daily results.
Figure 11. Dynamic performance of the cogeneration system—daily results.
Energies 13 03558 g011
Figure 12. Energy performance of the proposed layout: electric energy (left) and thermal energy (right).
Figure 12. Energy performance of the proposed layout: electric energy (left) and thermal energy (right).
Energies 13 03558 g012
Figure 13. Energy performance of the Proposed System—Steam production.
Figure 13. Energy performance of the Proposed System—Steam production.
Energies 13 03558 g013
Figure 14. Energy performance of the Proposed System—Cooling demand.
Figure 14. Energy performance of the Proposed System—Cooling demand.
Energies 13 03558 g014
Table 1. Thermoeconomic and environmental assumptions.
Table 1. Thermoeconomic and environmental assumptions.
ParameterDescriptionValueUnit
Jel,fromGRIDGrid electric energy unit cost180€/MWh
JNGAverage Natural gas unit cost for boilers and steam generators29.5€/MWhPE
JNG,CHPAverage Natural gas unit cost for CHP27.5€/MWhPE
JESCEconomic value of ESC 180€/ESC
LHVNGNatural gas lower heating value9.59kWh/Sm3
ηelConventional thermo-electric power plant efficiency46%
ηCBNatural gas condensing boiler efficiency95%
ηSGNatural gas steam generator efficiency75%
AFAnnuity factor8years
Table 2. Thermal zone simulation data.
Table 2. Thermal zone simulation data.
-ABCD
Geometric Features: Volume (m3)9249.8141624.244,787.219,655.9
Ventilation (vol/h)15331
Tset,winter(°C)20 ± 122 ± 221 ± 119 ± 1
Tset,summer(°C)23 ± 124 ± 226 ± 126 ± 1
DHW set point temperature (°C)45
Heating and cooling season (1.610-degree day)15th November–31st March
1st May–30th September
Occupancy schedule00:00–24:0000:00–24:0008:00–18:0000:00–24:00
Simulation Time step (h)0.05
Table 3. Elements of the building envelope.
Table 3. Elements of the building envelope.
Building ElementZones A & B & C & D
U-Value
(W/m2K)
Thickness
(m)
ρs
(–)
ε
(–)
Roof 0.6000.2350.40.9
Façades 0.4920.280
Ground floor 0.6080.560
Adjacent ceiling1.1110.400
Windows glass2.890.004/0.016/0.0040.130.18
Table 4. Design and operating parameters.
Table 4. Design and operating parameters.
ComponentParameterValueUnit
CHP systemModelEcomax 20 HE
ManufacturerAB
Rated thermal capacity 1882kW
Rated electrical capacity 2004
Rated fuel input4544
Rated electrical efficiency44.1%
Rated thermal efficiency43.0
Global rated efficiency87.1
Heat exchanger exhaust gas-condensed vaporRated thermal capacity750kW
Condensed water flow rate1284kg/h
Exhaust gas flow rate 10,753
Dissipator (DISS)Rated thermal capacity1300kW
DHW heat exchanger (DHWHE)Efficiency50%
Average DHW flow rate demand (P8)1360kg/h
Heating water flow rate (P7)40,480
Auxiliary boiler (heating loop CB)Rated thermal capacity10,500kWth
Auxiliary boiler (vapor loop CBVap)Rated thermal capacity4000kWth
Electrical auxiliary chillerRated thermal capacity9000kWth
COP5.95-
Absorption chillerRated cooling capacity769kW
Setpoint temperature for the chilled water7°C
Cooling towerRated thermal capacity1794kW
Table 5. Yearly result summary.
Table 5. Yearly result summary.
Eth,CHPEel,CHP ∆PE PES η el η th η ESC SPB ∆C PI NPV
(GWhth/year)(GWh/year)(GWh/year)(%)(M€/year)(years)(M€/year)(-)(M€)
13.1913.743.278.942.139.4272.540.2071.51.223.887.10
Table 6. Share of energy demand covered by the CCHP system.
Table 6. Share of energy demand covered by the CCHP system.
Eel,fromGRID/Eel,LOADEel,CHP/Eel,LOADEth,CHP,usefull/Eth,demandEth,ACH/Eth,cool
(%)
7.992.140.6528.00

Share and Cite

MDPI and ACS Style

Calise, F.; Cappiello, F.L.; Dentice d’Accadia, M.; Libertini, L.; Vicidomini, M. Dynamic Simulation and Thermoeconomic Analysis of a Trigeneration System in a Hospital Application. Energies 2020, 13, 3558. https://doi.org/10.3390/en13143558

AMA Style

Calise F, Cappiello FL, Dentice d’Accadia M, Libertini L, Vicidomini M. Dynamic Simulation and Thermoeconomic Analysis of a Trigeneration System in a Hospital Application. Energies. 2020; 13(14):3558. https://doi.org/10.3390/en13143558

Chicago/Turabian Style

Calise, Francesco, Francesco Liberato Cappiello, Massimo Dentice d’Accadia, Luigi Libertini, and Maria Vicidomini. 2020. "Dynamic Simulation and Thermoeconomic Analysis of a Trigeneration System in a Hospital Application" Energies 13, no. 14: 3558. https://doi.org/10.3390/en13143558

APA Style

Calise, F., Cappiello, F. L., Dentice d’Accadia, M., Libertini, L., & Vicidomini, M. (2020). Dynamic Simulation and Thermoeconomic Analysis of a Trigeneration System in a Hospital Application. Energies, 13(14), 3558. https://doi.org/10.3390/en13143558

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop