Next Article in Journal
Calculation of the Arc Velocity Along the Polluted Surface of Short Glass Plates Considering the Air Effect
Previous Article in Journal
Analysis and Prediction of Energy Production in Concentrating Photovoltaic (CPV) Installations
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Placement of Combined Heat, Power and Hydrogen Production Fuel Cell Power Plants in a Distribution Network

1
Department of Power and Control Engineering, School of Electrical and Computer Engineering, Shiraz University, Shiraz, Iran
2
Department of Electrical and Electronics Engineering, Shiraz University of Technology, Shiraz, Iran
*
Author to whom correspondence should be addressed.
Energies 2012, 5(3), 790-814; https://doi.org/10.3390/en5030790
Submission received: 5 January 2012 / Revised: 29 January 2012 / Accepted: 20 February 2012 / Published: 19 March 2012

Abstract

:
This paper presents a new Fuzzy Adaptive Modified Particle Swarm Optimization algorithm (FAMPSO) for the placement of Fuel Cell Power Plants (FCPPs) in distribution systems. FCPPs, as Distributed Generation (DG) units, can be considered as Combined sources of Heat, Power, and Hydrogen (CHPH). CHPH operation of FCPPs can improve overall system efficiency, as well as produce hydrogen which can be stored for the future use of FCPPs or can be sold for profit. The objective functions investigated are minimizing the operating costs of electrical energy generation of distribution substations and FCPPs, minimizing the voltage deviation and minimizing the total emission. In this regard, this paper just considers the placement of CHPH FCPPs while investment cost of devices is not considered. Considering the fact that the objectives are different, non-commensurable and nonlinear, it is difficult to solve the problem using conventional approaches that may optimize a single objective. Moreover, the placement of FCPPs in distribution systems is a mixed integer problem. Therefore, this paper uses the FAMPSO algorithm to overcome these problems. For solving the proposed multi-objective problem, this paper utilizes the Pareto Optimality idea to obtain a set of solution in the multi-objective problem instead of only one. Also, a fuzzy system is used to tune parameters of FAMPSO algorithm such as inertia weight. The efficacy of the proposed approach is validated on a 69-bus distribution system.

1. Introduction

1.1. Literature Review

In recent years, the attention to Distributed Generation (DG) units connected to the distribution network has increased [1]. Modular generating systems sized from less than a kilowatt to tens of megawatts and placed at or near consumer locations are considered as DG units [2]. Fuel Cell Power Plants (FCPPs) have advanced the electrochemical energy conversion of devices operating at high temperature and changing the chemical energy of fuel into electrical energy at high efficiency compared with diesel or gas engines. Considering the increasing concerns about the environmental effects in recent years, it is important to generate electrical power with minimum emission and contamination. Since FCPPs generate less pollution with respect to the other generation units, it is very desirable to reduce emission in power systems. Furthermore, FCPPs have less noise compared with internal combustion engines. Also, the maintenance of FCPPs is simple; since there are few moving parts in the system [3].
Many researchers have investigated the placement of DG units in distribution systems. For instance, El-Khattam and colleagues presented a new integrated model to achieve optimal sizing and siting of DG units and considered cost and loss as minimized objectives [4]. Jabr and Pal developed an ordinal optimization method for determining the location and size of DG units [5]. They applied a hybrid genetic algorithm for locating and sizing DG units. A new formulation for the optimum DG unit placement problem was proposed in [6]. This paper considered a hybrid combination of technical factors as minimization of the line losses, the voltage sag problem, etc., as well as the economical factors such as the installation and maintenance costs of the DG units. AlRashidi and AlHajri presented an improved Particle Swarm Optimization (PSO) algorithm for optimal planning of multiple DG units [7]. They divided the problem into two parts: continuous and discrete optimization for optimal sizing and localizing respectively in order to minimize real power losses. A method based on the analysis of power flow continuation and determination of most sensitive buses to voltage collapse was used for placement of DG units in [8]. Celli et al. presented a multi-objective evolutionary algorithm for sizing and locating DG units. Their technique is based on a genetic algorithm and an epsilon-constraint method that produces a set of non inferior solutions [9]. Niknam et al. used a modified honey bee mating optimization algorithm for multi-objective placement of renewable energy resources [10]. They considered conflicting objectives such as the total cost, deviation of the bus voltage, power losses and emission. In order to minimize the power losses and maximizing the profitability, in [11] a new method was proposed which investigated the optimal size and location of biomass fuelled gas turbines in distribution systems. Application and comparison of several metaheuristic techniques for optimizing the placement and supplying the area of biomass-fueled power plants was presented in [12]. In all the above papers, the placement of CHPH FCPPs has not been investigated. Therefore, this problem is assessed in this paper.
This paper assesses the proper cost function for CHPH FCPPs which is essential for the optimal operation and placement of these devices in distributed networks. El-Sharkh et al. perused the optimal cost of CHPH operation of FCPP in different models of cost functions [13,14]. In fact, they used these models to determine the optimal operation strategy that yields the minimum operating cost. Optimal operation management of distribution networks with regard to FCPPs using effective evolutionary algorithms has been investigated by Niknam et al. in [15,16]. Nanaeda et al. considered some operating strategies including optimal sizing of the FCPP, thermal energy storage for dispatching the heat, and operation of FCPP to provide flexible grid power [17]. Ren and Gao evaluated two micro CHP systems including gas engine and FCPP for residential buildings in terms of minimum-cost operation and minimum-emission operation [18]. They showed that the FCPP system is a better option for residential buildings both economically and environmentally.
Since the load flow is the bare bone essential for calculating the objective functions, the proposed problem can be considered as a mixed integer nonlinear optimization problem. Therefore, this paper utilizes a new evolutionary algorithm called Fuzzy Adaptive Modified Particle Swarm Optimization (FAMPSO) for the placement of CHPH FCPPs in the distribution networks. The PSO algorithm is an evolutionary algorithm first proposed by Kennedy and Eberhart [19,20]. It is used for solving the nonlinear mixed integer and the complex optimization problem [21,22,23,24,25]. The performance of the PSO algorithm is highly dependent on its parameters such as inertia weight and learning factors. Therefore, a fuzzy system is used to adjust the inertia weight [22,26].
Nowadays, as the result of the increase in fuel prices and consequently the augment in electrical power costs, it is important to find a way to produce electricity for distribution networks and customers with lower operating costs. The CHPH operation of FCPP can decrease operating costs. Also, considering the increasing concern over environmental protection in recent years, it is important to generate electricity with minimum emissions. Moreover, the power quality is an important issue in transmission and distribution networks, and this issue is becoming more significant. Voltage deviation can satisfy the power quality concern and improve it. Therefore, the operating cost, voltage deviation and emission are considered simultaneously as objective functions in this paper. Since the objectives are different, non-commensurable and nonlinear, it is difficult to solve the problem using conventional approaches that may optimize a single objective. Therefore, this paper modifies the mentioned algorithm for enhancing the performance of the algorithm to eliminate these conflictions. During the optimization process, a set of obtained non-dominated solutions, called Pareto optimal solutions, is stored in an external memory called repository.

1.2. Contributions

In the mentioned papers, the placement of the FCPPs and the effect of CHPH operation of FCPPs are considered independently while they have a direct influence on each other. Therefore, in the proposed approach, both of the issues are investigated simultaneously. In this paper will be shown that considering the effect of CHPH operation of FCPPs is very effective in reducing the cost.
In conclusion, the main contributions of this paper are as follows: (i) the placement of FCPPs considering the effect of CHPH operation of FCPPs is investigated; (ii) the problem is solved in a multi-objective framework with different strategies for considering the effect of produced hydrogen and thermal energy; (iii) the idea of non-dominated solutions called Pareto optimal solutions is utilized to find all optimal solutions; and (iv) the performance of the algorithm is improved using a new mutation operator and a fuzzy-based adjustment technique.

2. Placement of FCPPs in Distributed Networks

The main goal of this paper is to determine the best location for FCPPs by a trade-off between the different and conflicting objective functions. Therefore, this section introduces objective functions as well as the main constraints for solving the problem.

2.1. Objective Functions

2.1.1. Operating Cost of Energy

The operating cost function includes the cost of electrical energy generated by substation bus and FCPPs, the cost of thermal energy generated by FCPPs, and the cost of hydrogen produced. This paper considers thermal and electrical loads that FCPPs can supply them. If the FCPP is not able to supply all the thermal loads, the amount of thermal loads that are not supplied should be fed by natural gas. The operating cost function is modeled as follows [13,14]:
f 1 ( X ) = t = 1 T ( P S u b t × C S u b + C n 1 j N F C P P ( P F C P P j t + P H j t η j ) + C n 2 i N b u s max ( L t h i P t h i t , 0 ) + O M C H s j N F C P P ( P H j t × H f a c t o r ) )
X = [ L F C P P P F C P P ] 1 × n × ( 1 + T )
L F C P P = [ l o c a t i o n 1 l o c a t i o n 2 ... l o c a t i o n n ] 1 × n
P F C P P = [ P F C P P 1 P F C P P 2 ... P F C P P n ] 1 × n × T
P F C P P j = [ P F C P P j 1 P F C P P j 2 ... P F C P P j t ... P F C P P j T ] 1 × T
The cost objective function includes five terms: (1) cost of energy prepared by substation bus ($); (2) overall fuel cost for FCPPs ($); (3) cost of purchased gas for thermal load if the thermal energy produced by FCPPs is not enough to meet the thermal energy demand ($); (4) the operation and maintenance cost of the FCPPs ($); and (5) the income from the sale of the generated hydrogen by FCPPs ($). The amount of heat generated by FCPP has been developed in [13,14], as follows:
P L R j = P F C P P j t P M a x , F C P P F o r P L R j 0.05 ,             η j = 0.2716 , r T E j = 0.6801
F o r      P L R j 0.05 ,           η j = 0.9033 P L R j 5 2.999 P L R j 4 + 3.6503 P L R j 3                  2.0704 P L R j 2 + 0.4623 P L R j + 0.3747
r T E j = 1.0785 P L R j 4 1.9739 P L R j 3 + 1.5005 P L R j 2          0.2817 P L R j + 0.6938
The efficiency value and the ratio of thermal energy to electrical energy are both functions of the PLR. The amount of thermal energy generated by FCPP is based on the amount of the output electrical energy and is calculated as follows [13,14]:
P t h i t = r T E j ( P P C P P j t + P H j t )
P M a x , F C P P = P P C P P j t + P H j t

2.1.2. Emission

Summation of FCPPs and substation bus emissions is one of the major objectives of the placement of FCPPs problem that can be described as follows [15]:
f 2 ( X ) = t = 1 T ( E g r i d t + j = 1 N F C P P E F C P P , j t )
E g r i d t = P S u b t × e g r i d , S O 2 + P S u b t × e g r i d , N O x
E F C P P j t = P F C P P j t × e F C P P , S O 2 + P F C P P j t × e F C P P , N O x
where E g r i d t and E F C P P j t are the emission produced by grid and FCPPj units during time t, respectively; e g r i d , S O 2 and e g r i d , N O x are the emission coefficients of the grid; e F C P P , S O 2 and e F C P P , N O x are the emission coefficients of FCPP units.

2.1.3. Voltage Deviation

Decreasing the voltage deviation can enhance the power quality. Mathematically, it can be defined as follows [15]:
f 3 ( X ) = t = 1 T i = 1 N b u s ( | V r e f V i t | V r e f ) × Δ t N B u s
where V r e f and V i t are nominal voltage and voltage magnitude of the bus i during time t respectively. N b u s and T are the total number of buses and total time, respectively.

2.2. Constraints

2.2.1. Bus Voltage Limits

The voltage profile is maintained within specified limits, as follows [16]:
V M i n | V i t | V M a x
where V M i n and V M a x are the lowest and the highest voltage levels of each bus respectively. Also | V i t | is the magnitude of voltage in the bus i.

2.2.2. Active Power Output of FCPPs

The amount of active power output of each FCPP is limited, as follows [16]:
P F C P P , j t , min P F C P P , j t P F C P P , j t , max
where P F C P P , j t , min and P F C P P , j t , max are the minimum and the maximum active power produced by FCPPj during time t respectively.

3. Multi-Objective Approach for Pareto Optimal Solutions

The optimum Pareto method includes a set of solutions. In fact, all dominant solutions are shown in a graph which is called Pareto graph. One solution ( X 1 ) can dominate another solution ( X 2 ) if the below equation is satisfied [10]:
{ i = 1 , ... , m      f i ( X 1 ) f i ( X 2 ) i f i ( X 1 ) f i ( X 2 )
If X 1 dominates X 2 , X 1 is stored in the repository as a non-dominate solution. Solutions in the repository make up the Pareto graph. One solution can go into the repository if it can satisfy the following conditions:
  • Repository is not full
  • The answer is not dominated by any of the solutions in the repository.

4. Best Compromise Solution

The decision maker needs to select one solution as the best compromise solution among the Pareto optimal set of non-dominated solutions. Since the mentioned objective functions are imprecise, they are formulated as fuzzy sets. In this procedure, a fuzzy membership function is used to specify the best compromise solution. For any particle in the repository, the membership function of each objective function is defined as follows [10]:
μ f i ( X ) = { 0 f i ( X ) f i max f i max f i ( X ) f i max f i min f i min f i ( X ) f i max 1 f i ( X ) f i min
where f i min and f i max are the lower and the upper bounds of the ith objective function. In the proposed algorithm, the values of f i min and f i max are evaluated using the results obtained by optimizing each objective, separately.
The normalized membership value is calculated for each particle in the repository as follows [10]:
N μ ( X i ) = k = 1 h w k × μ f k ( X i ) i m k h w k × μ f k ( X i )
where h is the number of objective functions, m is the number of non-dominated solutions in the repository and w k is the weight of the kth objective function. The best compromise solution is the one which has the maximum value of N μ .

5. PSO Algorithm

5.1. Original PSO Algorithm

PSO algorithm is a population-based stochastic optimization method. The algorithm is derived by the social behavior of bird flocks, colonies of insects, schools of fishes, and groups of animals feeding and traveling together. The algorithm is started by initializing a population of random solutions called particles and searches for the best position by updating production through the following velocity and position update equations. The velocity and position are updated by the following equations:
V e l j k + 1 = ω × V e l j k + C 1 × r a n d ( . ) × ( P B e s t , j k X j k ) + C 2 × r a n d ( . ) × ( G B e s t k X j k )
X j k + 1 = X j k + V e l j k + 1
where V e l j k is the current velocity of particle j at iteration k, V e l j k + 1 is the modified velocity of particle j at iteration k + 1 , r a n d ( . ) is the random number between 0 and 1, X j k is the current position of particle j at iteration k . The particles have memory and each particle keeps track of its previous best position (called the P B e s t k ) and its corresponding fitness. There exist a number of P B e s t k for the respective particles in the swarm and the particle with the greatest fitness is called the global best ( G B e s t k ) of the swarm. The learning factors C 1 and C 2 can control each particle to move in a single iteration. Typically, these are both set to a value of 2.0 [20]. The inertia weight ω is used to control the convergence behavior of the PSO. Typical implementations of the PSO adapt the value of ω during the training stage, e.g., linearly decreasing it from 1.0 to near 0 over the execution. Convergence can be obtained with fixed values, as shown in [20]. Since in this method the initial population is generated randomly similar to the other optimization methods, so the program may be not robust. The lower convergence rate is a disadvantage in this method rather than the classical and gradient-based methods.

5.2. Modified PSO Algorithm

In its part, a new mutation is applied to the PSO algorithm to increase the population diversity and preventing premature convergence. Inopportune convergence may happen under different situations: the population has converged to local optima of the objective function or the population has lost its variety or the search algorithm has proceeded slowly. Variegating the PSO population and amending its performance in a hindering inopportune convergence to local minima mutation are potent strategies. This paper uses a new mutation operator. In this method the algorithm selects three different particles from the initial population and mutates the population using these particles. To cover the whole searching region, in each iteration X m 1 X m 2 X m 3 X j are selected and are mutated by other particles within the population. A mutant vector X m u t , j k is generated as:
X m u t , j k = X m 1 k + r a n d ( . ) × ( X m 2 k X m 3 k ) X m u t , j k = [ x m u t 1 , x m u t 2 , ... , x m u t D ]
Then the mutant vector is mixed with each swarm of population to obtain the trial vector as follows:
X n e w , j k = [ x n e w , 1 k , x n e w , 2 k , ... , x n e w , D k ] x n e w , z k = { x m u t , z k i f C r r a n d ( . ) x s w a r m , z k o t h e r w i s e
where Cr is a number between 0.1 and 0.9, and r a n d ( . ) is a random number between zero and one. If the problem is a kind of single objective optimization X n e w , j k and X s w a r m , z k are compared in terms of cost function value, as follows:
X s w a r m , j k + 1 = { X n e w , j k i f f ( X n e w , j k ) f ( X s w a r m , j k ) X s w a r m , j k o t h e r w i s e
If the objective function value of X n e w , j k ( f ( X n e w , j k ) ) is less than the objective function value of X s w a r m , j k ( f ( X s w a r m , j k ) ) , X n e w , j k is replaced by X s w a r m , j k in the next generation. When the problem is multi-objective, if X n e w , j k dominates X s w a r m , z k , X n e w , j k is replaces by X s w a r m , j k in the next generation.

5.3. Fuzzy Adaptive PSO

The procedure of the proposed FAPSO begins like the standard PSO described in Section 4.2. The main difference is that the proposed FAPSO utilizes a fuzzy logic to adaptively adjust inertia weights instead of using the fixed constant in the original PSO. The parameters of PSO algorithm have a salient influence on the performance of the search process. Inertia weight directly affects the convergence of the algorithm. Large amounts of inertia weight cause the particle to search for new parts of space related to optimization problem; in other words they perform a global search. Also, the local search can be included for less values of inertia weight. Local search is suitable for increasing the accuracy of an existing answer while global search is used to find possible better answers in unknown places within the search space. To establish a better balance between global search and local search, the inertia weight needs to be adjusted. By appropriate selection of ω, the algorithm requires less iterations on average to locate the global optimum solution [22,26]. In this way, the process allows the swarm to explore the search space in the beginning of the run for finding global optimum, and still manages to shift towards a local search when fine-tuning is required. Based on the mentioned reasons, the best candidate for this process is using a fuzzy system to adjust the inertia weight.
The Mamdani-type fuzzy is a good candidate for dynamically tuning the inertia weight of the PSO. The current best performance evaluation and the current inertia weight are selected as input for the fuzzy system. Changing the inertia weight is the output of fuzzy system. The normalized fitness value NFV is used as an input variable between 0 and 1, and is defined as [27]:
N F V = F V F V min F V max F V min
The calculated value of NFV from (25) at the first iteration may be used as F V min for the next iterations. F V max is a very large value, which is greater than any acceptable feasible solution. The typical inertia weight value is 0.4 ω 0.9 , therefore, both positive and negative corrections are required for the inertia weight. So, a range of −0.1 to 0.1 has been chosen for the inertia weight correction values [27]:
ω k + 1 = ω k + Δ ω
The input fuzzy variables are classified in three fuzzy sets of linguistic values: S (small), M (medium) and L (large) with associated membership functions as shown in Figures 1(a,b). Also, the output variable is defined in three fuzzy sets of linguistic values: NE (negative), ZE (zero) and PE (positive) as shown in Figure 1(c). The Mamdani-type fuzzy rule is employed to formulate the conditional statements including fuzzy logic. For example:
R i : I f ( N F V i s S ) a n d ( ω i s M ) T h e n ( Δ ω i s N E )
Each rule represents a mapping from the input into the output space and determines the inertia weight correction ( Δ ω ) in each iteration. These fuzzy rules are shown in Table 1.
Figure 1. Membership functions of inputs and outputs (a) NFV (b) ω (c) ∆ω.
Figure 1. Membership functions of inputs and outputs (a) NFV (b) ω (c) ∆ω.
Energies 05 00790 g001
Table 1. Fuzzy rules for variations of the inertia weight.
Table 1. Fuzzy rules for variations of the inertia weight.
∆ω Ω
SML
NFVSZENENE
MPENENE
LPEZENE

6. Implementing FAMPSO for Placement of FCPPs

In this section, the proposed FAMPSO algorithm for the placement of FCPP is described in detail:
  • Step 1: Data Input, including cost coefficients of FCPPs, emission coefficients of FCPPs, network data, thermal and electrical loads, number of population, initial value of inertia weight and values of learning factors.
  • Step 2: Generation of initial population Xj and an initial velocity Velj, which must satisfy constraints, as follows:
    P o p u l a t i o n = [ X 1 X 2 ... X N ] N × n × ( 1 + T )
    X j = [ L F C P P P F C P P ] 1 × n × ( 1 + T )
    L F C P P = [ l o c a t i o n 1 l o c a t i o n 2 ... l o c a t i o n n ] 1 × n
    P F C P P = [ P F C P P 1 P F C P P 2 ... P F C P P n ] 1 × n × T
    P F C P P j = [ P F C P P j 1 P F C P P j 2 ... P F C P P j t ... P F C P P j T ] 1 × T
    V e l o c i t y = [ V e l 1 V e l 2 ... V e l N ] N × n × ( 1 + T )
    V e l j = [ V e l L F C P P V e l P F C P P ] 1 × n × ( 1 + T )
    V e l L F C P P = [ V e l l o c a t i o n 1 V e l l o c a t i o n 2 .... V e l l o c a t i o n n ] 1 × n
    V e l P F C P P = [ V e l P F C P P 1 V e l P F C P P 2 .... V e l P F C P P n ] 1 × n × T
    V e l P F C P P j = [ V e l P F C P P j 1 V e l P F C P P j 2 ... V e l P F C P P j t ... V e l P F C P P j T ] 1 × T
    where N is the number swarms in the population and n is the number of FCPPs, locationn is the location of FCPPn, P F C P P n t is active power generated by FCPPn during time t. locationn changes between 1 and maximum number of the buses and P F C P P n t changes between 0 and maximum capacity of FCPPn. V e l l o c a t i o n n and V e l P F C P P n t are velocities of locationn and P F C P P n t , respectively.
  • Step 3: Evaluation of objective functions. The objective functions (Equation (1), Equation (11), and Equation (14)) are calculated for each particle using the result of load flow distribution.
  • Step 4: Select P B e s t k .
The locations and real power output of all FCPPs are represented as the position of the particle in the swarm. The best position of a particle is P B e s t k .
  • Step 5: Non-dominated solutions of initial population are determined and stored in the repository.
  • Step 6: Select G B e s t k .
Normalized membership values are calculated [Equation (19)] for non-dominated solutions in the repository. The G B e s t k is a solution which has the biggest value of N μ .
  • Step 7: Set i = 1.
  • Step 8: Update velocity and position.
To update the position of each individual, it is necessary to calculate the velocity of each individual in the next stage which is obtained from (20). The position of each individual is updated by (21).
  • Step 9: Implement mutation as described in Section 5.2.
  • Step 10: Select the non-dominate solutions. If the particle i is a non-dominated solution, it is stored in the repository.
  • Step 11: If all of the individuals are selected, go to Step 12, otherwise set up i = i + 1 and return to Step 8.
  • Step 12: Update P B e s t k . P B e s t k is updated when one of the following conditions is satisfied, otherwise it would be the same as the previous mentioned population:
    • If the current individual dominates the former P B e s t , it is considered as P B e s t k .
    • If no one dominates another, the one that its normalized membership function is greater will be considered as P B e s t k .
  • Step 13: Update G B e s t k . For updating G B e s t k , non-dominated solutions in the repository are sorted with respect to the value of N μ and the solution which has the biggest value of N μ is selected as G B e s t k .
  • Step 14: Update the inertia weight ω . In this algorithm, the suitable selection of inertia weight ω is updated by the fuzzy rules described in Section 5.3.
  • Step 15: Check the termination criteria. If the termination criterion is met, finish the algorithm, otherwise go to Step 7 and repeat the process.

7. Simulation Results

In this section, the mentioned optimization algorithm has been employed for placement of FCPPs on a 69-bus distribution system. This network consists of one source transformer and 68 load points. The total system load is 3802 (kW). The system base values are Vb = 12.66 kV and Sb = 10 MVA. The system data are given in [28] and the single line diagram of this system is shown in Figure 2. The thermal load is considered as 0.4 of the active load on each feeder. In this network, four FCPPs are placed and each of these sources can generate 250 kW. Information regarding the gas price, hydrogen selling price and the parameters of cost objective function are shown in Table 2 and the values of emission coefficients are shown in Table 3.
Figure 2. Single line diagram of distribution test system.
Figure 2. Single line diagram of distribution test system.
Energies 05 00790 g002
Table 2. Information of cost parameters.
Table 2. Information of cost parameters.
ParameterValue
Cost of substation active power Csub ($/kWh)0.035
Price of natural gas for FCPPs Cn1 ($/kWh)0.04
Fuel price for thermal loads Cn2 ($/kWh)0.05
operation and maintenance cost of FCPPs OM ($/h)19.32
Hydrogen selling price CHs ($/kg)1.8
Table 3. Emission coefficients related to NOx and SO2.
Table 3. Emission coefficients related to NOx and SO2.
Emission coefficients (gr/kWh)
Emission typeSubstationFCPP
NO x30.015
SO260.024
Four strategies are considered for the cost objective function, as follows:
  • Strategy 1: Neglecting the effect of hydrogen and thermal energy produced by FCPPs and supplying thermal loads just with natural gas.
  • Strategy 2: Considering the effect of thermal energy on supplying thermal loads.
  • Strategy 3: Considering the effect of Hydrogen production by FCPP.
  • Strategy 4: Investigating the effect of both thermal supplement and hydrogen production.
The daily load variation in this problem is shown in Figure 3.
Figure 3. Daily load variation.
Figure 3. Daily load variation.
Energies 05 00790 g003
At first, all objective functions are optimized separately. Table 4 presents a comparison among the results obtained by FAMPSO algorithm for the placement of FCPPs considering four strategies for the cost objective function. Table 5 shows the value of thermal energy and hydrogen produced by each FCPP. As shown in Table 4, the lowest cost value is related to the strategy in which both thermal energy and hydrogen produced have been considered. The highest cost value is related to the strategy in which thermal energy and hydrogen produced by FCPPs are not considered. In the strategy which considers the effect of thermal energy produced by FCPPs in the cost objective function, the cost value is less than that of the strategy which considers the effect of hydrogen produced by FCPPs on the cost objective function. In fact, the reason is that the value of thermal energy produced by FCPPs is more than the amount of hydrogen produced by FCPPs. Table 5 shows that the equivalent electrical energy generated by produced hydrogen of FCPPs is low. Because the maximum capacity of FCPP 1, 2&3 are used to generate electrical energy, the equivalent amount of electrical energy produced by hydrogen is zero for these FCPPs and only FCPP 4 produces electrical energy using hydrogen. In those strategies that don’t use the thermal energy generated by FCPPs, thermal loads must be supplied by natural gas which can cause increase in cost value. Therefore, the CHPH operating of FCPP decreases cost objective function effectively and data in Table 4 confirm these results. The convergence plots of FAMPSO for four strategies of cost function are shown in Figure 4, Figure 5, Figure 6 and Figure 7. The results for the placement of FCPPs considering emission and voltage deviation objective functions are presented in Table 6. The FCPPs are electrical power sources with extremely low amount of emission which can affect the emission objective function significantly. Table 6 shows that the voltage deviation objective function is placed at a very low level. Convergence plots of FAMPSO for emission and voltage deviation objective functions are shown in Figure 8 and Figure 9.
Table 4. Results obtained by optimizing the Cost.
Table 4. Results obtained by optimizing the Cost.
Strategies Cost ($)CPU time (s)FCCPs locations (Bus Number)Total electrical energy generation in a day (kW)
Strategy 18.6574 × 103176.364,61,62,656 × 103, 6 × 103, 6 × 103, 1.346 × 103
Strategy 27.6996 × 103181.664.62,61,656 × 103, 6 × 103, 6 × 103, 1.716 × 103
Strategy 38.6569 × 103179.464,61,62,656 × 103, 6 × 103, 6 × 103, 1.345 × 103
Strategy 47.5472 × 103184.261,64,62,656 × 103, 6 × 103, 6 × 103, 1.404 × 103
Table 5. Results obtained for thermal energy & hydrogen production for FCPPs by optimizing the Cost.
Table 5. Results obtained for thermal energy & hydrogen production for FCPPs by optimizing the Cost.
Strategies Total electrical energy generation by hydrogen production in a day (kW)Total thermal energy generation in a day (kW)
FCCP1FCCP1FCCP1FCCP4FCCP1FCCP2FCCP3FCCP 4
Strategy 100000000
Strategy 200006.0432 × 1036.0432 × 1036.0432 × 1031.1794 × 103
Strategy 30004.6547 × 1030000
Strategy 40004.5959 × 1036.0432 × 1036.0432 × 1036.0432 × 1034.067 × 103
Figure 4. Convergence plot of FAMPSO for cost function without considering CHPH.
Figure 4. Convergence plot of FAMPSO for cost function without considering CHPH.
Energies 05 00790 g004
Figure 5. Convergence plot of FAMPSO for cost function considering CHP.
Figure 5. Convergence plot of FAMPSO for cost function considering CHP.
Energies 05 00790 g005
Figure 6. Convergence plot of FAMPSO for cost function considering H.
Figure 6. Convergence plot of FAMPSO for cost function considering H.
Energies 05 00790 g006
Figure 7. Convergence plot of FAMPSO for cost function considering CHPH.
Figure 7. Convergence plot of FAMPSO for cost function considering CHPH.
Energies 05 00790 g007
Table 6. Results obtained by optimizing the emission and voltage deviation.
Table 6. Results obtained by optimizing the emission and voltage deviation.
ObjectiveEmission (gr)Voltage deviation (pu)CPU time (s)FCCPs locations (Bus Number)Total electrical energy generation in a day (kW)
Emission6.3132 × 105129.262,64,63,616 × 103, 6 × 103, 6 × 103, 6 × 103
Voltage deviation0.3636126.425,27,65,266 × 103, 6 × 103, 6 × 103, 6 × 103
Figure 8. Convergence plot of FAMPSO for emission function.
Figure 8. Convergence plot of FAMPSO for emission function.
Energies 05 00790 g008
Figure 9. Convergence plot of FAMPSO for Voltage deviation function.
Figure 9. Convergence plot of FAMPSO for Voltage deviation function.
Energies 05 00790 g009
The proposed algorithm has been implemented to optimize the objective functions simultaneously. In Figure 10, Figure 11, Figure 12 and Figure 13, the distribution of the Pareto optimal set over the trade-off surface for the three objectives using the four mentioned strategies considered for cost objective function are shown. In each figure, the best compromise solution is shown by a red circle. Here, in Equation (19) wi = 0.33, i = 1, 2, 3 for three objective functions.
Figure 10. Pareto front for cost considering strategy 1, emission and voltage deviation objective functions.
Figure 10. Pareto front for cost considering strategy 1, emission and voltage deviation objective functions.
Energies 05 00790 g010
Figure 11. Pareto front for cost considering strategy 2, emission and voltage deviation objective functions.
Figure 11. Pareto front for cost considering strategy 2, emission and voltage deviation objective functions.
Energies 05 00790 g011
Figure 12. Pareto front for cost considering strategy 3, emission and voltage deviation objective functions.
Figure 12. Pareto front for cost considering strategy 3, emission and voltage deviation objective functions.
Energies 05 00790 g012
Figure 13. Pareto front for cost considering strategy 4, emission and voltage deviation objective functions.
Figure 13. Pareto front for cost considering strategy 4, emission and voltage deviation objective functions.
Energies 05 00790 g013
Table 7 presents a comparison among the results obtained by the proposed FAMPSO algorithm for placement of FCPPs to optimize the objective functions simultaneously considering four strategies for the cost objective function. Table 8 shows the values of thermal energy and hydrogen produced by each FCPP for different strategies of the cost objective function. In multi objective optimization, as shown in Table 7, the lowest cost value is related to strategy 4 and the highest cost value is related to strategy 1. Electrical energy produced by FCPPs releases less pollution in the environment and is very effective in reducing the voltage deviation. Therefore, in the multi objective optimization case, considering emission, voltage deviation, and cost as objective functions result in the FCPPs with higher capacity which are used to generate electrical energy as well as reduce the amount of electrical energy produced by hydrogen. Table 8 demonstrates the above statement where, using FCPPs with more capacity for producing electrical energy causes an increasing production of thermal energy. In this paper the output power of each FCPP is considered to be constant. Since the total capacity of FCPPs supplies a low percentage of the total load and considering the problems of distribution network such as high losses, it is more economical to use the total capacity of FCPPs. As the results show, FCPPs in different cases are used in their maximum or close to their nominal capacity.
Table 7. Results of best compromise solution for multi objective optimization.
Table 7. Results of best compromise solution for multi objective optimization.
Strategies Cost ($)Emission (gr)Voltage deviation (pu)CPU time (s)FCCPs locations (Bus Number)Total electrical generation in a day (kW)
Strategy 19.0838 × 1036.3553 × 1050.4156236.220,65,63,596 × 103, 6 × 103, 6 × 103, 5.815 × 103
Strategy 17.9386 × 1036.3687 × 1050.3857238.762,25,63,196 × 103,6 × 103, 6 × 103,6 × 103
Strategy 38.9432 × 1036.4551 × 1050.3993240.864,17,18,636 × 103, 6 × 103, 6 × 103, 5.11 × 103
Strategy 47.8233 × 1036.3856 × 1050.4168241.361,59,23,656 × 1103, 6 × 103, 6 × 103, 5.505 × 103
Table 8. Results obtained for thermal energy & hydrogen production for FCPPs by multi objective optimization.
Table 8. Results obtained for thermal energy & hydrogen production for FCPPs by multi objective optimization.
Results obtained for thermal energy & hydrogen production for FCPPs by multi objective optimization.
Strategies Total electrical energy generation by hydrogen production in a day (kW)Total thermal energy generation in a day (kW)
FCCP 1FCCP 2FCCP 3FCCP 4FCCP 1FCCP 2FCCP 3FCCP 4
Strategy 100000000
Strategy 200006.0432 × 1036.0432 × 1036.0432 × 1036.0432 × 103
Strategy 3000889.4078000
Strategy 4000494.72116.0432 × 1036.0432 × 1036.0432 × 1035.5693 × 103
Each Pareto optimal solution is an alternative choice for a decision maker. The decision maker can adopt one of them for the respective system based on objective function preferences. In fact, after obtaining the Pareto optimal solutions, the decision maker needs to choose one best compromise solution according to the specific preference for different applications. After generating the Pareto set by FAMPSO, the normalized fuzzy membership function, i.e., Equation (19) is applied to select the best compromise solution of this set. It should be noted that in the fuzzy decision making approach, the importance of the objective functions should be determined. In this regard, w i refers to the importance of the objective functions such that i = 1 3 w i = 1 (in this paper w 1 , w 2 and w 3 shows the importance of cost considering strategy 4 (f1), emission (f2), and voltage deviation (f3) objective functions, respectively).
This paper includes four cases in order to better illustrating the multi-objective placement of FCCP units with CHPH operation problem. Three of the cases solve the proposed problem as a single objective and in the other case the proposed problem is solved as a multi-objective functions considering strategy 4. The results are classified into the following cases:
  • Case I: considering the f1 function
  • Case II: considering the f2 function
  • Case III: considering the f3 function
  • Case IV: considering f1, f2 and f3 functions
The results of executing the fuzzy decision making approach over Pareto optimal solutions in case IV are illustrated in Table 9. In this table some combinations of decision maker preferences in objective functions are considered as wi. To compare single-objective with multi-objective optimization, cases I to IV are devoted to the single objective optimization results.
Table 9. Fuzzy decision making on Pareto optimal set.
Table 9. Fuzzy decision making on Pareto optimal set.
CasesImportancef1 (kW)f2 (gr)f3 (pu)
w1w2w3
Case I---7.5472 × 1036.7561 × 1050.4716
Case II---7.9170 × 1036.3132 × 1050.4377
Case III---7.9656 × 1036.4380 × 1050.3636
Case IV0.330.330.337.8233 × 1036.3856 × 1050.4168
0.40.40.27.7192 × 1036.4308 × 1050.45
0.40.20.47.6783 × 1036.4972 × 1050.419
0.20.40.47.9239 × 1036.3310 × 1050.4071
0.80.10.17.5620 × 1036.7642 × 1050.4431
0.10.80.17.9184 × 103 6.3168 × 1050.4408
0.10.10.87.9636 × 1036.4328 × 1050.3638
Analyzing the results outcomes the following points:
-
In Cases I–III, when each objective is minimized individually, its value is the best one among the cases. Also, it can be seen that when each objective reaches its minimum value, the value of the other objectives will increase with respect to their minimum (when they are minimized in a single objective optimization process).
-
Objectives f1 and f2 are conflicting. To minimize the emissions, FCPPs should generate more active power, so the energy costs will be increased. The results of Cases I, II, and IV-3, 4, 5 and 6 support this fact.
-
Objectives f1 and f3 are conflicting. For instance, in case IV when w 1 = 0.8 and w 3 = 0.1, the cost function and voltage deviation are 7.5620 × 103 $ and 0.4431 pu, respectively; in contrast when w 1 = 0.1 and w 3 = 0.8, the cost and voltage deviation are 7.9636 × 103 $ and 0.3638 pu, respectively. The results of cases I, III and IV 2 and 4 confirm the above statements.
-
The objectives f2 and f3 have similar interests. In cases IV-3 and 4 when the importance of f2 is fixed and the importance of f3 is increased, the value of f2 decreases.
-
In cases I and II when the value of f2 is decreased, the value of f3 is also decreased.
-
In case IV when the importance of f1 is decreased the values of f2 and f3 are increased.
-
Case IV-1 has a suitable tradeoff between all objective functions.

8. Conclusions

In this paper, a multi-objective FAMPSO algorithm was proposed and applied to locate FCPPs in distribution systems. The objective functions consists of the total cost of the system (including the CHPH FCPP units), the total emission produced by the system and the voltage deviation of each bus from its nominal value. The mentioned algorithm uses the concept of Pareto optimality. One of the most important privileges of the multi-objective formulation is that it allows the decision maker to apply his personal experiences in selecting any of the non-dominated solutions called Pareto optimal solutions in the repository. To improve the original PSO algorithm, the mating process is enhanced to improve the exploration ability of the algorithm in the entire search space. In this paper, the effect of hydrogen production and thermal recovery on the optimal cost of FCPP units in a distribution network was investigated. Results show that considering the effect of heat and hydrogen produced by FCPPs reduces the cost extremely, which obviously causes in a significant cost savings. Using FCPPs in distributed networks reduces emission and voltage deviation, which are benefits for the grid operator. Due to the increase in the energy demand all over the World, reducing the cost is crucial. In this regard, the cost objective function includes the production cost, thermal recovery, hydrogen production and the charge of buying natural gas to satisfy the thermal loads. In this paper the proposed procedure gives the decision maker a very good point of view for selecting the best solution between the Pareto optimal solutions. In conclusion, this paper introduces an efficient algorithm with a low convergence time while investigating the actual model of grid and FCPPs. The simulation results show the satisfying and good performance of the proposed method.

Nomenclature

P S u b t
active power produced by the substation of network
P F C P P j t
active power generated by FCPPj during time t
C n 1
price of purchasing natural gas for FCPPs
C n 2
fuel price for thermal loads
P M a x , F C P P
maximum power of FCPP
P H j t
equivalent electric power for hydrogen production during time t
η j t
efficiency of FCPPj during time t
N F C P P
total number of FCPPs
N b u s
total number of buses
L t h i
thermal load demand of bus i
P t h i t
produced thermal by FCPP in bus i if there is a FCPP in this bus during time t
O M
operation and maintenance cost of FCPPs
C S u b
cost of substation active power
C H S
hydrogen selling price
T
the total time
l o c a t i o n n
the location of FCPPn
r T E j
thermal energy to electrical energy ratio
P L R j
part load ratio of FCPPj (equal to electrical generated power/maximum power)
H f a c t o r
a conversion factor (kg of hydrogen/kW of electric power), where H f a c t o r = 1.05 × 10 8 / v c e l l and v c e l l is the cell operating voltage, v c e l l = 0.6 v o l t
X
optimization variable
E g r i d t
emission produced by grid during time t
E F C P P j t
emission produced by FCPPj units during time t
e g r i d , S O 2
emission coefficient of grid
e g r i d , N O x
emission coefficient of grid
e F C P P , S O 2
emission coefficient of FCPP units
e F C P P , N O x
emission coefficient of FCPP units
V r e f
nominal voltage
V i t
voltage magnitude of the bus i during time t
V M i n
lowest voltages of each bus
V M a x
highest voltages of each bus
P F C P P , j t , min
minimum of active power produced by FCPPj during time t
P F C P P , j t , max
maximum of active power produced by FCPPj during time t
f i min
lower bound of each objective function
f i max
upper bounds of each objective function
μ f i ( X )
membership function of each objective function
N μ ( X i )
normalized membership value of each particle in the repository
h
number of objective function
m
number of non-dominated solutions in the repository
w k
weight of kth objective function
V e l j k
current velocity of particle j at iteration k
V e l j k + 1
modified velocity of particle j at iteration k + 1
r a n d ( . )
random number between 0 and 1
X j k
current position of particle j at iteration k
X m u t , j k
mutant vector of particle j at iteration k
X n e w , j k
the trial vector
N F V
normalized fitness value

References

  1. Geske, M.; Heuer, M.; Heideck, G. A.; Styczynski, Z. Current density distribution mapping in PEM fuel cells as an instrument for operational measurements. Energies 2010, 3, 770–783. [Google Scholar] [CrossRef]
  2. Iranzo, A.; Rosa, F.; Pino, J. A Simulation tool for geometrical analysis and optimization of fuel cell bipolar plates: development, validation and results. Energies 2009, 2, 582–594. [Google Scholar] [CrossRef]
  3. Liu, S.; Kong, W.; Lin, Z. A microscale modeling tool for the design and optimization of solid oxide fuel cells. Energies 2009, 2, 427–444. [Google Scholar] [CrossRef]
  4. El-Khattam, W.; Hegazy, Y.G.; Salama, M.M.A. An integrated distributed generation optimization model for distribution system planning. IEEE Trans. Power Syst. 2005, 20, 1158–1165. [Google Scholar] [CrossRef]
  5. Jabr, R.A.; Pal, B.C. Ordinal optimization approach for locating and sizing of distributed generation. IET Gener Trans. Dis. 2009, 3, 713–723. [Google Scholar] [CrossRef]
  6. Biswas, S.; Goswami, S.K.; Chatterjee, A. Optimum distributed generation placement with voltage sag effect minimization. Energy Conver. Manag. 2012, 53, 163–174. [Google Scholar] [CrossRef]
  7. AlRashidi, M.R.; AlHajri, M.F. Optimal planning of multiple distributed generation sources in distribution networks: A new approach. Energy Conver. Manag. 2011, 52, 3301–3308. [Google Scholar] [CrossRef]
  8. Hedayati, H.; Nabaviniaki, S.A.; Akbarimajd, A. A method for placement of DG units in distribution networks. IEEE Trans. Power Deliv. 2008, 23, 1620–1628. [Google Scholar] [CrossRef]
  9. Celli, C.; Ghiani, E.; Mocci, S.; Pilo, F. A multi objective evolutionary algorithm for the sizing and siting of distributed generation. IEEE Trans. Power Syst. 2005, 20, 750–757. [Google Scholar] [CrossRef]
  10. Niknam, T.; Taheri, S.I.; Aghaei, J.; Tabatabaei, S.; Nayeripour, M. A modified honey bee mating optimization algorithm for multi objective placement of renewable energy resources. Appl. Energy 2011, 88, 4817–4830. [Google Scholar] [CrossRef]
  11. Jurado, F.; Cano, A. Optimal placement of biomass fuelled gas turbines for reduced losses. Energy Conver. Manag. 2006, 47, 2673–2681. [Google Scholar] [CrossRef]
  12. Reche-López, P.; Ruiz-Reyes, N.; García Galán, S.; Jurado, F. Comparison of metaheuristic techniques to determine optimal placement of biomass power plants. Energy Conver. Manag. 2009, 50, 2020–2028. [Google Scholar] [CrossRef]
  13. El-Sharkh, M.Y.; Tanrioven, M.; Rahman, A.; Alam, M.S. Economics of hydrogen production and utilization strategies for the optimal operation of a grid-parallel PEM fuel cell power plant. Int. J. Hydrog. Energy 2010, 35, 8804–8814. [Google Scholar] [CrossRef]
  14. El-Sharkh, M.Y.; Tanrioven, M.; Rahman, A.; Alam, M.S. Impact of hydrogen production on optimal economic operation of a grid-parallel PEM fuel cell power plant. J. Power Sources 2006, 153, 136–144. [Google Scholar] [CrossRef]
  15. Niknam, T.; Zeinoddini Meymand, H.; Doagou Mojarrad, H. An efficient algorithm for multi-objective optimal operation management of distribution network considering fuel cell power plants. Energy 2011, 36, 119–132. [Google Scholar] [CrossRef]
  16. Niknam, T.; Zeinoddini Meymand, H.; Doagou Mojarrad, H. A practical multi-objective PSO algorithm for optimal operation management of distribution network with regard to fuel cell power plants. Renew. Energy 2011, 36, 1529–1544. [Google Scholar] [CrossRef]
  17. Nanaeda, K.; Mueller, F.; Brouwer, J.; Samuelsen, S. Dynamic modeling and evaluation of solid oxide fuel cell—combined heat and power system operating strategies. J. Power Sources 2010, 195, 3176–3185. [Google Scholar] [CrossRef]
  18. Ren, H.; Gao, W. Economic and environmental evaluation of micro CHP systems with different operating modes for residential buildings in Japan. Energy Build. 2010, 42, 853–861. [Google Scholar] [CrossRef]
  19. Kennedy, J.; Eberhart, R. Particle swarm optimization. IEEE Int. Conf. Neural Netw. 1995, 4, 1942–1948. [Google Scholar]
  20. Kennedy, J. The particle swarm: social adaptation of knowledge. IEEE Int. Conf. Evol. Comput. 1997. [Google Scholar] [CrossRef]
  21. Niknam, T.; Azadfarsani, E.; Jabbari, M. A new hybrid evolutionary algorithm based on new fuzzy adaptive PSO and NM algorithms for distribution feeder reconfiguration. Energy Conver. Manag. 2012, 54, 7–16. [Google Scholar] [CrossRef]
  22. Niknam, T. A new fuzzy adaptive hybrid particle swarm optimization algorithm for non-linear, non-smooth and non-convex economic dispatch problem. Appl. Energy 2010, 87, 327–390. [Google Scholar] [CrossRef]
  23. Kuo, C.; Lee, C.; Sheim, Y. Unit commitment with energy dispatch using a computationally efficient encoding structure. Energy Conver. Manag. 2011, 52, 1575–1582. [Google Scholar] [CrossRef]
  24. Wang, Y.; Zhou, J.; Qin, H.; Lu, Y. Improved chaotic particle swarm optimization algorithm for dynamic economic dispatch problem with valve-point effects. Energy Conver. Manag. 2010, 51, 2893–2900. [Google Scholar] [CrossRef]
  25. Duan, P.; Xie, K.; Guo, T.; Huang, X. Short-term load forecasting for electric power systems using the PSO-SVR and FCM clustering techniques. Energies 2011, 4, 173–184. [Google Scholar] [CrossRef]
  26. Zhang, W.; Liu, Y. Multi-objective reactive power and voltage control based on fuzzy optimization strategy and fuzzy adaptive particle swarm. J. Electr. Power Energy Syst. 2008, 30, 525–532. [Google Scholar] [CrossRef]
  27. Niknam, T.; Doagou Mojarrad, H.; Nayeripour, M. A new fuzzy adaptive particle swarm optimization for non-smooth economic dispatch. Energy 2010, 35, 1764–1778. [Google Scholar] [CrossRef]
  28. Su, C.T.; Lee, C.S. Network reconfiguration of distribution systems using improved mixed-integer hybrid differential evolution. IEEE Trans. Power Deliv. 2003, 18, 1022–1027. [Google Scholar] [CrossRef]

Share and Cite

MDPI and ACS Style

Farjah, E.; Bornapour, M.; Niknam, T.; Bahmanifirouzi, B. Placement of Combined Heat, Power and Hydrogen Production Fuel Cell Power Plants in a Distribution Network. Energies 2012, 5, 790-814. https://doi.org/10.3390/en5030790

AMA Style

Farjah E, Bornapour M, Niknam T, Bahmanifirouzi B. Placement of Combined Heat, Power and Hydrogen Production Fuel Cell Power Plants in a Distribution Network. Energies. 2012; 5(3):790-814. https://doi.org/10.3390/en5030790

Chicago/Turabian Style

Farjah, Ebrahim, Mosayeb Bornapour, Taher Niknam, and Bahman Bahmanifirouzi. 2012. "Placement of Combined Heat, Power and Hydrogen Production Fuel Cell Power Plants in a Distribution Network" Energies 5, no. 3: 790-814. https://doi.org/10.3390/en5030790

APA Style

Farjah, E., Bornapour, M., Niknam, T., & Bahmanifirouzi, B. (2012). Placement of Combined Heat, Power and Hydrogen Production Fuel Cell Power Plants in a Distribution Network. Energies, 5(3), 790-814. https://doi.org/10.3390/en5030790

Article Metrics

Back to TopTop