Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Evaluating the Energy Potential of Solar PV Located on Mining Properties in the Northern Cape Province of South Africa

by
Waldo van der Merwe
1,* and
Alan C. Brent
1,2
1
Department of Industrial Engineering and the Centre for Renewable and Sustainable Energy Studies, Stellenbosch University, Stellenbosch 7602, South Africa
2
Sustainable Energy Systems, School of Engineering and Computer Science, Victoria University of Wellington, Wellington 6140, New Zealand
*
Author to whom correspondence should be addressed.
Sustainability 2020, 12(14), 5857; https://doi.org/10.3390/su12145857
Submission received: 18 June 2020 / Revised: 12 July 2020 / Accepted: 17 July 2020 / Published: 21 July 2020
(This article belongs to the Special Issue Renewable Energy for Sustainable Development)

Abstract

:
The lauded Renewable Energy Independent Power Producer Procurement Program (REIPPPP) has achieved much in stimulating private sector investment in the renewable energy market in South Africa. Yet, 95% of electricity generated is still from a single source, the state-owned utility Eskom. This paper set out to explore the policy sphere governing electricity generation and identifying possible avenues that can contribute to a more vibrant solar energy market in the most solar abundant province of South Africa, the Northern Cape Province. Licensed mines were identified as low hanging fruit due to a large policy overlap and leeway within existing mining policy. A solar audit of these areas was performed, based on accepted multi-criteria decision analysis techniques, and found that a potential 369 TWh to 679 TWh per annum can be generated, exceeding South Africa’s current electricity usage.

1. Introduction

1.1. Mining as a Consumer of Energy and as a Potential New Renewable Enegy Generator

Mining and energy are intrinsically linked within the South African economy in what has become known as the Minerals-Energy Complex [1], and mining alone accounted for as much as 18% of GDP, and 60% of all exports, at its peak during the turn of the century [2]. Because 93% (during 2014) of all electricity in the country is generated from coal sources [3], and the mining sector is responsible for 15% of South Africa’s entire electricity demand [2]—40% of members of the Energy Intensive Users Group (EIUG) of Southern Africa are involved in downstream beneficiation [4,5]—this relationship becomes partly circular. Electricity production supplied by coal mined within the country’s borders supplies 29% of South Africa’s total energy demand (including transportation fuels) and is responsible for 50% of all local carbon emissions [5], making it the largest energy sub-sector.
While mines could traditionally rely on relatively cheap electricity supply from the national utility Eskom, this trend seems to be coming to an end with Eskom increasing the price of electricity by 26% from 2007 to 2012 [2,6] and continuing the trend of above inflation increases on average by 9.75% (tariffs as reported by Eskom SOC for the mining sector) p.a. from 2013 to 2019 [7], while the other major energy source, diesel used in generators, has seen a 15.7% increase during the same period [2], resulting in a combined increase of 7% to 20% in the seven-year period from 2008 to 2014 for 47% of the companies in the mining sector who are part of the EIUG [8]. A looming carbon tax can potentially increase the price of diesel from a further 11.4 cents per litre to 28.6 cents per litre [9]. These factors all contribute to a market conducive to the adoption of alternative forms of energy, not for altruistic reasons, but driven purely by market forces.
Solar photovoltaic (PV) seems the most likely candidate to succeed in the mining environment, due to it having one of the lowest prices per installed power unit, and it has one of the most predictable and steady power supply curves of the renewables stable, which is a good fit with the almost constant demand of mines. Furthermore, while South Africa has some of the world’s largest coal reserves, it pales in comparison to its solar resources, ranking together with Chile as having some of the highest solar insolation figures in the world [10,11]. Nowhere in the country is this as true as in the Northern Cape Province, and subsequently developers of utility-scale solar energy sources have overwhelmingly settled here first [12]. While the development of utility-scale projects, through the government Renewable Energy Independent Power Producer Procurement Program (REIPPPP), feeding the national grid has been an internationally lauded success [11], the uptake of renewables in other private sector markets has been lagging. Even after commissioning in excess of 2900 MW of renewable energy through privately funded projects worth US$13.1 billion (exchange rate of 15.37 ZAR:1 USD as per South African Reserve Bank data for the 1st quarter of the 2020 fiscal year) of investment [11], Eskom remains the largest generator of electricity in the country at 95%, through an installed capacity of 47 GW, of which 39 GW is from coal-based sources [13]. The government has also been slow with passing new policy to supplement the REIPPPP success, such as the proposed Independent System and Market Operator (ISMO) bill, which is meant to establish a single buyer and wholesale distributor of electricity, separate from Eskom [14].

1.2. Objective of the Paper

The objective of this paper is to evaluate the potential, in terms of energy extraction, of the land licensed to the mining industry in the Northern Cape Province of South Africa. This is quantified in terms of a simulated audit of the solar energy potential and qualified within the policy framework that exists currently within the mining and energy sectors. Section 2 describes the steps followed to achieve each sub-objective as described in Figure 1 below. The research literature review covers the first two sub-objectives. All the studies found to be relevant to energy audits, which initially included a number of studies which included other technologies such as wind and biomass energy, were used to identify the first sub-objective. The next step was to exclude studies of other technologies and only focus on solar PV audits or where solar PV was included as part of a multi-technology audit. This was done to determine the specific framework used, down to the fine detail of selection criteria, in order to formulate a customized framework to apply to this research. Data gathering was achieved by assembling a database of all the resources used in the literature study and adding further studies to this which focus on locally relevant content. This was followed by exploratory fieldwork to obtain access to quality local data. Lastly, all of the above was applied practically to build and execute a model to input data and calculate meaningful information from it. To achieve this, additional research had to be done qualitatively outside of the literature study sphere in order to gain the required knowledge on the specialized subject of GIS systems.

2. Literature Review and Model Design

2.1. Multi-Criteria Decision Analysis

In the GIS-based (Geographic Information System) PV potential studies in literature, most authors use some form of Multi-Criteria Decision Analysis (MCDA) with weighted selection criteria, preceded with a Boolean filter to eliminate areas completely unsuitable, such as holy grounds or bodies of water. The weighted selection criteria take many forms. The most common method of assigning weights is the Analytical Hierarchy Process (AHP) [15] with variants, such as using fuzzy logic [16]. Two studies have combined the Eliminating Choice and Translating Reality (ELECTRE) method [17] with their MCDA, and another used the Technique for Order Preference by Similarity to Ideal Solution (TOPSIS) method [18]. One of the most interesting cases was by Borgogno Mondino et al. [19], who trained an Artificial Neural Network (ANN) in what the conditions around existing solar plants in the investigated area are and let it come up with the criteria and associated weights for the MCDA itself. Five studies [20,21,22,23,24] used Boolean logic as the basis of their MCDA. The latter two of these five did not explicitly specify their MCDA as using Boolean logic, but this could be inferred after a careful look at their methodology. A specific type of MCDA, known as an Environmental Decision Support System (EDSS) [25], requires large amounts of spatial information to facilitate the decision-making process, as well as visualizing the results. It is for this reason that GIS systems are such a good match for this customized type of MCDA.

2.2. External Influence on Model Design

This study differs from those in the literature on one specific point. Where those studies attempted to classify a large area according to suitability, this study was limited to very specific smaller areas, or pockets, due to pre-determined criteria. This flows from the decision to limit the study area to licensed mines in the Northern Cape Province of South Africa. This allowed for some generalization of many of the criteria, which will be detailed in the following sections, but for the purpose of the MCDA, it had the consequence of allowing the MCDA to be vastly simplified to that of Boolean choices only.

2.3. Model Criteria Selection

The Northern Cape Province was deliberately chosen as the starting point of the study, as this province can be generalized in terms of solar radiation in exactly the way that the geographic regions of the literature could not. If the nine provinces of South Africa were to be ranked on average solar radiation received, including quality, then this province would be ranked the best [26]. In addition, it would not be meaningful to use a ranking system to order the different mining areas on solar insolation, as the objective is to reveal the collective solar insolation that these areas hold. Additionally, if it is assumed that the majority of mines must have some type of road or rail infrastructure in place to haul equipment and people to the mine and extract ore from the mine, then there is no reason to build in weighted criteria to exclude areas far away from roads. The same argument can be applied to electricity infrastructure given the energy intensity of mines, and the finding that all the mines investigated as part of the study by Votteler & Brent [27] were connected to the grid. Lastly, it can also be assumed with relative confidence that mining rights would not be granted for a specific area if that area contained any known historical landmarks, paleontological significant sites, archaeological sites, and protected wildlife sanctuaries. The remaining exclusions that were included in the model were the following:
  • Rivers (not including dry riverbeds)
  • Areas where the defined mining area included a portion of the ocean along a coastline.
  • Farm sheds
  • Farm housing
  • Mining housing
  • Mining machine sheds
  • Open grooved mines
  • Mine earth dumps (if discernible)
  • National and regional tarred roads
  • Airfields
  • Railway tracks
These exclusions were all identified manually through human input due to a lack of consistency in the datasets at hand. Inclusion was based on a system of positive identification, which implies that the final result for net insolation might not represent the worst-case scenario. On the other side of the spectrum are items that can also be positively identified but were deliberately not included as exclusions. These are:
  • Gravel/sand roads
  • Agricultural activity
These were seen as non-permanent and can be rerouted or removed without a significant cost compared to the overall cost of development. Furthermore, as agriculture does not alter or change the landscape topography dramatically, it would not be something that poses a great limitation to a developer. Figure 2 shows an example of the identified exclusions for one specific mining area.

Slope and Aspect

Many of the studies in literature note that there is no definite number at which a slope is considered to be unfeasible to build a utility-scale PV plant, as opposed to what is the case for concentrating solar power (CSP). This caused the studies to have a wide range of cut-off values beginning as low as 3% (commonly including 5%, 10% and 15%) up to 30% and even 50%. When slope was combined with an aspect, there were usually two numbers, such as 3% for north facing land (the majority of the studies are northern hemisphere based) and 5% for south facing land, therefore including the factor that south facing land is more preferable to north facing land in the northern hemisphere. This is in line with findings of studies such as that of Le Roux [28] studying the optimal tilt angle of solar panels for local South African conditions, which implies that a tilted solar panel (north aspect) is preferred to a flat panel as one moves further south of the equator. By extension, this implies that a greater amount of leeway should be allowed for naturally north aspect sloping ground. To this end, a cut-off of three per cent was chosen, while for slopes with a northern aspect (being defined as from 315° to 45°) the limit was increased to five per cent.

2.4. Model Application

When unfolding a three-dimensional sphere like earth onto a two-dimensional piece of paper, there will inevitably be some type of distortion. An example is the manner in which the Mercator projection distorts the size of the land area in an attempt to preserve shape. Equal area projections, on the other hand, distort shape while preserving area. The equal area projection selected is from the conical family of projections named Albers, having the characteristic that visual distortion is limited between the so-called standard parallels, which means that an Albers projection can be adapted to a localized area in order to be accurate while also having nearly no distortion when compared to a Mercator projection in that same area. The South African Albers NGI Aerials (reported to have 0.001% error when reporting projected area compared to actual area (source: Waywell, T. The effect of various map projections on surface area. PositionIT, 2009)) projection is exactly customized for this purpose, and as such this was the de facto projection favored in all calculations unless otherwise stated in the research.

2.4.1. Solar Resource Data

Solar resource maps can be created from mainly two sources: ground measurements, and satellite-derived data. The latter typically covers very large areas and are, therefore, suitable to exploratory work, and the datasets available usually offer much longer time periods, which alleviates at least some investor fears, as solar plants are built to be operated for decades. For ground measurements, a measurement device, such as a pyranometer or a pyrheliometer is required. Both these devices are extremely accurate, but as a consequence, are also very expensive. They also require deployment in many locations and this, combined with the high cost, makes it understandable why Fluri [29] reported only 11 weather stations, managed by the South African Weather Services (SAWS), equipped with such devices. For the purposes of this study, a satellite-derived solar resource map was best suited and the available solar resource maps for South Africa are discussed by three papers [29,30,31] in the local context with a summary of these given in Table 1. Only the NASA dataset was found to grant access to the full raw dataset before any variables are included through manipulations in an unknown software environment.

2.4.2. Data Sources

According to Regulation 2, sub-section (2), paragraph (f) of the Mineral and Petroleum Resources Development Regulations, as enacted by the Mineral and Petroleum Resources Development Act (2002) [32,33], to obtain a mining permit the application should include a plan that includes “the boundaries of the land to which the application relates.” Within data sourced from the Directorate: National Geo-Spatial Information (NGI), a branch of Department of Rural Development and Land Reform, data defining these boundaries were found and assumed to be the verified product of the above-mentioned requirement. In general, a preference was enforced for publicly available data in order to promote reproducibility and, therefore, it was not only the mining boundary data, but also the aerial photographs and topographical data, sourced from the NGI.

2.4.3. Simulation Tool

The seat-cost for GIS work in the academic community is prohibitive [34], especially in the African context, and for this reason, open-source software was considered a prerequisite. Since the start of the millennium, the uptake of R [35] (R is a free software environment for statistical computing and graphics) in the underfunded teaching and research sphere of developing countries has been noticeably high [36]. Bivand [36] reported in 2006 that a search on the R website for the term “spatial” yielded 1219 results, which was considerably more than the 447 results during the year of 2002. Repeating this in 2018 yielded 7280 results.
On recommendation by Endel and Filzmoser [37], RStudio was selected as the preferred graphical user interface. The basic R distribution is capable of computing mathematical and statistical data functions as reported by Grunsky [38], but to perform true GIS operations extra libraries need to be installed. A summary of these is given in Table 2.

2.4.4. Data Manipulation and Calculations

The requirement to exclude areas exceeding a pre-determined slope limit creates the need for datasets that include data for both aspect and slope. A digital elevation model (DEM) is merely a raster object with each cell containing a single value: height. Interpolation provides a way of assigning values to these areas that exist between two topographical lines. In general, nearby data is selected with a weighted average to calculate the missing values at a given location. According to Babak and Deutsch [47], there are two main branches of interpolation. Either a statistical criterion can be used to select the nearby weighted values, or a simpler deterministic method can be used. For the former, techniques such as kriging (including but not limited to: simple-, ordinary-, universal- and simple cokriging) can be implemented, while for the latter, inverse distance weighted (IDW) interpolation is the most commonly implemented technique. IDW especially takes advantage of the principle of spatial autocorrelation, which assumes that values closer to the missing value should be more similar to it than values that are far away [48]. Simply stated, when taking one step away from your current position on earth, you never really find yourself in a very different state (with the exception of stepping over a cliff). The implementation of this is based on assigning a higher weight to points that are closer [47] or, as the name suggests, using the inverse distance.
The function requires the user to choose between two techniques, namely: Fleming & Hoffer, or Horn. A thorough comparison of these two techniques was made by Jones [49] who found that Fleming & Hoffer performed better for smooth surfaces, and Horn performed better for noisy surfaces. Jones [49] warns that when topographical lines are digitized and converted to a DEM through interpolation, it might create step artefacts, and thus Horn was selected.
Figure 3 shows the intermediate steps toward calculating the aspect and slope data. In Figure 3a,b the original cropped topographical data is shown next to the same data that has been converted from lines to points. Below that Figure 3c shows what the result of the interpolation process looks like. The aspect and slope plots are shown in Figure 3d,e, respectively. It should be noted that the values for aspect are seemingly random, or noisy, in areas that are not close to the original topographical lines.

3. Results

The sum of the areas under investigation was calculated as being 2572 km2, which represents 0.69% of the total land area of the Northern Cape Province, with a combined net solar insolation of 12,057 GWh/day. Because the assessed areas vary wildly in size, the net insolation results also vary with the largest value for a single mine at 1,609,358 MWh/day, and the minimum a mere 2 MWh/day. The lower limit is typical of a licensed mining area that is smaller than average, combined with a high level of area utilization dedicated toward mining activities. To provide some insight, the results shown in Table 3 are summarized according to order of magnitude in a pseudo-logarithmic style. The majority of mines fall in the 10–100 GWh/day category, while the broader 1–100 GWh/day category holds the outright majority share.
These numbers should be understood in context, as this is far from the realistic levels of energy that can be expected to be evacuated. The factors that play the largest role were found to be panel efficiency and area-factor. From the literature, three studies [20,22,50] reported their applied panel efficiency, with values ranging between 8.8% and 37.9%. Only the study by Yushchenko et al. [51] reported ranges, which were mostly referenced to meta-studies on the subject at hand and can, therefore, be seen as the most reliable. The reported efficiencies were between 13.3% and 22% for monocrystalline cells and between 12% and 15.67% for polycrystalline cells. For this study, the simplest case was to assume a high and low case with values set at 12% and 22%, respectively, enveloping both aforementioned ranges.
Area factors are an indication of what fraction of a specific area can be covered with panels since it is inevitable that space has to be left open between rows and mitigate shading and to leave room for service roads. The study of Gastli and Charabi [52] is the only one found that included an area factor of 0.7 when calculating electric power generation potential, and, therefore, in the absence of alternatives, this study proceeded with the same value. The formula utilized was similar to that implemented by Carrión et al. [24], and the adaptation used in this study is given by Equation (1):
E = G × A × ε
where:
E = Electric power generation per day (MWh/day)
G = Solar radiation received (MWh/day)
A = Area factor
ε = Panel efficiency
Table 4. summarizes the results after the effect of Equation (1) is included. Table 5 provides the headline numbers.
Finally, dispatchability remains the last link in the energy chain. Figure 4 shows the locations of where a broad selection of the REIPPPP projects are located. It is clear that solar resources are located in areas that were previously net receivers of energy, with the Northern Cape Province under-developed in terms of large-scale grid infrastructure. This disconnect between the locations of generation and consumption, in essence, is the reason why solar-generated power, at present, will not be able to satisfy the entire country’s electricity needs, even if the resource exceeds the demand.

4. Conclusions

South Africa uses over 220 TWh of electricity annually [6], which is exceeded by even the low-case of 369 TWh per annum, and certainly by the high-case of 679 TWh per annum; implying that even on a worst-case base estimation, using only the identified mines to commission utility-scale solar PV plants, would satisfy the entire country’s electricity (energy, not power) demand requirements. To achieve this, the national grid would have to be reorganized. The fact that the national grid operator is also the single largest generator of coal-derived electricity is a major conflict of interest in achieving this goal and, again, highlights the importance of the need for the ISMO bill to be promulgated. However, depending on the interpretation of existing policy frameworks, opportunities exist to export energy after mine closures through the policies that govern environmental rehabilitation. This would open various permutations of co-ownership and commercial relationships between mining companies and solar energy developers.
All the options that exist are dependent on either small policy changes, or leniency in execution. It would also require inter-departmental cooperation. This has already been proven successful between the Departments of Energy, Environmental Affairs and Water Affairs during the development and execution of the REIPPPP, and would only require a single department, the Department of Mineral Resources, to be aligned. Agile policy could also play a large role in load-generation matching by shifting or flattening peak load times through mechanisms such as time-dependent pricing strategies on the demand-side. On the generation-side, incorporating a favorable pricing strategy in the negotiated power purchase agreement (PPA) for supply during current peak times could allow the financial impetus required to make incorporated energy storage financially viable for energy developers, as in the widely publicized Tesla battery project in southern Australia [54]. In addition, investing in further research into storage technologies, such as is currently the case between the government and private sector on a vanadium redox flow battery project [55], could help alleviate peaking supply problems and stimulate GDP growth by making South Africa a serious player in a global market where demand for storage solutions will only get bigger in the future.
The own-consumption model is by far the simplest and presents the least number of variables to analyze in terms of its business sense to a company mainly concerned with profiting from mining activities. Possible variables can relate to the cost of obtaining a grid connection to a previously unconnected area or to avoid loss of services by an increasingly unstable grid utility. The first question should be whether enough reliable solar power can be generated, and this study found that the annual electricity generation potential varied between 36.5 GWh and 3650 GWh (100 MWh–10 GWh per day) for the majority of the mines analyzed. This compares favorably to the annual consumption per mine, reported as 4.2 GWh to 2752 GWh in the sample of the study by Votteler & Brent [27]. It was also found that the Acts regulating the mining industry and mining rights/permit holders provide the freedom to bring onto the land being mined any equipment and erecting any structure which is used for, or is incidental to, mining activities. While the final decision would be in the hands of the Minister, it can be stated that there should be no reason, insofar as generation potential or policy blockades, to prevent solar PV plant development for our own-consumption. Whether by own-consumption or as a grid supplier, market forces alone cannot guarantee uptake, leaving government policy as the largest common denominator that can halt or stimulate a vibrant privately funded solar energy market in the mining sector.

Author Contributions

Conceptualisation, W.v.d.M.; Formal analysis, W.v.d.M.; Methodology, W.v.d.M.; Supervision, A.C.B.; Validation, W.v.d.M.; Writing—original draft, W.v.d.M.; Writing—review and editing, A.C.B. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Fine, B.; Rustomjee, Z. The Political Economy of South Africa: From Minerals-Energy Complex to Industrialisation; Witwatersrand University Press: Witwatersrand, South Africa, 1996. [Google Scholar]
  2. Boyse, F.; Causevic, A.; Duwe, E.; Orthoffer, M. Sunshine for Mines: Implementing Renewable Energy for off-Grid Operations; Carbon War Room: Washington, DC, USA, 2014. [Google Scholar]
  3. World Bank. Electricity Production from Coal Sources (% of Total) | Data 2018. Available online: https://data.worldbank.org/indicator/EG.ELC.COAL.ZS?locations=ZA (accessed on 17 July 2018).
  4. EIUG. EIUG—Energy Intensive User Group of Southern Africa 2018. Available online: http://eiug.org.za/ (accessed on 17 July 2018).
  5. Baker, L. Governing electricity in South Africa: Wind, coal and power struggles. Gov. Clean Dev. 2011, 15, 1–27. [Google Scholar]
  6. Krupa, J.; Burch, S. A new energy future for South Africa: The political ecology of South African renewable energy. Energy Policy 2011, 39, 61–6254. [Google Scholar] [CrossRef]
  7. Eskom. Available online: http://www.eskom.co.za/CustomerCare/TariffsAndCharges/Pages/Tariff_History.aspx (accessed on 17 June 2020).
  8. Votteler, R.G. A Mining Perspective on the Potential of Renewable Electricity Sources for Operations in South Africa; Stellenbosch University: Western Cape, South Africa, 2016. [Google Scholar]
  9. BusinessTech. How SA’s New Carbon Tax will Affect Petrol and Electricity Prices. BusinessTech, 2018. Available online: https://businesstech.co.za/news/energy/218691/how-sas-new-carbon-tax-will-affect-petrol-and-electricity-prices/ (accessed on 22 July 2018).
  10. Parrado, C.; Girard, A.; Simon, F.; Fuentealba, E. 2050 LCOE projection for a hybrid PV-CSP plant in the Atacama Desert, Chile. Energy 2016, 94, 30–422. [Google Scholar] [CrossRef]
  11. Nakumuryango, A.; Inglesi-Lotz, R. South Africa’s performance on renewable energy and its relative position against the OECD countries and the rest of Africa. Renew. Sustain. Energy Rev. 2016, 56, 999–1007. [Google Scholar] [CrossRef] [Green Version]
  12. Urban-Econ. Northern Cape Renewable Energy Strategy. 2013. Available online: https://urban-econ.com/capabilities/energy/ (accessed on 27 October 2018).
  13. Eskom. Generation Plant Mix 2017. Available online: http://www.eskom.co.za/AboutElectricity/FactsFigures/Documents/GX0001GenPlantMixRev19.pdf (accessed on 16 July 2018).
  14. Montmasson-Clair, G.; Ryan, G. Lessons from South Africa’s Renewable Energy Regulatory and Procurement Experience. J. Econ. Financ. Sci. 2014, 7, 26–507. [Google Scholar] [CrossRef]
  15. Saaty, T.L. The Analytic Hierarchy Process; Applications and Studies: Berlin, Germany, 1980. [Google Scholar] [CrossRef]
  16. Noorollahi, E.; Fadai, D.; Akbarpour Shirazi, M.; Ghodsipour, S. Land Suitability Analysis for Solar Farms Exploitation Using GIS and Fuzzy Analytic Hierarchy Process (FAHP)—A Case Study of Iran. Energies 2016, 9, 643. [Google Scholar] [CrossRef]
  17. Sánchez-lozano, J.M.; Henggeler, C.; García-cascales, M.S.; Dias, L.C. GIS-based photovoltaic solar farms site selection using ELECTRE-TRI: Evaluating the case for Torre Pacheco, Murcia, Southeast of Spain. Renew. Energy 2014, 66, 94–478. [Google Scholar] [CrossRef]
  18. Sánchez-lozano, J.M.; Teruel-solano, J.; Soto-elvira, P.L.; García-cascales, M.S. Geographical Information Systems (GIS) and Multi-Criteria Decision Making (MCDM) methods for the evaluation of solar farms locations: Case study in south-eastern Spain. Renew. Sustain. Energy Reviews 2013, 24, 56–544. [Google Scholar] [CrossRef]
  19. Borgogno Mondino, E.; Fabrizio, E.; Chiabrando, R. Site Selection of Large Ground-Mounted Photovoltaic Plants: A GIS Decision Support System and an Application to Italy. Int. J. Green Energy 2014, 12, 25–515. [Google Scholar] [CrossRef] [Green Version]
  20. Abed, M.; Nagasaka, K. Utility-scale implementable potential of wind and solar energies for Afghanistan using GIS multi-criteria decision analysis. Renew. Sustain. Energy Reviews 2017, 71, 60–150. [Google Scholar] [CrossRef]
  21. Jahangiri, M.; Ghaderi, R.; Haghani, A.; Nematollahi, O. Finding the best locations for establishment of solar-wind power stations in Middle-East using GIS: A review. Renew. Sustain. Energy Reviews 2016, 66, 38–52. [Google Scholar] [CrossRef]
  22. Merrouni, A.A.; Mezrhab, A.; Mezrhab, A. PV sites suitability analysis in the Eastern region of Morocco. Sustain. Energy Technol. Assess. 2016, 18, 6–15. [Google Scholar] [CrossRef]
  23. Domínguez, B.J.; García, C.X.; Pinedo, P.I. GIS approach to the definition of capacity and generation ceilings of renewable energy technologies. Energy Policy 2007, 35, 92–4879. [Google Scholar] [CrossRef]
  24. Carrión, J.A.; Espín, E.A.; Aznar, D.F.; Ridao, A.R. The electricity production capacity of photovoltaic power plants and the selection of solar energy sites in Andalusia (Spain). Renew. Energy 2008, 33, 52–545. [Google Scholar] [CrossRef]
  25. Rizzoli, A.E.; Young, W.J. Delivering environmental decision support systems: Software tools and techniques. Environ. Model. Softw. 1997. [Google Scholar] [CrossRef]
  26. Suri, M.; Cebecauer, T.; Skoczek, A. Cloud Cover Impact on Photovoltaic Power Production in South Africa. In Proceedings of the Southern African Solar Energy Conference, Port Elizabeth, South Africa, 5 February 2014. [Google Scholar]
  27. Votteler, R.G.; Brent, A.C. A mining perspective on the potential of renewable electricity sources for operations in South Africa: Part 2-A multi-criteria decision assessment. J. S. Afr. Inst. Min. Metall. 2017, 117, 299–312. [Google Scholar] [CrossRef] [Green Version]
  28. Le Roux, W.G. Optimum tilt and azimuth angles for fixed solar collectors in South Africa using measured data. Renew. Energy 2016, 96, 12–603. [Google Scholar] [CrossRef] [Green Version]
  29. Fluri, T. Solar Resource Mapping in South Africa; University of Stellenbosch: Western Cape, South Africa, 2009. [Google Scholar]
  30. Zawilska, E.; Brooks, M.J.; Meyer, A.J. A review of solar resource assessment initiatives in South Africa: The case for a national network. In Proceedings of the World Renewable Energy Forum (WREF 2012), Denver, CO, USA, 13–17 May 2012. [Google Scholar]
  31. Winkler, H.; Franke, B.; Eltrop, L.; Telsnig, T. How applicable are standard Solar Irradiation Maps? Insights from Case Studies. In Proceedings of the ISES-Europe Solar Conference, Opatija and Rejika, Croatia, 18–20 September 2012. [Google Scholar]
  32. Republic of South Africa. Mineral and Petroleum Resources Development Act; Government Gazette: Pretoria, South Africa, 2002.
  33. Department of Mineral Resources. A Guideline for a Mining Work Programme to be Submitted for a Applications for a Mining Right in Terms of the Minerals and Petroleum Resources Development Act; Department of Mineral Resources: Pretoria, Republic of South Africa, 2002.
  34. Bivand, R.; Gebhardt, A. Implementing functions for spatial statistical analysis using the R language. J. Geogr. Syst. 2000, 2, 17–307. [Google Scholar] [CrossRef]
  35. R Core Team. R: A Language and Environment for Statistical Computing; R Foundation for Statistical Computing: Vienna, Austria, 2015. [Google Scholar]
  36. Bivand, R. Implementing Spatial Data Analysis Software Tools in R. Geogr. Anal. 2006, 38, 23–40. [Google Scholar] [CrossRef]
  37. Endel, F.; Filzmoser, P. R&GIS: Geospatial Plotting FFG IFEDH Project Student at Vienna University of Technology. IFAC Proc. Vol. 2012, 47, 1–6. [Google Scholar] [CrossRef]
  38. Grunsky, E.C. R: A data analysis and statistical programming environment-an emerging tool for the geosciences. Comput. Geosci. 2002, 28, 22–1219. [Google Scholar] [CrossRef]
  39. Blondel, E. Cleangeo: Cleaning Geometries from Spatial Objects. 2017. Available online: https://CRAN.R-project.org/package=cleangeo (accessed on 26 October 2018).
  40. Wickham, H.; Francois, R. Dplyr: A Grammar of Data Manipulation, version 0.4; 2016. Available online: https://CRAN.R-project.org/package=dplyr (accessed on 25 October 2018).
  41. Graler, B.; Pebesma, E.; Heuvelink, G. Spatio-Temporal Interpolation using gstat. RFIE J. 2016, 8, 204–218. [Google Scholar] [CrossRef]
  42. Bivand, R.; Lewin-Koh, N. Maptools: Tools for Reading and Handling Spatial Objects, version 0.8; 2017. Available online: https://CRAN.R-project.org/package=maptools (accessed on 24 October 2018).
  43. Pebesma, E.J.; Bivand, R. Classes and Methods for Spatial Data in R, version 1.4-2; 2005. Available online: https://cran.r-project.org/doc/Rnews/ (accessed on 23 October 2018).
  44. Hijmans, R.J. Raster: Geographic Data Analysis and Modeling, version 2.8; 2016. [Google Scholar]
  45. Bivand, R.; Keitt, T.; Rowlingson, B. Rgdal: Bindings for the Geospatial Data Abstraction Library, version 1; 2016. Available online: https://CRAN.R-project.org/package=raster (accessed on 22 October 2018).
  46. Bivand, R.; Rundel, C. Rgeos: Interface to Geometry Engine-Open Source (GEOS), version 0.3; 2017. Available online: https://CRAN.R-project.org/package=rgeos (accessed on 21 October 2018).
  47. Babak, O.; Deutsch, C.V. Statistical approach to inverse distance interpolation. Stoch. Environ. Res. Risk Assess. 2008. [Google Scholar] [CrossRef]
  48. Setianto, A.; Triandini, T. Comparison of Kriging and Inverse Distance Weighted (IDW) interpolation methods in lineament extraction and analysis. J. Southeast Asian Appl. Geol. 2013, 5, 9–21. [Google Scholar] [CrossRef]
  49. Jones, K.H. A Comparison of Two Approaches to Ranking Algorithms Used to Compute Hill Slopes. GeoInformatica. GeoInformatica 1998, 2, 56–235. [Google Scholar] [CrossRef]
  50. Charabi, Y.; Gastli, A. PV site suitability analysis using GIS-based spatial fuzzy multi-criteria evaluation. Renew. Energy 2011, 36, 61–2554. [Google Scholar] [CrossRef]
  51. Yushchenko, A.; De Bono, A.; Chatenoux, B.; Kumar, M.; Ray, N. GIS-based assessment of photovoltaic (PV) and concentrated solar power (CSP) generation potential in West Africa. Renew. Sustain. Energy Rev. 2018, 81, 103–2088. [Google Scholar] [CrossRef]
  52. Charabi, Y.; Gastli, A. GIS assessment of large CSP plant in Duqum, Oman. Renew. Sustain. Energy Reviews 2010, 14, 41–835. [Google Scholar] [CrossRef]
  53. Eskom, T.D. Generation Connection Capacity Assessment of the 2022 Transmission Network. 2015. Available online: http://www.eskom.co.za/Whatweredoing/GCCAReport/Pages/GCCA2022UpdateInteractiveMap-.aspx (accessed on 18 October 2018).
  54. Krieger, N. After One Year of Operation, Tesla’s Australian Mega Battery Is Doing Just Fine. EngineeringCom, 2018. Available online: https://www.engineering.com/ElectronicsDesign/ElectronicsDesignArticles/ArticleID/17746/After-One-Year-of-Operation-Teslas-Australian-Mega-Battery-Is-Doing-Just-Fine.aspx (accessed on 20 October 2018).
  55. James, N. South Africa to pilot first utility-scale vanadium redox flow battery. Engineering News. 2018. Available online: http://www.engineeringnews.co.za/article/lessons-from-the-deployment-of-first-utility-scale-redox-battery-2018-02-23 (accessed on 19 October 2018).
Figure 1. Research objectives.
Figure 1. Research objectives.
Sustainability 12 05857 g001
Figure 2. GID 97373 outline in black and identified exclusion areas in red.
Figure 2. GID 97373 outline in black and identified exclusion areas in red.
Sustainability 12 05857 g002
Figure 3. (a) Original topographical data; (b) converted to point, or raster, data; (c) result of interpolation; (d) the slope and aspect data and (e), respectively.
Figure 3. (a) Original topographical data; (b) converted to point, or raster, data; (c) result of interpolation; (d) the slope and aspect data and (e), respectively.
Sustainability 12 05857 g003aSustainability 12 05857 g003b
Figure 4. National electricity grid within the borders of South Africa. Solid lines show transmission lines of different carrying capacity. Black, red and yellow dots show current Eskom infrastructure (sub-stations) and purple dots around crosshairs show REIPPPP projects. (Source: Eskom Transmission Division [53]).
Figure 4. National electricity grid within the borders of South Africa. Solid lines show transmission lines of different carrying capacity. Black, red and yellow dots show current Eskom infrastructure (sub-stations) and purple dots around crosshairs show REIPPPP projects. (Source: Eskom Transmission Division [53]).
Sustainability 12 05857 g004
Table 1. Various sources of solar maps relevant to local conditions (Source: Fluri [29], Zawilska et al. [30], Winkler et al. [31]).
Table 1. Various sources of solar maps relevant to local conditions (Source: Fluri [29], Zawilska et al. [30], Winkler et al. [31]).
Map NameAuthorYearAvailabilityData Source
Solar radiation data handbook for Southern Africa-1990-Ground measurements
South African Renewable Energy Resource DatabaseCSIR, Eskom, DME1999PublicGround measurements
Solar and Wind Energy Resource Assessment (SWERA) USDE, NREL & DLR2006PublicSatellite
Surface Meteorology and Solar Energy (NASA SMSE or SSE)NASA2008PublicSatellite
Photovoltaic Geographical Information SystemEuropean Commission Joint Research Centre2007PublicSatellite
Meteonorm.Meteotest AG.2009CommercialSatellite & ground measurements
SolarGIS.Solargis.-Commercial-
3Tier.Vaisala.-Commercial-
Table 2. Summary of all additional libraries added to the base R.
Table 2. Summary of all additional libraries added to the base R.
LibraryAuthor
cleangeoBlondel (2017) [39]
dplyr Wickham & Francois (2016) [40]
gstatGraler et al. (2016) [41]
maptoolsBivand & Lewin-Koh (2017) [42]
spPebesma & Bivand (2005) [43]
rasterHijmans (2016) [44]
rgdalBivand et al. (2016) [45]
rgeosBivand & Rundel (2017) [46]
Table 3. Ranges of classification and total number of investigated areas within each.
Table 3. Ranges of classification and total number of investigated areas within each.
Classification RangeNumber of Areas
0–10 MWh/day3
10–100 MWh/day7
100–1000 MWh/day18
1–10 GWh/day27
10–100 GWh/day33
100–1000 GWh/day21
1–10 TWh/day4
Table 4. High and Low case after performing Equation (1) on Table 3.
Table 4. High and Low case after performing Equation (1) on Table 3.
From Table 3Low CaseHigh Case
0 < 10 MWh/day3106
10 < 100 MWh/day72117
100 < 1000 MWh/day182428
1 < 10 GWh/day273429
10 < 100 GWh/day332327
100 < 1000 GWh/day2116
1 < 10 TWh/day400
Total113113113
Table 5. Summary of headline values.
Table 5. Summary of headline values.
Total Insolation-Gross [TWh/day]Total Insolation-Minus Exclusions [TWh/day]Energy Production-High Case [TWh/day]Energy Production-Low Case [TWh/day]
14.8812.061.861.01

Share and Cite

MDPI and ACS Style

van der Merwe, W.; Brent, A.C. Evaluating the Energy Potential of Solar PV Located on Mining Properties in the Northern Cape Province of South Africa. Sustainability 2020, 12, 5857. https://doi.org/10.3390/su12145857

AMA Style

van der Merwe W, Brent AC. Evaluating the Energy Potential of Solar PV Located on Mining Properties in the Northern Cape Province of South Africa. Sustainability. 2020; 12(14):5857. https://doi.org/10.3390/su12145857

Chicago/Turabian Style

van der Merwe, Waldo, and Alan C. Brent. 2020. "Evaluating the Energy Potential of Solar PV Located on Mining Properties in the Northern Cape Province of South Africa" Sustainability 12, no. 14: 5857. https://doi.org/10.3390/su12145857

APA Style

van der Merwe, W., & Brent, A. C. (2020). Evaluating the Energy Potential of Solar PV Located on Mining Properties in the Northern Cape Province of South Africa. Sustainability, 12(14), 5857. https://doi.org/10.3390/su12145857