1. Introduction
Modular steel construction is a novel kind of building structure. The modular building structure system uses a single room as a “module” that is built in the factory. The interior of the module can be arranged and decorated in the factory, and then the module is lifted to the building site and connected to the other modules to make the building body. This system has a high prefabrication ratio, saves labor and materials, shortens construction time, and is green. Modular building has an advantage over traditional architecture in that it can simplify the complex building structure and break up the complex functional system into subsystems, making it easier to manage and implement [
1,
2]. Today, the development of assembled buildings is relatively fast in the United States, Japan, Canada, Singapore, and other countries.
In general, keywords are used to describe the knowledge areas found in a particular subject of study. It may show the borders of the study domain and certain connections and trends between the research fields.
Figure 1 shows the keywords network of modular construction based on the literature visualization tool VOSviewer. As shown in
Figure 1, the keywords related to the modular structure, including Building Information Modeling (BIM) technology, off-site construction, efficient management, and prefabricated components, can be seen.
The spread of the novel coronavirus disease (COVID-19) pandemic created considerable excitement about emergency preparations. Emergency buildings would have rapid construction methods such as modular buildings, integrated buildings with fast construction methods, 3D-printed buildings, and temporary structures such as inflatable membranes [
3,
4,
5]. All of these emergency building forms must fulfill the following specifications to respond to the needs in disaster time: streamlined designs, industrialized machining and processing, simple assembly phase, installed interiors, parts, and incorporated equipment and facilities points to functional satisfaction, quick construction, and intense productivity [
6,
7,
8,
9].
Modular integrated construction (MiC) is a game-changing technology due to its inherent topological modular structure and increased number of repeatable modules. It enables faster construction, safer fabrication, improved quality control, and lower environmental impact than traditional on-site construction [
10]. Modular construction is a viable alternative to on-site construction in the case of repetitive modules. Prefabricated volumetric modules are manufactured in a controlled environment such as a factory, then transported and assembled on-site to construct bigger, more permanent structures, such as modular steel buildings (MSB) [
11]. On the other hand, BIM opens up new ways to use computers to design and build modular buildings, which increases productivity and saves money. Sanchez et al. [
12] made a BIM tool that automatically picks the right parameters so that modular building parameters can be automatically extracted. Using BIM, Gan [
13] came up with a way to make it easier and more efficient to make modular buildings. The graphical data model he created is based on the modular theoretical representation of the building’s most important features. He and others [
14] looked into how BIM could be used to design and build connected modular shells on a computer. The BIM-based automated lifecycle assessment (LCA) of prefabricated buildings was developed by Ansah et al. [
15]. It has different assessment levels, unique system boundaries, and functional units, making it unique.
Today’s modular structures have sophisticated architectural, structural, and mechanical systems that span their entire lifespan, necessitating more study into interconnected building systems to improve lifecycle performance through the digital twin. In order to make the transition to data-driven decisionmaking, the Internet of Things (IoT) and artificial intelligence (AI) research fields must be expanded to gather massive data from preconfigured processes and conduct predictive analytics to improve control choices for manufacturing facility operations. In architecture, digital twins (BDTs) may be thought of as a manifestation of BIM+ derived from digital descriptions. The BIM design encompasses the potential of selecting building shapes, comparing and analyzing the performance of various materials, and using digital twins (BDTs) and BIM for architectural design [
16].
After decades of growth and progress, artificial intelligence is establishing a foothold in our everyday lives and starting to influence the disciplines of design and sustainability significantly. AI applications in sustainable buildings include energy-efficient building design, energy forecasting, and consumption minimization; devising methods to alleviate environmental and climatic consequences; and enhancing the safety and comfort of living spaces. Due to the dramatic rise in Internet speed and accessibility over the last several years and the decline in computer and data storage costs, big data (BD) now plays a critical complementary function to AI. The algorithms and computer programs have been created for data mining and analysis. The BD has reintroduced artificial intelligence technologies and applications in various disciplines, including sustainable architecture [
17].
The IoT is a self-contained intelligent service system capable of holistic status awareness, efficient data processing, and flexible information application. It is comprehensive in scope and extensively uses sophisticated information and communication technologies such as mobile Internet and artificial intelligence to enable human interaction with all power system components. Numerous IoT-enabled BIM (BIM) solutions have been created to improve production management by increasing information visibility, traceability, and collaboration [
18].
The present study tackles this gap by evaluating modular building research utilizing a three-tiered research strategy (data collation, scientific mapping, and systems analysis). The findings indicate that digital tools and technologies (DTT) are underutilized in the prefabricated transportation phase of modular integrated construction (MiC) and that blockchain and other integrated DTT have significant potential for usage in MiC projects [
19]. These findings underline the critical nature of the planning and design phases in effectively executing circular modular building projects [
20]. These examples demonstrate the critical nature of the planning and design phases in effectively executing circular modular building projects. Zabin et al. [
21] used machine learning approaches to go through the study field of BIM data production. The stages of modular building design and construction were identified as potential research objectives.
The hospital for dealing with emergencies uses modular construction to provide different areas. This article describes the establishment of a temporary emergency hospital—Vulcan Mountain Hospital/Huoshen Mountain Hospital—for patients with novel coronavirus-infected pneumonia (NCIP).
Figure 2 shows a panoramic view of the construction of Vulcan Mountain Hospital/Huoshen Mountain Hospital. This research framework in the present study blends the ideas of both the building and the layout. This article describes the in-depth integration of BIM technology in the design and construction process of the Vulcan Mountain Project, which may be seen as a rapid and time-saving solution given that BIM technology was employed throughout the building of the Vulcan Mountain Hospital project. The construction of emergency hospitals can be seen as an example of timely crisis management and response to potential risks [
1,
22].
This study is based on the Vulcan Mountain Hospital/Huoshen Mountain Hospital engineering background and uses the organic integration of modular design and assembly construction for project building. Structure and electromechanical equipment are constructed using a modular container assembly approach; BIM technology based on big data is employed to handle information exchange and collaboration. Using the quick construction idea of modular design and assembly construction, Vulcan Mountain Hospital/Huoshen Mountain Hospital was completed promptly with excellent quality. This study examines its technical capabilities and application features better to understand the benefits of modular construction for emergency buildings. The research shows how BIM design and modular construction may be used to enhance the quality of manufactured structures.
2. Background and Project Overview
Figure 2 shows the panoramic view of emergency hospital construction. The hospital occupies 220,000 m
2 of constructed space and 79,000 m
2 of unconstructed space. The hospital’s primary mission is to diagnose and treat patients with new coronavirus pneumonia. The east and west areas are planned and designed as isolation medical areas and medical and nursing living areas, respectively, with a total bed count of 1500 in the isolation medical area and approximately 2300 medical and nursing staff in the medical and nursing living area, which is equipped with the related operation and maintenance rooms. The isolated medical area and the medical and nursing living areas are primarily self-contained, and tight flow lines for medical and nursing, patients, logistics, and dirt are designed, with physicians and patients moving in separate directions; the sewage, rainwater, and medical waste are all collected and treated separately and are not discharged into the lake [
1,
23,
24].
3. Standardized, Modular, and Low-Carbon Design of Emergency Hospital
3.1. Incorporating BIM and Modular Construction
The cloud platform is configured automatically throughout the project’s design phase, and the design is carried out concurrently by people from different departments to maximize consistent standards and information interoperability. Using Revit software a28s as an example, the benefits of combining the two technologies in the design process are summarized to optimize and correct conflicting issues that arise during the design process, such as colliding pipes and incompatible structural elements within the building, as well as issues such as design considerations that were overlooked during construction and installation [
25,
26].
Furthermore, BIM technology enables the pre-calculation of engineering quantities during the design stage and the more scientific calculation of engineering quantities during the design stage. Additionally, the building model created using BIM technology has increased visibility, facilitating the depth and detail design phases of architectural design. The 3D visualization model saves half the work required for plan screening [
27].
To fulfill the construction deadline, the structural design of emergency hospitals must provide safety while also achieving the target in the shortest amount of time feasible. The modular light system may be free of the conventional building methods required at the building site and, at the same time, fulfill the demands of the emergency hospital’s functional area, which are crucial for responding to public health crises.
The hospital assembly structure follows standardization, modularity, and integration principles and uses established industrialized product systems extensively. The greater the degree of integration of completed modules, the less installation work is required on-site, the quicker the building process, and the simpler it is to guarantee the final product’s quality. The structural design process must consider site construction circumstances. The early design phase must communicate with the builder about the construction time, processing and transportation, personnel and equipment, material supply, and site-building techniques.
The structural plan is presented based on a complete demonstration to guarantee that on-site execution is feasible. The isolated medical area is a new one-story temporary structure that houses the health care unit, the ward nursing unit, the medical technology unit, and the reception area, but not the emergency clinic. The ward nursing unit is a light modular and steel frame construction mix. At the same time, the medical technology section is a steel frame + lightweight wall panel construction with a “fishbone” arrangement. The isolation medical sector comprises 30 isolation wards and 2 critical care units. The living space for medical and nursing staff includes a dormitory, an office, a dining area, and a storage room for cleaning materials. The dormitory area will see the addition of ten new dormitory buildings, all of which will be light steel movable panel structures, the majority of which will be two stories.
Perhaps it should be mentioned that the “Vulcan Mountain” and “Thunder Mountain” emergency hospitals were constructed in reaction to the COVID-19 pandemic. On a piece of waste ground, the Vulcan Hill Hospital was constructed. The Thunder God Hill Hospital was constructed on the parking lot of the 2019 7th World Military Games’ athletes’ village, and the original athletes’ restaurant of the military games may be used directly.
Figure 3 shows the planning diagram of the Vulcan Mountain Hospital/Huoshen Mountain Hospital.
The emergency hospital building comprises surgical isolation beds, patient and nursing living quarters, complete logistics environment, where the isolated medical area is separated into hospitals, reception rooms, intensive care units, medical technology rooms, positive and negative pressure stations, liquid oxygen stations, sewage treatment stations, sanitation services, and other functional areas [
28]. These critical sections may be modularly decomposed into regular units and then assembled and mixed according to the same modules. The architectural concepts of an emergency hospital are composed of the following.
3.1.1. Scalable, Symmetrical, Central-Axis Herringbone Configuration
In the shape of a fishbone with a central-axis symmetry, the architectural structure of the hospital consists of three zones and two channels. The working zoning module of the emergency hospital is seen in
Figure 4. The sterile location of the polluted site, the semi-polluted, and the contaminated sites are the three areas. The medical personnel channel and the patient channel are the two networks. The different groups of patients should be isolated from the networks utilized by patients and medical personnel, meaning that the medical staff’s role can be safe and more covered. While the clean region between ward units is the semi-contaminated field, the ward in the ward unit is the contaminated area [
29].
Figure 4 demonstrates that the emergency hospital buildings have an overall “fishbone” layout in the center and the wards on both sides. The “main fishbone” is the long hallway in the center, which acts as a corridor for medical, nursing, and office workers. The “secondary fishbone” linked to the aisle is the nine wards, which can be reached from one of the wardrobes in the gallery. The long arms of the floor plan consist of 12 simple units situated opposite each other, all of which form the whole medical unit of the emergency hospital.
Every “fishbone” is an individual treatment facility, and entry to the hospital is entirely segregated for patients and medical staff, with patients accessing the ward from the “fishbone” perimeter of the ward and medical staff entering the ward through the core “fishbone” path, eliminating cross-contamination.
One of the critical benefits of this “fishbone” style, inherited from an emergency Hospital during the SARS period, is that it is highly scalable—if desired, it can be extended easily to the appropriate “long-arm” without disrupting the original construction purpose, which is a unique architectural feature that addresses the present outbreak’s needs and requires a capacity to be developed for additional wards as the epidemic progresses.
3.1.2. Assembled Design and Space Modularization Realization
As shown in
Figure 5 and
Figure 6, Vulcan Hill Hospital will consist of multiple H modules arranged as shown in
Figure 5b, with office areas and medical staff access along the central axis. Each H-module is responsible for four nursing units. Two rows of wards are placed in the nursing units, each with 49 beds. Forty-nine beds are arranged as shown in
Figure 5c and
Figure 6. Four nursing units are one H-module, i.e., one treatment area.
Patients are admitted to and discharged from the unit through the outer ward. Medical and nursing personnel enter the center through several layers of clothes and hygienic passages to conduct examinations, administer medicine, and provide care. Such a strong structure enables strict control of the air purity scale, ensuring the health and welfare of medical and nursing personnel and providing for their optimum treatment.
3.1.3. Assembled Design Together with BIM
BIM technology combines and categorizes construction and structural materials electromechanical devices and specifically directs factory production [
8]. At the same time, BIM technology simulability is used to mimic on-site construction and determine the right assembly construction strategy that will significantly increase on-site assembly performance and speed development.
For BIM’s complete model forward design, the design and building period of the emergency hospital was too short. The design deals together with the stainless steel unit and the specialized design tools while developing the critical structure of the assembled stainless steel structure inside the medical/technical sector. The design model is specifically connected with the data for factory output, and the design phase information is directly imported into workshop production, saving much time.
3.2. Structural Design
The architecture of the building at the emergency hospital uses the concepts of standardization, modularity, and incorporation by allowing the use of mature, standardized building materials as much as possible. The more precisely the module systems are aligned, the less on-site assembly personnel is required, the faster the construction pace, and the easier it is to maintain uniformity. The engineering concept of the emergency hospital integrated two types of structural steel frameworks to fulfill different construction purposes in the separated patient field and medical and nursing living areas.
3.2.1. Nursing Unit Model
The nursing unit layout has a three-zone, two-aisle configuration, as seen in
Figure 6. There are 50 beds in a nursing unit, and one field is four nursing units. The essential criteria for hospitalization with infectious diseases are “three zones and two channels”: three regions are sterile areas, half-polluted areas, and polluted areas. The patient channel and the medical channel are linked to two outlets.
Partitioning considers that the medical workers should provide a safe work environment and continuous entry, as shown in
Figure 6. An axis in the center of the plan is the washing location, access, and function area, and both sides of the central axis are ward units. The semi-contaminated region is between the cleaning area and the ward unit, and the ward in the ward unit is the contaminated area, i.e., the transfer section where the medical staff and the ward come into touch, and a lot of medical staff’s work is performed in the semi-contaminated area.
Access for patients is beyond a nursing facility such that the access for patients is independent of access for health employees, meaning that the health workers are not infected. As seen in
Figure 7, the workers enter from clean areas into the emergency hospital, change into protective clothes in the wards; enter the work area for medical and nursing preparations, change into insulation garments and entering into the medical and nursing hall into the semi-contaminated area; and enter the contaminated wavelength.
3.2.2. Designing of a Modular Steel Frame
The isolated medical zone is a single-story building that includes a health access facility, a ward unit, a medical technology unit, and an intake space. Different assembly building types are used due to the other specifications of functional areas with varying net heights. The nursing unit is a standardized assembly-style, integrated architecture unit.
Figure 8 demonstrates the ward unit plan (module). The hospital has a rigid “three zones and two channels” design for medical and nursing workers to organize their work areas according to the “clean zone-semi-polluted zone-polluted zone” workflow. Each time people reach the first-floor region, the medical and nursing channels are segregated from the patient channels. There is a transition room in the isolation ward composed of two layers of glass and an ultraviolet light device under which the meals and drugs of the patient are passed and disinfected to prevent contamination by the ultraviolet light system in the cell. In each ward, two beds are located, and a separate toilet in the room provides medical and nursing staff with several safeguards in a secure and efficient working setting.
According to market inventory, the main sizes that can be procured are two types of 6.0 m × 3.0 m × 2.9 m and 2.0 m × 6.0 m × 3.0 m box-type modules (
Figure 9), and the building plane adopts a standardized design according to this condition. All units can be divided into two basic units, arranged and combined. The module unit height is 2900 mm, and the module is united by the main structure, floor, wall, ceiling, equipment pipeline, and interior parts. Furthermore, the module is a functionally integrated three-dimensional space body to meet the requirements of various building functions and lifting and transport requirements. The single container module consists of prefabricated plates and prefabricated steel columns, the size of prefabricated plates is 3 m × 6 m, the steel columns are “L”-shaped angles with a height of 3m, and bolts connect the hooks and prefabricated plates [
26,
27].
In the emergency hospital’s engineering design, modular and standard steel structures are adopted for the various building functions and spatial characteristics of isolated medical areas and medical and nursing homes. Since the modular assembly style steel framework insulating the ward care unit patient area has standard model modular characteristics, the modular assembly style steel structure construction technique is used. This modular box-type unit adopts a steel frame and color steel composite panel walls, which has strong structural integrity, high bearing capacity, wind and earthquake resistance, and safety and applicability.
The modular box units can be used individually and combined in different combinations as required and freely spliced to form a spacious usage space through different combinations in horizontal and vertical directions. They can be stacked vertically to form a multi-layer modular assembly building system. This project utilizes only one-layer modular assemblies, and the total amount of modules used exceeds 3190. The modular box is a steel frame structure, and the mainframe beams and columns are all cold-formed steel welded together, with a cold-formed steel spacing of 500~1200 mm welded on all six sides to ensure wall, top, and bottom plate strength and stability.
Figure 9 displays the box room unit’s module configuration decomposition schematic diagram. The prefabricated manufacturing plant prefabricates and extracts the products according to the processing diagram. After building requirements are available, the components are transported to the assembly site. Many on-site production procedures are transferred to the plant for industrial standardization, specialization, and mechanization, transforming the building and installation industry’s conventional construction mode, increasing performance, minimizing material waste, and reducing site emissions.
The medical–technical building and ICU’s s internal roles are diverse, and all are non-standardized units, so a light steel frame is used close to the shape of a temporary panel house.
The emergency hospital project reserved the rooting points of the brackets and holes through the walls needed for the electromechanical pipelines to ensure strong and durable powers during the container processing level. The pipeline equipment is mounted on-site owing to design and installation coordination. It requires the interspersed articulation of several technical jobs, creating shared constraints to combat a volatile circumstance and eventually disrupting the development time. For this purpose, mechanical and electrical engineers consider matching the modularization of building ward units. Each practical electromechanical pipeline equipment often adopts a modular device rapid-replication architecture, which can modularize and standardize pipeline production and equipment acquisition and processing, significantly accelerating development.
All wards are manufactured with the fire performance of container-type environmentally safe products; factory manufacturing and on-site prefabricating can significantly accelerate construction development. In order to ensure that the waterproof nodes are tight and eliminate water leakage, all components of the modular buildings are made in one go in the factory, which can control the installation error to the millimeter level. The hospital ward windows are locked, and the wards are fitted with a transition chamber comprising two layers of glass and an ultraviolet disinfection device. Each ward is uniquely fitted with a non-circulating fresh air system and an exhaust air system, creating a negative pressure system. Each ward care unit has 700 sets of fan supply and exhaust appliances, and the ventilation system plays the function of “guiding and navigating” indoor air. A pressure gradient of 5–10 Pa is established between contaminated, semi-polluted, and clean areas by monitoring air adjustments, air supply, and exhaust volume in polluted, semi-polluted, and clean rooms to “guide” it from a safe zone to a dirty zone. Simultaneously, it is set in the poisoning device’s exhaust duct to destroy the first poisoning treatment indoor air before discharge to remove air pollution.
3.2.3. Foundation and Seepage Control Design
In general, the pouring and hardening of concrete were achieved in less than eight days (with low temperatures), ending on the eighth day. The concrete design of the emergency hospital project belongs to the winter construction, which has steps to speed up the structure, while maintaining the building quality is a cautious problem.
Due to the bigger foundation area, heavier backfill at the site, and short construction duration, the design uses a reinforced concrete raft slab foundation to minimize uneven settling. In order to make equipment pipeline laying quick and easy, the raft foundation surface was lowered 150~300 mm, and steel beams were installed on top to support container units.
Figure 10 shows the two foundation types for Vulcan Hill Hospital. This method allows impermeable membrane protection and equipment majors’ pipeline laying requirements to be met simultaneously, shortening construction time.
The emergency hospital is built and developed for wastewater management in line with long-term construction and is completely enclosed for service. It is similar to a whole patient wearing a protective clothing layer. The medical wastewater is pumped to the municipal network after tertiary liquid chlorine disinfection. The whole hospital foundation is paved with an impermeable membrane according to landfill requirements, and all rainfall is collected and treated to ensure no sewage enters the environment. Specific procedures are listed here.
The anti-seepage construction method is as follows: sand of 20 cm thickness is laid on the leveled ground and interspersed with the pre-burial pipeline construction. Then, two cloths and one membrane (two layers of 600 g/m
2 polypropylene filament geotextile and one layer of 2.0 mm double rough surface impermeable membrane HDPE) are laid on top, and then 20 cm of sand is applied, which has an anti-seepage solid effect (
Figure 11).
4. Accelerated Construction of the Emergency Hospital
The emergency hospital’s building phase focuses on the general contractor model, incorporating the project’s planning procurement and construction to accelerate building development. The project was introduced based on requirements such as the Code for the Development and Approval of Hospital Buildings for Infectious Diseases (GB 50686-2011), Building Architecture Code for General Hospitals (GB 51039-2014), and Building guidelines of the emergency medical facility (IWA38).
4.1. Difficulties of Accelerated Construction and Countermeasures
The emergency hospital project encountered several difficulties, from a patch of wasteland to a standard infectious disease facility: firstly, the extreme environments in preparation, the gap in height between the east and west of the site up to 10 m, the high workload of the site leveling, and the massive volume of planning for the relocation of the initial gas and high-voltage pipelines; secondly were the challenge of personnel mobilization, the complexity of organization and coordination, and the hundreds of subcontracting groups. Part of the construction photos are shown in
Figure 12.
Moreover, the supply demand is enormous; the need for site materials is considerable: the demand for box-type cubicles amounts to 1650, different doors amount to 1500, the demand for concrete amounts to 14,000 m
3, and the need for HDPE film amounts to 100,000 square meters. Because the construction was during the Chinese New Year, ordering was difficult, and there were differences in the specifications of the required modular panels. The protection and disease will be inconsistent; epidemic preventive protection was also evaluated.
Table 1 demonstrates the project’s challenges, countermeasures, and measures studied.
4.2. Control of Information and Development Installation
Because of the standard container material supply size error, the assembly error is far greater than the typical module space because of the horizontal configuration of two standard modules plus one standard vertical module arrangement (corridor) of the assembly type. If the seam width is not treated correctly, the roof leakage issue may occur, but it affects home décor and medical equipment installation afterward. In order to solve the above problems, BIM technology was implemented comprehensively to evaluate and compare construction solutions and decide on the structural system, combined segment, and attachment node solutions for rapid construction of ICU buildings, and medical–technical buildings. In order to realize the rapid construction of assembled steel framework, the line model in AutoCAD format was refined, completed, and imported into the Tekla program to create a BIM model online and render the comprehensive design of steel structure construction to solve the problems of irregular building shape, complicated structural layout, and collision of bars.
The BIM model is used to encourage construction technology performance, as anticipated. Electromechanical installation includes water supply and drainage, illumination, ventilation, air conditioning, connectivity, electricity service, and medical gas. The project adopts BIM technology to develop a clean area and separation area pipeline arrangement model to simulate pipeline collisions and other problems in advance, not just to achieve the necessary pipeline interspersed phase but also to optimize space and time to ensure the aesthetics of the pipeline arrangement.
The construction technology is incorporated into the engineering design by understanding both the building and structure functions and the processing quality and construction performance at the design level, which essentially solves the problem of information fault and information island among the rapid construction elements such as project design, manufacturing, and construction.
BIM technology facilitates the exchange and control of engineering knowledge via a standardized framework. In the medical care field building, the project technical team used BIM modeling to refine six designs, including utilizing a steel framework instead of the standard concrete base, backfilling instead of partial site hardening, adapting indoor stairs to outdoor, and so on. A total of 18 days were saved during the building of the Vulcan Mountain Hospital scheme, and its inhabitants could experience the new dormitory.
BIM technology is used to overcome the contradiction created by thousands of cross-operational events in the project. The planning, layout, manufacturing, and installation were meticulously planned and coordinated to speed up the construction process. Since the Vulcan Mountain Hospital project was developed during the winter, urgent hardening measures were necessary for the site: the flexible use of site conditions according to local requirements, the use of quick hardening of the ground, and the use of a variety of foundation forms, including steel support piers and raft slabs, to address the foundation construction issues that impede the rapid construction of assembly buildings. Another example is using beryllium beams to supplement the overhead beams and fix issues such as column footing installation.
4.3. Phase for Building
The design phases of the emergency hospital project involve the following: Site leveling → seepage resistance → tying of reinforcement → pouring of foundation → assembly of the main structure of modular building → power on, and commissioning. The development schedule of the project is shown in
Table 2.
5. Intelligent Emergency Hospital Project Scenario
There has been a huge rise in the use and development of technologies such as ICT, AI, cloud computing, and big data, which has led to changes in the medical and health fields. During the COVID-19 pandemic, 5G, IoT, AI, and service-oriented robots worked very well together to fight the pandemic, which was very bad.
(1) The creation of BIM, 5G, robots, and other technology such as Drone Technology: BIM aids in the integrated design of each specialty within the emergency hospital, the design and optimization of assembly modules, cost analysis, processing and production simulation, on-site visualization and delivery, 5D monitoring, and other applications, and the use of BIM, IoT (IoT), cloud platform, GIS, and 2D Code to enable on-site verification and tracking of the assembly process.
(2) For teleconsultation, remote diagnosis and treatment, remote monitoring, enormous data transfer, and supporting frontline medical professionals, 5G can provide high-speed Internet access.
(3) Medical AI that can precisely locate tumors on CT scans. The top of Vulcan Mountain Hospital/Huoshen mountain hospital has 1597 patients. Inpatients stay an average of 20 days in the hospital, and CT imaging is required every 3–4 days to identify patients. Reviewing and comparing patients’ prior imaging data would be laborious for clinicians. Medical AI solves this. The developers created a novel AI model to capture changes in patients’ situations throughout therapy that uses rich CT image samples to detect lesions and quantify their percentage change. Normal CT reading time is now 20 s, and AI now writes most imaging reports.
(4) Hospitals employ one set of network to connect various IoT devices. Many IoT devices are employed in hospitals, such as pharmacy temperature and humidity sensors, patient monitoring in isolation rooms, mobile care bracelets, and infectious waste tracking. Verified terminal and application identification achieve bandwidth assurance for specified terminals and applications. Realize modern medical care approaches such as telemedicine and AI to identify ailments and arrange treatments. Improve hospital service quality and operational efficiency. Simultaneously, it can perform real-time patient data analysis and clinical decision support.
6. Conclusions
Vulcan Mountain Hospital/Huoshen Mountain Hospital is built on a modular design and construction philosophy that combines modular design with assembly-based construction. The primary structure is constructed utilizing the MSBs assembly technique, which uses MiC to manufacture all components of the modular buildings in the factory and then install and prefabricate them on the construction site.
From four aspects, including assembly design, rapid construction, anti-pollution diffusion, and BIM technology and information technology, the paper studied the fast construction process of the emergency hospital project, drawing the following conclusions based on the above study.
Construction assembled. This is the first concept of emergency hospital design utilizing assembly technologies, using container-type package operation room for integrated assembly, up to 6.0 m × 3.0 m × 2.9 m panel splicing to form a standard unit, the full realization of the modular, automated, installed project to increase engineering progress design.
Preventing and designing waste. The emergency hospital project adopts the design of “three zones and two channels,” and the medical and nursing workers organize the work areas according to the “clean zone-semi-polluted zone-polluted zone” workflow. The project adopts a modular sealing device, air pressure management ward anti-proliferation technology, and comprehensive anti-seepage technology, “two cloths and one film,” to achieve successful infection prevention and control.
Speedy building technology. BIM technology is utilized throughout the building process to facilitate information exchange, integrated management of all professions, and coordination across all professions. It refers to the integrated design, assembly module design, and optimization of each specialization of the construction project with the assistance of BIM. Artificial intelligence, 5G, and the IoT are all being combined to construct a smart activity and maintenance management network for the emergency hospital.
Practical advice and instruction. Emergency buildings are still imperfect regarding relevant standards, and there are not many standardized series of standards that can be used as a reference for enterprises. China IPPR International Engineering Co., Ltd. prepared the Building guideline for the emergency medical facility (IWA38), authorized by the ISO Technical Committee for the Construction of the Scheme, to summarize the expertise acquired in the construction of emergency medical facilities and to provide the international community with a reference software.
Limitations. Vulcan Mountain Hospital/Huoshen Mountain Hospital is an EMT project. In an emergency, when only modular structures can be created fast, assembled buildings “may represent the future of swiftly deployable healthcare.” Unlike long-term hospital structures, the Vulcan Mountain Hospital/Huoshen Mountain Hospital must answer current concerns. They are not created for eternity, but their remarkable timing and global testimony on the air may make their architectural history. However, this so-called experience may only be somewhat important.
Author Contributions
Conceptualization, Methodology, and original draft, L.C.; Data curation, Formal analysis, and Writing—review and editing, C.Z.; Software, Visualization, and Writing—review & editing, L.W.; Formal analysis, Software, and Visualization, X.H. (Xiaolun Hu); Project administration, and Writing—review and editing X.H. (Xiaoming Huang). All authors have read and agreed to the published version of the manuscript.
Funding
This research is supported by the National Key Research and Development Program of China under Grant No. 2021YFB2600600.
Institutional Review Board Statement
Not applicable.
Informed Consent Statement
Not applicable.
Data Availability Statement
Not applicable.
Acknowledgments
The corresponding author thanks the 2018 Jiangsu Provincial Government Scholarship Program (No. 228) for the University of California, Los Angeles. Moreover, the authors are also grateful to CITIC design, China Construction Third Engineering Bureau, and China Construction Fifth Engineering Bureau for providing design drawings and construction photos. Special thanks to CITIC DESIGN. CITIC DESIGN declares the launch and distribution of the free donation of the emergency hospital design findings for all parties in need.
Conflicts of Interest
The authors declare no conflict of interest.
References
- Cai, S.; Ma, Z.; Skibniewski, M.J.; Bao, S. Construction automation and robotics for high-rise buildings over the past decades: A comprehensive review. Adv. Eng. Inform. 2019, 42, 100989. [Google Scholar] [CrossRef]
- Pan, M.; Linner, T.; Pan, W.; Cheng, H.M.; Bock, T. Influencing factors of the future utilisation of construction robots for buildings: A Hong Kong perspective. J. Build. Eng. 2020, 30, 101220. [Google Scholar] [CrossRef]
- Sendanayake, S.V.; Thambiratnam, D.P.; Perera, N.; Chan, T.; Aghdamy, S. Seismic mitigation of steel modular building structures through innovative inter-modular connections. Heliyon 2019, 5, E02751. [Google Scholar] [CrossRef]
- Walker, N.; Eberhard, P. Model order reduction of a modular scale model of a high rise building. PAMM 2019, 19, e201900069. [Google Scholar] [CrossRef]
- Lacey, A.W.; Chen, W.; Hao, H.; Bi, K.; Tallowin, F.J. Shear behaviour of post-tensioned inter-module connection for modular steel buildings. J. Constr. Steel Res. 2019, 162, 105707. [Google Scholar] [CrossRef]
- Chen, Z.; Liu, Y.; Zhong, X.; Liu, J. Rotational stiffness of inter-module connection in mid-rise modular steel buildings. Eng. Struct. 2019, 196, 109273. [Google Scholar] [CrossRef]
- Liu, H.; Abudayyeh, O.; Liou, W. BIM-Based Smart Facility Management: A Review of Present Research Status, Challenges, and Future Needs. Constr. Res. Congr. 2020, 2020, 2020. [Google Scholar]
- Hammad, A.W.; Akbarnezhad, A.; Wu, P.; Wang, X.; Haddad, A. Building information modelling-based framework to contrast conventional and modular construction methods through selected sustainability factors. J. Clean. Prod. 2019, 228, 1264–1281. [Google Scholar] [CrossRef]
- Chen, L.K.; Yuan, R.P.; Ji, X.J. Modular composite building in urgent emergency engineering projects: A case study of accelerated design and construction of Wuhan Thunder God Mountain/Leishenshan hospital to COVID-19 pandemic. Autom. Constr. 2021, 124, 103555. [Google Scholar] [CrossRef]
- Thai, H.; Ngo, T.; Uy, B. A review on modular construction for high-rise buildings. Structures. Elsevier 2020, 28, 1265–1290. [Google Scholar]
- Sanches, R.; Tao, J.; Fathieh, A.; Mercan, O. Investigation of the seismic performance of braced low-, mid-and high-rise modular steel building prototypes. Eng. Struct. 2021, 234, 111986. [Google Scholar] [CrossRef]
- Sanchez, B.; Rausch, C.; Haas, C.; Hartmann, T. A framework for BIM-based disassembly models to support reuse of building components. Resour. Conserv. Recycl. 2021, 175, 105825. [Google Scholar] [CrossRef]
- Gan, V.J.L. BIM-based graph data model for automatic generative design of modular buildings. Autom. Constr. 2022, 134, 104062. [Google Scholar] [CrossRef]
- He, R.; Li, M.; Gan, V.J.L.; Ma, J. BIM-enabled computerized design and digital fabrication of industrialized buildings: A case study. J. Clean. Prod. 2021, 278, 123505. [Google Scholar] [CrossRef]
- Ansah, M.K.; Chen, X.; Yang, H.; Lu, L.; Lam, P.T.I. Developing an automated BIM-based life cycle assessment approach for modularly designed high-rise buildings. Environ. Impact Assess. Rev. 2021, 90, 106618. [Google Scholar] [CrossRef]
- Wang, W.; Guo, H.; Li, X.; Tang, S.; Xia, J.; Lv, Z. Deep learning for assessment of environmental satisfaction using BIM big data in energy efficient building digital twins. Sustain. Energy Technol. Assess. 2022, 50, 101897. [Google Scholar] [CrossRef]
- Mehmood, M.U.; Chun, D.; Zeeshan; Han, H.; Jeon, G.; Chen, K. A review of the applications of artificial intelligence and big data to buildings for energy-efficiency and a comfortable indoor living environment. Energy Build. 2019, 202, 109383. [Google Scholar] [CrossRef]
- Wu, L.; Lu, W.; Xue, F.; Li, X.; Zhao, R.; Tang, M. Linking permissioned blockchain to IoT (IoT)-BIM platform for off-site production management in modular construction. Comput. Ind. 2022, 135, 103573. [Google Scholar] [CrossRef]
- Olawumi, T.O.; Chan, D.W.M.; Ojo, S.; Yam, M.C.H. Automating the modular construction process: A review of digital technologies and future directions with blockchain technology. J. Build. Eng. 2021, 46, 103720. [Google Scholar] [CrossRef]
- Wuni, I.Y.; Shen, G.Q. Developing critical success factors for integrating circular economy into modular construction projects in Hong Kong. Sustain. Prod. Consum. 2022, 29, 574–587. [Google Scholar] [CrossRef]
- Zabin, A.; González, V.A.; Zou, Y.; Amor, R. Applications of machine learning to BIM: A systematic literature review. Adv. Eng. Inform. 2022, 51, 101474. [Google Scholar] [CrossRef]
- Shalabi, F.; Turkan, Y. IFC BIM-based facility management approach to optimize data collection for corrective maintenance. J. Perform. Constr. Facil. 2017, 31, 04016081. [Google Scholar] [CrossRef]
- Kwuimy, C.A.K.; Nazari, F.; Jiao, X.; Rohani, P.; Nataraj, C. Nonlinear dynamic analysis of an epidemiological model for COVID-19 including public behavior and government action. Nonlinear Dyn. 2020, 101, 1545–1559. [Google Scholar] [CrossRef]
- Pan, S.; Guo, R.; Bertleff-Zieschang, N.; Li, S.; Caruso, F. Modular assembly of host–guest metal–phenolic networks using macrocyclic building blocks. Angew. Chem. Int. Ed. 2020, 59, 275–280. [Google Scholar] [CrossRef]
- Liu, X.; Zheng, X.; Balachandran, B. COVID-19: Data-driven dynamics, statistical and distributed delay models, and observations. Nonlinear Dyn. 2020, 101, 1527–1543. [Google Scholar] [CrossRef] [PubMed]
- Wang, H.; Zhao, X.; Ma, G. Novel coupled modular steel structure and seismic tests on high-performance interconnection. J. Constr. Steel Res. 2022, 189, 107058. [Google Scholar] [CrossRef]
- Dai, Z.; Cheong, T.C.; Pang, S.D.; Liew, J.R. Experimental study of grouted sleeve connections under bending for steel modular buildings. Eng. Struct. 2021, 243, 112614. [Google Scholar] [CrossRef]
- Gatheeshgar, P.; Poologanathan, K.; Gunalan, S.; Shyha, I.; Sherlock, P.; Rajanayagam, H.; Nagaratnam, B. Development of affordable steel-framed modular buildings for emergency situations (COVID-19). Structures 2021, 31, 862–875. [Google Scholar] [CrossRef]
- Gbadamosi, A.Q.; Oyedele, L.; Olawale, O.; Abioye, S. Offsite construction for emergencies: A focus on isolation space creation (ISC) measures for the COVID-19 pandemic. Prog. Disaster Sci. 2020, 8, 100130. [Google Scholar] [CrossRef]
| Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations. |
© 2022 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).