3.1.2. The Countries That Provided Significantly Inadequate or Incomplete Data
Scheduling can be regarded to be perfect when the dots in the scatter chart showing the joint distribution of the real and the forecasted wind power data lie on the diagonal. Ideal situations such as that, however, never take place, so dots lying on the diagonal signal some problem in the provision of data.
Among the countries involved in the investigation, there were some which submitted information related to wind power generation and/or forecasted schedule data to the ENTSO-E Transparency Platform, but their study indicated seriously flawed or incomplete provision of data. These were the countries below:
Onshore wind farms: the Netherlands, Norway, and the Slovak Republic;
Offshore wind farms: no country in this category.
Onshore wind farms.
The Netherlands.
In the case of the Netherlands,
Figure A1 shows that until the end of the period examined, the DA and ID schedule energy generation forecasts contained values exceeding the actual data significantly, i.e., overscheduling occurred. This suggests that the actual data and the forecasted values belonged to onshore wind farms of different capacities, whose order of magnitude is illustrated by data from 2015, 2018, and 2021:
Period: 24 August 2015 21:15–21:30 (CET), real power: 383 MW, DA forecasted power: 2196 MW;
Period: 21 June 2018 18:30–18:45 (CET), real power: 972 MW, DA forecasted power: 4042 MW;
Period: 1 November 2021 12:15–1 November 2021 12:30 (CET), real power: 1532 MW, ID forecasted power: 3941 MW.
Because of the scheduling issues above, the quantities of the downward and upward regulation requirements were not determined from the differences between the actual energy generation and the forecasts.
Norway.
Although there were data provisions for the ENTSO-E system on the part of Norway, it can be seen that the actual power data and the DA schedule energy generation forecast data were mostly identical during the period 2015–2021 (
Figure A2). Therefore, this country was classified as a ‘country with severely inadequate or incomplete data provision.’ Due to the above scheduling problems, the amounts of the downward and upward regulation requirements were not established from the differences between the actual energy generation and the forecasts for this nation.
The Slovak Republic.
Slovakia was also included in the category of the ‘countries with severely inadequate or incomplete data provision,’ since there was data provision to the ENTSO-E Transparency Platform, albeit inadequate. During most of the period 2015–2021, there is a value of 0 in the database of the actual power, while 1 and 2 MW can be seen for the DA and ID values. Due to these scheduling anomalies, the quantities of the downward and upward regulation requirements were not determined from the differences between the real energy generation and the forecasts, and the distributions were not displayed either.
3.1.3. The Nations with Suitable Data for the Comparative Analysis of the Scheduling Characteristics of Their Wind Farms
Among the examined countries, there were 26 (Austria, Bosnia and Herzegovina, Belgium, Bulgaria, Switzerland, Cyprus, Germany, Denmark, Estonia, Spain, Finland, France, Greece, Croatia, Hungary, Ireland, Italy, Lithuania, Latvia, Montenegro, the Republic of North Macedonia, Poland, Portugal, Romania, Sweden, and the United Kingdom) whose onshore wind farm scheduling parameters proved to be suitable for analysis, while in the case of onshore wind farms, this was only true for 6 nations (Belgium, Germany, Denmark, The Netherlands, Portugal, and the United Kingdom). It was highlighted by the results of the investigation that under- or overscheduling was characteristic (to a lesser or greater degree) to the countries studied (clusters of dots below or above the diagonal in the visualizations of the joint distributions). The following section presents the characteristics of the onshore and offshore wind farm scheduling and the amounts of the downward and upward regulation requirements in the particular countries. The case of every examined nation is presented in a similar logical arrangement to enhance comparability.
Onshore wind farms.
Austria.
In the case of Austria, it can be observed that both under- and overscheduling characterized the DA and ID forecasts made for the onshore wind farms (
Figure A3). In the case of ID forecasts, there were scheduling periods between 27 and 28 October 2021 when the value of the ID forecast was 10000 MW, but the actual data differed significantly from that. This is illustrated below:
Period: 27 October 2021 15:30–15:45 (CET), real power: 4 MW, ID forecasted power: 10000 MW;
Period: 28 October 2021 19:00–19:15 (CET), real power: 2024 MW, ID forecasted power: 10000 MW.
The situation outlined above suggests operational disorders at the system level, however, in the schedules submitted to the TSO, these forecasted values were taken into consideration. Taking the annual energy generation as a basis, the proportions of the downward and upward regulation developed as follows (
Table A1):
In the case of DA scheduling, the proportion of the downward regulation requirement to the annual energy generation ranged from 9.8% to 15.9%, which could be improved by a few percentage points by the deployment of ID scheduling.
As for the proportion of the upward regulation need for the annual energy generation in the case of DA scheduling, it varied between 11.6% and 14.6%, which could also be improved by some percentage points when using ID scheduling, in the majority of the cases.
Bosnia and Herzegovina.
In the case of Bosnia and Herzegovina, it can be seen that overscheduling was characteristic of the DA and ID forecasts made for the onshore wind farms; a significant part of the dots are above the diagonal in the scatter plots of the joint distributions (
Figure A4). Based on the proportions of the annual downward and upward regulation requirements for energy generation, the following observations can be made (
Table A2):
The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling was 6.3%. Compared to the DA forecasts, the deployment of ID scheduling only resulted in minimal improvement.
The need for upward regulation compared to the annual energy generation in the case of DA scheduling was 44.8%. The application of ID scheduling made the accuracy even worse, compared to the DA one.
Belgium.
Of the examined nations, Belgium was the country with the most detailed data available on onshore wind farms. Based on the results, (
Figure A5), it can be seen that under- and overscheduling occurred in the case of both DA and ID forecasting for onshore wind farms. The proportions of the downward and upward regulation needs per year for energy production are shown in
Table A3:
In the case of DA scheduling, the proportion of the downward regulation need to the annual energy generation varied between 5.1% and 12.7%, which could be improved by some percentage points by using ID scheduling in the overwhelming majority of the cases.
The proportion of the upward regulation need to the annual energy generation in the case of DA scheduling lay between 10.2% and 20.6%. Compared to the DA forecasts, the deployment of ID scheduling caused a maximum improvement of 6.5% of the annual upward regulation need.
Bulgaria.
In the case of Bulgaria, it can be observed that overscheduling was characteristic of the DA forecasts made for the onshore wind farms; the majority of the dots are above the diagonal in the scatter plots of the joint distributions (
Figure A6). Taking the annual energy generation as a basis, the proportions of the downward and upward regulation developed as follows (
Table A4):
The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling ranged between 11.3% and 15.5%.
Compared to the downward regulation needs, the annual upward regulation requirement posed a greater challenge in terms of the management of scheduling, which might have been caused by the fact that those preparing the forecasts were not in possession of the weather data related to meteorological situations which proved to be more changeable than expected during the scheduling period. The proportion of the upward regulation need to the annual energy generation in the case of DA scheduling varied between 19.8% and 40.3%.
Switzerland.
As for Switzerland, both under- and overscheduling could be observed in the case of the DA forecasts made for the onshore wind farms (
Figure A7). During the examined period, it was only in 2020 and 2021 when the data provided was not adequate (the forecasted power figures had zero value), and this was the reason why this nation was not classified as one of the ‘countries with significantly inadequate or incomplete data provision’. It was due to this that the amounts of the downward and upward regulation requirements were not determined from the differences between the real energy generation and the forecasts for these two years. The proportions of the annual downward and upward regulation requirements for energy production were as follows (
Table A5):
The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling varied between 15.5% and 41.5%.
The proportion of the upward regulation need to the annual energy generation in the case of DA scheduling lay between 8.9% and 67.9%.
Cyprus.
In the case of Cyprus, it can be observed that both under- and overscheduling characterized the DA forecasts made for the onshore wind farms (
Figure A8). Taking the annual energy generation as a basis, the proportions of the downward and upward regulation developed as follows (
Table A6):
The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling varied between 17.1% and 21.9%.
The proportion of the upward regulation need to the annual energy generation in the case of DA scheduling ranged between 16.7% and 23.4%.
Germany.
One of the most accurate DA and ID forecasting mechanisms connected to onshore wind farms is seen in the case of Germany. It can be observed that, in the case of the DA forecasts, the dots are nearer to the diagonal, which indicates accurate forecasting (
Figure A9).
For this country, appropriate ID forecast data are available starting from 2018, so the amounts of the downward and upward regulation requirements related to them were established for the years 2018–2021. The ID forecasts dated earlier than 2018 appear to be connected to onshore wind farms of different capacities, which resulted in underscheduling. This is illustrated below:
Period: 1 June 2015 00:00–00:15 (CET), real power: 15052 MW, ID forecasted power: 6820 MW;
Period: 7 February 2016 06:30–06:45 (CET), real power: 20098 MW, ID forecasted power: 10967 MW;
Period: 23 February 2017 01:30–23 February 2017 01:45 (CET), real power: 26327 MW, ID forecasted power: 10535 MW.
Taking the annual energy generation as a basis, the proportions of the downward and upward regulation developed as follows (
Table A7):
In the case of DA scheduling, the proportion of the downward regulation need to the annual energy generation varied between 4.9% and 6.4%, which could be improved to some extent by using ID scheduling in the overwhelming majority of the cases.
In the case of DA scheduling, the proportion of the upward regulation requirement to the annual energy generation ranged from 4.1% to 6.5%, which could be improved by the deployment of ID scheduling.
There may be several reasons for Germany’s forecasting accuracy. On the one hand, among the examined ENTSO-E countries, it has the most onshore wind farms over a large geographical area, and thus they offset one another’s inaccuracies to some degree. On the other hand, developments related to onshore wind farm power generation forecasting have a continuous history of more than 10 years there [
64].
Denmark.
In Denmark, both under and overscheduling can be observed in the case of the DA forecasts made for the onshore wind farms. However, it is also to be seen that most of the dots are located near the diagonal, which suggests a relatively high level of forecasting precision (
Figure A10). The proportions of the annual downward and upward regulation requirements for energy production were as follows (
Table A8):
The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling varied between 4.6% and 7.9%.
The proportion of the upward regulation need to the annual energy generation in the case of DA scheduling ranged between 3.7% and 13.2%.
Estonia.
In the case of Estonia too, it can be seen that both under- and overscheduling were characteristic of the DA forecasts made for the onshore wind farms (
Figure A11). This observation is also supported by the proportions of the annual downward and upward regulation requirements for energy generation (
Table A9):
The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling was between 6.2% and 40.5%.
The proportion of the upward regulation need to the annual energy generation in the case of DA scheduling ranged between 2.7% and 32.4%.
Spain.
Similarly to the case of Germany, the results of Spain also indicate that this country can boast one of the most accurate DA and ID forecasting mechanisms related to onshore wind farms. It is to be seen that, in the case of the DA forecasts, the clusters of dots are near the diagonal, which signals accurate forecasting (
Figure A12).
In the course of DA scheduling, the proportion of the downward regulation requirement to the annual energy generation ranged from 0.8% to 4.7%, which could be improved by a few percentage points by the deployment of ID scheduling.
In the case of DA scheduling, the proportion of the upward regulation requirement to the annual energy generation varied between 0.8% and 4.6%, which could be improved further by the deployment of ID scheduling (
Table A10).
Similar to the case of Germany, there may be several reasons behind Spain’s accuracy in forecasting. On the one hand, it also belongs to those examined ENTSO-E countries which possess a large amount of onshore wind farm capacity (26.6 GW in 2021), spread over a vast geographical area, and thus the wind farms compensate for one another’s inaccuracies to a certain degree. On the other hand, developments related to onshore wind farm power generation forecasting have been going on dynamically for more than 10 years [
65,
66].
Finland.
In the case of Finland, the results show that the DA and ID forecasts made for onshore wind farms were characterized by both under- and overscheduling (
Figure A13). Based on the proportions of the annual downward and upward regulation requirements for energy generation, the following observations can be made:
France.
Similarly to Germany and Spain, the French results also suggest that this nation possesses one of the most accurate DA and ID forecasting mechanisms connected to onshore wind farms. It can be seen that, in the cases of both the DA and the ID forecasts, the clusters of dots are located near the diagonal, which indicates accurate forecasting (
Figure A14):
In the course of DA scheduling, the proportion of the downward regulation requirement to the annual energy generation ranged from 5.2% to 7.5%, which could be improved by a maximum of 1.3% by the deployment of ID scheduling.
In the case of DA scheduling, the proportion of the upward regulation requirement to the annual energy generation varied between 4.2% and 6.2%, which could be improved further by the deployment of ID scheduling in most of the cases (
Table A12).
The reasons leading to France’s accuracy in forecasting must be similar to those in the cases of Germany and Spain. On the one hand, France is also one of the examined ENTSO-E countries that possess a large volume of onshore wind farm capacity (17.2 GW in 2021), scattered over a vast geographical area, with the wind farms offsetting one another’s inaccuracies to some extent. On the other hand, developments related to onshore wind farm power generation forecasting have been going on dynamically in France for more than 10 years too [
65,
66].
Greece.
In the case of Greece, it can be observed that overscheduling was characteristic of the DA and ID forecasts made for the onshore wind farms; a significant part of the dots are above the diagonal in the scatter plots of the joint distributions (
Figure A15). Based on the proportions of the annual downward and upward regulation requirements for energy generation, the following conclusions can be drawn (
Table A13):
The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling varied between 3.2% and 7.9%. Compared to the DA forecasts, the deployment of ID scheduling could achieve a maximum improvement of 1.5% of the annual downward regulation need.
Regarding scheduling, the volume of the upward regulation need was more significant than that of the downward regulation requirement, which may have been caused by the fact that those preparing the forecasts could not precisely calculate with the changeable weather conditions. In the case of DA scheduling, the proportion of the upward regulation requirement to the annual energy generation ranged between 8.2% and 17.3%, which could be improved further by the deployment of ID scheduling, albeit only to a negligible degree.
Croatia.
Both under- and overscheduling could be observed in the case of the DA and ID forecasts made for the onshore wind farms in Croatia (
Figure A16). The proportions of the downward and upward regulation needs per year for energy production are displayed in
Table A14:
In the case of DA scheduling, the proportion of the downward regulation need to the annual energy generation varied between 9.7% and 9.9%, which could be improved to a negligible extent by using ID scheduling.
The proportion of the upward regulation need to the annual energy generation in the case of DA scheduling lay between 7.9% and 9.0%. Compared to the DA forecasts, the deployment of ID scheduling could lead to a maximum improvement of 0.9% of the annual upward regulation need.
Hungary.
Overscheduling was characteristic of most of the DA and ID forecasts made for the onshore wind farms in a Hungary; a significant part of the dots are above the diagonal in the scatter plots of the joint distributions (
Figure A17). The proportions of the annual downward and upward regulation requirements for energy production were as follows (
Table A15):
The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling varied between 10.3% and 15.8%. Compared to the DA forecasts, the deployment of ID scheduling could improve the annual downward regulation need even by a maximum of 8.2%.
Regarding scheduling, the volume of the upward regulation need was more significant than that of the downward regulation requirement, which might have been caused by the fact that those preparing the forecasts were not in possession of the weather data related to meteorological situations, which proved to be more changeable than expected during the scheduling period. The proportion of the upward regulation need to the annual energy generation in the case of DA scheduling lay between 11.3% and 26.7%, which could be improved by 3.2% maximum by the use of ID scheduling.
Ireland.
Based on the results, (
Figure A18), it can be seen that under- and overscheduling both characterized DA forecasting for onshore wind farms in Ireland. The proportions of the annual downward and upward regulation requirements for energy production were as follows (
Table A16):
The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling varied between 8.4% and 14.5%.
The proportion of the upward regulation need to the annual energy generation in the case of DA scheduling lay between 7.2% and 16.6%.
Italy.
In the case of Italy, the results indicate that underscheduling was characteristic of the DA and ID forecasts made for the onshore wind farms; a significant part of the dots are below the diagonal in the scatter plots of the joint distributions (
Figure A19). Based on the proportions of the annual downward and upward regulation requirements for energy generation, the following observations can be made (
Table A17):
Regarding scheduling, the volume of the downward regulation need was more significant than that of the upward regulation requirement, which might have been caused by the fact that those preparing the forecasts were not in possession of the weather data related to meteorological situations that proved to be more changeable than expected during the scheduling period. The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling varied between 10.4% and 11.8%. Compared to the DA forecasts, the deployment of ID scheduling could only lead to a minimal improvement of the annual downward regulation need.
In the case of DA scheduling, the proportion of the upward regulation requirement to the annual energy generation ranged between 2.7% and 4.8%, which could be improved only to a negligible degree by the deployment of ID scheduling.
Lithuania.
In the case of Lithuania, the results show that the DA and ID forecasts made for onshore wind farms were characterized by both under- and overscheduling (
Figure A20). The proportions of the annual downward and upward regulation needs for energy production also illustrate this observation (
Table A18):
In the case of DA scheduling, the proportion of the downward regulation need to the annual energy generation varied between 6.1% and 14.2%, which could be improved by some percentage points by using ID scheduling.
The proportion of the upward regulation need to the annual energy generation in the case of DA scheduling lay between 9.2% and 24.3%, which could be improved by 4.8% maximum by the use of ID scheduling.
Latvia.
Both under- and overscheduling could be observed in the case of the DA and ID forecasts made for the onshore wind farms in Latvia (
Figure A21). The proportions of the annual downward and upward regulation requirements for energy production were as follows (
Table A19):
In the course of DA scheduling, the proportion of the downward regulation requirement to the annual energy generation ranged from 10.3% to 24.2%, which could be improved by a maximum of 1.6% by the deployment of ID scheduling
The proportion of the upward regulation need to the annual energy generation in the case of DA scheduling lay between 14.3% and 29.6%, which could be improved by 1.3% maximum by the use of ID scheduling.
Montenegro.
Both under- and overscheduling could be observed in the case of the DA and ID forecasts made for the onshore wind farms in Latvia (
Figure A22). This is also verified by the proportions of the annual downward and upward regulation requirements for energy generation (
Table A20).
The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling varied between 10.6% and 24.6%. The application of ID scheduling either did not make any difference or even made the accuracy worse by up to 3.7% compared to the DA one.
The proportion of the upward regulation need to the annual energy generation in the case of DA scheduling lay between 18.4% and 36.2%. Compared to the DA forecasts, the deployment of ID scheduling could improve the accuracy by up to 3.8%.
The Republic of North Macedonia.
One of the least accurate forecasting mechanisms is observable in the case of the Republic of North Macedonia (
Figure A23). The analysis of the actual and the forecasted data could not reveal clearly whether they were related to differing onshore wind farm capacities. This was the reason why this country was not classified as one of the ‘countries with significantly inadequate or incomplete data provision’ (
Table A21).
The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling varied between 26.5% and 49.1%.
The proportion of the upward regulation need to the annual energy generation in the case of DA scheduling lay between 22.9% and 132.4%.
Poland.
In the case of Poland, it can be observed that underscheduling characterized the DA and ID forecasts made for the onshore wind farms. It can be seen in
Figure A24 that a significant part of the dots are below the diagonal in the scatter plots of the joint distributions. The proportions of the downward and upward regulation needs per year for energy production are displayed in
Table A22:
The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling varied between 8.4% and 12.7%. Compared to the DA forecasts, the deployment of ID scheduling could achieve an improvement of only a few percentage points of the annual downward regulation need.
In the case of DA scheduling, the proportion of the upward regulation requirement to the annual energy generation ranged between 0.2% and 4.0%, which could be improved by the deployment of ID scheduling in the majority of the cases.
Portugal.
In the case of Portugal, both under- and overscheduling can be observed in the case of the DA and ID forecasts made for the onshore wind farms. However, it is also to be seen that most of the dots are located near the diagonal, which suggests a relatively high level of forecasting precision (
Figure A25). Taking the annual energy generation as a basis, the proportions of the downward and upward regulation developed as follows (
Table A23):
In the course of DA scheduling, the proportion of the downward regulation requirement to the annual energy generation ranged from 4.9% to 11.2%, which could be improved by a few percentage points by the deployment of ID scheduling.
In the case of DA scheduling, the proportion of the upward regulation need to the annual energy generation varied between 2.7% and 9.2%, which could be improved to some extent by using ID scheduling in the overwhelming majority of the cases.
Romania.
Both under- and overscheduling were characteristic of the DA and ID forecasts made for the onshore wind farms in Romania (
Figure A26), which is also verified by the proportions of the annual downward and upward regulation requirements for energy generation (
Table A24).
The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling varied between 6.3% and 23.6%. The deployment of ID scheduling decreased the forecasting accuracy to a slight degree in 2020, while it improved the precision in 2021.
The proportion of the upward regulation need to the annual energy generation in the case of DA scheduling lay between 5.1% and 26.6%, which could be improved by the use of ID scheduling, albeit only to a slight degree.
Sweden.
Similarly to the situation of scheduling in Germany, Spain, and France, Sweden also seems to possess one of the most accurate DA and ID forecasting mechanisms connected to onshore wind farms. It can be seen that, in the cases of both the DA and the ID forecasts, the clusters of dots are located near the diagonal, which indicates accurate forecasting (
Figure A27):
In the course of DA scheduling, the proportion of the downward regulation requirement to the annual energy generation ranged from 1.5% to 5.5%, which could be improved by a maximum of 3.5% by the deployment of ID scheduling.
In the case of DA scheduling, the proportion of the upward regulation requirement to the annual energy generation varied between 2.5% and 3.9%, which could be improved further by the deployment of ID scheduling in most of the cases (
Table A25).
Similar to the case of Germany, Spain, and France, there may be similar reasons behind Sweden’s accuracy in forecasting. On the one hand, this country also has a large amount of onshore wind farm capacity (10.0 GW in 2021), spread over a vast geographical area, and thus the wind farms compensate for one another’s inaccuracies to a certain degree. On the other hand, developments related to onshore wind farm power generation forecasting have been going on dynamically in recent years [
67,
68].
The United Kingdom.
In the case of the United Kingdom, the results indicate that overscheduling was characteristic of the DA and ID forecasts made for the onshore wind farms; a significant part of the dots are above the diagonal in the scatter plots of the joint distributions (
Figure A28). The proportions of the annual downward and upward regulation needs for energy production also verify this observation (
Table A26):
The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling varied between 0.3% and 9.2%. The use of ID scheduling resulted in a slight decrease of the forecasting accuracy compared to DA scheduling in all the cases.
Regarding scheduling, the volume of the upward regulation need was more significant than that of the downward regulation requirement, which may have been caused by the fact that those preparing the forecasts could not precisely calculate with the changeable weather conditions. In the case of DA scheduling, the proportion of the upward regulation requirement to the annual energy generation varied between 15.6% and 29.8%, which could be improved further by the deployment of ID scheduling by up to 18.8%.
Offshore wind farms.
Belgium.
Of the examined nations, Belgium was the country with the most detailed data available related to offshore wind farms. The results (
Figure A29) show that under- and overscheduling characterized both DA and ID forecasting in the case of offshore wind farms. The proportions of the annual downward and upward regulation needs for energy production also verify this observation (
Table A27):
In the case of DA scheduling, the proportion of the downward regulation need to the annual energy generation varied between 3.1% and 12.5%, which could be improved by some percentage points by using ID scheduling in the overwhelming majority of the cases.
Compared to the downward regulation need, the annual upward regulation requirement posed a greater challenge in terms of the management of scheduling in certain cases (e.g., 2020, 2021), which might have been caused by the fact that those preparing the forecasts were not in possession of the weather data related to meteorological situations which proved to be more changeable than expected during the scheduling period. In the case of DA scheduling, the proportion of the upward regulation requirement to the annual energy generation ranged from 9.3% to 30.4%, which could be improved by the deployment of ID scheduling.
Germany.
Similarly to Belgium, under- and overscheduling occurred in the case of the DA and ID forecasts made for the offshore wind farms in Germany too. However, it is also to be seen that most of the dots are located near the diagonal, which suggests a high level of forecasting precision (
Figure A30). Taking the annual energy generation as a basis, the proportions of the downward and upward regulation developed as follows (
Table A28):
In the course of DA scheduling, the proportion of the downward regulation requirement to the annual energy generation ranged from 6.7% to 33.3%, which could be improved by a few percentage points by the deployment of ID scheduling in the majority of the cases.
In the case of DA scheduling, the proportion of the upward regulation requirement to the annual energy generation varied between 7.4% and 9.5%, which could be improved further by the deployment of ID scheduling in most of the cases.
Denmark.
In the case of Denmark, it can be observed that both under- and overscheduling characterized the DA and ID forecasts made for the offshore wind farms (
Figure A31). The proportions of the annual downward and upward regulation requirements for energy production are shown in
Table A29:
Compared to the upward regulation need, the annual downward regulation requirement posed a greater challenge in terms of the management of scheduling in certain cases (e.g., 2015, 2021), which might have been caused by the fact that those preparing the forecasts were not in possession of the weather data related to meteorological situations which proved to be more changeable than expected during the scheduling period. The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling varied between 5.2% and 26.0%.
The proportion of the upward regulation need to the annual energy generation in the case of DA scheduling lay between 2.9% and 8.6%.
The Netherlands.
In the case of the Netherlands, it can be seen that underscheduling was characteristic of most of the DA and ID forecasts made for the offshore wind farms; the majority of the dots are below the diagonal in the scatter plots of the joint distributions (
Figure A32). Based on the proportions of the annual downward and upward regulation requirements for energy generation, the following observations can be made (
Table A30):
The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling varied between 12.9% and 61.7%. It was only in 2018 that some slight improvement could be achieved by the use of ID forecasting compared to DA forecasting. In the subsequent years, the DA and ID schedules were practically identical.
The proportion of the upward regulation need to the annual energy generation in the case of DA scheduling lay between 1.5% and 15.2%. Although the use of ID scheduling decreased the forecasting accuracy to some slight degree compared to DA scheduling in 2018, the DA and ID schedules were practically identical in the subsequent years.
Portugal.
Both under- and overscheduling were characteristic of the DA and ID forecasts made for the offshore wind farms in Portugal (
Figure A33), which is also verified by the proportions of the annual downward and upward regulation requirements for energy generation (
Table A31).
The proportion of the downward regulation need to the annual energy generation in the case of DA scheduling varied between 38.7% and 50.4%. The use of ID scheduling improved the forecasting accuracy compared to DA scheduling, in 2021 by even 13.3%.
The proportion of the upward regulation need to the annual energy generation in the case of DA scheduling lay between 18.8% and 35.4%. The application of ID scheduling made the accuracy worse compared to DA scheduling in 2020, while it resulted in some improvement in 2021.
The United Kingdom.
In the case of the United Kingdom, it can be seen that overscheduling was characteristic of a significant part of the DA and ID forecasts made for the offshore wind farms; the majority of the dots are above the diagonal in the scatter plots of the joint distributions (
Figure A34). Based on the proportions of the annual downward and upward regulation requirements for energy generation, the following observations can be made: