The assessment of environmental licenses in Sweden is performed on the basis of an integrated system of legal principles, rules and processes contained in the Environmental Code: from the principles of precaution and “polluter pays”, via substantive rules for environmental consideration, natural resource management and environmental quality standards, which are all interconnected in the EIA process, to a system of licensing, supervision and sanctions [
30] (pp. 168–170). Hence, according to this “principle” of an integrated approach to environmental law, all aspects of an activity (e.g., pollution, use of chemicals, processing, waste management, etc.) should be assessed in context: “The licensing process and supervisory practices should create incentives for the operator to be ahead of the legal requirements” [
30] (p. 169, authors’ translation). This means that, in the licensing process, the permit authority is obliged to assess the whole activity in relation to the environment, including direct, indirect and even cumulative effects, to some extent. These effects (or consequences) are primarily accounted for in an Environmental Impact Assessment (EIA), which must be prepared by the operator and accompany the permit application. This integrated regulatory approach may add to a lack of predictability concerning the scope of the EIA, and below (in
Section 3.2.1), we describe and comment on a court case in which this issue resulted in a lengthy and largely uncertain licensing process.
3.2.1. Environmental Consideration Rules
The main requirement imposed on operators of polluting activities is to be cautious,
i.e., to take the measures necessary to prevent, avoid or counteract the damage or nuisance to human health or the natural environment. The precautionary requirement, as it is expressed in Ch. 2, s. 3, of the Environmental Code [
27], covers all activities and measures that may impact human health and the environment. The second paragraph of this section clearly reflects the precautionary principle: “These precautions shall be taken as soon as there is reason to assume that an activity or action may result in damage or harm to human health or the environment.” The other requirements, including those connected to the possession or acquisition of necessary knowledge [
27] (s. 2), the conservation of raw materials or energy [
27] (s. 5) or the application of the principle of substitution [
27] (s. 4), can therefore be regarded as specifications of different areas where precaution can/must be taken. With support of both s. 3 and s. 5 of the Code, it can, for example, be required of an operator to change the energy or heating system if the suggested solution implies undue risks for the environment,
cf. [
32].
For professional activities [
33], it is furthermore mandatory to use the best possible technique [
27] (s. 3). Under Swedish law, the technique requirement refers to the best possible, rather than the best available, technique. The term includes the technology used and the ways in which a plant is constructed, designed, maintained, operated and decommissioned. To be regarded as “the best possible”, the technique should moreover be industrially possible to use in the relevant industry [
34] (p. 17). Consequently, the assessment of what constitutes the best possible technique includes two criteria: (1) it must be operational (technical solutions on the experimental stage do not count); and (2) the cost for using the technology must be reasonable, based on general industry conditions and not on individual circumstances [
30] (p. 232). This essentially corresponds to the BAT requirements of the IED:
IED, Article 3(10) [
16]: “best available technique” means the most effective and advanced stage in the development of activities and their methods of operation, which indicates the practical suitability of particular techniques for providing the basis for emission limit values and other permit conditions designed to prevent and, where that is not practicable, to reduce emissions and the impact on the environment as a whole:
“Techniques” includes both the technology used and the way in which the installation is designed, built, maintained, operated and decommissioned;
“Available techniques” means those developed on a scale that allows implementation in the relevant industrial sector, under economical and viable conditions, taking into consideration the costs and advantages, whether or not the techniques are used or produced inside the Member State in question, as long as they are reasonably accessible to the operator;
“Best” means most effective in achieving a high general level of protection of the environment as a whole [
16].
Furthermore, the environmental requirements are applicable “to the extent it cannot be considered unreasonable [for the operator] to meet them” (s. 7) [
27], implying that plant-specific issues and economic feasibility shall be taken into account in the assessment. The principle of “environmentally motivated” underpins this assessment of reasonableness: if the first step technique (A) has been objectively determined as “the best possible”, the second step will be taken to assess if the marginal (environmental) benefit of using that technology exceeds the marginal costs of introducing it from the operator’s point of view. Important to note here is that it is the state of the environment at the specific location that is crucial for any impairment of the requirements; if the area suffers from acidification, a trade-off where the initial requirement for a specific sulfur abatement technique is replaced is thus unlikely even if the costs for introducing the technology are considerable.
The issue of the scope of the integrated EIA in accordance with the Environmental Code came to the fore in the licensing process regarding the opening of a new iron ore mine in the North of Sweden. In May, 2010, a license to open a mine at Gruvberget in the municipality of Svappavaara was granted by the then Environmental Court (now the Land and Environmental Court) [
35]. The license admitted permission for mining and processing a certain amount of ore annually. This decision was however appealed by the Swedish Environmental Protection Agency (SEPA) on the grounds that the assessment should have included both the new and the existing activities in the area. According to SEPA, it is unclear what was included in the Court’s assessment and what is covered by the permit, for instance with regard to the disposal of waste rock at the existing landfill and of groundwater and surface water to the reservoir. SEPA therefore argued that: “it is clear that these issues have not been assessed in an appropriate manner and that there has been no comprehensive assessment of all of the licensed activities” [
36] (p. 2) and that it is impossible to a make an assessment of the overall environmental impacts of the new mining operation and regulate it in an appropriate manner if interconnected activities, like the pelletizing plant, are not included in the assessment.
The company had no objection to SEPA’s argument for a more comprehensive and integrated assessment, but did not consider this to be the main issue in the case. Instead, the company argued that it was not only possible, but also more suitable to regulate the different activities separately; it is common that a processing plant serves several mines, and “there has never been any doubt that these activities both can and should be regarded as independent units with respect to assessment and authorization” [
36] (p. 5).
The Environmental Court of Appeal began by noting that the main issue in the case is “whether the activity applied for is an independent activity that can be assessed and examined separately, as the company claims, or, if the existing plants have such links to the new activity that they should be regarded as one activity that should be considered jointly, as the Environmental Protection Agency alleges” [
36] (p. 8). Thereafter, the Court concluded that the aim of the Environmental Code is to enable a comprehensive and integrated assessment of activities that impact the environment, e.g., by introducing legally binding principles and environmental consideration rules applicable to all environmentally impacting activities and measures. The activities in the mining case were considered by the Court to be both geographically and technically connected. For example, water from the new pit would be led to an existing reservoir not covered by the permit; additional noise pollution and air emissions would cause cumulative effects not covered by the permit; and there was no permit for the landfill for the waste rock. Hence, the Environmental Court of Appeal decided to set aside the judgment of the Environmental Court and reject the previous permit application. The company was forced, therefore, to submit a new license application covering the entire operations, including the processing plant. Overall, this delayed the final decision on the permit by about four years.
This case suggests that there is uncertainty with regards to what shall be included in the application for license in accordance with the Environmental Code; even different regulatory authorities may come to different conclusions on this matter. Although, in this case, it was found that the geographical and technical links between the activities were such that they should be assessed and regulated in a context, the legal position is far from certain. The Environmental Court of Appeal only establishes that an application for license must be “complete”, i.e., appropriately delimited and covering all environmental impacts that may be caused by the activity. In specific cases, this provides little guidance in how to determine the scope of the EIA. With reference to the Porter hypothesis, the regulatory environment manifested in this case cannot be considered to fully adhere to the principles for a properly-designed environmental regulation; there are considerable uncertainties both with regard to what shall be included in the license application and what thus must be prepared for, as well as (partly as a result of this) regarding the time schedule for the licensing process.
3.2.2. Specific Rules for Industrial Emissions
Since June 18, 2013, the IED has been implemented in Swedish legislation, mainly through Ordinance (2013:250) on industrial emissions [
31]. Like the IPPC, IED is based on the notion that pollution from industrial activities is a transboundary issue that needs to be addressed at the EU level [
37] and aims to “ensure a high level of environmental protection and the improvement of environmental quality,” [
16] (Recital 44): “In order to prevent, reduce and as far as possible eliminate pollution arising from industrial activities in compliance with the “polluter pays” principle and the principle of pollution prevention”, it has been considered necessary to establish a legal framework for the control of the main industrial activities [
16] (Recital 2). The main features of the legal framework are the licensing process and the substantive requirements in this respect, most notably the more prominent role given to the concept of BAT, where the BAT conclusions will play a more obligating role in the licensing process compared to the IPPC Directive [
38].
Like its predecessor, the IPPC, the IED prescribes an obligation for operators of polluting industries to hold a permit and lays down the grounds for the granting of a permit, as well as permit conditions. A permit is required for new, as well as for substantial changes in existing activity [
16] (Articles 4(1), 5(1–3) and 14(1)). Substantively, the Member States are required to take the necessary measures to see to it that all appropriate preventive measures against industrial pollution are taken, including that best available techniques are applied, that energy is used efficiently and that no significant pollution is caused [
16] (Art. 11). The permit shall include emission limit values for polluting substances, based on BAT conclusions, which are the main reference for setting permit conditions, as well as suitable emission monitoring requirements (e.g., [
16] Recital 13). Since the IED is a mini directive, Member States are allowed to set stricter conditions than those described in the BAT conclusions, provided that such measures are compatible with the Treaties and the Commission has been notified [
16] (Art. 14), [
39].
Another basic element of the IED is the requirement to regularly reconsider, and update, permit conditions, so that they truly reflect BAT, taking into account technological development and progression [
16] (Art. 19, Recital 21). Within four years of the publication of the BAT conclusions, all permit conditions for installations concerned must be reconsidered and updated to be in compliance with the directive [
16] (Art. 21). This thus provides an opportunity to impose regulations that gives industrial plants incentives to continuously improve their environmental performance; in
Section 4, we comment on this opportunity in more detail and highlight the difficulties in imposing such gradually more stringent requirements without creating additional uncertainties and excessive costs. How frequent new BAT reference documents are to be produced is not regulated by the directive; the Commission shall, according to Recital 13 [
16], strive to update the documents within eight years after they have been published. However, the directive also recognizes the importance of flexibility and allows, under certain circumstances, emission limit values that deviate from BAT. Accordingly, the license authority may set emission limits that differ from those associated with BAT “in terms of the values, periods of time and reference conditions applied” if it can be shown, through monitoring that the emissions do not exceed the levels associated with the best available techniques [
16] (Recital 15). It is, in other words, possible to set emission limit values based on other values than the BAT conclusions, for example with respect to other time periods. The use of such an alternative value may, however, not lead to increased emission levels, under normal operating conditions, than would have been the case if the BAT conclusions had been used as a reference.
The criteria for best possible technique, including BAT reference documents (BREFs) and BAT conclusions, are frequently applied by licensing authorities like the Land and Environmental Courts and assessed by the Land and Environmental Court of Appeal in guiding cases. BREFs describe applied techniques, present emissions and consumption levels, as well as techniques considered for the determination of BAT, emerging techniques and BAT conclusions for certain defined activities. BAT conclusions are the parts of the BREF documents that lay down what is considered the best available technique, including its applicability, associated emission limit values and monitoring aspects [
40].
There appears to be a general consensus, both within industry and among authorities, that BAT requirements and BREFs are indicated in the licensing process for polluting industries, and were so already before the implementation of the allegedly stricter IED. The licensing authorities also seem to be in agreement that the general consideration rules in the Environmental Code, most notably s. 3 [
27], are applicable in this process and may imply stricter requirements than what follows from EU law.
However, in recent court cases, not the least of which is from the Land and Environmental Court of Appeal, the assessment of what the best technique is seems to be primarily based on EU legislation. The possibility to impose stricter regulation was not used in any of the examined cases [
41]. In a judgment from 2014 [
42], concerning the conditions for air emissions of sulfur from an oil refinery, the Swedish Environmental Protection Agency (SEPA) appealed a partial judgment from the Land and Environmental Court at Nacka District Court because of (too) low emission limit values for the sulfur recovery plant. The case involved an application for license in accordance with the Environmental Code for extended and changed activity; the judgment from the Land and Environmental Court [
43] was a partial (second) assessment concerning the trial period for air emissions of sulfur and volatile organic compounds (VOC). Regarding the VOC emissions, the Court terminated the trial period and decided on additional conditions for the activity, for example that annual measurements to quantify the emissions of VOC from the refinery shall form the basis for assessing improvement needs and that vacuum valves shall be installed on all crude oil tanks. For the sulfur emissions, the Court concluded that, in accordance with the IED, the licensing authority shall set emission limit values that ensure that emissions under normal operating conditions do not exceed the emission levels associated with BAT according to the BAT conclusions. The Court found no support in the investigation that indicated that the future BAT conclusions also would include extraordinary events, like malfunctions and poorer accessibility. Hence, the company’s proposal for the limit value for the recycling rate, where the lowest recycling rate includes typical deviations from normal operating conditions, were found acceptable, and the Court determined that the recycling rate, based on the input of sulfur to the recovery plant and the output of sulfur to the tail gas facility would amount to 98.5%, calculated as a monthly average. The condition is considered fulfilled if the limit value is met for at least ten months in a year.
In the appeal, SEPA argued that according to the current BREF document, BAT for the recycling rate for sulfur recovery plants ranges between 99.5% and 99.9% and that the eight best facilities have a performance of 99.8% or more, including accessibility. In relation to the IED, SEPA pointed out that, since the IED is a minimum directive, Member States have the opportunity to invoke stricter rules and that no amendments in the general consideration rules thus will be made as a result of the Directive. Furthermore, to catch operational malfunction and similar incidents, the Swedish licensing system relies on: (1) probation for the permit; and (2) flexibility in the permit conditions, e.g., by letting the condition apply for a longer period of time. With regard to this, SEPA argued that, since the condition set by the Court did not encompass the sour gas that is flared in the case of operational malfunction, a recovery rate of 98.5% is too low, not the least of which is in consideration of the fact that the condition is deemed fulfilled if the limit values are met in ten out of twelve months. In conclusion, SEPA did not consider that the condition reflected the “best available technology” according to the Swedish rules and suggested an increase in the recycling rate to 99.1% or 99.2%. The company objected to this, arguing that: “EPA’s opinion and references to the BAT conclusions go beyond what the legislature intended and what is environmentally justified and reasonable to require” [
42] (p. 5). SEPA’s requirement was considered unreasonable since: (1) the current levels were in keeping with BAT; and (2) it would require large investments that could not be considered environmentally motivated.
The Environmental Court of Appeal found that the sulfur recovery plant indeed fulfilled the requirements under current BREF documents and that there were no compelling EU legal requirements to tighten the current conditions. However, the Court recognized that the rules of the Environmental Code may imply more stringent requirements with regard to the establishment of best possible technique and that an assessment pertaining to this therefore was necessary. To obtain updated information about different technical solutions, the draft for new BREF’s for refineries [
44] was considered in this assessment. In assessing the level of requirements that could apply, the Court noted that the company had agreed to SEPA’s claim that the condition should relate to efficiency rather than recycling rate. Since the calculations therefore include also emissions from the sour gas flaring, the condition will comprise also abnormal operating conditions. Moreover, since even a short period of disruption in the operation of the sulfur recovery plant may temporarily greatly impair the efficiency and also result in an increase of sulfur emissions, the court found that very strict requirements on the efficiency could be justified. However, based on the fact that the total emissions of sulfur from the plant also were limited by another condition, according to which the total emissions of sulfur may not exceed 250 tons per year, and which would also govern the emissions from the recycling plant, the Court decided that the emission limitation value suggested by the company and established by the licensing authority was in fact BAT and, hence, sufficient.
On the one hand, the outcome of this case indicates that the environmental regulations at least partially satisfy Porter’s criteria; the application of the regulatory framework leaves room for the company to make decisions in terms of compliance measures and technology selection. On the other hand, there still remains uncertainty both in terms of what can be considered as part of the BAT conclusions and the possibilities to impose stricter requirements as a result of the general rules of consideration in the Environmental Code. The Court’s decision in the oil refinery case gives no clear guidance in these respects; on both issues, the Court merely concludes that, in practice, the emission ceiling in the overall conditions will imply sufficiently stringent demands on both the recovery rate and the availability for the sulfur recovery plant.
The issue of BAT requirements and BREF documents
versus the Environmental Code’s best possible technology was also subject to assessment in another judgment from 2014 [
45]. The case concerned an application for a permit to increase the production of bleached kraft pulp by around 18% and cardboard production by around 14 percent. The increased production would lead to increased emissions to the air of, e.g., sulfur, due a transition from fossil fuels to heating with pitch oil. The Land and Environmental Court approved the company’s environmental impact assessment and found that the activity also otherwise met the substantive requirements of the Environmental Code and that a license in principle thus could be granted. The main issue in the case was therefore on which conditions the activity should be permitted. Here, two of the referral bodies, SEPA and the County Administrative Board (CAB), were of a different opinion than the company and suggested prolonged probation and a stricter formulation of some of the proposed conditions. Regarding dust emissions to air from the biomass boiler and the lime kiln, the Court considered the levels claimed by the company to be on the high side in relation to the best possible technique and decided to support the (stricter) requirements suggested by SEPA and CAB.
The company appealed the judgment regarding the condition of the dust content in flue gases from the biomass boiler and argued that, although the Court’s stance is seemingly clear, there are significant uncertainties behind its reasoning. The contested condition was expressed as follows: the dust content in the flue gases from biomass boiler P12 may not exceed 50 mg/m
3 at six percent O
2, calculated as annual mean and limit values. The company called for an increase of the value to 75 mg/m
3 at 6% O
2 [
46] on the basis that all emission levels values are in line with the specified BREF document and that the contested condition is significantly lower than what has been imposed for comparable units at other mills in recent times. According to the company, it would not be possible to uphold the permitted production if the suggested condition remains; new investments would be necessary. The CAB acknowledged that the company may have to complete the current abatement system to meet the suggested condition, but did not consider this to be unreasonable or out of the ordinary in consideration of the production increase. In fact, the CAB even suggested a tightening of the contested condition. SEPA stated that the suggested emission level should be regarded as BAT, based on, among other things, the records of the company’s previous emissions.
The Land and Environmental Court of Appeal stated that the company in 2013 completed a renovation of the biomass boiler resulting in lower dust emissions, implying that the proposed condition could be upheld. According to the Court, the argument that the dust emissions increase rapidly at a specific flue gas flow was not considered to motivate imposing a lower emission value, although it may be justified to allow for some margin to avoid that temporary overloads lead to exceeding of the condition. The suggested emission limit value was therefore considered sufficient in this respect, and the Land and Environmental Court of Appeal rejected the appeals.
Furthermore, in this case, BAT was primarily determined on the basis of the BREF documents for the particular activity, but with a much clearer assessment based on the substantive rules of the Environmental Code. In conformity with the Land and Environmental Court, the Superior Court balances the environmental requirements with what can be considered environmentally motivated in each individual case and arrives at a solution based on both what is technically possible and economically feasible. Emphasis is also put on the possibilities for the company to affect the emissions by the choice of fuel type, and the renovating of the biomass boiler is taken into account.
Pursuant to the IPPC/IED system, it is furthermore possible to deviate from the BAT conclusions if the application of these levels would lead to disproportionately high costs compared to the environmental benefits, as a result of the installation’s geographical location or environmental or technical conditions [
16] (Art. 15(4), Recital 16). Furthermore, those deviations may only be granted on the condition that no significant pollution is caused and that a high level of environmental protection is still achieved.
The meaning of the IED on the issue of the exceptions for “abnormal conditions” was subject to assessment by the licensing authority in a case related to conditions for dust emissions at a cement plant [
47]. Based on the new directive, the Land and Environmental Court considered it necessary to change the suggested conditions. The main issue was the interpretation of the exception for “abnormal operating conditions”. The suggested condition for dust emissions from the cement kilns included an exception for abnormal operation that was feared to counteract the purpose of the exception as it is expressed in the directive; the formulation of the condition was considered too imprecise and to lead to a situation where every emission deviation is seen as an example of abnormal conditions. The Land and Environmental Court thus reformulated the condition to the effect that also emissions from coolant gas were included. The company appealed the judgment to the Land and Environmental Court of Appeal [
48], arguing that emissions from a separate filter for the purification of coolant gases are not possible to calculate according to the current formulation of the condition where the dust emissions are normalized at an oxygen level of ten percent. The Court began by noting that, since the entry into force of the Ordinance on industrial emissions, the licensing authority shall use emission limit values and other precautions listed for the activity in relevant BREF documents as a basis for its assessment. Thereafter, the Land and Environmental Court of Appeal concluded that it is not technically possible for the company to comply with the condition as it has been formulated by the Land and Environmental Court and arrived at the conclusion that the emissions of coolant gases should not be regulated as prescribed by the condition. The condition was changed in the way suggested by the company. Additional adjustments on account of the existing BREFs were not considered necessary.
The Swedish implementation of the IPPC model in general and the requirement for the best available technology in particular certainly seem to be comprehensive; the licensing authorities comply with both the BAT conclusions from the BREF documents and leave the door open for stricter requirements in accordance with national law, if that should be considered necessary. In specific cases, the Swedish courts have chosen to lean heavily on the BREF documents in determining BAT, and there are thus few (if any) attempts to go beyond these requirements.
3.2.3. Legal Bases for Land Use
The licensing process does however include more assessment criteria than pollution prevention via individual performance standards. A very important part of the Swedish licensing process involves the siting and access to land and water areas. Here, the starting point for the assessment is that “priority shall be given to use that promotes good management from the point of view of public interests” [
27] (Ch. 3, s. 1). The basic resource management provisions thus provide guidance for conflicts of interests regarding the use of land. The rules also include specific land uses that are of particular interest (from a public perspective) and which therefore are subject to some degree of “protection”, where activities that could significantly damage or significantly hamper the intended land use can be hindered. Land and water areas that contain valuable substances or materials should, for example, “as far as possible” be protected against activities that can “significantly hamper” the extraction of these substances or materials [
27] (Ch. 3, s. 7). If the area is considered of national interest for some purpose, it “shall” be protected. When conflicts over land use arise, for example if an area is of national interest for more than one purpose, the guiding principle is that priority shall be given to the purpose that best promotes sustainable development [
27] (Ch. 3, s. 10).
Overall, the rules are very generally formulated and the discretionary space extensive. With reference to the principles for properly-designed environmental regulation [
7], the implication of this for the efficiency of the licensing process is potentially significant. While the rules on BAT and the BREF documents provide relatively clear indications regarding what can be expected, for example in terms of emission limits and, thus, conditions for permitting, the assessment under these rules can be performed on widely divergent inducements, leading to increased uncertainty regarding both the outcome of the licensing process and its duration; e.g., [
26], [
49] (p. 49), [
50] (pp. 45–46), [
51] (pp. 224–225). The ambiguity of the provisions also risks counteracting the sustainability objective. The guidance in terms of how to manage conflicting interests, especially regarding conflicting national interests, is scant, and the rules are formulated to steer away from, rather than to promote, the designated interests. As a result, the rules’ governing function as a tool for sustainable development is almost negligible.
The general rules on land use as described above constitute the national spatial planning in Sweden. In addition to an assessment in accordance with these rules, the licensing process also includes assessments and decisions according to local-level spatial planning. Here, the system is characterized by a municipal planning monopoly under which the municipalities have the responsibility to, within the framework of the Planning and Building Act, decide if and when to plan for certain activities and on what basis. The County Administrative Board has some influence over the planning process through its position as the state representative for national interests, although to a limited extent; the Board cannot, for example, initiate, enforce or take over the planning. Industrial activities typically require preparation and adoption of zoning plans (e.g., for certain buildings and facilities), assignment of land for the purpose (e.g., for mining operations), as well as building permits. This, in turn, should conform to the comprehensive plan for the area, which is also established by the municipality.
Although the licensing in accordance with the Environmental Code is largely separated from the permitting process under the Planning and Building Act, the planning system thus has a considerable impact on the licensing process as a whole; without municipal consent, it is virtually impossible to commence activities. In accordance with this, the licensing authority also typically places great importance on both the activity’s conformity with the spatial planning and on the opinion of the municipality,
cf. [
49] (p. 64). For certain types of facilities, amongst other larger polluting industries, the municipality also has the right of veto, making their opinion
de facto decisive.
Even though the planning process is largely detached from the environmental licensing process, an evaluation of the licensing process as a whole in relation to Porter’s concept of properly-designed environmental regulations must include all necessary permits and associated processes. In relation to the legal system for land use and spatial planning, the system may be viewed as holding certain flexibility, but at the same time, the current procedure probably represents a significant institutional barrier to a licensing process that is characterized by predictability. The substantial municipal influence and scope for discretion, together with a serious lack of comprehensive control over the planning process, leaves considerable room for uncertainty with respect to, primarily, the duration of the licensing process as a whole.