Risk Factors That Lead to Time and Cost Overruns of Building Projects in Saudi Arabia
Abstract
:1. Introduction
- To explore and identify the influential risk factors leading to duration and cost overrun during the construction stage, with special consideration for building projects in Saudi Arabia (i.e., risk factors list and classification) through the completion of a comprehensive literature review.
- To study, rank, and analyse the identified risk factors (i.e., ‘risk impact × likelihood’) by conducting questionnaires.
2. Literature Review
2.1. Overview of Construction Industry
2.2. Saudi Arabian Construction Industry
2.3. Risk Factors Leading to Cost and Time Overruns
3. Research Methodology
3.1. Ranking of Risks
- RII—is the Relative Importance Index;
- Wi—is the weight given to each factor by the respondents from 1, 2, 3, 4, and 5 for very low, low, moderate, high, and very high, respectively;
- A—is the highest weight (i.e., 5 in five-point Likert scale);
- N—is the total number of respondents for every variable.
- RI—is the Risk Importance to determine the level of importance of each identified risk;
- P—is the probability of risk occurrence;
- I—is the impact of risk on time or cost.
3.2. Reliability of Factor Analysis
- Cα—is Cronbach’s alpha;
- K—is many items;
- —is the variance of test score;
- —is the variance of item scores after weighing.
3.3. Agreement Analysis
- —is Spearman’s rank correlation coefficient between two parties;
- —is the difference between ranks assigned to each risk;
- —is the number of pairs of rank.
4. Results and Discussion
4.1. Participants’ Demographics
4.2. Delay and Cost Overrun in Construction Projects
4.3. Ranking of Risks
4.3.1. Reliability of Factor Analysis
4.3.2. Agreement Analysis
5. Conclusions
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Acknowledgments
Conflicts of Interest
Appendix A
Studies | Methodologies | Country | No. of Factors Identified | Major Risk Factors | Impact on Construction Projects |
---|---|---|---|---|---|
Memon et al. (2012) [61] | Interviews and surveys | Malaysia | 35 | Design and documentation issues, financial resource management, project management and contract administration, contractors site management, information and communication technology, material and machinery resource, labour (human) resource, external factors | Time and cost overrun |
Aljohani et al. (2017) [52] | Literature Review | Multiple countries | 173 | Increase in material cost, inaccurate material estimates, shortage of skilled labour, client’s late contract award, project complexity, increase in labour costs, bidding differences, shortage manpower, design issues, poor planning and implementation, lack of talent resources | Cost overrun |
Allahaim and Liu (2015) [14] | Literature Review and Surveys | Saudi Arabia | 41 | Market conditions, unrealistic estimations, decision-making errors, payment issues, project size, lack of talent resources, poor planning and implementation, waste on site, currency fluctuations, lack of technology and material resources, changes in design and scope, political obstacles, poor strategies | Cost overrun |
Creedy et al. (2010) [57] | Case studies | Australia | 37 | Design issues, political issues, requirements changes, cultural issues, material costs increase, contract failures, administration issues, location changes, inflation | Time, cost, quality, performance |
Jackson (2002) [58] | Interviews | UK | 341 | Design changes, project management, site conditions, commercial pressures, lack of talent resources, external factors, estimation methods, information availability | Time, cost, quality, performance, planning, project management |
Baloyi and Bekker (2011) [55] | Literature Review and Surveys | South Africa | 18 | Increase in material cost, inaccurate material estimates, shortage of skilled labour, client’s late contract award, project complexity, increase in labour costs, bidding differences, shortage manpower, design issues, poor planning and implementation, labour issues, poor information availability, delay in approvals | Time, cost, quality, performance, planning, project management |
Subramani et al. (2014) [63] | Case studies and Literature Review | India | 10 | Slow decision making, poor schedule management, increase in material/machine prices, poor contract management, poor design/ delay in providing design, rework due to wrong work, problems in land acquisition, wrong estimation/ estimation method, and long period between design and time of bidding/tendering | Cost overrun |
Memon et al. (2011) [2] | Case studies and Survey | Malaysia | 30 | Practice of assigning contract to lowest bidder, contractor’s poor site management, cash flow and financial difficulties faced by contractors, ineffective planning and scheduling by contractors, problems with subcontractors, inadequate contractor experience, material procurement, poor estimate project duration, incompetent designers, shortage of site workers, lack of communication among parties, unforeseen ground condition, changes in scope of projects, low speed of decision making, frequent changes by owners, escalation of material prices, owner interference, change in management | Time overrun |
Mahamid et al. (2015) [60] | Survey and Literature Review | Saudi Arabia | 31 | Bid awarded for lowest price, changes in material types and specifications during construction, contract management, duration of contract period, fluctuation of prices of materials, frequent changes in design, improper planning, inflationary pressure, lack of adequate manpower, long period between design and time of implementation, payments delay, poor labour productivity and rework | Time overrun |
Mahamid (2017) [44] | Case studies and survey | Saudi Arabia | 34 | Improper planning, poor labour productivity, additional works, rework, and lack of contractor experience, disputes, arbitration, litigation, and poor quality | Time overrun, Performance |
Tebeje Zewdu and Teka Aregaw (2015) [64] | Survey and Literature Review | Ethiopia | 41 | Poor planning, fluctuation of price of materials, poor productivity, inflationary pressure and project financing, economic instability, lack of talented labour | Cost overrun, Performance |
Sharma and Goyal (2019) [62] | Literature Review and Expert opinion | India | 55 | Fluctuation in price of materials, lowest bid procurement policy, inflation inappropriate govt. Policy, mistakes and discrepancies in the contract document, inaccurate time and cost estimate, additional work, frequent design change, unrealistic contract duration and financial difficulty faced by contractors | Cost overrun, Performance |
Cirovic and Sudjic (2012) [56] | Literature Review and Case studies | Montenegro | 16 | Local market issues, Montenegrin legislation, local infrastructure, poor resources management, delay in approvals, lack of planning, lack of labour | Cost and duration overrun |
Bahamid et al. (2019) [54] | Literature Review | Multiple countries | 111 | Inflation/price fluctuation, technology issues, incomplete design scope, changes, labour equipment, delays in approvals, financial issues, poor estimations, poor designs, political instability, criminal acts, poor communication, poor planning and control | Time, cost, quality, performance, planning, project management |
Liu et al. (2016) [59] | Survey and Literature Review | China | 20 | Host government–related risk, contractor’s lack of experience, and lack of managerial skills had significant effect on project cost, quality, and schedule objectives, resource price fluctuation | Time, cost, quality, performance, planning, project management |
Iqbal et al. (2015) [4] | Survey | Pakistan | 24 | Financial issues for projects, accidents on site and defective design, subcontractors, labour, machinery, availability of materials and quality, issues related to design documents, changes in codes and regulations, political instability, and scope of work | Time, cost, quality, performance, planning |
Zhao et al. (2016) [65] | Survey | Singapore | 28 | Inaccurate cost estimation, cost overrun, poor planning, external factors | Time, cost, quality |
Appendix B
No | Code | Risk Factors | Probability | Impact on Time | Impact on Cost | Risk Importance (RI) | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Project Delay | Cost Overrun | Overall RI | ||||||||||||
RII | Rank | RII | Rank | RII | Rank | RI | Rank | RI | Rank | RI | Rank | |||
Clients-Related Risks | ||||||||||||||
1 | G1R1 | Client’s lack of experience about construction project. | 0.665 | 33 | 0.724 | 40 | 0.713 | 25 | 0.482 | 35 | 0.474 | 25 | 0.482 | 39 |
2 | G1R2 | Excessive bureaucracy in owner’s administration | 0.735 | 11 | 0.742 | 33 | 0.665 | 44 | 0.545 | 18 | 0.489 | 19 | 0.545 | 18 |
3 | G1R3 | Client’s financial difficulties | 0.665 | 33 | 0.818 | 8 | 0.720 | 19 | 0.544 | 19 | 0.479 | 22 | 0.544 | 19 |
4 | G1R4 | Owner’s delay in making progress payments for completed works (payment delays) | 0.767 | 3 | 0.876 | 1 | 0.684 | 37 | 0.672 | 2 | 0.525 | 12 | 0.672 | 2 |
5 | G1R5 | Selecting consultant, or designer, based on the lowest price | 0.760 | 4 | 0.756 | 29 | 0.742 | 11 | 0.575 | 14 | 0.564 | 4 | 0.575 | 14 |
6 | G1R6 | Contract awarded to the lowest bidder | 0.818 | 1 | 0.771 | 24 | 0.735 | 13 | 0.631 | 3 | 0.601 | 2 | 0.631 | 3 |
7 | G1R7 | Unrealistic/Inadequate original contract duration (tight schedule) | 0.702 | 19 | 0.822 | 5 | 0.720 | 19 | 0.577 | 13 | 0.505 | 16 | 0.577 | 13 |
8 | G1R8 | Political pressure to complete the project and speed up construction processes | 0.549 | 71 | 0.644 | 70 | 0.753 | 9 | 0.353 | 68 | 0.413 | 49 | 0.413 | 58 |
9 | G1R9 | Delay in land acquisition/Handover to the contractor | 0.571 | 65 | 0.684 | 55 | 0.524 | 77 | 0.390 | 61 | 0.299 | 76 | 0.390 | 64 |
10 | G1R10 | Difficulties in obtaining work permits from the authorities | 0.640 | 44 | 0.760 | 27 | 0.589 | 69 | 0.486 | 31 | 0.377 | 55 | 0.486 | 35 |
11 | G1R11 | Change orders during construction | 0.756 | 5 | 0.829 | 3 | 0.822 | 1 | 0.627 | 4 | 0.622 | 1 | 0.627 | 4 |
12 | G1R12 | Scope of work reduction by owner during execution phase | 0.535 | 72 | 0.545 | 79 | 0.575 | 74 | 0.292 | 80 | 0.307 | 75 | 0.307 | 78 |
13 | G1R13 | Delay penalty clause in the Saudi Public Works Contract is inefficient | 0.582 | 60 | 0.680 | 57 | 0.596 | 65 | 0.396 | 58 | 0.347 | 62 | 0.396 | 61 |
14 | G1R14 | Inaccurate estimation of construction cost by owner | 0.684 | 24 | 0.669 | 63 | 0.771 | 3 | 0.457 | 43 | 0.527 | 10 | 0.527 | 27 |
15 | G1R15 | Project suspension by owner | 0.556 | 68 | 0.789 | 17 | 0.684 | 37 | 0.439 | 46 | 0.380 | 53 | 0.439 | 47 |
16 | G1R16 | Delays due to dispute resolution | 0.673 | 31 | 0.789 | 17 | 0.698 | 31 | 0.531 | 24 | 0.470 | 28 | 0.531 | 24 |
Designer-Related Risks | ||||||||||||||
17 | G2R1 | Unclear and inadequate drawings, specifications, bills of quantities (BOQ) | 0.724 | 13 | 0.804 | 12 | 0.767 | 4 | 0.582 | 11 | 0.555 | 5 | 0.582 | 11 |
18 | G2R2 | Discrepancies between project documents (contract, BOQ, specifications, and drawings) | 0.647 | 41 | 0.749 | 31 | 0.738 | 12 | 0.485 | 32 | 0.478 | 23 | 0.485 | 36 |
19 | G2R3 | Mistakes and deficiencies in design documents | 0.651 | 40 | 0.742 | 33 | 0.727 | 18 | 0.483 | 34 | 0.473 | 26 | 0.483 | 38 |
20 | G2R4 | Inaccurately estimated quantities (BOQ) | 0.680 | 26 | 0.695 | 51 | 0.764 | 5 | 0.472 | 40 | 0.519 | 13 | 0.519 | 28 |
21 | G2R5 | All existing underground utilities information not available on the design documents (e.g., live cables and pipelines) for the contractor | 0.687 | 23 | 0.782 | 21 | 0.705 | 28 | 0.537 | 20 | 0.485 | 20 | 0.537 | 20 |
22 | G2R6 | Inadequate geotechnical investigations report about ground conditions of the project site (if available) | 0.647 | 41 | 0.731 | 39 | 0.778 | 2 | 0.473 | 39 | 0.504 | 17 | 0.504 | 32 |
23 | G2R7 | Complexity of design | 0.495 | 79 | 0.665 | 64 | 0.665 | 44 | 0.329 | 74 | 0.329 | 68 | 0.329 | 74 |
24 | G2R8 | Absence of contractor’s involvement in the design stage | 0.615 | 49 | 0.509 | 82 | 0.524 | 77 | 0.313 | 76 | 0.322 | 70 | 0.322 | 76 |
25 | G2R9 | Speeding up of design phase’s schedule | 0.676 | 28 | 0.665 | 64 | 0.691 | 34 | 0.450 | 45 | 0.467 | 30 | 0.467 | 43 |
26 | G2R10 | Limited budget for design | 0.647 | 41 | 0.662 | 66 | 0.676 | 42 | 0.428 | 50 | 0.438 | 38 | 0.438 | 48 |
Consultant-Related Risks | ||||||||||||||
27 | G3R1 | Lack of experience and competence of consultant’s staff. | 0.691 | 22 | 0.764 | 26 | 0.680 | 39 | 0.528 | 26 | 0.470 | 27 | 0.528 | 26 |
28 | G3R2 | Slowness in decision making for approval (shop drawings, submittals, sample materials, change orders, etc.) | 0.716 | 17 | 0.793 | 14 | 0.655 | 46 | 0.568 | 15 | 0.469 | 29 | 0.568 | 15 |
29 | G3R3 | Consultant’s rejection of submittals (shop drawings, equipment, and material samples) | 0.596 | 52 | 0.720 | 43 | 0.607 | 60 | 0.429 | 49 | 0.362 | 57 | 0.429 | 53 |
30 | G3R4 | Consultant’s delay in performing inspection and testing, and giving instructions | 0.567 | 66 | 0.695 | 51 | 0.571 | 75 | 0.394 | 59 | 0.324 | 69 | 0.394 | 62 |
31 | G3R5 | Poor coordination and communication between consultant and other parties | 0.636 | 46 | 0.753 | 30 | 0.615 | 59 | 0.479 | 37 | 0.391 | 51 | 0.479 | 41 |
32 | G3R6 | Poor quality control and assurance | 0.662 | 37 | 0.684 | 55 | 0.687 | 35 | 0.452 | 44 | 0.455 | 32 | 0.455 | 46 |
33 | G3R7 | Consultant’s corruption | 0.585 | 58 | 0.724 | 40 | 0.720 | 19 | 0.424 | 52 | 0.422 | 46 | 0.424 | 55 |
34 | G3R8 | Inflexibility (rigidity) of consultant | 0.575 | 64 | 0.676 | 59 | 0.560 | 76 | 0.389 | 63 | 0.322 | 71 | 0.389 | 65 |
35 | G3R9 | Excessive safety consideration | 0.447 | 81 | 0.505 | 83 | 0.491 | 83 | 0.226 | 83 | 0.220 | 83 | 0.226 | 83 |
36 | G3R10 | Internal company problems (at consultant company’s head office) | 0.535 | 72 | 0.604 | 77 | 0.509 | 80 | 0.323 | 75 | 0.272 | 80 | 0.323 | 75 |
Contractor-Related Risks | ||||||||||||||
37 | G4R1 | Inadequate contractor experience (lack of experience, and managerial skills) | 0.724 | 13 | 0.822 | 6 | 0.731 | 15 | 0.595 | 8 | 0.529 | 8 | 0.595 | 8 |
38 | G4R2 | Contractor’s financial difficulties (ineffective cash flow management) | 0.789 | 2 | 0.876 | 1 | 0.756 | 7 | 0.692 | 1 | 0.597 | 3 | 0.692 | 1 |
39 | G4R3 | Contractor’s poor site management and supervision | 0.731 | 12 | 0.822 | 6 | 0.720 | 19 | 0.601 | 7 | 0.526 | 11 | 0.601 | 7 |
40 | G4R4 | Ineffective planning and scheduling of project by contractor | 0.756 | 5 | 0.829 | 3 | 0.698 | 31 | 0.627 | 4 | 0.528 | 9 | 0.627 | 4 |
41 | G4R5 | Ineffective control of the project progress | 0.676 | 28 | 0.782 | 21 | 0.676 | 42 | 0.529 | 25 | 0.457 | 31 | 0.529 | 25 |
42 | G4R6 | Delays in sub-contractors’ work or caused by suppliers | 0.745 | 9 | 0.789 | 17 | 0.636 | 51 | 0.588 | 9 | 0.474 | 24 | 0.588 | 9 |
43 | G4R7 | Delay in preparation of shop drawings and material samples | 0.709 | 18 | 0.782 | 21 | 0.604 | 62 | 0.554 | 16 | 0.428 | 45 | 0.554 | 16 |
44 | G4R8 | Delay in site mobilization. | 0.662 | 37 | 0.698 | 49 | 0.524 | 77 | 0.462 | 41 | 0.347 | 63 | 0.462 | 44 |
45 | G4R9 | Rework and wastage on site, due to errors or quality of work (poor quality of workmanship) | 0.665 | 33 | 0.749 | 31 | 0.680 | 39 | 0.498 | 30 | 0.453 | 34 | 0.498 | 34 |
46 | G4R10 | Variations in quantities | 0.684 | 24 | 0.629 | 73 | 0.731 | 15 | 0.430 | 47 | 0.500 | 18 | 0.500 | 33 |
47 | G4R11 | Cost of penalties | 0.589 | 53 | 0.582 | 78 | 0.622 | 54 | 0.343 | 71 | 0.366 | 56 | 0.366 | 69 |
48 | G4R12 | The contractor does not carry out a field visit to the site during the bidding process | 0.655 | 39 | 0.724 | 40 | 0.695 | 33 | 0.474 | 38 | 0.455 | 33 | 0.474 | 42 |
49 | G4R13 | New existing underground utilities not mentioned on the design documents (e.g., live cables and pipelines) | 0.676 | 28 | 0.793 | 14 | 0.756 | 7 | 0.536 | 21 | 0.512 | 15 | 0.536 | 21 |
50 | G4R14 | Health and Safety requirements (in light of COVID-19) | 0.589 | 53 | 0.629 | 73 | 0.585 | 70 | 0.371 | 66 | 0.345 | 64 | 0.371 | 68 |
51 | G4R15 | Accidents on site | 0.524 | 74 | 0.524 | 81 | 0.509 | 80 | 0.274 | 81 | 0.267 | 81 | 0.274 | 81 |
52 | G4R16 | Conflict between contractor and consultant | 0.702 | 19 | 0.735 | 37 | 0.622 | 54 | 0.516 | 28 | 0.436 | 40 | 0.516 | 30 |
53 | G4R17 | Tender-winning prices are unrealistically low (suicide tendering) | 0.640 | 44 | 0.804 | 12 | 0.749 | 10 | 0.514 | 29 | 0.479 | 21 | 0.514 | 31 |
54 | G4R18 | Unavailability of incentives for contractor for finishing ahead of schedule or to reduce the cost | 0.720 | 15 | 0.673 | 61 | 0.625 | 52 | 0.484 | 33 | 0.450 | 35 | 0.484 | 37 |
Labour-Related Risks | ||||||||||||||
55 | G5R1 | Shortage of manpower (skilled, semi-skilled, and unskilled) | 0.753 | 7 | 0.807 | 10 | 0.705 | 28 | 0.608 | 6 | 0.531 | 7 | 0.608 | 6 |
56 | G5R2 | Unqualified/inexperienced workers | 0.745 | 9 | 0.789 | 17 | 0.735 | 13 | 0.588 | 9 | 0.548 | 6 | 0.588 | 9 |
57 | G5R3 | Low productivity level of manpower/labourers | 0.720 | 15 | 0.807 | 10 | 0.713 | 25 | 0.581 | 12 | 0.513 | 14 | 0.581 | 12 |
58 | G5R4 | Low payment for labour force | 0.665 | 33 | 0.640 | 71 | 0.622 | 54 | 0.426 | 51 | 0.414 | 48 | 0.426 | 54 |
59 | G5R5 | Injuries to labourers on the construction site | 0.556 | 68 | 0.545 | 79 | 0.505 | 82 | 0.303 | 77 | 0.281 | 79 | 0.303 | 79 |
60 | G5R6 | Delayed salary payments to staff by the contractor | 0.753 | 7 | 0.735 | 37 | 0.596 | 65 | 0.553 | 17 | 0.449 | 37 | 0.553 | 17 |
61 | G5R7 | High turn-over of personnel | 0.622 | 47 | 0.651 | 69 | 0.578 | 72 | 0.405 | 56 | 0.360 | 59 | 0.405 | 59 |
62 | G5R8 | Labour strikes | 0.498 | 78 | 0.709 | 45 | 0.622 | 54 | 0.353 | 69 | 0.310 | 74 | 0.353 | 71 |
Materials-Related Risks | ||||||||||||||
63 | G6R1 | Shortage of construction materials—special building materials not available in the local market | 0.509 | 76 | 0.705 | 46 | 0.655 | 46 | 0.359 | 67 | 0.333 | 67 | 0.359 | 70 |
64 | G6R2 | Delay in delivery of materials | 0.622 | 47 | 0.738 | 35 | 0.607 | 60 | 0.459 | 42 | 0.378 | 54 | 0.459 | 45 |
65 | G6R3 | Delay in the special manufacture of building materials/equipment | 0.673 | 31 | 0.793 | 14 | 0.647 | 49 | 0.533 | 23 | 0.435 | 41 | 0.533 | 23 |
66 | G6R4 | Delay in procurement of materials | 0.680 | 26 | 0.760 | 27 | 0.604 | 62 | 0.517 | 27 | 0.410 | 50 | 0.517 | 29 |
67 | G6R5 | Damage to material in storage/at site | 0.487 | 80 | 0.618 | 76 | 0.644 | 50 | 0.301 | 78 | 0.314 | 73 | 0.314 | 77 |
68 | G6R6 | Rejecting materials’ submittals | 0.585 | 58 | 0.713 | 44 | 0.585 | 70 | 0.417 | 53 | 0.343 | 65 | 0.417 | 56 |
Equipment-Related Risks | ||||||||||||||
69 | G7R1 | Inadequate or inefficient equipment, tools, and plants | 0.582 | 60 | 0.687 | 53 | 0.604 | 62 | 0.400 | 57 | 0.351 | 61 | 0.400 | 60 |
70 | G7R2 | Equipment availability and failure | 0.578 | 63 | 0.676 | 59 | 0.593 | 68 | 0.391 | 60 | 0.343 | 66 | 0.391 | 63 |
External Risks | ||||||||||||||
71 | G8R1 | Economic instability | 0.582 | 60 | 0.738 | 35 | 0.713 | 25 | 0.429 | 48 | 0.415 | 47 | 0.429 | 52 |
72 | G8R2 | High fluctuation in cost (e.g., money exchange rate; taxes and burdens; and interest rates charged by bankers on loan) | 0.589 | 53 | 0.662 | 66 | 0.731 | 15 | 0.390 | 62 | 0.431 | 44 | 0.431 | 51 |
73 | G8R3 | Inflation (e.g., material, equipment, and labour prices) | 0.607 | 50 | 0.633 | 72 | 0.720 | 19 | 0.384 | 64 | 0.437 | 39 | 0.437 | 49 |
74 | G8R4 | Changes in government regulations and laws (e.g., economy, tax, safety, environment, industrial, recruitment and workers’ visas, and localization) | 0.604 | 51 | 0.687 | 53 | 0.720 | 19 | 0.415 | 55 | 0.435 | 42 | 0.435 | 50 |
75 | G8R5 | Delay in connecting services with external parties (e.g., electricity, water, sewage, etc.) | 0.695 | 21 | 0.771 | 24 | 0.625 | 52 | 0.535 | 22 | 0.434 | 43 | 0.535 | 22 |
76 | G8R6 | Delay in recruitment and workers’ visa approval | 0.589 | 53 | 0.705 | 46 | 0.596 | 65 | 0.416 | 54 | 0.351 | 60 | 0.416 | 57 |
77 | G8R7 | Corruption (fraudulent practices, kickbacks, and lack of respect for the law) | 0.560 | 67 | 0.622 | 75 | 0.687 | 35 | 0.348 | 70 | 0.385 | 52 | 0.385 | 66 |
78 | G8R8 | Legal disputes between various parties | 0.556 | 68 | 0.680 | 57 | 0.651 | 48 | 0.378 | 65 | 0.362 | 58 | 0.378 | 67 |
79 | G8R9 | Import/Export restrictions | 0.516 | 75 | 0.662 | 66 | 0.618 | 58 | 0.342 | 73 | 0.319 | 72 | 0.342 | 73 |
Force Majeure Risks | ||||||||||||||
80 | G9R1 | Earthquakes, fires, and floods | 0.356 | 83 | 0.702 | 48 | 0.702 | 30 | 0.250 | 82 | 0.250 | 82 | 0.250 | 82 |
81 | G9R2 | Severe weather conditions | 0.509 | 76 | 0.673 | 61 | 0.578 | 72 | 0.342 | 72 | 0.294 | 77 | 0.342 | 72 |
82 | G9R3 | Wars in region/Political instability | 0.425 | 82 | 0.698 | 49 | 0.680 | 39 | 0.297 | 79 | 0.289 | 78 | 0.297 | 80 |
83 | G9R4 | Spreading of disease, epidemic or pandemic (e.g., COVID-19) | 0.589 | 53 | 0.815 | 9 | 0.764 | 5 | 0.480 | 36 | 0.450 | 36 | 0.480 | 40 |
No | Code | Risk Factors | Client | Consultant | Contractor | RI Overall | ||||
---|---|---|---|---|---|---|---|---|---|---|
RI | Rank | RI | Rank | RI | Rank | RI | Rank | |||
Client-Related Risks | ||||||||||
1 | G1R1 | Client’s lack of experience about the construction project. | 0.504 | 29 | 0.497 | 40 | 0.438 | 65 | 0.482 | 39 |
2 | G1R2 | Excessive bureaucracy in owner’s administration. | 0.538 | 16 | 0.529 | 32 | 0.581 | 29 | 0.545 | 18 |
3 | G1R3 | Client’s financial difficulties. | 0.489 | 34 | 0.566 | 23 | 0.713 | 6 | 0.544 | 19 |
4 | G1R4 | Owner’s delay in making progress payments for completed works (payment delays). | 0.632 | 1 | 0.680 | 2 | 0.809 | 1 | 0.672 | 2 |
5 | G1R5 | Selecting consultant, or designer, based on the lowest price. | 0.527 | 17 | 0.640 | 9 | 0.700 | 7 | 0.575 | 14 |
6 | G1R6 | Contract awarded to the lowest bidder. | 0.593 | 6 | 0.676 | 3 | 0.743 | 4 | 0.631 | 3 |
7 | G1R7 | Unrealistic/Inadequate original contract duration (tight schedule). | 0.556 | 13 | 0.577 | 20 | 0.656 | 13 | 0.577 | 13 |
8 | G1R8 | Political pressure to complete the project and speed up construction processes. | 0.397 | 58 | 0.403 | 62 | 0.474 | 55 | 0.413 | 58 |
9 | G1R9 | Delay in land acquisition/Handover to the contractor. | 0.406 | 55 | 0.315 | 76 | 0.440 | 64 | 0.390 | 64 |
10 | G1R10 | Difficulties in obtaining work permits from the authorities. | 0.450 | 43 | 0.495 | 42 | 0.595 | 25 | 0.486 | 35 |
11 | G1R11 | Change orders during construction. | 0.591 | 9 | 0.657 | 6 | 0.675 | 11 | 0.627 | 4 |
12 | G1R12 | Scope of work reduction by owner during execution phase. | 0.290 | 77 | 0.308 | 79 | 0.325 | 78 | 0.307 | 78 |
13 | G1R13 | Delay penalty clause in the Saudi Public Works Contract is inefficient. | 0.508 | 27 | 0.308 | 78 | 0.281 | 81 | 0.396 | 61 |
14 | G1R14 | Inaccurate estimation of construction cost by owner. | 0.523 | 20 | 0.530 | 31 | 0.578 | 31 | 0.527 | 27 |
15 | G1R15 | Project suspension by owner. | 0.413 | 52 | 0.432 | 54 | 0.532 | 39 | 0.439 | 47 |
16 | G1R16 | Delays due to dispute resolution. | 0.435 | 44 | 0.646 | 8 | 0.619 | 19 | 0.531 | 24 |
Designer-Related Risks | ||||||||||
17 | G2R1 | Unclear and inadequate drawings, specifications, bills of quantities (BOQ) | 0.592 | 7 | 0.586 | 16 | 0.638 | 15 | 0.582 | 11 |
18 | G2R2 | Discrepancies between project documents (contract, BOQ, specifications, and drawings). | 0.472 | 38 | 0.511 | 37 | 0.574 | 33 | 0.485 | 36 |
19 | G2R3 | Mistakes and deficiencies in design documents. | 0.486 | 35 | 0.505 | 38 | 0.520 | 42 | 0.483 | 38 |
20 | G2R4 | Inaccurately estimated quantities (BOQ). | 0.524 | 19 | 0.505 | 38 | 0.638 | 15 | 0.519 | 28 |
21 | G2R5 | All existing underground utilities information not available on the design documents (e.g., live cables and pipelines) for the contractor. | 0.508 | 27 | 0.596 | 13 | 0.495 | 50 | 0.537 | 20 |
22 | G2R6 | Inadequate geotechnical investigations report about ground conditions of the project site (if available). | 0.495 | 32 | 0.566 | 23 | 0.371 | 72 | 0.504 | 32 |
23 | G2R7 | Complexity of design. | 0.326 | 72 | 0.361 | 70 | 0.338 | 77 | 0.329 | 74 |
24 | G2R8 | Absence of contractor’s involvement in the design stage. | 0.362 | 66 | 0.260 | 82 | 0.316 | 79 | 0.322 | 76 |
25 | G2R9 | Speeding up of design phase’s schedule. | 0.516 | 23 | 0.459 | 48 | 0.374 | 71 | 0.467 | 43 |
26 | G2R10 | Limited budget for design. | 0.429 | 46 | 0.459 | 47 | 0.471 | 57 | 0.438 | 48 |
Consultant-Related Risks | ||||||||||
27 | G3R1 | Lack of experience and competence of consultant’s staff. | 0.499 | 30 | 0.596 | 14 | 0.540 | 38 | 0.528 | 26 |
28 | G3R2 | Slowness decision making for approval (shop drawings, submittals, sample materials, change orders, etc.) | 0.520 | 21 | 0.620 | 11 | 0.598 | 23 | 0.568 | 15 |
29 | G3R3 | Consultant’s rejection of submittals (shop drawings, equipment, and material samples). | 0.430 | 45 | 0.411 | 60 | 0.471 | 57 | 0.429 | 53 |
30 | G3R4 | Consultant’s delay in performing inspection and testing and giving instructions. | 0.378 | 64 | 0.404 | 61 | 0.453 | 59 | 0.394 | 62 |
31 | G3R5 | Poor coordination and communication between consultant and other parties. | 0.427 | 48 | 0.586 | 16 | 0.531 | 40 | 0.479 | 41 |
32 | G3R6 | Poor quality control and assurance. | 0.464 | 39 | 0.490 | 43 | 0.446 | 63 | 0.455 | 46 |
33 | G3R7 | Consultant’s corruption. | 0.394 | 60 | 0.517 | 36 | 0.413 | 68 | 0.424 | 55 |
34 | G3R8 | Inflexibility (rigidity) of consultant. | 0.359 | 67 | 0.381 | 66 | 0.516 | 43 | 0.389 | 65 |
35 | G3R9 | Excessive safety consideration. | 0.227 | 82 | 0.227 | 83 | 0.273 | 83 | 0.226 | 83 |
36 | G3R10 | Internal company problems (at consultant company’s head office). | 0.257 | 79 | 0.449 | 51 | 0.344 | 76 | 0.323 | 75 |
Contractor-Related Risks | ||||||||||
37 | G4R1 | Inadequate contractor experience (lack of experience, and managerial skills). | 0.569 | 11 | 0.666 | 4 | 0.574 | 33 | 0.595 | 8 |
38 | G4R2 | Contractor’s financial difficulties (ineffective cash flow management). | 0.627 | 2 | 0.798 | 1 | 0.763 | 2 | 0.692 | 1 |
39 | G4R3 | Contractor’s poor site management and supervision. | 0.592 | 7 | 0.664 | 5 | 0.553 | 36 | 0.601 | 7 |
40 | G4R4 | Ineffective planning and scheduling of project by contractor. | 0.598 | 5 | 0.657 | 7 | 0.678 | 9 | 0.627 | 4 |
41 | G4R5 | Ineffective control of the project progress. | 0.556 | 12 | 0.552 | 29 | 0.453 | 59 | 0.529 | 25 |
42 | G4R6 | Delays in sub-contractors work or due to suppliers. | 0.570 | 10 | 0.562 | 27 | 0.675 | 11 | 0.588 | 9 |
43 | G4R7 | Delay in preparation of shop drawings and material samples. | 0.526 | 18 | 0.595 | 15 | 0.616 | 20 | 0.554 | 16 |
44 | G4R8 | Delay in site mobilization | 0.489 | 33 | 0.473 | 45 | 0.375 | 70 | 0.462 | 44 |
45 | G4R9 | Rework and wastage on site, due to errors or quality of work (poor quality of workmanship). | 0.456 | 41 | 0.521 | 34 | 0.591 | 28 | 0.498 | 34 |
46 | G4R10 | Variations in quantities. | 0.511 | 25 | 0.520 | 35 | 0.508 | 45 | 0.500 | 33 |
47 | G4R11 | Cost of penalties. | 0.369 | 65 | 0.400 | 63 | 0.300 | 80 | 0.366 | 69 |
48 | G4R12 | The contractor does not carry out a field visit to the site during the bidding process. | 0.499 | 30 | 0.465 | 46 | 0.488 | 53 | 0.474 | 42 |
49 | G4R13 | New existing underground utilities not mentioned on the design documents (e.g., live cables, pipelines). | 0.518 | 22 | 0.566 | 23 | 0.580 | 30 | 0.536 | 21 |
50 | G4R14 | Health and Safety requirements (in light of COVID-19). | 0.338 | 70 | 0.364 | 69 | 0.506 | 46 | 0.371 | 68 |
51 | G4R15 | Accidents on site. | 0.250 | 81 | 0.284 | 80 | 0.413 | 67 | 0.274 | 81 |
52 | G4R16 | Conflict between contractor and consultant. | 0.464 | 40 | 0.579 | 18 | 0.595 | 25 | 0.516 | 30 |
53 | G4R17 | Tender-winning prices are unrealistically low (suicide tendering). | 0.481 | 36 | 0.557 | 28 | 0.595 | 25 | 0.514 | 31 |
54 | G4R18 | Unavailability of incentives for contractor for finishing ahead of schedule or to reduce the cost. | 0.410 | 54 | 0.497 | 40 | 0.744 | 3 | 0.484 | 37 |
Labour-Related Risks | ||||||||||
55 | G5R1 | Shortage of manpower (skilled, semi-skilled, and unskilled). | 0.616 | 3 | 0.612 | 12 | 0.678 | 9 | 0.608 | 6 |
56 | G5R2 | Unqualified/inexperienced workers. | 0.610 | 4 | 0.579 | 19 | 0.630 | 17 | 0.588 | 9 |
57 | G5R3 | Low productivity level of manpower/labourers. | 0.553 | 14 | 0.629 | 10 | 0.616 | 20 | 0.581 | 12 |
58 | G5R4 | Low payment for labour force. | 0.429 | 47 | 0.422 | 57 | 0.523 | 41 | 0.426 | 54 |
59 | G5R5 | Injuries to labourers on the construction site. | 0.292 | 76 | 0.309 | 77 | 0.359 | 74 | 0.303 | 79 |
60 | G5R6 | Delayed salary payments to staff by the contractor. | 0.548 | 15 | 0.562 | 26 | 0.680 | 8 | 0.553 | 17 |
61 | G5R7 | High turnover of personnel. | 0.419 | 49 | 0.387 | 65 | 0.489 | 52 | 0.405 | 59 |
62 | G5R8 | Labour strikes. | 0.320 | 73 | 0.397 | 64 | 0.474 | 55 | 0.353 | 71 |
Materials-Related Risks | ||||||||||
63 | G6R1 | Shortage of construction materials—special building materials not available in the local market. | 0.327 | 71 | 0.373 | 68 | 0.495 | 50 | 0.359 | 70 |
64 | G6R2 | Delay in delivery of materials. | 0.454 | 42 | 0.436 | 53 | 0.578 | 31 | 0.459 | 45 |
65 | G6R3 | Delay in the special manufacture of building materials/equipment. | 0.512 | 24 | 0.568 | 22 | 0.598 | 23 | 0.533 | 23 |
66 | G6R4 | Delay in procurement of materials. | 0.509 | 26 | 0.552 | 29 | 0.560 | 35 | 0.517 | 29 |
67 | G6R5 | Damage to material in storage/at site. | 0.339 | 69 | 0.315 | 75 | 0.281 | 81 | 0.314 | 77 |
68 | G6R6 | Rejecting materials’ submittals. | 0.412 | 53 | 0.375 | 67 | 0.553 | 36 | 0.417 | 56 |
Equipment-Related Risks | ||||||||||
69 | G7R1 | Inadequate or inefficient equipment, tools, and plants. | 0.418 | 51 | 0.350 | 72 | 0.504 | 47 | 0.400 | 60 |
70 | G7R2 | Equipment availability and failure. | 0.404 | 56 | 0.338 | 73 | 0.504 | 47 | 0.391 | 63 |
External Risks | ||||||||||
71 | G8R1 | Economic instability. | 0.386 | 62 | 0.442 | 52 | 0.613 | 22 | 0.429 | 52 |
72 | G8R2 | High fluctuation in cost (e.g., money exchange rate; taxes and burdens; and interest rates charged by bankers on loan). | 0.378 | 63 | 0.422 | 58 | 0.630 | 17 | 0.431 | 51 |
73 | G8R3 | Inflation (e.g., material, equipment and labour prices). | 0.403 | 57 | 0.459 | 49 | 0.503 | 49 | 0.437 | 49 |
74 | G8R4 | Changes in government regulations and laws (e.g., economy, tax, safety, environment, industrial, recruitment and workers’ visas, and localisation). | 0.418 | 50 | 0.450 | 50 | 0.453 | 59 | 0.435 | 50 |
75 | G8R5 | Delay in connecting services with external parties (e.g., electricity, water, sewage, etc.) | 0.473 | 37 | 0.570 | 21 | 0.656 | 13 | 0.535 | 22 |
76 | G8R6 | Delay in recruitment and workers’ visa approval. | 0.355 | 68 | 0.474 | 44 | 0.516 | 43 | 0.416 | 57 |
77 | G8R7 | Corruption (fraudulent practices, kickbacks, and lack of respect for law). | 0.396 | 59 | 0.414 | 59 | 0.356 | 75 | 0.385 | 66 |
78 | G8R8 | Legal disputes between various parties. | 0.313 | 75 | 0.432 | 54 | 0.488 | 53 | 0.378 | 67 |
79 | G8R9 | Import/export restrictions. | 0.320 | 73 | 0.359 | 71 | 0.450 | 62 | 0.342 | 73 |
Force Majeure Risks | ||||||||||
80 | G9R1 | Earthquakes, fires, and floods. | 0.225 | 83 | 0.277 | 81 | 0.360 | 73 | 0.250 | 82 |
81 | G9R2 | Severe weather conditions. | 0.267 | 78 | 0.424 | 56 | 0.435 | 66 | 0.342 | 72 |
82 | G9R3 | Wars in region/political instability. | 0.252 | 80 | 0.334 | 74 | 0.407 | 69 | 0.297 | 80 |
83 | G9R4 | Spreading of disease, epidemic, or pandemic (e.g., COVID-19). | 0.386 | 61 | 0.523 | 33 | 0.736 | 5 | 0.480 | 40 |
References
- Luong, D.; Tran, D.; Nguyen, P. Optimizing multi-mode time-cost-quality trade-off of construction project using opposition multiple objective difference evolution. Int. J. Constr. Manag. 2018, 21, 271–283. [Google Scholar] [CrossRef]
- Memon, A.H.; Rahman, I.A.; Abdullah, M.R.; Aziz, A.A.A. Time Overrun in Construction Projects from the Perspective of Project Management Consultant (PMC). J. Surv. Constr. Prop. 2011, 2, 1–13. [Google Scholar] [CrossRef] [Green Version]
- Lotfi, R.; Yadegari, Z.; Hosseini, S.; Khameneh, A.; Tirkolaee, E.; Weber, G. A robust time-cost-quality-energy-environment trade-off with resource-constrained in project management: A case study for a bridge construction project. J. Ind. Manag. Optim. 2022, 18, 375. [Google Scholar] [CrossRef]
- Iqbal, S.; Choudhry, R.; Holschemacher, K.; Ali, A.; Tamošaitienė, J. Risk management in construction projects. Technol. Econ. Dev. Econ. 2015, 21, 65–78. [Google Scholar] [CrossRef]
- Maqsoom, A.; Choudhry, R.; Umer, M.; Mehmood, T. Influencing factors indicating time delay in construction projects: Impact of firm size and experience. Int. J. Constr. Manag. 2019, 21, 1251–1262. [Google Scholar] [CrossRef]
- Yap, J.; Goay, P.; Woon, Y.; Skitmore, M. Revisiting critical delay factors for construction: Analysing projects in Malaysia. Alex. Eng. J. 2021, 60, 1717–1729. [Google Scholar] [CrossRef]
- Assaf, S.A.; Al-Hejji, S. Causes of delay in large construction projects. Int. J. Proj. Manag. 2006, 24, 349–357. [Google Scholar] [CrossRef]
- Kaliba, C.; Muya, M.; Mumba, K. Cost escalation and schedule delays in road construction projects in Zambia. Int. J. Proj. Manag. 2009, 27, 522–531. [Google Scholar] [CrossRef]
- Arditi, D.; Akan, G.T.; Gurdamar, S. Reasons for delays in public projects in Turkey. Constr. Manag. Econ. 1985, 3, 171–181. [Google Scholar] [CrossRef]
- Kraiem, Z.M.; Diekmann, J.E. Concurrent Delays in Construction Projects. J. Constr. Eng. Manag. 1987, 113, 591–602. [Google Scholar] [CrossRef]
- Azhar, N.; Farouqui, R.U. Cost Overrun Factors in Construction Industry of Pakistan. In Proceedings of the First International Conference on Construction in Developing Countries (ICCIDC–I) “Advancing and Integrating Construction Education, Research & Practice”, Karachi, Pakistan, 4–5 August 2008. [Google Scholar]
- Wang, M.-T.; Chou, H.-Y. Risk Allocation and Risk Handling of Highway Projects in Taiwan. J. Manag. Eng. 2003, 19, 60–68. [Google Scholar] [CrossRef]
- Barrie, D.S.; Paulson, B.C., Jr. Professional Construction Management: Including Contracting CM, Design-Construct, and General Contracting; McGraw-Hill: New York, NY, USA, 1992. [Google Scholar]
- Allahaim, F.S.; Liu, L. Causes of cost overruns on infrastructure projects in Saudi Arabia. Int. J. Collab. Enterp. 2015, 5, 32. [Google Scholar] [CrossRef]
- Seddeeq, A.; Assaf, S.; Abdallah, A.; Hassanain, M. Time and Cost Overrun in the Saudi Arabian Oil and Gas Construction Industry. Buildings 2019, 9, 41. [Google Scholar] [CrossRef] [Green Version]
- Long, R.J. Typical Problems Leading to Delays, Cost Overruns, and Claims on Process Plant and O Shore Oil and Gas Projects. Available online: https://www.long-intl.com/wp-content/uploads/2014/02/Long-Intl-Typical-Problems-Leading-to-Delays-Cost-Overruns-Claims.pdf (accessed on 9 July 2021).
- Abdellatif, H.; Alshibani, A. Major Factors Causing Delay in the Delivery of Manufacturing and Building Projects in Saudi Arabia. Buildings 2019, 9, 93. [Google Scholar] [CrossRef] [Green Version]
- Mahamid, I.; Laissy, M. Time Overrun in Construction of Road Projects in Developing Countries: Saudi Arabia as a Case Study. Int. J. Eng. Inf. Syst. (IJEAIS) 2019, 3, 18–23. [Google Scholar]
- Velumani, P.; Nampoothiri, N.; Urbański, M. A Comparative Study of Models for the Construction Duration Prediction in Highway Road Projects of India. Sustainability 2021, 13, 4552. [Google Scholar] [CrossRef]
- Khalifa, W.M.A.; Mahamid, I. Causes of Change Orders in Construction Projects. Eng. Technol. Appl. Sci. Res. 2019, 9, 4956–4961. [Google Scholar] [CrossRef]
- Dixit, S.; Sharma, K.; Singh, S. Identifying and Analysing Key Factors Associated with Risks in Construction Projects. In Emerging Trends in Civil Engineering; Springer: Singapore, 2020; pp. 25–32. [Google Scholar] [CrossRef]
- Kartam, N.A.; Kartam, S.A. Risk and its management in the Kuwaiti construction industry: A contractors’ perspective. Int. J. Proj. Manag. 2001, 19, 325–335. [Google Scholar] [CrossRef]
- Ranns, R.H.B.; Ranns, E.J.M. Practical Construction Management, 1st ed.; Routledge: Oxfordshire, UK, 2016; p. 4. [Google Scholar]
- Global Construction Outlook to 2023—Q3 2019 Update. Available online: https://www.reportlinker.com/p05582683/Global-Construction-Outlook-to-Q3-Update.html?utm_source=PRN (accessed on 16 December 2021).
- Future-Ready Index. Global Construction Survey 2019. Available online: https://assets.kpmg/content/dam/kpmg/xx/pdf/2019/04/global-construction-survey-2019.pdf (accessed on 15 December 2021).
- Global Construction 2030: A Global Forecast for the Construction Industry to 2030. Available online: https://www.pwc.com/vn/en/industries/engineering-and-construction/pwc-global-construction-2030.html (accessed on 12 December 2021).
- Robinson, G. Global Construction Market to Grow $8 trillion by 2030: Driven by China, US and India. Global Construction Perspectives and Oxford Economics, UK. Available online: https://www.ice.org.uk/ICEDevelopmentWebPortal/media/Documents/News/ICE%20News/Global-Construction-press-release.pdf (accessed on 16 December 2021).
- Meisels, M. 2018 Global Construction Industry Overview. Global Construction Industry: A Positive Outlook. Deloitte Report (GPOC). Available online: https://www2.deloitte.com/us/en/pages/energy-and-resources/articles/global-construction-industry-overview.html (accessed on 14 December 2021).
- Impact of COVID-19 on the Construction Sector. 2021. Available online: https://www.ilo.org/wcmsp5/groups/public/---ed_dialogue/---sector/documents/briefingnote/wcms_767303.pdf (accessed on 28 August 2021).
- COVID-19’s Impact on the Engineering & Construction Sector|Deloitte Global. Deloitte. 2021. Available online: https://www2.deloitte.com/global/en/pages/about-deloitte/articles/covid-19/understanding-the-sector-impact-of-covid-19--engineering---const.html (accessed on 28 August 2021).
- Mordor Intelligence. Saudi Arabia Construction Market—Growth, Trends, and Forecast (2019–2024). Available online: https://www.mordorintelligence.com/industry-reports/saudi-arabia-construction-market-growth-trends-and-forecast-2019-2024 (accessed on 19 December 2021).
- Davids, G. Potential for Construction Sector in GCC—Linesight. Available online: https://meconstructionnews.com/36485/ksa-holds-greatest-potential-for-construction-sector-in-gcc-linesight (accessed on 19 December 2021).
- Almutairi, Y.; Arif, M.; Khalfan, M. Moving towards managing offsite construction techniques in the Kingdom of Saudi Arabia: A review. Middle East J. Manag. 2016, 3, 164. [Google Scholar] [CrossRef]
- Algahtany, A.; Alhammadi, Y.; Kashiwagi, D. Introducing a New Risk Management Model to the Saudi Arabian Construction Industry. Procedia Eng. 2016, 145, 940–947. [Google Scholar] [CrossRef]
- Alrashed, I.; Alrashed, A.; Taj, S.A.; Kantamaneni, M.P.K. Risk Assessments for Construction projects in Saudi Arabia. Res. J. Manag. Sci. 2014, 3, 1–6. [Google Scholar]
- Research & Markets. Construction in Saudi Arabia—Key Trends and Opportunities to 2025 (Q2 2021). 2021. Available online: https://www.researchandmarkets.com/reports/5367699/construction-in-saudi-arabia-key-trends-and?utm_source=BW&utm_medium=PressRelease&utm_code=rbmm66&utm_campaign=1566018+-+Saudi+Arabia+Construction+Market+Report+2021%3a+Key+Trends+and+Opportunities+to+2025%2c+Q2+2021+Update&utm_exec=chdo54prd (accessed on 7 September 2021).
- Puri-Mirza, A. Saudi Arabia: Growth Value of Planned Construction Contract Awards 2022|Statista. 2021. Available online: https://www.statista.com/statistics/1100182/saudi-arabia-growth-value-of-plannned-construction-contract-awards/ (accessed on 7 September 2021).
- Puri-Mirza, A. Saudi Arabia: Value of Planned Buildings Contract Awards 2022|Statista. 2021. Available online: https://www.statista.com/statistics/1100216/saudi-arabia-value-of-planned-buildings-contract-awards/ (accessed on 7 September 2021).
- MOMRA. Contractors Classification Agency. Available online: https://contractors.momra.gov.sa (accessed on 12 December 2021).
- Silva, G.A.; Warnakulasooriya, B.N.F.; Arachchige, B. Criteria for Construction Project Success: A Literature Review. In Proceedings of the University of Sri Jayewardenepura, Sri Lanka, 13th International Conference on Business Management (ICBM), Nugegoda, Sri Lanka, 8 December 2016; Available online: https://ssrn.com/abstract=2910305 (accessed on 17 December 2021).
- Ramlee, N.; Tammy, N.J.; Raja Mohd Noor, R.N.; Ainun Musir, A.; Abdul Karim, N.; Chan, H.B.; Mohd Nasir, S.R. Critical success factors for construction project. AIP Conf. Proc. 2016, 1774, 030011. [Google Scholar]
- Alzara, M.; Kashiwagi, J.; Kashiwagi, D.; Al-Tassan, A. Using PIPS to Minimize Causes of Delay in Saudi Arabian Construction Projects: University Case Study. Procedia Eng. 2016, 145, 932–939. [Google Scholar] [CrossRef]
- Baghdadi, A.; Kishk, M. Saudi Arabian Aviation Construction Projects: Identification of Risks and Their Consequences. Procedia Eng. 2015, 123, 32–40. [Google Scholar] [CrossRef] [Green Version]
- Mahamid, I. Schedule Delay in Saudi Arabia Road Construction Projects: Size, Estimate, Determinants and Effects. Int. J. Arch. Eng. Constr. 2017, 6, 51–58. [Google Scholar] [CrossRef] [Green Version]
- Sha’Ar, K.; Assaf, S.; Bambang, T.; Babsail, M.; El Fattah, A.A. Design—Construction interface problems in large building construction projects. Int. J. Constr. Manag. 2016, 17, 238–250. [Google Scholar] [CrossRef] [Green Version]
- Al-Emad, N.; Rahman, I.A.; Nagapan, S.; Gamil, Y. Ranking of Delay Factors for Makkah’s Construction Industry. MATEC Web Conf. 2017, 103, 3001. [Google Scholar] [CrossRef] [Green Version]
- Arditi, D.; Nayak, S.; Damci, A. Effect of organizational culture on delay in construction. Int. J. Proj. Manag. 2017, 35, 136–147. [Google Scholar] [CrossRef]
- Elawi, G.S.A.; Algahtany, M.; Kashiwagi, D. Owners’ Perspective of Factors Contributing to Project Delay: Case Studies of Road and Bridge Projects in Saudi Arabia. Procedia Eng. 2016, 145, 1402–1409. [Google Scholar] [CrossRef] [Green Version]
- Sánchez, O.; Castañeda, K.; Mejía, G.; Pellicer, E. Delay Factors: A Comparative Analysis between Road Infrastructure and Building Projects. In Proceedings of the Construction Research Congress, Tempe, AZ, USA, 8–10 March 2020; pp. 223–231. [Google Scholar] [CrossRef]
- Sanni-Anibire, M.O.; Zin, R.M.; Olatunji, S.O. Causes of Delay in Tall Building Projects in GCC Countries. In Proceedings of the 8th International Conference on Construction Engineering and Project Management, Hong Kong, China, 7–8 December 2020. [Google Scholar]
- Mohammed Gopang, R.K.; Alias Imran, Q.B.; Nagapan, S. Assessment of Delay Factors in Saudi Arabia Railway/Metro Construction Projects. Int. J. Sustain. Constr. Eng. Technol. 2020, 11, 225–233. [Google Scholar] [CrossRef]
- Aljohani, A. Construction Projects Cost Overrun: What Does the Literature Tell Us? Int. J. Innov. Manag. Technol. 2017, 8, 137–143. [Google Scholar] [CrossRef]
- Ahady, S.; Gupta, S.; Malik, R.K. A critical review of the causes of cost overrun in construction industries of developing countries. Int. Res. J. Eng. Technol. 2017, 4, 2550–2558. [Google Scholar]
- Bahamid, R.A.; Doh, S.I.; Al-Sharaf, M.A. Risk factors affecting the construction projects in the developing countries. IOP Conf. Ser. Earth Environ. Sci. 2019, 244, 012040. [Google Scholar] [CrossRef]
- Baloyi, L.; Bekker, M. Causes of construction cost and time overruns: The 2010 FIFA World Cup stadia in South Africa. Acta Structilia J. Phys. Dev. Sci. 2011, 18, 51–67. [Google Scholar]
- Cirovic, G.; Sudjic, S. Risk Assessment in Construction Industry. Available online: https://www.irbnet.de/daten/iconda/CIB15854.pdf (accessed on 11 December 2019).
- Creedy, G.D.; Skitmore, M.; Wong, J.K.W. Evaluation of risk factors leading to cost overrun in delivery of highway construction projects. J. Constr. Eng. Manag. 2010, 136, 528–537. [Google Scholar] [CrossRef] [Green Version]
- Jackson, S. Project cost overruns and risk management. In Proceedings of the Association of Researchers in Construction Management 18th Annual ARCOM Conference, Newcastle, UK, 2–4 September 2002; Volume 1, pp. 99–108. [Google Scholar]
- Liu, J.; Zhao, X.; Yan, P. Risk Paths in International Construction Projects: Case Study from Chinese Contractors. J. Constr. Eng. Manag. 2016, 142, 05016002. [Google Scholar] [CrossRef]
- Mahamid, I.; Al-Ghonamy, A.; Aichouni, M. Risk Matrix for Delay Causes in Construction Projects in Saudi Arabia. Res. J. Appl. Sci. Eng. Technol. 2015, 9, 665–670. [Google Scholar] [CrossRef]
- Memon, A.H.; Rahman, I.A.; Azis, A.A.A. Time and Cost Performance in Construction Projects in Southern and Central Regions of Peninsular Malaysia. Int. J. Adv. Appl. Sci. 2012, 1, 45–52. [Google Scholar] [CrossRef]
- Sharma, S.; Goyal, P.K. Fuzzy assessment of the risk factors causing cost overrun in construction industry. Evol. Intell. 2019, 1–13. [Google Scholar] [CrossRef]
- Subramani, T.; Sruthi, P.; Kavitha, M. Causes of Cost Overrun in Construction. IOSR J. Eng. 2014, 3, 1–7. [Google Scholar] [CrossRef]
- Zewdu, Z.T.; Aregaw, G.T. Causes of Contractor Cost Overrun in Construction Projects: The Case of Ethiopian Construction Sector. Int. J. Bus. Econ. Res. 2015, 4, 180. [Google Scholar] [CrossRef] [Green Version]
- Zhao, X.; Hwang, B.G.; Gao, Y. A fuzzy synthetic evaluation approach for risk assessment: A case of Singapore’s green projects. J. Clean. Prod. 2016, 115, 203–213. [Google Scholar] [CrossRef]
- Saunders, M.; Lewis, P.; Thornhill, A. Research Methods for Business Students, 8th ed.; Pearson: New York, NY, USA, 2019. [Google Scholar]
- Taber, K.S. The use of Cronbach’s alpha when developing and reporting research instruments in science education. Res. Sci. Educ. 2018, 48, 1273–1296. [Google Scholar] [CrossRef]
- Alsuliman, J.A. Causes of delay in Saudi public construction projects. Alex. Eng. J. 2019, 58, 801–808. [Google Scholar] [CrossRef]
- Ikediashi, D.I.; Ogunlana, S.O.; Alotaibi, A. Analysis of project failure factors for infrastructure projects in Saudi Arabia: A multivariate approach. J. Constr. Dev. Ctries. 2014, 19, 35. [Google Scholar]
- Al-Khalil, M.I.; Al-Ghafly, M.A. Important causes of delay in public utility projects in Saudi Arabia. Constr. Manag. Econ. 1999, 17, 647–655. [Google Scholar] [CrossRef]
- Shash, A.A.; Qarra, A.A. Cash flow management of construction projects in Saudi Arabia. Proj. Manag. J. 2018, 49, 48–63. [Google Scholar] [CrossRef]
- Le-Hoai, L.; Dai Lee, Y.; Lee, J.Y. Delay and cost overruns in Vietnam large construction projects: A comparison with other selected countries. KSCE J. Civ. Eng. 2008, 12, 367–377. [Google Scholar] [CrossRef]
- Abd El-Razek, M.E.; Bassioni, H.A.; Mobarak, A.M. Causes of delay in building construction projects in Egypt. J. Constr. Eng. Manag. 2008, 134, 831–841. [Google Scholar] [CrossRef] [Green Version]
- Albogamy, A.; Scott, D.; Dawood, N. Addressing construction delays in the Kingdom of Saudi Arabia. Int. Proc. Econ. Dev. Res. 2012, 45, 148–153. [Google Scholar]
- Koushki, P.A.; Al-Rashid, K.; Kartam, N. Delays and cost increases in the construction of private residential projects in Kuwait. Constr. Manag. Econ. 2005, 23, 285–294. [Google Scholar] [CrossRef]
- Assaf, S.A.; Al-Khalil, M.; Al-Hazmi, M. Causes of Delay in Large Building Construction Projects. J. Manag. Eng. 1995, 11, 45–50. [Google Scholar] [CrossRef]
- Hammadi, S.; Nawab, M. Study of Delay Factors in Construction Projects. Int. Adv. Res. J. Sci. Eng. Technol. 2016, 3, 87–93. [Google Scholar] [CrossRef]
- Arain, F.M.; Pheng, L.S.; Assaf, S.A. Contractors’ Views of the Potential Causes of Inconsistencies between Design and Construction in Saudi Arabia. J. Perform. Constr. Facil. 2006, 20, 74–83. [Google Scholar] [CrossRef] [Green Version]
- Babalola, O.; Ibem, E.; Ezema, I. Implementation of lean practices in the construction industry: A systematic review. Build. Environ. 2019, 148, 34–43. [Google Scholar] [CrossRef]
- Bajjou, M.S.; Chafi, A. Lean construction implementation in the Moroccan construction industry: Awareness, benefits and barriers. J. Eng. Des. Technol. 2018, 16, 533–556. [Google Scholar] [CrossRef]
- Sarhan, J.; Xia, B.; Fawzia, S.; Karim, A.; Olanipekun, A. Barriers to implementing lean construction practices in the Kingdom of Saudi Arabia (KSA) construction industry. Constr. Innov. 2018, 18, 246–272. [Google Scholar] [CrossRef] [Green Version]
- Jagtap, M.; Kamble, S. The effect of the client–contractor relationship on project performance. Int. J. Product. Perform. Manag. 2019, 69, 541–558. [Google Scholar] [CrossRef]
- Aliakbarlou, S.; Wilkinson, S.; Costello, S. Rethinking client value within construction contracting services. Int. J. Manag. Proj. Bus. 2018, 11, 1007–1025. [Google Scholar] [CrossRef]
Category | Respondent Number | Percentage | Category | Respondent Number | Percentage |
---|---|---|---|---|---|
Years of Experience | Sector/Entity | ||||
Less than 5 years | 1 | 1.82% | Public sector | 30 | 54.55% |
6–15 years | 19 | 34.55% | Private sector | 19 | 34.55% |
16–25 years | 26 | 47.27% | Semi-government sector | 3 | 5.45% |
More than 25 years | 9 | 16.36% | Academic and research institutions | 3 | 5.45% |
100.00% | 100.00% | ||||
Educational Background | Role | ||||
Civil Engineering | 33 | 60.00% | Owner/government agency | 27 | 49.09% |
Architecture | 7 | 12.73% | Designer | 2 | 3.64% |
Electrical Engineering | 5 | 9.09% | Consultant | 16 | 29.09% |
Mechanical Engineering | 10 | 18.18% | Contractor | 8 | 14.55% |
Others | 2 | 3.64% | |||
100.00% | 100.00% |
Project Delays | Project Cost Overruns | ||||
---|---|---|---|---|---|
Category | Respondent Number | Percentage | Category | Respondent Number | Percentage |
% Projects Exposed to Delays | % of Projects Exposed to Cost Overruns | ||||
Never | 0 | 0 | Never | 1 | 1.82% |
Less than 10% | 1 | 1.82% | Less than 10% | 11 | 20.00% |
11–20% | 9 | 16.36% | 11–20% | 11 | 20.00% |
21–30% | 4 | 7.27% | 21–30% | 13 | 23.64% |
31–40% | 11 | 20.00% | 31–40% | 9 | 16.36% |
More than 40% | 30 | 54.55% | More than 40% | 10 | 18.18 |
55 | 100.00% | 55 | 100.00% | ||
Average delay % | Average cost overruns % | ||||
Never | 0 | 0% | Never | 1 | 1.82% |
Less than 10% | 1 | 1.82% | Less than 5% | 6 | 10.91% |
11–20% | 10 | 18.18% | 6–10% | 19 | 34.55% |
21–30% | 19 | 34.55% | 11–15% | 10 | 18.18% |
31–40% | 10 | 18.18% | 16–20% | 8 | 14.55% |
More than 40% | 15 | 27.27% | 21–25% | 8 | 14.55% |
More than 25% | 3 | 5.45% | |||
55 | 100.00% | 55 | 100.00% |
No | Code | Risk Factors | Risk Importance | Category | |||||
---|---|---|---|---|---|---|---|---|---|
Project Delay | Project Cost Overruns | Overall | |||||||
RI | Rank | RI | Rank | RI | Rank | ||||
38 | G4R2 | Contractor’s financial difficulties (ineffective cash flow management) | 0.692 | 1 | 0.597 | 3 | 0.692 | 1 | Contractor-related |
4 | G1R4 | Owner’s delay in making progress payments for completed works (Payment delays) | 0.672 | 2 | 0.525 | 12 | 0.672 | 2 | Client-related |
6 | G1R6 | Contract awarded to lowest bidder | 0.631 | 3 | 0.601 | 2 | 0.631 | 3 | |
11 | G1R11 | Change orders during construction | 0.627 | 4 | 0.622 | 1 | 0.627 | 4 | |
40 | G4R4 | Ineffective planning and scheduling of project by contractor | 0.627 | 5 | 0.528 | 9 | 0.627 | 5 | Contractor-related |
55 | G5R1 | Shortage of manpower (skilled, semi-skilled, unskilled) | 0.608 | 6 | 0.531 | 7 | 0.608 | 6 | Labour-related |
39 | G4R3 | Contractor’s poor site management and supervision | 0.601 | 7 | 0.526 | 11 | 0.601 | 7 | Contractor-related |
37 | G4R1 | Inadequate contractor experience (lack of experience, and managerial skills) | 0.595 | 8 | 0.529 | 8 | 0.595 | 8 | |
42 | G4R6 | Delays in sub-contractors’ work or suppliers | 0.588 | 9 | 0.474 | 24 | 0.588 | 9 | |
56 | G5R2 | Unqualified/inexperienced workers. | 0.588 | 10 | 0.548 | 6 | 0.588 | 10 | Labour-related |
Group No. | Risk Factor Group | RI | Rank | Category |
---|---|---|---|---|
G1 | Client-related Risks | 0.55 | 1 | Internal |
G4 | Contractor-related Risks | 0.505 | 2 | Internal |
G5 | Labour-related Risks | 0.477 | 3 | External |
G2 | Designer-related Risks | 0.455 | 4 | Internal |
G6 | Materials-related Risks | 0.431 | 5 | External |
G3 | Consultant-related Risks | 0.421 | 6 | Internal |
G8 | External Risks | 0.397 | 7 | External |
G7 | Equipment-related Risks | 0.395 | 8 | External |
G9 | Force Majeure Risks | 0.342 | 9 | External |
Group No. | Risk Factor Group | No. of Risk Factors | Probability (P) | Impact on Time (IT) | Impact on Cost (IC) | |||
---|---|---|---|---|---|---|---|---|
Cα | Result | Cα | Result | Cα | Result | |||
G1 | Client-related Risks | 16 | 0.825 | Good | 0.813 | Good | 0.847 | Good |
G2 | Designer-related Risks | 10 | 0.862 | Good | 0.824 | Good | 0.842 | Good |
G3 | Consultant-related Risks | 10 | 0.866 | Good | 0.865 | Good | 0.897 | Good |
G4 | Contractor-related Risks | 18 | 0.915 | Excellent | 0.906 | Excellent | 0.940 | Excellent |
G5 | Labour-related Risks | 8 | 0.860 | Good | 0.847 | Good | 0.901 | Excellent |
G6 | Materials-related Risks | 6 | 0.867 | Good | 0.884 | Good | 0.937 | Excellent |
G7 | Equipment-related Risks | 22 | 0.853 | Good | 0.837 | Good | 0.841 | Good |
G8 | External Risks | 9 | 0.873 | Good | 0.828 | Good | 0.877 | Good |
G9 | Force Majeure Risks | 4 | 0.839 | Good | 0.864 | Good | 0.862 | Good |
Overall | 0.9858 | Excellent |
Parties | Spearman Rank Correlation Coefficient | |||||
---|---|---|---|---|---|---|
Client and Consultant | 0.834 | |||||
Client and Contractor | 0.653 | |||||
Consultant and Contractor | 0.736 | |||||
Parties | Probability (P) | Impact (I) | Risk Importance (RI) | |||
Project Delay | Project Cost Overruns | Project Delay | Project Cost Overruns | Overall | ||
Client and Consultant | 0.814 | 0.778 | 0.788 | 0.817 | 0.830 | 0.828 |
Client and Contractor | 0.650 | 0.633 | 0.433 | 0.655 | 0.341 | 0.641 |
Consultant and Contractor | 0.756 | 0.683 | 0.610 | 0.765 | 0.548 | 0.738 |
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations. |
© 2022 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Alshihri, S.; Al-Gahtani, K.; Almohsen, A. Risk Factors That Lead to Time and Cost Overruns of Building Projects in Saudi Arabia. Buildings 2022, 12, 902. https://doi.org/10.3390/buildings12070902
Alshihri S, Al-Gahtani K, Almohsen A. Risk Factors That Lead to Time and Cost Overruns of Building Projects in Saudi Arabia. Buildings. 2022; 12(7):902. https://doi.org/10.3390/buildings12070902
Chicago/Turabian StyleAlshihri, Saad, Khalid Al-Gahtani, and Abdulmohsen Almohsen. 2022. "Risk Factors That Lead to Time and Cost Overruns of Building Projects in Saudi Arabia" Buildings 12, no. 7: 902. https://doi.org/10.3390/buildings12070902
APA StyleAlshihri, S., Al-Gahtani, K., & Almohsen, A. (2022). Risk Factors That Lead to Time and Cost Overruns of Building Projects in Saudi Arabia. Buildings, 12(7), 902. https://doi.org/10.3390/buildings12070902