Development of a Taxonomy for Causes of Changes in Construction Projects
Abstract
:1. Introduction
- Practitioners can use the proposed taxonomy to differentiate change causes, handle the related change causes together, and minimize the changes at the outset of project initiation, enhancing the overall productivity of projects.
- A taxonomy encompassing all possible change causes can enhance the effectiveness of the decision-making process in case of a change by assisting project parties to identify potential underlying causes of changes.
- A standardized taxonomy on knowledge about causes of changes can improve knowledge sharing among project parties regarding the causes and effects of changes. Such a knowledge management framework not only reduces the occurrence of changes, but also minimizes the adverse consequences of them.
- The proposed taxonomy can also enhance the monitoring capability of project teams on changes as well as aiding the reporting of changes and/or causes associated with them in more detail and more reliably; this is expected to construct a trust bridge among parties that can be disrupted due to changes and/or change requests.
2. Critical Review of the Studies on Causes of Changes
3. Examining the Current Categories of Change Causes
- First, many of the existing studies revealed the change causes classification based on case studies. That is to say, existing accounts only reviewed specific project records and documents to identify the change causes. Therefore, the findings of these studies cannot be generalized for all construction projects, rather they can be used only for specific projects and/or in specific locations while being applicable only for the investigated time horizons. Briefly, the majority of recent studies on change causes are project-specific, project type-specific, and/or country-specific.
- Secondly, in many of the existing research, the methodology used to identify change cause classification is in the form of questionnaire surveys with experts working in the construction industry. However, since these questionnaires were prepared based on previous studies and were finalized without discussion with the experts from a wide range of projects, the questionnaires can provide limited insights into the evolving causes of changes. The researchers chiefly ranked the existing change causes based on the collected questionnaires causing subjective insights, which led to different ranks in the previous studies.
- Another limitation of the current taxonomies is that the majority of the existing classifications were based upon the origin agent approach, in which the responsible parties were identified instead of proposing a generic model of the taxonomy for change causes. The present approaches can only be beneficial for those conducted with the same project and/or contract type as the case studies used for developing these classification schemes. However, they are not suitable for use as a general model to determine the cause of changes in all types of building projects.
- Although there exist studies that used change cause classifications, the main purpose of most of them was not to develop a comprehensive taxonomy for the causes of changes. The classifications were primarily used by researchers for various purposes, such as establishing a relationship between change causes and impacts or ranking the causes of changes. Therefore, there is a need for a comprehensive classification of change causes that can be used by all parties to monitor and control the changes in any type of project and any location. Overall, the current research aims to extend the scope of change management for practitioners, who have usually used an incomplete list of “Change Causes”, resulting in unexpected outcomes.
4. Research Methodology
4.1. Developing Preliminary Taxonomy (Step 1 and Step 2)
4.2. Case Studies (Step 3)
4.3. Focus Group Discussion (Step 4)
4.4. Validation of the Taxonomy (Step 5)
5. Discussion of Findings
5.1. Implications of Findings for Project Management
5.2. Benefits and Challenges of Utilizing the Proposed Taxonomy
5.3. Suggestions for Effective Change Management
6. Conclusions
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
Appendix A
Level 1: Human resources | ||
Level 2: Organizing and Managing | ||
1 | Inequitable labor distribution | Rahman et al. [6] |
2 | Replacement of key personnel | Zadeh et al. [40] |
3 | Turnover of contractor’s employee | Sun and Meng [21], Safapour et al. [41], and Yap et al. [42] |
4 | Overstaffing or understaffing | Okada et al. [43] |
5 | Extensive overtime for labor | Hanna et al. [44], Safapour et al. [41], Arditi et al. [45] |
6 | Additional shifts | Waney et al. [46] |
7 | Replacement of key personnel by owner | Rahman et al. [6], Al-Kharashi and Skitmore [47] |
8 | Excessive turnover of owner’s technical personnel | Sun and Meng [21], Safapour et al. [41], Yap et al. [42] |
9 | Absenteeism of labor | Safapour et al. [41], Hanna et al. [44], Ajayi and Chinda [48], Arditi et al. [45] |
10 | Absenteeism of consultant’s supervisors | Assaf and Al-Hejji [23], Alaghbari et al. [49] |
11 | Low motivation and morale of labors | Yap and Tan [50], Shoar et al. [51], Kumar [28], Niazi and Painting [52] |
12 | Nationality of labors | Assaf and Al-Hejji [23], Al-Kharashi and Skitmore [47], Niazi and Painting [52] |
13 | Conflict among workers due to different personality | Safapour et al. [41] |
Level 2: Availability | ||
1 | Unavailability/shortage of labor | Altaf et al. [53], Staiti et al. [54], Kumar [28], Yates [55], Al-Kharashi and Skitmore [47], Marzouk and El-Rasas [56] |
2 | Shortage of contractor’s technical professionals | Rahman et al. [6], Al-Kharashi and Skitmore [47] |
3 | Shortage of qualified/skilled labor/craft | Altaf et al. [53], Enshassi et al. [35], Rashid et al. [57], Project 5 |
4 | Shortage of qualified local labor | Hilali et al. [58], Toor and Ogunlana [59], Arditi et al. [45] |
5 | Shortage of qualified owner’s engineers | Alnuaimi et al. [37] |
6 | Shortage of management support and staff training to simulate the construction process | Kumar [28], Lee et al. [60] |
7 | Shortage of qualified managers | Yap et al. [42] |
8 | Shortage of qualified owner’s representative | Jarkas and Mubarak [18], Toor and Ogunlana [59], Arditi et al. [45] |
9 | Shortage of contractor’s administrative personnel | Rahman et al. [6], Al-Kharashi and Skitmore [47], Sweis et al. [61] |
10 | Shortage of contractor’s site staff | Alaghbari et al. [49] |
Level 2: Capabilities | ||
1 | Unqualified/Inexperienced labor | Maqbool and Rashid [62], Staiti et al. [54], Chan and Kumaraswamy [20], Marzouk and El-Rasas [56] |
2 | Unskillful labor | Safapour et al. [41], Yap et al. [42], Lee et al. [60], Al-Kharashi and Skitmore [47] |
3 | Skill shortage in certain trades | Sun and Meng [21], Rahman et al. [6], Yap et al. [42] |
4 | Low level of labors efficiency/Productivity | Rahman et al. [6], Kumar [28], Yates [55], Al-Kharashi and Skitmore [47], Prasad et al. [63] |
5 | Inadequate skill of equipment-operator | Rahman et al. [6], Al-Kharashi and Skitmore [47] |
6 | Inexperienced consultant’s site staff | Alshihri et al. [29], Alaghbari et al. [49] |
7 | Incompetent technical staff | Maqbool and Rashid [62] |
Level 1: Material | ||
Level 2: Procurement Process of Materials | ||
1 | Delay in material delivery | Staiti et al. [54], Kumar [28], Alshihri et al. [29], Rashid et al. [57], Yates [55] |
2 | Poor programming of material procurement | Rahman et al. [6], Chan and Kumaraswamy [20] |
3 | Poorly scheduled supply of material to the site | Arefazar et al. [19] |
4 | Delay in manufacturing special building materials | Kumar [28], Alshihri et al. [29] |
5 | Problems arising from imported materials and plant items | Hilali et al. [58], Hansen et al. [36], Prasad et al. [63] |
6 | Late procurement of materials | Jarkas and Mubarak [18], Alshihri et al. [29], Keane et al. [64] |
7 | Inappropriate/Poor procurement method | Maluleke et al. [65], Dosumu and Aigbavboa [66], Enshassi et al. [35] |
8 | Fluctuation of material prices | Bitamba and An [12] |
9 | Substituting material price | Bitamba and An [12] |
10 | Poor handling of material on-site | Yap and Tan [50] |
11 | Delays/Problems in delivery of materials or goods due to faults of the owner | Wu et al. [7] |
Level 2: Availability and Variety of Materials | ||
1 | Unavailability of necessary materials on-site | Jarkas and Mubarak [18], Alaghbari et al. [49], Project 3 |
2 | Delay in the selection of materials due to the existence of many choices | Kumar [28], Assaf and Al-Hejji [23] |
3 | Shortage of construction materials in the market | Kumar [28], Enshassi et al. [35], Alshihri et al. [29], Alaghbari et al. [49], Prasad et al. [63] |
Level 2: Storage of Materials in the Construction Site | ||
1 | Problems in material storage | Lee et al. [60], Alshihri et al. [29] |
2 | Damage to materials during storage | Kumar [28], Alshihri et al. [29], Yates [55] |
3 | Unforeseen material damages | Lee et al. [60], Lerche et al. [67] |
4 | Lack of information about available materials | Enshassi et al. [35], Perera et al. [68], Keane et al. [64], Badawy [14] |
Level 2: Quality of Procured Materials | ||
1 | Materials in incompliant with specifications | Bitamba and An [12], Lee et al. [60], Mahamid [5] |
2 | Rejected material | Rahman et al. [6] |
3 | Poor quality of materials | Lerche et al. [67], Rahman et al. [6], Ajayi and Chinda [48], Yates [55] |
4 | Changes in material specifications during construction | Rahman et al. [6], Yap et al. [31] |
5 | Problems with new materials | Rahman et al. [6], Padala et al. [3], Sun and Meng [21], Project 2, Project 4 |
6 | Changes in material types during construction | Rahman et al. [6], Ajayi and Chinda [48], Kumar [28] |
7 | Replacement/Substitution of materials | Rahman et al. [6], Mohammad et al. [4], Keane et al. [64] |
8 | Material changes due to shortage of particular material in the market | Choudhry et al. [69] |
Level 1: Other resources | ||
Level 2: Procurement and Delivery of Equipment and Machines | ||
1 | Equipment delivery problem | Ajayi and Chinda [48], Yates [55] |
2 | Improper handling of machinery and equipment | Yap and Tan [50], Yap et al. [42] |
3 | Wrong selection | Chan and Kumaraswamy [20], Padala et al. [3] |
4 | Delay in manufacturing special building equipment | Alshihri et al. [29], Rashid et al. [57] |
5 | Procurement of poor qualified equipment | Yates [55] |
Level 2: Availability of Equipment and Machines in the Market | ||
1 | Lack of appropriate equipment/tools | Bitamba and An [12], Yates [55] |
2 | Lack of equipment/tools | Mohammad et al. [4], Bitamba and An [12], Gunduz et al. [70] |
3 | Lack of specified products | Rashid et al. [57] |
4 | Lack of new and high-technology mechanical equipment | Altaf et al. [53], Almasi et al. [71] |
5 | Lack of knowledge about available equipment | Perera et al. [68], Badawy [14], Enshassi et al. [35] |
6 | Lack of spare parts | Enshassi et al. [35] |
Level 2: Repair and Maintenance Capabilities | ||
1 | Lack of repair facilities for equipment and tools | Ajayi and Chinda [48], Chan and Kumaraswamy [20], Yates [55] |
2 | Lack of maintenance facilities for equipment and tools | Yap et al. [42] |
Level 2: Productivity of Machines and Equipment | ||
1 | Insufficient productivity of equipment | Mahamid [5], Chan and Kumaraswamy [20], Gunduz et al. [70] |
2 | Poor qualified equipment used for the works | Waty and Sulistio [32], Alshihri et al. [29], Gunduz et al. [70] |
3 | Inadequate modern equipment | Gunduz et al. [70] |
Level 2: Quality of Machines and Equipment | ||
1 | Poor standard of machinery and equipment | Yap et al. [42], Yates [55] |
2 | Improper/Wrong tools for materials | Yates [55] |
3 | Frequent equipment breakdowns | Gunduz et al. [70] |
Level 1: Financial Factors | ||
Level 2: Cashflows | ||
1 | Delays in contractor’s progress payments | Alshihri et al. [29], Yap and Tan [50], Maqbool and Rashid [62], Ajayi and Chinda [48], Marzouk and El-Rasas [56], Project 4, Project 5, Project 6 |
2 | Additional payments to the contractor | Famadico and Baccay [72], Perera et al. [68] |
3 | Late payment to the subcontractor by the main contractor | Almasi et al. [71], Prasad et al. [63] |
4 | Delay of retention payment | Gunduz and Mohammad [73], Ajayi and Chinda [48] |
Level 2: Financing Conditions | ||
1 | Poor project financing | Chan and Kumaraswamy [20] |
2 | Failure to finance the project on time/financing difficulties | Faten Albtoush et al. [74] |
3 | Funding changes | Faten Albtoush et al. [74] |
4 | Lack of owner’s finance | Afelete and Jung [9] |
5 | Financial constraints faced by the owner | Yap et al. [31], Aljassmi et al. [75] |
6 | Contractor’s financial difficulties | Alshihri et al. [29], Mohammad et al. [4], Hanif et al. [76], Enshassi et al. [35], Rashid et al. [57], Keane et al. [64] |
7 | Owner’s financial difficulties | Faten Albtoush et al. [74], Ismail et al. [10], Mahamid [5], Rashid et al. [57], Keane et al. [64], Project 1, Project 2, Project 4, Project 5, Project 6 |
8 | Problems in cash flow management | Rahman et al. [6], Maqbool and Rashid [62], Alshihri et al. [29] |
9 | Contractor’s financial obligations | Balbaa et al. [77], Faten Albtoush et al. [74] |
10 | Bankruptcy by contractor/subcontractor or supplier | Yang and Chen [78], Sun and Meng [21], Afelete and Jung [9], Yates [55] |
11 | Subcontractor’s financial difficulties | Rahman et al. [6], Project 6 |
12 | Owner’s/contractor’s cash flow problem | Rahman et al. [6], Aljohani et al. [79] |
Level 2: Resource Costs | ||
1 | Change in material costs applied by a supplier | Peansupap and Cheang [80], Aljohani et al. [79] |
2 | A wide variety of labor costs | Rahman et al. [6], Aljohani et al. [79], Project 5 |
3 | Wide variety of equipment and machinery costs (e.g., first cost, rent) | Project 1, Project 4 |
4 | High material costs | Project 3, Project 4 |
Level 2: Contract and Overhead Costs | ||
1 | Wide variety of overhead costs | Maqbool and Rashid [62], Rahman et al. [6], Project 2 |
Level 1: External factors | ||
Level 2: Weather | ||
1 | Extreme hot weather | Ezenta [81] |
2 | Weather changes | Bakr [82], Mohammad et al. [4] |
3 | Humidity effect on construction activities | Jarkas and Mubarak [18], Ballesteros-Pérez et al. [83], Yates [55] |
4 | Inclement weather effect on construction activities | Hao et al. [84], Jarkas and Mubarak [18] |
5 | Wind effect on construction activities | Lerche et al. [67], Dosumu and Aigbavboa [66] |
6 | Rain/snow effect on construction activities | Wu et al. [7], Dosumu and Aigbavboa [66], Yates [55], Project 2 |
7 | Extreme cold weather effect on construction activities | Ezenta [81], Yates [55] |
8 | Blizzards | Wu et al. [7], Sun and Meng [21] |
9 | Storms | Ballesteros-Pérez et al. [83] |
10 | Hurricanes/Cyclones/Tornadoes | Okada et al. [43] |
Level 2: Catastrophes | ||
1 | Artificial/Manmade disasters | Wu et al. [7] |
2 | Earthquakes | Sun and Meng [21], Okada et al. [43], Almasi et al. [71], Marzouk and El-Rasas [56] |
3 | Landslides | Waty and Sulistio [32], Hsieh et al. [85] |
4 | Volcanic eruptions | Wu et al. [7], Sun and Meng [21] |
5 | Floods | Hsieh et al. [85], Waty and Sulistio [32], Sun and Meng [21] |
6 | Limnic eruptions | Sun and Meng [21], Wu et al. [7] |
7 | Tsunamis | Sun and Meng [21], Wu et al. [7] |
8 | Droughts | Sun and Meng [21], Wu et al. [7] |
9 | Wildfires | Sun and Meng [21], Wu et al. [7] |
10 | Avalanches | Sun and Meng [21], Wu et al. [7] |
11 | Soil settlement | Hsieh et al. [85], Waty and Sulistio [32] |
Level 2: Environmental Problems | ||
1 | Environmental protection and mitigation costs | Sun and Meng [21], Waty and Sulistio [32] |
2 | Problems due to site pollution and noise | Padala et al. [3], Arditi et al. [45] |
3 | Environmental concerns and restrictions | Chan and Kumaraswamy [20], Yates [55] |
4 | Conservation restrictions | Sun and Meng [21], Marzouk and El-Rasas [56] |
Level 2: Security Problems | ||
1 | Poor site security | Hsieh et al. [85] |
2 | Theft/Vandalism inside the site | Waty and Sulistio [32] |
Level 1: Health and Safety Concerns | ||
Level 2: Safety Concerns | ||
1 | Poor safety conditions | Sun and Meng [21], Arditi et al. [45] |
2 | Accidents during construction | Kumar [28], Abd El-Razek et al. [86], Mpofu et al. [87] |
3 | Unsafe practices during construction | Rahman et al. [6] |
4 | Damage to structure | Abd El-Razek et al. [86] |
5 | Lateness in safety facilities reinforcement | Hsieh et al. [85] |
6 | Failure to meet safety rules and regulations | Balbaa et al. [77], Sweis et al. [61] |
7 | Lack of safety rules and regulations | Balbaa et al. [77] |
8 | Residential safety | Wu et al. [7] |
9 | Work incidents | Wu et al. [7], Chang [88] |
Level 2: Health Concerns | ||
1 | Epidemics | Alshihri et al. [29], Trauner et al. [89] |
2 | Pandemics | Alshihri et al. [29], Nguyen and Do [90] |
3 | Endemics | Yap and Tan [50] |
4 | High noise level | Padala et al. [3] |
5 | Labor injuries | Safapour et al. [41] |
Level 1: Project Location | ||
Level 2: Ground Conditions | ||
1 | Unexpected foundation conditions | Wu et al. [7] |
2 | Incomplete geological survey/information | Wu et al. [7] |
3 | Groundwater location | Wu et al. [7] |
4 | Unexpected underground conditions (geological issues/groundwater level issues, etc.) | Wu et al. [7], Marzouk and El-Rasas [56] |
5 | Changes in geological conditions | Wu et al. [7], Abad et al. [91] |
6 | Uncertainty in locating pipe positions underground | Wu et al. [7] |
7 | Archaeology findings (unexpected archaeological finds) | Lee et al. [60], Lee [92] |
8 | Conflict with existing underground utilities | Shrestha et al. [93], Prasad et al. [63] |
9 | Unanticipated underground utilities | Okada et al. [43], Yap et al. [31] |
10 | Insufficient soil investigation | Yap et al. [31] |
11 | Unforeseen ground conditions (rock, acid, sediment basin) | Yap et al. [31], Sun and Meng [21], Annamalaisami and Kuppuswamy [94] |
12 | Unexpected ground elevation and landform | Wu et al. [7] |
13 | Changes in site location | Padala et al. [3] |
Level 2: Site Condition and Restrictions | ||
1 | Poor investigation of project location | Rahman et al. [6], Altaf et al. [53], Abad et al. [91], Project 5 |
2 | Changes in site conditions due to the contractor | Wu et al. [7] |
3 | Differing site conditions | Enshassi et al. [35], Hilali et al. [58], Rashid et al. [57] |
4 | Discrepancies between the survey and existing on-site conditions | Wu et al. [7] |
5 | Unforeseen site conditions | Afelete and Jung [9], Motawa et al. [95], Arditi et al. [45] |
6 | Poor traffic control regulation and inadequate restriction | Assaf and Al-Hejji [23], Marzouk and El-Rasas [56] |
7 | Poor site storage capacity | Lee et al. [60], Arditi et al. [45] |
8 | Overcrowded work area/Congestion | Padala et al. [3], Sun and Meng [21] |
9 | Poor site layout | Padala et al. [3], Arditi et al. [45] |
10 | Problems due to site restrictions | Rahman et al. [6], Wu et al. [7] |
11 | Inconsistency between drawings and site conditions | Hsieh et al. [85], Abad et al. [91] |
Level 2: Accessibility and Possession | ||
1 | Late delivery of the construction site to the contractor | Wu et al. [7], Marzouk and El-Rasas [56], Project 5 |
2 | Difficulty in site acquisition | Sun and Meng [21] |
3 | Expropriation costs (underestimated expropriation costs) | Wu et al. [7], Lee [92] |
4 | Restricted access to the site | Rashid et al. [57] |
5 | Negligence of Employer regarding egress and entrance | Sun and Meng [21] |
6 | Failure of the employer to provide right of way | Wu et al. [7] |
Level 1: Project Stakeholders | ||
Level 2: Project Stakeholders’ Competence and Experience | ||
1 | Lack of owner’s technical knowledge | Afelete and Jung [9], Alaghbari et al. [49] |
2 | Lack of experience of the owner in construction projects | Afelete and Jung [9], Heravi and Charkhakan [96], Ameyaw et al. [97] |
3 | Lack of technical knowledge of the consultant | Afelete and Jung [9], Keane et al. [64] |
4 | Consultant’s inability | Yap et al. [98], Chang [88] |
5 | Inexperienced consultant | Rahman et al. [6], Yap et al. [31], Marzouk and El-Rasas [56] |
6 | Inadequate contractor experience | Chan and Kumaraswamy [20], Yap et al. [99] |
7 | Lack of experience with the type of project | Yap et al. [99], Annamalaisami and Kuppuswamy [94] |
8 | Lack of experience in the project location | Annamalaisami and Kuppuswamy [94] |
9 | Unfamiliarity of contractor with local regulations | Rahman et al. [6], Yap et al. [99], Annamalaisami and Kuppuswamy [94] |
10 | Incompetent project team | Rahman et al. [6] |
11 | Lack of experience in the contract | Annamalaisami and Kuppuswamy [94] |
12 | Inadequate design-team experience | Heravi and Charkhakan [96], Chan and Kumaraswamy [20], Lopez et al. [100] |
13 | Lack of training programs offered to the design team | Assaf and Al-Hejji [23] |
14 | Inexperienced subcontractors | Rahman et al. [6], Jarkas and Mubarak [18], Project 3, Project 6 |
15 | Unfamiliarity with local conditions | Badawy [14], Keane et al. [64] |
16 | Insufficient training of designers | Yang and Wei [101] |
Level 2: Project Stakeholders’ Expectations | ||
1 | Unrealistic time/cost/quality targets of owner | Do et al. [102], Jarkas and Mubarak [18] |
2 | Unrealistic owner expectations | Shoar et al. [51] |
3 | Contractor’s desire to improve his financial situation | Mohammad et al. [4], Pourrostam et al. [103] |
4 | Unrealistic information expectations by the contractor | Do et al. [102] |
5 | Special owner requirements | Wu et al. [104] |
6 | Unclear owner’s needs during the design stage | Alnuaimi et al. [37], Project 1 |
7 | Owner’s unclear requirements | Mpofu et al. [87], Arditi et al. [45] |
8 | Growing needs of parties | Chang et al. [105], Chang [88] |
9 | Major changes in requirements | Yap et al. [31] |
10 | Changes in owner’s requirements | Enshassi et al. [35], Yang and Wei [101] |
11 | The design engineer’s misunderstanding of the owner’s requirements | Kumar [28], Assaf and Al-Hejji [23], Arefazar et al. [19] |
Level 2: Culture and Ethics | ||
1 | Owner or contractor’s disregard for the terms of the contract | Abd El-Razek et al. [86], Aljohani et al. [79], Prasad et al. [63] |
2 | Misuses of variations instructions by the contractor | Alnuaimi et al. [37] |
3 | Personality clashes between the parties | Do et al. [102], Lavikka et al. [15] |
4 | Uncooperative owner | Mpofu et al. [87] |
5 | Fraudulent behavior of the contractor and consultant | Alshihri et al. [29], Shoar et al. [51], Arditi et al. [45] |
6 | Existence of opportunistic behavior among project parties | Charkhakan and Heravi [106], Shoar et al. [51] |
7 | Inflexibility (rigidity) of consultant/client | Assaf and Al-Hejji [23], Alshihri et al. [29] |
8 | Issues regarding personality type | Safapour et al. [41] |
9 | Obstinate nature of employer | Badawy [14], Arefazar et al. [19], Keane et al. [64] |
Level 1: Project Management | ||
Level 2: Construction Site Management | ||
1 | Inadequate of contractor’s site management capability | Chan and Kumaraswamy [20] |
2 | Poor project management by contractor | Varghese et al. [107], Bitamba and An [12], Alnuaimi et al. [37] |
3 | Inadequate/poor project management assistance by consultant | Jarkas and Mubarak [18] |
4 | Untrained and inexperienced project management team | Safapour and Kermanshachi [108], Olawale and Sun [109] |
5 | The project manager’s inappropriate leadership style | Chan and Kumaraswamy [20], Almasi et al. [71], Arditi et al. [45] |
6 | Contractor’s inappropriate management style | Chan and Kumaraswamy [20], Maqbool and Rashid [62] |
7 | Unavailability of professional construction management | Kumar [28], Ramanathan et al. [110] |
8 | Poor site/project management skills | Sun and Meng [21] |
9 | Slow site clearance due to restrictions | Kumar [28], Ramanathan et al. [110] |
10 | Contractor’s poor site management | Alshihri et al. [29], Jarkas and Mubarak [18], Assaf and Al-Hejji [23] |
11 | Failure of the contractor/project manager to use the tools to manage the project symmetrically | Toor and Ogunlana [59], Arditi et al. [45] |
12 | Inaccurate site investigation by consultant | Ilter and Celik [111], Annamalaisami and Kuppuswamy [94] |
13 | Poor quality of site documentation | Lavikka et al. [15] |
14 | Improper control over site resource allocation | Chan and Kumaraswamy [20], Maqbool and Rashid [62], Faridi and El-Sayegh [112] |
15 | Lack of project management group | Faridi and El-Sayegh [112] |
16 | The contractor and his staff focus on other projects | Choudhry et al. [69] |
17 | Failure to provide adequate protection for materials and completed works | Yap et al. [42] |
18 | Labors re-allocation to other projects | Mahamid [5] |
Level 2: Project Quality Management | ||
1 | Delays in consultant’s site inspection | Alshihri et al. [29], Mpofu et al. [87], Prasad et al. [63] |
2 | Long waiting time for sample materials approval | Alshihri et al. [29], Mpofu et al. [87], Faridi and El-Sayegh [112] |
3 | Weak quality control and supervision consulting company | Charkhakan and Heravi [106] |
4 | Poor inspection and supervision by the contractor | Alshihri et al. [29], Jarkas and Mubarak [18], Assaf and Al-Hejji [23] |
5 | Long waiting time for approval of quality control tests or results due to the consultant | Faridi and El-Sayegh [112] |
6 | The consultant’s poor inspection and testing procedure | Rahman et al. [6], Faridi and El-Sayegh [112] |
7 | Consultant’s slow response to quality procedures | Rahman et al. [6], Sweis et al. [61] |
8 | Inefficient quality assurance and quality control | Lopez et al. [100], Safapour et al. [41], Alshihri et al. [29], Yates [55] |
9 | Lack of quality assurance of materials | Varghese et al. [107] |
10 | Long waiting time for confirmation of test samples and delivered materials due to consultant | Chan and Kumaraswamy [20] |
11 | Delay in performing the final audit and issuing certification by a third party | Assaf and Al-Hejji [23], Kumar [28], Marzouk and El-Rasas [56], Bramble and Callahan [113] |
12 | Poor consultant’s supervision | Alnuaimi et al. [37], Jadhav and Bhirud [114] |
13 | Inadequate value engineering | Keane et al. [64], Yap et al. [31], Shoar et al. [51], Balbaa et al. [77] |
Level 2: Project Time Management | ||
1 | Changes in project schedule | Mohammad et al. [4], Hanif et al. [76] |
2 | Inexperienced contractor in planning and controlling the project schedule | Chan and Kumaraswamy [20] |
3 | Underestimation of the complexity of the project | Bajjou and Chafi [115] |
4 | Non-availability of overall project planning | Alnuaimi et al. [37], Waty and Sulistio [32] |
5 | Overestimation of the labor productivity | Chanmeka et al. [116], Faridi and El-Sayegh [112] |
6 | Underestimation of quantities | Ameyaw et al. [97], Yates [55] |
7 | Failure to plan and schedule projects effectively by the contractor | Alshihri et al. [29], Assaf and Al-Hejji [23] |
8 | Nonavailability of records of similar projects | Kumar [28], Alnuaimi et al. [37] |
9 | Inexperienced experts in estimating time and resources | Ramanathan et al. [110] |
10 | Unrealistic design periods | Alnuaimi et al. [37], Jadhav and Bhirud [114] |
11 | Unrealistic or insufficient construction schedule | Alnuaimi et al. [37], Padala et al. [3], Yates [55] |
12 | Contractors’ planning and scheduling problems | Bajjou and Chafi [115] |
13 | Inaccurate evaluation of project time/duration | Frimpong et al. [117], Olawale and Sun [109], Yang and Wei [101] |
14 | Inaccurate estimate quantity | Yang and Chen [78], Prasad et al. [63] |
15 | Inadequate early planning of the project | Kumar [28], Jarkas and Mubarak [18], Ramanathan et al. [110], Al-Kharashi and Skitmore [47], Prasad et al. [63] |
16 | Unreasonable/unpractical initial schedule | Arefazar et al. [19] |
17 | Failure to effectively control project progress by the owner | Alshihri et al. [29] |
18 | Contractor’s poor project planning and scheduling process | Gunduz and Khan [118], Mpofu et al. [87], Prasad et al. [63] |
19 | Inefficient/poor work breakdown structure | Al-Kharashi and Skitmore [47] |
20 | Long waiting for information from other parties | Ramanathan et al. [110], Frimpong et al. [117] |
21 | Lack of contractor’s knowledge about planning and scheduling | Chan and Kumaraswamy [20], Maqbool and Rashid [62] |
22 | Conflicts between subcontractors’ and contractor’s schedules | Assaf and Al-Hejji [23] |
23 | Failure to effectively control project progress by the contractor/Inadequate progress review | Al-Kharashi and Skitmore [47], Alshihri et al. [29], Faridi and El-Sayegh [112] |
24 | Inadequate foresight about the nature of the project at the design stage | Alnuaimi et al. [37] |
25 | Unrealistic project schedule/design period | Arditi et al. [45] |
26 | Inappropriate software usage for time management | Olawale and Sun [109] |
27 | Lack of data related to activity duration and resources | Yang and Wei [101], Faridi and El-Sayegh [112], Abd El-Razek et al. [86] |
28 | Unreasonable/unpractical initial plan | Yang and Wei [101] |
Level 2: Project Communication management | ||
1 | Poor communication and coordination between designers | Yap et al. [42], Assaf et al. [119], Yap et al. [31], Jarkas and Mubarak [18], Yang and Wei [101] |
2 | Lack of coordination between international and local designers | Enshassi et al. [35] |
3 | Lack of coordination between contractor and consultant | Mohammad et al. [4] |
4 | Poor communication among the various parties | Do et al. [102], Nguyen and Do [90] |
5 | Lack of coordination and communication with related organizations outside of the project by the client | Charkhakan and Heravi [106] |
6 | Insufficient communication between the owner and designer | Keane et al. [64] |
7 | Poor communication between the designer and other construction parties | Hwang et al. [120] |
8 | Lack of design team involvement in the construction stage | Badawy [14], Arditi et al. [45] |
9 | Lack of contractor’s involvement in design | Keane et al. [64] |
10 | Conflicts between contractors and designers | Grau et al. [121] |
11 | Conflicts amongst consultants with other parties | Niazi and Painting [52] |
12 | Poor communication and coordination between consultants | Yap et al. [31], Padala et al. [3] |
13 | Poor communication and coordination among variousprofessional disciplines | Yap et al. [122] |
14 | Incapability of the owner in coordinating multiple contractors | Yates [55], Bramble and Callahan [113] |
15 | Inadequate pre-design communication | Wu et al. [7] |
16 | Conflicts between co-ownership of the project | Safapour and Kermanshachi [108] |
17 | Conflicts between the owner and other parties | Peansupap and Cheang [80], Olawale and Sun [109] |
18 | Poor communication and coordination between the owner and the consultant | Yap et al. [31] |
19 | Poor communication and coordination between the owner and end users | Yap et al. [31] |
20 | Poor communication and coordination among the project parties | Enshassi et al. [35], Balbaa et al. [77], Faridi and El-Sayegh [112], Marzouk and El-Rasas [56] |
21 | Poor communication and coordination between relevant governmental units and the owner | Alnuaimi et al. [37], Al-Kharashi and Skitmore [47] |
22 | Conflict of perspective between contractor and consultant | Abd El-Razek et al. [86], Alshihri et al. [29] |
23 | Poor communication and coordination between the contractor and other parties | Assaf and Al-Hejji [23] |
24 | Poor communication and coordination between the owner and other parties | Assaf and Al-Hejji [23], Rachid [123] |
25 | Problems in trade coordination | Yates [55] |
26 | Owner’s incomplete/incorrect information | Chang [88] |
27 | Failure of the owner to provide information | Chang [88] |
28 | Inadequate information and supervision by the owner | Yates [55], Mahamid [5] |
29 | Insufficient or poorly integrated baseline project data provided by the owner | Yang and Wei [101] |
30 | Poor collaboration among project team members | Ramanathan et al. [110] |
31 | Insufficient or poorly integrated baseline project data provided by the contractor | Yang and Wei [101] |
32 | Ineffective involvement of the contractor’s head office | Al-Kharashi and Skitmore [47] |
33 | Personal conflicts among labors | Assaf and Al-Hejji [23] |
34 | Labor and management relations | Abd El-Razek et al. [86] |
35 | Unnecessary interference by the owner | Marzouk and El-Rasas [56], Niazi and Painting [52], Bramble and Callahan [113] |
36 | Slow information delivery between designers | Yang and Wei [101] |
37 | Poor information dissemination/provision by consultant | Aibinu and Odeyinka [124] |
38 | Subcontractor interference | Yates [55] |
39 | Insufficient coordination between various departments in utility shifting and placing | Varghese et al. [107] |
40 | Poor communication between site management and the labor force | Jarkas and Mubarak [18] |
Level 2: Project Organization | ||
1 | Delay in issuing the owner’s change orders | Niazi and Painting [52], Project 6 |
2 | Changes in decision-making authority | Chang [88], Project 3 |
3 | Slow decision-making by designers | Yang and Wei [101] |
4 | Delay in revisions made by consultant while construction is in progress | Abd El-Razek et al. [86], Assaf and Al-Hejji [23] |
5 | Delay in the consultant’s interim valuation | Aibinu and Odeyinka [124] |
6 | Owner’s protracted refusal to settle contractor claims | Al-Kharashi and Skitmore [47], Sweis et al. [61] |
7 | Delay in consultant’s valuation of variation works | Aibinu and Odeyinka [124] |
8 | Delayed and slow supervision in making decisions | Alaghbari et al. [49], Frimpong et al. [117] |
9 | Delay in the consultant engineer’s approval of the contractor’s submissions | Sweis et al. [61], Frimpong et al. [117], Aibinu and Odeyinka [124] |
10 | Delay in issuance of the consultant engineer’s instructions | Niazi and Painting [52] |
11 | Slow consultant engineer’s response to contractor inquiries | Sweis et al. [61] |
12 | Problems due to the consultant’s organization | Al-Kharashi and Skitmore [47] |
13 | Slow owner’s responses | Arditi et al. [45] |
14 | Failure of the owner to give timely orders/instructions | Yates [55] |
15 | Excessive bureaucracy arising from owner management | Faridi and El-Sayegh [112], Ramanathan et al. [110], Mpofu et al. [87], Alshihri et al. [29], Yang and Wei [101] |
16 | Slow decision-making process by the owner | Keane et al. [64], Marzouk and El-Rasas [56] |
17 | Insufficient structure linking all parties in the project | Maqbool and Rashid [62], Al-Kharashi and Skitmore [47], Chan and Kumaraswamy [20] |
18 | Slow decision-making process by all project teams | Chan and Kumaraswamy [20], Frimpong et al. [117] |
19 | Slow decision-making within each project team | Chan and Kumaraswamy [20], Frimpong et al. [117] |
20 | Lack of responsibility of project manager/contractor | Arditi et al. [45] |
21 | Lack of contractor’s authority | Arditi et al. [45] |
22 | Lack of timely corrective decisions by contractor/project manager | Arditi et al. [45] |
23 | Slow response from contractor/project manager | Arditi et al. [45] |
24 | Delay in preparation of contractor deliverables | Sweis et al. [61], Al-Kharashi and Skitmore [47] |
25 | Problems arising from the contractor’s company organization | Al-Kharashi and Skitmore [47] |
26 | Unilateral decisions taken by the owner without contractual considerations | Alnuaimi et al. [37], Jadhav and Bhirud [114] |
27 | Contractor’s internal problems | Al-Kharashi and Skitmore [47] |
28 | Consultant’s internal problems | Al-Kharashi and Skitmore [47], Alshihri et al. [29] |
29 | Ill-defined duties and responsibilities by the contractor | Arditi et al. [45] |
30 | Contractor’s inadequate decision-making mechanism | Arditi et al. [45] |
31 | Delay in consultant’s approval of major changes in the scope of work | Al-Kharashi and Skitmore [47], Assaf and Al-Hejji [23], Gunduz et al. [70] |
32 | A large number of participants in the project | Arditi et al. [45] |
33 | Involvement of several contractors/foreign contractors | Arditi et al. [45] |
34 | Project commissioning and ownership transfer | Chang [88] |
35 | Lack of strategic planning | Keane et al. [64], Balbaa et al. [77], Staiti et al. [54], Badawy [14] |
Level 1: Contractual Document and Contract Management | ||
Level 2: Project Scope Management | ||
1 | Technology complexity | Sun and Meng [21], Keane et al. [64] |
2 | Technical challenges | Charles et al. [125] |
3 | Complexity of project | Zadeh et al. [40], Olawale and Sun [109] |
4 | Project characteristics | Chanmeka et al. [116] |
5 | Project size | Khalafallah and Shalaby [126], Chanmeka et al. [116] |
6 | Inadequate project objectives | Badawy [14], Ali Kamal Balbaa et al. [77], Keane et al. [64] |
7 | Inadequate scope of work for contractor | Bakr [82], Mohammad et al. [4] |
8 | Ambiguous scope of work | Safapour and Kermanshachi [108], Tran et al. [127], Nguyen and Do [90] |
9 | Risk and uncertainty associated with projects | Olawale and Sun [109] |
10 | Poor scope definition | Yang and Wei [101], Prasad et al. [63] |
Level 2: Tendering and Project Delivery | ||
1 | Type of project tendering | Assaf and Al-Hejji [23], Bajjou and Chafi [115], Marzouk and El-Rasas [56] |
2 | Type of construction contract | Assaf and Al-Hejji [23] |
3 | Inappropriate choice of project delivery system | Ilter and Çelik [111] |
4 | Inappropriate choice of contract type | Ilter and Çelik [111] |
5 | Lack of contractor’s field visit to the site during the bidding | Alshihri et al. [29] |
6 | Exceptionally low bids | Yap et al. [99], Ilter and Çelik [111], Ramanathan et al. [110], Prasad et al. [63] |
7 | Insufficient time for bid preparation | Enshassi et al. [35] |
8 | Type of construction contract/project delivery system | Choudhry et al. [69], Assaf and Al-Hejji [23] |
9 | Selection of inappropriate type of main construction | Chan and Kumaraswamy [20] |
10 | Inappropriate contractor or consultant selection | İlter and Çelik [111], Arditi et al. [45] |
11 | Non-feasibility of construction methodology | Padala et al. [3] |
12 | Improper project feasibility study | Arditi et al. [45] |
13 | Unclear contract language and translation | Bakr [82] |
14 | Ambiguous contract terms | Ameyaw et al. [97] |
15 | Faulty negotiations and obtaining of contracts | Abd El-Razek et al. [86], Ramanathan et al. [110] |
16 | Improper subcontractor selection | Mahamid [5] |
17 | Low consultancy fee | Alnuaimi et al. [37] |
18 | Client’s late contract award | Aljohani et al. [79], Bramble and Callahan [113] |
19 | Inadequate and unclear information provided by the consultant in the tender documents | Jadhav and Bhirud [114], Alnuaimi et al. [37] |
20 | Contract awarded to the lowest bidder | Alshihri et al. [29], Prasad et al. [63] |
Level 2: Contract Document Management | ||
1 | Unfair risk allocation in contracts | Do et al. [102], Arditi et al. [45] |
2 | Conflicts among contract documents | Bakr [82], Ameyaw et al. [97], Mohammad et al. [4], Enshassi et al. [35] |
3 | The existence of errors and incomplete information in the pricing document | Wu et al. [7] |
4 | Improper or wrong cost estimation | Almasi et al. [71], Prasad et al. [63] |
5 | Errors in contract documents due to the owner | Rashid et al. [57], Günhan et al. [128], Arditi et al. [45] |
6 | Errors in contract documents due to contractor | Rashid et al. [57], Arditi et al. [45] |
7 | Owner’s contract modifications | Günhan et al. [128] |
8 | Unrealistic contract duration imposed in contract | Alshihri et al. [29], Mpofu et al. [87], Marzouk and El-Rasas [56], Prasad et al. [63] |
9 | Existence of gray areas in general conditions and request variations to the contract | Alnuaimi et al. [37] |
10 | Incomplete/erroneous contract documentation | Safapour et al. [41], Yap and Tan [50] |
11 | Misinterpretation of contract documents | Perera et al. [68], Padala et al. [3] |
12 | Poor contract familiarity | Hassanein and El Nemr [129], Hilali et al. [58] |
13 | Difference in contract interpretation | Rashid et al. [57] |
14 | Absence of financial rewards for completing the project earlier | Alshihri et al. [29], Assaf and Al-Hejji [23] |
15 | Ineffective delay penalties in contract | Alshihri et al. [29], Assaf and Al-Hejji [23], Marzouk and El-Rasas [56] |
16 | Inappropriate contact form | Hsieh et al. [85], Toor and Ogunlana [59] |
17 | Ambiguities in contract clauses | Gunduz et al. [70] |
18 | Poor contract administration | Tran et al. [127], Hansen et al. [36] |
19 | Poor contract management by consultant/contractor | Shoar et al. [51], Ilter and Celik [111], Frimpong et al. [117] |
20 | Non-use of professional contract management | Abd El-Razek et al. [86] |
21 | Legal disputes between various parties | Alshihri et al. [29], Assaf and Al-Hejji [23] |
22 | Inaccurate estimates—errors or omissions in quantity estimating/inaccurate bills of quantities | Yap et al. [99] |
23 | Unreasonable estimation and adjustment of the project cost | Maqbool and Rashid [62], Ilter and Celik [111], Lee [92] |
24 | Underestimates or omissions by the consultant | Chang [88] |
25 | Erroneous, incomplete, or inaccurate pricing documents | Wu et al. [104] |
26 | Contract and specification interpretation disagreement | Olawale and Sun [109] |
Level 1: Design Process | ||
Level 2: Problems in Design | ||
1 | Errors and omissions in design | Ismail et al. [10], Jarkas and Mubarak [18], Nguyen and Do [90], Project 1, Project 4 |
2 | Inadequate shop drawing details | Mohammad et al. [4], Staiti et al. [54], Hanif et al. [76], Keane et al. [64] |
3 | Unclear and inadequate details in the drawing | Kumar [28], Assaf and Al-Hejji [23], Keane et al. [64] |
4 | Incomplete/Defective/Poor design drawings, specifications, or documents | Wu et al. [104], Yap et al. [99], Prasad et al. [63], Project 1, Project 2, Project 6 |
5 | Errors and omissions in design documents and specifications | Yap et al. [99], Ilter and Celik [111], Keane et al. [64] |
6 | Citation of inadequate specification | Hsieh et al. [85] |
7 | Poor design quality—improper/wrong/impractical design | Chang et al. [105], Keane et al. [64], Project 6 |
8 | Inconsistency between drawings and site conditions | Hsieh et al. [85], Ilter and Celik [111] |
9 | Errors and discrepancies in design documents | Chan and Kumaraswamy [20], Assaf and Al-Hejji [23], Marzouk and El-Rasas [56] |
10 | Outdated designs and specifications | Yap and Skitmore [8] |
11 | Ineffective design by the consultant | Alnuaimi et al. [37], Jadhav and Bhirud [114] |
12 | Lack of design information | Motawa et al. [95], Peansupap and Cheang [80] |
13 | Poor quality design documentation | Lopez et al. [100] |
14 | Errors/changes in the design criteria provided by the employer | Prasad et al. [63] |
Level 2: Changes in Design | ||
1 | Design function change due to the client’s requirement | Peansupap and Cheang [80], Prasad et al. [63] |
2 | Design changes by consultant | Enshassi et al. [35], Mohammad et al. [4], Keane et al. [64] |
3 | Plan changes by owner/client | Mohammad et al. [4] |
4 | Specification changes by the owner | Gunduz and Khan [118], Enshassi et al. [35], Keane et al. [64] |
5 | Specification changes by the designer | Peansupap and Cheang [80] |
6 | Specification changes by the consultant | Keane et al. [64] |
7 | Change due to poor and incomplete design | Peansupap and Cheang [80] |
8 | Design changes due to inconsistent site conditions | Peansupap and Cheang [80] |
9 | Design changes due to poor brief, errors, and omissions | Peansupap and Cheang [80], Sun and Meng [21], Yang and Chen [78] |
10 | Design changes due to design deficiency | Rashid et al. [57] |
Level 2: Design Procedure | ||
1 | Inadequate data collection before design | Assaf and Al-Hejji [23], Shoar et al. [51] |
2 | Inadequate site investigation before design | Abad et al. [91], Wu et al. [7] |
3 | Poor material/equipment investigation before design | Wu et al. [7], Project 3 |
4 | Problems in the preparation and approval of shop drawings | Assaf and Al-Hejji [23], Jarkas and Mubarak [18], Mpofu et al. [87] |
5 | Conflicts between the designers and foreign designers | Toor and Ogunlana [59], Safapour and Kermanshachi [108], Arditi et al. [45] |
6 | Discrepancy in original design specifications | Dosumu and Aigbavboa [66] |
7 | Non-use of the earned value management method | Lee [92] |
8 | Poor application of standardization in design | Toor and Ogunlana [59], Arditi et al. [45] |
9 | Non-use of advanced engineering design software | Assaf and Al-Hejji [23] |
10 | Delays in the delivery of design information | Chan and Kumaraswamy [20] |
11 | Late revision and approval of design documents by the owner | Bajjou and Chafi [115], Assaf and Al-Hejji [23], Mpofu et al. [87], Marzouk and El-Rasas [56] |
12 | Delays in drawing revision and distribution | Bramble and Callahan [113] |
13 | Delays in approval of drawings | Chan and Kumaraswamy [20], Maqbool and Rashid [62], Ramanathan et al. [110] |
14 | Delays in design document preparation | Chan and Kumaraswamy [20], Assaf and Al-Hejji [23], Mpofu et al. [87], Prasad et al. [63] |
15 | Delays in design error correction | Bramble and Callahan [113] |
16 | Slow consultant’s responses to review and approval of design documents | Assaf and Al-Hejji [23] |
17 | Slow consultant’s responses to preparation and approval of shop drawings | Chan and Kumaraswamy [20], Marzouk and El-Rasas [56] |
18 | Slow owner’s responses to review and approval of design documents, schedules, and materials | Gunduz et al. [70], Al-Kharashi and Skitmore [47] |
19 | Discrepancy between design specification and building code | Mpofu et al. [87] |
20 | Over-design increasing the overall cost | Arditi et al. [45] |
Level 2: Design Properties | ||
1 | Complex interfaces | Lee [92], Prasad et al. [63] |
2 | Complexity of project design | Assaf and Al-Hejji [23], Keane et al. [64] |
3 | Low constructability of design | Choudhry et al. [69], Arditi et al. [45], Prasad et al. [63] |
Level 1: Project Implementation | ||
Level 2: Mobilization of Construction Site | ||
1 | Delay in providing utilities (such as water, and electricity) | Assaf and Al-Hejji [23], Alshihri et al. [29], Marzouk and El-Rasas [56] |
2 | Lack of utilities (such as water, electricity, phone, etc.) on site | Marzouk and El-Rasas [56] |
3 | Lack of temporary facilities (such as office buildings etc.) | Mpofu et al. [87], Arditi et al. [45] |
4 | External work (such as roads, utilities, and public services) due to public obligations | Alaghbari et al. [49] |
5 | Difficulties in obtaining energy (electricity, fuel) | Arditi et al. [45] |
6 | Delay in site mobilization | Assaf and Al-Hejji [23], Alshihri et al. [29], Marzouk and El-Rasas [56] |
7 | Slow mobilization of equipment | Gunduz et al. [70], Project 3 |
8 | Slow mobilization and demobilization of labor | Kumar [28] |
9 | Subcontractor’s slow mobilization | Bajjou and Chafi [115], Ramanathan et al. [110] |
Level 2: Logistics | ||
1 | Transportation delays beyond the control | Alaghbari et al. [49] |
2 | Poor logistic control | Yang and Chen [78], Sun and Meng [21] |
Level 2: Construction Methodology | ||
1 | Problems in the introduction of new construction methodology | Shoar et al. [51], Wu et al. [104], Padala et al. [3], Sun and Meng [21] |
2 | Technology changes | Erdogan et al. [130], Keane et al. [64] |
3 | Changes in construction methodology due to newly emerging site conditions | Wu et al. [7] |
4 | Using outdated construction methodology and technologies | Arditi et al. [45], Alnuaimi et al. [37] |
5 | Improper construction methods/techniques implemented by the contractor | Ajayi and Chinda [48] |
6 | Problems in off-site prefabrication | Chan and Kumaraswamy [20] |
Level 2: Subcontract Management | ||
1 | Unavailability of the construction group | Faridi and El-Sayegh [112] |
2 | Frequent change of subcontractors due to their poor performance | Assaf and Al-Hejji [23], Kumar [28], Niazi and Painting [52] |
3 | Poor subcontract management | Yap et al. [42] |
4 | Poor subcontracting (system) | Chan and Kumaraswamy [20] |
5 | Incapable subcontractor | Alaghbari et al. [49] |
6 | Inexperienced subcontractor | Alaghbari et al. [49] |
7 | Untrustful subcontractors | Gunduz et al. [70] |
8 | Long required time for finding appropriate subcontractors | Abd El-Razek et al. [86] |
9 | Delays in appointing a subcontractor | Sun and Meng [21] |
10 | Degree of subcontracting | Chan and Kumaraswamy [20] |
Level 2: Productivity Issues | ||
1 | Defective workmanship | Mahamid [5], Jarkas and Mubarak [18], Badawy [14] |
2 | Workmanship not meeting the specification | Ismail et al. [10], Mohammad et al. [4] |
3 | Delays in contractor’s field survey | Al-Kharashi and Skitmore [47] |
4 | Delays caused by subcontractor | Faten Albtoush et al. [74] |
5 | Accelerating works | Wu et al. [104] |
6 | Inadequate contractor’s work | Kumar [28] |
7 | Construction errors and defective work | Yap et al. [99] |
8 | Delays in construction activities | Lee [92] |
9 | Excessive scope changes and constructive change orders | Sweis et al. [61], Marzouk and El-Rasas [56], Arditi et al. [45] |
10 | Inappropriate technical work by the contractor during the tender phase | Sweis et al. [61], Prasad et al. [63] |
11 | Errors committed during field construction on site | Ramanathan et al. [110] |
12 | Rework due to errors during construction | Kumar [28], Assaf and Al-Hejji [23], Rachid et al. [123] |
13 | Poor performance of the owner’s workforce | Turner and Turner [131], Yates [55] |
14 | Work suspension by the owner | Assaf and Al-Hejji [23], Maqbool and Rashid [62], Mpofu et al. [87], Sweis et al. [61], Marzouk and El-Rasas [56] |
15 | Low contractor productivity | Sun and Meng [21] |
16 | Poor workmanship | Chan and Kumaraswamy [20], Sun and Meng [21], Ali Kamal Balbaa et al. [77] |
17 | Low subcontractors’ productivity | Bajjou and Chafi [115] |
18 | Interference with other trades (trade stacking) | Hanna et al. [44] |
19 | Inappropriate/Inadequate use (misuse) of material | Niazi and Painting [52] |
20 | Addition/omission of scope | Yap and Skitmore [8] |
21 | Extra works imposed by the owner | Turner and Turner [131] |
22 | Change orders during construction | Alshihri et al. [29] |
23 | Change in scope of work | Ameyaw et al. [97], Keane et al. [64] |
24 | Poorly executed design drawings | Wu et al. [104] |
Level 1: Macro Factors | ||
Level 2: Societal Factors | ||
1 | Nationalization | Kumar [28] |
2 | Residents’ protests may result in modifications or halts to the peripheral details’ construction. | Wu et al. [104] |
3 | Effects of social and cultural factors | Assaf and Al-Hejji [23], Perera et al. [68] |
4 | Labor dispute | Waty and Sulistio [32] |
5 | Civil unrest | Kumar [28] |
6 | Fraudulent practices and kickbacks | Mpofu et al. [87], Prasad et al. [63] |
7 | Public strikes | Almasi et al. [71], Marzouk and El-Rasas [56] |
8 | The effects of changing demographics on labor supply and demand | Sun and Meng [21], Erdogan et al. [130] |
9 | Change in demand | Almasi et al. [71] |
Level 2: Political Factors | ||
1 | Internal political problems | Perera et al. [68], Enshassi et al. [35] |
2 | Political instability | Alshihri et al. [29] |
3 | Political pressure to complete the project ahead of the schedule | Alshihri et al. [29] |
4 | Government intervention | Do et al. [102] |
5 | Government policies | Mpofu et al. [87] |
6 | Wars in region | Alshihri et al. [29], Almasi et al. [71] |
Level 2: Economic Factors | ||
1 | Cycle of economic development and how it affects demand | Sun and Meng [21] |
2 | Economic instability | Alshihri et al. [29], Perera et al. [68] |
3 | Freight/Economic embargoes | Almasi et al. [71] |
4 | Labor, material, and plant price inflation | Padala et al. [3], Sun and Meng [21] |
5 | Market competition | Sun and Meng [21] |
6 | Inflation/Escalation of prices | Alshihri et al. [29], Rahman et al. [6], Arditi et al. [45] |
7 | Import/Export Restrictions | Alshihri et al. [29] |
8 | Price adjustments for commodities in contracts with fixed or unit prices | Alshihri et al. [29], Sweis et al. [61] |
9 | Unforeseeable financial and economic crises | Mpofu et al. [87], Arditi et al. [45] |
10 | Price/Financial fluctuations | Sun and Meng [21] |
11 | Fluctuation of exchange rate/currency | Yap et al. [31], Alshihri et al. [29], Olawale and Sun [109] |
12 | Changes in interest rates | Yap et al. [31], Aljohani et al. [79], Arditi et al. [45] |
13 | Changes in tax rates | Yap et al. [31], Alshihri et al. [29], Annamalaisami and Kuppuswamy [94] |
Level 2: Influence of external stakeholders | ||
1 | Issues brought on by hold-up work | Al-Kharashi and Skitmore [47] |
2 | Difficulties in obtaining work permits from the authorities | Alshihri et al. [29], Varghese et al. [107] |
3 | Previous construction delays by other contractors | Wu et al. [104] |
4 | Problem with adjacent properties | Yap and Skitmore [8], Ramanathan et al. [110] |
5 | Work damaged by others | Lerche et al. [67] |
6 | Associated causes | Wu et al. [7] |
7 | Opposition of neighboring community | Sun and Meng [21], Padala et al. [3], Arefazar et al. [19] |
8 | Residential requirements | Padala et al. [3] |
9 | Changes made due to modifications by other organizations | Wu et al. [104], Sun and Meng [21] |
10 | Non-cooperation from labor unions | Arditi et al. [45] |
11 | Routine of government authorities | Mpofu et al. [87] |
12 | Lack of cooperation from local authorities | Arditi et al. [45] |
Level 2: Rules and Regulations | ||
1 | Acquiring required permits/approvals from the municipality/different government authorities | Sun and Meng [21], Alshihri et al. [29], Mpofu et al. [87], Marzouk and El-Rasas [56] |
2 | New government regulations | Ismail et al. [10], Mahamid [5] |
3 | Obtaining (working) permits for laborers | Sweis et al. [61], Ramanathan et al. [110] |
4 | Legislative or policy changes | Erdogan et al. [130], Padala et al. [3] |
5 | Lack of engineering licenses to protect the quality of consulting services | Alnuaimi et al. [37] |
6 | Lack of construction guidelines and procedures | Alnuaimi et al. [37] |
7 | Changes owing to policy or regulations changes | Wu et al. [7] |
8 | Changes in legislation on employment, and working conditions | Sun and Meng [21] |
9 | Changes in government policies (environmental protection, sustainability, waste recycling, brownfield use, etc.) | Sun and Meng [21], Yap and Skitmore [8] |
10 | Weak regulation and control | Olawale and Sun [109] |
11 | Change in Laws | Annamalaisami and Kuppuswamy [94], Perera et al. [68], Yap and Skitmore [8] |
12 | Quarantine restrictions | Trauner et al. [89] |
13 | Changes in government regulations | Perera et al. [68], Do et al. [102], Yap and Skitmore [8], Sweis et al. [61] |
14 | Obtaining transportation permit | Faridi and El-Sayegh [112] |
15 | Building permit approval process | Abd El-Razek et al. [86] |
16 | Prevention of contractor’s resource | Turner and Turner [131] |
17 | Procurement problems due to statutory actions | Turner and Turner [131] |
18 | A body’s statutory obligations | Turner and Turner [131] |
19 | Legal issues because of existing rules and regulations | Toor and Ogunlana [59] |
20 | Challenges in acquiring construction licenses | Arditi et al. [45] |
21 | Changes in standards/norms | Lee [92] |
References
- Ibbs, C.W.; Wong, C.K.; Kwak, Y.H. Project Change Management System. J. Manag. Eng. 2001, 17, 159–165. [Google Scholar] [CrossRef]
- Senaratne, S.; Sexton, M.G. Role of Knowledge in Managing Construction Project Change. Eng. Constr. Archit. Manag. 2009, 16, 186–200. [Google Scholar] [CrossRef]
- Padala, S.P.S.; Maheswari, J.U.; Hirani, H. Identification and Classification of Change Causes and Effects in Construction Projects. Int. J. Constr. Manag. 2020, 14, 2788–2807. [Google Scholar] [CrossRef]
- Mohammad, N.; Ani, A.I.C.; Rakmat, R.; Yusof, M.A. Investigation on the Causes of Variation Orders in the Construction of Building Project–a Study in the State of Selangor, Malaysia. J. Build. Perform. 2010, 1, 12010. [Google Scholar]
- Mahamid, I. Effect of Change Orders on Rework in Highway Projects in Palestine. J. Financ. Manag. Prop. Constr. 2017, 22, 62–76. [Google Scholar] [CrossRef]
- Rahman, I.A.; Al Ameri, A.E.S.; Memon, A.H.; Al-Emad, N.; Alhammadi, A.S.A.M. Structural Relationship of Causes and Effects of Construction Changes: Case of UAE Construction. Sustainability 2022, 14, 596. [Google Scholar] [CrossRef]
- Wu, C.; Hsieh, T.; Cheng, W. Statistical Analysis of Causes for Design Change in Highway Construction on Taiwan. Int. J. Proj. Manag. 2005, 23, 554–563. [Google Scholar] [CrossRef]
- Yap, J.B.H.; Skitmore, M. Investigating Design Changes in Malaysian Building Projects. Archit. Eng. Des. Manag. 2018, 14, 218–238. [Google Scholar] [CrossRef]
- Afelete, E.; Jung, W. Causes of Design Change Depending on Power Project-Types in Ghana. Energies 2021, 14, 6871. [Google Scholar] [CrossRef]
- Ismail, A.; Pourrostam, T.; Soleymanzadeh, A.; Ghouyounchizad, M. Factors Causing Variation Orders and Their Effects in Roadway Construction Projects. Res. J. Appl. Sci. Eng. Technol. 2012, 4, 4969–4972. [Google Scholar]
- Khalifa, W.M.A.; Mahamid, I. Causes of Change Orders in Construction Projects. Technol. Appl. Sci. Res. 2019, 9, 4956–4961. [Google Scholar] [CrossRef]
- Bitamba, B.F.; An, S.H. Construction Project Change Management in the Democratic Republic of the Congo: Status, Causes, and Impacts. Sustainability 2020, 12, 9766. [Google Scholar] [CrossRef]
- Alameri, A.; Rahman, I.A.; Nasaruddin, N.A.N. Ranking of Factors Causing Construction Project Changes in Uae Mega Construction Projects. Int. J. Sustain. Constr. Eng. Technol. 2020, 11, 1–6. [Google Scholar]
- Badawy, M. Second-Order Confirmatory Factor Analysis Model for Estimating the Overall Risk of Change Orders in Road Projects. J. Eng. Des. Technol. 2022, 20, 1217–1235. [Google Scholar] [CrossRef]
- Lavikka, R.H.; Kyrö, R.; Peltokorpi, A.; Särkilahti, A. Revealing Change Dynamics in Hospital Construction Projects. Eng. Constr. Archit. Manag. 2019, 26, 1946–1961. [Google Scholar] [CrossRef]
- Taylor, T.R.B.; Uddin, M.; Goodrum, P.M.; McCoy, A.; Shan, Y. Change Orders and Lessons Learned: Knowledge from Statistical Analyses of Engineering Change Orders on Kentucky Highway Projects. J. Constr. Eng. Manag. 2012, 138, 1360–1369. [Google Scholar] [CrossRef]
- Arrain, F.M. Critical Causes of Changes in Oil and Gas Construction Projects in Alberta, Canada. Proc. Annu. Conf. Can. Soc. Civ. Eng. 2011, 3, 1836–1845. [Google Scholar]
- Jarkas, A.M.; Mubarak, S.A. Causes of Construction Change Orders in Qatar: Contractors’ Perspective. Int. J. Proj. Organ. Manag. 2016, 8, 275–299. [Google Scholar] [CrossRef]
- Arefazar, Y.; Nazari, A.; Hafezi, M.R.; Maghool, S.A.H. Prioritizing Agile Project Management Strategies as a Change Management Tool in Construction Projects. Int. J. Constr. Manag. 2022, 22, 678–689. [Google Scholar] [CrossRef]
- Chan, D.W.M.; Kumaraswamy, M.M. A Comparative Study of Causes of Time Overruns in Hong Kong Construction Projects. Int. J. Proj. Manag. 1997, 15, 55–63. [Google Scholar] [CrossRef]
- Sun, M.; Meng, X. Taxonomy for Change Causes and Effects in Construction Projects. Int. J. Proj. Manag. 2009, 27, 560–572. [Google Scholar] [CrossRef]
- Mansfield, N.R.; Ugwu, O.O.; Doran, T. Causes of Delay and Cost Overruns in Nigerian Construction Projects. Int. J. Proj. Manag. 1994, 12, 254–260. [Google Scholar] [CrossRef]
- Assaf, S.A.; Al-Hejji, S. Causes of Delay in Large Construction Projects. Int. J. Proj. Manag. 2006, 24, 349–357. [Google Scholar] [CrossRef]
- Nyumba, T.O.; Wilson, K.; Derrick, C.J.; Mukherjee, N. The Use of Focus Group Discussion Methodology: Insights from Two Decades of Application in Conservation. Methods Ecol. Evol. 2018, 9, 20–32. [Google Scholar] [CrossRef]
- Budayan, C.; Okudan, O.; Dikmen, I. Identification and Prioritization of Stage-Level KPIs for BOT Projects—Evidence from Turkey. Int. J. Manag. Proj. Bus. 2020, 13, 1311–1337. [Google Scholar] [CrossRef]
- Krueger, R.A.; Casey, M.A. Focus Groups: A Practical Guide for Applied Research; Sage Publications: Thousand Oaks, CA, USA, 2014; ISBN 1483365239. [Google Scholar]
- Groves, R.M.; Fowler, F.J., Jr.; Couper, M.P.; Lepkowski, J.M.; Singer, E.; Tourangeau, R. Survey Methodology; John Wiley & Sons: Hoboken, NJ, USA, 2011; ISBN 1118211340. [Google Scholar]
- Kumar, D. Causes and Effects of Delays in Indian Construction Projects. Int. Res. J. Eng. Technol. 2016, 3, 1831–1837. [Google Scholar]
- Alshihri, S.; Al-Gahtani, K.; Almohsen, A. Risk Factors That Lead to Time and Cost Overruns of Building Projects in Saudi Arabia. Buildings 2022, 12, 902. [Google Scholar] [CrossRef]
- Gurgun, A.P.; Koc, K.; Kunkcu, H. Exploring the Adoption of Technology against Delays in Construction Projects. Eng. Constr. Archit. Manag. 2023. ahead-of-print. [Google Scholar] [CrossRef]
- Yap, J.B.H.; Abdul-Rahman, H.; Wang, C.; Skitmore, M. Exploring the Underlying Factors Inducing Design Changes during Building Production. Prod. Plan. Control 2018, 29, 586–601. [Google Scholar] [CrossRef]
- Waty, M.; Sulistio, H. Causes for the Change Orders in Road Construction: Reviewed from Owner. Commun. Sci. Lett. Univ. Zilina 2022, 24, D72–D84. [Google Scholar] [CrossRef]
- Alraie, A.A.; Ali Kadhum, A.M.; Shabbar, R. Causes of Change Orders in the Cycle of Construction Project: A Case Study in Al-Najaf Province. Open Eng. 2022, 12, 799–807. [Google Scholar] [CrossRef]
- Assaf, S.; Hassanain, M.A.; Abdallah, A.; Sayed, A.M.Z.; Alshahrani, A. Significant Causes of Claims and Disputes in Construction Projects in Saudi Arabia. Built Environ. Proj. Asset Manag. 2019, 9, 597–615. [Google Scholar] [CrossRef]
- Enshassi, A.; Arain, F.; Al-Raee, S. Causes of Variation Orders in Construction Projects in the Gaza Strip. J. Civ. Eng. Manag. 2010, 16, 540–551. [Google Scholar] [CrossRef]
- Hansen, S.; Rostiyanti, S.F.; Rif’at, A. Causes, Effects, and Mitigations Framework of Contract Change Orders: Lessons Learned from GBK Aquatic Stadium Project. J. Leg. Aff. Disput. Resolut. Eng. Constr. 2020, 12, 05019008. [Google Scholar] [CrossRef]
- Alnuaimi, A.S.; Taha, R.A.; Al Mohsin, M.; Al-Harthi, A.S. Causes, Effects, Benefits, and Remedies of Change Orders on Public Construction Projects in Oman. J. Constr. Eng. Manag. 2010, 136, 615–622. [Google Scholar] [CrossRef]
- Mejlænder-Larsen, Ø. Using a Change Control System and Building Information Modelling to Manage Change in Design. Archit. Eng. Des. Manag. 2017, 13, 39–51. [Google Scholar] [CrossRef]
- Likhitruangsilp, V.; Handayani, T.N.; Ioannou, P.G.; Yabuki, N. A BIM-Enabled System for Evaluating Impacts of Construction Change Orders. In Proceedings of the Construction Research Congress 2018, New Orleans, LA, USA, 2–4 April 2018; pp. 622–631. [Google Scholar]
- Zadeh, M.T.; Dehghan, R.; Ruwanpura, J.Y.; Jergeas, G. Factors Influencing Design Changes in Oil and Gas Projects. Int. J. Constr. Eng. Manag. 2014, 3, 117–133. [Google Scholar]
- Safapour, E.; Kermanshachi, S.; Taneja, P.; Pamidimukkala, A. Exploratory Analysis of Human-, Organizational-, and Project-Based Reworks: Challenges and Strategies. J. Leg. Aff. Disput. Resolut. Eng. Constr. 2022, 14, 04521045. [Google Scholar] [CrossRef]
- Yap, J.B.H.; Rou Chong, J.; Skitmore, M.; Lee, W.P. Rework Causation That Undermines Safety Performance during Production in Construction. J. Constr. Eng. Manag. 2020, 146, 04020106. [Google Scholar] [CrossRef]
- Okada, R.C.; Simons, A.E.; Sattineni, A. Owner-Requested Changes in the Design and Construction of Government Healthcare Facilities. Procedia Eng. 2017, 196, 592–606. [Google Scholar] [CrossRef]
- Hanna, A.S.; Camlic, R.; Peterson, P.A.; Nordheim, E.V. Quantitative Definition of Projects Impacted by Change Orders. J. Constr. Eng. Manag. 2002, 128, 57–64. [Google Scholar] [CrossRef]
- Arditi, D.; Akan, G.T.; Gurdamar, S. Reasons for Delays in Public Projects in Turkey. Constr. Manag. Econ. 1985, 3, 171–181. [Google Scholar] [CrossRef]
- Waney, E.Y.V.; Wala, M.M.; Kapoh, H. Development of Model for Controlling Contract Change Order in Pier Project (Case Study in North Sulawesi, Indonesia). ARPN J. Eng. Appl. Sci. 2017, 12, 1359–1368. [Google Scholar]
- Al-Kharashi, A.; Skitmore, M. Causes of Delays in Saudi Arabian Public Sector Construction Projects. Constr. Manag. Econ. 2009, 27, 3–23. [Google Scholar] [CrossRef]
- Ajayi, B.O.; Chinda, T. Impact of Construction Delay-Controlling Parameters on Project Schedule: DEMATEL-System Dynamics Modeling Approach. Front. Built Environ. 2022, 8, 799314. [Google Scholar] [CrossRef]
- Alaghbari, W.; Razali, M.A.K.; Salim, A. Ernawati The Significant Factors Causing Delay of Building Construction Projects in Malaysia. Eng. Constr. Archit. Manag. 2007, 14, 192–206. [Google Scholar] [CrossRef]
- Yap, J.B.H.; Tan, S.M. Investigating Rework: Insights from the Malaysian Construction Industry. ASM Sci. J. 2021, 14, 1–9. [Google Scholar] [CrossRef]
- Shoar, S.; Chileshe, N.; Payan, S. Assessment of the Causes and Effects of Design Deficiencies for Large Construction Projects Using Social Network Analysis. Int. J. Manag. Proj. Bus. 2022, 15, 371–395. [Google Scholar] [CrossRef]
- Niazi, G.A.; Painting, N. Significant Factors Causing Cost Overruns in the Construction Industry in Afghanistan. Procedia Eng. 2017, 182, 510–517. [Google Scholar] [CrossRef]
- Altaf, M.; Musarat, M.A.; Khan, A.; Shoukat, Z.; Salahuddin, U. Change Order Impact on Construction Industry of Pakistan. In Lecture Notes in Civil Engineering; Springer International Publishing: Cham, Switzerland, 2020; Volume 53, pp. 391–402. ISBN 9783030328160. [Google Scholar]
- Staiti, M.; Othman, M.; Jaaron, A.A.M. Impact of Change Orders in Construction Sector in the West Bank. In Proceedings of the International Conference on Industrial Engineering and Operations Management, Kuala Lumpur, Malaysia, 8–10 March 2016; pp. 1690–1698. [Google Scholar]
- Yates, J.K. Construction Decision Support System for Delay Analysis. J. Constr. Eng. Manag. 1993, 119, 226–244. [Google Scholar] [CrossRef]
- Marzouk, M.M.; El-Rasas, T.I. Analyzing Delay Causes in Egyptian Construction Projects. J. Adv. Res. 2014, 5, 49–55. [Google Scholar] [CrossRef] [PubMed]
- Rashid, I.A.; El-mikawi, M.a; Saleh, M.E.A. The Impact of Change Orders on Construction Projects Sports Facilities Case Study. J. Am. Sci. 2012, 8, 628–631. [Google Scholar]
- Hilali, A.; Charoenngam, C.; Barman, A. Barriers in Contractual Scope Management of International Development Projects in Afghanistan. Eng. Constr. Archit. Manag. 2019, 26, 1574–1592. [Google Scholar] [CrossRef]
- Toor, S.; Ogunlana, S. Problems Causing Delays in Major Construction Projects in Thailand. Constr. Manag. Econ. 2008, 26, 395–408. [Google Scholar] [CrossRef]
- Lee, S.; Cha, Y.; Han, S.; Hyun, C. Application of Association Rule Mining and Social Network Analysis for Understanding Causality of Construction Defects. Sustainability 2019, 11, 618. [Google Scholar] [CrossRef]
- Sweis, G.; Sweis, R.; Abu Hammad, A.; Shboul, A. Delays in Construction Projects: The Case of Jordan. Int. J. Proj. Manag. 2008, 26, 665–674. [Google Scholar] [CrossRef]
- Maqbool, R.; Rashid, Y. Detrimental Changes and Construction Projects: Need for Comprehensive Controls. Int. J. Proj. Organ. Manag. 2017, 9, 154. [Google Scholar] [CrossRef]
- Prasad, K.V.; Vasugi, V.; Venkatesan, R.; Bhat, N.S. Critical Causes of Time Overrun in Indian Construction Projects and Mitigation Measures. Int. J. Constr. Educ. Res. 2019, 15, 216–238. [Google Scholar] [CrossRef]
- Keane, P.; Sertyesilisik, B.; Ross, A.D. Variations and Change Orders on Construction Projects. J. Leg. Aff. Disput. Resolut. Eng. Constr. 2010, 2, 89–96. [Google Scholar] [CrossRef]
- Maluleke, P.; Aigbavboa, C.; Thwala, W.D. Causes of Variation Orders in Construction: A Case Study of Polokwane, Limpopo Province. In Advances in Intelligent Systems and Computing; Springer International Publishing: Cham, Switzerland, 2019; Volume 903, pp. 914–920. ISBN 9783030110505. [Google Scholar]
- Dosumu, O.S.; Aigbavboa, C.O. Effects of Variation on Project Cost of Selected Building Projects in Lagos State. In Proceedings of the International Conference on Construction and Real Estate Management, Guangzhou, China, 10 November 2017; American Society of Civil Engineers: Reston, VA, USA, 2017; pp. 42–52. [Google Scholar]
- Lerche, J.; Lindhard, S.; Enevoldsen, P.; Neve, H.H.; Møller, D.E.; Jacobsen, E.L.; Teizer, J.; Wandahl, S. Causes of Delay in Offshore Wind Turbine Construction Projects. Prod. Plan. Control 2022, 34, 1513–1526. [Google Scholar] [CrossRef]
- Perera, B.A.K.S.; Sirimewan, D.C.; Senadeera, A.D. Management of Variations in the Public-Sector Building Construction Projects in Sri Lanka. J. Eng. Des. Technol. 2021, 19, 1601–1619. [Google Scholar] [CrossRef]
- Choudhry, R.M.; Gabriel, H.F.; Khan, M.K.; Azhar, S. Causes of Discrepancies between Design and Construction in the Pakistan Construction Industry. J. Constr. Dev. Ctries. 2017, 22, 1–18. [Google Scholar] [CrossRef]
- Gunduz, M.; Nielsen, Y.; Ozdemir, M. Fuzzy Assessment Model to Estimate the Probability of Delay in Turkish Construction Projects. J. Manag. Eng. 2013, 31, 04014055. [Google Scholar] [CrossRef]
- Almasi, G.; Moradianmina, R.; Zavari, S. Changes and Their Main Causes and Effects in Iranian Projects. In Proceedings of the 2011 International Conference on Management and Service Science, Wuhan, China, 12–14 August 2011; IEEE: Toulouse, France, 2011; pp. 1–6. [Google Scholar]
- Famadico, J.J.F.; Baccay, M.A. Comparative Study on Change Orders in Building Projects. In Lecture Notes in Civil Engineering; Pradhan, B., Ed.; Springer: Singapore, 2019; Volume 9, pp. 79–110. ISBN 9789811080166. [Google Scholar]
- Gunduz, M.; Mohammad, K.O. Assessment Of Change Order Impact Factors On Construction Project Performance Using Analytic Hierarchy Process (AHP). Technol. Econ. Dev. Econ. 2019, 26, 71–85. [Google Scholar] [CrossRef]
- Faten Albtoush, A.M.; Doh, S.I.; Rahman, R.A. Underlying Factors of Cost Overruns in Developing Countries: Multivariate Analysis of Jordanian Projects. IOP Conf. Ser. Earth Environ. Sci. 2021, 682, 012019. [Google Scholar] [CrossRef]
- Aljassmi, H.; Han, S.; Davis, S. Analysis of the Complex Mechanisms of Defect Generation in Construction Projects. J. Constr. Eng. Manag. 2016, 142, 04015063. [Google Scholar] [CrossRef]
- Hanif, H.; Khurshid, M.B.; Lindhard, S.M.; Aslam, Z. Impact of Variation Orders on Time and Cost in Mega Hydropower Projects of Pakistan. J. Constr. Dev. Ctries. 2016, 21, 37–53. [Google Scholar] [CrossRef]
- Ali Kamal Balbaa, A.; Aly Mousa El-Nawawy, O.; Mohamed El-Dash, K.; Badawy Abd El-Megeed Badawy, M. Risk Assessment for Causes of Variation Orders for Residential Projects. J. Eng. Appl. Sci. 2019, 14, 701–708. [Google Scholar] [CrossRef]
- Yang, J.-B.; Chen, C.-C. Causes of Budget Changes in Building Construction Projects: An Empirical Study in Taiwan. Eng. Econ. 2015, 60, 1–21. [Google Scholar] [CrossRef]
- Aljohani, A.; Ahiaga-Dagbui, D.; Moore, D. Construction Projects Cost Overrun: What Does the Literature Tell Us? Int. J. Innov. Manag. Technol. 2017, 8, 137–143. [Google Scholar] [CrossRef]
- Peansupap, V.; Cheang, L. Identifying Issues of Change Leading to Cost Conflicts: Case Study in Cambodia. Procedia Eng. 2015, 123, 379–387. [Google Scholar] [CrossRef]
- Ezenta, B. Project Change Management for Oil and Gas Projects in Alberta: Towards a Predictive Approach. Master’s Thesis, University of Calgary, Calgary, Canada, 2015. [Google Scholar] [CrossRef]
- Bakr, G.A. Studying the Status of Variations in Construction Contracts in Jordan. In Proceedings of the 2014 International Conference on Computing in Civil and Building Engineering, Orlando, FL, USA, 23–25 June 2014; American Society of Civil Engineers: Reston, VA, USA, 2014; pp. 187–194. [Google Scholar]
- Ballesteros-Pérez, P.; del Campo-Hitschfeld, M.L.; González-Naranjo, M.A.; González-Cruz, M.C. Climate and Construction Delays: Case Study in Chile. Eng. Constr. Archit. Manag. 2015, 22, 596–621. [Google Scholar] [CrossRef]
- Hao, Q.; Neelamkavil, J.; Shen, W. Managing Changes in Construction; Institute for Research in Construction, National Research Council Canada: Ottawa, ON, Canada, 2008. [Google Scholar]
- Hsieh, T.Y.; Lu, S.T.; Wu, C.H. Statistical Analysis of Causes for Change Orders in Metropolitan Public Works. Int. J. Proj. Manag. 2004, 22, 679–686. [Google Scholar] [CrossRef]
- Abd El-Razek, M.E.; Bassioni, H.A.; Mobarak, A.M. Causes of Delay in Building Construction Projects in Egypt. J. Constr. Eng. Manag. 2008, 134, 831–841. [Google Scholar] [CrossRef]
- Mpofu, B.; Ochieng, E.G.; Moobela, C.; Pretorius, A. Profiling Causative Factors Leading to Construction Project Delays in the United Arab Emirates. Eng. Constr. Archit. Manag. 2017, 24, 346–376. [Google Scholar] [CrossRef]
- Chang, A.S.-T. Reasons for Cost and Schedule Increase for Engineering Design Projects. J. Manag. Eng. 2002, 18, 29–36. [Google Scholar] [CrossRef]
- Trauner, T.J.; Manginelli, W.A.; Lowe, J.S.; Nagata, M.F.; Furniss, B.J. Construction Delays: Understanding Them Clearly, Analyzing Them Correctly, 2nd ed.; Butterworth-Heinemann: London, UK, 2009; ISBN 0080957145. [Google Scholar]
- Nguyen, V.T.; Do, S.T. Assessing the Relationship Chain among Causes of Variation Orders, Project Performance, and Stakeholder Performance in Construction Projects. Int. J. Constr. Manag. 2021, 23, 1592–1602. [Google Scholar] [CrossRef]
- Abad, F.; Eshtehardian, E.; Taghizade, K. Framework for Proactive Change Management: Assessing the Risk of Change in Construction Projects Using Fuzzy Fault Tree Analysis. J. Archit. Eng. 2019, 25, 04019010. [Google Scholar] [CrossRef]
- Lee, J.-K. Cost Overrun and Cause in Korean Social Overhead Capital Projects: Roads, Rails, Airports, and Ports. J. Urban Plan. Dev. 2008, 134, 59–62. [Google Scholar] [CrossRef]
- Shrestha, P.P.; Zeleke, H.B.; Shrestha, K.K. An Analysis of Change Orders in Public School Projects. Proc. Annu. Conf. Can. Soc. Civ. Eng. 2013, 1, 700–709. [Google Scholar]
- Annamalaisami, C.D.; Kuppuswamy, A. Managing Cost Risks: Toward a Taxonomy of Cost Overrun Factors in Building Construction Projects. ASCE-ASME J. Risk Uncertain. Eng. Syst. Part. A Civ. Eng. 2021, 7, 04021021. [Google Scholar] [CrossRef]
- Motawa, I.A.; Anumba, C.J.; El-Hamalawi, A. A Fuzzy System for Evaluating the Risk of Change in Construction Projects. Adv. Eng. Softw. 2006, 37, 583–591. [Google Scholar] [CrossRef]
- Heravi, G.; Charkhakan, M.H. Predicting Change by Evaluating the Change Implementation Process in Construction Projects Using Event Tree Analysis. J. Manag. Eng. 2015, 31, 04014081. [Google Scholar] [CrossRef]
- Ameyaw, E.E.; Chan, A.P.C.; Owusu-Manu, D.G.; Coleman, E. A Fuzzy Model for Evaluating Risk Impacts on Variability between Contract Sum and Final Account in Government-Funded Construction Projects. J. Facil. Manag. 2015, 13, 45–69. [Google Scholar] [CrossRef]
- Yap, J.B.H.; Abdul-Rahman, H.; Wang, C. A Conceptual Framework for Managing Design Changes in Building Construction. MATEC Web Conf. 2016, 66, 00021. [Google Scholar] [CrossRef]
- Yap, J.B.H.; Lim, B.L.; Skitmore, M.; Gray, J. Criticality of Project Knowledge and Experience in the Delivery of Construction Projects. J. Eng. Des. Technol. 2022, 20, 800–822. [Google Scholar] [CrossRef]
- Lopez, R.; Love, P.E.D.; Edwards, D.J.; Davis, P.R. Design Error Classification, Causation, and Prevention in Construction Engineering. J. Perform. Constr. Facil. 2010, 24, 399–408. [Google Scholar] [CrossRef]
- Yang, J.-B.; Wei, P.-R. Causes of Delay in the Planning and Design Phases for Construction Projects. J. Archit. Eng. 2010, 16, 80–83. [Google Scholar] [CrossRef]
- Do, S.T.; Nguyen, V.T.; Nguyen, N.H. Relationship Networks between Variation Orders and Claims/Disputes Causes on Construction Project Performance and Stakeholder Performance. Eng. Constr. Archit. Manag. 2022. ahead of printing. [Google Scholar] [CrossRef]
- Pourrostam, T.; Ismail, A.; Mansournejad, M. Identification and Evaluation of Causes and Effects of Change Orders in Building Construction Projects. Appl. Mech. Mater. 2011, 94–96, 2261–2264. [Google Scholar] [CrossRef]
- Wu, C.H.; Hsieh, T.Y.; Cheng, W.L.; Lu, S.T. Grey Relation Analysis of Causes for Change Orders in Highway Construction. Constr. Manag. Econ. 2004, 22, 509–520. [Google Scholar] [CrossRef]
- Chang, A.S.T.; Shih, J.S.; Choo, Y.S. Reasons and Costs for Design Change during Production. J. Eng. Des. 2011, 22, 275–289. [Google Scholar] [CrossRef]
- Charkhakan, M.H.; Heravi, G. Evaluating the Preventability of Conflicts Arising from Change Occurrence in Construction Projects. Eng. Constr. Archit. Manag. 2019, 26, 1777–1800. [Google Scholar] [CrossRef]
- Varghese, P.S.; Parakkal, R.; KK, S.; Babu, S.T.; Anilkumar, S. Analysis of Change Order in Road Construction Projects. Int. Res. J. Eng. Technol. 2018, 5, 2671–2674. [Google Scholar]
- Safapour, E.; Kermanshachi, S. Identifying Manageable Scope Creep Indicators and Selecting Best Practice Strategies for Construction Projects. In Proceedings of the Canadian Society of Civil Engineering Annual Conference 2019, Montreal, QC, Canada, 12–15 June 2019; pp. 1–10. [Google Scholar]
- Olawale, Y.A.; Sun, M. Cost and Time Control of Construction Projects: Inhibiting Factors and Mitigating Measures in Practice. Constr. Manag. Econ. 2010, 28, 509–526. [Google Scholar] [CrossRef]
- Ramanathan, C.; Narayanan, S.P.; Idrus, A.B. Construction Delays Causing Risks on Time and Cost—A Critical Review. Constr. Econ. Build. 2012, 12, 37–57. [Google Scholar] [CrossRef]
- İlter, O.; Çelik, T. Investigation of Organizational and Regional Perceptions on the Changes in Construction Projects. Tek. Dergi 2021, 32, 11257–11286. [Google Scholar] [CrossRef]
- Faridi, A.S.; El-Sayegh, S.M. Significant Factors Causing Delay in the UAE Construction Industry. Constr. Manag. Econ. 2006, 24, 1167–1176. [Google Scholar] [CrossRef]
- Bramble, B.B.; Callahan, M.T. Construction Delay Claims, 4th ed.; Aspen Publishers: Gainthersburg, MD, USA, 2011. [Google Scholar]
- Jadhav, O.U.; Bhirud, A.N. An Analysis of Causes and Effects of Change Orders on Construction Projects in Pune. J. Eng. Res. Appl. 2015, 4, 2248–962201. [Google Scholar]
- Bajjou, M.S.; Chafi, A. Empirical Study of Schedule Delay in Moroccan Construction Projects. Int. J. Constr. Manag. 2020, 20, 783–800. [Google Scholar] [CrossRef]
- Chanmeka, A.; Thomas, S.R.; Caldas, C.H.; Mulva, S.P. Assessing Key Factors Impacting the Performance and Productivity of Oil and Gas Projects in Alberta. Can. J. Civ. Eng. 2012, 39, 259–270. [Google Scholar] [CrossRef]
- Frimpong, Y.; Oluwoye, J.; Crawford, L. Causes of Delay and Cost Overruns in Construction of Groundwater Projects in a Developing Countries; Ghana as a Case Study. Int. J. Proj. Manag. 2003, 21, 321–326. [Google Scholar] [CrossRef]
- Gunduz, M.; Khan, O.H. Effective Framework for Change Order Management Using Analytical Hierarchy Process (AHP). Gazi Univ. J. Sci. 2018, 31, 1079–1091. [Google Scholar]
- Assaf, S.; Hassanain, M.A.; Abdallah, A. Review and Assessment of the Causes of Deficiencies in Design Documents for Large Construction Projects. Int. J. Build. Pathol. Adapt. 2018, 36, 300–317. [Google Scholar] [CrossRef]
- Hwang, B.-G.; Thomas, S.R.; Haas, C.T.; Caldas, C.H. Measuring the Impact of Rework on Construction Cost Performance. J. Constr. Eng. Manag. 2009, 135, 187–198. [Google Scholar] [CrossRef]
- Grau, D.; Back, W.E.; Prince, J.R. Benefits of On-Site Design to Project Performance Measures. J. Manag. Eng. 2012, 28, 232–242. [Google Scholar] [CrossRef]
- Yap, J.B.H.; Skitmore, M.; Gray, J.; Shavarebi, K. Systemic View to Understanding Design Change Causation and Exploitation of Communications and Knowledge. Proj. Manag. J. 2019, 50, 288–305. [Google Scholar] [CrossRef]
- Rachid, Z.; Toufik, B.; Mohammed, B. Causes of Schedule Delays in Construction Projects in Algeria. Int. J. Constr. Manag. 2019, 19, 371–381. [Google Scholar] [CrossRef]
- Aibinu, A.A.; Odeyinka, H.A. Construction Delays and Their Causative Factors in Nigeria. J. Constr. Eng. Manag. 2006, 132, 667–677. [Google Scholar] [CrossRef]
- Charles, S.P.R.; Wanigarathna, N.; Sherratt, F. Construction Project Change: Investigating Cost and Benefits. In Proceedings of the 31st Annual ARCOM Conference, Lincoln, UK, 7–9 September 2015; pp. 833–842. [Google Scholar]
- Khalafallah, A.; Shalaby, Y. Change Orders: Automating Comparative Data Analysis and Controlling Impacts in Public Projects. J. Constr. Eng. Manag. 2019, 145, 04019064. [Google Scholar] [CrossRef]
- Tran, N.N.N.; Do, S.T.; Nguyen, T.A.; Le, L.H. Variation Order Management in Vietnam Construction Projects. In Proceedings of the ICSCEA 2019, Lecture Notes in Civil Engineering 80; Reddy, J.N., Wang, C.M., Luong, V.H., Le, A.T., Eds.; Springer Singapore: Singapore, 2020; Volume 80, pp. 1007–1014. [Google Scholar]
- Günhan, S.; Arditi, D.; Doyle, J. Avoiding Change Orders in Public School Construction. J. Prof. Issues Eng. Educ. Pract. 2007, 133, 67–73. [Google Scholar] [CrossRef]
- Hassanein, A.A.G.; El Nemr, W. Management of Change Order Claims in the Egyptian Industrial Construction Sector. J. Financ. Manag. Prop. Constr. 2007, 12, 45–60. [Google Scholar] [CrossRef]
- Erdogan, B.; Anumba, C.; Bouchlaghem, D.; Nielsen, Y. Change Management in Construction: The Current Context. In Association of Researchers in Construction Management ARCOM 2005—Proceedings of the 21st Annual Conference, London, UK, 7–9 September 2005; Association of Researchers in Construction Management: London, UK, 2005; Volume 2, pp. 1085–1095. [Google Scholar]
- Turner, D.F.; Turner, A. Building Contract Claims and Disputes; Routledge: London, UK, 2014; ISBN 1317888952. [Google Scholar]
Participant | Project | Organization Type | Experience of the Participant | Project Type | Owner Type |
---|---|---|---|---|---|
Ptp. 1 | Project 1 | Contractor | 6–10 | Manufacturing hall | Private |
Ptp. 2 | Project 2 | Consultant | 16–20 | Student Dormitory Building | Public |
Ptp. 3 | Project 3 | Client | >20 | Administrative Building | Public |
Ptp. 4 | Project 4 | Contractor | >20 | Infrastructure (sewerage system) | Public |
Ptp. 5 | Project 5 | Contractor | >20 | Hospital | Public |
Ptp. 6 | Project 6 | Contractor | 6–10 | Highway | Public |
Participant | Organization Type | Experience of the Participant | Role of the Participant |
---|---|---|---|
Participant 1 | Contractor | >20 | Project Manager |
Participant 2 | Consultant | 16–20 | Owner |
Participant 3 | Client | 10–15 | Project Manager |
Participant 4 | Consultant | >20 | Owner |
Participant 5 | Contractor | >20 | Head of the planning department |
Participant 6 | Contractor | 10–15 | Planning Engineer |
Level 1 (Categories) | Level 2 (Subcategories) |
---|---|
Human resources | - Human Resource Management - Availability of Human Resources - Capabilities |
Material | - Procurement Process of Materials - Availability and Variety of Materials - Storage of Materials in the Construction Site - Quality of Procured Materials |
Other resources | - Procurement and Delivery of Equipment and Machines - Availability of Equipment and Machines in the Market - Repair and Maintenance Facilities - Productivity of Machines and Equipment - Quality of Machines and Equipment |
Financial Factors | - Cashflows - Financing Conditions - Resources Cost - Contract and Overhead Costs |
External Factors | - Weather - Catastrophes - Environmental Problems - Security Problems |
Health and Safety Concerns | - Safety Concerns - Health Concerns |
Project Location | - Ground Conditions - Construction Site Conditions - Accessibility and Possession |
Project Stakeholders (Contractor, Client, Consultant, Designer, etc.) | - Project Stakeholders’ Competence and Experience - Project Stakeholders’ Expectations - Project Stakeholders’ Culture and Ethics |
Project Management | - Construction Site Management - Project Quality Management - Project Time Management - Project Communication Management - Project Organization |
Contract Document and Contract Management | - Project Scope Management - Tendering and Project delivery - Contract Document Management |
Design Process | - Problems in Design - Changes in Design - Design Procedure - Design Properties |
Project Implementation | - Mobilization of Construction Site - Logistics - Construction Methodology - Subcontract Management - Productivity Issues |
Macro Factors | - Societal Factors - Political Factors - Economic Factors - Influence of External Stakeholders - Rules and Regulations |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2024 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Birgonul, Z.; Budayan, C.; Koc, K. Development of a Taxonomy for Causes of Changes in Construction Projects. Buildings 2024, 14, 278. https://doi.org/10.3390/buildings14010278
Birgonul Z, Budayan C, Koc K. Development of a Taxonomy for Causes of Changes in Construction Projects. Buildings. 2024; 14(1):278. https://doi.org/10.3390/buildings14010278
Chicago/Turabian StyleBirgonul, Zeynep, Cenk Budayan, and Kerim Koc. 2024. "Development of a Taxonomy for Causes of Changes in Construction Projects" Buildings 14, no. 1: 278. https://doi.org/10.3390/buildings14010278
APA StyleBirgonul, Z., Budayan, C., & Koc, K. (2024). Development of a Taxonomy for Causes of Changes in Construction Projects. Buildings, 14(1), 278. https://doi.org/10.3390/buildings14010278