Unshoring Process of a Temporary Pillar, in a Seventeen-Storey Building in Sant Adrià del Besós
Abstract
:1. Introduction
2. Brief Description of the Building
3. Description of the Structure of the Building
4. Description of the Frame That Contains the Shoring
- A composite steel-concrete vertical pillar (A), which goes from the foundation to the roof. It was designed as a composite, in order to facilitate the union with the rest of the metallic diagonals, which will be defined below;
- An inclined steel diagonal (B), HEM 400/320 with added plates, goes from the second floor to the thirteenth floor. It is 36.2 m long and 78° inclined. In the foot, it is born from the pillar described above (A), and in the head, it coincides with the beginning of the vertical metallic tension bar (D) and with the end of the top diagonal (C) that will be described below;
- An inclined steel diagonal (C), HEM 320 with added plates, goes from the head of the previous diagonal to the ceiling of the sixteenth floor. It is 15 m long and 60° inclined;
- A vertical steel tension bar (D), HEM-200 with added plates, that completes the frame, goes from the third floor to the twelfth floor ceiling. Above this floor, it continues as a compressed pillar. As a particular characteristic, it is worth mentioning that this element will be compressed during the construction phase, and will be subjected to traction in its final state.
5. Description of the Structural Solution Adopted for the Unshoring Process
- Four strain gauges (S.G): these are sensors that determine the axial load of the inspected elements, depending on the elongation observed. They have been placed according to Figure 1: in the head of the tension element, which is an extension of the provisional pillar (S.G. nº1); in the web of the temporary pillar (S.G. nº2); between the cantilever beams (S.G. nº3); and in the inclined pillar (S.G. nº4);
- Four displacement transducers: they control the vertical movement of the analyzed points, in this case, the tip of the metallic cantilever beams, getting to know at all times of the process the inclination of the plane formed by the four beams;
- Four pressure sensors: they give information on the pressure of each piston, which can be corrected at any time; one on each metallic cantilever beam.
6. Description of the Unshoring Process
- -
- Pre-loading process and subsequent unloading of the cantilever beams: On 14 March 2022, all control elements were placed and checked. The system was then placed under load using four steps of equal magnitude, with a final load of 6800 kN, which represents 85% of the load in ELU. Once this force was reached, it was unloaded without having started any cutting process. This previous step was, so to speak, the “insurance” of the “insurance”, that is, a load test of the system. The proposal can also be understood as a prestressing of a metal structure for its control [46]. The final deformations obtained in each cantilever beam are detailed below in Table 2:
- -
- Pillar cutting process: On the following day, 15 March 2022, after placing and checking all the control elements, as well as the pistons, a prior force of 900 kN was introduced to the cantilever beams, to pre-load the pistons. This action represented approximately 13% of the final estimated load. Once the entire system had been checked, the space remaining between the two groups of four brackets was cut with oxyfuel. The pillar-cutting process was carried out at a height of 1.2 m above the first-floor ceiling, that is, in the lower part of the double height, making two flat cuts about 150 mm apart from each other. In that position, the oxyfuel team could work comfortably. First, an outer flange was completely removed from an HEM section. Then, the opposite flange of the other HEM section, to finish cutting the four flanges. In this way, this section was weakened, allowing it to rotate itself. Finally, the central core was removed, completely freeing the pillar, and progressively transferring the action to the pistons.
7. Results and Discussion: Follow-Up of the Deformation in the Following Days
- -
- Time difference: it seemed that solar radiation might have affected some cases.
- -
- Disposal of materials in various levels: during the days after the cut, some partition walls were built that increased the weight, and therefore the deformation of the cantilever area.
- -
- Small inaccuracies in the measurement: although the measurement system was at all times careful and efficient, as it was not an electronic lecture system, it could contain slight deviations. It was not understood, in any case, that the results shown were incorrect. The method used to track the deformations consisted of the use of a transparent millimeter scale and the measurement of two indelible marks placed at the two ends of the cut temporal pillar.
8. Conclusions
- -
- Axial forces in the truss: Table 1 details the stresses that were initially considered in the executive project for each element that makes up the truss, both in the case of the shoring structure and in the case after the removal of the provisional pillar. The results obtained in the structure, once the prop has been removed, can be found in Table 3. Comparison of these stresses indicates that the maximum load transmitted by the cats was 2825 kN, while a compression of 6000 kN had been applied. The difference in these figures suggests that the construction system, as well as the supposed overloads of use, was considered on the safety side. The construction process was not complete until the conclusion of the truss, so the construction floor by floor, as well as the rigidity of the provisional prop, was decisive. A phase-by-phase calculation was not carried out because it was excessively complex to analyze. Finally, it was decided that all the upper floors would be free of any other load than their own weight, and some of the facades that were planned to be built in this area were not executed. It is clear that the final forecast of the loads must be carried out on the safety side in order to know from the beginning the model of the hydraulic jacks used;
- -
- Deformations observed in the four pistons during the cutting process: The deformations observed during the preloading process of the cantilevers, shown in Table 2, reached a value of up to 2.15 mm in one of the arms, and left an imperceptible initial deformation residue of up to 0.16 mm. The initially expected deformation according to computer calculations was 5 mm, so the results once again favored safety. It was not a minor action, since the beams were designed for 6800 kN previously introduced by the hydraulic jacks. The final deformations, which can be seen in Figure 5, were approximately 18.50 mm. These deformations refer not to the descent of the beams, but to that of the upper cantilever. They were also lower than expected, in this case 30 mm, for reasons parallel to those explained in the previous points; the beams
- -
- Tensions in the brackets: The stresses and the final deformations in the cantilevers were checked manually using material strength formulas [22]. In this article we use a three-dimensional model under academic license (Figure 4) that, two years later, corroborated the initial calculations of the project, always remaining below the admissible steel resistance. The deformations achieved in the cantilevers also indicate the good response of the system;
- -
- The subsequent manual monitoring of the deformations: At both ends of the cut abutment, two indelible and fixed marks (Figure 7) were placed to measure the deformations that occurred in the days following the cut. For a month and a half, a maximum deformation of 3 mm was accumulated caused by the gradual introduction of new loads in the building. The deformations varied throughout the day, possibly because the thermal expansions had a slight impact on the final result. The deformations were accepted because they were always in the expected range of less than 30 mm;
- -
- Final monitoring of the transfer of the forces: As can be seen in the final image (Figure 9), the forces were transferred first during the cutting process of the column, then during the waiting or observation time corresponding to approximately 30 min, and finally during the unloading of the hydraulic jacks.
- Values corresponding to the cut provisional abutment: To cut the pillar, an initial load of 900 kN is introduced by the hydraulic pistons. As the section of the pillar is reduced—progressively removing the flanges and then the webs from the section—the load is transferred to the pistons. Figure 9 shows the evolution of the loads of the different columns monitored in the cutting of the column. It is observed that before the discharge of the pistons, the value of the load supported by the pistons, 2748 kN, is practically identical to that corresponding to that measured in the progressive discharge of the pillar 2825 kN. The difference between the two values is approximately 3%. This similarity between both values shows that the maneuver was being monitored correctly. The resulting load is much lower than the estimated expected 6000 kN;
- Values corresponding to the upper sections of the pillar (pillar corresponding to the 12th floor). It is observed how the pillar is unloaded. This must be interpreted as the axial changing sign, since initially it was compressed, and after the cut, it is tensile;
- Values corresponding to the diagonal pillar: It is verified that the inclined pillar gains load. As can be seen in Figure 3, the displacements—as has happened with the loads—are markedly lower than expected: they are around 18 mm, with the expected values being in the order of 30 mm;
- After 48 h of cutting the pillar, the variation in loads and displacements is checked with respect to the values measured at the end of the load transfer operation.
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
References
- Buchla, D.; McLachlan, W. Applied Electronic Instrumentation and Measurement; Prentice Hall: Hoboken, NJ, USA, 1992. [Google Scholar]
- Sydenham, P.H.; Hancock, N.H.; Thorn, R. Introduction to Measurement Science and Engineering; Reprinted; Wiley Series in Measurement Science and Technology; Wiley: Chichester, UK, 1994. [Google Scholar]
- Romeral Martínez, J.L.; Balcells Sendra, J. Transductores y Sensores Industriales; Universitat Politècnica de Catalunya Departament d’Enginyeria Electrònica, Escola Tècnica Superior d’Enginyers Industrials de Terrassa; Student delegation E.T.S.E.I.T: Barcelona, Spain, 1992; OCLC 803064965. [Google Scholar]
- Riu Costa, P.J.; Rosell Ferrer, J.F.; Ramos Castro, J. Sistemas de Instrumentación; U.P.C. Edicions: Barcelona, Spain, 1995; ISBN 9788498802887. [Google Scholar] [CrossRef]
- Código Estructural; Boletín Oficial del Estado Real Decreto 470/2021, BOE-A-2021-13681; Ministerio de la Presidencia, Relaciones con las Cortes y Memoria Democrática: Barcelona, Spain, 2021.
- Eurocódigo 2: Proyecto de Estructuras de Hormigón; Comité técnico AEN/CTN 140; AENOR: Madrid, Spain, 2013.
- EHE-08: Instrucción de Hormigón Estructural; Comisión Permanente del Hormigón; Ministerio de Fomento de España: Madrid, Spain, 2010.
- González Fernández, V.; Barrios-Padura, A.; Molina-Huelva, M. Aplicaciones de las técnicas no destructivas Pull-Off y ultrasonidos en el control de calidad del refuerzo con materiales compuestos en estructuras de concreto. Cienc. E Ing. Neogranadina 2017, 28, 5–26. [Google Scholar] [CrossRef]
- Scarponi, C.; Briotti, G. Ultrasonic technique for the evaluation of delaminations on CFRP, GFRP, KFRP composite materials. Compos. Part B Eng. 2000, 31, 237–243. [Google Scholar] [CrossRef]
- Calavera Ruiz, J. Cálculo, Construcción, Patología y Rehabilitación de Forjados de Edificación: Unidireccionales y Sin Vigas-Hormigón Metálicos y Mixtos; Instituto Técnico de Materiales y Construcciones INTEMAC: Madrid, Spain, 2002; ISBN 978-84-88764-14-0. [Google Scholar]
- Boix, S. La Norma ISO 9001: 2000; Gestion: Barcelona, Spain, 2000; ISBN 978-84-8088-505-8. [Google Scholar]
- Normalización y Certificación: Conceptos Básicos; Asociación Española de Normalización y Certificación AENOR: Madrid, Spain, 1993; ISBN 978-84-86688-86-8.
- Zabara Czorna, O. Curso de Oxicorte; Centro Nacional de Investigaciones Metalúrgicas; CENIM: Madrid, Sapin, 1966; OCLC 802803333. [Google Scholar]
- Poutanen, T.; Länsivaara, T.; Pursiainen, S.; Mäkinen, J.; Asp, O. Calculation of safety factors of the Eurocodes. Appl. Sci. 2020, 11, 208. [Google Scholar] [CrossRef]
- Poutanen, T. Code calibration of the eurocodes. Appl. Sci. 2021, 11, 5474. [Google Scholar] [CrossRef]
- Pacheco, J.; Martín Morejón, L. Levantamiento de Plano Topográfico Basado en un Terreno Real; Escuela de Arquitectos Técnicos; Sección de Publicaciones; U.P.C.: Barcelona, Spain, 1989; OCLC: 802683108. [Google Scholar]
- Nakasone, Y.; Yoshimoto, S.; Stolarski, T. Engineering Analysis with ANSYS Software; Elsevier Science: Chantilly, France, 2006. [Google Scholar] [CrossRef]
- Maristany i Carreras, J. Método práctico de cálculo de estructuras en periodo de construcción: Aplicación informática. In Departament D’estructures; Monografia 9.43 ETSAB; U.P.C: Barcelona, Spain, 1986. [Google Scholar]
- Rodríguez, D.; Brunesi, E.; Nascimbene, R. Fragility and sensitivity analysis of steel frames with bolted-angle connections under progressive collapse. Eng. Struct. 2021, 228, 111508. [Google Scholar] [CrossRef]
- Zhang, J.-Z.; He, Y.-H.; Li, G.-Q.; Hai, L.-T.; Zhou, J.-W. A novel approach for quantifying dynamic impacts on steel frames induced by instantaneous interior column loss. J. Constr. Steel Res. 2024, 220, 108837. [Google Scholar] [CrossRef]
- Comité técnico. AEN/CTN 140 UNE-EN 1993-1-1:2008/AC; Eurocódigo 3: Proyecto de Estructuras de Acero: Parte 1-1: Reglas Generales y Reglas Para Edificios; AENOR: Madrid, Spain, 2010. [Google Scholar]
- Font Basté, J.; Díaz Gómez, C. Evolució de la Tipologia i Sistemes Constructius en Edificis D’habitatges de Promoció Pública a L’àrea Metropolitana de Barcelona 1975–1992; Departament de Tecnologia de l’Arquitectura, Universitat Politècnica de Catalunya: Barcelona, Spain, 2017; OCLC: 1120527522. [Google Scholar]
- Normativa Urbanística Metropolitana Normes Urbanístiques del Pla General Metropolità, Ordenances Metropolitanes D’edificació, Ordenança Metropolitana de Rehabilitació, Ordenança Metropolitana de Publicitat; Mancomunitat de Municipis de l’Àrea Metropolitana de Barcelona: Barcelona, Spain, 2001; ISBN 978-84-87881-06-0.
- Soltanalipour, M.; Ferrer-Ballester, M.; Marimon Carvajal, F.; Albareda Valls, A.; Casafont Ribera, M.; Iglesias Toquero, G. New shear transfer system for concrete-filled steel tube (CFST) columns. Steel Constr. Des. Res. 2022, 15, 59–68. [Google Scholar] [CrossRef]
- Freyssinet, E.; Guyon, F.; Rui–Wamba, J.; Fernández Alba, A. Eugène Freyssinet, Un Ingeniero Revolucionario; Fundación Esteyco: Madrid, Spain, 2003; ISBN 8492109297. [Google Scholar]
- Argüelles Álvarez, R.; Argüelles Bustillo, R.; Arriaga Martitegui, F.; Argüelles Bustillo, J.M.; Esteban Herrero, M. Cálculo Matricial de Estructuras en Primer y Segundo Orden: Teoría y Problemas; Ed. Bellisco: Madrid, Spain, 2005; ISBN 9788496486126. [Google Scholar]
- Zenz, G.; Berger, W.; Gerstmayr, J.; Nader, M.; Krommer, M. Design of piezoelectric transducer arrays for passive and active modal control of thin plates. Smart Struct. Syst. 2013, 12, 547–577. [Google Scholar] [CrossRef]
- Norma de Construcción Sismorresistente: Parte General y Edificación NCSE-02, con Comentarios de la Subcomisión Permanente de Normas Sismoresistentes Real Decreto 997/2002, de 27 de septiembre; Ministerio de Fomento: Madrid, Spain, 2003.
- UNE-EN 1991-1-4; Eurocódigo 1: Acciones En Estructuras, Parte 1–4. Acciones Generales. Acciones de Viento. Asociación Española de Normalización y Certificación. AENOR: Madrid, Spain, 2007.
- Documento Básico, Seguridad Estructural: Acciones en la Edificación AE-88; Ministerio de Fomento: Madrid, Spain, 1996.
- Stoller, E.; Khan, Y.S. The John Hancock Center; The Building Blocks Series; Princeton Architectural Press: New York, NY, USA, 2000. [Google Scholar]
- Macchi, G. Stabilization of the Leaning Tower of Pisa. In Proceedings of the Structures Congress; American Society of Civil Engineers: New York, NY, USA, 2005; pp. 1–11. [Google Scholar] [CrossRef]
- Gromysz, K. Revitalization of a Vertically Deflected Historical 16th Century Bell Tower. IOP Conf. Ser. Mater. Sci. Eng. 2019, 471, 052025. [Google Scholar] [CrossRef]
- Zhang, X.; Shan, R.; Lu, M. Rectification of Jacking Method for Brick-Wooden Buildings in Deformation Analysis with CFST Reinforcement. Struct. Des. Tall Spec. Build. 2018, 27, e1439. [Google Scholar] [CrossRef]
- Basu, B.; Oreste, S.B.; Casciati, F.; Casciati, S.; E. Del Grosso, E.; Domaneschi, M.; Faravelli, L. A European Association for the Control of Structures joint perspective. Recent studies in civil structural control across Europe. Struct. Control Health Monit. 2014, 21, 1414–1436. [Google Scholar] [CrossRef]
- Gromysz, K.; Smolana, M.; Drusa, M. Research on the Characteristics of Jacks Used to Rectify Tilted Buildings. Buildings 2024, 14, 1581. [Google Scholar] [CrossRef]
- Gromysz, K. In Situ Experimental Study on the Active Support Used for Building Rectification. Materials 2020, 13, 2015. [Google Scholar] [CrossRef] [PubMed]
- Gromysz, K. A bar model of a temporary wooden support used to remove deflections of buildings. J. Phys. Conf. Ser. 2021, 1781, 12024. [Google Scholar] [CrossRef]
- Quintero Moreno, F.; Cudós Samblancat, V. Estructuras metálicas: Uniones U.D.2, Uniones; Universidad Nacional de Educación a Distancia (UNED): Madrid, Spain, 1988; ISBN 978-84-86957-08-7. [Google Scholar]
- Instrucción de Acero Estructural (EAE): Con Comentarios de los Miembros de la Comisión Permanente de Estructuras de Acero; Real decreto 751/2011; Ministerio de Fomento, Boletín oficial del Estado N°149: Madrid, Spain, 2011.
- Chacon, R.; Mirambell, E.; Real, E. Influence of initial imperfections on the resistance of hybrid steel plate girders subjected to concentrated loads. In Proceedings of 6th International Conference Steel and Aluminium Structures ICSAS’07, Oxford, UK, 1 January 2007; pp. 736–743. [Google Scholar]
- Chacon, R.; Mirambell, E.; Real, E. Resistance of transversally stiffened hybrid steel plate girders subjected to concentrated loads. Proceedings SDSS. In International Colloquium on Stability and Ductility of Steel Structures; Universitat Politècnica de Catalunya: Lisbon, Portuga, 2006. [Google Scholar]
- Chacon, R.; Mirambell, E.; Real, E. Influence of designer-assumed initial conditions of the numerical modelling of steel plate girders subjected to patch loading. Thin Walled Struct. 2009, 47, 391–402. [Google Scholar] [CrossRef]
- Chacon, R.; Guzman, F.; Mirambell, E.; Real, E.; Oñate, E. Wireless Sensor Networks for Strain Monitoring during Steel Bridges Launching. Int. J. Struct. Health Monit. 2009, 8, 195–205. [Google Scholar] [CrossRef]
- Ansys® Academic Research Mechanical, Release 24.1, Help System, Structural Analysis Guide; ANSYS, Inc.: Canonsburg, PA, USA, 2024.
- Costales Calvo, I.; Obiol Sánchez, A.; Gómez Serrano, J. El Pretensado en las Estructuras de Acero; Departament d’Estructures a l’Arquitectura, Universitat Politècnica de Catalunya, U.P.C.: Barcelona, Spain, 2012. [Google Scholar]
- Brufau, R. Edificio Fórum; Revista de Obras Públicas; 151 3442; Escuela Técnica Superior de Ingenieros de Caminos, Canales y Puertos: Madrid, Spain, 2004; pp. 67–81. Available online: https://quickclick.es/rop/pdf/publico/2004/2004_marzo_3442_07.pdf (accessed on 18 July 2024).
Element (See Each Position in Figure 1) | Axil Force with the Prop. Upper Floor (SLS) | Axil Force with the Prop. Lower Floor (SLS) | Final Axial Force Upper Floor (SLS) | Final Axial Force Lower Floor (SLS) |
---|---|---|---|---|
(A) | −159 kN | 9932 kN | 14,000 kN | 18,500 kN |
(B) | 2470 kN | 4252 kN | 2300 kN | 8050 kN |
(C) | 1605 kN | 3003 kN | −100 kN | −690 kN |
(D) | 2204 kN | 6800 kN | −510 kN | −186 kN |
Stage | Transferred Load (kN) | Load Obtained in the Pillar (kN) | Displacement of the Cantilevers (mm) | |||
---|---|---|---|---|---|---|
TR 1 | TR 2 | TR 3 * | TR 4 | |||
1 | 1700 | 1950 | 0.39 | 0.52 | 0.62 | 0.41 |
2 | 3400 | 3982 | 0.81 | 1.03 | 1.26 | 0.83 |
3 | 5100 | 6067 | 1.23 | 1.58 | 1.92 | 1.24 |
4 | 6800 | 8177 | 1.67 | 2.15 | 2.57 | 1.68 |
Leftover | - | - | 0.08 | 0.16 | 0.04 | 0.10 |
Loads (kN) | Displacement (mm) | |||||||
---|---|---|---|---|---|---|---|---|
STAGE | Piston Sum | Cut Pillar | Pillar 12th Level | Inclined Pillar | TR 1 | TR 2 | TR 3 | TR 4 |
Start cutting | 900 | 0 | 0 | 0 | 0 | 0 | 0 | 0 |
Final cut | 2748 | −160 | −25 | 48 | 0.81 | 2.07 | 1.0 | 0.5 |
Piston-lowering | 0 | 2825 | 925 | −1458 | −17.75 | −16.86 | −19.65 | −18.5 |
After 48 h | - | 2819 | 1036 | −1305 | - | - | - | - |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2024 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Costales Calvo, I.; Font i Basté, J.; Gimferrer i Vilaplana, X.; Llorens Solivera, M. Unshoring Process of a Temporary Pillar, in a Seventeen-Storey Building in Sant Adrià del Besós. Buildings 2024, 14, 3436. https://doi.org/10.3390/buildings14113436
Costales Calvo I, Font i Basté J, Gimferrer i Vilaplana X, Llorens Solivera M. Unshoring Process of a Temporary Pillar, in a Seventeen-Storey Building in Sant Adrià del Besós. Buildings. 2024; 14(11):3436. https://doi.org/10.3390/buildings14113436
Chicago/Turabian StyleCostales Calvo, Ignacio, Jaume Font i Basté, Xavier Gimferrer i Vilaplana, and Miquel Llorens Solivera. 2024. "Unshoring Process of a Temporary Pillar, in a Seventeen-Storey Building in Sant Adrià del Besós" Buildings 14, no. 11: 3436. https://doi.org/10.3390/buildings14113436
APA StyleCostales Calvo, I., Font i Basté, J., Gimferrer i Vilaplana, X., & Llorens Solivera, M. (2024). Unshoring Process of a Temporary Pillar, in a Seventeen-Storey Building in Sant Adrià del Besós. Buildings, 14(11), 3436. https://doi.org/10.3390/buildings14113436