A Proposed Model for Variation Order Management in Construction Projects
Abstract
:1. Introduction
1.1. Variation Order Types
1.2. Variation Order Sources and Causes
1.3. Variation Order Procedures
2. Methodology
- The items with no changes based on the tender design.
- Increased quantities of items beyond the tender design and the effect on additional changes.
- Decreased quantities of items from the tender design and the effect on deduction change.
- New items, the new items inside the tender design, and the effect on addition or deduction changes.
- Omitted items from the tender design and the effect on addition or deduction changes.
- (a)
- Interviews were conducted with project managers (contractors, consultants, and the project management office of the owner KFU-PMO to verify the reasons and conditions for the changes and to classify the effects of quantities, cost, and ratio that occurred in each discipline as significant findings.
- (b)
- Classifying the phases of VOM approach in two phases includes the initiation processes phase and the variation order course processes phase based on a certain number of procedures and weight for each parameter assigned to this phase to support decision processes based on a certain average ratio of weights calculation. Applying VOM supported the decision maker of the case study campus organization in the ongoing 32 projects, which positively reduced the negative impacts of the variation order on cost and schedule overrun issues and presented a comprehensive and robust model in the construction industry that can be adopted and updated according to project conditions. Figure 2 shows the study method flowchart.
- ▪
- The financial value based on the bill of quantities = 1,196,916,993.70 Saudi riyals
- ▪
- The final financial value after the handover completion = 1,282,271,123.98 Saudi riyals
- ▪
- The final financial value of the change = 85,354,130.28 Saudi riyals; the final total change was 7.13%.
3. Results and Discussions
3.1. Analysis of Change Order Types
- Type 1: No change items implemented based on the original design and contract documents with rate 18.65% and arithmetic average 18.58%. This means that 81% of the drawing and original design for all the study sample projects has been changed.
- Type 2: Quantity increase with rate + 20.72% of the total value of projects according to the bill of quantities and arithmetic average of 22.97%.
- Type 3: Quantity decrease with −10.87% of the total value of projects according to the bill of quantities and arithmetic average of −10.79%.
- Type 4: New items with a rate of + 8.94% of the project’s total value according to the bill of quantities and arithmetic average of 9.56%.
- Type 5: Deducted items with a rate of −11.66% of the total value of projects according to the bill of quantities and an arithmetic average rate of −10.47%.
3.2. The Design and Tender Document Quality
3.3. The Owner Team Changes
3.4. The Changes in Disciplines Scope and Value
3.5. The Effect of Changes in Projects on Claims and Disputes
3.6. Variation Order Management (VOM) as a Proposed Support Methodology
- Weakness of the tender document’s preparation by the designer, whether for design work, quantification, or conflict between documents, is among the most important causes of changes/variation orders and sources of claims and disputes.
- An integrated and quantitative specific system of procedures helps the owner to manage and control changes and variation orders in a planned manner at the entire project level and not in a partial phase.
- Using preventive control for variation did not depend on the work progress.
- Procedures to avoid lack of technical and financial control over time, cost, quality, and scope reduce the risk of claims and disputes.
3.6.1. Procedures in the Initiation Process Stage
- An inventory of the architectural, civil, electrical, and mechanical works, comparing them to the tender documents, which is the responsibility of the contractor and needs the approval of the supervising authority and the owner using the Building Information Modeling (BIM) and REVIT program.
- Presenting and approving long-term item schedules (long lead items) for all disciplines, anticipating the time of supply and installation, which are the responsibility of the contractor and require the approval of the supervising authority and the owner using the PRIMAVERA program.
- Specifying the cost of the architectural, civil, electrical, and mechanical works, which is the responsibility of the supervising authority and requires the approval of the owner using the bill of quantities and specifications.
- Specifying the influence of stakeholders on approving, which is the responsibility of the owner using meetings and specific models.
- Specifying a record of previous risks, which is the responsibility of the owner using site surveys, interviews, presentations, and site visits.
- Specifying a list of approved suppliers and sub-contractors, which is the responsibility of the owner using site surveys, interviews, presentations, and site visits.
- The approval of all calculations for structural, mechanical, and electrical systems is the responsibility of suppliers and subcontractors and requires the approval of the owner using programs such as SAP.
3.6.2. Procedures for Dealing with the Course of Change Orders Stage
- Conducting the initial determination of the reason for the request to make a variation order if it is a formal request from the stakeholders, improving the quality or technological progress or an inevitable technical necessity, and then agreeing to continue the study with technical and financial analysis or refusing to study the change order.
- Procedures for studying and analyzing the quantitative criteria, technically and financially, to determine the degree of approval or disapproval of a change order, which can be controlled through the four main focuses in the project management methodology (quality, cost, lifecycle, and project scope).
- Inspection by the specialists of technical, financial, and contractual analysis: first, the quality department to prove compliance with the technical specifications of the item with a rate of 30%; second, the scheduling department to study the impact on the project time and supply and installation time with a rate of 30%; third, other technical departments for determining the impact and technical and financial relationship with a rate of 20%; fourth, the department of accounting and finance to determine its impact on the cost of the technical department with a rate of 10%; and fifth, using value engineering to study alternatives for cost, supply time, installation time, and technical compliance with item specifications at a rate of 30%. Figure 10 illustrates the methodology of the VOM approach as a significant finding for this study.
3.6.3. Procedures for the Decision Stage
4. Conclusions
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
References
- Construction Extension to the Pmbok® Guide, PMI Institute. 2021. Available online: http://faspa.ir/wp-content/uploads/2017/03/faspa.ir-Constrauction.pdf (accessed on 10 January 2024).
- AIA Document A201–2017 General Conditions of the Contract for Construction; American Institute of Architects: Washington, DC, USA, 2017.
- Mahamid, I. Effect of change orders on rework in highway projects in Palestine. J. Financ. Manag. Prop. Constr. 2017, 22, 62–76. [Google Scholar] [CrossRef]
- Hussein, A.F.F.; Al-Mamary, Y.H. S, Conflicts: Their types, and their negative and positive effects on organizations. Int. J. Sci. Technol. Res. 2019, 8, 10–13. [Google Scholar]
- Hughes, W.; Champion, R. Construction Contracts: Law and Management; Routledge: London, UK, 2021; Volume 87. [Google Scholar]
- Balbaa, A.A.K.; El-Nawawy, O.A.M.; El-Dash, K.M.; El-Mageed Badawy, M.B.A. Risk assessment for causes of variation orders for residential projects. J. Eng. Appl. Sci. 2019, 14, 701–708. [Google Scholar]
- Mohammad, N.; Ani, A.I.C.; Rakmat, R.A.O. Causes and effects of variation orders in the construction of terrace housing projects: A case study in the state of Selangor, Malaysia. Int. J. Supply Chain Manag. 2017, 6, 226–232. [Google Scholar]
- Naji, K.K.; Gunduz, M.; Naser, A.F. The effect of change-order management factors on construction project success: A structural equation modeling approach. J. Constr. Eng. Manag. 2022, 148, 04022085. [Google Scholar] [CrossRef]
- Msallam, M.; Abojaradeh, M.; Jrew, B.; Zaki, I. Controlling of variation orders in highway projects in Jordan. J. Eng. Archit. 2015, 3, 95–104. [Google Scholar] [CrossRef]
- Khanzadi, M.; Nasirzadeh, F.; Dashti, M.S. Fuzzy cognitive map approach to analyze causes of change orders in construction projects. J. Constr. Eng. Manag. 2018, 144, 04017111. [Google Scholar] [CrossRef]
- Mohammad, K.H.; Ali, N.S.; Najm, B.M. Assessment of the cost and time impact of variation orders on construction projects in Sulaimani governorate. J. Eng. 2021, 27, 106–125. [Google Scholar] [CrossRef]
- Alsuliman, J.A. Effective Stakeholder Engagement in Variation Order Management at the Design Stage of Public Sector Construction Projects in Saudi Arabia. Ph.D. Thesis, Heriot-Watt University, Edinburgh, UK, 2014. [Google Scholar]
- El-Sayegh, S.; Ahmad, I.; Aljanabi, M.; Herzallah, R.; Metry, S.; El-Ashwal, O. Construction disputes in the UAE: Causes and resolution methods. Buildings 2020, 10, 171. [Google Scholar] [CrossRef]
- Hayati, K.; Latief, Y. Risk analysis and prevention system to minimize claim and dispute on construction projects. IOP Conf. Ser. Earth Environ. Sci. 2019, 365, 012030. [Google Scholar] [CrossRef]
- Illankoon, I.M.C.S.; Tam, V.W.; Le, K.N.; Ranadewa, K.A.T.O. Causes of disputes, factors affecting dispute resolution and effective alternative dispute resolution for Sri Lankan construction industry. Int. J. Constr. Manag. 2019, 22, 1–11. [Google Scholar] [CrossRef]
- Nachatar, J.S.; Hussin, A.A.; Omran, A. Variations in government contract in Malaysia. Manag. J. 2010, 12, 40–53. [Google Scholar]
- Oyewobi, L.O.; Jimoh, R.; Ganiyu, B.O.; Shittu, A.A. Analysis of causes and impact of variation order on educational building projects. J. Facil. Manag. 2016, 14, 139–164. [Google Scholar] [CrossRef]
- Mahmoud, S.Y.; Elshaikh, E.A. The potential effects of variation orders on building projects in Khartoum State-Sudan. Int. J. Constr. Eng. Manag. 2019, 8, 70–79. [Google Scholar]
- Gobana, A.B.; Thakur, A.S. Critical review on causes and effects of variation order on construction project. Crit. Rev. 2017, 4, 1602–1606. [Google Scholar]
- Enshassi, A.; Arain, F.; Al-Raee, S. Causes of variation orders in construction projects in the Gaza Strip. J. Civ. Eng. Manag. 2010, 16, 540–551. [Google Scholar] [CrossRef]
- Sadewo, A.P. Identifying Causes, Effects, Benefits, and Remedies of Change Orders on Building Projects in Yogyakarta. Ph.D. Thesis, Uajy, Sleman, Indonesia, 2018. [Google Scholar]
- Demirkesen, S.; Ozorhon, B. Impact of integration management on construction project management performance. Int. J. Proj. Manag. 2017, 35, 1639–1654. [Google Scholar] [CrossRef]
- Diekmann, J.E.; Nelson, M.C. Construction claims: Frequency and severity. J. Constr. Eng. Manag. 1985, 111, 74–81. [Google Scholar] [CrossRef]
- Assaf, S.A.; Al-Hejji, S. Causes of delay in large construction projects. Int. J. Proj. Manag. 2006, 24, 349–357. [Google Scholar] [CrossRef]
- Desai, N.; Pitroda, J.; Bhavsar, J. A review of change order and assessing causes affecting change order in construction. Int. Acad. Res. Multidiscip. 2015, 2, 152–162. [Google Scholar]
- Bakhary, N.A.; Adnan, H.; Ibrahim, A. A study of construction claim management problems in Malaysia. Procedia Econ. Financ. 2015, 23, 63–70. [Google Scholar] [CrossRef]
- Arain, F.M. Strategic management of variation orders for institutional buildings: Leveraging on information technology. Proj. Manag. J. 2005, 36, 66–77. [Google Scholar] [CrossRef]
- Memon, A.H.; Rahman, I.A.; Hasan, M.F.A. Significant causes and effects of variation orders in construction projects. Res. J. Appl. Sci. Eng. Technol. 2014, 7, 4494–4502. [Google Scholar] [CrossRef]
- Elziny, A.A.; Mohamadien, M.A.; Ibrahim, H.M.; Fattah, M.A. An expert system to manage dispute resolutions in construction projects in Egypt. Ain Shams Eng. J. 2016, 7, 57–71. [Google Scholar] [CrossRef]
- Alnuaimi, A.; Taha, R.; Mohsin, M.; Alharthi, A. Causes, Effects, Benefits, and Remedies of Change Order on Public Construction Projects in Oman. J. Constr. Eng. Manag. 2010, 136, 615–622. [Google Scholar] [CrossRef]
- Ndihokubwayo, R. An Analysis of the Impact of Variation Orders on Project Performance. Ph.D. Thesis, Cape Peninsula University of Technology, Cape Town, South Afirca, 2008. [Google Scholar]
- Tran, N.N.; Do, S.T.; Nguyen, T.A.; Le, L.H. Variation Order Management in Vietnam Construction Projects; Springer: Singapore, 2020; pp. 1007–1014. [Google Scholar]
- Soliman, E. Recommendations to mitigate delay causes in Kuwait construction projects. Am. J. Civil Eng. Archit. 2017, 5, 253–262. [Google Scholar] [CrossRef]
- Ammar, Y. Management of Change in Construction Projects—Study of Its Causes and Analysis of Its Effects on Claims and Disputes; Faculty of Engineering in Matarya—Helwan University: Cairo, Egypt, 2016. [Google Scholar]
- International Federation of Consulting Engineers. FIDIC Conditions of Contract for Construction for Building and Engineering Works Designed by the Employer; International Federation of Consulting Engineers: Geneva, Switzerland, 1999. [Google Scholar]
- Khalifa, W.M.; Mahamid, I. Causes of change orders in construction projects. Eng. Technol. Appl. Sci. Res. 2019, 9, 4956–4961. [Google Scholar] [CrossRef]
- Rashid, I.; Elmikawi, M.; Saleh, A. The impact of change orders on construction projects sports facilities case study. J. Am. Sci. 2012, 8, 628–631. [Google Scholar]
- Zawawi, N.A.W.A.; Azman, N.F.I.N.; Kamar, S.; Shamil, M. Sustainable construction practice: A review of change orders (CO) in construction projects. In Proceedings of the International Conference on Environment, Pulau Pinang, Malaysia, 23–25 March 2010. [Google Scholar]
- Arun, C.O.; Rao, B.N. Knowledge based decision support tool for duration and cost overrun analysis of highway construction projects. J. Inst. Eng. 2007, 88, 27–33. [Google Scholar]
- Wu, C.; Hsieh, T.; Cheng, W. Statistical Analysis of Causes for Design Change in Highway Construction in Taiwan. Int. J. Proj. Manag. 2005, 23, 554–563. [Google Scholar] [CrossRef]
- Alaryan, A.; Beltagi, E.; Elshahat, A.; Dawood, M. Causes and effects of change orders on construction projects in Kuwait. Int. J. Eng. Res. Appl. 2014, 4, 1–8. [Google Scholar]
- Soomro, F.A.; Memon, M.J.; Chandio, A.F.; Sohu, S.; Soomro, R. Causes of time overrun in construction of building projects in Pakistan. Eng. Technol. Appl. Sci. Res. 2019, 9, 3762–3764. [Google Scholar] [CrossRef]
- Dastyar, B.; Esfahani, A.F.; Askarifard, M.; Abbasi, A.M. Identification, Prioritization and Management of Construction Project Claims. J. Eng. Proj. Prod. Manag. 2018, 8, 90–96. [Google Scholar] [CrossRef]
- Hanna, A.; Camlic, R.; Peterson, P.; Lee, M. Cumulative effect of project changes for electrical and mechanical construction. J. Constr. Eng. Manag. 2004, 130, 762–771. [Google Scholar] [CrossRef]
- Perkins, R.A. Sources of changes in design/build contracts for a governmental owner, management of engineering and technology. Portland Int. Cent. Publ. 2009, 5–9, 2148–2153. [Google Scholar]
- Hwang, B.G.; Zhu, L.; Ming, J.T.T. Factors affecting productivity in green building construction projects: The case of Singapore. J. Manag. Eng. 2017, 33, 04016052. [Google Scholar] [CrossRef]
- Johnson, J. Practitioner’s Forum: Construction Quality Assurance under Change Conditions. J. Archit. Eng. 2000, 6, 103–104. [Google Scholar] [CrossRef]
- McEniry, G.; Ibbs, W. The cumulative effect of change orders on labour productivity: The Leonard study ‘reloaded’. Revay Rep 2007, 26, 1–8. [Google Scholar]
- Sun, M.; Sexton, M.; Aouad, G.; Fleming, A.; Senaratne, S.; Anumba, C.; Chung, P.; El-Hamalawi, A.; Motawa, I.; Yeoh, M.L. Managing changes in construction projects. EPSRC Ind. Rep. 2004, 185–190. [Google Scholar]
- Love, P.; Irani, Z.; Edwards, D. A Rework Reduction Model for Construction Projects. IEEE Trans. Eng. Manag. 2004, 51, 426–440. [Google Scholar] [CrossRef]
- Osama, M.; Assem, I.; El-Rayes, K. Change order impacts on labor productivity. J. Constr. Eng. Manage. 2005, 13, 354–359. [Google Scholar]
- Ibbs, W.; Nguyen, L.D.; Lee, S. Quantified impacts of project change. J. Prof. Issues Eng. Educ. Pract. 2007, 133, 45–52. [Google Scholar] [CrossRef]
- Assbeihat, J.M.; Sweis, G.J. Factors affecting change orders in public construction projects. Int. J. Appl. 2015, 5, 56–63. [Google Scholar]
- Hao, Q.; Shen, W.; Neelamkavil, J.; Thomas, R. Change management in construction projects. In Proceedings of the International Conference on Information Technology in Construction, Beijing, China, 16–18 October 2008. [Google Scholar]
- Yadeta, A.E. The impact of variation orders on public building projects. Int. J. Constr. Eng. Manag. 2016, 5, 86–91. [Google Scholar]
- Alnaas, K.A.A.; Khalil, A.H.H.; Nassar, G.E. Guideline for preparing comprehensive extension of time (EoT) claim. HBRC J. 2014, 10, 308–316. [Google Scholar] [CrossRef]
- Thani, H.A.; Saleh, M.E.; Amer, N.H. Identification and analysis of main reasons of variation orders and their impacts during construction project life cycle. In Proceedings of the International Conference on Civil and Architecture Engineering, Cairo, Egypt, 3–5 April 2018; pp. 1–19. [Google Scholar]
- Quarter Report, Quality Control Department; New Administration Project; King Faisal University: Al-Hofuf, Saudi Arabia, 2017.
- Accountant Department Report; New Administration Project; King Faisal University: Al-Hofuf, Saudi Arabia, 2017.
- Final Reports, Change Orders, Invoices, (APTEC–ALKIFAH–ALARAB—ALKHODARY–SOUTH STAR) Contractor Head Quarter; New Administration Project; King Faisal University: Al-Hofuf, Saudi Arabia, 2017.
Study Case Project | Variation Orders | Invoice Item Quantity | ||||
---|---|---|---|---|---|---|
Addition Million Saudi Riyals | Deduction Million Saudi Riyals | VO Quantity Number | Value Percent % | |||
1 | Dormitories (Boys and Girls) | 20.3 | 12.2 | 5 | 10 | 2090 |
2 | Main Administration | 2.3 | 6.8 | 8 | 8.4 | 600 |
3 | Mosque | 2.3 | 6.8 | 8 | 8.4 | 330 |
4 | Computer sciences college (Boys) | 11.2 | 1.4 | 9 | 8.7 | 610 |
5 | Computer sciences college (Girls) | 15.9 | 11.7 | 11 | 3.9 | 1156 |
6 | Science college | 11.2 | 11.3 | 11 | 0.3 | 1208 |
7 | English language | 4.9 | 4.1 | 12 | 0.1 | 1026 |
8 | Education college | 14.5 | 8.5 | 15 | 3.2 | 681 |
9 | Activity (Boys) | 17.6 | 7.8 | 12 | 4 | 326 |
10 | Activity (Girls) | 17.7 | 7.9 | 12 | 5.5 | 485 |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2024 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Ismaeil, E.M.H.; Sobaih, A.E.E. A Proposed Model for Variation Order Management in Construction Projects. Buildings 2024, 14, 726. https://doi.org/10.3390/buildings14030726
Ismaeil EMH, Sobaih AEE. A Proposed Model for Variation Order Management in Construction Projects. Buildings. 2024; 14(3):726. https://doi.org/10.3390/buildings14030726
Chicago/Turabian StyleIsmaeil, Esam M. H., and Abu Elnasr E. Sobaih. 2024. "A Proposed Model for Variation Order Management in Construction Projects" Buildings 14, no. 3: 726. https://doi.org/10.3390/buildings14030726
APA StyleIsmaeil, E. M. H., & Sobaih, A. E. E. (2024). A Proposed Model for Variation Order Management in Construction Projects. Buildings, 14(3), 726. https://doi.org/10.3390/buildings14030726