Proposed New Analytical Method of Tower Load in Large-Span Arch Bridge Cable Lifting Construction
Abstract
:Featured Application
Abstract
1. Introduction
- Based on the deformation coordination principle and suspension cable theory, the calculation method of the forces acting on a tower by a cable system when the rated load is lifted and moved on the main cable during the construction of an arch bridge is proposed.
- The correctness of the calculation method was verified by measuring the displacements of the tower tops.
- The calculation method is applied to tower analysis, and the method and example of tower refinement analysis is presented.
2. Proposed Calculation Method
2.1. Simplification of Calculation Model and Basic Assumptions
- It is assumed that the cable is flexible and can only bear tension;
- The stress–strain curve of the cable varies linearly, which means that it conforms to the generalized Hooke’s law;
- The cross-sectional area of the cable does not change when the cable is under force;
- The self-weight load of the cable is uniformly distributed along the span length;
- The cable is absolutely flexible and cannot be used to bear bending moments in any section.
2.2. The Acting Force of Main Cable to Tower
2.3. The Acting Force of Lifting Cable to Tower
2.4. The Acting Force of Towing Cable to Tower
3. Accuracy Verification of Calculation Method
3.1. Engineering Overview
3.2. Numerical Model
3.2.1. Establishment of Numerical Model
3.2.2. Loads in Analysis
3.3. Measurement of Engineering Actual Data
3.4. Discussion and Analysis of Data
4. Application in Tower Analysis
4.1. Stability Analysis
4.2. Load-Carrying Capacity
4.3. Deformation Analysis
5. Conclusions
- Based on the principle of deformation coordination and some assumptions, a method of calculating the loads acting on towers caused by the cable system when the arch bridge is constructed by a cable lifting method is proposed. The method has the characteristics of high calculation accuracy and easy operation, which is conducive to the rapid analysis of cable lifting construction by engineers.
- A new Y-shaped arch bridge with a cable suspension construction was used as the research case to verify the correctness and accuracy of the calculation method by comparing the actual measured and calculated values of displacement at the top of the tower, and a detailed verification method and process were given.
- The purpose of the calculation method is to calculate and analyze the mechanical properties of the towers in cable lifting construction, so the calculation method is specifically applied to the engineering case using the formula method and finite element method to analyze the overall stability, carrying capacity, and deformation of the tower, and give some suggestions about the design of arch bridge cable lifting.
- The deformation of the tower will directly affect the linearity of the arch rib. To reduce the nonlinear effect of the wind cable sag and increase the restraining effect of the wind cable to the tower, the wind cable should be set with a certain initial tension. Use the means of pre-deflection of the installation displacement of the tower under the action of initial tension of wind cable, which can achieve the purpose of allowing the maximum forward and maximum backward displacement of the tower to tend to be close.
- The tower is the main carrying structure, and the cable tower is prone to longitudinal overall overturning instability, and the steel pipe columns of the buckle tower are prone to twisting instability. Therefore, in the process of designing the tower, efforts should be made to find a balance between increasing the stability safety redundancy and reducing the self-weight of the structure.
- The normal stress of the tower’s part of the pressurized rod or pressurized bending rod is larger, which is mainly diagonal rods for the universal rod, due to its length–width ratio being relatively large. During design, to ensure structural safety, the allowable stress should be increased 30% under the combined load of the temporary structure.
- The steel pipe columns of towers are prone to compression bending instability, so their load-carrying capacity and deformation are analyzed in detail. The normal stresses on the top and bottom of the steel pipe columns will increase suddenly and should be given attention during design. The deformation analysis results of the tower show that the deformation trend on both sides of the tower is opposite and antisymmetric by the center line, which is consistent with the torsional instability results. Since the tower has relatively higher redundancy of compressive load-carrying capacity and smaller deformation safety reserve, therefore, the design can reduce the angle between the main cable behind the tower and the horizontal plane so as to reduce the horizontal thrust of the cable system to the tower, and then reduce the displacement of the tower by the thrust.
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Conflicts of Interest
References
- Chen, B.C.; Liu, J.P. Review of construction and technology development of arch bridges in the world. J. Traffic Transp. Eng. 2020, 20, 27–41. (In Chinese) [Google Scholar] [CrossRef]
- Zheng, J.L.; Wang, J.J. Concrete-Filled Steel Tube Arch Bridges in China. Engineering 2018, 4, 143–155. [Google Scholar] [CrossRef]
- Kang, C.J.; Schneider, S.; Wenner, M.; Marx, S. Development of design and construction of high-speed railway bridges in Germany. Eng. Struct. 2018, 163, 184–196. [Google Scholar] [CrossRef]
- Liu, J.P.; Chen, B.C.; Li, C.; Zhang, M.J.; Mou, T.M.; Tabatabai, H. Recent Application of and Research on Concrete Arch Bridges in China. Struct. Eng. Int. 2022, 5, 1–5. [Google Scholar] [CrossRef]
- Zheng, J.L.; Du, H.L.; Mu, T.M.; Liu, J.P.; Qin, D.Y.; Mei, G.X.; Tu, B. Innovations in Design, Construction, and Management of Pingnan Third Bridge-The Largest-Span Arch Bridge in the World. Struct. Eng. Int. 2022, 32, 134–141. [Google Scholar] [CrossRef]
- Li, Y.Z. Key Construction Techniques for Main Bridge of Yachi River Bridge on Chengdu-Guiyang Railway. Bridge Constr. 2020, 50, 16–21. (In Chinese) [Google Scholar] [CrossRef]
- Zhou, Z.X.; Fan, L.; Wang, S.R.; Liao, X.F. Chongqing Wansheng Zaodu Bridge-Steel Box-Concrete Composite Arch Bridge. Struct. Eng. Int. 2013, 23, 71–74. [Google Scholar] [CrossRef]
- Lei, J.H.; He, X.H. Green construction technology of a deck-arch railway bridge with concrete-filled steel-tube ribs in canyon area. J. Railw. Sci. Eng. 2020, 17, 3104–3110. (In Chinese) [Google Scholar] [CrossRef]
- Tang, M.C.; Ren, G.L. Design and Construction of the Main Spans of the Chongqing Caiyuanba Bridge, China. Struct. Eng. Int. 2010, 20, 296–298. [Google Scholar] [CrossRef]
- Wang, R. Key Construction Techniques for Long-Span Railway Arch Bridge in Mountainous Region of Plateau. Bridge Constr. 2020, 50, 105–110. (In Chinese) [Google Scholar] [CrossRef]
- Xie, K.Z.; Wang, H.W.; Guo, X.; Zhou, J.X. Study on the safety of the concrete pouring process for the main truss arch structure in a long-span concrete-filled steel tube arch bridge. Mech. Adv. Mater. Struct. 2021, 28, 731–740. [Google Scholar] [CrossRef]
- Huang, Q.; Wu, X.; Wei, H.; Chen, Q. Innovative Design of Novel Main and Secondary Arch Collaborative Y-Shaped Arch Bridge and Research on Shear Lag Effect of Its Unconventional Thin-Walled Steel Box Arch Ribs. Appl. Sci. 2022, 12, 8370. [Google Scholar] [CrossRef]
- Zhou, J.X. Research on Cable Force Calculation Method of Cable-Stayed Fastening Hanging Methods of Long Span Concrete Filled Steel Tube Arch Bridge. Master’s Thesis, Guangxi University, Nanning, China, June 2022. (In Chinese). [Google Scholar] [CrossRef]
- Pan, Q.; Yi, Z.P.; Zeng, Y.Y.; Yan, D.H.; Yang, S.J. Research on the Free Vibration of the Arch Bridge During Cable Hoisting or Rotation Erection Using an Analytical Modeling. J. Vib. Eng. Technol. 2022, 10, 1021–1035. [Google Scholar] [CrossRef]
- Han, Y.; Yang, Z.F.; Qin, D.Y.; Zheng, J. Key Technologies and Innovations in the Construction of Matan Hongshui River Super-Large Bridge. In Proceedings of the ARCH 2019 9th International Conference on Arch Bridges, Structural Integrity (STIN 11), Porto, Portugal, 2–4 October 2019; Springer: Cham, Switzerland, 2020; pp. 578–585. [Google Scholar] [CrossRef]
- Drag, L. Application of dynamic optimisation to the trajectory of a cable-suspended load. Nonlinear Dyn. 2016, 84, 1637–1653. [Google Scholar] [CrossRef]
- Bao, J.H.; Zhang, P.; Zhu, C.M. Dynamic Analysis of Flexible Hoisting Rope with Time-Varying Length. Int. Appl. Mech. 2015, 51, 710–720. [Google Scholar] [CrossRef]
- Chen, Z.H.; Sun, H.X.; Zhou, S.X.; Chen, Z.S.; Xue, X.Y.; Peng, Y.J. A Hybrid Algorithm for Cable Force Calculation of CFST Arch Brides During Construction. Int. J. Robot. Autom. 2022, 37, 192–199. [Google Scholar] [CrossRef]
- Xiong, S.H.; Chen, W.; Wang, F. Calculating Method of Arch Rib Installation Alignment of Large Span Cable Hoisting Arch Bridge. In Proceedings of the International Conference on Smart Transportation and City Engineering, Chongqing, China, 26–28 June October 2021; Spie: Bellingham, WA, USA, 2021. [Google Scholar] [CrossRef]
- Zhou, Q.; Zhou, J.T.; Ma, H.; Li, X.G.; Zhang, L. Improved algorithm of cable force for one-time cable tensioning on steel tube arch ribs with segmental hoisting. J. Traffic Transp. Eng. 2020, 20, 92–101. (In Chinese) [Google Scholar] [CrossRef]
- Wu, Y.H.; Liang, S.; Zhao, W.D. Design and Application of Bidirectional Moving Cable Crane of Tuoba Bridge. Bridge Constr. 2017, 47, 117–121. (In Chinese) [Google Scholar] [CrossRef]
- Deng, N.C.; Yu, M.S.; Yao, X.Y. Intelligent Active Correction Technology and Application of Tower Displacement in Arch Bridge Cable Lifting Construction. Appl. Sci. 2021, 11, 17. [Google Scholar] [CrossRef]
- Liu, Z.W.; Zhou, J.T.; Wu, Y.X.; You, X.; Qu, Y.H. Linear Control Method for Arch Ring of Oblique-Stayed Buckle Cantilever Pouring Reinforced Concrete Arch Bridge. Adv. Civ. Eng. 2021, 2021, 14. [Google Scholar] [CrossRef]
- Li, J.; Du, G.P.; Liang, Y.; He, Z.; Yan, X.; Feng, Y.L. Construction Analysis and Monitoring of the Vertical Rotation of Steel Tube Arch Ribs. Struct. Eng. Int. 2021, 31, 45–50. [Google Scholar] [CrossRef]
- Yu, X.M.; Chen, D.W. Innovative Method for the Construction of Cable-Stayed Bridges by Cable Crane. Struct. Eng. Int. 2018, 28, 498–505. [Google Scholar] [CrossRef]
- Wang, Y.; Wei, Y.H.; Hu, G.F. Construction Control Technology of Cable Hoisting System for the Arch Rib of Steel Box Bridge. In Proceedings of the 4th International Conference on Structures and Building Materials (ICSBM), Guangzhou, China, 15–16 March 2014; Trans Tech Publications Ltd.: Wollerau, Switzerland, 2014. [Google Scholar] [CrossRef]
- Yu, X.M.; Chen, D.W.; Bai, Z.Z. A New Method for Analysis of Sliding Cable Structures in Bridge Engineering. KSCE J. Civ. Eng. 2018, 22, 4483–4489. [Google Scholar] [CrossRef]
- Zhang, W.Y.; Yu, S.L.; Zhang, X.W.; Yan, J.S.; Chen, X.X. Construction Process Simulation and In Situ Monitoring of Dendritic Structure on Nanjing Niushou Mountain. Shock Vib. 2019, 2019, 13. [Google Scholar] [CrossRef]
- Li, Y.Z.; Li, H.H.; Xu, B.A. Jinsha River Bridge, China: The world’s first double-deck road and high-speed railway arch bridge. Proc. Inst. Civ. Eng.-Bridge Eng. 2020, 173, 179–189. [Google Scholar] [CrossRef]
- Zhao, C.Y.; Yang, W.S.; Li, C.X.; Tan, L.X. Study on static analysis and working performance of the main cable system in the cable-hoisting system. J. Guangxi Univ. 2010, 35, 615–620. (In Chinese) [Google Scholar] [CrossRef]
- Li, P. Discussion of Medium-Bearing Space Y-shaped Steel Box Arch Bridge Cable Suspension Main Cable Load-Bearing Safety Analysis. Sichuan Cement. 2021, 4, 335–337. (In Chinese) [Google Scholar]
- Huang, Q.; Wu, X.G.; Hu, K.J.; Xu, N. Design of Cable Suspension System for Spatial Y-shaped Steel Box Arch Bridge in V-shaped Canyon Area. In Proceedings of the World Forum on Transport Engineering and Technology (WTC2021), Xi’an, China, 16–18 June 2021. (In Chinese). [Google Scholar] [CrossRef]
- JTG D60-2015; Industry Standard of the People’s Republic of China; General Specifications for Design of Highway Bridges and Culverts. Industry Standard of the People’s Republic of China: Beijing, China, 2015.
(kN/m) | (m) | (m) | (m) | (m) | (m) | (m) | (m) | (°) | (°) | (m) |
1.346 | 2.5 | 430 | 207.5 | 15 | 68 | 65 | 360 | 23.0 | 34.1 | 20.5 |
(m) | (m) | (kN) | (°) | (°) | (°) | (ton) | (kN/m) | (m) | ||
18.9 | 21.3 | 71.7 | 0.33 | 0.98 | 22.6 | 34.3 | 67.5 | 0.012 | 0.196 | 24 |
Brand | Density (kg/m3) | Elastic Modulus (MPa) | Poisson’s Ratio | Yield Strength (MPa) | Ultimate Strength (MPa) |
---|---|---|---|---|---|
Q235 | 7850 | 206,000.00 | 0.30 | 235 | 370 |
Q345 | 7850 | 205,000.00 | 0.30 | 345 | 470 |
Bank Site | Designation of Wind Cable | Specification of Steel Cable | Ai (mm2) | T0i (kN) | |
---|---|---|---|---|---|
Left | Inter-span wind cable for cable tower | 1φ56 mm Fiber-core steel cable (6 × 37S + FC 1670 Mpa) | 1233.8 | 400.000 | 4.288 × 10−3 |
Wind cable behind cable tower | 6φ32 mm Steel-core steel cable (6 × 37S + IWR 1670 Mpa) | 2807.2 | 433.217 | 1.470 × 10−3 | |
Cross-wind cable for cable tower | 6φ22 mm Fiber-core steel cable (6 × 37S + FC 1670 Mpa) | 1142.5 | 391.622 | 4.534 × 10−3 | |
Wind cable before sling tower | 1142.5 | 416.909 | 4.827 × 10−3 | ||
Wind cable behind sling tower | 1142.5 | 301.433 | 3.490 × 10−3 | ||
Cross-wind cable for sling tower | 1142.5 | 346.410 | 4.011 × 10−3 | ||
Right | Inter-span wind cable for cable tower | 1φ56 mm Fiber-core steel cable (6 × 37S + FC 1670 Mpa) | 1233.8 | 400.000 | 4.288 × 10−3 |
Wind cable behind cable tower | 6φ32 mm Steel-core steel cable (6 × 37S + IWR 1670 Mpa) | 2807.2 | 484.204 | 1.643 × 10−3 | |
Cross-wind cable for cable tower | 6φ22 mm Fiber-core steel cable (6 × 37S + FC 1670 Mpa) | 1142.5 | 391.622 | 4.534 × 10−3 | |
Wind cable before sling tower | 1142.5 | 422.718 | 4.894 × 10−3 | ||
Wind cable behind sling tower | 1142.5 | 318.019 | 3.682 × 10−3 | ||
Cross-wind cable for sling tower | 1142.5 | 346.410 | 4.011 × 10−3 |
Tower Site | Load Category | Main Cable | Towing Cable | Lifting Cable | Sum | |
---|---|---|---|---|---|---|
Empty Cable | Loaded Cable | |||||
Left bank | 157.294 | 462.258 | 7.389 | 6.628 | 633.569 | |
1396.352 | 4037.225 | 55.919 | 73.244 | 5562.74 | ||
Right bank | 398.077 | 1163.234 | 43.800 | 1605.111 | ||
1880.204 | 5445.233 | 185.026 | 7510.463 |
Load Condition | Tower Site | Longitudinal Displacement | Transversal Displacement | Vertical Displacement |
---|---|---|---|---|
1 | Left bank | −41.2 | 0 | 7.7 |
Right bank | 192.1 | −5.7 | −20.5 | |
2 | Left bank | −28.4 | 0 | −7.0 |
Right bank | 134.4 | 0 | −18.3 | |
3 | Left bank | −43.1 | 0 | −8.9 |
Right bank | 194.2 | 2.5 | −22.1 |
Load Condition | Tower Site | Longitudinal Displacement | Transversal Displacement | Vertical Displacement |
---|---|---|---|---|
1 | Left bank | −43.6 | 0.4 | −8.8 |
Right bank | 197.1 | −6.2 | −22.8 | |
2 | Left bank | −29.7 | −0.5 | −7.6 |
Right bank | 138.7 | −1.2 | −20.0 | |
3 | Left bank | −45.3 | −1.4 | −9.7 |
Right bank | 199.4 | 3.4 | −24.2 |
Load Condition | Tower Site | Longitudinal Displacement | Transversal Displacement | Vertical Displacement |
---|---|---|---|---|
1 | Left bank | 2.4 | 0.4 | 1.1 |
Right bank | 5.0 | 0.5 | 2.3 | |
2 | Left bank | 1.3 | 0.5 | 0.6 |
Right bank | 4.3 | 1.2 | 1.7 | |
3 | Left bank | 2.2 | 1.4 | 0.8 |
Right bank | 5.2 | 0.9 | 2.1 |
Load Condition | Load Combination | Load Condition | Load Combination | Load Condition | Load Combination |
---|---|---|---|---|---|
1 | (1) + (2) + (3) + (6) | 5 | (1) + (2) + (5) + (6) | 9 | (3) |
2 | (1) + (2) + (3) + (8) | 6 | (1) + (2) + (5) + (8) | 10 | (4) |
3 | (1) + (2) + (4) + (6) | 7 | (1) + (2) + (7) | 11 | (5) |
4 | (1) + (2) + (4) + (8) | 8 | (1) + (2) + (9) | — | — |
Load Condition | Buckling Factor | Load Condition | Buckling Factor |
---|---|---|---|
1 | 8.01 | 5 | 7.52 |
2 | 8.02 | 6 | 7.53 |
3 | 8.15 | 7 | 22.91 |
4 | 8.16 | 8 | 23.13 |
Name of Component | Maximum Axial Force | Allowable Axial Force | Name of Component | Maximum Axial Force | Allowable Axial Force |
---|---|---|---|---|---|
Cable tower vertical rod | −2362.262 | −2660 | Buckle tower vertical rod | −523.017 | −1330 |
Cable tower diagonal rod | −693.515 | ±756 | Buckle tower diagonal rod | −498.708 | ±756 |
Cable tower horizontal rod | −570.826 | ±852 | Buckle tower horizontal rod | −246.033 | ±426 |
Name of Component | Maximum Normal Stress | Allowable Normal Stress | Maximum Shear Stress | Allowable Shear Stress |
---|---|---|---|---|
Cable tower distribution beam | −119.372 | ±210 | 19.243 | 120 |
Cable tower distribution beam connecting rod | 68.064 | ±145 | — | — |
Buckle tower distribution beam | −78.310 | ±145 | 49.878 | 85 |
Hinged seat distribution beam | 136.212 | ±210 | 48.221 | 120 |
Steel pipe column | −123.368 | ±210 | — | — |
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations. |
© 2022 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Huang, Q.; Wu, X.; Zhang, Y.; Ma, M. Proposed New Analytical Method of Tower Load in Large-Span Arch Bridge Cable Lifting Construction. Appl. Sci. 2022, 12, 9373. https://doi.org/10.3390/app12189373
Huang Q, Wu X, Zhang Y, Ma M. Proposed New Analytical Method of Tower Load in Large-Span Arch Bridge Cable Lifting Construction. Applied Sciences. 2022; 12(18):9373. https://doi.org/10.3390/app12189373
Chicago/Turabian StyleHuang, Qian, Xiaoguang Wu, Yunfei Zhang, and Min Ma. 2022. "Proposed New Analytical Method of Tower Load in Large-Span Arch Bridge Cable Lifting Construction" Applied Sciences 12, no. 18: 9373. https://doi.org/10.3390/app12189373
APA StyleHuang, Q., Wu, X., Zhang, Y., & Ma, M. (2022). Proposed New Analytical Method of Tower Load in Large-Span Arch Bridge Cable Lifting Construction. Applied Sciences, 12(18), 9373. https://doi.org/10.3390/app12189373