To evaluate the impact of various topological changes, such as the connections and disconnections of distributed generators, on the fault current perceived by the head relay, a sensitivity study was conducted on the CIGRE medium-voltage network with IIDG integration. This study considered three scenarios: pre-fault conditions for each level of IIDG penetration, fault conditions without IIDGs, and fault conditions with various levels of IIDG penetration. The results of this analysis provided the foundation for making adaptive adjustments to the head relay, which is essential for maintaining the effectiveness of the protection system amidst changes in network topology due to the integration of renewable generation sources.
4.1. Pre-Fault Condition
In this initial pre-fault scenario, a reduction in the RMS current magnitudes detected by the head relay is observed as the penetration of IIDGs increases. This trend is evident in
Table 1, where the highest current is recorded without the connection of IIDGs and the lowest is recorded with 60% penetration. Although this pattern is consistent across all three phases, for illustrative purposes, the variation of phase A is graphically presented in
Figure 5.
Given the fluctuation of currents due to the connection or disconnection of IIDGs, it is crucial to adaptively adjust the
based on the current state of the network instead of using a fixed threshold, as is customary in networks without IIDGs. As illustrated in
Table 1, if the
is set at twice the pre-fault current—resulting in 265.73 A—a
of 1.5 is obtained. However, maintaining a constant
results in significant deficiencies when faced with variations in IIDG penetration; for example, at a penetration level of 16%, the calculation of
is (1.5 × 2 × 114.472)/(2 × 132.865) ≈ 1.29, which is clearly below the value of 1.5. Similarly,
values for penetration levels of 33%, 44%, 50%, and 60% are 1.07, 0.93, 0.89, and 0.75, respectively. This indicates that a fixed
value for different network states causes relay underreach or blindness, which worsens with increased DG penetration, as shown in
Figure 6, where the
for all levels of penetration falls below 1.5.
An effective solution to this challenge involves adapting the based on the load current corresponding to the current state of the system (connection or disconnection of IIDGs). This ensures that the consistently remains at 1.5, allowing the protection system to adequately respond to the smallest fault in all topological states of the network. In this way, the overcurrent curve will always operate with an of 1.5, regardless of the connections or disconnections of the IIDGs. This adaptive adjustment resolves the issue of underreach or blindness of protections, a common consequence of the inclusion of IIDGs, and enhances the reliability and effectiveness of the protection system in the evolving network.
4.3. Fault Current Behavior with IIDGs
This study examines the influence of the fault location on the current detected by the head relay while maintaining a constant level of IIDG penetration. Branches T2-A, T2-B, and T2-C of the feeder were analyzed, as shown in
Figure 3. For each branch, the amplitudes of the fault currents observed by the head relay were measured, revealing that the magnitude of the fault current decreases as the fault point moves away from the feeder head. This phenomenon was consistently manifested across all branches, levels of DG penetration, and types of faults, which is similar to observations in systems without DGs. The current results for branch T2-C, with a 50% DG penetration, and the decreasing trend for three-phase faults are shown in
Figure 8, while
Table 3 presents the current results for feeder T2-C with a 50% IIDG penetration. Additionally, it was noted that short-circuit currents are lower in scenarios with DGs compared to those without DGs. The minimum current detected by relay R1 occurred with the maximum DG penetration, while the maximum fault current was recorded in the absence of DGs, especially near the substation during a three-phase fault.
Considering the calculation of the
multipliers, using Equation (4) and considering the adaptive
depending on each level of DG penetration as detailed in study 1 of this section, results were obtained as shown in
Table 4 for simulated faults in feeder T2-C at the 50% level of renewable generator penetration. From the results obtained, it can be concluded that regardless of the level of IIDG penetration in the network, the fault current will tend to decrease as it moves away from the feeder head, thereby maintaining the concept of the inverse-time overcurrent curve, as faults further from the substation will have a longer operation time of the relay-associated breaker, while for faults closer to the feeder head, this time decreases. On the other hand, as reflected in
Table 5, the data indicate that the fault current perceived by the head relay significantly decreases as the level of IIDG penetration increases, reaching the lowest value with 60% penetration. This suggests that a higher level of IIDG penetration leads to reduced fault currents, thus extending the operation time on the overcurrent curve and allowing the network to tolerate these currents for an extended period. In contrast, 0% IIDG penetration results in the maximum fault currents, which require a quicker relay response to ensure adequate network protection, as shown in
Figure 9.
In this context, the multiplier M, detailed in
Table 5, should tend to be lower for higher levels of IIDG penetration, while higher values of M are expected in scenarios without IIDG inclusion. Contrary to expectations, the simulation results show that M is lower when the fault current is at its maximum, implying a delay in the circuit breaker’s operation in the presence of high and severe currents, which should be interrupted almost instantaneously to protect the network. Additionally, M increases as the level of IIDG penetration increases, resulting in faster activation for lower currents. This behavior is contrary to what is desirable according to the logic of a typical overcurrent curve, where faults with high currents are expected to trigger faster actions, while faults with lower currents allow for a longer time interval before the breaker intervenes, as seen in
Table 5 and
Figure 10.
Therefore, it is evident that merely adjusting the pickup current for each system state—including the various states of connection or disconnection of the IIDGs—while effectively resolving the issues of protection blindness and delay in tripping also introduces a complication, as the M calculated for a level of penetration is greater than for a system without IIDGs, which contradicts the conventional overcurrent protection theory. To address this discrepancy, the M used for fault detection is adjusted. The mathematical expression for this adjustment is based on the premise that the maximum multiplier (
) is established from a simulated three-phase fault at the relay location for the scenario without connected DGs, as shown in Equation (5).
From
, it is inferred that the M calculated for variations in IIDG penetration will be lower than this value. Thus, with the increase in IIDG penetration, any fault along the feeder will result in a lower current magnitude compared to
. Consequently, all of the trip multipliers (
) are calculated based on the maximum pickup current, as per Equation (6).
Table 6 and
Table 7 present the results of the
calculations obtained from Equations (5) and (6), respectively. These calculations were performed for two fault locations on the T2-C branch: the fault at B1, which is closest to the substation, and the fault at B7, which is the furthest away. The purpose of these calculations is to verify the proper functionality of the proposed current multiplier, thus ensuring that the calculated values exceed 1.5. This guarantees that regardless of the type and location of the fault, the relay is sufficiently sensitive to detect faults under variations in the DGs.
As observed in
Table 6, the multipliers calculated from Equation (5), which only considers the adjustment of the adaptive pickup current without the proposed modification, were found to be greater than 1.5. However, an erroneous trend is identified in these values, as the multiplier increases in a way that is directly proportional to the increase in the DG penetration level. This is conceptually incorrect, as a higher multiplier value implies a reduced operation time theoretically for higher currents. However, as demonstrated throughout this article, the higher the level of DG penetration, the lower the current perceived by the relay, suggesting that the multiplier should decrease as the level of penetration increases, a trend not observed in
Table 6.
On the other hand, incorporating the proposed variation in Equation (6),
is determined for faults at bars B2 and B7 for different levels of penetration, as indicated in
Table 7. The results clearly show that the pickup multiplier decreases as the level of penetration increases, corroborating the premise that faults occurring under an increasing level of penetration produce lower fault currents and, therefore, require a longer operation time. Analyzing the two fault locations—the one closest to the substation at bar B2 and the farthest at B7—it is observed that the
calculated are lower for the fault farther from the head, while they increase for the fault closer to the substation. This confirms that the adjustment of the multiplier adequately considers the dynamic variation in the magnitude of the feeder current, which is influenced by various factors, such as different levels of IIDG penetration and the location of the fault.