1. Introduction to FMECA
Economic problems have forced electric utility providers to provide better quality electricity under lower operating and maintenance costs. Therefore, the effective and efficient use of transmission assets is of prime concern to gain maximum benefits, whereas maintenance costs should be reduced [
1,
2,
3,
4,
5,
6,
7,
8]. Currently, some high voltage (HV) transmission lines in Thailand are very old and deteriorated. From a database of technical information on overhead transmission lines in Thailand, approximately 35% of all transmission lines are over 30 years of age, which leads to a continual increase in the deterioration and failure of the line components. Consequently, new investments into the replacement and refurbishment of such aged and deteriorated transmission lines must be properly allocated according to the risk of transmission line usage. Therefore, a concrete transmission line condition assessment procedure should be developed to determine the actual risk of the transmission lines.
In general, the uprating, upgrading, or renovation/replacement of transmission lines have been performed to fulfill new system requirements, such as increasing the load current and short circuit current, as well as due to climate change [
9,
10,
11]. However, the criteria for deciding to engage in the uprating, upgrading, or renovation/replacement of transmission lines have not been clearly defined. Therefore, condition and importance assessments of the transmission lines and their components have been proposed based on the health index, importance index, reliability index, etc. [
12,
13,
14,
15,
16] to support this type of analysis. For this reason, transmission system risk assessments have challenged the utility and power industry to determine the actual risk in order to manage the relevant assets with optimal costs and maintain system reliability [
17,
18,
19,
20]. To fulfill the risk assessment, various aspects affecting the transmission system, such as condition, social and environmental concerns, safety and reliability, and financial costs have been considered [
21,
22,
23,
24].
The Failure Modes, Effects, and Criticality Analysis (FMECA) method, which has different applications in power systems [
25,
26,
27,
28,
29,
30], is a crucial technique for technical maintenance management. The key objectives of FMECA are to identify and analyze feasible severities and criticalities causing unwanted effects on system performance, to recognize system risks resulting in equipment damage and financial losses, to identify effective techniques for improving system reliability, and to provide proper maintenance planning to reduce system risk. Generally, the FMECA procedure involves breaking the system into components and exploring the failure modes and the associated effects for all components. Then, the severity and criticality of the components and the system are analyzed and plotted in a criticality matrix. The failure modes along and potential risk management of all the components and systems are prioritized. The FMECA is an effective tool to evaluate and improve system reliability, thereby reducing costs associated with maintenance, and is used in a wide range of industries.
In this paper, an FMECA analysis for overhead transmission network assets is proposed. For this study, 20 transmission lines in Thailand with actual data at 115, 230, and 500 kV are presented. The transmission lines and their components are shown in
Figure 1. The major components are classified into eight groups including conductor, conductor accessories, insulator, steel structure, foundation, lightning protection system, tower accessories, and right-of-way, as given in
Table 1. The sub-components are also given. The eight major components and their sub-components are classified according to their function, test, and inspection methods, as well as their order of inspection and installation location in the tower to facilitate convenient routine inspection.
To calculate the overall transmission line renovation index, we use the average percentage condition index (%CI
avg) of each component of a transmission tower along a transmission line, including the %CIC
avg for conductors, %CICA
avg for conductor accessories, %CII
avg for insulators, %CISS
avg for steel structures, %CIF
avg for foundations, %CILP
avg for lightning protection, %CITA
avg for tower accessories, and %CIRW
avg for right of way, as illustrated in
Figure 1. Then, a criticality analysis of the components and transmission lines is performed.
2. Criticality Analysis
The criticality analysis was performed by considering the occurrence and severity together. The severity is classified into four aspects, such as efficiency to identify the relationship between the failure frequency of the line and the actual conditions of the transmission tower. This sub-system is evaluated based on the inspection and test results. The safety/reliability is the second aspect that reflects the importance of the transmission line in the electrical system in terms of power transmission, redundancy, etc. The environment is the third aspect and reflects the impact from human activity, the operating environment, and pollution on transmission line failure. Finally, the financial aspect considers maintenance costs together with the actual conditions from the first aspect to support spare part management. The criticality of the transmission line is plotted in a criticality matrix, which is divided into four levels: low, medium, high, and very high risk. Maintenance strategies according to the obtained risk are also recommended.
For the criticality analysis of each criterion, both failure occurrence and severity are needed to calculate the criticality, as shown in Equation (1):
where CR is criticality, SE is severity, and OC is the occurrence of an individual severity criterion.
The occurrence implies a statistical record (events/year) of the malfunction or failure of the transmission lines. In
Table 2, the occurrence score is differentiated and classified into five levels from 1 to 5 (from low to high failure frequency).
Figure 2 shows the coordination of occurrence and severity plotted in a criticality matrix with 5 × 5 dimensions. The risk is classified into only 4 levels as low (L), moderate (M), high (H), and very high (VH) and differentiated into four color bands as green, yellow, orange, and red. The criticality is obtained by multiplying the severity with the occurrence of four severity criteria. The numbers 1–3, 4–9, 10–15, and 16–25 represent the risk as the L, M, H, and VH risk level, respectively. The aims of applying the L, M, H, and VH levels are to visually recognize issues for maintenance engineers and technicians, to realize the actual risk in the matrix of all components and transmission lines, and to reduce complexity while increasing simplicity in risk management and maintenance strategies, as mentioned in
Table 3.
The criticality of the transmission line components and sub-components can be plotted in the criticality matrix shown in
Figure 2. The risks of transmission line components are located under different colors depending on the conditions and risks. After the criticality levels of the transmission line components and sub-components are analyzed, the maintenance strategy, failure mitigation method, and spare part management [
31,
32,
33,
34,
35,
36] are addressed, as outlined in
Table 3.
4. Result and Discussion
In [
33], a web-application asset management program for transmission network maintenance was developed and subsequently used by a utility provider not only to record all of the technical data, inspection results, and maintenance costs of transmission line in the central database, but also to evaluate the condition of overhead transmission lines. After software implementation, all technical information of every transmission line was eventually recorded in the central database, while the inspection and test results were input online via the internet by a maintenance crew. This program is now widely used by all operation and maintenance divisions in their respective areas in the utility provider to evaluate the condition and risk of all 115, 230, and 500 kV transmission lines. In this way, the actual technical and testing data of 20 pilot transmission lines recorded by technicians and engineers from all responsible regions in Thailand were able to be quickly retrieved from the database for further analysis in this paper.
The 230 kV line no. 8 was selected as an example. In this line, four severity scores of the components belonging to tower no. 1 were determined, as shown in
Table 10. Finally, the criticality scores of the eight components with their symbols were calculated and are shown in
Table 11. The criticalities of the eight components regarding the efficiency, safety/reliability, environmental, and financial criteria were plotted in criticality matrices, as shown in
Figure 4. Almost all of the CR
efficiency values are located at zone 3 (the green zone) because of their very good condition with low risk. However, the CR
efficiency of the conductor and steel structure and insulator foundation are located at zones 6 and 9 and have medium risk. The CR
safety/reliability values of all the components are in zone 12 (the orange zone), indicating high risk. The CR
environment values are in zone 6, which is the yellow zone with medium risk because all components are located in the same tower and area. The CR
finance values are in zones 3, 6, and 9 with low and medium risk because of the maintenance costs of the components related to the condition of the equipment, as mentioned in
Section 3.2. Almost all of the sub-criteria are in a medium risk zone, except for the safety/reliability criterion, which needs a plan to reduce the importance of the components, i.e., short-term planning to reduce power transmission or medium planning to add parallel transmission lines. The recommended maintenance strategies are outlined in
Table 3.
Next, the severity and criticality of 20 transmission lines were determined. The criticality scores (CR) of all transmission lines were calculated and are summarized in
Table 12. These scores were then plotted in criticality matrices of efficiency, environment, safety/reliability, and finance, as shown in
Figure 5. The practical data of the 20 transmission lines are analyzed and summarized in
Table 13.
In
Table 12, the results show that the CR
finance of the 115 kV lines #7 and #12 fall in zones 20 and 16, which are classified as very high risk (red zone) because of the very high cost of their maintenance according to their condition with high failure occurrence. The CR
finance values of lines #4 and #15, as well as #1, #6, #10, #17, and #18, fall in zones 15 and 12, respectively. The failure causes of these lines must be closely observed. Otherwise, the number of failures could increase, leading to line efficiency and poor reliability of the system. In addition, the utility provider should pay more attention to maintenance and spare part management.
The CRefficiency values of lines #7 and #12 fall into zone 12 with high risk (orange zone) because of the poor condition of the lines with a very high number of failures. The ages of these lines are also greater than 30 years. Consequently, these lines are currently under short-term planning for line reconstruction because their actual conditions will not be able to fulfill system requirements in the near future. Similarly, lines #4 and #5 fall into zone 12 (high risk, orange zone) because of their moderate condition but also their high number of failures. Thus, the utility provider should determine the causes of failures and plan to reduce the number of failures, as well as plan to categorize those lines under the secondary priority for reconstruction planning because of their age. The other lines are in the orange zone and should be closely observed due to their problems.
The CRsafety/reliability values of lines #7 and #12 fall into zone 16, which indicates a very high risk (red zone) because of the low redundancy, high percentage loading, and age of the lines, while line #18 falls into zone 12, which indicates high risk (orange zone) due to a high percentage of loading and age, as well as operating at the highest (500 kV) level in the country. The importance of these lines must be reduced to maintain better reliability of the system by increasing the capability of the line loading. Then, the utility provider could plan to add a new line or parallel line for sharing the line loading. The CRsafety/reliability of lines #1, #8, #10, and #17 fall into zone 9, indicating high risk (orange zone) but a lower number of failures than lines #7 and #12. However, these lines are also more than 30 years old. Therefore, these lines should be given third priority for reconstruction planning, but the importance scores of these lines in terms of safety and reliability should be managed by reducing failure frequency.
The CR
environment values of lines #13 and #14 indicate high risk (orange zone) because of the pollution effected by animals and agriculture. These lines are located in important areas where blackouts may lead to complaints from customers. These areas must be intensively cared for with more frequent periods of maintenance. The analysis of all four critically criteria for the other transmission lines can use a similar process, and this analysis should be very detailed. The maintenance strategies outlined in
Table 3 should be referred to.
Using the FMECA method, the criticality scores shown in
Table 12 and the criticality matrices in
Figure 5 will be very useful for the utility provider to analyze risks under the different criteria of efficiency, environment, safety/reliability, and finance. In this way, the risk of all components and transmission lines can be carefully observed, and the risk can be easily managed in depth. Then, the utility provider can prioritize the maintenance tasks of transmission lines according to the risks of the lines. Thus, the maintenance strategy for and inventory of the components can be effectively managed, and future system planning for refurbishment or replacement, including future investments, can be properly conducted.
5. Conclusions
In this paper, an FMECA approach for the criticality and risk analysis of HV transmission lines was introduced. The severity criteria were efficiency, safety/reliability, environment, and finance. The %LRI was interpreted as the efficiency severity score. The line loading, system usage, voltage level, contingency, and age were the key factors used to determine the safety/reliability severity score, while human, impact pollution, and public image were used to calculate the environmental severity score. The percentage costs of components and their associated maintenance costs were transformed into the financial severity score. Then, the criticality was plotted in a criticality matrix, where the risk was differentiated and classified into four levels. Twenty practical transmission lines (115, 230, and 500 kV) in the Thailand transmission system were presented with actual data. The severity and criticality of all components and individual transmission lines were analyzed and plotted in criticality matrices based on four criteria. Consequently, the need for the maintenance, refurbishment, or replacement of the components and transmission lines was able to be ranked depending on the obtained risk. According to the results, it can be concluded that lines #7 and #12 encountered the greatest problems in the network, except for problems based on environmental criteria because the lines are located in the countryside with a medium environmental impact. These lines should be the first priority for short-term reconstruction planning because of their unacceptable condition and high risk in terms of safety, reliability, and finances. Based on these data, we formulated and presented recommendations for the utility provider to engage in maintenance strategies and risk mitigation at all levels of criticality and risk. In this way, the effective and efficient maintenance planning of the transmission system can be managed. Using these recommendations, the transmission network could maintain better condition, higher reliability, a lower risk of failure, and a lower cost of maintenance.