Next Article in Journal
Mould Growth Models and Risk Assessment for Emerging Timber Envelopes in Australia: A Comparative Study
Next Article in Special Issue
A Method to Qualify the Impacts of Certifications for Prefabricated Constructions
Previous Article in Journal
Comparison of Downdraught and Up Draft Passive Air Conduction Systems (PACS) in a Winery Building
Previous Article in Special Issue
The Relationship between Building Agents in the Context of Integrated Project Management: A Prospective Analysis
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Case Report

A Case Study of a Negotiated Tender within a Small-to-Medium Construction Contractor: Modelling Project Cost Variance

by
James Ellis
1,
David John Edwards
1,*,
Wellington Didibhuku Thwala
2,
Obuks Ejohwomu
3,
Ernest Effah Ameyaw
4 and
Mark Shelbourn
1
1
Faculty of Engineering and the Built Environment, Birmingham City University, Birmingham B4 7XG, UK
2
SARChi in Sustainable Construction Management and Leadership in the Built Environment, Faculty of Engineering and the Built Environment, University of Johannesburg, Johannesburg 2193, South Africa
3
Department of Mechanical, Aerospace and Civil Engineering, Manchester University, Manchester M13 9PR, UK
4
Department of Architecture and Built Environment, Northumbria University, Newcastle upon Tyne NE7 7XA, UK
*
Author to whom correspondence should be addressed.
Buildings 2021, 11(6), 260; https://doi.org/10.3390/buildings11060260
Submission received: 18 April 2021 / Revised: 5 June 2021 / Accepted: 13 June 2021 / Published: 18 June 2021

Abstract

:
This research explores the failure of competitively tendered projects in the UK construction industry to procure the most suited contractor(s) to conduct the works. Such work may have equal relevance for other developed nations globally. This research seeks to teach clients and their representatives that “lowest price” does not mean “best value”, by presenting a case study of a successfully negotiated tender undertaken by a small-to-medium enterprise (SME) contractor; SME studies are relatively scant in academic literature. By applying the “lessons learnt” principle, this study seeks to improve future practice through the development of a novel alternative procurement option (i.e., negotiation). A mixed philosophical stance combining interpretivism and pragmatism was used—interpretivism to critically review literature in order to form the basis of inductive research to discuss negotiation as a viable procurement route, and pragmatism to analyse perceptions of tendering and procurement. The methods used follow a three-stage waterfall process including: (1) literature review and pilot study; (2) quantitative analysis of case study data; and (3) qualitative data collection via a focus group. Our research underscores the need to advise clients and their representatives of the importance of understanding the scope of works allowed within a tender submission before discounting it based solely on price. In addition, we highlight the failings of competitive tendering, which results in increased costs and project duration once the works commence on site. These findings provide new contemporary insight into procurement and tendering in the construction industry, with emphasis on SME contractors, existing relationships, and open-book negotiation. This research illustrates the adverse effects of early cost estimates produced without first securing a true understanding of project buildability and programming. Our work concludes with a novel insight into an alternative procurement option that involves early SME contractor involvement in an open-book environment, without the need for a third-party cost control.

1. Introduction

Following the Joint Contracts Tribunal (JCT’)’s launch of the Design and Build (D&B) form of contract in 1981 [1], the UK construction industry has moved away from traditional procurement routes involving bills of quantities and designs complete to RIBA Stage 4—Technical Design [2,3]. Instead, construction professionals and clients have opted for single-stage or two-stage competitive D&B tendering, with an often- incomplete design to RIBA stages 2 or 3 viz: Concept Design or Developed Design, respectively [4]. This approach embeds ambiguity within the scope of works included in the tender documents, due to a lack of design information [5]. Consequently, the project requirements are largely defined and delineated by the contractors’ interpretations [6], thus increasing the difficulty of levelling bids, especially due to the inclusion of qualifications that form the basis of the tender return [7,8]. In addition, this approach reduces the clarity of procuring a contractor who has fully understood and allowed for the full extent of the scope of the works [9]. This lack of clarity in terms of scope, and the inherently competitive element of this procurement route, compel contractors to strategically plan their approach to each tender in order to increase the appeal of their tender return [10] and participate in the infamous “race to the bottom” [11]. By producing an artificially low tender sum, contractors seek to improve their chances of being called for a post-tender interview [12]. However, this strategy encourages decisions to exclude work items and then use provisional or prime cost sums to reduce element costs, and/or value engineering of the specification in order to offer cheaper alternatives [13].
Lack of consistency across the bids is a major issue with this approach, because it becomes increasingly difficult for the professional quantity surveyor (PQS) to align bids and conduct a thorough tender adjudication [14,15]. In contrast, a traditional bill of quantities allows for much easier comparison, because it is a uniform document providing itemised, measured quantities [16]. Consequently, the process of comparing tenders often involves looking purely at the bottom-line figure and ignoring the contents allowed within them [17], thus contradicting the guidance set out in the JCT Tendering Practise Note 2017 [18]. Therefore, during tender negotiations, and following the commencement of works on site, the costs tend to increase significantly to reflect the true scope of the works [19]. For example, the Scottish Parliament building was originally budgeted for a contract sum of GBP GBP 40 million (UK Sterling) in 1999, but the final account settled in 2004 was a staggering GBP GBP 414 million [20]. Another notable example was the London Crossrail Programme, which saw an increase in the total sum of the various contracts from GBP GBP 14.8 billion in 2013 to GBP GBP 17.6 billion in 2018 [21]. Similarly, the Olympic Games’ original construction budget was GBP GBP 4.2 billion in 2005 when the site preparation for the Olympic Park commenced, but the final construction costs were reported to be an astonishing GBP GBP 9.32 billion in 2011 [22,23].
Given this backdrop, this research reports upon a successfully negotiated project, as a contemporary vignette of a case study in practice that illustrates the palpable benefits that this approach has over the often unsuccessful competitively tendered procurement route. Specifically, this work uncovers the strategic decisions made by the contractor to improve the chances of securing the project, and answers the question: does a negotiated contract provide a better option (for the mutual benefit of all parties) than the competitively tendered contract? Such work adds much-needed modernity to the wider field of studies on the cost escalations involved in different types of procurement paths, but also offers invaluable insight into the actual cost variances experienced by a small-to-medium enterprise (SME)-sized contractor using a negotiated contract; case study research using SME contractors and real-life cost data is relatively scant in academic literature. Upon achieving these aims, associated objectives seek to generate renewed polemic discourse on the importance of defining and understanding the scope of works, reduce variations and improve cost certainty for all involved parties, and engender greater transparency in order to avoid disputes as projects progress—resulting in greater client satisfaction, increased contractor profitability, and enhanced value management.

2. Procurement and Tendering in the UK Construction Industry: A Review

The Royal Institution of Chartered Surveyors (RICS) [24] defines procurement as “the overall act of obtaining goods and services from external sources i.e., a building contractor”, and tendering as “the bidding process to obtain a price and how a contractor is appointed.” Over time, the process has adapted; originally being a mechanism to control various trades required to carry out construction works [25], it has developed into a system to capture and manage the client’s needs (ibid). In the construction industry, procurement and tendering usually involves some form of competition [26]. In order to appoint the most appropriate contractor to carry out the works, various procurement routes have been developed [27]. Figure 1 presents a timeline showing the evolution of procurement in the construction industry.

3. Preferred Tendering and Procurement Routes

The shift from traditionally procured projects towards D&B procurement routes is apparent from the National Construction Contracts and Law Surveys [35,36,37]. This trend can also be observed internationally [38]. In surveys carried out in 2012, 22% of consultants had been involved in D&B-procured projects [36], which increased to 37% [35] and 41% [37] in the 2015 and 2018 surveys, respectively. Contrastingly, consultants’ involvement in traditionally procured projects was 72% in 2012 [36], and fell to 52% in 2015 [35] and 48% in 2018 [37]. These data highlight a clear shift in the preferred procurement routes in the UK construction industry; Naoum and Egbu [39] supported this view through their literature synthesis [40,41,42], concluding that there has been a particularly evident increase in D&B projects. The 2018 NBS survey showed 82% of participants as being involved in single-stage competitive tenders, 50% being involved in two-stage competitive tenders, and 50% in negotiations (ibid), highlighting an industry-wide preference for competitively tendered procurement routes [43].

4. Strategic Pricing Pre-Contract and Change Orders Post-Contract

During competitively tendered projects, Okada et al. [44] acknowledge that there has been an increase in contractors taking strategic pricing decisions and submitting artificially low/underpriced bids in order to win a project. This tactic is a common feature in the D&B procurement route and, consequently, changes to the contract sum are inevitable to reflect the true scope of the works [45]. Therefore, contractors rely on change orders and scope alterations as an opportunity to recuperate lost profits through cost increases for completing additional works [44]. Change can be perceived as any alteration to the scope, period, cost, and or/quality of the contracted works [46]. Although undesirable to the client, change is inevitable during construction works [45,47,48]. Hence, “change” and the subsequent cost increases [49] increase the contract sum to reflect the true value of the employer’s requirements, as opposed to the scope allowed at tender stage [45]. The RIBA plan of works [50] outlines the whole life cycle of the construction process. The introduction of Stage 0—Strategic Definition was to further enhance the core design phases by confirming the client requirements (refer to Figure 2). The RIBA Plan of Work suggests that all design changes should occur from stages 1–4, with the exception of site queries at stage 5 [3]. However, current literature recognises that change often occurs during the construction phase and, therefore, there is a need to understand what the cause and effects of changes are, so that mitigation strategies can be adopted [51]. Table 1 summarises the sources of change during the construction phase, and the resultant effects are time, cost, or quality alterations to the project parameters [46].
Smith et al. [49] concluded that the sources of change can be categorised under the overarching issue of a poorly defined brief and design during the project’s early stages. This directly impacts contractors’ tender submissions, therefore making change and cost increases during the delivery phase inevitable so as to correct the flawed project brief (ibid). Furthermore, the client consultant team are often out of their depth, with designers producing concepts that are not achievable in practice due to a lack of technical construction knowledge, and PQSs providing cost estimates without understanding or considering the sequencing and buildability of works (ibid). Consequently, early cost estimates produced for clients are often inaccurate and, thus, budgetary advice for the project is lower than the true cost of carrying out the works [65]. The concept of “rework” is applicable to this situation [62], which includes failure of the design team and cost consultants to produce a tender pack free from errors, omissions, and inconsistencies early in the project [66], during RIBA stages 2 and 3 [50]. Hence, had the client’s consultants been more competent and produced an accurate brief [67], contractors would not have had to make strategic pricing decisions in order to submit the lowest price [68]. There is much discussion amongst academics regarding the effects of “rework”. Love [66], as cited by Forcada et al. [58], states that rework contributes to 52% of total cost increases, and can range from 5% to 20% of the contract value. Analysis of 359 projects by Hwang et al. [69] concluded that rework costs added an extra 5% to the contract value and, similarly, Taylor et al. [61] found the average increase of change orders to be 4.53% among 610 contracts studied. Various other research studies have revealed that rework costs can account for up to 20% [62] of the contract value, with Fayek et al. [70] reporting 2–12%, and Oyewobi et al. [71] reporting 5.06% and 3.23% for new builds and refurbishments, respectively.
The main contractor is usually held accountable for the resultant increases in the final account caused by the changes, leading to worsened contractor–client relationships [72]. However, this is an inaccurate prognosis of a complex issue [63]. The reality supports the findings of Smith et al. [49] that the clients’ team of consultants is at fault, while the contractor is merely the scapegoat for their failings. Therefore, Clause 2.12 of the JCT Design and Build Contract [73] applies, and any inadequacies found with the design are rectified—“the employers’ requirements shall be corrected, altered or modified accordingly’ and ‘treated as a change’”. Under clause 5.2 regarding evaluation of changes, the contractor is entitled to the additional value of the work, and the contract sum increases to reflect this (ibid).

5. The Need for Change

Competitiveness is a recognised characteristic of the construction industry [74] and thus, procurement often takes place via competitive tendering routes, such as the D&B or design, bid, build approaches [75]. These routes often increase project duration, cost overruns, change orders, and rework, ultimately leaving the client dissatisfied [76]. Briscoe and Dainty [77] suggested that this was due to the vast number of stakeholders involved in construction projects, resulting in fragmentation and a lack of integration—a view supported by Harper et al. [78] and Papadonikolaki and Wamelink [79]. Project team members work almost exclusively on their portion of the works [80], further highlighting the fragmented environment created by these procurement routes [81]. To address the issues of competitive procurement routes, a cultural change is required in order to promote and incorporate collaboration [74,76].
The concept of integrated project delivery (IPD) was established in order to address these issues [82], by improving project efficiency through collaboration [81], therefore reducing the number of changes during the construction phase in order to avoid increased costs, whilst also seeking to offer cost savings and shorter durations [83]. Following its inception, surveys carried out suggested that competitive tendering was not an effective procurement method (ibid). Further studies showed that six projects that adapted IPD were able to successfully deliver or exceed the clients’ requirements in terms of budget, programme, and design [84]. The research findings suggested that the reasons for success were due to traditional issues being avoided through enhanced collaboration and early involvement, therefore reducing ambiguity within the scope of the works. Early contractor involvement allowed for more realistic bids as the competitive element was removed (ibid). Collins and Parrish [45] support this position, arguing that early involvement of all project stakeholders (including the contractor) is more advantageous for offering cost certainty to the client. Figure 3 identifies an IPD team selection process using a case study project detailing how early stakeholder involvement and collaboration was achieved [85]. Despite the recognised benefits of IPD, it is not widely used in the UK construction industry [86]. This lack of adoption may contribute to projects that continue to be completed over budget and with extended durations. Arguably, IPD has not gained momentum due to its close relationship with building information modelling (BIM), and the associated barriers to entry this presents (ibid). Other barriers are defined in Figure 4.
Due to these barriers, an alternative tender and procurement route is required in order to avoid the “lowest price wins” scenario [85], which does not achieve best value or successful project delivery for the client [92]. There appears to be a notable gap in current literature exploring negotiation as a procurement route to achieve the desired cost certainty by avoiding contractors’ strategic low-pricing tactics; hence, the rationale for this research.

6. Research Methodology

This research adopts a mixed philosophical stance that combines interpretivism [96,97,98] and pragmatism [99]. As an epistemological stance, interpretivism was adopted in order to critically review extant literature and generate questions that then informed the ensuing inductive research approach, which sought to generate new theory on “negotiation” as a viable procurement path [100]. Interpretivism has been extensively used within construction management and civil engineering research [101,102,103]. For example, Roberts et al. [104] reviewed the benefits and challenges of digital asset management, while Al-Saeed et al. [105] sought to automate construction manufacturing procedures using building information modelling (BIM) digital objects. Pragmatism [106] was adopted in order to analyse practitioner perceptions and values, so as to resolve the phenomena under investigation. This overarching epistemological design was contextualised within a case study strategy [107]—specifically, a successfully secured and delivered negotiated project wherein the main contractor was not responsible for the design. The project consisted of a new-build swimming pool and gym at a private dwelling with a floor area of 125 m2. The main contractor (which was an SME) was based in Birmingham, UK, and operates mainly in the West Midlands conurbation, undertaking work in various sectors, including industrial, residential, commercial, and private dwellings. The contractor employs only 10 people, and has an annual turnover of circa GBP GBP 5 million—this research therefore gives a rare glimpse of project costings as experienced by an SME contractor. The research method follows a waterfall process, using three key phases consisting of: (1) literature review and pilot study; (2) quantitative analysis of the case study data; and (3) qualitative data collection using a focus group (Figure 5).
Phase 1—Literature review and pilot study: Published literature on tendering and procurement was reviewed, and a pilot study convened with three professional practitioners (who also participated in the focus group), in order to assess the failure of competitive tendering and the need to develop a more successful procurement route for SMEs. During these discussions, findings from the literature were presented to pilot study participants in order to: (1) elicit professional practitioner feedback and guidance on the relevance and currency of the body of knowledge accumulated for the present study; (2) secure their insight on the key questions that should be posed and the types of data that should be collected in order to allow a robust analysis to commence; and (3) check on the validity of both the approach adopted and the scientific instruments used (such as for data collection). At the end of the pilot work, minor modifications were made to the questions developed for the focus group, in order to remove any ambiguity.
Phase 2—Quantitative analysis of the case study data: The main contract works as described in the JCT Minor Works 2016 contract were to carry out the construction of a single-storey gymnasium and swimming pool. Works on site commenced on 7 May 2019, and practical completion was achieved in December 2019. The contract sum was GBP GBP 294,994, and the final account agreed at GBP GBP 325,118. Participant action research (PAR) was implemented by the lead researcher, who worked as part of the project team for the main contractor [108]. Throughout the project’s duration, monthly valuations were compiled in order to track the costs incurred on site, including preliminaries, drawdown, main contract works, and variations. This process also provided the facility to track the anticipated final account against the contract sum. The valuations became the application for payment, with the final valuation forming the basis of the final account. Quantitative cost data were extracted from the valuation reports, and empirical research implemented in order to determine cost differences (e.g., anticipated versus actual values) for various elements of the construction works. Qualitative narratives described the variations in the valuations, and provided justification for cost changes. Bivariate regression was then used to highlight the relationship between the monthly cumulative cost growth and the project duration, and then benchmarked against the agreed contract sum.
Phase 3—Qualitative data collection using a focus group: Upon completion of the data analysis phase, the results were presented to a focus group (held on MS Teams) consisting of three professional practitioner participants who were involved in the project management team (refer to Table 2). Participants were required to have a minimum of five years of industry experience, so as to ensure that they held the required competence to discuss the phenomena under investigation. A semi-structured data collection instrument that contained open-ended questions sourced from Phases 1 and 2 was developed and used to gather data. Participants were invited to provide their opinions of: (1) tendering and procurement, and the reasons for changes; and (2) the procurement route used, and whether they deemed this to have been a factor influencing the success of the project. This abductive approach [109] allowed evidence to be drawn together in order to derive reasoned conclusions.

7. Analysis

Data analysis involved collecting all of the applications for payment (16 in total—including 2 within the final account) in the case study project and presenting the cost data in a spreadsheet in order to show the bimonthly cumulative growth for the construction works, preliminaries, overheads and profit, materials on site, and variations. In collecting the data, an arithmetic error was found from Application 1 to Application 7—a SUM formula included in the Excel application for payment document did not capture all of the costs intended. The main contractor identified this error and corrected it in Application 8. For this research, the arithmetic error has been corrected, and the data have been adjusted to reflect the true cumulative costs had the error not occurred.
Once the applications data were compiled into one spreadsheet, they were then sorted into subcategories (e.g., Prelims: Fixed; Prelims: Time-Related, etc.) and the various construction works elements, following the BCIS elements [110] showing the cumulative cost growth. Variations were allocated to the corresponding preliminary item or construction works element. This process highlighted five variations that formed new items of work that did not form part of the main contract. To avoid the anticipated versus actual cost data being skewed, two cost summaries of the applications for payment were produced: the first showing all cost data, including the variations classified as “Additional Works”; and the second excluding the “Additional Works” items, in order to allow cost versus value analysis (Table 3 and Table 4).

7.1. Cross-Sectional Time Horizon (Based on Table 3)

The cross-sectional time horizon was completed in order to show the percentage increase or decrease of the various construction works elements, together with the reasons for these changes, as classified by the professional practitioners involved in the project (Table 5).
Of the 30 categories, 6 saw no change from the contract sum to the final account, 11 saw a percentage increase, s6 saw a percentage decrease, and there were 7 new entries in the final account that did not form part of the contract sum. Of the 7 new entries, 5 accounted for the additional work outside of the contract sum and 2 were due to arithmetic errors. The 5 items of additional works identified added GBP 26,321, which equates to 8.92% of the contract sum. Due to these items not being foreseen at the outset, there was no value allocated against them. The overall percentage error was 10.21%. The three professional practitioners (i.e., Commercial Manager, Site Manager, and Managing Director) involved in the project classified each variation with a weighting out of 100%. The occurrence for each response (without considering the weighting) was as follows: design error (19); design omission (13); client-driven (55); change to scope of works (31); managerial factors (3); unforeseen conditions (11); and other (2). Upon final allocation of the classifications, 5.5 were due to design errors, 2.5 to design omission, 20 were client-driven, 5 due to changes to the scope of works, 0 to managerial factors, 3 to unforeseen conditions, and 3 for other reasons. Conclusively, the main reasons for changes were client driven (at 51.28%).

7.2. Cross-Sectional Time Horizon (Based on Table 4)

The cross-sectional time horizon was repeated as described above in order to show the percentage increase or decrease supported by justification for variations, excluding the five additional works items (Table 6). Removing the additional works items resulted in 25 categories; as before, 6 categories had no change, 11 had a percentage increase, 6 had a percentage decrease, and there were now 2 new entries due to arithmetic errors in the final account. The overall percentage error was 1.29%. This low overall percentage increase suggests that cost certainty was achieved, as there was little variance from the contract sum to the agreed final account. A two-tailed paired sample t-test was completed on Excel. The null hypothesis under investigation was that the mean difference between the anticipated and actual costs would equal zero, and the alternative hypothesis was that the mean difference between the anticipated and actual costs would not equal zero. The t-test results were: t-statistic = 0.49 (2 dp); and critical t-statistic for two-tailed test = 2.06 (2 dp). Due to the fact that the t-statistic < the critical t-statistic, we can accept the null hypothesis. Therefore, the data suggest that the mean difference can equal zero, thus suggesting that cost certainty was achieved. The data were also used to calculate the mean difference, standard deviation of the difference, standard error of the difference, and the confidence intervals (Table 7).
The data show with 95% confidence that the mean difference between the agreed final account (actual cost) and the contract sum (anticipated cost) is a mere GBP 152. This result suggests that cost certainty was achieved. The mean percentage error (MPE) and mean absolute percentage error (MAPE) were then calculated in order to provide comparison between the anticipated and the actual costs of the various elements of the works. For a comparison of actual versus anticipated costs, all “new entry” data items were omitted. To prevent the data from being skewed, the interquartile range (IQR = upper quartile (Q3)–lower quartile (Q1)) was calculated and an outlier test was completed using the following formula:
High-value outlier = Q3 + 1.5 (IQR);
therefore, 18.57% + 1.5 (18.57%) = 46.43%
Low-value outlier = Q1 − 1.5 (IQR);
therefore, 0.00% −1.5(18.57%) = − 27.86%
The following outliers were identified and removed: 4. FF&E 62.5% (mean absolute percentage error (MAPE)); 5.11 Lightning Protection 100% (MAPE); 8.3 Soft Landscaping 360.2% (MAPE); 8.4 Fencing, Railings, and Walls 2080% (MAPE). Refer to Table 8 for the data for the outlier, MPE, and MAPE calculations.
MPE = 100 % n t 1 n A t F t A t
where n = the number of elements of the construction works; and t 1 n A t F t A t = the sum of the percentage errors. MPE = 100 % 19   ×   2.93 ; therefore, MPE = 0.15%.
MAPE = 1 n t = 1 n A t F t A t
where n = the number of elements of the construction works; and t = 1 n A t F t A t = the sum of the absolute percentage errors. MAPE = 1 19   ×   97.80 ; therefore, MAPE = 5.15%.
These results support the findings of the cross-sectional time horizon and the t-test. The final account was in line with the estimated costs and, on average, a 5.15% change to the package value was expected, while the average change in each element of the construction works was 0.15%, considering both positive and negative changes.

7.3. Longitudinal Time Horizon (Based on Table 3)

The longitudinal time horizon was modelled using bivariate regression, in order to show the cumulative cost growth for each application for payment [111]. For the case study project, the independent variable was the application for payment (with each application equidistant at 2-week intervals), and the dependant variable was the cumulative cost growth. The regression module utilises the formula:
Y = a + bx
where Y is the dependent variable (i.e., cumulative growth); a is the Y-axis intercept; and bx is the gradient of the independent variable (i.e., application number). The cumulative cost growth at each application for payment was plotted along with the contract sum, in order to provide a benchmark from which to ascertain the point at which the actual cost exceeded the anticipated cost (Figure 6a).
The result produced a formula of: Y = −16,191 + 23,620x. This indicates that before an application for payment was made the cumulative cost growth is estimated at GBP −16,191. For the case study project, at the point x = 0, Y will also equal zero, as no work on site has been done.
The negative figure may represent the pre-construction and site setup costs incurred by the contractor, which will not be paid for until Application 1. The equation also estimates that for each additional application for payment the cumulative cost will increase by GBP 23,620 on average. Model accuracy was also tested using the root-mean-square error (RMSE) calculation, as shown in Equation (6):
RMSE fo = [ i = 1 N z f i z o i 2 / N 1 / 2
where ∑ = summation; (zfizoi)2 = differences squared; and N = sample size. This value came to GBP 16,654.26, which is incredibly small in comparison to the overall costs involved in the project, and demonstrates a good cost fit for the model.
The results also produced an R2 of 0.9771, showing an extremely strong relationship between the cumulative cost increase and the bimonthly applications. The cumulative cost (actual) exceeded the contract sum (anticipated) during Application 13 of 16, and continued to rise until Application 15 before falling during Application 16—where Applications 15 and 16 represent the final account “application” and the “agreed” final account, respectively. Application 15 therefore represents what the contractor requested from the client, Application 16 represents what was agreed. The decline between Applications 15 and 16 reflects the final account negotiations, with Application 15 representing the contractor’s final account submission at GBP 330,319, and Application 16 showing the agreed final account at GBP 325,118 (a reduction of GBP 5201). The final account exceeded the contract sum by 10.21% due to the cumulative effects of the reasons for change (Table 5).

7.4. Longitudinal Time Horizon (Based on Table 4)

A second longitudinal time horizon was conducted excluding the “Additional Work”, based on Table 4. This allowed analysis of the data without their being skewed by items that were not considered when the contract was agreed (Figure 6b).
The result produced a formula of: Y = −8104.60 + 21,830x. This indicates that before an application for payment was made the cumulative cost growth was estimated at GBP –8104.60. Again, when x = 0, Y will also equal 0 due to no work having been completed on site. The RMSE grew slightly to GBP 19,427.59 but, again, this figure is incredibly small compared to the overall project costs involved—again demonstrating a good cost fit for the model. However, the equation estimates that for each additional application for payment, the cumulative cost will increase by GBP 21,830 on average. With an R2 of 0.9641, an extremely strong relationship between the cumulative cost increase and the bimonthly applications is evident. The cumulative cost (actual) exceeded the contract sum (anticipated) during Application 14 of 16. The cumulative cost continued to rise in Application 15 and then fell during Application 16, reflecting the contractor’s final account submissions and the agreed final account. The final account exceeded the contract sum by 1.29%, the reasons for which are explained in Table 6. This small increase in the contract sum suggests that cost certainty had been achieved. Figure 6b provides a visual aid showing the actual costs as marginally higher than the anticipated costs. Comparing Figure 6a with Figure 6b, the gap between the cumulative cost and the contract sum is much greater in Figure 6a than Figure 6b.

8. Focus Group Discussion

A focus group session was established to discuss the analysis results with the three members of the project management team. A Microsoft PowerPoint presentation summary of the literature review and data analysis was delivered by the lead researcher. A series of investigative open questions were then delivered to the group (except for participant B, who provided responses via e-mail); the questions posed are detailed in Table 9. The first three questions investigated tendering and procurement generally. Unanimously, participants agreed that the main factor for contractor selection is “cheapest price”, with participant A suggesting “9 times out of 10 you will be driven by the costs” and participant B simply stating “price.” When prompted on other factors, such as the scope of works, participant A confirmed that the price took precedence over this, saying “unfortunately they go straight to the bottom line and will make a decision to interview on that basis. It doesn’t always mean that’s the result when you have finished the post tender/pre-contract negotiation.” This point is supported by previous studies, which found that the lowest price gets called to interview [12], that the bottom line is considered more than the scope of works [17], and that the price increases during the pre-contract negotiations [19].
Collaboration? Certainty for all parties?To test the hypothesis that the UK construction industry prefers competitively tendered design and build projects (as stated in the literature), a question was posed in order to ascertain the most frequently experienced forms of contracts. Participant A responded, “single-staged competitively tendered D&B”, participant B said “design and build”, and participant C said “more recently most of the projects have been design and build.” This reinforces the findings of the NBS surveys [35,36,37]. Participant B suggested the reason being “there is a perception that the contractor takes all the risk (although this is a misconception)”, while participant A continued this discussion, suggesting that the client uses D&B to protect their position, as it becomes the contractor’s responsibility to “prove change is due to a lack of information, part of the clarifications or a client-changed requirement.” They continued to say “traditional-type contracts seem to have gone by the wayside”.
The conversation continued to discuss strategies implemented during the tender process to improve the chances of being called for a post-tender interview. Participant A stated “price what you see”, however, if it is unclear, you can “put in a different figure, move figures below the line or try and reduce the cost.” Participant B added “exclusions and clarifications are always a good way to lower the price and make it more attractive.” This discourse concurs with Okada et al. [44], who found that contractors implement strategies to submit an artificially low price, which will inevitably result in changes to the contract sum to reflect the true scope of the works [45]. At this point, the discussion began to explore negotiation, and participant A suggested “the figures tend to be more aligned at the end of the job, than during a competitively tendered, all-risk D&B”, therefore supporting the data analysis showing that cost certainty was achieved.
At this point, the conversation was directed towards the case study project. A question was posed regarding the impact of the negotiated procurement route on the project delivery. Key words and phrases from the participants included: “communication”, “close working relationships”, “early contractor–client relationships”, and “clearly defined scope of work.” Consequently, once the works commenced on site, the project delivery was relatively easy, as there was minimal “ambiguity” and, therefore, the site only encountered “minor changes but nothing of great consequence” as described by participant C. Various elements of the construction work saw a reduction from the contract sum to the final account. Participants agreed that one contributing factor was that the project was set up well at the start and, therefore, the contractor was able to reimburse costs that were not expended vis-à-vis holding onto them. Participant A described the relationship as a “collaborative relationship as opposed to the aggressive type of situation you sometimes find”, and participant B agreed the relationships led to an “honest approach.
When discussing the reasons for change, participant A said “a lot of the changes were due to additional works the client decided he wanted”, and participant B agreed that change was largely due to “client request.” This supports the data analysis, as 20 of the 39 variations had been classified as client-driven. Participants agreed that the established relationships allowed management of change to be more “informal”, which helped in maintaining good working relationships. Due to the proximity of the site to the client’s residence, participant A suggested “it could have been a monumental disaster having the client that close to site because he would be there every day wanting to change or tweak things, but it worked out alright in the end.
Upon discussion of the success of the project delivery, participant A said, “it was delivered well, the client was very happy, and the product is exactly what he wanted so from that perspective it was extremely successful.” From a site perspective, participant C also deemed the project to be successful; “it finished well, and the client was over the moon with it.” The scope of the works was clearly defined and, therefore, any ambiguity or requests for information related to changes were as described by participant C, who said “The majority of RFIs were because we knew there was a variation coming”, and where things were not clear “they were very quickly resolved.” Furthermore, participant A said “The majority of change was the client requiring extras rather than change because the design was inadequate, or things hadn’t been interpreted correctly, or that the tender documents weren’t sufficient.” These reasons are supported by Smith et al. [49], Love et al. [112], and Ashworth et al. [67]. In addition, the completed project resulted in a recommendation and another negotiated project for the contractor.

9. Discussion

This research case study has provided a novel insight into an alternative procurement route (i.e., the negotiated procurement path) adopted by an SME contractor, thus providing both theoretical and practical contributions to knowledge and practice. From a theoretical perspective, the negotiated procurement created an “open book” environment that fostered trust and good working relationships between the contractor and the client. This included good adjudication of tender submissions to facilitate a two-way transparent knowledge transfer between client requirements and construction risks identified by the contractor. For example, during the pre-contract phase, the client regularly attended the main contractor’s office to review the proposals, including a line-by-line review of the scope of the works and the associated costs of each item of work. This contrasts with extant literature, which reveals that during a competitive tender period, the contractor’s submissions do not cater for the full scope of works and, consequently, the costs are artificially low so as to improve the probability of securing the project. Thereafter, variations during the construction phase are used as a tool to bring the project back in line with the scope of the works required, whilst also seizing the opportunity to submit manipulated costs in order to increase the total cost over and above the actual value of the works.
From a practical perspective, this research underpins the importance of both clients and contractors firmly embedding the attributes of confidence, transparency, and trust in a project. All too often, an unnecessarily adversarial relationship transpires, in which both client and contractor place their own business priorities ahead of those of the other contract parties. However, by working in harmony with one another, such attributes were shown in this case study to better control costs and mitigate disputes for the mutual benefit of both parties. The project provided cost certainty for the client and secured another negotiated project for the contractor. Following the presentation of the case study data analysis, cost certainty was discussed during the focus group, and participant A stated that: “without his changes the contract sum was ultimately almost the finite cost.” Importantly, the project did not involve a PQS or third-party cost control operative, but instead the negotiation was completed between the client and the contractor directly. This proved beneficial to the project, as the client was not subjected to inaccurate early cost advice. Extant literature identifies this as a failing of the tender process, as the estimates frequently fail to consider site conditions, sequencing, and buildability [49]. Consequently, the client and the contractor worked together to develop the scheme to meet the client’s budget, programme, and desired end product. A possible difference is that the client was knowledgeable about construction works, and that it may not be advisable to remove the third-party cost control (via a PQS) for less knowledgeable clients.
This research study has two main limitations: First, the lead researcher and study participants worked for the main contractor. Consequently, there is a potential for bias, as the opinions and experiences of client-side construction professionals have not been explored; future work should seek to address this deficiency. In addition, a single case study is unable to draw inference to determine whether or not the findings are applicable to other similar projects or procurement routes. Future research should therefore seek to run a cross-comparative analysis across various projects and procurement paths, in order to determine whether the findings presented here are unique or generalizable.

10. Conclusions

The literature review and responses from professional practitioners confirm that the UK construction industry’s (and those of other nations globally) current preference for competitive tendering and design and build fails to procure the most suited contractor to complete the project, subsequently leaving the client dissatisfied, the final account not reflecting the contract sum, and a vast number of variations. This scenario stems from inaccuracies in the early cost estimates, design issues, and contractors implementing strategic pricing tactics to secure work due to the “race to the bottom” culture instilled by this industry preference. Often, the determining factor for project success is based on cost, and yet, literature points towards recurrent issues of variations, rework and, ultimately, cost inflations [44,58,62]. This case study’s findings (involving an SME contractor) illustrate cost certainty being achieved and, therefore, provide a novel alternative procurement route centred on relationships, the scope of works, and transparency among stakeholders. A number of the design changes took place during the tender period; this was an advantage of the negotiation, as the contractor was involved early and, therefore, items that were foreseen could be dealt with at the tender stage. Therefore, the majority of changes during the construction stage were client-driven variations. Subsequently, the contractor understood what the client wanted to achieve, and the client had clear visibility on what they were getting. During the focus group, however, it was discussed that early contractor engagement is not common enough. In addition, due to the limitations discussed, this route of negotiation may not be applicable in all situations.
In addition to cost certainty, the findings also underscore the client’s satisfaction, due to the recommendation for another future project for the SME contractor. Consequently, the outcome of the project delivery was mutually beneficial, and provided value to the client. Ultimately, the research findings support current literature that has recognised a need for change. This research therefore provides a catalyst for further research into the failings of competitive tendering, in order to draw inference and produce new guidance with the view to making tendering, procurement, and project delivery more efficient.

Author Contributions

Conceptualization, J.E. and D.J.E.; methodology, J.E., D.J.E. and M.S.; validation, J.E. and D.J.E., W.D.T., O.E., E.E.A.; formal analysis, J.E., D.J.E., M.S., W.D.T., O.E., E.E.A.; investigation, J.E. and D.J.E.; data curation, J.E. and D.J.E.; writing—original draft preparation, J.E., D.J.E. and M.S.; writing—review and editing, J.E., D.J.E., M.S., W.D.T., O.E., E.E.A.; supervision, D.J.E.; project administration, J.E. and D.J.E. All authors have read and agreed to the published version of the manuscript.

Funding

This research received no external funding.

Institutional Review Board Statement

The study was conducted according to an ethical protocol that was approved by the Computing, Engineering and the Built Environment Faculty Academic Ethics Committee) of Birmingham city University (Edwards /#7741 /sub1 /Mod /2020 /Sep /CEBE FAEC—BNV6200 ACM Version D.J. Edwards—13th October 2020).

Informed Consent Statement

Informed consent was obtained from all subjects involved in the study.

Data Availability Statement

Anonymized data is available from the corresponding author upon written request and subject to review.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. RICS. Procure and Contract: Different Project Types Mean Different Contract Strategies. 2019. Available online: https://bit.ly/3usWgts (accessed on 29 June 2020).
  2. Sarhan, S.; Pasquire, C.; King, A.; Manu, E. Institutional waste within the UK construction procurement context: A conceptual framework. Eng. Proj. Organ. J. 2018, 8, 36–64. [Google Scholar]
  3. RIBA. RIBA Plan of Work 2020 Overview, London, RIBA. 2020. Available online: https://bit.ly/3wC6NEB (accessed on 26 October 2020).
  4. RIBA. RIBA Plan of Works 2013 Overview: RIBA. 2013. Available online: https://bit.ly/2Q7YbVs (accessed on 26 October 2020).
  5. Nibbelink, J.; Sutrisna, M.; Zaman, A. Unlocking the potential of early contractor involvement in reducing design risks in commercial building refurbishment projects–A Western Australian perspective. Archit. Eng. Des. Manag. 2017, 13, 439–456. [Google Scholar]
  6. Towey, D. Construction Quantity Surveying a Practical Guide for the Contractor’s QS, 1st ed.; Wiley-Blackwell: Chichester, UK; Hoboken, NJ, USA, 2012; ISBN 978-0-470-65942-7. [Google Scholar]
  7. Uff, J.F.; Clayton, C.R.I. Role and Responsibility in Site Investigation; Construction Industry Research and Information Association (CIRIA): London, UK, 1991; pp. 1–48. ISBN 978-0860173212. [Google Scholar]
  8. Laryea, S.; Hughes, W. Commercial reviews in the tender process of contractors. Eng. Constr. Archit. Manag. 2009, 16, 558–572. [Google Scholar] [CrossRef]
  9. Jaśkowski, P.; Czarnigowska, A. Contractor’s bid pricing strategy: A model with correlation among competitors’ prices. Open Eng. 2019, 9, 159–166. [Google Scholar] [CrossRef]
  10. Wong, C.; Holt, G.; Cooper, P. Lowest price or value? Investigation of UK construction clients’ tender selection process. Constr. Manag. Econ. 2000, 18, 767–774. [Google Scholar] [CrossRef]
  11. Orstavik, F.; Dainty, A.; Abbott, C. Construction Innovation, 1st ed.; John Wiley & Sons: Chichester, UK; Hoboken, NJ, USA, 2015; p. 65. ISBN 978-1-118-65553-5. [Google Scholar]
  12. Wong, C.; Holt, G.; Harris, P. Multi-criteria selection or lowest price? Investigation of UK construction clients’ tender evaluation preferences. Eng. Constr. Archit. Manag. 2001, 8, 257–271. [Google Scholar] [CrossRef]
  13. Apfelbaum, A. Construction Cost Management: Cost Engineering, Cost Controls & Controlled Bidding, 2nd ed.; Authorhouse: Bloomington, IN, USA, 2013; pp. 160–161. ISBN 9781420871418. [Google Scholar]
  14. Kodikara, G.W.; Thorpe, A.; McCaffer, R. The use of bills of quantities in building contractor organizations. Constr. Manag. Econ. 1993, 11, 261–269. [Google Scholar] [CrossRef]
  15. Hatush, Z.; Skitmore, M. Criteria for contractor selection. Constr. Manag. Econ. 2010, 15, 19–38. [Google Scholar] [CrossRef] [Green Version]
  16. Katar, I.; Howeidy, D. Effective construction utilizing design-build vs. design-bid-build methods; 5-feature appraisal (time-drawings-calendar-communication-changes). Int. J. Civil. Eng. Technol. 2018, 9, 921. [Google Scholar]
  17. Fong, P.; Choi, S. Final contractor selection using the analytical hierarchy process. Constr. Manag. Econ. 2010, 18, 547–557. [Google Scholar] [CrossRef]
  18. JCT. Tendering Practise Note 2017; Thomson Reuters (Professional) UK Ltd.: London, UK, 2017; p. 10. [Google Scholar]
  19. Igwe, U.; Mohamed, S.; Azwarie, M.; Paulson Eberechukwu, N. Recent developments in construction post contract cost control systems. J. Comput. Theor. Nanosci. 2020, 17, 1236–1241. [Google Scholar] [CrossRef]
  20. Auditor General for Scotland. Management of the Holyrood Building Project. Audit Scotland. 2004. Available online: https://bit.ly/39Xa6g2 (accessed on 26 October 2020).
  21. Department for Transport. Completing Crossrail, London, Comptroller and Auditor General. 2019. Available online: https://bit.ly/3s5ckzW (accessed on 26 October 2020).
  22. Department for Culture Media and Sport. London 2012 Olympic and Paralympic Games Annual Report January. London, DCMS. 2009. Available online: https://bit.ly/3cYVWNi (accessed on 26 October 2020).
  23. Jennings, W. Why costs overrun: Risk, optimism and uncertainty in budgeting for the London 2012 Olympic Games. Constr. Manag. Econ. 2012, 9, 455–462. [Google Scholar] [CrossRef]
  24. RICS. Tendering Strategies. 2014. Available online: https://bit.ly/3wDNTgG (accessed on 18 October 2020).
  25. Ahamad, N.; Binti Mazlan, A.; Zin, R.; Tukirin, S. Construction Procurement in Industrialised Building System. IOP Conf. Ser. Mater. Sci. Eng. 2020, 849, 012072. [Google Scholar] [CrossRef]
  26. Smith, A. Estimating, Tendering and Bidding for Construction Work. 2017. Available online: https://bit.ly/39Sqr5m (accessed on 18 October 2020).
  27. Jelodar, M.; Yiu, T.; Wilkinson, S. A conceptualisation of relationship quality in construction procurement. Int. J. Proj. Manag. 2016, 34, 997–1011. [Google Scholar] [CrossRef]
  28. Oyegoke, A.; Dickinson, M.; Khalfan, M.; McDermott, P.; Rowlinson, S. Construction project procurement routes: An in-depth critique. Int. J. Manag. Proj. Bus. 2009, 2, 338–354. [Google Scholar] [CrossRef]
  29. Viana, M.; Hadikusumo, B.; Mohammad, M.; Kahvandi, Z. Integrated project delivery (IPD): An updated review and analysis case study. J. Eng. Proj. Prod. Manag. 2020, 10, 147–161. [Google Scholar] [CrossRef]
  30. Davidson, J.; Fowler, J.; Pantazis, C.; Sannino, M.; Walker, J.; Sheikhkhoshkar, M.; Rahimian, F.P. Integration of VR with BIM to facilitate real-time creation of bill of quantities during the design phase: A proof of concept study. Front. Eng. Manag. 2020, 7, 396–403. [Google Scholar] [CrossRef] [Green Version]
  31. Chappell, D. Professional Practise for Architects and Project Managers, 1st ed.; Wiley Blackwell: Oxford, UK; Hoboken, NJ, USA, 2019; pp. 183–185. ISBN 9781119540090. [Google Scholar]
  32. Lee, J.H.; Zhou, Y.; Ashuri, B. Key Challenges to design professional liability in the design-build environment. J. Leg. Aff. Disput. Resolut. Eng. Constr. 2020, 12, 04520031. [Google Scholar]
  33. Ma, G.F.; Jia, J.Y.; Jiang, S.; Wu, Z.J. Incentives and contract design for knowledge sharing in construction joint ventures. Autom. Constr. 2020, 119, 103343. [Google Scholar]
  34. AIA California Council. Integrated Project Delivery: A Guide, Version 1. American Institute of Architects. 2007. Available online: https://bit.ly/3dKa6RE (accessed on 19 October 2020).
  35. NBS. National Construction Contracts and Law Survey: NBS. 2015. Available online: https://bit.ly/3s6qYqB (accessed on 26 October 2020).
  36. NBS. National Construction Contracts and Law Survey: NBS. 2012. Available online: https://bit.ly/2Q2sddf (accessed on 26 October 2020).
  37. NBS. National Construction Contracts and Law Survey: NBS. 2018. Available online: https://bit.ly/3wEEN3f (accessed on 26 October 2020).
  38. Aje, I.O.; Oladinrin, O.; Nwaole, A.N.C. Factors influencing success rates of contractors in competitive bidding for construction works in South-East Nigeria. J. Constr. Dev. Ctries. 2016, 21, 19–23. [Google Scholar] [CrossRef]
  39. Naoum, S.G.; Egbu, C. Modern selection criteria for procurement methods in construction. A state-of the-art literature review and a survey. Int. J. Manag. Proj. Bus. 2016, 9, 309–336. [Google Scholar] [CrossRef]
  40. Eriksson, P.E.; Pesämaa, O. Modelling procurement effects on cooperation. Constr. Manag. Econ. 2007, 25, 893–901. [Google Scholar] [CrossRef] [Green Version]
  41. Hamza, N.; Greenwood, D. The impact of procurement methods on delivering environmentally sensitive buildings. In Proceedings of the Boyd, D (Ed) 23rd Annual ARCOM Conference, Belfast, UK, 3–5 September 2007; pp. 723–732. [Google Scholar]
  42. Shafik, M.; Martin, P. The impact of procurement methods on the Scottish housebuilding industry. In Proceedings of the Boyd, D (Ed) Procs 22nd Annual ARCOM Conference, Birmingham, UK, 4–6 September 2006; pp. 81–90. [Google Scholar]
  43. Morledge, R.; Smith, A. Building Procurement, 2nd ed.; Wiley-Blackwell: Chichester, UK, 2013; ISBN 978-0-470-67243-3. [Google Scholar]
  44. Okada, R.; Simons, A.; Sattineni, A. Owner-requested changes in the design and construction of government healthcare facilities. Procedia Eng. 2017, 196, 592–606. [Google Scholar] [CrossRef]
  45. Collins, W.; Parrish, K. The need for integrated project delivery in the public sector. In Proceedings of the 2014 Construction Research Congress, Atlanta, GA, USA, 19–21 May 2014; pp. 719–728. [Google Scholar]
  46. Ibbs, W.; Nguyen, L.; Lee, S. Quantified impacts of project change. J. Prof. Issues Eng. Educ. Pract. 2007, 133, 45–52. [Google Scholar] [CrossRef]
  47. Nuaimi, A.; Taha, R.; Al Mohsin, M.; Al-Harthi, A. Causes, effects, benefits, and remedies of change orders on public construction proects in Oman. J. Constr. Eng. Manag. 2010, 136, 615–622. [Google Scholar]
  48. Günhan, S.; Arditi, D.; Doyle, J. Avoiding change orders in public school construction. J. Prof. Issues Eng. Educ. Pract. 2007, 133, 67–73. [Google Scholar] [CrossRef]
  49. Smith, J.; Edwards, D.J.; Martek, I.; Chileshe, N.; Hayhow, S.; Roberts, C.J. The antecedents of construction project change: An analysis of design and build procurement application. J. Eng. Des. Technol. 2021. [Google Scholar] [CrossRef]
  50. Willers, N. Project Leadership: RIBA Plan of Work 2013 Guide RIBA, 1st ed.; RIBA Publishing: London, UK, 2014; ISBN 978-1-8594-6551-6. [Google Scholar]
  51. Stasis, A.; Whyte, J.; Dentten, R. A critical examination of change control processes. Procedia CIRP 2013, 11, 177–182. [Google Scholar] [CrossRef] [Green Version]
  52. Ostime, N. RIBA Job Book, 9th ed.; RIBA Publishing: London, UK, 2019; pp. 10–12. ISBN 978-1-85946-496-0. [Google Scholar]
  53. Foxell, S. Starting a Practice Plan of Work, 2nd ed.; RIBA Publishing: London, UK, 2015; ISBN 978-1-85946-580-6. [Google Scholar]
  54. Sinclair, D. RIBA Plan of Work 2013 Guide Design Management, 1st ed.; RIBA Publishing: London, UK, 2014; ISBN 978-1-85946-550-9. [Google Scholar]
  55. Holden, P. A Practical Guide to the RIBA Plan of Work 2013 Stages 4, 5 and 6, 1st ed.; RIBA Publishing: London, UK, 2015; ISBN 978-1-85946-572-1. [Google Scholar]
  56. Forcada, N.; Macarulla, M.; Gangolells, M.; Casals, M. Handover defects: Comparison of construction and post-handover housing defects. Build. Res. Inf. 2015, 44, 279–288. [Google Scholar] [CrossRef] [Green Version]
  57. Lock, D. Project Management in Construction; Routledge Taylor & Francis Group: Oxfordshire, UK, 2016. [Google Scholar]
  58. Forcada, N.; Gangolells, M.; Casals, M.; Macarulla, M. Factors affecting rework costs in construction. J. Constr. Eng. Manag. 2017, 143, 04017032. [Google Scholar] [CrossRef] [Green Version]
  59. Safapour, E.; Kermanshachi, S. Identifying early indicators of manageable rework causes and selecting mitigating best practices for construction. J. Manag. Eng. 2019, 35, 04018060. [Google Scholar] [CrossRef]
  60. Love, P.; Smith, J.; Ackermann, F.; Irani, Z.; Teo, P. The costs of rework: Insights from construction and opportunities for learning. Prod. Plan. Control. 2018, 29, 1082–1095. [Google Scholar] [CrossRef]
  61. Taylor, T.; Uddin, M.; Goodrum, P.; McCoy, A.; Shan, Y. Change orders and lessons learned: Knowledge from statistical analyses of engineering change orders on Kentucky highway projects. J. Constr. Eng. Manag. 2012, 138, 1360–1369. [Google Scholar] [CrossRef]
  62. Love, P.; Edwards, D.; Smith, J. Rework causation: Emergent theoretical insights and implications for research. J. Constr. Eng. Manag. 2016, 142, 1943. [Google Scholar] [CrossRef]
  63. Shahparvari, M.; Fong, D. The review of rework causes and costs in housing construction supply chain. In Proceedings of the 26th Annual Conference of the International Group for Lean Construction, Chennai, India, 16–22 June 2018. [Google Scholar]
  64. Love, P.; Curtin, J. Creating a mindfulness to learn from errors: Enablers of rework containment and reduction in construction. Dev. Built Environ. 2020, 1. [Google Scholar] [CrossRef]
  65. Ismail, N.A.A.; Idris, N.H.; Ramli, H.; Sahamir, S.R.; Rooshdi, R.R.R.M. Sustainable BIM-based cost estimating for quantity surveyors. Chem. Eng. Trans. 2018, 63, 235–240. [Google Scholar]
  66. Love, P. Influence of project type and procurement method on rework costs in building construction projects. J. Constr. Eng. Manag. 2002, 128, 18–29. [Google Scholar] [CrossRef] [Green Version]
  67. Ashworth, A.; Hogg, K.; Higgs, C. Willis’s Practice and Procedure for the Quantity Surveyor, 13th ed.; John Wiley & Sons: Hoboken, NJ, USA, 2013; ISBN 978-0-470-67219-8. [Google Scholar]
  68. Lo, W.; Lin, C.; Yan, M. Contractor’s opportunistic bidding behavior and equilibrium price level in the construction market. J. Constr. Eng.Manag. 2007, 133, 409–416. [Google Scholar] [CrossRef]
  69. Hwang, B.; Thomas, S.; Haas, C.; Caldas, C. Measuring the impact of rework on construction cost performance. J. Constr. Eng. Manag. 2009, 135, 187–198. [Google Scholar] [CrossRef]
  70. Fayek, A.; Dissanayake, M.; Campero, O. Developing a standard methodology for measuring and classifying construction field rework. Can. J. Civil Eng. 2004, 31, 1077–1089. [Google Scholar] [CrossRef]
  71. Oyewobi, L.; Oke, A.; Ganiyu, B.; Shittu, A.; Isa, R.; Nwokobia, L. The effect of project types on the occurrence of rework in expanding economy. J. Civil Eng. Constr. Tech. 2011, 2, 119–124. [Google Scholar]
  72. Perkins, R. Sources of changes in design-build contracts for a governmental owner. J. Constr. Eng. Manag. 2007, 135, 2148–2153. [Google Scholar]
  73. JCT. DB 2016 Design and Build. Contract 2016; Sweet & Maxwell: London, UK, 2016; pp. 34–56. [Google Scholar]
  74. Martin, D. Evaluating the evolution of construction management students’ conflict management styles as a result of andragogical methods. In Proceedings of the 2020 ASEE Virtual Annual Conference Content Access Proceedings, Ellensburg, WA, USA, 7 July 2002; pp. 1–19. [Google Scholar] [CrossRef]
  75. Ma, Z.; Zhang, D.; Li, J. A dedicated collaboration platform for integrated project delivery. Autom. Constr. 2018, 86, 199–209. [Google Scholar] [CrossRef]
  76. Durdyev, S.; Hosseini, M.; Martek, I.; Ismail, S.; Arashpour, M. Barriers to the use of integrated project delivery (IPD): A quantified model for Malaysia. Eng. Constr. Archit. Manag. 2019, 27, 186–204. [Google Scholar] [CrossRef]
  77. Briscoe, G.; Dainty, A. Construction supply chain integration: An elusive goal? Supply Chain Manag. Int. J. 2005, 10, 319–326. [Google Scholar] [CrossRef]
  78. Harper, C.; Molenaar, K.; Cannon, J. Measuring constructs of relational contracting in construction projects: The owner’s perspective. J. Constr. Eng. Manag. 2016, 142, 1–11. [Google Scholar] [CrossRef]
  79. Papadonikolaki, E.; Wamelink, H. Inter- and intra-organizational conditions for supply chain integration with BIM. Build. Res. Inf. 2017, 45, 649–664. [Google Scholar] [CrossRef]
  80. Kibert, C.J. Sustainable Construction: Green Building Design and Delivery; John Wiley & Sons: Hoboken, NJ, USA, 2016; ISBN 978-1-119-05517-4. [Google Scholar]
  81. Kahvandi, Z.; Saghatforoush, E.; ZareRavasan, A.; Preece, C. Integrated project delivery implementation challenges in the construction industry. Civil. Eng. J. 2019, 5, 1672–1683. [Google Scholar] [CrossRef]
  82. Ghassemi, R.; Becerik-Gerber, B. Transitioning to integrated project delivery: Potential barriers and lessons learned. Lean Constr. J. 2011, 32–52. [Google Scholar]
  83. Kent, D.; Becerik-Gerber, B. Understanding construction industry experience and attitudes toward integrated project delivery. J. Constr. Eng. Manag. 2010, 136, 815–825. [Google Scholar] [CrossRef]
  84. Cohen, J. Integrated Project Delivery: Case Studies. The American Institute of Architects. 2010. Available online: https://bit.ly/3uz6gkV (accessed on 26 October 2020).
  85. Townes, T.; Franz, B.; Leicht, R.M. A case study of IPD delivery team selection. In Proceedings of the 2015 Engineering Project Organization Conference, Edinburgh, UK, 3–4 September 2015; pp. 1–16. [Google Scholar]
  86. Piroozfar, P.; Farr, E.; Zadeh, A.; Timoteo Inacio, S.; Kilgallon, S.; Jin, R. Facilitating Building Information Modelling (BIM) using integrated project delivery (IPD): A UK perspective. J. Build. Eng. 2019, 26, 100907. [Google Scholar] [CrossRef]
  87. Newman, C.; Edwards, D.; Martek, I.; Lai, J.; Thwala, W.D.; Rillie, I. Industry 4.0 deployment in the construction industry: A bibliometric literature review and UK-based case study. Smart Sustain. Built Environ. 2020. ahead-of-print. [Google Scholar] [CrossRef]
  88. Kim, Y.; Rezquallah, K.; Lee, H.; Angeley, J. Integrated project delivery in public projects: Limitations and opportunity. In Proceedings of the 24th Annual Conference of the Int’l. Group for Lean Construction, Boston, MA, USA, 24 July 2016; pp. 93–102. [Google Scholar]
  89. Franz, B.; Leicht, R.; Molenaar, K.; Messner, J. Impact of team integration and group cohesion on project delivery performance. J. Constr. Eng. Manag. 2017, 143, 04016088. [Google Scholar] [CrossRef]
  90. Raisbeck, P.; Millie, R.; Maher, A. Assessing integrated project delivery: A comparative analysis of IPD and alliance contracting procurement routes. In Proceedings of the 26th Annual ARCOM Conference, Leeds, UK, 6–8 September 2010; pp. 1019–1028. [Google Scholar]
  91. Zhang, L.; Cheng, J.; anf Fan, W. Party selection for integrated project delivery based on interorganizational transactive memory system. J. Constr. Eng. Manag. 2016, 142, 04015089. [Google Scholar] [CrossRef]
  92. Kahvandi, Z.; Saghatforoush, E.; Mahoud, M.; Preece, C. Analysis of the barriers to the implementation of integrated project delivery (IPD): A meta-synthesis approach. journal of engineering. Proj. Prod. Manag. 2019, 9, 2–11. [Google Scholar] [CrossRef] [Green Version]
  93. Gomez, S.; Naderpajouh, N.; Ballard, G.; Hastak, M.; Weidner, T.J.; Barriga, P. Implications of the integrated project delivery research in practice. In Proceedings of the Construction Research Congress, New Orleans, LA, USA, 2–4 April 2018; pp. 86–96. [Google Scholar]
  94. Kahvandi, Z.; Saghatforoush, E.; Zare Ravasan, A.; Mansouri, T. An FCM-based dynamic modelling of integrated project delivery implementation challenges in construction projects. Lean Constr. J. 2018, 87, 63–87. [Google Scholar]
  95. Greenwald, N. Transforming a Fractured Industry: Employing Adr Techniques to Improve Collaboration in the Construction Industry. NYSBA—N. Y. Dispute Resolution Lawyer 2016, 9, 35–36. Available online: https://bit.ly/3fRgvwP (accessed on 26 October 2020).
  96. Zeng, T.; Deschênes, J.; Durif, F. Eco-design packaging: An epistemological analysis and transformative research agenda. J. Clean. Prod. 2020, 276, 123361. [Google Scholar] [CrossRef]
  97. Spellacy, J.; Edwards, D.J.; Roberts, C.J.; Hayhow, S.; Shelbourn, M. An investigation into the role of the quantity surveyor in the value management workshop process. J. Eng. Des. Technol. 2020, 19, 423–445. [Google Scholar] [CrossRef]
  98. Brandao, R.; Edwards, D.J.; Hossieni, M.R.; André, M.S.; Alcebiades, M. A reverse supply chain conceptual model for construction and demolition waste. Waste Manag. Res. 2021. [Google Scholar] [CrossRef]
  99. Kelly, L.; Cordeiro, M. Three principles of pragmatism for research on organizational processes. Methodol. Innov. 2020, 13, 1–10. [Google Scholar] [CrossRef]
  100. Kelemen, M.; Rumens, N. Pragmatism and heterodoxy in organization research. Int. J. Organ. Anal. 2012, 20, 5–12. [Google Scholar] [CrossRef]
  101. Riaz, Z.; Edwards, D.J.; Thorpe, A. SightSafety: A hybrid information and communication technology system for reducing vehicle/pedestrian collisions. Autom. Constr. 2006, 15, 719–728. [Google Scholar] [CrossRef]
  102. Akinlolu, M.; Haupt, T.C.; Edwards, D.J.; Simpeh, F. A bibliometric review of the status and emerging trends in construction safety management technologies. Int. J. Constr. Manag. 2020, 1–13. [Google Scholar] [CrossRef]
  103. Darko, A.; Chan, A.; Edwards, D.J.; Reza Hosseini, M.; Ameyaw, E. A scientometric analysis of artificial intelligence research in the construction industry. Autom. Constr. 2020, 112, 103081. [Google Scholar] [CrossRef]
  104. Roberts, C.J.; Pärn, E.A.; Edwards, D.J.; Aigbavboa, C. Digitalising asset management: Concomitant benefits and persistent challenges. Int. J. Build. Pathol. Adapt. 2018, 36, 152–173. [Google Scholar] [CrossRef]
  105. Al-Saeed, Y.; Edwards, D.; Scaysbrook, S. Automating construction manufacturing procedures using BIM digital objects (BDOs): Case study of knowledge transfer partnership project in UK. Constr. Innov. 2020, 20, 345–377. [Google Scholar] [CrossRef]
  106. Kaushik, V.; Walsh, C. Pragmatism as a research paradigm and its implications for social work research. Soc. Sci. 2019, 8, 255. [Google Scholar] [CrossRef]
  107. Ahmed, H.; Edwards, D.J.; Lai, J.H.K.; Roberts, C.; Debrah, C.; Owusu-Manu, D.G.; Thwala, W.D. Post occupancy evaluation of school refurbishment projects: Multiple case study in the UK. Buildings 2021, 11, 169. [Google Scholar] [CrossRef]
  108. Siu, K.W.M.; Xiao, J.X. Public facility design for sustainability: Participatory action research on household recycling in Hong Kong. Action Res. 2017, 18, 448–468. [Google Scholar] [CrossRef]
  109. Perera, G.; Tennakoon, T.; Kulatunga, U.; Jayasena, H.; Wijewickrama, M. Selecting suitable procurement system for steel building construction. Built Environ. Proj. Asset Manag. 2020. [Google Scholar] [CrossRef]
  110. Makarfi Ibrahim, Y.; Kaka, A.; Aouad, G.; Kagioglou, M. Framework for a generic work breakdown structure for building projects. Constr. Innov. 2009, 9, 388–405. [Google Scholar] [CrossRef]
  111. Dougherty, C. Introduction to Econometrics, 4th ed.; Oxford University Press: Oxford, UK, 2011; pp. 83–97. ISBN 978-0-19-956708-9. [Google Scholar]
  112. Love, P.; Holt, G.; Shen, L.; Li, H.; Irani, Z. Using systems dynamics to better understand change and rework in construction project management systems. Int. J. Proj. Manag. 2020, 20, 425–436. [Google Scholar] [CrossRef]
Figure 1. Timeline showing the evolution of procurement in the construction industry [25,28,29,30,31,32,33,34,35].
Figure 1. Timeline showing the evolution of procurement in the construction industry [25,28,29,30,31,32,33,34,35].
Buildings 11 00260 g001
Figure 2. RIBA Plan of Work 2020 design involvement/responsibility [3,50,52,53,54,55,56,57].
Figure 2. RIBA Plan of Work 2020 design involvement/responsibility [3,50,52,53,54,55,56,57].
Buildings 11 00260 g002
Figure 3. Integrated project delivery (IPD) selection process [26,34,85,87,88,89,90,91].
Figure 3. Integrated project delivery (IPD) selection process [26,34,85,87,88,89,90,91].
Buildings 11 00260 g003
Figure 4. Barriers to integrated project delivery (IPD) [76,81,85,91,92,93,94,95].
Figure 4. Barriers to integrated project delivery (IPD) [76,81,85,91,92,93,94,95].
Buildings 11 00260 g004
Figure 5. Waterfall research methodology.
Figure 5. Waterfall research methodology.
Buildings 11 00260 g005
Figure 6. (a) Longitudinal time horizon; (b) longitudinal time horizon excluding additional work.
Figure 6. (a) Longitudinal time horizon; (b) longitudinal time horizon excluding additional work.
Buildings 11 00260 g006aBuildings 11 00260 g006b
Table 1. Sources of change during the construction phase.
Table 1. Sources of change during the construction phase.
Source of ChangeDescription of the SourceReference
Design errorsOversights, mistakes, and inaccuracies in the design information that forms part of the contract documents. Resulting in revisions of the drawings therefore allowing the contractor to claim for the cost of the additional works.[44,58,59,60,61,62].
Design omissionsDesign information lacking sufficient information to allow the full extent of the project to be costed. Therefore, adding in the omissions at a later date is supplemented by cost increases.[44,58,59,60,61,62].
Client-drivenChanges requested/variation enquiries by the client that affect the time cost or quality of the project. Any change request provides the contractor an opportunity to revalue the item of works and submit a revised cost.[44,58,59,60,61,62].
Changes to the scope of worksChanges to the contract documents i.e., contractor qualifications, clarifications or omissions resulting in additional work on top of the contractual works. This can include re-introducing items that had been excluded by the contractor or changes to design to allow the work to be physically carried out due to an oversight of the complexity and buildability during the design phase for example.[58,59,60,61,62,63].
Design inconsistencies Discrepancies in the contract documents i.e., fundamental differences between the architects and structural engineers drawing. This links to changes the scope of works as it is dependent on the contractor’s clarifications as to what the costing was based on.[58].
Managerial factorsChanges resulting from failings of the client’s team. Including but not limited to:
-
Inaccurate cost estimates and advise to the client due to a lack of understanding of buildability
-
Design information not produced on time creating ambiguity
-
Inability to learn from passed experience and relying solely bottom-line comparison
Poor communication and leadership to consolidate various stakeholders design inputs.
[58,59,60,63,64].
Unforeseen conditionsThe ‘unknown-unknowns’—Things that cannot be foreseen or accounted for i.e., force majeure or regulatory changes.[44,59,61]
Table 2. Demographic profiles of focus group participants.
Table 2. Demographic profiles of focus group participants.
ParticipantPosition in BusinessYears of Experience in IndustryYears of Experience in Current PositionHighest Qualification
AManaging Director35+13 as MD and 7 prior to that as a regional directorMCIOB
BCommercial Manager233BSc
CSite Manager3220CIOB (Level 4) and SMSTS
Table 3. Cost data to show bimonthly cumulative growth.
Table 3. Cost data to show bimonthly cumulative growth.
APPLIC ATIONFINAL ACCOUNT
DESCRIPTIONCONTRACT1234567891011121314APPLICATIONAGREED
SUM
ESTIMATEDTOTALTOTALTOTALTOTALTOTALTOTALTOTALTOTALTOTALTOTALTOTALTOTALTOTALTOTALTOTALTOTAL
COST
Prelims: Fixed£12,215.00£648.00£810.00£810.00£810.00£1092.00£1092.00£5730.75£7277.00£7277.00£7277.00£7737.00£9060.00£9060.00£11,706.00£12,215.00£12,215.00
Prelims: Time Related£29,628.37£2370.27£4740.54£7407.09£9777.36£12,443.92£14,814.19£17,283.22£19,752.25£22,221.28£24,690.31£27,159.34£29,628.37£29,628.37£33,906.37£33,906.37£29,628.37
Prelims: adjustment to final
account −£509.00−£509.00
0. Facilitating works£3742.00£3167.00£3217.00£3217.00£3217.00£3517.00£3517.00£3517.00£3517.00£3517.00£3517.00£3517.00£3742.00£3742.00£3742.00£3742.00£3742.00
1. Substructure£30,729.93£6878.00£15,900.41£25,559.56£28,579.56£28,253.03£28,253.03£28,253.03£25,290.17£25,290.17£25,290.17£25,290.17£25,290.17£25,290.17£25,946.92£25,805.00£25,245.00
2.1 Structural Frame£1500.00£0.00£900.00£1350.00£1500.00£1500.00£1500.00£1500.00£1500.00£1500.00£1500.00£1500.00£1500.00£1500.00£1500.00£1500.00£1500.00
2.3 Roof Structure£30,388.57£1426.50£1426.50£2853.00£5940.47£10,720.47£15,220.47£21,369.11£29,197.46£30,669.76£30,669.76£30,669.76£30,669.76£30,669.76£30,669.76£30,670.57£30,670.57
2.5 External Walls£15,756.71£0.00£0.00£0.00£6684.60£13,845.86£14,209.61£15,271.71£15,271.71£15,271.71£15,271.71£15,654.96£15,654.96£15,654.96£15,654.96£15,894.71£15,894.71
2.6 Windows & External Doors£27,994.00£0.00£0.00£559.88£0.00−£199.80£2039.72£2039.72£14,467.36£17,534.83£29,134.53£29,134.53£29,134.53£29,134.53£29,134.53£29,142.00£29,142.00
2.7 Internal Walls & Partitions£22,386.10£0.00£0.00£0.00£232.16£232.16£348.24£348.24£1246.80£11,772.41£19,611.67£22,085.77£22,031.29£22,031.29£22,031.29£22,166.10£22,166.10
2.8 Internal Doors (Joinery)£2159.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£50.00£901.97£1736.97£1756.97£1756.97£1756.97£2560.00£2560.00
3.1 Wall Finishes£5850.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£670.00£670.00£1715.00£4150.34£4485.34£4485.34£4485.34£4610.00£4610.00
3.2 Floor Finishes£1310.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£220.00£0.00£1060.00£1060.00£1280.00£1280.00£1280.00£1280.00
3.3 Ceiling Finishes£11,237.00£0.00£0.00£0.00£0.00£0.00£0.00£1978.00£3956.00£6923.00£10,167.50£10,662.00£10,662.00£10,662.00£10,662.00£10,662.00£10,662.00
4. FF&E£400.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£200.00£400.00£524.30£524.30£650.00£650.00
5.1 M&E£54,859.00£272.80£272.80£272.80£272.80£272.80£272.80£272.80£16,367.70£27,279.50£38,191.30£54,481.00£57,208.95£57,698.69£57,698.69£58,492.00£58,492.00
5.11 Lightning Protection£500.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00
5.14 BWIC£1000.00£0.00£0.00£0.00£0.00£250.00£250.00£250.00£200.00£500.00£750.00£1000.00£1000.00£1000.00£1000.00£1000.00£1000.00
8.2 Roads, Paths, Paving’s &
Surfacing’s£8760.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£70.00£2577.50£8670.00£9130.00£9130.00
8.3 Soft Landscaping£500.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£1336.20£1480.50£2301.00£2301.00
8.4 Fencing, Railings & Walls£80.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£1406.19£1406.19£1486.19£1486.19£1486.19£1744.00£1744.00
8.6 External Drainage£9593.00£0.00£6143.75£6143.75£6143.75£7396.20£7396.20£7396.20£7396.20£7396.20£7396.20£7396.20£7396.20£8420.70£10,040.70£10,043.00£10,043.00
8.7 External Services£3825.00£0.00£2175.00£2175.00£2175.00£2175.00£2175.00£2175.00£2175.00£2175.00£2175.00£2175.00£2950.00£3825.00£3825.00£3825.00£3825.00
Additional Work 1: Extent
Building by 450 mm£0.00£0.00£0.00£0.00£0.00£656.06£1180.90£1180.90£2361.80£2361.80£2361.80£2361.80£2624.23£2624.23£2624.23£2639.00£2639.00
Additional Work 2: Patio, shed
base and supplies to outdoor
kitchen£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£3362.14£12,103.72£13,179.60£13,655.00£13,655.00
Additional Works 3: Outdoor
kitchen£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£4810.00£6794.82£6972.00£6972.00
Additional Works 4: Outdoor
kitchen foundation£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£820.48£825.00£825.00
Additional Works 5: Gravel to
driveway£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£2230.00£2230.00
Construction works adjustment
to final account £122.81£122.81
OH&P£20,581.03£1107.19£2668.95£3776.11£4899.95£6161.60£6922.33£8144.57£11,295.81£13,699.01£16,666.40£18,727.58£19,624.44£21,296.15£22,458.90£23,045.52£22,682.67
Material on site; Aqua panel & anti corrosive stud£0.00£0.00£0.00£0.00£0.00£0.00£0.00£15,000.00£15,000.00£7500.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00
Material on site; paving slabs£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£3043.40£3043.40£0.00£0.00£0.00£0.00
TOTAL£294,994.71£15,869.76£38,254.94£54,124.18£70,232.64£88,316.29£99,191.48£131,710.24£176,942.26£203,828.67£238,693.52£271,149.01£283,840.94£302,598.06£323,079.55£330,319.08£325,118.23
Table 4. Cost data to show bimonthly cumulative growth (excluding additional work).
Table 4. Cost data to show bimonthly cumulative growth (excluding additional work).
APPLICATION
DESCRIPTIONCONTRACT SUM1234567891011121314
ESTIMATED
COST
TOTAL VALUETOTALTOTALTOTALTOTALTOTALTOTALTOTALTOTALTOTALTOTALTOTALTOTALTOTAL
Prelims: Fixed£12,215.00£648.00£810.00£810.00£810.00£1092.00£1092.00£5730.75£7277.00£7277.00£7277.00£7737.00£9060.00£9060.00£11,706.00
Prelims: Time Related£29,628.37£2370.27£4740.54£7407.09£9777.36£12,443.92£14,814.19£17,283.22£19,752.25£22,221.28£24,690.31£27,159.34£29,628.37£29,628.37£33,906.37
Prelims: adjustment to final
account
0. Facilitating works£3742.00£3167.00£3217.00£3217.00£3217.00£3517.00£3517.00£3517.00£3517.00£3517.00£3517.00£3517.00£3742.00£3742.00£3742.00
1. Substructure£30,729.93£6878.00£15,900.41£25,559.56£28,579.56£28,253.03£28,253.03£28,253.03£25,290.17£25,290.17£25,290.17£25,290.17£25,290.17£25,290.17£25,946.92
2.1 Structural Frame£1500.00£0.00£900.00£1350.00£1500.00£1500.00£1500.00£1500.00£1500.00£1500.00£1500.00£1500.00£1500.00£1500.00£1500.00
2.3 Roof Structure£30,388.57£1426.50£1426.50£2853.00£5940.47£10,720.47£15,220.47£21,369.11£29,197.46£30,669.76£30,669.76£30,669.76£30,669.76£30,669.76£30,669.76
2.5 External Walls£15,756.71£0.00£0.00£0.00£6684.60£13,845.86£14,209.61£15,271.71£15,271.71£15,271.71£15,271.71£15,654.96£15,654.96£15,654.96£15,654.96
2.6 Windows & External Doors£27,994.00£0.00£0.00£559.88£0.00−£199.80£2039.72£2039.72£14,467.36£17,534.83£29,134.53£29,134.53£29,134.53£29,134.53£29,134.53
2.7 Internal Walls & Partitions£22,386.10£0.00£0.00£0.00£232.16£232.16£348.24£348.24£1246.80£11,772.41£19,611.67£22,085.77£22,031.29£22,031.29£22,031.29
2.8 Internal Doors (Joinery)£2159.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£50.00£901.97£1736.97£1756.97£1756.97£1756.97
3.1 Wall Finishes£5850.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£670.00£670.00£1715.00£4150.34£4485.34£4485.34£4485.34
3.2 Floor Finishes£1310.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£220.00£0.00£1060.00£1060.00£1280.00£1280.00
3.3 Ceiling Finishes£11,237.00£0.00£0.00£0.00£0.00£0.00£0.00£1978.00£3956.00£6923.00£10,167.50£10,662.00£10,662.00£10,662.00£10,662.00
4. FF&E£400.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£200.00£400.00£524.30£524.30
5.1 M&E£54,859.00£272.80£272.80£272.80£272.80£272.80£272.80£272.80£16,367.70£27,279.50£38,191.30£54,481.00£57,208.95£57,698.69£57,698.69
5.11 Lightning Protection£500.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00
5.14 BWIC£1000.00£0.00£0.00£0.00£0.00£250.00£250.00£250.00£200.00£500.00£750.00£1000.00£1000.00£1000.00£1000.00
8.2 Roads, Paths, Paving’s &
Surfacing’s£8760.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£70.00£2577.50£8670.00
8.3 Soft Landscaping£500.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£1336.20£1480.50
8.4 Fencing, Railings & Walls£80.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£1406.19£1406.19£1486.19£1486.19£1486.19
8.6 External Drainage£9593.00£0.00£6143.75£6143.75£6143.75£7396.20£7396.20£7396.20£7396.20£7396.20£7396.20£7396.20£7396.20£8420.70£10,040.70
8.7 External Services£3825.00£0.00£2175.00£2175.00£2175.00£2175.00£2175.00£2175.00£2175.00£2175.00£2175.00£2175.00£2950.00£3825.00£3825.00
Additional Work 1: Extent
Building by 450 mm£0.00
Additional Work 2: Patio, shed
base and supplies to outdoor
kitchen£0.00
Additional Works 3: Outdoor
kitchen£0.00
Additional Works 4: Outdoor
kitchen foundation£0.00
Additional Works 5: Gravel to
driveway£0.00
Construction works adjustment
to final account
OH&P£20,581.03£1107.19£2668.95£3776.11£4899.95£6161.60£6922.33£8144.57£11,295.81£13,699.01£16,666.40£18,727.58£19,624.44£21,296.15£22,458.90
Material on site; Aqua panel & anti corrosive stud£0.00£0.00£0.00£0.00£0.00£0.00£0.00£15,000.00£15,000.00£7500.00£0.00£0.00£0.00£0.00£0.00
Material on site; paving slabs£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£0.00£3043.40£3043.40£0.00£0.00
£294,994.71£15,869.76£38,254.94£54,124.18£70,232.64£87,660.23£98,010.58£130,529.34£174,580.46£201,466.86£236,331.71£268,787.21£277,854.57£283,060.12£299,660.42
Table 5. Cross-sectional time horizon.
Table 5. Cross-sectional time horizon.
DescriptionContract SumFinal Account Agreed% ErrorReason for Change
Estimated CostActual CostVariationsTotal
Prelims: Fixed£12,215£12,215£−£12,2150.00%No change
Prelims: Time Related£29,628£29,628£−£29,6280.00%No change (V036. removed from final account
as agreed)
Prelims: adjustment to£−−£509£−−£509New entryArithmetical error
final account
0. Facilitating works£3742£3742£−£37420.00%No change
1. Substructure£30,730£29,100−£3855£25,245−17.85%V02.Client-driven
V06.Unforeseen conditions
V034.Client-driven/change to scope of works
2.1 Structural Frame£1500£1500£−£15000.00%No change
2.3 Roof Structure£30,389£30,389£282£30,6710.93%V08.Other-Material availability
V012.Client Driven
V016.Design error/omission
2.5 External Walls£15,757£15,757£138£15,8950.88%V07.Client-driven
V09.Design error
2.6 Windows & External£27,994£27,994£1148£29,1424.10%V05.Design error/omission
Doors
2.7 Internal Walls &£22,386£22,146£20£22,166−0.98%V010.Design error/omission
Partitions V014.Design error
V020.Change to scope of works
2.8 Internal Doors£2159£2159£401£256018.57%V018.Client-driven
(Joinery) V019.Change to scope of works
V022.Client-driven
3.1 Wall Finishes£5850£5850−£1240£4610−21.20%V021. Client-driven
V025.Client-driven/change to scope of works
3.2 Floor Finishes£1310£1060£220£1280−2.29%V013.Change to scope of work
3.3 Ceiling Finishes£11,237£10,662£−£10,662−5.12%False ceiling to steam shower Not required
therefore, value not drawn
4. FF&E£400£400£250£65062.50%V027.Client-driven
5.1 M&E£54,859£54,859£3633£58,4926.62%V011.Client-driven
V026.Client-driven
V028.Client-driven
V029.Design error/omission
V030.Client-driven
V035.2. Client-driven
V037.Design error
5.11 Lightning£500£−£−£−−100.00%Not required therefore value not drawn
Protection
5.14 BWIC£1000£1000£−£10000.00%No change
8.2 Roads, Paths,£8760£8010£1120£91304.22%Construction of new brick bier and capping’s not
Paving’s & Surfacing’s required therefore value not drawn
V031.Client-driven
V032.Unforseen conditions
V035.3. Client-driven
8.3 Soft Landscaping£500£500£1801£2301360.20%V023.Other-provisional sum expenditure
8.4 Fencing, Railings &£80£80£1664£17442080.00%V015.Client-driven
Walls V035.1. Client-driven
8.6 External Drainage£9593£9593£450£10,0434.69%V03.Design error
V04.Design omission
8.7 External Services£3825£3825£−£38250.00%No change
Additional Work 1:£−£−£2639£2639New entryV01.Client-driven
Extent Building by
450 mm
Additional Work 2:£−£−£13,655£13,655New entryV017.Client-driven
Patio, shed base and V033.Change to scope of work
supplies to outdoor
kitchen
Additional Works 3:£−£−£6972£6972New entryV024.A. Client-driven
Outdoor kitchen
Additional Works 4:£−£−£825£825New entryV024.B. Client-driven
Outdoor kitchen
foundation
Additional Works 5:£−£−£2230£2230New entryV038.Client-driven
Gravel to driveway
Construction Works:£−£123£−£123New entryArithmetical error
adjustment to final
account
OH&P£20,581£20,256£2426£22,68310.21%
TOTAL:£294,995£290,339£34,779£325,11810.21%As discussed above
Table 6. Cross-sectional time horizon (excluding additional work).
Table 6. Cross-sectional time horizon (excluding additional work).
DescriptionContract SumFinal Account Agreed% ErrorReasons for Change
Estimated
Cost
Actual
Cost
VariationsTotal
Prelims: Fixed£12,215£12,215£−£12,2150.00%No change
Prelims: Time Related£29,628£29,628£−£29,6280.00%No change (V036. removed from final account as agreed)
Prelims: adjustment to final£−−£509£−−£509New entryArithmetical error
account
0. Facilitating works£3742£3742£−£37420.00%No change
1. Substructure£30,730£29,100−£3855£25,245−17.85%V02.Client-driven
V06.Unforeseen conditions
V034.Client-driven/change to scope of works
2.1 Structural Frame£1500£1500£−£15000.00%No change
2.3 Roof Structure£30,389£30,389£282£30,6710.93%V08.Other-Material availability
V012.Client Driven
V016.Design error/omission
2.5 External Walls£15,757£15,757£138£15,8950.88%V07.Client-driven
V09.Design error
2.6 Windows & External£27,994£27,994£1148£29,1424.10%V05.Design error/omission
Doors
2.7 Internal Walls &£22,386£22,146£20£22,166−0.98%V010.Design error/omission
Partitions V014.Design error
V020.Change to scope of works
2.8 Internal Doors (Joinery)£2159£2159£401£256018.57%V018.Client-driven
V019.Change to scope of works
V022.Client-driven
3.1 Wall Finishes£5850£5850−£1240£4610−21.20%V021. Client-driven
V025.Client-driven/change to scope of works
3.2 Floor Finishes£1310£1060£220£1280−2.29%V013.Change to scope of work
3.3 Ceiling Finishes£11,237£10,662£−£10,662−5.12%False ceiling to steam shower Not required therefore value
not drawn
4. FF&E£400£400£250£65062.50%V027.Client-driven
5.1 M&E£54,859£54,859£3633£58,4926.62%V011.Client-driven
V026.Client-driven
V028.Client-driven
V029.Design error/omission
V030.Client-driven
V035.2. Client-driven
V037.Design error
5.11 Lightning Protection£500£−£−£−−100.00%Not required therefore value not drawn
5.14 BWIC£1000£1000£ -£10000.00%No change
8.2 Roads, Paths, Paving’s£8760£8010£1120£91304.22%Construction of new brick bier and capping’s not required
& Surfacing’s therefore value not drawn
V031.Client-driven
V032.Unforseen conditions
V035.3. Client-driven
8.3 Soft Landscaping£500£500£1801£2301360.20%V023.Change to scope of works
8.4 Fencing, Railings &£80£80£1664£17442080.00%V015.Client-driven
Walls V035.1. Client-driven
8.6 External Drainage£9593£9593£450£10,0434.69%V03.Design error
V04.Design omission
8.7 External Services£3825£3825£−£38250.00%No change
Construction works£−£123£−£123New entryArithmetical error
adjustment to final account
OH&P£20,581£20,256£2426£22,68310.21%
£294,995£290,339£8458£298,7971.29%As discussed above
Table 7. Summary of statistical data following t-test.
Table 7. Summary of statistical data following t-test.
StatisticResult
Mean Difference£152
Standard Deviation of Difference£1549
Standard Error of Difference£323
½ T alpha 95% Confidence interval2.06
Lower Confidence Interval−£487
Upper Confidence Interval£791
Table 8. Outlier, MPE, and MAPE data.
Table 8. Outlier, MPE, and MAPE data.
DESCRIPTIONContract SumFinal Account Agreed% ErrorAbsolute
% Error
Notes
Estimated CostActual CostVariations
£−
Total
Prelims: Fixed£12,215£12,215£0£12,2150.00%0.00%
Prelims: Time Related£29,628£29,628£0£29,6280.00%0.00%
0. Facilitating works£3742£3742£0£37420.00%0.00%
2.1 Structural Frame£1500£1500£0£15000.00%0.00%
5.14 BWIC£1000£1000£0£10000.00%0.00%
8.7 External Services£3825£3825£0£38250.00%0.00%Q1
2.5 External Walls£15,757£15,757£138£15,8950.88%0.88%
2.3 Roof Structure£30,389£30,389£282£30,6710.93%0.93%
2.7 Internal Walls & Partitions£22,386£22,146£20£22,166−0.98%0.98%
3.2 Floor Finishes£1310£1060£220£1280−2.29%2.29%
2.6 Windows & External Doors£27,994£27,994£1148£29,1424.10%4.10%
8.2 Roads, Paths, Paving’s &
Surfacing’s£8760£8010£1120£91304.22%4.22%Mid-Point
8.6 External Drainage£9593£9593£450£10,0434.69%4.69%
3.3 Ceiling Finishes£11,237£10,662£0£10,662−5.12%5.12%
5.1 M&E£54,859£54,859£3633£58,4926.62%6.62%
OH&P£20,581£20,285£2426£22,71210.35%10.35%
1. Substructure£30,730£29,100−£3855£25,245−17.85%17.85%
2.8 Internal Doors (Joinery)£2159£2159£401£256018.57%18.57%Q3
3.1 Wall Finishes£5850£5850−£1240£4610−21.20%21.20%
4. FF&E£400£400£250£65062.50%62.50%Outlier removed
5.11 Lightning Protection£500£0£0£0−100.00%100.00%Outlier removed
8.3 Soft Landscaping£500£500£1801£2301360.20%360.20%Outlier removed
8.4 Fencing, Railings & Walls£80£80£1664£17442080.00%2080.00%Outlier removed
£293,515£289,774£4743£294,5172.93%97.80%
Table 9. Focus group questions.
Table 9. Focus group questions.
No.QuestionPrompts
1
  • Based on your experience of tendering for work, what is the key determining factor for contractor selection?
  • Price?
  • Understanding of the scope of works? Qualifications and clarifications?
  • Previous experience?
2
  • Of the tenders you have been involved in, what is the most frequently used procurement route?
  • And why do you think this is?
  • Traditional? Design and build? Construction Management/Management Contracting? IPD?
  • Cost certainty? Ease of levelling bids? Design and construction occur at the same time? Off load risk? Competence/incompetence of design team?
3
  • During a competitively tendered project what strategies do you implement in order to increase the chances of being consider for the post tender Q&A process?
  • Exclusions and clarifications to lower the overall tender sum?
  • Can provisional and prime cost sums be used strategically during the tender process?
  • How can ambiguity in the scope of works/design be used tactically to improve your position?
  • Raise TQ’s and communication with client team? Examples?
4
  • Based on your involvement in the case study project—what impact if any did the negotiated procurement route have on the project delivery phase?
  • Communication?
  • Open book approach to variations? Contract/client relationship?
  • Project success—time cost and quality
5
  • Excluding the additional work outside of the contract scope of works. The cross-sectional time horizon shows the contract sum increased by 1.29% to the final account. What influence did the negotiated procurement route and the contractor/client relationship have on this?
  • Open book environment Cost certainty
  • No need to use variations to increase final account to true value of the works?
  • Scope of works correctly allowed for at tender stage? Profitable job from outset?
6
  • Various elements of construction work saw percentage reductions from the contract sum to the final account. Why was this?
  • Omission from the scope of works? Provisional sum expenditure?
  • Procurement route influence (project already profitable)?
  • Honest approach—win/win situation?
7
  • The large value variations have been classified as additional works. Why were these items not allowed for at tender stage?
  • Not included in scope of works? Client request/Change?
  • Excluded as the scope was ambiguous?
8
  • Would you class the project delivery as successful and why?
  • Time?
  • Cost?
  • Quality?
  • Client satisfaction? Profitability?
9
  • What impact did the negotiated procurement route have on this?
  • Communication? Open book?
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Ellis, J.; Edwards, D.J.; Thwala, W.D.; Ejohwomu, O.; Ameyaw, E.E.; Shelbourn, M. A Case Study of a Negotiated Tender within a Small-to-Medium Construction Contractor: Modelling Project Cost Variance. Buildings 2021, 11, 260. https://doi.org/10.3390/buildings11060260

AMA Style

Ellis J, Edwards DJ, Thwala WD, Ejohwomu O, Ameyaw EE, Shelbourn M. A Case Study of a Negotiated Tender within a Small-to-Medium Construction Contractor: Modelling Project Cost Variance. Buildings. 2021; 11(6):260. https://doi.org/10.3390/buildings11060260

Chicago/Turabian Style

Ellis, James, David John Edwards, Wellington Didibhuku Thwala, Obuks Ejohwomu, Ernest Effah Ameyaw, and Mark Shelbourn. 2021. "A Case Study of a Negotiated Tender within a Small-to-Medium Construction Contractor: Modelling Project Cost Variance" Buildings 11, no. 6: 260. https://doi.org/10.3390/buildings11060260

APA Style

Ellis, J., Edwards, D. J., Thwala, W. D., Ejohwomu, O., Ameyaw, E. E., & Shelbourn, M. (2021). A Case Study of a Negotiated Tender within a Small-to-Medium Construction Contractor: Modelling Project Cost Variance. Buildings, 11(6), 260. https://doi.org/10.3390/buildings11060260

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.