Investigation on the Influence of Active Underpinning Process on Bridge Substructures during Shield Tunnelling: Numerical Simulation and Field Monitoring
Abstract
:1. Introduction
2. Engineering Background
2.1. Project Introduction
2.2. Engineering Geological Conditions
2.3. Position of Bridge Pile Foundation and Shield Tunnel
3. The Underpinning Scheme of Bridge Pile
- (1)
- A jack is set on the underpinning platform, the underpinning beam and the underpinning pile are constructed independently, and a rigid overall structure is formed after the underpinning force of the pile foundation is converted. When the underpinning pile, underpinning beam and underpinning platform concrete reach the design strength, the loading underpinning construction will be carried out;
- (2)
- During underpinning, a jack is set up between the underpinning beam and the underpinning cap to transfer the load of the superstructure to the new underpinning pile and make most of the displacement of the new pile to offset the preload of the jack simultaneously, making the new underpinning pile can replace the force of the original pile through active loading;
- (3)
- During the underpinning process of pile foundation, the PLC hydraulic synchronous control system is used to jack up the underpinning beam and preload the underpinning pile. At the same time, the load and displacement changes of the underpinning pile are monitored to ensure the settlement of underpinned pile does not exceed the control value. The loading is divided 10 times, with 10% of the total jacking force as the interval;
- (4)
- After the end of the jacking stage, the unloading stage begins, and the unloading process is divided 5 times, with 20% as the interval;
- (5)
- Considering that the structure above the underpinning beam needs to remain balanced, the original pile foundation is cut off using a wire saw. The cutting height of the pile is controlled within the range of 300~500 mm, and the cutting gap is 5~10 mm. After the first cutting is completed, it is necessary to ensure continuous monitoring for more than 1 h, and the second cutting can only be carried out after the settlement becomes stable. During the pile cutting process and after the pile cutting is completed, the jacking force should be monitored and adjusted to ensure that the original column elevation remains unchanged. The construction process of the underpinning pile foundation is shown in Figure 3.
4. Numerical Simulation of Pile Foundation Underpinning Process
4.1. The Establishment of Model
4.2. Simulation Procedure
- (1)
- Step 0: the balance of earth stress;
- (2)
- Before the underpinning, because the “jack” does not work between the underpinning beam and the bearing platform, the “jack” concrete block is not activated first;
- (3)
- According to the “General Code for Design of Highway Bridges and Culverts” (JTG D60-2015) [34], the standard value of the uniformly distributed load of the I-level lane is qk = 10.5 kN/m, and the span is 20 m, hence a uniformly distributed load of 210 kN is applied to the bridge deck to simulate the traffic load;
- (4)
- Step 1–10 jacking stage: as shown in Figure 5c, jacking force is subjected to the bottom of underpinning beams and the upper part of the cap at two sides. According to the construction scheme, the loadings applied to the left and right pile platforms are 3466 kN and 4588 kN, respectively, which are converted into equivalent pressure in Table 3. The loading is divided 10 times, and 10% of the total jacking force is applied each time;
- (5)
- Step 11–15 unloading stage: after the lifting is completed, unloading is carried out. The unloading interval is 20% of the total lifting force, and the unloading is carried out 5 times;
- (6)
- Step 16 Pile cutting and sealing stage: In the actual project, the truncation is carried out in two steps. In this simulation, it is simplified to activate the “jack” concrete block to simulate the completion of the pile sealing and truncate the old pile to be separated by 0.2 m, as shown in Figure 5d.
Pile No. | Total Pressure on Left Pile Platform/kPa | Pressure on Left Pile Platform Each Loading Step/kPa | Pressure on Left Pile Platform Each Unloading Step/kPa | Total Pressure on Right Pile Platform/kPa | Pressure on Right Pile Platform Each Loading Step/kPa | Pressure on Left Pile Platform Each Unloading Step/kPa |
---|---|---|---|---|---|---|
C15 | 3066 | 306.6 | 613.2 | 4058 | 405.8 | 811.6 |
4.3. The Analysis of Simulation Result
5. Field Verification of Pile Foundation Underpinning Scheme
5.1. Monitoring Content and Methods
5.2. Monitoring Data Analysis
5.2.1. Jacking Stage of Underpinning Pile
5.2.2. Underpinning Pile Unloading Stage
5.2.3. Underpinning Pile Cutting Stage
6. Conclusions
- (1)
- It can be seen from the changing trend of the displacement of the new piles through numerical simulation that were the same as the bridge pier and the underpinning beam, that there is a relatively stable growth of the displacement in the first five times of jacking, and after the 6th jacking, especially at the new pile near the old pile side, the settlement value in the last jacking was increased by 40% compared with the previous one. The maximum settlement value of the new pile on the side away from the old pile was 2.12 mm, while the maximum settlement value of the new pile was 3.48 mm, which reached the early warning value during monitoring, but did not reach the control value; thus, the focus should be on monitoring the settlement changes of the new piles near the old piles during the jacking process of the jack underpinning the pile foundation;
- (2)
- When the jack was unloaded in the numerical simulation, the piers, underpinning beams and new piles had relatively stable displacement changes. In the actual monitoring data, the same displacement change was within the safe range. When the old piles were cut off, there was no sudden change in the displacement of the bridge piers, underpinning beams and new piles, which proved that the pile foundation underpinning construction scheme is reasonable and feasible. In the actual monitoring of the pile cutting stage, there was no displacement exceeding the early warning value in the two cutting-off old piles;
- (3)
- In the monitoring of the two piles, the displacement of the bridge piers had an upward trend. This is because in the jacking stage, due to the existence of the old piles, the jacking force will generate prestress between the old piles and the bridge piers. When the old piles are cut off, the stress is gradually released, resulting in an increase in the displacement of the bridge piers. The displacement tends to be stable, and the magnitude of the change is also within a safe range. The above phenomena indicate more attention should be paid to the monitoring of the substructure of the bridge during the pile-cutting stage;
- (4)
- According to the analysis of the monitoring results of the bridge piers, underpinning beams and new piles, the data calculated by the finite element software were roughly the same as the monitoring trend. The main structure of the lower part of the bridge did not have a large displacement, indicating that the finite element calculation results are credible.
Author Contributions
Funding
Data Availability Statement
Conflicts of Interest
References
- Xiao, C.; Yang, Y.; Chi, G. Subway development and obesity: Evidence from China. J. Transp. Health 2021, 21, 101065. [Google Scholar] [CrossRef]
- Ding, L.; Jie, X.U. A review of metro construction in China: Organization, market, cost, safety and schedule. Front. Eng. Manag. 2017, 16, 4–19. [Google Scholar] [CrossRef] [Green Version]
- Wang, T.; Tan, L.; Xie, S.; Ma, B. Development and applications of common utility tunnels in China. Tunn. Undergr. Space Technol. 2018, 76, 92–106. [Google Scholar] [CrossRef]
- Chang, X.S. Underground Tunnel Development Survey of Shield Tunnelling Machine. Adv. Mater. Res. 2011, 299–300, 1111–1114. [Google Scholar] [CrossRef]
- Koyama, Y. Present status and technology of shield tunneling method in Japan. Tunn. Undergr. Space Technol. 2003, 18, 145–159. [Google Scholar] [CrossRef]
- Mao, J.-H.; Yuan, D.-J.; Jin, D.-L.; Zeng, J.-F. Optimization and application of backfill grouting material for submarine tunnel. Constr. Build. Mater. 2020, 265, 120281. [Google Scholar] [CrossRef]
- Cao, L.; Kalinski, M. Risk Analysis of Subway Shield Tunneling. In Geo-Risk 2017; The American Society of Civil Engineers: Reston, VA, USA, 2017; pp. 309–319. [Google Scholar]
- Liu, C.; Li, J.; Zhang, Z.; Li, P.; Cui, J.; Liu, H.; Yang, Y. Model tests on tail-grouting process during URUP shield tunneling in soft soil. Tunn. Undergr. Space Technol. 2020, 103, 103451. [Google Scholar] [CrossRef]
- Hajjar, M.; Hayati, A.N.; Ahmadi, M.M.; Sadrnejad, S.A. Longitudinal Settlement Profile in Shallow Tunnels in Drained Conditions. Int. J. Geomech. 2015, 15, 04014097. [Google Scholar] [CrossRef]
- Fargnoli, V.; Boldini, D.; Amorosi, A. TBM tunnelling-induced settlements in coarse-grained soils: The case of the new Milan underground line 5. Tunn. Undergr. Space Technol. 2013, 38, 336–347. [Google Scholar] [CrossRef]
- Loganathan, N.; Poulos, H.G.; Stewart, D.P. Centrifuge model testing of tunnelling-induced ground and pile deformations. Géotechnique 2000, 50, 283–294. [Google Scholar] [CrossRef]
- Wu, C.; Zhu, Z. Analytical Method for Evaluating the Ground Surface Settlement Caused by Tail Void Grouting Pressure in Shield Tunnel Construction. Adv. Civ. Eng. 2018, 2018, 3729143. [Google Scholar] [CrossRef]
- Xie, X.; Yang, Y.; Ji, M. Analysis of ground surface settlement induced by the construction of a large-diameter shield-driven tunnel in Shanghai, China. Tunn. Undergr. Space Technol. 2016, 51, 120–132. [Google Scholar] [CrossRef]
- Li, X.-G.; Chen, X.-S. Using Grouting of Shield Tunneling to Reduce Settlements of Overlying Tunnels: Case Study in Shenzhen Metro Construction. J. Constr. Eng. Manag. 2012, 138, 574–584. [Google Scholar] [CrossRef]
- Mirhabibi, A.; Soroush, A. Effects of surface buildings on twin tunnelling-induced ground settlements. Tunn. Undergr. Space Technol. 2012, 29, 40–51. [Google Scholar] [CrossRef]
- Li, Z.; Chen, Z.; Wang, L.; Zeng, Z.; Gu, D. Numerical simulation and analysis of the pile underpinning technology used in shield tunnel crossings on bridge pile foundations. Undergr. Space 2021, 6, 396–408. [Google Scholar] [CrossRef]
- Zhang, K.; Chavez Torres, J.L.; Zang, Z. Numerical Analysis of Pipelines Settlement Induced by Tunneling. Adv. Civ. Eng. 2019, 2019, 4761904. [Google Scholar] [CrossRef] [Green Version]
- Lin, C.-G.; Zhang, Z.-M.; Wu, S.-M.; Yu, F. Key techniques and important issues for slurry shield under-passing embankments: A case study of Hangzhou Qiantang River Tunnel. Tunn. Undergr. Space Technol. 2013, 38, 306–325. [Google Scholar] [CrossRef]
- Wang, N.; Jiang, Y.; Geng, D.; Huang, Z.; Ding, H. Numerical Investigation of the Combined Influence of Shield Tunneling and Pile Cutting on Underpinning Piles. Front. Earth Sci. 2022, 10, 896634. [Google Scholar] [CrossRef]
- Zumsteg, R.; Langmaack, L. Mechanized Tunneling in Soft Soils: Choice of Excavation Mode and Application of Soil-Conditioning Additives in Glacial Deposits. Engineering 2017, 3, 863–870. [Google Scholar] [CrossRef]
- Soomro, M.A.; Ng, C.W.W.; Liu, K.; Memon, N.A. Pile responses to side-by-side twin tunnelling in stiff clay: Effects of different tunnel depths relative to pile. Comput. Geotech. 2017, 84, 101–116. [Google Scholar] [CrossRef]
- Xu, Q.; Zhu, H.; Ma, X.; Ma, Z.; Li, X.; Tang, Z.; Zhuo, K. A case history of shield tunnel crossing through group pile foundation of a road bridge with pile underpinning technologies in Shanghai. Tunn. Undergr. Space Technol. 2015, 45, 20–33. [Google Scholar] [CrossRef]
- Yan, L.; Wang, G.; Chen, M.; Yue, K.; Li, Q. Experimental and Application Study on Underpinning Engineering of Bridge Pile Foundation. Adv. Civ. Eng. 2018, 2018, 5758325. [Google Scholar] [CrossRef]
- Liu, C.; Zhang, Z.; Regueiro, R.A. Pile and pile group response to tunnelling using a large diameter slurry shield—Case study in Shanghai. Comput. Geotech. 2014, 59, 21–43. [Google Scholar] [CrossRef]
- Stulgis, R.P.; Barry, B.E.; Francis, S.; Harvey, J. Foundation Underpinning with Mini-Piles: “A First” in Guyana, South America. In Proceedings of the GeoSupport Conference 2004, Orlando, FL, USA, 29–31 December 2004; pp. 700–711. [Google Scholar]
- Ma, L.; Wang, J. Technology of Pile Foundation Underpinning in Shield Tunnel of Xi’an Subway. Appl. Mech. Mater. 2012, 204–208, 1445–1448. [Google Scholar] [CrossRef]
- Yao, A.; Yang, X.; Dong, L. Numerical Analysis of the Influence of Isolation Piles in Metro Tunnel Construction of Adjacent Buildings. Procedia Earth Planet. Sci. 2012, 5, 150–154. [Google Scholar] [CrossRef] [Green Version]
- Park, Y.-H.; Kim, J.-P.; Cho, K.-H. Stability analysis of subway box structure supported by modified underpinning method. Tunn. Undergr. Space Technol. 2015, 50, 199–208. [Google Scholar] [CrossRef]
- Wang, F.; Yuan, D.; Cai, R.; Mu, Y.; Wang, M. Field Test Study on Cutting Obstacle Piles Directly by Shield Cutters. Appl. Mech. Mater. 2013, 353–356, 1433–1439. [Google Scholar] [CrossRef]
- Peng, F.; Ma, S.; Li, M.; Fu, K. Stress Performance Evaluation of Shield Machine Cutter Head during Cutting Piles under Masonry Structures. Adv. Civ. Eng. 2022, 2022, 4111637. [Google Scholar] [CrossRef]
- Fu, D.-M. Model Test on Concrete Cutting Directly by Shield and Pile Foundation Cutting Technology. Tunn. Constr. 2014, 34, 472–477. [Google Scholar]
- Chen, H.-F.; Yuan, D.-J.; Wang, F.; Wang, M.-S. Study on shield cutting parameters when cutting big diameter piles. China Civ. Eng. J. 2016, 49, 103–109. (In Chinese) [Google Scholar]
- Yuan, D.-J.; Wang, F.; Dong, C.-W.; Han, B.; Wang, M.-S. Study on New-style Cutter for Shield Cutting Large-diameter Reinforced Concrete Pile. China J. Highw. Transp. 2016, 29, 89–97. [Google Scholar]
- Institute CHPaD. General Code for Design of Highway Bridges and Culverts; People’s Transpotation Press; China Communications Press: Beijing, China, 2015. [Google Scholar]
Line | Classification of Surrounding Rock | Surrounding Rock Classification | Stratum Passed by Tunnel | ||
---|---|---|---|---|---|
Tunnel Top | Tunnel Wall | Tunnel Bottom | |||
Left line | VI | VI~IV | IV | IV | Cave top: <2-1>, <2-2>, <2-3>, <2-4>, <2-5>, <2-6>, <2-7> Cave wall: <2-4>, <2-6>, <2-7> Cave bottom: <2-4>, <2-6>, <2-7>, <5-1-1>, <5-1-2> |
Right line | VI | VI~IV | IV | IV | Cave top: <2-1>, <2-2>, <2-3>, <2-4>, <2-5>, <2-6>, <2-7> Cave walll: <2-4>, <2-6>, <2-7> Cave bottom: <2-4>, <2-6>, <2-7>, <5-1-1>, <5-1-2> |
Material Type | Density (ρ) /kg/m3 | Young’s Modulus (E)/MPa | Poisson’s Ratio (ν) | Friction Angle (φ)/° | Cohesion (c)/kPa | Thickness (h)/m |
---|---|---|---|---|---|---|
Miscellaneous fill | 1780 | 7 | 0.32 | 10 | 5 | 4 |
Silty clay | 1870 | 8 | 0.34 | 15 | 25 | 3.4 |
Coarse sand | 1900 | 20 | 0.32 | 29 | 0 | 3.9 |
Pebble | 2000 | 30 | 0.33 | 30 | 0 | 7 |
Strongly weathered argillaceous siltstone | 2100 | 140 | 0.32 | 28 | 38 | 3.7 |
Moderately weathered argillaceous siltstone | 2450 | 4 × 103 | 0.3 | 38 | 1000 | 28 |
Concrete (underpinning beam, platform, piles) | 2400 | 3 × 104 | 0.23 | — | — | — |
No. | Monitoring Variables | Monitoring Instruments | Precision | Alarming Value | Controlling Value |
---|---|---|---|---|---|
1 | Pier displacement | Hydrostatic level | 0.1 mm | 2.0 mm | 3.0 mm |
2 | Pier inclination | Inclinometer | 0.001° | 0.06° | 0.12° |
3 | New pile displacement | Hydrostatic level | 0.1 mm | 3.5 mm | 5 mm |
4 | Underpinning displacement | Hydrostatic level | 0.1 mm | 3.5 mm | 5 mm |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2023 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Zheng, F.; Jiang, Y.; Wang, N.; Geng, D.; Xu, C. Investigation on the Influence of Active Underpinning Process on Bridge Substructures during Shield Tunnelling: Numerical Simulation and Field Monitoring. Buildings 2023, 13, 241. https://doi.org/10.3390/buildings13010241
Zheng F, Jiang Y, Wang N, Geng D, Xu C. Investigation on the Influence of Active Underpinning Process on Bridge Substructures during Shield Tunnelling: Numerical Simulation and Field Monitoring. Buildings. 2023; 13(1):241. https://doi.org/10.3390/buildings13010241
Chicago/Turabian StyleZheng, Fengqu, Yalong Jiang, Ning Wang, Daxin Geng, and Changjie Xu. 2023. "Investigation on the Influence of Active Underpinning Process on Bridge Substructures during Shield Tunnelling: Numerical Simulation and Field Monitoring" Buildings 13, no. 1: 241. https://doi.org/10.3390/buildings13010241
APA StyleZheng, F., Jiang, Y., Wang, N., Geng, D., & Xu, C. (2023). Investigation on the Influence of Active Underpinning Process on Bridge Substructures during Shield Tunnelling: Numerical Simulation and Field Monitoring. Buildings, 13(1), 241. https://doi.org/10.3390/buildings13010241