Risk Assessment in Sustainable Infrastructure Development Projects: A Tool for Mitigating Cost Overruns
Abstract
:1. Introduction
2. Literature Review
3. Materials and Methods
3.1. The Case Study
3.2. The Method: Measuring Risks
- Phase I: identify a list of items/events that can generate unexpected events during construction;
- Phase II: develop a description to illustrate each risk;
- Phase III: establish a risk matrix by associating both a qualitative probability of occurrence of each event (quite impossible, unlikely, likely, very likely, almost certain) and the estimation of cost overruns in case of occurrence. The assessment of cost overruns is calculated as percentage increases on the base cost for each event and classified as light, mediocre, severe, and critical;
- Phase IV: describe the identified mitigation measures and the assessment of residual risks after prevention;
- Phase V: perform a risk value assessment applying the cost levels of increase.
- Quite impossible (A): [0%,1%]
- Unlikely (B): [1%,25%]
- Likely (C): [25%,50%]
- Very likely (D): [50%,75%]
- Almost certain (E): [75%,100%]
- Light (1), which implies an increase in costs of [0%,5%]
- Mediocre (2), which implies an increase in costs of [5%,10%]
- Severe (3), which implies an increase in costs of [10%,20%]
- Critical (4), which implies an increase in costs of [20%,∞]
- Risk Category;
- Risk Type;
- Risk Code;
- Risk Description, which includes the description of the risk associated with the examined SSv-51 project. This column also describes the reasons that led to the estimations in columns 5 and 6;
- Probability of risk occurrence, which defines the selected probability of occurrence as defined above (quite impossible, unlikely, likely, very likely, and almost certain),
- Impacts on Costs, which defines the expected quantification of costs to be accounted for if that risk will occur, as defined above (light, mediocre, severe, and critical);
- Matrix combination is derived from the compilation of the matrix presented in Table 2 as a combination of columns 5 and 6;
- Risk mitigation tools, which indicate the risk mitigation measures proposed for the analyzed infrastructure project.
4. Results and Discussion
- (a)
- None, with an Increase in Value (IVa) = 0.0%
- (b)
- Slight, with an Increase in Value (IVb): [0%,5%]
- (c)
- Moderate, with an Increase in Value (IVc): [5%,10%]
- (d)
- Significant, with an Increase in Value (IVd): [10%,20%]
- (e)
- Grave, with an Increase in Value (IVe): [20%,∞]
- -
- Increase Level (i) is defined above;
- -
- Increase in Value (IVi) represents the deviation class, which falls within a defined percentage range that defines its increment on estimated costs. These intervals have been described above, and, in this table, we associated to each level a specific percentage increase, which corresponded to the arithmetic average of the interval. However, for the IVe, since there is no higher limit (+∞), we decided to apply a 50% increase to estimated costs. This percentage is considered quite critical in the literature, as the 20–40% range is deemed the maximum threshold of acceptability for valuation accuracy [26,52,53]. Therefore, we have chosen a slightly higher percentage to highlight the critical nature of this Level of Increase.
- -
- Increased Costs (ICi): in this column, the base value amplified with the associated percentage (IVi) for each corresponding increment type (i) has been calculated, where ICa is the Estimated Base Cost in 2017 (CC2017) for that specific Cost Item as reported in Table 5.
- -
- Cost Impact (CIi) was calculated by subtracting from the Increased Cost (CIi) the Increased Cost associated to the previous Increase Level (CIi−1). In the Increase Levela, IVa is equal to 0.0% and the corresponding CIa is equal to 0.
- -
- Probability (Pi) represents the probability of occurrence associated with each type of Increase Level for each risk. This probability has been estimated considering the matrix reported in Table A2.
- -
- Risk Value (RVi) is calculated by multiplying the Cost Impact (CIi) of each Increased Level by its corresponding Probability (Pi). The sum of the RVi values corresponds to the Estimated Risk Value for each single risk, which has been analyzed.
5. Conclusions
Author Contributions
Funding
Data Availability Statement
Acknowledgments
Conflicts of Interest
Appendix A
Risk Type | Probability of Risk Occurrence (Percentage or Qualitative Values) | Impact: Higher Costs and/or Delays (Percentage or Quantitative Values in € or Days) | Risk Mitigation Tools |
---|---|---|---|
Planning/Design Risk | |||
Discrepancy Risk | |||
Risk of increase in production costs | |||
Risk of inaccurate assessment of construction costs and project timelines | |||
The risk of suppliers and subcontractors failing to meet their contractual obligations | |||
Risk of unreliability and inadequacy of the used technology | |||
Commissioning risk | |||
Administrative risk | |||
Eminent domain risk | |||
Environmental and/or archaeological risk | |||
Risk of interference | |||
Risk of extraordinary maintenance | |||
Performance risk | |||
Risk of unavailability | |||
Risk of technical obsolescence | |||
Risk of contraction in market demand | |||
Risk of contraction in specific demand | |||
Planning-regulatory risk | |||
Financial risk | |||
Risk of insolvency | |||
Residual value risk |
Risk Category | Risk Type | Risk Code | Description | Probability of Risk Occurrence * | Impact: Costs Overrun ** | Matrix Combination | Risk Mitigation Tools |
---|---|---|---|---|---|---|---|
Construction Risks | Planning/Design Risk | RC1 | The level of design currently reached (2019) is developed on the basis of the final project that had already been improved in terms of its integration into the territory, as suggested by the Superintendence for Architectural and Landscape Heritage in 2005. | B | 1 | Acquire opinions, authorizations, approvals. Attach further explanatory tables to the project even if they are not mandatory. | |
Discrepancy Risk | RC2 | The current design level is feasible for construction, following numerous investigations and studies, so the risk of discrepancies is minimal. | B | 1 | Perform a precise and accurate design analysis. | ||
Risk of increase in production costs | RC3 | This risk is exacerbated for the project by two factors: the increase in construction material prices that occurred during the pandemic and post-pandemic period, and the extended timelines that occurred between project delivery and the start of construction. | B | 2 | Prepare the project based on the updated regional price list. In the case of an integrated contract, verify in advance with suppliers the updated price lists and the availability of materials in the market. Pay particular attention to the easy availability of construction materials. | ||
Risk of inaccurate assessment of construction costs and project timelines | RC4 | This level of design specifies the construction costs in the estimate and defines the detailed schedule of work. For large projects, it must be considered that the design is very complex, and often, as in the case of tunnel construction, it is not possible to rely on precise outcomes of conducted investigations. This entails the risk of encountering unforeseen circumstances that affect the overall cost. | C | 4 | Consult updated regional price lists. Seek opinions, authorizations, approvals in order to avoid extending the project schedule due to administrative procedures. Include thorough soil knowledge analyses and conduct them at multiple points. Additionally, gather information from historical data and works of the same category carried out in nearby areas. | ||
The risk of suppliers and subcontractors failing to meet their contractual obligations | RC5 | The contract in question is an integrated contract, and the winning company is responsible for drafting the executive project and carrying out the construction work, with the aim of minimizing the risk of non-compliance. | A | 1 | Select subcontractors carefully by verifying in advance their compliance with requirements, including Chamber of Commerce records and ANAC files, to assess if there are any past contract resolutions. Request the subcontractor to provide a surety bond. Clearly define the contractual obligations and include penalties for non-compliance with these obligations. | ||
Risk of unreliability and inadequacy of the used technology | RC6 | The project presented has undergone several changes over the years, taking into account that technological design solutions have evolved, and as a result, the project has been adapted accordingly. | A | 1 | Implement parallel control and safety systems to allow, in the event of a component failure, the other systems to function. Stay updated on the latest technologies in use. | ||
Commissioning risk | RC7 | The project has been the subject of numerous investigations and protests from the local community regarding issues related to expropriations, potential environmental impact, and the proposed project route. | D | 2 | Evaluate possible design alternatives in advance, estimating their associated costs and environmental impact. Prepare administrative documents related to expropriations with great care and involve the community through meetings and roundtable discussions to share project details. | ||
Administrative risk | RC8 | This risk is associated with the duration of the administrative procedures. | D | 2 | Obtain opinions, authorizations, and approvals in advance. Attach to the project all additional documents that may be necessary to demonstrate a comprehensive assessment of the context and the relative compatibility of the work, even if not mandatory. | ||
Eminent domain risk | RC9 | This risk can result in both delays and costs increase. | E | 2 | Evaluate design alternatives that minimize the need for expropriation and, if possible, prioritize expropriations that do not involve the demolition of buildings. Prepare administrative documents related to expropriations with great care to ensure there are no loopholes that expropriated individuals could use to claim a higher compensation while also prolonging the expropriation and administrative timelines. | ||
Construction Risks | Environmental and/or archaeological risk | RC10 | The project is located in the vicinity of the ecclesiastical district of St. Andrew, already known for archaeological findings dating back to the 6th century. | E | 1 | Include comprehensive soil knowledge analyses and conduct them at multiple points. Additionally, gather information from historical data and works of the same category carried out in nearby areas. Preemptively verify archaeological interest. Plan archaeological investigations before project implementation and allocate resources for archaeological support during the works. | |
Risk of interference | RC11 | This type of risk is mainly associated with the presence of above and below-ground utilities of various types (e.g., water, gas, fiber optics, etc.). In the absence of updated plans, it is possible that during excavation, pipes may be inadvertently damaged or cables may be cut. | D | 3 | Retrieve updated plans of the underground services, possibly in dwg extension. Make use of BIM design systems. | ||
Performance Risks | Risk of extraordinary maintenance | RP1 | This level of design requires, among the documents, the drafting of the Maintenance Plan for the work, whose purpose is to plan and schedule maintenance activities in order to "sustain over time the functionality, quality characteristics, efficiency, and economic value" (Article 38 D.P.R. 207/2010). | A | 2 | Prepare the Maintenance Plan of the Work accurately. | |
Performance risk | RP2 | The road design was based on traffic volumes obtained from the previous detailed project in 2004 by projecting municipal traffic data to 2010. It is realistic to assume that these traffic volumes are likely to increase over the years, further reinforcing the reasons that led to the request for this project, making it increasingly important in addressing the traffic issue in the historical center. | A | 1 | Accurate identification of traffic volumes. | ||
Risk of technical obsolescence | RP4 | This project, which is realized after numerous design phases, must take into account that over the years, technological design solutions have certainly changed, and therefore the project needs to be adapted. | A | 1 | Anticipate a design level updated to technical and technological evolution. | ||
Demand Risks | Risk of contraction in market demand | RD1 | This project has undergone numerous studies on vehicular traffic with the aim of freeing the historical center from car traffic in order to preserve its characteristics, bringing a significant impact to the area. | B | 1 | Draft the project based on updated studies on vehicular traffic. | |
Other Risks | Planning-regulatory risk | RO1 | The project has an extensive development timeline that has witnessed changes in regional price lists (regional price lists from 2006 to the present are available on the Veneto Region’s website). | C | 3 | Allocate adequate amounts available to the contracting authority under the ‘unforeseen‘ item, update the project to the current regional price list. Include, where possible and in compliance with current regulations, appropriate contractual clauses regarding price revisions. | |
Residual value risk | RO4 | The road and infrastructure design was based on traffic volumes derived from the previous 2004 detailed project by projecting municipal traffic data to 2010. It is realistic to assume that these traffic volumes are likely to increase over the years, further reinforcing the reasons that led to the request for this project, making it increasingly important in addressing the traffic issue in the historical center. | A | 1 | To plan for a design level updated to technological and technical evolution. |
References
- CPT Settori. Agenzia per la Coesione Territoriale, Sistema dei Conti Pubblici Territoriali e Produzione di Statistiche, Indagini e Ricerche Sulla Conduzione Delle Politiche Pubbliche. 2023. Available online: https://www.agenziacoesione.gov.it/wp-content/uploads/2023/04/2-Spesa_CPT_Settori_Vol2_TRASPORTI-1.pdf (accessed on 23 November 2023).
- European Commission. Mobility and Transport Transport in the European Union Current Trends and Issues; European Commission: Brussels, Belgium, 2019; p. 144. [Google Scholar]
- Avotos, I. Cost-relevance analysis for overrun control. Int. J. Proj. Manag. 1983, 1, 142–148. [Google Scholar] [CrossRef]
- Flyvbjerg, B.; Ansar, A.; Budzier, A.; Buhl, S.; Cantarelli, C.; Garbuio, M.; Glenting, C.; Holm, M.S.; Lovallo, D.; Lunn, D. Five things you should know about cost overrun. Transp. Res. Part A Policy Pract. 2018, 118, 174–190. [Google Scholar] [CrossRef]
- Pehlivan, S.; Öztemir, A.E. Integrated Risk of Progress-Based Costs and Schedule Delays in Construction Projects. Eng. Manag. J. 2018, 30, 108–116. [Google Scholar] [CrossRef]
- Love, P.E.D.; Ahiaga-Dagbui, D.D.; Irani, Z. Cost overruns in transportation infrastructure projects: Sowing the seeds for a probabilistic theory of causation. Transp. Res. Part A Policy Pract. 2016, 92, 184–194. [Google Scholar] [CrossRef]
- Fan, C.F.; Yu, Y.C. BBN-based software project risk management. J. Syst. Softw. 2004, 73, 193–203. [Google Scholar] [CrossRef]
- Kardes, I.; Ozturk, A.; Cavusgil, S.T.; Cavusgil, E. Managing global megaprojects: Complexity and risk management. Int. Bus. Rev. 2013, 22, 905–917. [Google Scholar] [CrossRef]
- Valipour, A.; Yahaya, N.; Md Noor, N.; Kildienė, S.; Sarvari, H.; Mardani, A. A fuzzy analytic network process method for risk prioritization in freeway PPP projects: An Iranian case study. J. Civ. Eng. Manag. 2015, 21, 933–947. [Google Scholar] [CrossRef]
- Canesi, R. Urban Policy Sustainability through a Value-Added Densification Tool: The Case of the South Boston Area. Sustainability 2022, 14, 8762. [Google Scholar] [CrossRef]
- Anelli, D.; Tajani, F. Spatial decision support systems for effective ex-ante risk evaluation: An innovative model for improving the real estate redevelopment processes. Land Use Policy 2023, 128, 106595. [Google Scholar] [CrossRef]
- Hillson, D. Managing Risk in Projects; Routledge: London, UK, 2009. [Google Scholar]
- Floyd, M.K.; Barker, K.; Rocco, C.M.; Whitman, M.G. A Multi-Criteria Decision Analysis Technique for Stochastic Task Criticality in Project Management. Eng. Manag. J. 2017, 29, 165–178. [Google Scholar] [CrossRef]
- Qazi, A.; Quigley, J.; Dickson, A.; Kirytopoulos, K. Project Complexity and Risk Management (ProCRiM): Towards modelling project complexity driven risk paths in construction projects. Int. J. Proj. Manag. 2016, 34, 1183–1198. [Google Scholar] [CrossRef]
- Fang, C.; Marle, F. Dealing with project complexity by matrix-based propagation modelling for project risk analysis. J. Eng. Des. 2013, 24, 239–256. [Google Scholar] [CrossRef]
- Demirkesen, S.; Ozorhon, B. Measuring Project Management Performance: Case of Construction Industry. Eng. Manag. J. 2017, 29, 258–277. [Google Scholar] [CrossRef]
- Renigier-Biłozor, M.; Źróbek, S.; Walacik, M.; Borst, R.; Grover, R.; D’Amato, M. International acceptance of automated modern tools use must-have for sustainable real estate market development. Land Use Policy 2022, 113, 105876. [Google Scholar] [CrossRef]
- Canesi, R. A multicriteria approach to prioritize urban sustainable development projects|Un approccio multicriteri per il ranking di progetti urbani sostenibili. Valori E Valutazioni 2023, 2023, 117–132. [Google Scholar] [CrossRef]
- Afzal, F.; Yunfei, S.; Nazir, M.; Bhatti, S.M. A review of artificial intelligence based risk assessment methods for capturing complexity-risk interdependencies: Cost overrun in construction projects. Int. J. Manag. Proj. Bus. 2021, 14, 300–328. [Google Scholar] [CrossRef]
- Islam, M.S.; Nepal, M.P.; Skitmore, M.; Attarzadeh, M. Current research trends and application areas of fuzzy and hybrid methods to the risk assessment of construction projects. Adv. Eng. Inform. 2017, 33, 112–131. [Google Scholar] [CrossRef]
- Zhang, L.; Huang, Y.; Wu, X.; Skibniewski, M.J. Risk-based estimate for operational safety in complex projects under uncertainty. Appl. Soft Comput. J. 2017, 54, 108–120. [Google Scholar] [CrossRef]
- Cárdenas, I.C.; Al-Jibouri, S.S.H.; Halman, J.I.M.; Van Tol, F.A. Modeling risk-related knowledge in tunneling projects. Risk Anal. 2014, 34, 323–339. [Google Scholar] [CrossRef]
- Gabrielli, L.; Ruggeri, A.G.; Scarpa, M. Detecting information transparency in the Italian real estate market: A machine learning approach|Identificare la trasparenza informativa nel mercato immobiliare italiano: Un approccio machine learning. Valori E Valutazioni 2022, 2022, 33–48. [Google Scholar] [CrossRef]
- D’Alpaos, C.; Moretto, M.; Rosato, P. Common-Property Resource Exploitation: A Real Options Approach. Land 2023, 12, 1304. [Google Scholar] [CrossRef]
- Russo, F.; Maselli, G.; Vietri, M.; Nesticò, A. Urban Slum Upgrading: A Model for Expeditious Estimation of the Cost of Interventions. In Computational Science and Its Applications—ICCSA 2023 Workshops; Springer: Berlin/Heidelberg, Germany, 2023. [Google Scholar]
- Hager, D.P.; Lord, D.J. The property market, property valuations and property performance measurement. J. Inst. Actuar. 1985, 112, 19–60. [Google Scholar] [CrossRef]
- Flyvbjerg, B.; Holm, M.S.; Buhl, S. Underestimating Costs in Public Works Projects: Error or Lie? J. Am. Plan. Assoc. 2002, 68, 279–295. [Google Scholar] [CrossRef]
- Flyvbjerg, B.; Skamris holm, M.K.; Buhl, S.L. What Causes Cost Overrun in Transport Infrastructure Projects? Transp. Rev. 2004, 24, 3–18. [Google Scholar] [CrossRef]
- Park, Y.I.; Papadopoulou, T.C. Causes of cost overruns in transport infrastructure projects in Asia: Their significance and relationship with project size. Built Environ. Proj. Asset Manag. 2012, 2, 195–216. [Google Scholar] [CrossRef]
- Paris, S.; Tajani, F.; Pennacchia, E.; Ranieri, R.; Di Liddo, F. A Methodological Approach for the Assessment of Parametric Costs of Sustainable Urban Roads: An Application to the City of Rome (Italy). In Computational Science and Its Applications—ICCSA 2023 Workshops; Springer: Berlin/Heidelberg, Germany, 2023. [Google Scholar]
- Antoniucci, V.; Marella, G. Public works in north-east italy: An efficiency and risk allocation analysis. In Appraisal and Valuation; Springer: Berlin/Heidelberg, Germany, 2021. [Google Scholar]
- Asiedu, R.O.; Adaku, E. Cost overruns of public sector construction projects: A developing country perspective. Int. J. Manag. Proj. Bus. 2020, 13, 66–84. [Google Scholar] [CrossRef]
- Ghazal, M.M.; Hammad, A. Application of knowledge discovery in database (KDD) techniques in cost overrun of construction projects. Int. J. Constr. Manag. 2022, 22, 1632–1646. [Google Scholar] [CrossRef]
- Shoar, S.; Yiu, T.W.; Payan, S.; Parchamijalal, M. Modeling cost overrun in building construction projects using the interpretive structural modeling approach: A developing country perspective. Eng. Constr. Archit. Manag. 2023, 30, 365–392. [Google Scholar] [CrossRef]
- Jennings, W. Why costs overrun: Risk, optimism and uncertainty in budgeting for the London 2012 Olympic Games. Constr. Manag. Econ. 2012, 30, 455–462. [Google Scholar] [CrossRef]
- Flyvbjerg, B. Survival of the unfittest: Why the worst infrastructure gets built—And what we can do about it. Oxf. Rev. Econ. Policy 2009, 25, 344–367. [Google Scholar] [CrossRef]
- Dominic, A.D.D.; Smith, S.D. Rethinking construction cost overruns: Cognition, learning and estimation. J. Financ. Manag. Prop. Constr. 2014, 19, 38–54. [Google Scholar] [CrossRef]
- Skitmore, R.M.; Ng, S.T. Forecast models for actual construction time and cost. Build. Environ. 2003, 38, 1075–1083. [Google Scholar] [CrossRef]
- Ökmen, Ö.; Öztaş, A. Construction cost analysis under uncertainty with correlated cost risk analysis model. Constr. Manag. Econ. 2010, 28, 203–212. [Google Scholar] [CrossRef]
- Love, P.E.D.; Edwards, D.J.; Irani, Z. Moving beyond optimism bias and strategic misrepresentation: An explanation for social infrastructure project cost overruns. IEEE Trans. Eng. Manag. 2012, 59, 560–571. [Google Scholar] [CrossRef]
- Subramani, T. Causes of Cost Overrun In Construction. IOSR J. Eng. 2014, 4, 01–07. [Google Scholar] [CrossRef]
- Flyvbjerg, B. Over Budget, Over Time, Over and Over Again: Managing Major Projects. In The Oxford Handbook of Project Management; Oxford Academic: Oxford, UK, 2011; pp. 321–344. [Google Scholar] [CrossRef]
- Cantarelli, C.C.; Flybjerg, B.; Molin, E.J.E.; van Wee, B. Cost Overruns in Large-Scale Transport Infrastructure Projects. Autom. Constr. 2018, 2, 19. [Google Scholar]
- Al-Hazim, N.; Salem, Z.A.; Ahmad, H. Delay and Cost Overrun in Infrastructure Projects in Jordan. Procedia Eng. 2017, 182, 18–24. [Google Scholar] [CrossRef]
- Herrera, R.F.; Sánchez, O.; Castañeda, K.; Porras, H. Cost overrun causative factors in road infrastructure projects: A frequency and importance analysis. Appl. Sci. 2020, 10, 5506. [Google Scholar] [CrossRef]
- Flyvbjerg, B.; Skamris holm, M.K.; Buhl, S.L. How common and how large are cost overruns in transport infrastructure projects? Transp. Rev. 2003, 23, 71–88. [Google Scholar] [CrossRef]
- Cantarelli, C.C.; van Wee, B.; Molin, E.J.E.; Flyvbjerg, B. Different cost performance: Different determinants? The case of cost overruns in Dutch transport infrastructure projects. Transp. Policy 2012, 22, 88–95. [Google Scholar] [CrossRef]
- Mišić, S.; Radujković, M. Critical Drivers of Megaprojects Success and Failure. Procedia Eng. 2015, 122, 71–80. [Google Scholar] [CrossRef]
- Nabawy, M.; Khodeir, L.M. A systematic review of quantitative risk analysis in construction of mega projects. Ain Shams Eng. J. 2020, 11, 1403–1410. [Google Scholar] [CrossRef]
- ANAC. Linee Guida n. 9. Attuazione del DL 18 aprile 2016, n. 50. In Monitoraggio delle Amministrazioni Aggiudicatrici Sull’attività Dell’operatore Economico nei Contratti di Partenariato Pubblico Privato; Autorità Nazionale Anticorruzione: Roma, Italy, 2018. [Google Scholar]
- MIMS. Linee Guida per la Valutazione Degli Investimenti; Ministero delle Infrastrutture e della Mobilità Sostenibile: Roma, Italy, 2022.
- Crosby, N. Valuation accuracy, variation and bias in the context of standards and expectations. J. Prop. Investig. Financ. 2000, 18, 130–161. [Google Scholar] [CrossRef]
- Morano, P. Sul grado di approssimazione delle stime. Genio Rural. 2002, 10, 11–25. [Google Scholar]
Risk Category | Risk Type | Risk Code |
---|---|---|
Construction Risks (RC) | Planning/Design Risk | RC1 |
Discrepancy Risk | RC2 | |
Risk of increase in production costs | RC3 | |
Risk of inaccurate assessment of construction costs and project timelines | RC4 | |
The risk of suppliers and subcontractors failing to meet their contractual obligations | RC5 | |
Risk of unreliability and inadequacy of the used technology | RC6 | |
Commissioning risk | RC7 | |
Administrative risk | RC8 | |
Eminent domain risk | RC9 | |
Environmental and/or archaeological risk | RC10 | |
Risk of interference | RC11 | |
Performance Risks (RP) | Risk of extraordinary maintenance | RP1 |
Performance risk | RP2 | |
Risk of unavailability | RP3 | |
Risk of technical obsolescence | RP4 | |
Demand Risks (RD) | Risk of contraction in market demand | RD1 |
Risk of contraction in specific demand | RD2 | |
Other Risks (RO) | Planning-regulatory risk | RO1 |
Financial risk | RO2 | |
Risk of insolvency | RO3 | |
Residual value risk | RO4 |
Impact on Costs | |||||||
Light | Mediocre | Severe | Critical | ||||
1 | 2 | 3 | 4 | ||||
[0%,5%] | [5%,10%] | [10%,20%] | [20%,∞] | ||||
Probability | Quite impossible | (A) | [0%,1%] | ||||
Unlikely | (B) | [1%,25%] | |||||
Likely | (C) | [25%,50%] | |||||
Very likely | (D) | [50%,75%] | |||||
Almost certain | (E) | [75%,100%] | |||||
Risk | Action | ||||||
MINIMUM | EVALUATE IMPROVEMENT ACTIONS | ||||||
LOW | PLAN CORRECTIVE ACTIONS IN THE MEDIUM-SHORT TERM | ||||||
MEDIUM | URGENTLY SCHEDULE CORRECTIVE ACTIONS | ||||||
HIGH | IMPLEMENT IMMEDIATE CORRECTIVE ACTIONS |
Risk Category | Risck Code | Probability of Risk Occurrence (Quite Impossible-A, Unlikely-B, Likely-C, Very Likely-D, and Almost Certain-E) | Impact: Costs Overrun (Light-1, Mediocre-2, Severe-3, and Critical-4) | Matrix Combination |
---|---|---|---|---|
Construction Risks | RC1 | B | 1 | |
RC2 | B | 1 | ||
RC3 | B | 2 | ||
RC4 | C | 4 | ||
RC5 | A | 1 | ||
RC6 | A | 1 | ||
RC7 | D | 2 | ||
RC8 | D | 2 | ||
RC9 | E | 2 | ||
RC10 | E | 1 | ||
RC11 | D | 3 | ||
Performance Risks | RP1 | A | 2 | |
RP2 | A | 1 | ||
RP4 | A | 1 | ||
Demand Risks | RD1 | B | 1 | |
Other Risks | RO1 | C | 3 | |
RO4 | A | 1 |
Increase Level (i) | Increase in Value (IVi) | Increased Cost (ICi) | Cost Impact (CIi) | Probability (Pi) | Risk Value (RVi) = (CIi) × (Pi) |
---|---|---|---|---|---|
a | IVa = 0.0% | ICa | 0 | Pa | RVa |
b | IVb = 2.5% | ICb = ICa × (1 + IVb) | ICb − ICa | Pb | RVb |
c | IVc = 8.0% | ICc = ICa × (1 + IVc) | ICc − ICb | Pc | RVc |
d | IVd = 15.5% | ICd = ICa × (1 + IVd) | ICd − ICc | Pd | RVd |
e | IVe = 50.0% | ICe = ICa × (1 + IVe) | ICe − ICd | Pe | RVe |
Cost Code | Cost Item | Estimated Costs in 2017 | Actual Costs in 2019 | Cost Difference (€) | Delta 2019–2017 (%) |
---|---|---|---|---|---|
CC(2017) | CC(2019) | CD = CC(2019) − CC(2017) | De = CD/CC(2017) | ||
CC1 | Construction Costs | 45,609,732 € | 43,482,988 € | −2,126,744 € | −4.66% |
CC2 | Construction Site Security | 2,420,342 € | 4,164,468 € | 1,744,126 € | 72.06% |
CC3 | Engineering Fees | 395,158 € | 878,737 € | 483,579 € | 122.38% |
CC4 | Surveys | 24,000 € | 24,000 € | - | 0.00% |
CC5 | Interferences | 210,000 € | 1,089,803 € | 879,803 € | 418.95% |
CC6 | Contingencies | 1,422,630 € | - | −1,422,630 € | −100.00% |
CC7 | Eminent Domain | 1,500,000 € | 5,415,645 € | 3,915,645 € | 261.04% |
CC8 | General Office Overhead | 183,179 € | 93,327 € | −89,852 € | −49.05% |
CC9 | Energy Efficiency | 223,453 € | 223,453 € | - | 0.00% |
CC10 | Taxes | 3664 € | - | −3664 € | −100.00% |
CC11 | Marketing | 32,000 € | 32,000 € | - | 0.00% |
CC12 | Testing and Inspections | 522,102 € | 522,102 € | - | 0.00% |
CC13 | Financial Costs | 8,478,189 € | 8,478,189 € | - | 0.00% |
TOTAL | 61,024,448 € | 64,404,711 € | 3,380,263 € | 5.54% | |
TOTAL (CC1 + CC2 + CC5 + CC7) | 49,740,074 € | 54,152,904 € | 4,412,830 € | 8.87% |
Increase Level (i) | Increase in Value (IVi) | Increased Cost (ICi) | Cost Impact (CIi) | Probability (Pi) | Estimated Risk Value (RVi) = (CIi) × (Pi) | Estimated Risk Value (%) (ERVi) = (RVi)/(ICa) | |
---|---|---|---|---|---|---|---|
RC9 (CC7) | a | 0.0% | 1,500,000 € | - | 1% | - | 0.00% |
b | 2.5% | 1,537,500 € | 37,500 € | 3% | 1125 € | 0.08% | |
c | 8.0% | 1,620,000 € | 82,500 € | 80% | 66,000 € | 4.40% | |
d | 15.5% | 1,732,500 € | 112,500 € | 9% | 10,125 € | 0.68% | |
e | 50.0% | 2,250,000 € | 517,500 € | 7% | 36,225 € | 2.42% | |
RC9 Risk Value | 113,475 € | 7.57% | |||||
RC11 (CC5) | a | 0.0% | 210,000 € | - | 10% | - | 0.00% |
b | 2.5% | 215,250 € | 5250 € | 20% | 1050 € | 0.07% | |
c | 8.0% | 226,800 € | 11,550 € | 51% | 5891 € | 0.39% | |
d | 15.5% | 242,550 € | 15,750 € | 11% | 1733 € | 0.12% | |
e | 50.0% | 315,000 € | 72,450 € | 8% | 5796 € | 0.39% | |
RC11 Risk Value | 14,469 € | 6.89% | |||||
RC4 (CC1 + CC2) | a | 0.0% | 48,030,074 € | - | 10% | - | 0.00% |
b | 2.5% | 49,230,826 € | 1,200,752 € | 30% | 360,226 € | 24.02% | |
c | 8.0% | 51,872,480 € | 2,641,654 € | 25% | 660,414 € | 44.03% | |
d | 15.5% | 55,474,735 € | 3,602,256 € | 25% | 900,564 € | 60.04% | |
e | 50.0% | 72,045,111 € | 16,570,375 € | 10% | 1,657,038 € | 110.47% | |
RC4 Risk Value | 3,578,240 € | 7.45% | |||||
Total Risk Value | 3,706,184 € | 7.45% |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2023 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Canesi, R.; Gallo, B. Risk Assessment in Sustainable Infrastructure Development Projects: A Tool for Mitigating Cost Overruns. Land 2024, 13, 41. https://doi.org/10.3390/land13010041
Canesi R, Gallo B. Risk Assessment in Sustainable Infrastructure Development Projects: A Tool for Mitigating Cost Overruns. Land. 2024; 13(1):41. https://doi.org/10.3390/land13010041
Chicago/Turabian StyleCanesi, Rubina, and Beatrice Gallo. 2024. "Risk Assessment in Sustainable Infrastructure Development Projects: A Tool for Mitigating Cost Overruns" Land 13, no. 1: 41. https://doi.org/10.3390/land13010041
APA StyleCanesi, R., & Gallo, B. (2024). Risk Assessment in Sustainable Infrastructure Development Projects: A Tool for Mitigating Cost Overruns. Land, 13(1), 41. https://doi.org/10.3390/land13010041