Optimization of Blasting Parameters Considering Both Vibration Reduction and Profile Control: A Case Study in a Mountain Hard Rock Tunnel
Abstract
:1. Introduction
2. Materials and Methods
2.1. Overview of the Tunnel Project
2.1.1. Tunnel Project Introduction
2.1.2. Original Tunnel Excavation Design
2.2. Blasting Vibration Monitoring
2.2.1. Vibration Monitoring Instruments
2.2.2. Monitoring Points Arrangement
2.2.3. Specific Monitoring Schemes
2.3. Tunnel Profile Measurement
2.4. Optimization of Tunnel Blasting
2.4.1. Optimization of Cutting Hole Area
2.4.2. Optimization of Delay Time Interval for Detonator
2.4.3. Optimization of Peripheral Hole Charge Structure
2.5. Fractal Evaluation Method of Tunnel Overbreak–Underbreak Based on Python Image Processing
2.5.1. Fractal Theory and Boxing-Counting Dimension
2.5.2. Visualization Algorithm of Overbreak–Underbreak Based on Python Image Processing
- Overbreak–underbreak Profile Curve Data Collection Module
- 2.
- Overbreak–Underbreak Profile Curve Data Visualization Module
- 3.
- Overbreak–underbreak Profile Curve Data Feature Analysis Module
3. Results and Discussion
3.1. Analysis of Blasting Vibration Data on Site
3.1.1. Analysis of Blasting Vibration Velocity Characteristics
- Target tunnel
- 2.
- Residential buildings
- 3.
- Adjacent tunnel
- 4.
- Mountain slopes
3.1.2. The Attenuation Law of Blasting Vibration Velocity in Different Areas
3.2. Analysis of Tunnel Overbreak–Underbreak Data
3.2.1. Brenner Base Tunnel (BBT) Case
3.2.2. A Short Mountain Tunnel in Southwest China Case Study
3.3. Analysis of Optimization Effect of Tunnel Blasting Scheme
3.3.1. Analysis of Vibration Reduction Effect at Adjacent Tunnel Measurement Points
3.3.2. Analysis of Smooth Blasting Effect of Tunnel
4. Conclusions
- According to on-site blasting vibration monitoring technology, the vibration response law of the tunnel different areas during the construction of the upper step blasting were studied. The blasting vibration velocity of the target tunnel, residential areas, and mountain slopes were analyzed. The vibration wave in the Z-axis vertical direction contributed the most to the vibration response of the target tunnel, residential areas, and mountain slopes. Meanwhile, the blasting vibration velocity was analyzed at the adjacent tunnel. The vibration wave in Z-axis horizontal radial direction contributed the most to the vibration response of the adjacent tunnel.
- By collecting and analyzing the blasting peak velocity data of different areas, the attenuation law of blasting vibration velocity in different areas of the target tunnel was revealed based on the Sadowski empirical formula. Sadowski’s empirical prediction formula for different areas were constructed, which provided a theoretical basis for vibration control of the tunnel’s right-line blasting construction.
- A visualization method for tunnel the overbreak–underbreak profile was developed based on Python image processing technology combined with fractal theory. The fractal dimension value can analyze and evaluate the degree of overbreak–underbreak of the tunnel profile after blasting, to a certain extent. Taking the BBT tunnel and target tunnel as case studies of overbreak–underbreak analysis, it provides a new method for overbreak–underbreak evaluation. The comparison between the calculated overbreak–underbreak values using this method and the on-site measured values shows an error range of 15%, which can be used to effectively and accurately evaluate the blasting effect of the tunnel profile. Moreover, the findings of this study are limited to the data used in the study. Every underground excavation is unique and should be evaluated regarding its very unique properties. However, the fractal evaluation approach in this study can be used in any tunnel excavation. So, once the fractal value of tunnel excavation profile for any tunnel is identified, it can be easily applied by the crew.
- Through on-site blasting experiments, the optimal design of a blasting scheme was carried out from the aspects of cutting hole form, detonator interval time, and the peripheral hole charge structure. The optimized design scheme can not only meet the requirements of tunnel blasting vibration control but also effectively control the problem of tunnel overbreak–underbreak.
Author Contributions
Funding
Institutional Review Board Statement
Informed Consent Statement
Data Availability Statement
Acknowledgments
Conflicts of Interest
References
- Kumar, P.; Mohammadi, H.; Chopra, R. A newly developed blasting cut in tunnels; application of “combined method” in small to medium-sized tunnels. Tunn. Undergr. Space Technol. 2023, 142, 105426. [Google Scholar] [CrossRef]
- Zuo, J.; Yang, R.; Xie, Q. Propagation Characteristics of Explosion Wave and Explosion Gas in Blast-Hole. Shock Vib. 2023, 2023, 5054971. [Google Scholar] [CrossRef]
- Xu, Y.; Tang, J.; Yu, Y. Dynamic responses and failure mechanisms of the existing tunnel under transient excavation unloading of an adjacent tunnel. J. Rock Mech. Geotech. Rock Eng. 2023, 15, 2930–2942. [Google Scholar] [CrossRef]
- Ren, K.; Jiang, A.N.; Guo, X.P.; Min, Q.H. Research on Optimization Design of Tunnel Blasting Scheme Adjacent to Buildings. Appl. Sci. 2023, 13, 1509. [Google Scholar] [CrossRef]
- Liu, Y.; Chen, J. Monitoring and Analysis of Blasting Vibration in Daxuanling Tunnel with Small Clear Space. Blasting 2008, 2, 92–94. [Google Scholar]
- Lin, C.; Chen, L.; Jiang, L. Research on blasting stability control technology of large-span highway tunnel with super-small clear spacing at highway expansion project. Chin. J. Rock Mech. Eng. 2010, 29, 1371–1378. [Google Scholar]
- Hu, Q.; Cui, W.; Gao, J.; Zhao, F.; Liang, Q. Blasting Excavation and Vibration Monitoring Design for Diversion Tunnel. Adv. Mat. Res. 2013, 639–640, 969–973. [Google Scholar] [CrossRef]
- Ling, T.; Cao, F.; Zhang, S. Blast vibration characteristics of transition segment of a branch tunnel. J. Vib. Shock 2018, 37, 43–50. [Google Scholar] [CrossRef]
- Cardu, M.; Coragliotto, D.; Oreste, P. Analysis of predictor equations for determining the blast-induced vibration in rock blasting. Int. J. Min. Sci. Technol. 2019, 29, 905–915. [Google Scholar] [CrossRef]
- Xia, X.; Li, H.; Li, J. A case study on rock damage prediction and control method for underground tunnels subjected to adjacent excavation blasting. Tunn. Undergr. Space Technol. 2013, 35, 1–7. [Google Scholar] [CrossRef]
- Dang, V.; Vo, T. Effect of Blasting During Tunnel Excavation on an Existing Adjacent Tunnel. Tek. Dergi 2022, 33, 12725–12740. [Google Scholar] [CrossRef]
- Xiao, P.; Li, B.; Ding, Q.; Yang, R.; Yang, X.; Qian, H.; Xu, N. Evaluation of blasting parameters for hydraulic tunnels based on multiple monitoring information. Geomat. Nat. Hazards Risk 2024, 15, 2311895. [Google Scholar] [CrossRef]
- Hong, Z.; Tao, M.; Liu, L. An intelligent approach for predicting overbreak in underground blasting operation based on an optimized XGBoost model. Eng. Appl. Artif. Intell. 2023, 126, 107097. [Google Scholar] [CrossRef]
- Satici, Ö. Drilling and Blasting as a Tunnel Excavation Method. 2000. Available online: https://www.researchgate.net/publication/285057196_Drilling_and_blasting_as_a_tunnel_excavation_method?channel=doi&linkId=565b86c708aefe619b243d4d&showFulltext=true (accessed on 1 January 2024).
- Singh, S. The effects of rock mass characteristics on blast hole deviation. CIM Bull. 1998, 91, 90–95. [Google Scholar]
- Satici, Ö.; Topal, T. Evaluation of Tunnel Excavation Methods in Accordance with Engineering Geology and Rock Mass Classification Systems. J. Geo Eng. 2015, 39. [Google Scholar]
- Zeng, Y.; Jiang, H.; Chen, P. Research on key technologies of tunnel blasting construction under poor geological conditions. Chin. Water Trans. 2018, 18, 205–207. [Google Scholar]
- Yin, W.; Wang, H.; Hu, H. Study of Tunnel Controlled Blasting Technology and Blast-induced Damage Zone of Surrounding Rocks. Tunn. Constr. 2018, 38, 851–856. [Google Scholar]
- Tran, T.-H.; Bui, T.; Dang, V. Assessment of blasted excavation inaccuracy at tunnel face and influences on tunnelling effectiveness. J. Mater. Eng. Struc. 2022, 9, 615–620. [Google Scholar]
- Hao, G.; Zhang, W.; Li, S. Research on the Shaping Effect of Horizontal Layered Rock Tunnel under Different Blasting Cyclical Footage. Chin. J. Undergr. Space Eng. 2020, 16, 316–322. [Google Scholar]
- Guo, J.; Li, B.; Liu, G. Study on control of backbreak and underbreak in tunnel excavation by drilling-and-blasting. Tunn. Constr. 2021, 27, 79–84. [Google Scholar] [CrossRef]
- Lv, R. Study on Blasting Forming Control Technology of Horizontal Sand Mudstone Tunnel. Tunn. Constr. 2021, 33, 156–160. [Google Scholar]
- Xie, H.; Gao, F.; Ju, Y. Research and Development of Rock Mechanics in Deep Ground Engineering. Chin. J. Rock Mech. Eng. 2015, 18, 2161–2178. [Google Scholar] [CrossRef]
- Wang, J.; Xie, H.; Kovasniewski, M. Measurement and description of rock fracture surface roughness using laser technology and fractal theory. Chin. J. Rock Mech. Eng. 1997, 4, 61–68. [Google Scholar] [CrossRef]
- Wei, J.; Wu, J.; Sun, S. Image processing on the evaluation of overbreak and underbreak in the tunnels. Hydrogeol. Eng. Geol. 2005, 32, 105–108. [Google Scholar] [CrossRef]
- Zhang, P.; Chen, J.; Zhao, A. Wavelet Analysis and Application for Fractal Dimention of Tunnel Surrounding Rock Outline. Hydrogeol. Eng. Geol. 2011, 19, 669–673. [Google Scholar] [CrossRef]
- Hong, Z.; Tao, M.; Zhao, R. Investigation on overbreak and underbreak of pre-stressed tunnels under the impact of decoupled charge blasting. Int. J. Impact Eng. 2023, 182, 104784. [Google Scholar] [CrossRef]
- Xu, R.; Zhang, J.; Wu, B. Vibration Reduction and Explosion Control Investigation for an Ultra-Shallow Buried Tunnel under Crossing Buildings Based on HHT Analysis. Sensors 2023, 23, 7589. [Google Scholar] [CrossRef] [PubMed]
- Shan, R.; Zhao, Y.; Wang, H. Blasting vibration response and safety control of mountain tunnel. Bull. Eng. Geol. Environ. 2023, 82, 166. [Google Scholar] [CrossRef]
- Lin, F.; Liu, R.; Zhang, Z. Reduction of Blasting Induced Ground Vibrations Using High-Precision Digital Electronic Detonators. Front. Earth Sci. 2022, 9, 804504. [Google Scholar] [CrossRef]
- Mei, J.; Zhang, W.; Xu, B. Optimization Methods of Blasting Parameters of Large Cross-Section Tunnel in Horizontal Layered Rock Mass. Geotech. Geol. Eng. 2021, 39, 5309–5323. [Google Scholar] [CrossRef]
- Xia, W.; Lu, W.; Wang, G. Safety threshold of blasting vibration velocity in foundation excavation of Baihetan super-high arch dam. Bull. Eng. Geol. Environ. 2020, 79, 4999–5012. [Google Scholar] [CrossRef]
- Song, K.; Oh, T.; Cho, G. Precutting of tunnel perimeter for reducing blasting-induced vibration and damaged zone—Numerical analysis. KSCE J. Civ. Eng. 2014, 18, 1165–1175. [Google Scholar] [CrossRef]
- Mohammadi, H.; Azad, A. Applying Rock Engineering Systems Approach for Prediction of Overbreak Produced in Tunnels Driven in Hard Rock. Geotech. Geol. Eng. 2020, 38, 2447–2463. [Google Scholar] [CrossRef]
- GB6722-2014; Safety Regulations for Blasting. Standardization Administration of China: Beijing, China, 2014.
- Fu, H.; Shen, Z.; Zhao, Y. Experimental study of decreasing vibration technology of tunnel blasting with digital detonator. Chin. J. Rock Mech. Eng. 2012, 31, 597–603. [Google Scholar]
- Qiu, X.; Shi, X.; Gou, Y. Short-delay blasting with single free surface: Results of experimental tests. Tunn. Undergr. Space Technol. 2018, 74, 119–130. [Google Scholar] [CrossRef]
- Li, P.; Lu, W.B.; Wu, X.X. Spectral prediction and control of blast vibrations during the excavation of high dam abutment slopes with millisecond-delay blasting. Soil Dyn. Earthq. Eng. 2017, 94, 116–124. [Google Scholar] [CrossRef]
- Koopialipoor, M.; Ghaleini, E.N.; Tootoonchi, H. Developing a new intelligent technique to predict overbreak in tunnels using an artificial bee colony-based ANN. Environ. Earth Sci. 2019, 78, 165. [Google Scholar] [CrossRef]
- Hu, Y.; Lu, W.; Zhang, L. Dynamic response and control of middle rock sidewall under impact of blast loading. J. Vib. Control 2019, 25, 1572–1584. [Google Scholar] [CrossRef]
- Mandelbrot, B.B. How Long Is the Coast of Britain? Statistical Self-Similarity and Fractional Dimension. Science 1967, 156, 636–638. [Google Scholar] [CrossRef]
- Mandelbrot, B.B. The Fractal Geometry of Nature. Am. J. Phys. 1998, 51, 286–287. [Google Scholar] [CrossRef]
- Wang, J.; Zeng, X.; Xu, C. Study on Quantitative Identification Method of Rock Fracture Based on Image Processing Technology. Chin. J. Rock Mech. Eng. 2022, 18, 446–457. [Google Scholar]
- Fodera, G.M.; Voza, A.; Barovero, G. Factors influencing overbreak volumes in drill-and-blast tunnel excavation. A statistical analysis applied to the case study of the Brenner Base Tunnel—BBT. Tunn. Undergr. Space Technol. 2020, 105, 103475. [Google Scholar] [CrossRef]
- Kim, Y.; Bruland, A. Analysis and Evaluation of Tunnel Contour Quality Index. Autom. Constr. 2019, 99, 223–237. [Google Scholar] [CrossRef]
- Chen, W.; Cai, X.; Chen, X. Core Image Segmentation Algorithm Based on HSV Space. China Powder Sci. Technol. 2013, 19, 1–6. [Google Scholar]
- Saidi, A.; Bouramtane, T.; Achab, M. The Hough transform algorithm coupled with spatial filtering for the study of geological structuring control on the drainage network: Application to the North Oulmes region, Morocco. Arab. J. Geosci. 2020, 13, 1026. [Google Scholar] [CrossRef]
- Wang, C.; Wang, B. Research on automatic identification method of cracks in asphalt concrete pavement. J. China For. Highway 2013, 33, 51–55. [Google Scholar] [CrossRef]
- Tian, X.; Song, Z.; Wang, J. Study on the propagation law of tunnel blasting vibration in stratum and blasting vibration reduction technology. Soil Dyn. Earthq. Eng. 2019, 126, 105813. [Google Scholar] [CrossRef]
- Doneva, N.; Despodov, Z.; Mirakovski, D.; Hadzi-Nikolova, M.; Mijalkovski, S. Reasons for difference between real and projected operating supplies for supporting during construction of ramps. Undergr. Min. Eng. 2016, 28, 1–7. [Google Scholar] [CrossRef]
- Mancini, R.; Badino, V.; Innaurato, N. Technical and economic aspects of tunnel blasting accuracy control. Tunn. Undergr. Space Technol. 1996, 11, 455–463. [Google Scholar] [CrossRef]
- Zhang, W.; Liu, D.; Tang, Y. Multifractal Characteristics of Smooth Blasting Overbreak in Extra-Long Hard Rock Tunnel. Fractal Fract. 2023, 7, 842. [Google Scholar] [CrossRef]
- Dambov, R.; Doneva, N.; Hadzi-Nikolova, M. Some methodological drilling: Blasting parameters in the excavation of tunnel. Undergr. Min. Eng. 2017, 2017, 17–30. [Google Scholar] [CrossRef]
- Satici, Ö.; Ünver, B. Assessment of tunnel portal stability at jointed rock mass: A comparative case study. Comput. Geotech. 2014, 64, 72–82. [Google Scholar] [CrossRef]
Blasthole Type | Blasthole Diameter | Blasthole Spacing | Amount | Blasthole Depth | Detonator Segment | Per Hole Charge | Total Charge |
---|---|---|---|---|---|---|---|
Cut hole | 42 mm | 500 mm | 14 | 3.8 m | MS1 | 1.2 kg | 16.8 kg |
Auxiliary cut hole | 42 mm | 950 mm | 8 | 3.8 m | MS3 | 2.4 kg | 19.2 kg |
Breast hole #1 | 42 mm | 950 mm | 12 | 3.8 m | MS5/MS7 | 1.8 kg | 21.6 kg |
Breast hole #2 | 42 mm | - | 8 | 4.3 m | MS9/MS11 | 2.1 kg | 16.8 kg |
Second-ring hole | 42 mm | 1200 mm | 15 | 3.8 m | MS11/MS13 | 1.8 kg | 27 kg |
Baseplate hole | 42 mm | 1450 mm | 8 | 3.8 m | MS15 | 1.8 kg | 14.4 kg |
Bottom-corner hole | 42 mm | - | 2 | 3.8 m | MS15 | 0.9 kg | 1.8 kg |
Peripheral hole | 42 mm | 600 mm | 33 | 3.8 m | MS15 | 1.2 kg | 16.8 kg |
Blasthole Parameters | Explosive Parameters | Charge (kg) | |||||
---|---|---|---|---|---|---|---|
Blasthole Type | Amount | Depth (m) | Angle (°) | Segment | Time Delay (ms) | Per Hole Charge | Total Charge |
Primary cut hole | 10 | 3.1 | 34 | MS1 | 0–60 | 1.2 | 12.0 |
Secondary cut hole | 14 | 4.5 | 47 | MS3 | 60–120 | 2.1 | 29.4 |
Auxiliary cut hole | 14 | 3.8 | 60 | MS5 | 120–180 | 2.4 | 33.6 |
Breast hole #1 | 12 | 3.2 | 70 | MS7 | 180–240 | 2.1 | 25.2 |
Breast hole #2 | 12 | 3.1 | 80 | MS9 | 240–300 | 1.5 | 18.0 |
Breast hole #3 | 6 | 3.0 | 85 | MS11 | 300–360 | 1.5 | 9.0 |
Vault breast hole #1 | 3 | 3.0 | 90 | MS11 | 300–360 | 1.5 | 4.5 |
Vault breast hole #2 | 5 | 3.0 | 90 | MS13 | 360–420 | 1.5 | 7.5 |
Arched waist second-ring hole | 8 | 3.0 | 90 | MS13 | 360–420 | 2.1 | 16.8 |
Vault second-ring hole | 7 | 3.0 | 90 | MS15 | 420–480 | 1.8 | 12.6 |
Arched waist peripheral hole | 24 | 3.0 | 90 | MS17 | 480–540 | 1.2 | 28.8 |
Vault peripheral hole | 21 | 3.0 | 90 | MS19 | 540–600 | 0.6 | 12.6 |
Bottom-corner hole | 2 | 3.2 | 90 | MS21 | 600–660 | 1.5 | 3.0 |
Position | Proportionality Coefficient-K | Site Coefficient-α | Fitting Formula |
---|---|---|---|
Target tunnel | 58.25 | 1.52 | SD−1.52 |
Residential areas | 60.26 | 1.45 | SD−1.45 |
Adjacent tunnel | 411.86 | 2.02 | SD−2.02 |
Mountain slopes | 90.51 | 1.23 | SD−1.23 |
Profile Position | Fractal Dimension Values of Different Regions | |||||||||||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|---|
Overall Profile | Left Arch Foot | Left Arch Waist | Vault | Right Arch Waist | Right Arch Foot | |||||||||||||
A | I | △D | A | Ideal | △D | A | I | △D | A | I | △D | A | I | △D | A | I | △D | |
50 m | 1.11 | 0.99 | 0.12 | 0.92 | 0.81 | 0.11 | 0.89 | 0.79 | 0.10 | 0.86 | 0.81 | 0.05 | 0.89 | 0.79 | 0.10 | 0.87 | 0.80 | 0.07 |
53 m | 1.13 | 1.01 | 0.12 | 0.91 | 0.82 | 0.09 | 0.91 | 0.78 | 0.13 | 0.83 | 0.80 | 0.03 | 0.91 | 0.80 | 0.11 | 0.85 | 0.79 | 0.06 |
56 m | 1.09 | 0.99 | 0.11 | 0.88 | 0.80 | 0.08 | 0.90 | 0.79 | 0.11 | 0.84 | 0.81 | 0.03 | 0.93 | 0.81 | 0.12 | 0.84 | 0.80 | 0.04 |
59 m | 1.12 | 0.98 | 0.14 | 0.89 | 0.80 | 0.09 | 0.92 | 0.80 | 0.12 | 0.85 | 0.80 | 0.05 | 0.90 | 0.79 | 0.11 | 0.86 | 0.79 | 0.07 |
62 m | 1.11 | 1.01 | 0.10 | 0.88 | 0.81 | 0.07 | 0.93 | 0.81 | 0.12 | 0.86 | 0.81 | 0.05 | 0.92 | 0.80 | 0.12 | 0.88 | 0.81 | 0.07 |
65 m | 1.10 | 0.99 | 0.11 | 0.90 | 0.81 | 0.09 | 0.91 | 0.79 | 0.12 | 0.85 | 0.81 | 0.04 | 0.91 | 0.80 | 0.11 | 0.87 | 0.81 | 0.06 |
Blasting Parameter | The Original Scheme | The Optimized Scheme | Effect (Growth rate) |
---|---|---|---|
Number of blastholes | 121 | 147 | 21% |
Total length of blastholes/m | 411.8 | 451.2 | 10% |
Total powder charge/kg | 134.4 | 153 | 14% |
5 m PPV cm/s | 10.37 | 7.68 | −26% |
15 m PPV cm/s | 3.11 | 2.87 | −8% |
Depth of cutting hole/m | 4.8 | Primary cutting hole: 4.5 Secondary cutting hole: 3.1 | - |
Distance between the cutting hole and the tunnel center line/m | 3.0 | 2.5 | - |
Distance between peripheral holes/m | 0.6 | 0.45 | - |
Thickness of smooth blasting layer/m | 0.6 | 0.55 | - |
Utilization ratio of blasthole/% | 76% | 90% | 14% |
the maximum roughness/cm | 60 cm | 25 cm | −26% |
Profile fractal dimension value | 1.21 | 1.09–1.11 | −8% |
Shotcrete dosage m3/m | 15.61 | 5.33 | −65% |
Disclaimer/Publisher’s Note: The statements, opinions and data contained in all publications are solely those of the individual author(s) and contributor(s) and not of MDPI and/or the editor(s). MDPI and/or the editor(s) disclaim responsibility for any injury to people or property resulting from any ideas, methods, instructions or products referred to in the content. |
© 2024 by the authors. Licensee MDPI, Basel, Switzerland. This article is an open access article distributed under the terms and conditions of the Creative Commons Attribution (CC BY) license (https://creativecommons.org/licenses/by/4.0/).
Share and Cite
Zhou, J.; Gao, S.; Luo, P.; Fan, J.; Zhao, C. Optimization of Blasting Parameters Considering Both Vibration Reduction and Profile Control: A Case Study in a Mountain Hard Rock Tunnel. Buildings 2024, 14, 1421. https://doi.org/10.3390/buildings14051421
Zhou J, Gao S, Luo P, Fan J, Zhao C. Optimization of Blasting Parameters Considering Both Vibration Reduction and Profile Control: A Case Study in a Mountain Hard Rock Tunnel. Buildings. 2024; 14(5):1421. https://doi.org/10.3390/buildings14051421
Chicago/Turabian StyleZhou, Junjie, Shan Gao, Pingkuang Luo, Jiale Fan, and Congcong Zhao. 2024. "Optimization of Blasting Parameters Considering Both Vibration Reduction and Profile Control: A Case Study in a Mountain Hard Rock Tunnel" Buildings 14, no. 5: 1421. https://doi.org/10.3390/buildings14051421
APA StyleZhou, J., Gao, S., Luo, P., Fan, J., & Zhao, C. (2024). Optimization of Blasting Parameters Considering Both Vibration Reduction and Profile Control: A Case Study in a Mountain Hard Rock Tunnel. Buildings, 14(5), 1421. https://doi.org/10.3390/buildings14051421