Next Article in Journal
Effect of Fine Particle Peening Using Hydroxyapatite Particles on Rotating Bending Fatigue Properties of β-Type Titanium Alloy
Next Article in Special Issue
Smart Helmet-Based Personnel Proximity Warning System for Improving Underground Mine Safety
Previous Article in Journal
Color Texture Image Complexity—EEG-Sensed Human Brain Perception vs. Computed Measures
Previous Article in Special Issue
A New Challenge: Path Planning for Autonomous Truck of Open-Pit Mines in The Last Transport Section
 
 
Font Type:
Arial Georgia Verdana
Font Size:
Aa Aa Aa
Line Spacing:
Column Width:
Background:
Article

Stochastic Predictions of Ore Production in an Underground Limestone Mine Using Different Probability Density Functions: A Comparative Study Using Big Data from ICT System

Department of Energy Resources Engineering, Pukyong National University, Busan 48513, Korea
*
Author to whom correspondence should be addressed.
Appl. Sci. 2021, 11(9), 4301; https://doi.org/10.3390/app11094301
Submission received: 17 April 2021 / Revised: 4 May 2021 / Accepted: 5 May 2021 / Published: 10 May 2021
(This article belongs to the Special Issue Recent Advances in Smart Mining Technology)

Abstract

:
This study stochastically predicted ore production through discrete event simulation using four different probability density functions for truck travel times. An underground limestone mine was selected as the study area. The truck travel time was measured by analyzing the big data acquired from information and communications technology (ICT) systems in October 2018, and probability density functions (uniform, triangular, normal, and observed probability distribution of real data) were determined using statistical values. A discrete event simulation model for a truck haulage system was designed, and truck travel times were randomly generated using a Monte Carlo simulation. The ore production that stochastically predicted fifty times for each probability density function was analyzed and represented as a value of lower 10% (P10), 50% (P50), and 90% (P90). Ore production was underestimated when a uniform and triangular distribution was used, as the actual ore production was similar to that of P90. Conversely, the predicted ore production of P50 was relatively consistent with the actual ore production when using the normal and observed probability distribution of real data. The root mean squared error (RMSE) for predicting ore production for ten days in October 2018 was the lowest (24.9 ton/day) when using the observed probability distribution.

1. Introduction

A mine project generally seeks to maximize production profits by using minimum capital and operating costs over the mine’s lifetime [1]. Accordingly, mines require optimal operating methods and equipment utilization strategies to increase productivity and minimize operating costs. In particular, efforts are being made to efficiently operate a truck haulage system, which constitutes greater than half of the operating cost [2]. The efficiency of a truck haulage system varies depending on the combination of the equipment used and operating patterns [3]. Therefore, it is necessary to operate an optimal truck haulage system capable of maximizing ore production and minimizing the equipment delay time [4].
An effective method for operating truck haulage systems is to simulate a virtual system model, using various optimization techniques. The input factors of the truck haulage system model include the system operating parameters (e.g., operating time, number of equipment, and load capacity) and truck cycle time. The outputs of the model include the truckload, production rate, equipment utilization, and equipment latency [4]. For the virtual system model, a simulation algorithm can be designed based on discrete events comprising truck haulage operations, such as traveling, spotting, loading, dumping, and queuing. In addition, mathematical optimization techniques can be applied to determine an optimal solution for the truck haulage operations. To date, several algorithms for truck haulage systems have been developed based on linear programming [5,6,7,8], genetic algorithms [9], queuing theory [10,11,12,13,14,15], fuzzy logic [16], and deep neural networks [17,18].
The system operating parameters and truck cycle times are not constant or definitive for each haulage operation cycle and frequently fluctuate according to the working conditions [19]. For instance, the daily working time and number of dispatched trucks can fluctuate according to the ore production schedule. The truck cycle time may vary depending on the equipment breakdown, plant interruption, and haul road conditions. For these reasons, an uncertainty exists in the deterministic simulation method, which predicts the truck haulage system, using constant input values. One method to simulate the system model considering the variability of input parameters is to apply the stochastic simulation technique. This method randomly extracts the input values from the probability distribution of a random variable and predicts the distribution of the output factors through iterative simulations [20].
Until recently, several researchers applied stochastic simulation techniques to analyze optimal equipment combinations and design truck dispatch scenarios in both open-pit and underground mines [1,19,21,22,23,24,25,26,27,28,29,30,31,32,33,34]. In these studies, truck cycle time data were statistically analyzed and a probability density function was selected using probability distribution models, such as Gaussian, triangular, Weibull, gamma, lognormal, exponential, Erlang, and uniform distribution models (Table 1). The optimal probability distribution model was determined by evaluating the goodness-of-fit using the chi-squared test [35], Akaike information criterion (AIC) [36], and Kolmogorov Smirnov tests [37]. The ore production, equipment utilization rate, and equipment downtime corresponding to the truck-shovel combination were analyzed probabilistically [25]. In addition, the ore production was predicted based on the confidence level, using iterative stochastic simulation [30], and the prediction sensitivity was analyzed by alternating the probability distribution models of the truck cycle time data [32]. However, little attention has been paid to analyze and use the probability distribution derived from a large amount of truck cycle time data for stochastic simulations.
The truck cycle time data were collected using the stopwatch method while boarding the equipment. For this reason, the theoretical probability distribution model was utilized in the stochastic simulations instead of the real statistical distribution pattern of the truck cycle time data. However, this may reduce the accuracy of the outputs from the truck haulage system simulations. Therefore, to improve the simulation accuracy, it is necessary to analyze and derive the probability distribution from a large amount of truck cycle time data collected over a long period.
Recently, mine safety management systems with information and communications technology (ICT) have been developed and actively implemented in mine sites worldwide [38,39,40,41,42,43,44,45]. The system recognizes the location of the equipment and workers in real time and monitors the work environment. Equipment location recognition data are transmitted to a web server through a wireless communication network and equipment locations are visualized on a dashboard in an outside office. An outstanding feature of this system is that big data are generated by continuously accumulating equipment location recognition data on the web server. Therefore, it is possible to analyze the long-term truck cycle time by extracting the equipment recognition time from the big data and calculating the difference in the recognition time. Baek and Choi [31] processed the big data acquired from a mine safety management system and statistically analyzed the truck travel time. In addition, the ore production and equipment utilization rates were predicted using a discrete event simulation. However, in this study, the probability distribution of the truck travel time data was assumed to be a normal distribution, as it was impossible to consider the exact variability of the truck travel time data.
The objective of the study was to analyze the probability distribution of the truck travel time using big data acquired from an ICT-based mine safety management system, and stochastically predict ore production through discrete event simulations, using different probability density functions for truck travel times. An underground limestone mine was selected as our study area. The probability distribution of the truck travel time was derived through statistical analysis of the big data acquired from the study area, and the truck travel time was randomly generated using Monte Carlo simulations based on four different probability density functions (uniform distribution, triangular distribution, normal distribution, and observed probability distribution of real data). A comparison between each of the stochastically predicted ore productions was performed to discuss the value of the truck cycle time data collected by the ICT-based mine safety management system.

2. Study Area

The Yeongcheon underground mine (37°4′14″, 128°18′46″) of Baek Kwang Mineral Products Co., located in Danyang-si, Chungcheongnam-do, South Korea, was selected as the study area (Figure 1). The mine comprises four levels; the average altitude of Levels 1, 2, 3 were 310, 250, and 280 m, respectively, while the lowest for Level 4 was 220 m. The mining method for room and pillar mining produces approximately 120 tons of limestone ore per year. The mine consists of four loading points underground (the IDs of which are 203, 233, 235 and 237) and a dumping area with a crusher on the surface. The ore was transported, using 30 ton dump trucks. The site’s production manager assigns trucks to the loading point daily, accounting for the ore production goals and quality. Next, the truck driver departs to the point to load the ore. The ore is loaded and subsequently moved to the dumping area. The truck driver checks the amount of ore accumulated in the crusher; if the ore quantity does not exceed the crusher capacity, the ore is unloaded into the crusher, and if it exceeds the capacity, the ore is unloaded into the yard. This operation is repeated during the working hours.
The study area was equipped with a mine safety management system based on ICT. Owing to the installation of a wireless communication network, it was possible to implement a digital environment to track the location of equipment in real time, make voice calls, and monitor the working environment at an underground mine site where communication was not possible. Through the wireless communication network, the location of the production equipment in the mine was received in real time on the dashboard in the office. The data acquired through the safety management system were stored in real time. In this study, the location tracking data of the production equipment were used in the mine safety management system. When the production equipment passes by a wireless access point (AP) installed in the study area, its location is tracked and stored as tag-recognition data. Figure 2 shows the process of a truck being recognized by the wireless APs as it passes by them while transporting ore in an underground mine. The tag recognition packet data, stored as the truck passes, includes information regarding the data category, presence of an emergency, tag recognition sequence, ID of the recognized tag, and distance between the wireless APs and the tag. These data are transmitted once every second, and approximately 200,000 packets are stored in the web server per month; the size of the data packet is 20 bytes each.

3. Methods

Big data collected for the location tracking of production equipment in the mining safety management systems were analyzed to compare and predict the ore production based on probability density functions. For the simulation, time and simulation parameters were received as input variables, and ore production was obtained as a probability distribution. Through big data analysis, the truck cycle time (TCT), which is the time parameter, was acquired. We designed a stochastic simulation model to fit the truck haulage system of the underground mine selected as the study area. Uniform, triangular, normal, and observed probability distributions were generated by measuring the truck travel time. Travel times and ore production rates were predicted by the Monte Carlo simulation (by applying the probability density functions) and stochastic simulation model, respectively (Figure 3).

3.1. Measuring Truck Travel Times from Big Data

The truck travel time was measured through the following process using big data. In this study, truck tag recognition packet data were extracted from big data for October 2018. The truck tag recognition packet data store approximately 200,000 packets per month. Among the packet data properties, tag recognition time, the IP address of wireless APs, and distance packet information were considered and classified according to the truck workplace. The study area consists of four loading points and four routes were identified. If all the wireless AP recognition data of the identified route do not exist and there are missing data, the data are deleted. By calculating the difference in the recognition time of the wireless APs, we obtained the truck travel time between each wireless AP. If the trucks remained in the recognized range for a considerable amount of time, the distance packet information was used to extract the tag recognition time, which is the minimum distance between the wireless APs and the truck. The difference in tag recognition time of the APs was calculated to measure the truck travel time. The types of truck travel times are as follows: the time lapsed when the truck moves from the portal to the loading point in an empty state (TEu); the time needed to load ore into the truck (LT); the time needed to transport the ore from the loading point to the portal with the ore loaded (TLu); the transport time from the portal to the dumping area and the unloading time in the dumping area (TLs); and the time to return to the portal (TEs) (Figure 4).

3.2. Design of a Truck Haulage System Model for Stochastic Discrete Event Simulation

A simulation model of a truck haulage system was designed to fit the study area (Figure 5). When the truck moves to the loading point, it determines whether a loader is available. If a loader is available, the truck loads the ore and proceeds to the dumping area. If another truck is loading, the truck waits for the job to be completed, loads the ore, and subsequently, proceeds to the dumping area. The trucks move to the dumping area and unload at the crusher or loading dock. If the simulation is not completed, the truck returns to the underground loading point. At the end of the simulation, the rate of ore production is predicted.
The truck haulage system simulation algorithm was modified for the measured truck travel time based on the TCT theory proposed by Suboleski [46]. TCT consists of the time a truck requires to travel from the portal to the loading point (TEu), the time a truck requires to load the ore at the loading point (LT), the time a truck needs to move to the portal from the loading point (TLu), the time taken by a truck to move to the dumping area (TLs), the time the truck needs to remain at the dumping area for the ore unloading process and the time needed to return to the portal (TEs) (see Equation (1)).
TCT =   TEu   +   LT   +   TLu   +   TLs   +   TEs
Table 2 lists the input and output values of the truck haulage system simulations. The input data include time parameters that control the TCT (which can control the truck operating time) and simulation parameters (which can control the operating facility or operating time). Time parameters were generated through Monte Carlo simulations and used as the input for the simulation model. The simulation parameters can be set as the conditions to be simulated. The simulation result is the rate of ore production.

3.3. Generation of Truck Travel Times

In this study, we compared the simulation results of instances wherein different probability density functions of the measured truck travel time were used as the input variables. The simulation results were compared by creating five temporal elements of the TCT with the Monte Carlo simulation, using the uniform, triangular, normal, and observed probability distributions derived from actual truck travel time data. The uniform, triangular, normal, and observed probability distributions were used in this study because they are widely used as probability density functions and can be defined using the big data of an ICT system. It should be noted that the uniform, triangular and normal distributions are theoretical probability density functions defined mathematically; however, the observed probability distribution is an empirical one. The uniform and triangular distributions were generated by considering the maximum and minimum values. The normal distribution was generated by considering the mean and standard deviation (STD), and the observed probability distribution was obtained using actual accumulated data (Figure 6).
Considering the measured truck travel time, a random variable for truck travel time was created based on a Monte Carlo simulation. A Monte Carlo simulation is a numerical, experimental method to obtain the output variable value of the system calculation model by considering the statistical value of the input variable. The values of the input random variable were sampled based on the statistical distribution, and the output variable was calculated using a computational model [47]. To use the Monte Carlo simulation, a cumulative relative frequency graph of the TCT was created.
The class width and relative frequency are required to generate the cumulative relative frequency graph of the TCT. Using the statistical analysis results, the class width required to create a cumulative relative frequency graph was calculated (Equation (2)). The frequency of each class was calculated according to the data, and the relative frequency of each class was calculated by dividing the total data recorded (Equation (3)). The cumulative relative frequency was calculated using the relative power of each class, as shown in Equation (4):
Class   width = M a x i m u m   v a l u e M i n i m u m   v a l u e N u m b e r   o f   c l a s s e s
F i r = f i N              
F n c = i = 1 n F i r
Using the cumulative relative frequency graph based on the probability function distribution, a random variable for truck travel time was created by Monte Carlo simulation, as follows: the cumulative relative frequency graph F(x) represents the probability P that the truck travel time X is less than or equal to x (Equation (5)). Because F(x) is a probability, it possesses a value from 0 to 1. Thus, we can determine the inverse function of F(x), where G(F(x)) is the inverse function of F(x), and r is any real number between 0 and 1. In this study, we generated the actual number between 0 and 1 and subsequently assumed each generated actual number as the y value of the cumulative relative frequency graph and predicted the trucking time by determining the x value corresponding to the y value (Equation (6)).
F ( x ) = P   ( X x )  
G ( F ( x ) ) = G ( r ) = x

3.4. Setting Simulation Parameters

To perform the simulation, we set the simulation parameters, which consisted of the daily working time, number of trucks, capacity of a truck, and number of simulations. The simulation parameters were set using the operational parameters analyzed from the big data. On the morning of 16 October in the study area, two 30 ton trucks were used at the loading point 237 from 7:00 a.m. to 12:50 p.m. The simulation was performed by setting the following parameters: operating time as 350 min, two trucks, a truck capacity of 30 tons, and simulation iterations as fifty times (Table 3).

4. Results

4.1. Statistical Characteristics of Truck Travel Times Measured from Big Data

In the study area, the TCT was analyzed using big data recorded in October 2018 (Table 4). Figure 7 shows the cumulative relative distributions of TEu, TEs, TLu, TLs, and LT at each of the four loading points. Loading point 203 required the least time with an average of approximately 22.74 min for a single haulage cycle; loading point 235 required the most time with an average of approximately 34.07 min. Loading point 203 was located closest to the portal, resulting in an average difference of approximately 11.33 min in TCT.
The uniform and triangular distributions of the truck travel time were set using the minimum and maximum values of the measured TCT. A normal distribution was simulated using the mean and standard deviation of the TCT. The cumulative distribution was simulated by calculating Equations (3)–(5), using actual data. For loading point 203, the difference between the maximum and minimum classes of TEu, TLu, and TLs, which are truck travel time elements, was 1.52, 1.10 and 4.40 min, respectively, whereas LT and TEs, which are the time required to load or unload ore, were 18.10 and 34.53 min, respectively, and exhibited additional differences than other factors. Loading point 233 exhibited significant differences in class at 17.30 and 18.40 min, respectively, for TEu and LT. Loading point 235 displayed a difference between the maximum and minimum classes at 7.80 min and 14.25 min for TEs and LT, and for loading point 237, at 11.65 min for LT. The comparison proved the existence of a significant time lag when working with ores. The TCTs were predicted using a Monte Carlo simulation. The generated times were used for simulations to predict ore production rates.

4.2. Predictions of Ore Productions by Stochastic Discrete Event Simulation

The actual production in the field and the simulation results were compared. In the designated study area, the simulation parameters were set and simulations with two 30 ton trucks and an operating time of 350 min were conducted, as shown in the data for 16 October. The TCT was used as the input in the Monte Carlo simulation as the time obtained for each uniform distribution, that is, triangular, normal, and observed probability distribution.
The simulation results indicated the production volumes of P10, P50 and P90. P10 represents the value of the lower 10% ore production, P50 represents a production rate lower than 50%, and P90 represents a simulated rate lower than 90%. If we cross-check the results with the P10 values, we can conclude that the ore production is low, while P50 and P90 are the average and high production volumes, respectively. In all four probability density functions, we confirmed that the actual field data are located within the range of the simulation results. The uniform and the triangular distribution models exhibited similar results for the actual and simulated results of P90. The overall prediction result was lower than that of the actual data. It was determined that the truck cycle time was generated longer than the actual truck cycle time owing to the distribution of the probability density function when the truck cycle time was generated. Conversely, the normal distribution and observed probability distribution models displayed results similar to that of the actual values and P50 as a result of the simulation (Figure 8).

5. Discussion

The truck haulage operations in the mine are not constant at each loading and unloading cycle and vary from time to time depending on the working conditions [19]. Therefore, the simulation results for each day were compared using data from October 2018 for long-term simulations. Time parameters were created by the Monte Carlo simulation for each loading point and the simulation parameters were set according to the date (Table 5). The truck capacity was set to 30 tons, and fifty iterations of the simulation were run. The ore production predictions achieved as a result of the simulation were expressed as P10, P50, and P90.
The observed probability distribution model was used to predict the actual field data in the distribution of the simulation results (Figure 9); the TCT generated was higher than the actual TCT. The actual field data were not included in the distribution of the results of the simulation model that generated the TCT by providing a uniform distribution as the input to the Monte Carlo simulation. In the triangular distribution model, only one day—that is, 16 October—was included. In the simulation model that used the normal distribution, the results for three days were not included in the ore production simulation distribution. To quantify the simulation results, we calculated the root mean square error (RMSE, ton/day) of the P50 results of each simulation result and the actual data (Figure 10). The observed probability distribution model achieved the lowest value at 24.9 ton/day.
The results indicate that the case using observed probability distribution based on the big data of an ICT system showed the best performance for ore prediction. This demonstrates the value and importance of the data collected by an ICT system in the mining site from a practical point of view.

6. Conclusions

This study stochastically predicted ore production through discrete event simulation, using four different probability density functions for truck travel times, and compared the simulation results for the four cases. The TCT was measured by dividing it based on the four loading points, using the truck tag recognition time record big data obtained through the mine safety management system based on a wireless communication network for an underground limestone mine. The discrete simulation model was designed to stochastically predict ore production in the designated study area. The uniform, triangular, normal, and observed probability distribution obtained using the measured truck driving time were fed into the Monte Carlo simulation to generate the respective TCTs. The generated TCTs were input into a discrete simulation model. The results of the ore production prediction were validated using field data of the morning of 16 October. As a result of the verification, the data on 16 October 2018 included all four models in the distribution of the simulation results. The uniform and triangular distribution models predicted relatively lower ore production than the actual production because the results of P90 and the field data were similar. The normal distribution and observed probability distribution models were similar to the P50 results and the field data.
Because the working conditions at the mine site changed regularly, the stochastic simulation model was used in the short term as well as in the long term in various ways. Therefore, we performed a simulation with ten days of valid data for October 2018. Simulated with data for the month of October, the RMSE of the observed probability distribution model was the lowest at 24.9 ton/day. The comparison results prove that the developed observed probability distribution model can predict the rate of total ore production within the range of actual values.
To use the observed probability distribution, the truck travel time data must be recorded. Simulation results of higher accuracy can be derived, such as that of the simulation of the observed probability distribution models used, by processing stored data. If the ICT-based mine safety management systems are introduced at various sites, simulations of higher accuracy can be achieved. It was possible to consider time through a Monte Carlo simulation using the data stored in the field without excluding various events occurring in the field. Thus, it is possible to obtain the resulting distribution of various ore productions. Because the stochastic simulation result is displayed as a distribution rather than a single value, various statistical values, such as the maximum and minimum, were confirmed in the field. It will be helpful for managers to use simulation results to set up or modify work plans according to desired production goals or perspectives.
Delay time is an important indicator for evaluating the performance of mining operation. This study did not use the delay time as an input or output parameter of the simulator; however, the delay time was considered during the simulation process. In future work, it would be interesting to stochastically estimate the delay time with simulation output to make decisions for maximizing ore production.

Author Contributions

Conceptualization, Y.C.; methodology, Y.C., J.B. and D.J.; software, D.J.; validation, J.B. and D.J.; formal analysis, J.B. and D.J.; investigation, Y.C.; resources, Y.C.; data curation, D.J.; writing—original draft preparation, Y.C., J.B. and D.J.; writing—review and editing, Y.C.; visualization, J.B. and D.J.; supervision, Y.C.; project administration, Y.C.; funding acquisition, Y.C. All authors have read and agreed to the published version of the manuscript.

Funding

This work was supported by the National Research Foundation of Korea (NRF) grant funded by the Korea government (MSIT) (2021R1A2C1011216).

Institutional Review Board Statement

Not applicable.

Informed Consent Statement

Not applicable.

Data Availability Statement

Not applicable.

Acknowledgments

Dahee Jung and Jieun Baek contributed equally as co-first authors.

Conflicts of Interest

The authors declare no conflict of interest.

References

  1. Torkamani, E.; Askari-Nasab, H. Verifying Short-Term Production Schedules using Truck-Shovel Simulation. In Mining Optimization Laboratory (MOL); University of Alberta: Edmonton, AB, Canada, 2012; pp. 190–205. [Google Scholar]
  2. Alarie, S.; Gamache, M. Overview of Solution Strategies Used in Truck Dispatching Systems for Open Pit Mines. Int. J. Surf. Mining, Reclam. Environ. 2002, 16, 59–76. [Google Scholar] [CrossRef]
  3. Burt, C.N.; Caccetta, L. Equipment Selection for Surface Mining: A Review. Interfaces 2014, 44, 143–162. [Google Scholar] [CrossRef] [Green Version]
  4. Afrapoli, A.M.; Askari-Nasab, H. Mining fleet management systems: A review of models and algorithms. Int. J. Min. Reclam. Environ. 2019, 33, 42–60. [Google Scholar] [CrossRef]
  5. Bonates, E.J.L. The Development of Assignment Procedures for Semi-Automated Truck/Shovel Systems. Ph.D. Thesis, McGill University, Montreal, QC, Canada, 1992. [Google Scholar]
  6. Gurgur, C.Z.; Dagdelen, K.; Artittong, S. Optimization of a real-time multi-period truck dispatching system in mining operations. Int. J. Appl. Decis. Sci. 2011, 4, 57–79. [Google Scholar] [CrossRef]
  7. Mena, R.; Zio, E.; Kristjanpoller, F.; Arata, A. Availability-based simulation and optimization modeling framework for open-pit mine truck allocation under dynamic constraints. Int. J. Min. Sci. Technol. 2013, 23, 113–119. [Google Scholar] [CrossRef]
  8. Patterson, S.R.; Kozan, E.; Hyland, P. An Integrated Model of an Open-pit Coal Mine: Improving Energy Efficiency Decisions. Int. J. Prod. Res. 2016, 54, 4213–4227. [Google Scholar] [CrossRef]
  9. Naoum, S.; Haidar, A. A Hybrid Knowledge Base System and Genetic Algorithms for Equipment Selection. Eng. Constr. Archit. Manag. 2000, 7, 3–14. [Google Scholar] [CrossRef]
  10. Koenigsberg, E. Cyclic queues. J. Oper. Res. Soc. 1958, 9, 22–35. [Google Scholar] [CrossRef]
  11. Carmichael, D.G. Engineering Queues in Construction and Mining; John Wiley & Sons: Hoboken, NJ, USA, 1987; ISBN 978-0132781442. [Google Scholar]
  12. Kappas, G.; Yegulalp, T.M. An application of closed queueing networks theory in truck-shovel systems. Int. J. Surf. Min. Reclam. Environ. 1991, 5, 45–51. [Google Scholar] [CrossRef]
  13. Xi, Y.; Yegulalp, T.M. Optimum Dispatching Algorithms for Anshan open Pit Mine. In Proceedings of the 24th International Symposium on Application of Computers and Operations Research in the Mineral Industry (APCOM 1993), Montreal, QC, Canada, 31 October–3 November 1993; Canadian Institute of Mining, Metallurgy and Petroleum: Westmount, QC, Canada, 1993; pp. 426–433. [Google Scholar]
  14. Raman, D.; Nagalingam, S.V.; Gurd, B.W.; Lin, G.C.I. Quantity of Material Handling Equipment-A Queuing Theory Based Approach. Robot. Comput. Integr. Manuf. 2009, 25, 348–357. [Google Scholar] [CrossRef]
  15. May, M.A. Applications of Queuing Theory for Open-Pit Truck/Shovel Haulage Systems. Master’s thesis, Virginia Polytechnic Institute and State University, Blacksburg, VA, USA, 19 December 2012. [Google Scholar]
  16. Bitarafan, M.K.; Ataei, M. Mining Method Selection by Multiple Criteria Decision Making Tools. J. S. Afr. Inst. Min. Metall. 2004, 104, 493–498. [Google Scholar]
  17. Baek, J.; Choi, Y. Deep Neural Network for Ore Production and Crusher Utilization Prediction of Truck Haulage System in Underground Mine. Appl. Sci. 2019, 9, 4180. [Google Scholar] [CrossRef] [Green Version]
  18. Baek, J.; Choi, Y. Deep Neural Network for Predicting Ore Production by Truck-Haulage Systems in Open-Pit Mines. Appl. Sci. 2020, 10, 1657. [Google Scholar] [CrossRef] [Green Version]
  19. Ozdemir, B.; Kumral, M. Simulation-based Optimization of Truck-Shovel Material Handling Systems in Multi-Pit Surface Mines. Simul. Model. Pract. Theory 2019, 95, 36–48. [Google Scholar] [CrossRef]
  20. Dekking, F.M.; Kraaikamp, C.; Lopuhaä, H.P.; Meester, L.E. A Modern Introduction to Probability and Statistics: Understanding Why and How; Springer: London, UK, 2005; pp. 1–488. [Google Scholar]
  21. Lizotte, Y.; Bonates, E. Truck and Shovel Dispatching Rules Assessment Using Simulation. Min. Sci. Technol. 1987, 5, 45–58. [Google Scholar] [CrossRef]
  22. Ta, C.H.; Kresta, J.V.; Forbes, J.F. A Stochastic Optimization Approach to Mine Truck Allocation. Int. J. Surf. Min. Reclam. Environ. 2006, 19, 162–175. [Google Scholar] [CrossRef]
  23. Bastos, G.S. Decision Making applied to Shift Change in Stochastic Open-pit Mining Truck Dispatching. In Proceedings of the 16th IFAC Symposium on Control, Optimization and Automation in Mining, Mineral and Metal Processing, San Diego, CA, USA, 25–28 August 2013; Florian, K., Ed.; Elsevier: Amsterdam, The Netherlands; pp. 34–39. [Google Scholar]
  24. Dindarloo, S.R.; Osanloo, M.; Frimpong, S. A Stochastic Simulation Framework for Truck and Shovel Selection and Sizing in Open Pit Mines. J. S. Afr. Inst. Min. Metall. 2015, 115, 209–219. [Google Scholar] [CrossRef]
  25. Torkamani, E.; Askari-Nasab, H. A Linkage of Truck-and-shovel Operations to Short-term Mine Plans Using Discrete-event Simulation. Int. J. Min. Miner. Eng. 2015, 6, 97–118. [Google Scholar] [CrossRef]
  26. Matamoros, M.E.V.; Dimitrakopoulos, R. Stochastic Short-term Mine Production Schedule Accounting for Fleet Allocation, Operational Considerations and Blending Restrictions. Eur. J. Oper. Res. 2016, 255, 911–921. [Google Scholar] [CrossRef] [Green Version]
  27. Park, S.; Choi, Y.; Park, H.S. Optimization of Truck-loader Haulage Systems in an Underground Mine Using Simulation Methods. Geosyst. Eng. 2016, 19, 222–231. [Google Scholar] [CrossRef]
  28. Chaowasakoo, P.; Seppälä, H.; Koivo, H.; Zhou, Q. Digitalization of Mine Operations: Scenarios to Benefit in Real-time Truck Dispatching. Int. J. Min. Sci. Technol. 2017, 27, 229–236. [Google Scholar] [CrossRef]
  29. Ristovski, K.; Gupta, C.; Harada, K.; Tang, H.K. Dispatch with Confidence: Integration of Machine Learning, Optimization and Simulation for Open Pit Mines. In Proceedings of the 23rd ACM SIGKDD International Conference on Knowledge Discovery and Data Mining, Halifax, NS, Canada, 13–17 August 2017; Association for Computing Machinery: New York, NY, USA; pp. 1981–1989. [Google Scholar]
  30. Afrapoli, A.M.; Tabesh, M.; Askari-Nasab, H. A Multiple Objective Transportation Problem Approach to Dynamic Truck Dispatching in Surface Mines. Eur. J. Oper. Res. 2019, 276, 331–342. [Google Scholar] [CrossRef]
  31. Baek, J.; Choi, Y. Simulation of Truck Haulage Operations in an Underground Mine Using Big Data from an ICT-Based Mine Safety Management System. Appl. Sci. 2019, 9, 2639. [Google Scholar] [CrossRef] [Green Version]
  32. Lisboa, A.C.; De Souza, F.H.B.; Ribeiro, C.M.; Maia, C.A.; Saldanha, R.R.; Castro, F.L.B.; Vieira, D.A.G. On Modelling and Simulating Open Pit Mine through Stochastic Timed Petri Nets. IEEE Access 2019, 7, 112821–112835. [Google Scholar] [CrossRef]
  33. Moniri-Morad, A.; Pourgol-Mohammad, M.; Aghababaei, H.; Sattarvand, J. A Methodology for Truck Allocation Problems Considering Dynamic Circumstances in Open Pit Mines, Case study of the Sungun Copper Mine. Min. Geol. Pet. Bull. 2019, 34, 57–65. [Google Scholar] [CrossRef]
  34. Jung, D.; Baek, J.; Choi, Y. Simulation and Real-time Visualization of Truck-Loader Haulage Systems in an Open Pit Mine using AnyLogic. J. Korean Soc. Miner. Energy Resour. Eng. 2020, 57, 45–57. [Google Scholar] [CrossRef]
  35. Pearson, K. On the Criterion that a Given System of Deviations from the Probable in the Case of a Correlated System of Variables. Philos. Mag. 1900, 5, 157–175. [Google Scholar] [CrossRef] [Green Version]
  36. Akaike, H. Information Theory and an Extension of the Maximum Likelihood Principle. In Proceedings of the 2nd International Symposium on Information Theory, Tsahkadsor, Armenia, 2–8 September 1971; Petrov, B.N., Csáki, F., Eds.; Akadémiai Kiadó: Budapest, Hungary, 1973; pp. 267–281. [Google Scholar]
  37. Kolmogorov, A. Sulla determinazione empirica di una lgge di distribuzione. Inst. Ital. Attuari Giorn. 1933, 4, 83–91. [Google Scholar]
  38. Yarkan, S.; Sabih, G.; Murphy, R.R. Underground Mine Communications: A Survey. IEEE Commun. Surv. Tutorials 2009, 11, 125–142. [Google Scholar] [CrossRef]
  39. Sunderman, C.; Waynert, J. An Overview of Underground Coal Miner Electronic Tracking System Technologies. In Proceedings of the 2012 IEEE Industry Applications Society Annual Meeting, Las Vegas, NV, USA, 7–11 October 2012; IEEE: New York, NY, USA, 2012; pp. 1–5. [Google Scholar]
  40. Forooshani, A.E.; Bashir, S.; Michelson, D.G.; Noghanian, S. A Survey of Wireless Communications and Propagation Modeling in Underground Mines. IEEE Commun. Surv. Tutor. 2013, 15, 1524–1545. [Google Scholar] [CrossRef]
  41. Dohare, Y.S.; Maity, T.; Das, P.S.; Paul, P.S. Wireless Communication and Environment Monitoring in Underground Coal Mines–Review. IETE Tech. Rev. 2015, 32, 140–150. [Google Scholar] [CrossRef]
  42. Thrybom, L.; Neander, J.; Hansen, E.; Landernäs, K. Future Challenges of Positioning in Underground Mines Future Challenges of Positioning in Underground Mines. IFAC PapersOnLine 2015, 48, 222–226. [Google Scholar] [CrossRef]
  43. Reddy, N.S.; Saketh, M.S.; Dhar, S. Review of Sensor Technology for Mine Safety Monitoring Systems: A Holistic Approach. In Proceedings of the 2016 IEEE First International Conference on Control, Measurement and Instrumentation (CMI), Kolkata, India, 8–10 January 2016; IEEE: New York, NY, USA, 2016; pp. 429–434. [Google Scholar]
  44. Muduli, L.; Mishra, D.P.; Jana, P.K. Application of Wireless Sensor Network for Environmental Monitoring in Underground Coal Mines: A systematic review. J. Netw. Comput. Appl. 2018, 106, 48–67. [Google Scholar] [CrossRef]
  45. Wu, Y.; Chen, M.; Wang, K.; Fu, G. A Dynamic Information Platform for Underground Coal Mine Safety based on Internet of Things. Saf. Sci. 2019, 113, 9–18. [Google Scholar] [CrossRef]
  46. Suboleski, S.C. Mine Systems Engineering Lecture Notes; The Pennsylvania State University: State College, PA, USA, 1975. [Google Scholar]
  47. Thomas, A. Cruse. Reliability-Based Mechanical Design; Marcel Dekker, Inc.: New York, NY, USA, 1997; p. 123. [Google Scholar]
Figure 1. Aerial view of the study area displaying the various facilities. (Image source: National Geographic Information Institute of South Korea).
Figure 1. Aerial view of the study area displaying the various facilities. (Image source: National Geographic Information Institute of South Korea).
Applsci 11 04301 g001
Figure 2. Diagram showing the sequence of wireless APs in the underground mine; W01 (W02): 1st (2nd) wireless access point (AP) installed underground.
Figure 2. Diagram showing the sequence of wireless APs in the underground mine; W01 (W02): 1st (2nd) wireless access point (AP) installed underground.
Applsci 11 04301 g002
Figure 3. Study process of truck-haulage system stochastic simulation using the proposed method.
Figure 3. Study process of truck-haulage system stochastic simulation using the proposed method.
Applsci 11 04301 g003
Figure 4. An illustration of the process of classifying the truck tag recognition packet data and measuring the five types of truck travel time: TEs1—empty truck surface travel time; TEu2—empty truck underground travel time; LT3—loading time; TLu4—loaded truck underground travel time; TLs5—loaded truck surface travel time.
Figure 4. An illustration of the process of classifying the truck tag recognition packet data and measuring the five types of truck travel time: TEs1—empty truck surface travel time; TEu2—empty truck underground travel time; LT3—loading time; TLu4—loaded truck underground travel time; TLs5—loaded truck surface travel time.
Applsci 11 04301 g004
Figure 5. Flow chart displaying procedures for implementing the truck haulage simulation algorithm.
Figure 5. Flow chart displaying procedures for implementing the truck haulage simulation algorithm.
Applsci 11 04301 g005
Figure 6. Probability density functions of the truck travel time for loading point 203. (a) Uniform distribution, (b) triangular distribution, (c) normal distribution, (d) observed probability distribution.
Figure 6. Probability density functions of the truck travel time for loading point 203. (a) Uniform distribution, (b) triangular distribution, (c) normal distribution, (d) observed probability distribution.
Applsci 11 04301 g006
Figure 7. Histogram and cumulative relative frequency graphs of the truck travel time for each loading point.
Figure 7. Histogram and cumulative relative frequency graphs of the truck travel time for each loading point.
Applsci 11 04301 g007
Figure 8. Comparison of the simulation and haulage operations results (observed) obtained on 16 October 2018 for (a) uniform distribution, (b) triangular distribution, (c) normal distribution, and (d) observed probability distribution.
Figure 8. Comparison of the simulation and haulage operations results (observed) obtained on 16 October 2018 for (a) uniform distribution, (b) triangular distribution, (c) normal distribution, and (d) observed probability distribution.
Applsci 11 04301 g008
Figure 9. Comparison of the simulation and haulage operation results (observed) for ten days (Month/Day) in October 2018 for (a) uniform distribution, (b) triangular distribution, (c) normal distribution, and (d) observed probability distribution.
Figure 9. Comparison of the simulation and haulage operation results (observed) for ten days (Month/Day) in October 2018 for (a) uniform distribution, (b) triangular distribution, (c) normal distribution, and (d) observed probability distribution.
Applsci 11 04301 g009
Figure 10. Results of the correlation analysis between the predicted and observed ore productions for ten days in October 2018 for (a) uniform distribution, (b) triangular distribution, (c) normal distribution, and (d) observed probability distribution.
Figure 10. Results of the correlation analysis between the predicted and observed ore productions for ten days in October 2018 for (a) uniform distribution, (b) triangular distribution, (c) normal distribution, and (d) observed probability distribution.
Applsci 11 04301 g010
Table 1. Study cases for the stochastic approach-based truck haulage system simulation.
Table 1. Study cases for the stochastic approach-based truck haulage system simulation.
ReferenceTheoretical Model Representing Probability Distribution
GaussianTriangularWeibullGammaLognormalExponentialErlangUniform
[1]ΧΧ
[19]Χ Χ Χ
[21]Χ Χ
[22]Χ
[23] Χ
[24]Χ Χ Χ
[25]ΧΧΧΧ
[26]Χ
[27]Χ
[28] Χ
[29] Χ
[30]Χ ΧΧΧ
[31]Χ
[32]Χ ΧΧΧ
[33]
[34]Χ
Table 2. Description of the input and output parameters of the truck haulage system simulation.
Table 2. Description of the input and output parameters of the truck haulage system simulation.
TypeDataUnit
InputTime parametersTravel time of the empty truckTEuMinutes
TEsMinutes
Travel time of the loaded truckTLuMinutes
TEuMinutes
Working timeLTMinutes
Simulation parametersDaily working time Minutes
Number of trucks Numbers
Capacity of a truck Tons
Number of simulations Numbers
Output Total amount of the loaded ore Tons
Table 3. The value of the simulation parameters used for truck haulage system simulation.
Table 3. The value of the simulation parameters used for truck haulage system simulation.
Simulation ParametersValue
Daily working time (min)350
Number of trucks2
Capacity of a truck (ton)30
Number of simulations50
Table 4. Results of the statistical analysis of the truck travel time measured using the big data.
Table 4. Results of the statistical analysis of the truck travel time measured using the big data.
Loading PointStatisticsTruck Travel Time
TEuTLuTLsTEsLT
203Mean (min)0.931.105.557.587.58
Min (min)0.570.754.022.723.58
Max (min)2.271.958.9844.3721.95
STD (min)0.270.230.929.823.73
Kurtosis7.144.333.707.093.19
233Mean (min)9.4710.175.483.754.25
Min (min)5.528.054.032.432.08
Max (min)23.0811.858.186.5520.55
STD (min)3.320.730.770.922.57
Kurtosis4.460.234.012.1826.67
235Mean (min)7.2010.975.524.635.75
Min (min)5.779.574.783.070.63
Max (min)13.6214.258.0011.3219.17
STD (min)1.851.320.632.073.95
Kurtosis28.0028.0027.0023.0028.00
237Mean (min)6.527.985.303.505.52
Min (min)4.726.424.722.703.53
Max (min)11.309.236.436.2316.57
STD (min)1.270.620.420.683.38
Kurtosis7.900.230.9010.474.18
Table 5. Description of the input data of the truck haulage system simulation for ten days in October 2018.
Table 5. Description of the input data of the truck haulage system simulation for ten days in October 2018.
Simulation
Parameters
Date
12 October13 October15 October16 October19 October22 October24 October26 October29 October30 October31 October
Loading point 203Daily working times (min)400 100 355 55 385
Number of trucks1 1 2 1 2
Loading point 233Daily working times (min) 3308040 445 290 280
Number of trucks 222 1 2 1
Loading point 235Daily working times (min) 245370
Number of trucks 22
Loading point 237Daily working times (min) 270 40 115
Number of trucks 2 1 3
Publisher’s Note: MDPI stays neutral with regard to jurisdictional claims in published maps and institutional affiliations.

Share and Cite

MDPI and ACS Style

Jung, D.; Baek, J.; Choi, Y. Stochastic Predictions of Ore Production in an Underground Limestone Mine Using Different Probability Density Functions: A Comparative Study Using Big Data from ICT System. Appl. Sci. 2021, 11, 4301. https://doi.org/10.3390/app11094301

AMA Style

Jung D, Baek J, Choi Y. Stochastic Predictions of Ore Production in an Underground Limestone Mine Using Different Probability Density Functions: A Comparative Study Using Big Data from ICT System. Applied Sciences. 2021; 11(9):4301. https://doi.org/10.3390/app11094301

Chicago/Turabian Style

Jung, Dahee, Jieun Baek, and Yosoon Choi. 2021. "Stochastic Predictions of Ore Production in an Underground Limestone Mine Using Different Probability Density Functions: A Comparative Study Using Big Data from ICT System" Applied Sciences 11, no. 9: 4301. https://doi.org/10.3390/app11094301

APA Style

Jung, D., Baek, J., & Choi, Y. (2021). Stochastic Predictions of Ore Production in an Underground Limestone Mine Using Different Probability Density Functions: A Comparative Study Using Big Data from ICT System. Applied Sciences, 11(9), 4301. https://doi.org/10.3390/app11094301

Note that from the first issue of 2016, this journal uses article numbers instead of page numbers. See further details here.

Article Metrics

Back to TopTop